Measurement iv
1. CADANGAN MEMBINA DAN MENYIAPKAN SATU UNIT RUMAH BANGLO DUA TINGKAT
DI ATAS LOT PT 11092, DAERAH HULU LANGAT, SELANGOR DARUL EHSAN.
UNTUK TETUAN: HAJI HAMZAH BIN
ABDUL MAJID
1-3, JALAN KASTURI 1, PLAZA KASTURI
OFF JALAN BALAKONG, 43200 CHERAS,
SELANGOR DARUL EHSAN
2. Construction and completion
of one unit of 2 storey
residential house including
external works within the lot
boundary
Excluding:
- Cold water services
- Sanitary plumbing
- Electrical installations
SCOPE OF
WORKS
3. - Site is generally flat
- External works outside lot
boundary, earthwork, site
clearance are completed by
others
SITE
CONDITIONS
12. F L O O R F I N I S
H E S
Ground Floor Plan
Standard Marble
Merbau Timber Flooring
Solid Merbau Plank Timber
Deck
MMK Satori Porcelain Floor
Tiles
MML Kelikir Floor Tiles
MML Mera Tiles
13. F L O O R F I N I
S H E S
First Floor Plan
Standard Marble
Merbau Timber Flooring
Solid Merbau Plank Timber
Deck
MMK Satori Porcelain Floor
Tiles
MML Kelikir Floor Tiles
MML Mera Tiles
24. Such declaration requires the tenderer to confirm that:
● Tender price has not been communicated to other
party
● Not given any inducements or rewards to client
Declaration of Non-Collusion
25. Fixed completion time = 10 months
Tendering period =
2 weeks from date of letter of invitation
Tender validity period = 60 days
Tender deposit =
RM 500.00
Tender bond =
RM 10,000.00
Place of collection/issuance of tender documents = At QS’s office
Place of submission of tender = At
Employer’s office
Instructions & Conditions of Tendering
26. Appendix to Form of contract:
-Defects Liability Period:
24 months
-Insurance cover of third parties and damage to property :
RM1,000,000.00
-Insurance deductible amount:
RM 50,000.00
-Percentage to cover Professional Fees for reinstatement: (Sum
equivalent to 10% of Contract Sum)
-Amount of removal of debris:
Sum equivalent to 1% of contract sum
-Value of existing structure together with all contents owned by the Employer: Not applicable
-Date of commencement :
To be stipulated on the LOA
Form of Contract - PAM FORM 2006 (WITH
QUANTITIES)
27. Form of Contract
-Interim claim interval:
1 month
-Period of honouring certificates:
30 days
-Percentage of value of materials and goods included in the certificate: 75%
-Percentage of certified value retained:
10%
-Limitation of retention:
5% of contract sum
28. It is contractor’s obligation to take up Contractor’s All
risk Insurance Policy to cover for material damage to
the whole of the contract works and third party liability
in the joint names of the employer and contractor,
subcontractors and all interested parties.
Contractor’s All Risk Insurance Policy ( Clause 20.A.1
)
29. Preambles
Explain the project, materials needed, unit prices,
provisional sums, methods of measurement and
potential errors.
Example : excavation is included in the project, the
type of rock must be outlined in the preamble.
30. Materials & Workmanship
Part A: General Requirements
- It includes relevant details of the site and
information on items which do not form part of
the permanent works
Part B: Specification of workmanship and materials
- Deals with the detailed requirements of every
trade. The type, the quality and method of fixing
and testing of every item for incorporation in
permanent works is described.
31. What’s included in Preliminaries:
Preliminaries
● Earnest money
● Working area
● Firm price contract
● Interpretation of tender
documents
● Drawings, shop drawings
● Temporary roads and
gangways
● Temporary buildings
● Construction plant
● Form of contract
● Performance bond
● Weekly report
32. PC sum & Provisional Sum
Cold water and Sanitary Plumbing Works :
RM20,000.00
Electrical Installation Works:
RM15,000.00
Supply and Delivery to Site of Sanitary Fittings: RM10,000.00
Contingencies:
RM100,000.00
36. ● Serves as a
basis in the
event of variation
Appendix D: Prices of basic
materials
37. Appendix E: Form of bank
guarantee for earnest money
● To ensure that
the contractor
does not pull out
if he is selected
by client
38. Appendix F: Form of bank guarantee for
performance bond
● performance bond protects
the owner from the
contractor’s failure to
perform in accordance with
the terms of the contract