SlideShare a Scribd company logo
1 of 70
Project and Cost Management
                                    A Quantity Surveying Approach




Carin Rautenbach – Vice President
John Merkler AIA – Executive Services Manager
Introduction


                 Atkinsorganization
                               Atkins
    Transport    Design & Engineering     Management &              Equity
                       Solutions          Project Services       Investments


  Rail     H&T                          Faithful & Management     Investments/
                        Water &                                     Metronet
                      Environment         Gould    Consultancy
                                         (World)
                      Engineering                     Asset
                       Solutions                   Management
                                                                   Lambert
                                                                    Smith
                    Design Solutions    Hanscomb    Project        Hampton
                                         Faithful Development
                   Design & Programme       &
                      Management          Gould
                                          (USA)
Introduction




COMPANY HISTORY              UNITED STATES                   WORDWIDE

 Atkins est. in 1938         A global company . . .         Presence in more than 60
                               Locally based                   countries and 190 offices
 Hanscomb est. in 1946                                        worldwide
                             26 offices - Major Cities in
 Faithful&Gould est. in       the USA                        2,150 independent,
  1947, acquired by Atkins                                     professional consultants
  1996                        420 Independent,
                                                               Worldwide
                               professional consultants
 Atkins HF&G merged in        in the United States
  June 2002



    Core business PROJECT and COST MANAGEMENT
    World’s leading cost consultant with over 55 years experience
Ability to Influence Project Cost & Schedule
What is Quantity Surveying?




   Quantity Surveying is in reality, a way of looking at a project
    through a Cost Management model that is quite specific
Chain of Services


                  Typical range of services

                      Contract &          Bid Analysis
                      Work Scope            & Award
                       Planning           Management




Customer                                                  Products
                              Pre-qualification
 Needs                                                   that meet
                                 & Inquiry
                                                         Customers’
                                Management
                                                           Needs
Chain of Services


                            Our range of services


                           Program and       Contract &          Bid Analysis        Change
      Feasibility
                           Procurement       Work Scope          and Award          and Trend
       Analysis
                             Strategy         Planning           Management        Management




Customer’s             Risk         Engineering      Pre-qualification     Cost and    Final Accounts
  Needs             Management      Management         and Inquiry          Project      and Asset
                                                       Management         Management      Listings
Elements of Quantity Surveying

•   Alignment & Essentials of Cost Management
•   Understanding Costs
•   Standard Formats
•   Identifying Cost Drivers
•   How to Manage Costs
     –   It all starts with a good budget
     –   Integrated cost management approach
     –   Careful use of historical information
     –   Intelligent Value analysis/engineering
     –   Sensitivity to life cycle costs & sustainability
     –   Design/Pricing Contingency
• Helpful Hints
• Industry Trends
• Recent Examples – UC Irvine; D/B Hospital
Essentials of Cost Management


Cost Management isAligning:
• Scope - Measurable and quantifiable aspects
  of the facility

• Expectations - Quality and performance
  expectations of the client

• Budget - The cost of the facility

and Maintaining Alignment over Time
Alignment



                      Scope



                     Ongoing
                      Effort

Expectations                            Budget


    Projects need to start right to finish right
Defining Scope, Expectations and Budget

              SCOPE                  EXPECTATIONS                         BUDGET
        Program                      Aesthetics                     Initial Costs
        - Functional Space Program    - Form & Massing               - Site Acquisition
        - Blocking &Stacking          - Image                        - Fees
        - Public Space                - Community Requirements       - Construction
        - Efficiency                  - Design Issues                - Inflation and Market Conditions
                                                                     - Contingencies
       Geometric Drivers              Quality                        - Other Costs
        - Wall Area Ratio             - Systems
        - Degree of Articulation      - Materials                   FutureOne-Time Costs
                                      - Workmanship                 - Replacements
       Volume Drivers                                               - Alterations
        - Clear Ceiling Height       Project Delivery               - Salvage
        - Plenum Height               - Phasing & Scheduling        - Other ne-Time Costs
                                                                           O
        - Interstitial Needs          - Continued Occupancy
        - Atria                       - Delivery System             Facility Annual Costs
        - Light Shelves                                              - Operations
                                     Systems Performance             - Maintenance
       Facility Parameters            - Functional Space Elements    - Financing
        - HVAC SF/Ton                 - Building Management          - Taxes
        - Watts/SF                    - Maintainability              - Insurance
        - Plumbing Fixtures           - Energy Consumption           - Security
        - Ductwork Poundage           - Sustainability               - Other Annual Costs
        - Steel Pounds/SF
        - Etc.                       Facility Performance           Functional Use Costs
                                      - Live Loads                   - Staffing
                                      - Expandability                - Materials
                                      - Flexibility                  - Denial of Use
                                      - Security & Safety            - Other Functional Use Costs
                                      - Access & Egress
                                      - Adjacencies
                                      - Natural Light

                                     External Requirements
                                      - Codes
                                      - Standards & Criteria
Understanding Costs
Definition of Cost




 Site Costs                             Hard Costs                               Soft Costs

     Land                   Building                    Interiors             Development Costs

                                                                               Design fees
 Land Cost              Foundations              Tenant Work
  Commission &                                                                 Management fees
                         Structure                Artwork
  Fees                                                                                                   TOTAL
                                                                               Legal fees
                         Enclosure                Furniture, Fixtures
 Title Insurance   +                         +                           +                           = CAPITAL
                                                    & Equipment                Taxes & Levies           COSTS
                         Interior Finishes
 Transfer Taxes
                                                   Telephone & Data           Insurance
                         Conveying
 Surveys                                           Communications
                                                                               Owner’s
                         HVAC &                    System
 Demolition                                                                    administration
                          Plumbing
 Sitework                                                                     Leasing commissions
                         Electrical
                                                                               Interim finance
                                                                               Moving Costs
Medical Center- Project Costs
                 (Hard Cost)
Breakdown of Construction Costs

                                     Total
                                  Hard Costs


                                     Prime
                                  Contractor /
                                  CM Mark-up
                                                                        General
                                                                      Conditions

                                 Sub-Contractor
                                    Mark-up
                                                                        General
                                                                      Conditions


             Materials                                             Installation


  Purchase Cost          Taxes                   Labor                               Equipment


                                  Premiums                                  Operations       Equipment
            Shipping &                                   Fringes
                                                                              Cost             Rental
             Handling

                                               Taxes /
                                             Insurance


                                               Base
                                               Wages
Standard Formats
Estimating Formats


• Standardized Format
  – Consistency
  – Data Base
  – Checklist
• Classifications
  –   Masterformat
  –   UNIFORMAT
  –   Contract Packages
  –   Activities
  –   Plan /Program areas
MasterFormat Divisions

DIVISION       1    General Requirements
               2    Sitework
               3    Concrete
               4    Masonry
               5    Metals
               6    Wood and Plastics
               7    Thermal and Moisture Protection
               8    Doors and Windows
               9    Finishes
               10   Specialties
               11   Equipment
               12   Furnishings
               13   Special Construction
               14   Conveying Systems
               15   Mechanical
               16   Electrical
Example - Exterior Wall System Detail


03450 - Plant-Precast Architectural Concrete
04230 - Concrete Masonry Units
07210 - Building Insulation

Three sections from three separate Divisions
  are required
UNIFORMAT Elements


• A10 Foundations
• A20 Basement Construction       •   E10   Equipment
                                  •   E20   Furnishings
•   B10   Superstructure          •   F10   Special Construction
•   B20   Exterior Closure        •   F20   Selective Building
•   B30   Roofing                 •   G10   Site Preparation
•   C10   Interior Construction   •   G20   Site Improvements
•   C20   Staircases
                                  •   G30   Site Mechanical Utilities
•   C30   Interior Finishes
•   D10   Conveying Systems
                                  • G40 Site Electrical Utilities
•   D20   Plumbing
                                  • G50 Other Site Construction
•   D30   HVAC
•   D40   Fire Protection
•   D50   Electrical
Where the Dollar Goes
         UNIFORMAT II                    Apartment          Office
            Element                       Building         Building
            (level 2)                     15 st –      15st – 140,000SF
                                         162,000SF      (shell & core)


         A.10 Foundations                 $ 0.98         $ 1.52
         A.20    Basement Construction      --             --
         B.10 Superstructure               11.41          15.38
         B.20 Exterior Closure              8.53          11.77
         B.30 Roofing                       0.24            0.35
         C.10    Interior Construction     13.16            2.74
         C.20 Staircases                    1.15            1.54
         C.30 Interior Finishes             9.74            9.35
         D.10 Conveying                     5.31            6.14
         D.20 Plumbing                      8.30            1.48
         D.30 HVAC                          9.63          11.82
         D.40 Fire Protection               1.95            2.81
         D.50 Electrical                    6.23            8.80
         F.10    Special Construction       1.33           --
         Z.      General Conditions        11.70          11.06

                ( Sitework Excluded)      $ 89.67/SF     $ 84.76/SF
UNIFORMAT II and MasterFormat
               Shell & Substructure




                                                                                                 07 Thermal & moisture protect
                                                                       MASTERFORMAT Categories




                                                                                                 13 Special construction
                                                                                                 14 Conveying systems
                                                                                                 01 General conditions




                                                                                                 08 Doors & windows
                                                                                                 06 Wood-plastic




                                                                                                 12 Furnishings


                                                                                                 15 Mechanical
                                                                                                 10 Specialties
                                                                                                 11 Equipment
                                                                                                 02 Site work




                                                                                                 16 Electrical
                                                                                                 03 Concrete
                                                                                                 04 Masonry




                                                                                                 09 Finishes
                                                                                                 05 Metals
   UNIFORMAT II Categories

Level 1                   Level 2                          Level 3
               A 10 Foundations          A 1010 Standard Foundations
SUBSTRUCTURE




                                         A 1020 Other Foundations
                                         A 1030 Slab on Grade
     A




               A 20 Basement Construction 2010 Basement Excavation
                                        A
                                        A 2020 Basement Walls

               B 10 Superstructure       B 1010 Floor Construction
                                         B 1020 Roof Construction
SHELL




               B 20 Exterior Enclosure   B 2010 Exterior Walls
  B




                                         B 2020 Exterior Windows
                                         B 2030 Exterior Doors

               B 30 Roofing              B 3010 Roof Coverings
                                         B 3020 Roof Openings
Hospitality Estimate- Uniformat
Hospitality Estimate- Masterformat
Identifying Cost Drivers
Factors Driving Building Costs

• Key Issues
  – The Pareto Principle – “The few affect the many”
  – Overlaps between disciplines
  – Timing and opportunity
• Driving Factors
  –   Geographical and Site
  –   Design – Shape, size, height & efficiency
  –   Qualitative
  –   Legal and Administrative
  –   Market and External Economic
  –   Unknowns – Contingency, escalation & risk
PARETO’S LAW OF DISTRIBUTION

                       100

                        90
  PERCENTAGE OF COST



                        80

                        70

                        60
                                           Best Value Focus
                        50

                        40

                        30

                        20

                        10

                         0
                             0      20      40       60       80       100

                             PERCENTAGE Of TOTAL FACILITY COMPONENTS
Focus on Interdisciplinary Areas


       Electrical                  Civil & structural




                                            Architectural
Mechanical




    Owner’s requirements
Relationship of Time and Change




                            Ability to                  Cost of
        High
                          make changes               making changes


 Degree of
  Change
                  Best Opportunity
                  for Improvement
        Low
               Planning              Design                 Construction

                                              Time
Building Efficiency Example



                   GFA        Cost per SF Net Rentable Net Rentable
                                         Floor Area Ratio Floor Area

Office Building A140,000 sf      85.00       80%        112,000 sf
Office Building B140,000 sf      85.00       85%        119,000 sf

What is the cost per SF of rentable area?

                      A = $106.25
                      B = $100.00
Relationship Between Quality & Cost

     HIGH
                                                                       Bankrupt Zone
                        TOTAL LIFE CYCLE COST




   COST                                         QUALITY LIMITS




                  FUTURE COSTS
      MAX
                                                                       INITIAL COSTS




      MIN


     LOW                      VC Tile Zone

            LOW                              MIN                 MAX               HIGH


                                         QUALITY
Effect of Competition on Prices

         1.25




         1.15



 Bid
         1.05
Factor

         0.95




         0.85
                0   2   4   6     8   10   12   14   16   18    20

                                Number of Bids
           Source: Area Cost Factor Study, U.S. Army Corps of Engineers
Market Conditions

   Comparison Between Bid Results and Fair Market Value                                                      Predatory
                                                                                                             Range +/-
 40                                                                                                          10-20%
                                                                                                             above or
 30
                                                                                                             below FMV
 20

 10                                                                                                           Reasonable
                                                                                                              Supply &
  0                                                                                                           Demand Range
                                                                                                              +/- 7%
 -10

 -20

 -30
       1982 1983 1984 1985 1986 1987 1988 1989 1990 1991 1992 1993 1994 1995 1996 1997 1998 1999 2000 2001


                                                YEAR
Contingencies and Escalation

• Contingencies are real costs - just not identified…. yet
• Contingency is risk dependent
• Contingency is dependent on development of design
• Where possible allocate contingency where costs will
  occur
• Clarify contingency/allowance for changes with all
  parties
• Be sure that the owner is carrying a project
  contingency
• Escalation will happen - Plan for it
• Be careful that multiple contractors are not
  overlapping
Design/Pricing Contingency

Why do we need a design/pricing contingency?
• At early stages (schematics), many decisions have yet
  to be made
• Specification yet to be defined
• Building code changes/interpretations
• Consultants who come in later (MEP) tend to add
  requirement.
• Owners requirements may change/develop.
• Market conditions – shortage of competition.
• Existing buildings – examination and testing
  incomplete.
• Definition of bid packaging/phasing.
• Front end requirements ( liquidated damages).
How to Manage Costs


•   It all starts with a good budget
•   Integrated cost management approach
•   Careful use of historical information
•   Intelligent Value analysis/engineering
•   Sensitivity to life cycle costs &
    sustainability
It All Starts with a Good Budget
   •A Good Budget Should:
        •   Reflect scope
        •   Reflect quality/performance
            expectations
        •   Reflect owners value objectives
        •   Be achievable and accepted
        •   Be defensible
        •   Contain “bridge” to ongoing cost
            control
        •   Be based on techniques and data
            available
        •   Contain adequate reserves
   •Avoid

        •   Socially acceptable budgets
        •   Playing it safe
Facility Cost Plan Summary
             Project Description:          Federal Level Office Building                                                                  Bid Date:               12/02
             Project Type:                 Office                                                                         Construction time(Months):               36
             Gross Building Area:(GSF)                 425,000                                                                   Market Conditions: good
                                                                   UNIFORMAT       TOTAL        COST PER     % OF                   ELEMENTAL ANALYSIS
UNIFORMAT             SYSTEM / ELEMENT DESCRIPTION
                       BUILDING:
                                                                   REFERENCE        COST
                                                                                     b
                                                                                                   GSF
                                                                                                 b / GSF
                                                                                                           BUILDING
                                                                                                            b / 27
                                                                                                                            MEASURE            UNIT    VALUE
                                                                                                                                                         c
                                                                                                                                                                       COST/UNIT
                                                                                                                                                                         b/c

Cost per      1
              2
                  Foundations
                       Standard Foundations
                                                                   (A10)
                                                                   (A1010)
                                                                                    3,824,493
                                                                                       75,507
                                                                                                      9.00
                                                                                                      0.18
                                                                                                                 5.5%
                                                                                                                 0.1%
                                                                                                                           Ground Floor Area SF
                                                                                                                           Ground Floor Area SF
                                                                                                                                                        108,975
                                                                                                                                                        108,975
                                                                                                                                                                           35.10
                                                                                                                                                                            0.69
                                                                                                                                                                                   UNIFORMAT
Gross Area
              3
              4
                       Other Foundations
                       Slab on Grade
                                                                   (A1020)
                                                                   (A1030)
                                                                                    2,144,701
                                                                                    1,604,285
                                                                                                      5.05
                                                                                                      3.77
                                                                                                                 3.1%
                                                                                                                 2.3%
                                                                                                                           Ground Floor Area SF
                                                                                                                           Ground Floor Area SF
                                                                                                                                                        108,975
                                                                                                                                                        108,975
                                                                                                                                                                           19.68
                                                                                                                                                                           14.72   Cost per
              5   Basement Construction                            (A20)                  -            -         0.0%      Ground Floor Area SF         108,975              -
              6                      Substructure - Sub-Total            (A)        3,824,493         9.00       5.5%      Ground Floor Area SF         108,975            35.10   System Unit
              7   Superstructure                                   (B10)            9,664,210       22.74      13.9%        Gross Bldg. Area EA         425,000            22.74
              8   Exterior Enclosure                               (B20)           17,374,453       40.88      25.0%    Gross Enclosure Area EA         188,000            92.42
              9   Roofing                                          (B30)            1,058,767         2.49       1.5%      Roof Surface Area SF         138,059             7.67
             10                               Shell - Sub-Total          (B)       28,097,431       66.11      40.5%        Gross Bldg. Area SF         425,000            66.11
             11   Interior Construction                            (C10)            3,665,491         8.62       5.3%       Gross Bldg. Area SF         425,000             8.62
             12   Stairs                                           (C20)              320,250         0.75       0.5%       Gross Bldg. Area SF         425,000             0.75
             13   Interior Finishes                                (C30)            4,197,176         9.88       6.0%       Gross Bldg. Area SF         425,000             9.88
             14                            Interiors - Sub-Total         (C)        8,182,917       19.25      11.8%        Gross Bldg. Area SF         425,000            19.25
             15   Conveying Systems                                (D10)            1,445,000         3.40       2.1%      Total No. of Stops EA             48           30,104
             16   Plumbing                                         (D20)            1,481,286         3.49       2.1%         No. of Fixtures EA            -                -
             17   HVAC                                             (D30)            9,876,438       23.24      14.2%        Tons (or MBH) EA              2,100            4,703
             18   Fire Protection                                  (D40)              989,900         2.33       1.4%         Protected Area SF         425,000             2.33
             19   Electrical                                       (D50)            9,890,639       23.27      14.3%        Gross Bldg. Area SF         425,000            23.27
             20     Electrical Service & Distribution              (D5010)          2,949,820         6.94       4.3%         Connected KW KW             8,000              369
             21     Lighting & Branch Wiring                       (D5020)          3,857,838         9.08       5.6%       Gross Bldg. Area SF         425,000             9.08
             22     Communications & Security                      (D5030)          2,171,737         5.11       3.1%       Gross Bldg. Area SF         425,000             5.11
             23     Other Electrical Systems                       (D5040)            911,244         2.14       1.3%       Gross Bldg. Area SF         425,000             2.14
             24                           Services - Sub-Total           (D)       23,683,263       55.73      34.1%        Gross Bldg. Area SF         425,000            55.73
             25             Equip. & Furnishings - Sub-Total             (E)        1,667,099         3.92       2.4%       Gross Bldg. Area SF         425,000             3.92
             26        Spec. Construct. & Demo - Sub-Total               (F)        3,932,792         9.25       5.7%       Gross Bldg. Area SF         425,000             9.25
             27        TOTAL BUILDING                                          $   69,387,994   $ 163.27      100.0%              Occupants EA            1,800    $      38,549
             28        SITEWORK & UTILITIES:
             29   Site Preparation                                 (G10)            2,105,133       4.95         3.0%        Gross Site Area   SF      522,720              4.03
             30   Site Improvements                                (G20)            3,812,500       8.97         5.5%        Gross Site Area   SF      522,720              7.29
             31   Site Mechanical Utilities                        (G30)              473,000       1.11         0.7%        Gross Site Area   SF      522,720              0.90
             32   Site Electrical Utilities                        (G40)              539,635       1.27         0.8%        Gross Site Area   SF      522,720              1.03
             33   Other Site Construction                          (G50)            4,714,207      11.09         6.8%        Gross Site Area   SF      522,720              9.02
             34    TOTAL SITEWORK & UTILITIES:                           (G)       11,644,476      27.40        16.8%        Gross Site Area   SF      522,720             22.28
             35   General Conditions, Overhead & Profit @             16.3%        13,232,602      31.14        19.1%
             36   TOTAL FACILITY COST - CURRENT                                $   94,265,072   $ 221.80       135.9%            Occupants EA            1,800     $      52,369
             37   Contingencies (Pricing, Phasing, Constr.)           18.0%        16,933,778      39.84        24.4%
             38   Escalation                                          10.3%        11,447,176      26.93        14.0%

Key          39
             40   TOTAL FACILITY COST - PROJECTED                              $ 122,646,026    $ 288.58       174.2%            Occupants EA            1,800     $      68,137

Parameter    Key Parameters:
                 1 Gross Bldg. Area
                                                                   Measure
                                                                   SF
                                                                                   Value
                                                                                     425,000
                                                                                                   Area Analysis:          Area (SF)

Tracking         2 Ground Floor Area
                 3 Gross Enclosure Area
                                                                   SF
                                                                   SF
                                                                                     108,975
                                                                                     188,000
                                                                                                Basement
                                                                                                Ground Floor                     108,975
                 4 Percent Fenestration                            %                     36%    Upper Floors                     312,025
                 5 Roof Surface Area                               SF                138,059    Penthouses                         4,000
                 6 Total No.of Conveying Stops                     STOPS                  48    Other Areas                          -
                 7 Tons Cooling (or MBH Htg)                       TONS                2,100
                 8 No. of Plumbing Fixtures                        EA                           Gross Floor Area                 425,000
                 9 Fire Protected Area                             SF                425,000
                 10 Connected KW                                   KW                  8,000
                 11 Occupants                                      EA                  1,800
                 12 Floor to Floor Height (Avg.)                   LF                     13
Integrated Cost Management Process




                                                  Cost Plan                                                                                                Revised Cost Plan                                                                                          Revised Cost Plan
                                                 by Discipline                                                                                               by Discipline                                                                                              by Discipline
                                                    Architectural                                                                                                Architectural                                                                                              Architectural
                                                                                                                  Market                                                                                                     Market
                                                  Cost       Parameter                                         Assessment,                                     Cost       Parameter                                       Assessment,                                     Cost       Parameter
                                                 Targets      Targets                                      Contingencies & Risks                              Targets      Targets                                    Contingencies & Risks                              Targets      Targets

                                                       Structural                                                                                                   Structural                                                                                                 Structural
                                                                                                                                                                                                           Constructibility,                            Historical
                                                   Cost        Parameter                         Massing,                   Quality &        Historical
                                    Historical                                                                                                                  Cost        Parameter                         Phasing &               Quality &        Benchmarks          Cost        Parameter
                                                  Targets       Targets                         Aesthetics &               Performance      Benchmarks         Targets       Targets                                                                                      Targets       Targets
 Scope           Expectations      Benchmarks                                                                                                                                                                Scheduling              Performance
                                                                                                  Image
                                                           Mechanical                                                                                                   Mechanical                                                                                                 Mechanical

                                                     Cost        Parameter                                                                                         Cost       Parameter                                                                                      Cost         Parameter
                                                    Targets       Targets                                                                                         Targets      Targets                                                                                      Targets        Targets
                Cost                                                                                                Milestone                 Revised                                                                          Milestone                 Revised
                                                                                                                                                                                                Ongoing Advice
             Analysis&             Cost Model                 Electrical               Ongoing Advice                 Cost                   CostModel                     Electrical                                            Cost                   CostModel                     Electrical
             Alignment                                                                                              Estimate                                                                                                   Estimate
                                                       Cost          Parameter                                                                                      Cost           Parameter                                                                                   Cost           Parameter
                                                      Targets         Targets                                                                                      Targets          Targets                                                                                   Targets          Targets

                                                           Equipment/Special                                                                                             Equipment/Special                                                                                          Equipment/Special
Criteria &            Site &                                                                            Phasing &            Life Cycle                                                                          Materials &            Life Cycle
Standards          Configuration                            Cost       Parameter                        Schedule           Performance &                                 Cost       Parameter
                                                                                                                                                                                                                  Systems             Performance &                                 Cost       Parameter
                                                           Targets      Targets                                            Sustainability                               Targets      Targets                                          Sustainability                               Targets      Targets

                                                                      Site                                                                                                         Site                                                                                                       Site

                                                             Cost          Parameter                                                                                      Cost          Parameter                                                                                    Cost          Parameter
                   Alternates                               Targets         Targets                                        Concepts                                                                                                   Systems
                                                                                                                                                                         Targets         Targets                                                                                    Targets         Targets
                                      Value                                                                                                    Value                                                                                                      Value
                                     Planning                                                                                                Engineering                                                                                                Engineering
                     Delivery                                                                                                System
                                                                                                                                                                                                                                      Components
                    Approaches                                                                                              Alternates


                                                                                                                                                                                                                                                                                          Project
                                                                                                                                                                                                                                                                                          History




                                                                                                               Concept Development & Schematic                                                                                 Design Development & Construction
                         Planning and Programming                                                                          Design                                                                                                         Documents
Summary of Estimating Methods


 (1)        Single Unit Rate
 (2)        Parametric/Cost Modeling
 (3)        System Elemental Cost Analysis
 (4)        Quantity Survey

Application of Cost Estimating Techniques

 Pre-Design Schematic     Design Development   Construction Documents   Pre-Bid


   SUR

             Parametric

                                System

                                                   Quantity Survey
Cost Management Tracking Example
                                                                                                                              PROJECT COST COMPARISON SUMMARY

          PROJECT: MODERNIZATION OF USCS/ICC/CW BUILDINGS COMPLEX                                                   PROJECT NO: IDC28143/IDC28144/IDC28145                            SHEET NO: 1A of 3

      LOCATION: WASHINGTON, D.C.                                                                                       COST MANAGER: HANSCOMB INC.

                                                                                                                                                    A/E ESTIMATE
                                                      Original PDS     Adjusted PDS Concept          Concept         Tentative (Rev.)Tentative (Rev.) 5%
                                                                                                                                                    7
     Construction Cost (ECCA)                         Option "A"       Option "A"   Pre-VE           After VE       Pre VE          After VE         Intermediate Final

    (Level 2)                                         Date: Jan.1992 Date: 12/6/94    Date: 07/10/95 Date: 10/10/95 Date: 11/14/95 Date: 11/28/95 Date: 12/18/95 Date:5/9/96



     01 FOUNDATIONS                                             $0                              $0             $0             $0              $0             $0              $0
      02 SUBSTRUCTURE                                       $5,000                              $0             $0             $0              $0             $0              $0
      03 SUPERSTRUCTURE                                   $385,000                       $310,105       $307,585       $844,847        $844,847      $1,349,596      $1,585,575
      04 EXTERIOR CLOSURE                               $3,029,927                      $4,715,882     $4,610,867     $6,680,867      $6,974,868     $5,618,130      $6,105,491
     05 ROOFING                                         $2,937,360                      $4,330,642     $4,330,642     $3,530,665      $3,530,665     $1,748,414      $1,654,206
       06 INTERIOR CONSTRUCTION                        $36,603,983                     $18,051,709    $15,079,374    $21,301,147     $21,103,312    $24,972,056     $27,880,252
       07 CONVEYING SYSTEMS                             $2,097,500                      $1,389,000     $1,321,791     $1,708,610      $1,708,610     $1,773,203      $1,862,732
     08 MECHANICAL                                     $27,926,204                     $28,706,881    $27,213,152    $21,973,075     $21,994,952    $24,526,254     $23,523,509
     09 ELECTRICAL                                     $17,566,534                     $24,187,059    $22,691,650    $21,106,943     $21,606,943    $20,298,145     $21,178,345
        10 GENERAL CONDITIONS AND PROFIT               $15,591,418                     $15,321,706    $14,225,258    $15,986,755     $16,016,755    $15,802,655     $17,077,336
     11 EQUIPMENT                                         $548,800                       $814,013       $814,013       $995,113        $995,113      $1,496,265      $1,434,306
     12 SITEWORK                                        $6,042,481                     $13,255,375    $12,182,236    $15,279,927     $16,142,148     $8,281,772      $8,114,647

    SUBTOTAL                                          $112,734,207                    $111,082,372   $102,776,568   $109,407,949 $110,918,213      $105,866,490    $110,416,399
     DESIGN CONTINGENCY                               Incl. in 01-12                   $11,108,237    $10,277,657    $10,940,795  $11,091,821        $7,939,987              $0

    SUBTOTAL                                          $112,734,207                    $122,190,609   $113,054,225   $120,348,744 $122,010,034      $113,806,477    $110,416,399
    ESCALATION :                                       $26,632,920                     $10,031,849     $9,281,752
                           TO START OF CC# 1 - 9/96                                                                    $206,739        $206,739       $180,888        $105,399
                           TO START OF CC# 2 - 2/97                                                                   $2,080,767      $2,561,242     $1,779,027      $1,020,008
                          TO START OF CC# 3 - 12/97                                                                   $4,459,648      $5,489,433     $3,860,835      $2,749,961

      SUBTOTAL (ECCA) - CC # 1, 2 and 3               $139,367,127 $130,588,000       $132,222,458   $122,335,977   $127,095,898 $130,267,448      $119,627,227    $114,291,767
      (including reimbursable items)
       CONSTRUCTION CONTINGENCY @ 7%                    $6,799,995       $9,141,000     $9,255,572     $8,563,518     $8,896,713      $9,118,721     $8,373,906      $8,000,424

       ESTIMATED CONSTRUCTION COST (ECC)              $146,167,122 $139,729,000       $141,478,030   $130,899,495   $135,992,611 $139,386,170      $128,001,133    $122,292,191
     Cost per SM                                                                         $1,253.16      $1,159.46       $1,204.57      $1,234.63       $1,133.79          $1,083.22
      Gross Floor Area (M2)                                                                112,897        112,897         112,897        112,897         112,897            112,897

    CONSTRUCTION CONTRACT No. 1 (ECC)                    $7,907,207      $7,955,000                                    $9,362,167     $9,362,167     $10,119,187      $7,890,514



    CONSTRUCTION CONTRACT No. 2 (ECC)                  $53,613,049      $55,208,000                                   $50,209,613    $51,295,552     $47,334,557     $51,156,045



    CONSTRUCTION CONTRACT No. 3 (ECC) + SITE           $84,646,866      $76,566,000                                   $76,420,830    $78,728,451     $70,547,388     $63,245,632
Historical Cost Model Database
                                                    BUILDING COST SUMMARY - ALL PROJECTS (Adjusted to April 2001)
  Project Description:               Elementary Schools Bid Date                   11/96                       8/95                        10/93                          1/97                       9/94              Adjusted                           Adjusted
  Project Type:                  School                  Constr Time                14                          15                           14                            14                         16               Average                            Average
                                                         Market                    good                        good                       excellent                       good                       good               of All                             of All
                                                           UNIFORMAT       Example 1       Adjusted    Example 2      Adjusted    Example 3       Adjusted        Example 4      Adjusted    Example 5      Adjusted
            SYSTEM / ELEMENT DESCRIPTION                  REFERENCE       TOTAL COST       $/sf by:   TOTAL COST      $/sf by:   TOTAL COST           $/sf by:   TOTAL COST      $/sf by:   TOTAL COST      $/sf by:    ($/SF)                       ($/Parameter)
                BUILDING:                                                      b               1.14        b              1.18        b                   1.32        b              1.13        b              1.21
    1   Foundations                                      (A10)                506,192        7.47         485,255       6.83         397,823           7.80          561,768       8.13         385,840       7.01        7.45       Ground Floor Area         74,780    SF       7.45
    2        Standard Foundations                        (A1010)              302,142        4.46         277,228       3.90         219,741           4.31          348,071       5.04         230,305       4.18        4.38       Ground Floor Area         74,780    SF       4.38
    3        Other Foundations                           (A1020)                  -           -               -          -               -              -                -          -               -          -           -         Ground Floor Area         74,780    SF        -
    4        Slab on Grade                               (A1030)              204,050        3.01         208,027       2.93         178,081           3.49          213,698       3.09         155,535       2.82        3.07       Ground Floor Area         74,780    SF       3.07
    5   Basement Construction                            (A20)                    -           -               -          -               -              -                -          -               -          -           -         Ground Floor Area         74,780    SF        -
    6                     Substructure - Sub-Total                  (A)       506,192        7.47         485,255       6.83         397,823           7.80          561,768       8.13         385,840       7.01        7.45       Ground Floor Area         74,780    SF       7.45
    7   Superstructure                                   (B10)                400,900        5.92         408,714       5.75         291,566           5.72          461,841       6.69         305,582       5.55        5.92        Gross Bldg. Area         74,780    SF       5.92
    8   Exterior Enclosure                               (B20)                537,917        7.94         504,529       7.10         391,216           7.67          563,351       8.16         360,819       6.55        7.48    Gross Enclosure Area         30,646    SF      18.25
    9   Roofing                                          (B30)                273,275        4.03         278,601       3.92         198,747           3.90          329,125       4.77         208,301       3.78        4.08      Roof Surface Area          77,492    SF       3.94
   10                             Shell - Sub-Total                 (B)     1,212,092       17.89       1,191,845      16.78         881,529          17.28        1,354,317      19.61         874,703      15.88       17.49        Gross Bldg. Area         74,780    SF      17.49
   11   Interior Construction                            (C10)                560,523        8.27         571,448       8.04         346,508           6.79          587,025       8.50         405,890       7.37        7.80        Gross Bldg. Area         74,780    SF       7.80
   12   Stairs                                           (C20)                    -           -               -          -               -              -                -          -               -          -           -          Gross Bldg. Area         74,780    SF        -
   13   Interior Finishes                                (C30)                394,833        5.83         483,034       6.80         258,438           5.07          413,501       5.99         361,149       6.56        6.05        Gross Bldg. Area         74,780    SF       6.05
   14                         Interiors - Sub-Total                 (C)       955,356       14.10       1,054,482      14.84         604,946          11.86        1,000,526      14.49         767,040      13.93       13.84        Gross Bldg. Area         74,780    SF      13.84
   15   Conveying Systems                                (D10)                  7,288        0.11           7,430       0.10           5,300           0.10            7,633       0.11           5,555       0.10        0.11       Total No. of Stops              1   EA      7,901
   16   Plumbing                                         (D20)                447,800        6.61         456,528       6.43         325,675           6.38          468,973       6.79         341,331       6.20        6.48          No. of Fixtures          144     EA      3,365
   17   HVAC                                             (D30)              1,049,400       15.49       1,283,824      18.07         763,206          14.96        1,099,017      15.91         799,895      14.53       15.79        Tons   (or MBH)            208     EA      5,689
   18   Fire Protection                                  (D40)                151,800        2.24         154,759       2.18         110,401           2.16          158,977       2.30         115,708       2.10        2.20          Protected Area         74,780    SF       2.20
   19   Electrical                                       (D50)                859,866       12.69         859,866      12.10         859,866          16.86          859,866      12.45         859,866      15.62       13.94        Gross Bldg. Area         74,780    SF      13.94
   20    Electrical Service & Distribution               (D5010)              182,120        2.69         185,670       2.61         132,452           2.60          190,731       2.76         138,819       2.52        2.64         Connected KW              660     KW        299
   21    Lighting & Branch Wiring                        (D5020)              286,132        4.22         291,709       4.11         208,098           4.08          344,610       4.99         218,101       3.96        4.27        Gross Bldg. Area         74,780    SF       4.27
   22    Communications & Security                       (D5030)              205,778        3.04         209,789       2.95         149,658           2.93          269,384       3.90         156,852       2.85        3.13        Gross Bldg. Area         74,780    SF       3.13
   23    Other Electrical Systems                        (D5040)              185,836        2.74         189,458       2.67         135,155           2.65          194,623       2.82         141,652       2.57        2.69        Gross Bldg. Area         74,780    SF       2.69
   24                         Services - Sub-Total                  (D)     2,516,154       37.14       2,762,407      38.89       2,064,449          40.47        2,594,466      37.57       2,122,355      38.54       38.52        Gross Bldg. Area         74,780    SF      38.52
   25             Equip. & Furnishings - Sub-Total                  (E)       211,210        3.12         215,327       3.03         153,609           3.01          221,196       3.20         193,191       3.51        3.17        Gross Bldg. Area         74,780    SF       3.17
   26        Spec. Construct. & Demo - Sub-Total                    (F)        28,500        0.42          29,055       0.41          20,727           0.41           29,848       0.43          21,724       0.39        0.41        Gross Bldg. Area         74,780    SF       0.41
   27        TOTAL BUILDING                                               $ 5,429,504       80.14     $ 5,738,371      80.78     $ 4,123,083          80.83      $ 5,762,121      83.44     $ 4,364,853      79.27       80.89     Accomodation Units            700     EA   $ 8,675
   28        SITEWORK & UTILITIES:                                                            -                          -                              -                           -                          -           -                                                       -
   29   Site Preparation                                 (G10)               467,598         6.90         657,181       9.25         375,979           7.37          482,827       6.99         527,489       9.58        8.02         Gross Site Area        620,000    SF       0.96
   30   Site Improvements                                (G20)                85,122         1.26          99,695       1.40          88,977           1.74           87,894       1.27          71,129       1.29        1.39         Gross Site Area        620,000    SF       0.17
   31   Site Mechanical Utilities                        (G30)               301,500         4.45         353,117       4.97         242,426           4.75          311,319       4.51         214,147       3.89        4.51         Gross Site Area        620,000    SF       0.55
   32   Site Electrical Utilities                        (G40)                   -            -               -          -               -              -                -          -               -          -           -           Gross Site Area        620,000    SF        -
   33   Other Site Construction                          (G50)                   -            -               -          -               -              -                -          -               -          -           -           Gross Site Area        620,000    SF        -
   34   TOTAL SITEWORK & UTILITIES:                                  (G)     854,220        12.61       1,109,993      15.63         707,382          13.87          882,041      12.77         812,765      14.76       13.93         Gross Site Area        620,000    SF       1.68
   35   General Conditions, Overhead & Profit @                   5.1%       322,647         4.76         351,639       4.95         248,027           4.86          341,154       4.94         265,852       4.83        4.87                                                     -
   36   TOTAL FACILITY COST - CURRENT                                    $ 6,606,371        97.51     $ 7,200,003     101.36     $ 5,078,492          99.56      $ 6,985,316     101.15     $ 5,443,470      98.86       99.69     Accomodation Units            700     EA   $ 10,692
   37   Contingency                                  @                           -            -               -          -               -              -                -          -               -          -           -                                                       -
   38   Escalation                                   @                           -            -               -          -               -              -                -          -               -          -           -                                                       -
   39                                                                                         -                          -                              -                           -                          -           -                                                       -
   40   TOTAL FACILITY COST - PROJECTED                                   $ 6,606,371       97.51     $ 7,200,003     101.36     $ 5,078,492          99.56      $ 6,985,316     101.15     $ 5,443,470      98.86       99.69     Accomodation Units            700     EA   $ 10,692
   41   TOTAL FACILITY COST/SF - PROJECTED                                $     85.57       97.51     $     85.71     101.36     $     75.24          99.56      $     89.21     101.15     $     81.37      98.86       99.69                   -

  Parameters:                                            Measure             Value                       Value                      Value                           Value                      Value                    Value
       1 Gross Bldg. Area                                SF                    77,200                      84,000                     67,500                          78,300                     66,900                 74,780
       2 Ground Floor Area                               SF                    77,200                      84,000                     67,500                          78,300                     66,900                 74,780
       3 Gross Enclosure Area                            SF                    31,000                      33,731                     28,000                          32,500                     28,000                 30,646
       4 Percent Fenestration                            %                        12%                         12%                        15%                             12%                        15%                    13%
       5 Roof Surface Area                               SF                    80,000                      87,047                     69,948                          81,140                     69,326                 77,492
       6 Total No.of Conveying Stops                     STOPS                      1                           1                          1                               1                          1                       1
       7 Tons Cooling (or MBH Htg)                       TONS                     200                         240                        200                             200                        200                    208
       8 No. of PlumbingFixtures                         EA                       150                         160                        130                             150                        130                    144
       9 Fire Protected Area                             SF                    77,200                      84,000                     67,500                          78,300                     66,900                 74,780
      10 Connected KW                                    KW                       650                         750                        600                             700                        600                    660
      11 Accomodation Units                              EA                       750                         800                        600                             750                        600                    700
      12 Floor to Floor Height (Avg.)                    LF                        12                          12                         12                              12                         12                     12
      13 Gross Site Area                                 SF                   600,000                     750,000                    580,000                         600,000                    570,000                620,000
      14 Gross Bldg. Area per Accomod Unit               SF/EA                    103                         105                        113                             104                        112                    107
Hospital Cost Model

Based on Historical Data from Other Hospitals
•   Compare/benchmark other hospitals
•   Adjust for OSHPD V non-OSHPD criteria
•   Adjust for location
•   Adjust for central plant V no central plant
•   Adjust for size factor
•   Adjust for phasing/links
•   Adjust for time/escalation
•   Adjust for unique costs
•   Adjust for shelled space
•   Adjust for medical equipment with hard cost
Sensitivity to Life Cycle Impact


                                  Transportation          Construction 18%
         2% Other Support Costs      5%
         1% School Allotment
             1% Textbooks
                                                                             Furnishings / Fitout 4%
Benefits / Overhead                                                           Fees 1%
               14%                                                              Other Project Costs 1%
                                                                                 ConstructionContingency 1%
                                                                                Major Capital Replacements
                                                                                5%

                                                                                  Maintenance 3%
Support Staffing
           11%

                                                                                Energy 2%




                                              Educational Staffing 31%
Life Cycle Costing Example

Life Cycle Cost Analysis                                                                                           Alternative 1                  Alternative 2                    Alternative 3            Alternative 4
General Purpose Worksheet                                                                                         Individual Rooftop             Central Plant with
                                                                                                                        Units                  4 - Pipe Fan Coil Units

Study Title:                                  HVAC System Analysis                                             Estimated        Present       Estimated      Present           Estimated      Present   Estimated      Present
Discount Rate :                                       8%           Date:   12/17/97                              Costs           Worth         Costs          Worth             Costs          Worth      Costs         Worth
Life Cycle (Yrs.)            30
            Initial/Collateral Costs
     INITIAL / COLLATERAL COSTS




       A. Equipment                                                                                              1,212,354        1,212,354     2,803,000      2,803,000
       B. Screening                                                                                                 55,501           55,501        40,000         40,000
       C. Plant Space                                                                                                                             128,000        128,000
       D.
       E.
       F.
       G.
                                  Total Initial/Collateral Costs                                                $1,267,855       $1,267,855    $2,971,000     $2,971,000
                                  Difference                                                                                                                 ($1,703,145)
                                  Replacement/Salvage                                                 PW
 REPLACEMENT / SALVAGE




                                  (Single Expenditures)                                  Year        Facto r

                                  A. Rooftop Units (70%)                                  8          0.540        770,000          416,007
                                  B. Rooftop Units (70%)                                  16         0.292        770,000          224,756
        COSTS




                                  C. Rooftop Units (70%)                                  24         0.158        770,000          121,428
                                  D. Fan Coils(100%)                                      15         0.315                                       408,888         128,899
                                  E. Central Plant Equipment                              20         0.215                                       600,000         128,729
                                  F.
                                  G.
                                  Total Replacement/Salvage Costs                                                                 $762,191                      $257,627
                                  Annual Costs                                        Differential    PW
                                                                                      Escal. Rate    Facto r
     ANNUAL COSTS




                                  A.   Maintenance - Rooftops                                1%       12.496       75,360          941,693
                                  B.   Maintenance - Fan Coils                               1%       12.496                                      37,680         470,847
                                  C.   Maintenance - Central Plant & Distrib.                1%       12.496                                      28,800         359,883
                                  D.   Energy                                                3%       15.631      468,000         7,315,296      192,000       3,001,147
                                  E.
                                  F.
                                  G.
                                  Total Annual Costs                                                             $543,360        $8,256,989     $258,480      $3,831,876
                                  Total Life Cycle Costs (Present Worth)                                                        $10,287,035                   $7,060,504
LIFE CYCLE
  COSTS




                                  Life Cycle Cost PW Difference                                                                                               $3,226,531
                                  Discounted Payback (Alt. 2,3,4 vs. Alt. 1)                                                                                             3.9
                                  Total Life Cycle Costs - Annualized                                             Per Year:       $913,771       Per Year:      $627,166          Per Year:                Per Year:
LEED Checklist Excerpted from
LEED Green Building Rating System™
Industry Trends

• Variety of delivery systems
• New risk sharing approaches
• Increasing interest in sustainability/green
• Increase in security measures
• Protectionist legislation to protect certain
  industries (steel, concrete, lumber)
• Demand for speed
• Outsourcing of management skills
• Local Factors
Industry Trends (cont.)


• Sector Corrections –
     • Volume up
            Medical, schools, housing
     • Volume down
             Office, hi-tech, most other sectors
• Materials/Union Wages
     • Union wage rates are increasing 3-4% per annum.
     • Materials are pretty erratic with some exceptions.
• Awareness of bidding climate
Helpful Cost Management Hints

• The budget must be aligned
• Apportion budgets by discipline …and manage
  them
• Manage scope
• Manage quality and performance
• Define and adhere to key parameter measures
• “Buy in” to all estimates – share responsibility
• If necessary, get a second opinion
• Use value engineering/value analysis
• Be willing to learn lessons and share results
Understanding Costs
                                     UC Irvine
Replacement Hospital Project – Recent Example
UCI Replacement Hospital

Change Order Review scope - ”…manage what?”
UCI Replacement Hospital

• Design/Build Hospital project
  – Estimating & D/B oversight initial charge
• Charge from Campus for Cost
  Management
  –   Real time review – but comprehensive
  –   Transparent process – OSHPD aware
  –   Organize Project Managers
  –   Integrate “field” & design
• Importance to Campus
  – Audit trail
  – Simple organization - One source of information
  – Understanding of “where the money went”
UCI Replacement Hospital


• How UCI chose to Manage Cost –
  Replacement Hospital
  – I/M system integration – “Prolog” based
     • HP Database + UCI Database = Collaboration
  – PM meetings – monthly scope/OSHPD/field review
  – Integrating “all” contracts – D/B + others + UCI provided
    material
  – Reporting - integrated
  – Document Control – RFI/Bulletin/Ltr of Instruction/CO’s
Alignment



                      Scope



                     Ongoing
                      Effort

Expectations                            Budget


    Projects need to start right to finish right
Project and Cost Management
                                    A Quantity Surveying Approach




Carin Rautenbach – Vice President
John Merkler AIA – Executive Services Manager
Market Inflation Indices
(Based on a 100 Value
in 1977)

300.00



                                                          CPI Basic                           Means Index
250.00




200.00




150.00




100.00




 50.00
                              1980




                                                                                       1988




                                                                                                                                                             1998
         1977

                1978

                       1979



                                     1981

                                            1982

                                                   1983

                                                           1984

                                                                  1985

                                                                         1986

                                                                                1987



                                                                                              1989

                                                                                                     1990

                                                                                                            1991

                                                                                                                   1992

                                                                                                                          1993

                                                                                                                                 1994

                                                                                                                                        1995

                                                                                                                                               1996

                                                                                                                                                      1997



                                                                                                                                                                    1999
   -
Index History
(Yearly Percent
Change)
  16.00%


  14.00%

  12.00%


  10.00%                                                                    GDP                  CPI Basic              Means Index


     8.00%


     6.00%


     4.00%

3%
     2.00%


     0.00%


  -2.00%
                                   Recession                                                      Recession
  -4.00%
             1978


                           1980
                                  1981
                                         1982
                                                1983
                                                       1984
                                                              1985
                                                                     1986
                                                                            1987
                                                                                   1988
                                                                                          1989
                                                                                                  1990
                                                                                                         1991
                                                                                                                1992
                                                                                                                       1993
                                                                                                                              1994
                                                                                                                                     1995
                                                                                                                                            1996
                                                                                                                                                   1997
                                                                                                                                                          1998
                    1979




                                                                                                                                                                 1999
Integrated Cost
Management Process
- Planning & Programming


                                                                      Cost Plan
                                                                     by Discipline

                                                                       Architectural
                                                                      Cost         Parameter
                                                                     Targets        Targets


                                                                          Structural
                                                                        Cost         Parameter
                                                        Historical
                                                                       Targets        Targets
                  Scope          Expectations          Benchmarks
                                                                           Mechanical
                                                                          Cost           Parameter
                                                                         Targets          Targets
                            Cost
                          Analysis &                   Cost Model                Electrical
                          Alignment                                         Cost           Parameter
                                                                           Targets          Targets

                                                                          Equipment/Special
                 Criteria &              Site &
                 Standards             Configuration                            Cost        Parameter
                                                                               Targets       Targets

                                                                                           Site
                                                                                  Cost         Parameter
                                   Alternates                                    Targets        Targets
                                                          Value
                                                         Planning
                                   Delivery
                                  Approaches




                                         Planning and Programming
Facility Value Target




                        01
       Foundations




                        02
       Substructure




                        03
     Superstructure
                                                     Sensible Trade-Offs




                        04
   Exterior Closures


                        05
            Roofing
                        06
Interior Construction
                        07



         Conveying
                        08




         Mechanical
                        09




           Electrical
                        10




General Conditions
                        11




           Sitework
Traditional Design-Bid-
Build Delivery
Traditional Design-Bid-Build Delivery



Fundamental Approach
• Prime contracts directly with owner
• A/E selected by qualifications or
  qualifications/price.
• A/E prepares design to 100%.
• Open bidding to general contractors (may
  be prequalified).
• Awarded of contract to lowest responsive
  bidder
Construction Manager at
Risk Delivery
Construction Manager at
  Risk Delivery



Approach

• CM (at risk) has direct contract with owner, as
  does A/E.
• A/E selected by qualifications or
  qualifications/price.
• CM (at risk) selected on qualifications or
  qualifications and fee for general conditions and
  profit.
• CM (at risk) responsible for work scheduling and
  means/methods.
Construction Manager at
 Risk Delivery



Variations

• CM (PM) can be retained in an agency
  relationship to coordinate process.

• GMP can be followed with CM (at risk) open
  bidding to subcontractors.
     Final price can “float” up to GMP.
     Or “shared savings” up to GMP with owner.
     Or a firm fixed price can be negotiated.
Design – Build Delivery
Advantage and
Disadvantages of Delivery
Systems


           Traditional Design-Bid Build
     ISSUES              ADVANTAGES                     DISADVANTAGES

  Cost and Budget     “Best price” potential.           Cost not finalized until
  Management           Perception of “best price”.   bids.
                                                        Cost overruns after bid
                                                     require
                                                        expensive redesign.
                                                        Bidders may seek to “get
                                                     low”
                                                        by omitting work not
                                                     clearly
                                                        shown.
  Schedule Impact       Delivery schedule                Construction difficult to
  and Management    stipulated in                    start
                        contract.                        before design is finished.
                                                         Extended/compressed
                                                         schedules may add cost
Advantage and
Disadvantages of Delivery
Systems


          Construction Manager at Risk
     ISSUES              ADVANTAGES                DISADVANTAGES

  Cost and Budget     Cost “guarantee” prior to     After GMP, costs may
  Management          design completion.         increase
                      Improved perception of        due to detailing not
                      control.                   correctly
                      Cost saving incentives are • reflected in the GMP.
                      feasible.                     CM may “expand” budget
                                                 to
                                                     create opportunity for
                                                 future
                                                     savings”.
  Schedule Impact      Construction can start      Schedule changes during
  and Management    before                         construction difficult to
                      design is complete.          implement.
                      Cost of impact of
                      extended/compressed
Advantage and
Disadvantages of Delivery
Systems


                          Design-Build
    ISSUES              ADVANTAGES                     DISADVANTAGES

 Cost and Budget     Early cost guarantee.            Fair price competition difficult
 Management          Price tends to match        to
                   quality.                          verify.
                     Can obtain best price for      Cost impact of risk issues
                      performance.               may
                                                     not be evident in initial
                                                 pricing.
                                                    Owner overemphasis on
                                                 price
                                                     as a selection criterion may
                                                     force the design-builder to
                                                     compromise quality to reduce
                                                     price.
 Schedule Impact      Construction can start        Schedule changes at any
 and Management    after                         point
Price Index / Cost
Index
Qs Approach To Project Cost

More Related Content

What's hot

problems on Staad.pro and analysis of a 5 storey building using Etabs
problems on Staad.pro and analysis of a 5 storey building using Etabsproblems on Staad.pro and analysis of a 5 storey building using Etabs
problems on Staad.pro and analysis of a 5 storey building using Etabssrinivas cnu
 
Analysis and design of reinforced concrete bridge structures copy
Analysis and design of reinforced concrete bridge structures copyAnalysis and design of reinforced concrete bridge structures copy
Analysis and design of reinforced concrete bridge structures copyimaduddin91
 
Book for Beginners, RCC Design by ETABS
Book for Beginners, RCC Design by ETABSBook for Beginners, RCC Design by ETABS
Book for Beginners, RCC Design by ETABSYousuf Dinar
 
Chapter 2 seviceability and durability
Chapter 2 seviceability and durabilityChapter 2 seviceability and durability
Chapter 2 seviceability and durabilityAnkit Patel
 
Redistribution of moments-Part-1
Redistribution of moments-Part-1Redistribution of moments-Part-1
Redistribution of moments-Part-1Subhash Patankar
 
Service Life Prediction of RC Structure With Respect to Corrosion of Steel
Service Life Prediction of RC StructureWith Respect to Corrosion of SteelService Life Prediction of RC StructureWith Respect to Corrosion of Steel
Service Life Prediction of RC Structure With Respect to Corrosion of SteelNitesh Jha
 
QUANTITY SURVEYING
QUANTITY SURVEYINGQUANTITY SURVEYING
QUANTITY SURVEYINGlizwi nyandu
 
Practice of Civil Engineering
Practice of Civil EngineeringPractice of Civil Engineering
Practice of Civil Engineeringjoshuajayjjj
 
A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006Melvin Lim
 
REPAIRING WORKS FOR CRACKS ...
																		     REPAIRING WORKS FOR CRACKS 				 				                  ...																		     REPAIRING WORKS FOR CRACKS 				 				                  ...
REPAIRING WORKS FOR CRACKS ...sathish sak
 
Civil Engineering Action Plan
Civil Engineering Action PlanCivil Engineering Action Plan
Civil Engineering Action Planrkosta
 
Major projects aluminium of formwork civil engineering
Major  projects aluminium of formwork civil engineeringMajor  projects aluminium of formwork civil engineering
Major projects aluminium of formwork civil engineeringGopal jakhar
 
Estimating and-costing book
Estimating and-costing bookEstimating and-costing book
Estimating and-costing bookThomas Britto
 
Condition assessment of RCC structures and their Rehabilitation
Condition assessment of RCC structures and their RehabilitationCondition assessment of RCC structures and their Rehabilitation
Condition assessment of RCC structures and their RehabilitationMairajnk99
 
Construction of marine and offshore structures(2007)
Construction of marine and offshore structures(2007)Construction of marine and offshore structures(2007)
Construction of marine and offshore structures(2007)calir2lune
 
Quantity surveying course
Quantity surveying courseQuantity surveying course
Quantity surveying courseJavid Hussain
 

What's hot (20)

RETAINING WALLS
RETAINING WALLSRETAINING WALLS
RETAINING WALLS
 
problems on Staad.pro and analysis of a 5 storey building using Etabs
problems on Staad.pro and analysis of a 5 storey building using Etabsproblems on Staad.pro and analysis of a 5 storey building using Etabs
problems on Staad.pro and analysis of a 5 storey building using Etabs
 
Analysis and design of reinforced concrete bridge structures copy
Analysis and design of reinforced concrete bridge structures copyAnalysis and design of reinforced concrete bridge structures copy
Analysis and design of reinforced concrete bridge structures copy
 
Book for Beginners, RCC Design by ETABS
Book for Beginners, RCC Design by ETABSBook for Beginners, RCC Design by ETABS
Book for Beginners, RCC Design by ETABS
 
Chapter 2 seviceability and durability
Chapter 2 seviceability and durabilityChapter 2 seviceability and durability
Chapter 2 seviceability and durability
 
Redistribution of moments-Part-1
Redistribution of moments-Part-1Redistribution of moments-Part-1
Redistribution of moments-Part-1
 
Service Life Prediction of RC Structure With Respect to Corrosion of Steel
Service Life Prediction of RC StructureWith Respect to Corrosion of SteelService Life Prediction of RC StructureWith Respect to Corrosion of Steel
Service Life Prediction of RC Structure With Respect to Corrosion of Steel
 
QUANTITY SURVEYING
QUANTITY SURVEYINGQUANTITY SURVEYING
QUANTITY SURVEYING
 
Practice of Civil Engineering
Practice of Civil EngineeringPractice of Civil Engineering
Practice of Civil Engineering
 
A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006
 
REPAIRING WORKS FOR CRACKS ...
																		     REPAIRING WORKS FOR CRACKS 				 				                  ...																		     REPAIRING WORKS FOR CRACKS 				 				                  ...
REPAIRING WORKS FOR CRACKS ...
 
Civil Engineering Action Plan
Civil Engineering Action PlanCivil Engineering Action Plan
Civil Engineering Action Plan
 
ETABS Modelling
ETABS ModellingETABS Modelling
ETABS Modelling
 
Major projects aluminium of formwork civil engineering
Major  projects aluminium of formwork civil engineeringMajor  projects aluminium of formwork civil engineering
Major projects aluminium of formwork civil engineering
 
Estimating and-costing book
Estimating and-costing bookEstimating and-costing book
Estimating and-costing book
 
Bridges In Pakistan
Bridges In PakistanBridges In Pakistan
Bridges In Pakistan
 
Condition assessment of RCC structures and their Rehabilitation
Condition assessment of RCC structures and their RehabilitationCondition assessment of RCC structures and their Rehabilitation
Condition assessment of RCC structures and their Rehabilitation
 
Construction of marine and offshore structures(2007)
Construction of marine and offshore structures(2007)Construction of marine and offshore structures(2007)
Construction of marine and offshore structures(2007)
 
Dss notes
Dss notesDss notes
Dss notes
 
Quantity surveying course
Quantity surveying courseQuantity surveying course
Quantity surveying course
 

Viewers also liked

Consultants estimating manual
Consultants estimating manualConsultants estimating manual
Consultants estimating manualDaniel Libe
 
Beyond the bca
Beyond the bcaBeyond the bca
Beyond the bcaRobb Dods
 
Optimizing Capital Investments in Health Facilities through Prototype Develop...
Optimizing Capital Investments in Health Facilities through Prototype Develop...Optimizing Capital Investments in Health Facilities through Prototype Develop...
Optimizing Capital Investments in Health Facilities through Prototype Develop...CannonDesign
 
cost control analysis as effective tools in construction industry in nigeria
cost control analysis as effective tools in construction industry in nigeriacost control analysis as effective tools in construction industry in nigeria
cost control analysis as effective tools in construction industry in nigeriaNewman Jonathan
 
Lecture 06 project_cost_management
Lecture 06 project_cost_managementLecture 06 project_cost_management
Lecture 06 project_cost_managementSayed Ahmed
 
Cleopatra Enterprise Added Value
Cleopatra Enterprise Added ValueCleopatra Enterprise Added Value
Cleopatra Enterprise Added ValueLeendertdegeus
 
PMP Training Project Cost Management Part 1
PMP Training Project Cost Management Part 1PMP Training Project Cost Management Part 1
PMP Training Project Cost Management Part 1Skillogic Solutions
 
GENERIC - Comparing Different Construction Delivery Methods - Aug 2014_r1
GENERIC - Comparing Different Construction Delivery Methods - Aug 2014_r1GENERIC - Comparing Different Construction Delivery Methods - Aug 2014_r1
GENERIC - Comparing Different Construction Delivery Methods - Aug 2014_r1Charles S. Maggio
 
Construction Projects Delivery Methods - Nilaksh Kothari, Manitowoc Public Ut...
Construction Projects Delivery Methods - Nilaksh Kothari, Manitowoc Public Ut...Construction Projects Delivery Methods - Nilaksh Kothari, Manitowoc Public Ut...
Construction Projects Delivery Methods - Nilaksh Kothari, Manitowoc Public Ut...marcus evans Network
 
ملاحظات مهمة عن تعجيل المشاريع
ملاحظات مهمة عن تعجيل المشاريعملاحظات مهمة عن تعجيل المشاريع
ملاحظات مهمة عن تعجيل المشاريعDr. Mahmoud Al-Naimi
 
Final Presentation for Project A.D.I.O.S.
Final Presentation for Project A.D.I.O.S.Final Presentation for Project A.D.I.O.S.
Final Presentation for Project A.D.I.O.S.Sung (Stephen) Kim
 
Management, Cost, and Schedule Paper for Project A.D.I.O.S.
Management, Cost, and Schedule Paper for Project A.D.I.O.S.Management, Cost, and Schedule Paper for Project A.D.I.O.S.
Management, Cost, and Schedule Paper for Project A.D.I.O.S.Sung (Stephen) Kim
 
Management, Cost, and Schedule Presentation for Project A.D.I.O.S.
Management, Cost, and Schedule Presentation for Project A.D.I.O.S.Management, Cost, and Schedule Presentation for Project A.D.I.O.S.
Management, Cost, and Schedule Presentation for Project A.D.I.O.S.Sung (Stephen) Kim
 
Mesurement presentation pavaruban
Mesurement presentation pavarubanMesurement presentation pavaruban
Mesurement presentation pavarubanthevaraja pavaruban
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost ManagementSerdar Temiz
 
Total Cost Management - Synergy between Cost Estimating and Project Controls
Total Cost Management - Synergy between Cost Estimating and Project ControlsTotal Cost Management - Synergy between Cost Estimating and Project Controls
Total Cost Management - Synergy between Cost Estimating and Project ControlsMartin van Vliet
 
PMBoK, discussion #5: Project Cost Management
PMBoK, discussion #5: Project Cost ManagementPMBoK, discussion #5: Project Cost Management
PMBoK, discussion #5: Project Cost ManagementOleksandr Lutsaievskyi
 
project cost management
project cost managementproject cost management
project cost managementjay mitkari
 
Composite Crews in Construction Cost Estimating
Composite Crews in Construction Cost Estimating Composite Crews in Construction Cost Estimating
Composite Crews in Construction Cost Estimating Doina Dobre, P.Eng, GSC
 

Viewers also liked (20)

Consultants estimating manual
Consultants estimating manualConsultants estimating manual
Consultants estimating manual
 
Beyond the bca
Beyond the bcaBeyond the bca
Beyond the bca
 
Optimizing Capital Investments in Health Facilities through Prototype Develop...
Optimizing Capital Investments in Health Facilities through Prototype Develop...Optimizing Capital Investments in Health Facilities through Prototype Develop...
Optimizing Capital Investments in Health Facilities through Prototype Develop...
 
European research experience and needs on smart metering
European research experience and needs on smart metering European research experience and needs on smart metering
European research experience and needs on smart metering
 
cost control analysis as effective tools in construction industry in nigeria
cost control analysis as effective tools in construction industry in nigeriacost control analysis as effective tools in construction industry in nigeria
cost control analysis as effective tools in construction industry in nigeria
 
Lecture 06 project_cost_management
Lecture 06 project_cost_managementLecture 06 project_cost_management
Lecture 06 project_cost_management
 
Cleopatra Enterprise Added Value
Cleopatra Enterprise Added ValueCleopatra Enterprise Added Value
Cleopatra Enterprise Added Value
 
PMP Training Project Cost Management Part 1
PMP Training Project Cost Management Part 1PMP Training Project Cost Management Part 1
PMP Training Project Cost Management Part 1
 
GENERIC - Comparing Different Construction Delivery Methods - Aug 2014_r1
GENERIC - Comparing Different Construction Delivery Methods - Aug 2014_r1GENERIC - Comparing Different Construction Delivery Methods - Aug 2014_r1
GENERIC - Comparing Different Construction Delivery Methods - Aug 2014_r1
 
Construction Projects Delivery Methods - Nilaksh Kothari, Manitowoc Public Ut...
Construction Projects Delivery Methods - Nilaksh Kothari, Manitowoc Public Ut...Construction Projects Delivery Methods - Nilaksh Kothari, Manitowoc Public Ut...
Construction Projects Delivery Methods - Nilaksh Kothari, Manitowoc Public Ut...
 
ملاحظات مهمة عن تعجيل المشاريع
ملاحظات مهمة عن تعجيل المشاريعملاحظات مهمة عن تعجيل المشاريع
ملاحظات مهمة عن تعجيل المشاريع
 
Final Presentation for Project A.D.I.O.S.
Final Presentation for Project A.D.I.O.S.Final Presentation for Project A.D.I.O.S.
Final Presentation for Project A.D.I.O.S.
 
Management, Cost, and Schedule Paper for Project A.D.I.O.S.
Management, Cost, and Schedule Paper for Project A.D.I.O.S.Management, Cost, and Schedule Paper for Project A.D.I.O.S.
Management, Cost, and Schedule Paper for Project A.D.I.O.S.
 
Management, Cost, and Schedule Presentation for Project A.D.I.O.S.
Management, Cost, and Schedule Presentation for Project A.D.I.O.S.Management, Cost, and Schedule Presentation for Project A.D.I.O.S.
Management, Cost, and Schedule Presentation for Project A.D.I.O.S.
 
Mesurement presentation pavaruban
Mesurement presentation pavarubanMesurement presentation pavaruban
Mesurement presentation pavaruban
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Total Cost Management - Synergy between Cost Estimating and Project Controls
Total Cost Management - Synergy between Cost Estimating and Project ControlsTotal Cost Management - Synergy between Cost Estimating and Project Controls
Total Cost Management - Synergy between Cost Estimating and Project Controls
 
PMBoK, discussion #5: Project Cost Management
PMBoK, discussion #5: Project Cost ManagementPMBoK, discussion #5: Project Cost Management
PMBoK, discussion #5: Project Cost Management
 
project cost management
project cost managementproject cost management
project cost management
 
Composite Crews in Construction Cost Estimating
Composite Crews in Construction Cost Estimating Composite Crews in Construction Cost Estimating
Composite Crews in Construction Cost Estimating
 

Similar to Qs Approach To Project Cost

EPC Services Capability Tra International limited
EPC Services Capability  Tra International limitedEPC Services Capability  Tra International limited
EPC Services Capability Tra International limitedHimanshu9974
 
Di Overview Who We Are What We Do 091011 Ds
Di Overview Who We Are What We Do 091011 DsDi Overview Who We Are What We Do 091011 Ds
Di Overview Who We Are What We Do 091011 Dsdsutton1570
 
Di overview who_we_are_what_we_do_091011-ds
Di overview who_we_are_what_we_do_091011-dsDi overview who_we_are_what_we_do_091011-ds
Di overview who_we_are_what_we_do_091011-dsdsutton1570
 
Au2010 Autodesk Deliberations11.28.10
Au2010 Autodesk Deliberations11.28.10Au2010 Autodesk Deliberations11.28.10
Au2010 Autodesk Deliberations11.28.10friscozephyr
 
Mega Project Management In The Oil & Gas Industry
Mega Project Management In The Oil & Gas IndustryMega Project Management In The Oil & Gas Industry
Mega Project Management In The Oil & Gas IndustryStephen_Forster
 
G2 It Services Overview 09.07.01
G2 It Services Overview 09.07.01G2 It Services Overview 09.07.01
G2 It Services Overview 09.07.01wdgleaton
 
Spp 201-pre-design services
Spp 201-pre-design servicesSpp 201-pre-design services
Spp 201-pre-design servicesMelvin Patawaran
 
Quest global overview
Quest global overviewQuest global overview
Quest global overviewQuEST Global
 
Skills Services Phoenix June2010
Skills Services Phoenix June2010Skills Services Phoenix June2010
Skills Services Phoenix June2010Mike Ryan
 
Bpr Process Modeling
Bpr Process ModelingBpr Process Modeling
Bpr Process Modelingrlynes
 
Hoffman.ed
Hoffman.edHoffman.ed
Hoffman.edNASAPMC
 
Vaibhav Misra Telecom Wireless Operations Management Consulting Presentation
Vaibhav Misra Telecom Wireless Operations Management Consulting PresentationVaibhav Misra Telecom Wireless Operations Management Consulting Presentation
Vaibhav Misra Telecom Wireless Operations Management Consulting PresentationVaibhav Misra
 
Strategy Recommendations: JOA Group - Project Managers to the SoCal Construct...
Strategy Recommendations: JOA Group - Project Managers to the SoCal Construct...Strategy Recommendations: JOA Group - Project Managers to the SoCal Construct...
Strategy Recommendations: JOA Group - Project Managers to the SoCal Construct...Alexandra Brooks
 
Competentia Presentation
Competentia PresentationCompetentia Presentation
Competentia Presentationkingk99
 
Improving safety, efficiency and regulatory compliance via asset documentatio...
Improving safety, efficiency and regulatory compliance via asset documentatio...Improving safety, efficiency and regulatory compliance via asset documentatio...
Improving safety, efficiency and regulatory compliance via asset documentatio...IBM Danmark
 

Similar to Qs Approach To Project Cost (20)

Prodapt Overview & Offering
Prodapt Overview & OfferingProdapt Overview & Offering
Prodapt Overview & Offering
 
EPC Services Capability Tra International limited
EPC Services Capability  Tra International limitedEPC Services Capability  Tra International limited
EPC Services Capability Tra International limited
 
Shivamtech brochure
Shivamtech brochureShivamtech brochure
Shivamtech brochure
 
Di Overview Who We Are What We Do 091011 Ds
Di Overview Who We Are What We Do 091011 DsDi Overview Who We Are What We Do 091011 Ds
Di Overview Who We Are What We Do 091011 Ds
 
Di overview who_we_are_what_we_do_091011-ds
Di overview who_we_are_what_we_do_091011-dsDi overview who_we_are_what_we_do_091011-ds
Di overview who_we_are_what_we_do_091011-ds
 
Au2010 Autodesk Deliberations11.28.10
Au2010 Autodesk Deliberations11.28.10Au2010 Autodesk Deliberations11.28.10
Au2010 Autodesk Deliberations11.28.10
 
Mega Project Management In The Oil & Gas Industry
Mega Project Management In The Oil & Gas IndustryMega Project Management In The Oil & Gas Industry
Mega Project Management In The Oil & Gas Industry
 
Sunget Precision Factory
Sunget Precision FactorySunget Precision Factory
Sunget Precision Factory
 
Sunget precision metal
Sunget precision metalSunget precision metal
Sunget precision metal
 
2013-02-21 Government Contractors Seminar
2013-02-21 Government Contractors Seminar2013-02-21 Government Contractors Seminar
2013-02-21 Government Contractors Seminar
 
G2 It Services Overview 09.07.01
G2 It Services Overview 09.07.01G2 It Services Overview 09.07.01
G2 It Services Overview 09.07.01
 
Spp 201-pre-design services
Spp 201-pre-design servicesSpp 201-pre-design services
Spp 201-pre-design services
 
Quest global overview
Quest global overviewQuest global overview
Quest global overview
 
Skills Services Phoenix June2010
Skills Services Phoenix June2010Skills Services Phoenix June2010
Skills Services Phoenix June2010
 
Bpr Process Modeling
Bpr Process ModelingBpr Process Modeling
Bpr Process Modeling
 
Hoffman.ed
Hoffman.edHoffman.ed
Hoffman.ed
 
Vaibhav Misra Telecom Wireless Operations Management Consulting Presentation
Vaibhav Misra Telecom Wireless Operations Management Consulting PresentationVaibhav Misra Telecom Wireless Operations Management Consulting Presentation
Vaibhav Misra Telecom Wireless Operations Management Consulting Presentation
 
Strategy Recommendations: JOA Group - Project Managers to the SoCal Construct...
Strategy Recommendations: JOA Group - Project Managers to the SoCal Construct...Strategy Recommendations: JOA Group - Project Managers to the SoCal Construct...
Strategy Recommendations: JOA Group - Project Managers to the SoCal Construct...
 
Competentia Presentation
Competentia PresentationCompetentia Presentation
Competentia Presentation
 
Improving safety, efficiency and regulatory compliance via asset documentatio...
Improving safety, efficiency and regulatory compliance via asset documentatio...Improving safety, efficiency and regulatory compliance via asset documentatio...
Improving safety, efficiency and regulatory compliance via asset documentatio...
 

Qs Approach To Project Cost

  • 1. Project and Cost Management A Quantity Surveying Approach Carin Rautenbach – Vice President John Merkler AIA – Executive Services Manager
  • 2. Introduction Atkinsorganization Atkins Transport Design & Engineering Management & Equity Solutions Project Services Investments Rail H&T Faithful & Management Investments/ Water & Metronet Environment Gould Consultancy (World) Engineering Asset Solutions Management Lambert Smith Design Solutions Hanscomb Project Hampton Faithful Development Design & Programme & Management Gould (USA)
  • 3. Introduction COMPANY HISTORY UNITED STATES WORDWIDE  Atkins est. in 1938  A global company . . .  Presence in more than 60 Locally based countries and 190 offices  Hanscomb est. in 1946 worldwide 26 offices - Major Cities in  Faithful&Gould est. in the USA  2,150 independent, 1947, acquired by Atkins professional consultants 1996  420 Independent, Worldwide professional consultants  Atkins HF&G merged in in the United States June 2002 Core business PROJECT and COST MANAGEMENT World’s leading cost consultant with over 55 years experience
  • 4. Ability to Influence Project Cost & Schedule
  • 5. What is Quantity Surveying? Quantity Surveying is in reality, a way of looking at a project through a Cost Management model that is quite specific
  • 6. Chain of Services Typical range of services Contract & Bid Analysis Work Scope & Award Planning Management Customer Products Pre-qualification Needs that meet & Inquiry Customers’ Management Needs
  • 7. Chain of Services Our range of services Program and Contract & Bid Analysis Change Feasibility Procurement Work Scope and Award and Trend Analysis Strategy Planning Management Management Customer’s Risk Engineering Pre-qualification Cost and Final Accounts Needs Management Management and Inquiry Project and Asset Management Management Listings
  • 8. Elements of Quantity Surveying • Alignment & Essentials of Cost Management • Understanding Costs • Standard Formats • Identifying Cost Drivers • How to Manage Costs – It all starts with a good budget – Integrated cost management approach – Careful use of historical information – Intelligent Value analysis/engineering – Sensitivity to life cycle costs & sustainability – Design/Pricing Contingency • Helpful Hints • Industry Trends • Recent Examples – UC Irvine; D/B Hospital
  • 9. Essentials of Cost Management Cost Management isAligning: • Scope - Measurable and quantifiable aspects of the facility • Expectations - Quality and performance expectations of the client • Budget - The cost of the facility and Maintaining Alignment over Time
  • 10. Alignment Scope Ongoing Effort Expectations Budget Projects need to start right to finish right
  • 11. Defining Scope, Expectations and Budget SCOPE EXPECTATIONS BUDGET Program Aesthetics Initial Costs - Functional Space Program - Form & Massing - Site Acquisition - Blocking &Stacking - Image - Fees - Public Space - Community Requirements - Construction - Efficiency - Design Issues - Inflation and Market Conditions - Contingencies Geometric Drivers Quality - Other Costs - Wall Area Ratio - Systems - Degree of Articulation - Materials FutureOne-Time Costs - Workmanship - Replacements Volume Drivers - Alterations - Clear Ceiling Height Project Delivery - Salvage - Plenum Height - Phasing & Scheduling - Other ne-Time Costs O - Interstitial Needs - Continued Occupancy - Atria - Delivery System Facility Annual Costs - Light Shelves - Operations Systems Performance - Maintenance Facility Parameters - Functional Space Elements - Financing - HVAC SF/Ton - Building Management - Taxes - Watts/SF - Maintainability - Insurance - Plumbing Fixtures - Energy Consumption - Security - Ductwork Poundage - Sustainability - Other Annual Costs - Steel Pounds/SF - Etc. Facility Performance Functional Use Costs - Live Loads - Staffing - Expandability - Materials - Flexibility - Denial of Use - Security & Safety - Other Functional Use Costs - Access & Egress - Adjacencies - Natural Light External Requirements - Codes - Standards & Criteria
  • 13. Definition of Cost Site Costs Hard Costs Soft Costs Land Building Interiors Development Costs  Design fees  Land Cost  Foundations  Tenant Work Commission &  Management fees  Structure  Artwork Fees TOTAL  Legal fees  Enclosure  Furniture, Fixtures  Title Insurance + + + = CAPITAL & Equipment  Taxes & Levies COSTS  Interior Finishes  Transfer Taxes  Telephone & Data  Insurance  Conveying  Surveys Communications  Owner’s  HVAC & System  Demolition administration Plumbing  Sitework  Leasing commissions  Electrical  Interim finance  Moving Costs
  • 14. Medical Center- Project Costs (Hard Cost)
  • 15. Breakdown of Construction Costs Total Hard Costs Prime Contractor / CM Mark-up General Conditions Sub-Contractor Mark-up General Conditions Materials Installation Purchase Cost Taxes Labor Equipment Premiums Operations Equipment Shipping & Fringes Cost Rental Handling Taxes / Insurance Base Wages
  • 17. Estimating Formats • Standardized Format – Consistency – Data Base – Checklist • Classifications – Masterformat – UNIFORMAT – Contract Packages – Activities – Plan /Program areas
  • 18. MasterFormat Divisions DIVISION 1 General Requirements 2 Sitework 3 Concrete 4 Masonry 5 Metals 6 Wood and Plastics 7 Thermal and Moisture Protection 8 Doors and Windows 9 Finishes 10 Specialties 11 Equipment 12 Furnishings 13 Special Construction 14 Conveying Systems 15 Mechanical 16 Electrical
  • 19. Example - Exterior Wall System Detail 03450 - Plant-Precast Architectural Concrete 04230 - Concrete Masonry Units 07210 - Building Insulation Three sections from three separate Divisions are required
  • 20. UNIFORMAT Elements • A10 Foundations • A20 Basement Construction • E10 Equipment • E20 Furnishings • B10 Superstructure • F10 Special Construction • B20 Exterior Closure • F20 Selective Building • B30 Roofing • G10 Site Preparation • C10 Interior Construction • G20 Site Improvements • C20 Staircases • G30 Site Mechanical Utilities • C30 Interior Finishes • D10 Conveying Systems • G40 Site Electrical Utilities • D20 Plumbing • G50 Other Site Construction • D30 HVAC • D40 Fire Protection • D50 Electrical
  • 21. Where the Dollar Goes UNIFORMAT II Apartment Office Element Building Building (level 2) 15 st – 15st – 140,000SF 162,000SF (shell & core) A.10 Foundations $ 0.98 $ 1.52 A.20 Basement Construction -- -- B.10 Superstructure 11.41 15.38 B.20 Exterior Closure 8.53 11.77 B.30 Roofing 0.24 0.35 C.10 Interior Construction 13.16 2.74 C.20 Staircases 1.15 1.54 C.30 Interior Finishes 9.74 9.35 D.10 Conveying 5.31 6.14 D.20 Plumbing 8.30 1.48 D.30 HVAC 9.63 11.82 D.40 Fire Protection 1.95 2.81 D.50 Electrical 6.23 8.80 F.10 Special Construction 1.33 -- Z. General Conditions 11.70 11.06 ( Sitework Excluded) $ 89.67/SF $ 84.76/SF
  • 22. UNIFORMAT II and MasterFormat Shell & Substructure 07 Thermal & moisture protect MASTERFORMAT Categories 13 Special construction 14 Conveying systems 01 General conditions 08 Doors & windows 06 Wood-plastic 12 Furnishings 15 Mechanical 10 Specialties 11 Equipment 02 Site work 16 Electrical 03 Concrete 04 Masonry 09 Finishes 05 Metals UNIFORMAT II Categories Level 1 Level 2 Level 3 A 10 Foundations A 1010 Standard Foundations SUBSTRUCTURE A 1020 Other Foundations A 1030 Slab on Grade A A 20 Basement Construction 2010 Basement Excavation A A 2020 Basement Walls B 10 Superstructure B 1010 Floor Construction B 1020 Roof Construction SHELL B 20 Exterior Enclosure B 2010 Exterior Walls B B 2020 Exterior Windows B 2030 Exterior Doors B 30 Roofing B 3010 Roof Coverings B 3020 Roof Openings
  • 26. Factors Driving Building Costs • Key Issues – The Pareto Principle – “The few affect the many” – Overlaps between disciplines – Timing and opportunity • Driving Factors – Geographical and Site – Design – Shape, size, height & efficiency – Qualitative – Legal and Administrative – Market and External Economic – Unknowns – Contingency, escalation & risk
  • 27. PARETO’S LAW OF DISTRIBUTION 100 90 PERCENTAGE OF COST 80 70 60 Best Value Focus 50 40 30 20 10 0 0 20 40 60 80 100 PERCENTAGE Of TOTAL FACILITY COMPONENTS
  • 28. Focus on Interdisciplinary Areas Electrical Civil & structural Architectural Mechanical Owner’s requirements
  • 29. Relationship of Time and Change Ability to Cost of High make changes making changes Degree of Change Best Opportunity for Improvement Low Planning Design Construction Time
  • 30. Building Efficiency Example GFA Cost per SF Net Rentable Net Rentable Floor Area Ratio Floor Area Office Building A140,000 sf 85.00 80% 112,000 sf Office Building B140,000 sf 85.00 85% 119,000 sf What is the cost per SF of rentable area? A = $106.25 B = $100.00
  • 31. Relationship Between Quality & Cost HIGH Bankrupt Zone TOTAL LIFE CYCLE COST COST QUALITY LIMITS FUTURE COSTS MAX INITIAL COSTS MIN LOW VC Tile Zone LOW MIN MAX HIGH QUALITY
  • 32. Effect of Competition on Prices 1.25 1.15 Bid 1.05 Factor 0.95 0.85 0 2 4 6 8 10 12 14 16 18 20 Number of Bids Source: Area Cost Factor Study, U.S. Army Corps of Engineers
  • 33. Market Conditions Comparison Between Bid Results and Fair Market Value Predatory Range +/- 40 10-20% above or 30 below FMV 20 10 Reasonable Supply & 0 Demand Range +/- 7% -10 -20 -30 1982 1983 1984 1985 1986 1987 1988 1989 1990 1991 1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 YEAR
  • 34. Contingencies and Escalation • Contingencies are real costs - just not identified…. yet • Contingency is risk dependent • Contingency is dependent on development of design • Where possible allocate contingency where costs will occur • Clarify contingency/allowance for changes with all parties • Be sure that the owner is carrying a project contingency • Escalation will happen - Plan for it • Be careful that multiple contractors are not overlapping
  • 35. Design/Pricing Contingency Why do we need a design/pricing contingency? • At early stages (schematics), many decisions have yet to be made • Specification yet to be defined • Building code changes/interpretations • Consultants who come in later (MEP) tend to add requirement. • Owners requirements may change/develop. • Market conditions – shortage of competition. • Existing buildings – examination and testing incomplete. • Definition of bid packaging/phasing. • Front end requirements ( liquidated damages).
  • 36. How to Manage Costs • It all starts with a good budget • Integrated cost management approach • Careful use of historical information • Intelligent Value analysis/engineering • Sensitivity to life cycle costs & sustainability
  • 37. It All Starts with a Good Budget •A Good Budget Should: • Reflect scope • Reflect quality/performance expectations • Reflect owners value objectives • Be achievable and accepted • Be defensible • Contain “bridge” to ongoing cost control • Be based on techniques and data available • Contain adequate reserves •Avoid • Socially acceptable budgets • Playing it safe
  • 38. Facility Cost Plan Summary Project Description: Federal Level Office Building Bid Date: 12/02 Project Type: Office Construction time(Months): 36 Gross Building Area:(GSF) 425,000 Market Conditions: good UNIFORMAT TOTAL COST PER % OF ELEMENTAL ANALYSIS UNIFORMAT SYSTEM / ELEMENT DESCRIPTION BUILDING: REFERENCE COST b GSF b / GSF BUILDING b / 27 MEASURE UNIT VALUE c COST/UNIT b/c Cost per 1 2 Foundations Standard Foundations (A10) (A1010) 3,824,493 75,507 9.00 0.18 5.5% 0.1% Ground Floor Area SF Ground Floor Area SF 108,975 108,975 35.10 0.69 UNIFORMAT Gross Area 3 4 Other Foundations Slab on Grade (A1020) (A1030) 2,144,701 1,604,285 5.05 3.77 3.1% 2.3% Ground Floor Area SF Ground Floor Area SF 108,975 108,975 19.68 14.72 Cost per 5 Basement Construction (A20) - - 0.0% Ground Floor Area SF 108,975 - 6 Substructure - Sub-Total (A) 3,824,493 9.00 5.5% Ground Floor Area SF 108,975 35.10 System Unit 7 Superstructure (B10) 9,664,210 22.74 13.9% Gross Bldg. Area EA 425,000 22.74 8 Exterior Enclosure (B20) 17,374,453 40.88 25.0% Gross Enclosure Area EA 188,000 92.42 9 Roofing (B30) 1,058,767 2.49 1.5% Roof Surface Area SF 138,059 7.67 10 Shell - Sub-Total (B) 28,097,431 66.11 40.5% Gross Bldg. Area SF 425,000 66.11 11 Interior Construction (C10) 3,665,491 8.62 5.3% Gross Bldg. Area SF 425,000 8.62 12 Stairs (C20) 320,250 0.75 0.5% Gross Bldg. Area SF 425,000 0.75 13 Interior Finishes (C30) 4,197,176 9.88 6.0% Gross Bldg. Area SF 425,000 9.88 14 Interiors - Sub-Total (C) 8,182,917 19.25 11.8% Gross Bldg. Area SF 425,000 19.25 15 Conveying Systems (D10) 1,445,000 3.40 2.1% Total No. of Stops EA 48 30,104 16 Plumbing (D20) 1,481,286 3.49 2.1% No. of Fixtures EA - - 17 HVAC (D30) 9,876,438 23.24 14.2% Tons (or MBH) EA 2,100 4,703 18 Fire Protection (D40) 989,900 2.33 1.4% Protected Area SF 425,000 2.33 19 Electrical (D50) 9,890,639 23.27 14.3% Gross Bldg. Area SF 425,000 23.27 20 Electrical Service & Distribution (D5010) 2,949,820 6.94 4.3% Connected KW KW 8,000 369 21 Lighting & Branch Wiring (D5020) 3,857,838 9.08 5.6% Gross Bldg. Area SF 425,000 9.08 22 Communications & Security (D5030) 2,171,737 5.11 3.1% Gross Bldg. Area SF 425,000 5.11 23 Other Electrical Systems (D5040) 911,244 2.14 1.3% Gross Bldg. Area SF 425,000 2.14 24 Services - Sub-Total (D) 23,683,263 55.73 34.1% Gross Bldg. Area SF 425,000 55.73 25 Equip. & Furnishings - Sub-Total (E) 1,667,099 3.92 2.4% Gross Bldg. Area SF 425,000 3.92 26 Spec. Construct. & Demo - Sub-Total (F) 3,932,792 9.25 5.7% Gross Bldg. Area SF 425,000 9.25 27 TOTAL BUILDING $ 69,387,994 $ 163.27 100.0% Occupants EA 1,800 $ 38,549 28 SITEWORK & UTILITIES: 29 Site Preparation (G10) 2,105,133 4.95 3.0% Gross Site Area SF 522,720 4.03 30 Site Improvements (G20) 3,812,500 8.97 5.5% Gross Site Area SF 522,720 7.29 31 Site Mechanical Utilities (G30) 473,000 1.11 0.7% Gross Site Area SF 522,720 0.90 32 Site Electrical Utilities (G40) 539,635 1.27 0.8% Gross Site Area SF 522,720 1.03 33 Other Site Construction (G50) 4,714,207 11.09 6.8% Gross Site Area SF 522,720 9.02 34 TOTAL SITEWORK & UTILITIES: (G) 11,644,476 27.40 16.8% Gross Site Area SF 522,720 22.28 35 General Conditions, Overhead & Profit @ 16.3% 13,232,602 31.14 19.1% 36 TOTAL FACILITY COST - CURRENT $ 94,265,072 $ 221.80 135.9% Occupants EA 1,800 $ 52,369 37 Contingencies (Pricing, Phasing, Constr.) 18.0% 16,933,778 39.84 24.4% 38 Escalation 10.3% 11,447,176 26.93 14.0% Key 39 40 TOTAL FACILITY COST - PROJECTED $ 122,646,026 $ 288.58 174.2% Occupants EA 1,800 $ 68,137 Parameter Key Parameters: 1 Gross Bldg. Area Measure SF Value 425,000 Area Analysis: Area (SF) Tracking 2 Ground Floor Area 3 Gross Enclosure Area SF SF 108,975 188,000 Basement Ground Floor 108,975 4 Percent Fenestration % 36% Upper Floors 312,025 5 Roof Surface Area SF 138,059 Penthouses 4,000 6 Total No.of Conveying Stops STOPS 48 Other Areas - 7 Tons Cooling (or MBH Htg) TONS 2,100 8 No. of Plumbing Fixtures EA Gross Floor Area 425,000 9 Fire Protected Area SF 425,000 10 Connected KW KW 8,000 11 Occupants EA 1,800 12 Floor to Floor Height (Avg.) LF 13
  • 39. Integrated Cost Management Process Cost Plan Revised Cost Plan Revised Cost Plan by Discipline by Discipline by Discipline Architectural Architectural Architectural Market Market Cost Parameter Assessment, Cost Parameter Assessment, Cost Parameter Targets Targets Contingencies & Risks Targets Targets Contingencies & Risks Targets Targets Structural Structural Structural Constructibility, Historical Cost Parameter Massing, Quality & Historical Historical Cost Parameter Phasing & Quality & Benchmarks Cost Parameter Targets Targets Aesthetics & Performance Benchmarks Targets Targets Targets Targets Scope Expectations Benchmarks Scheduling Performance Image Mechanical Mechanical Mechanical Cost Parameter Cost Parameter Cost Parameter Targets Targets Targets Targets Targets Targets Cost Milestone Revised Milestone Revised Ongoing Advice Analysis& Cost Model Electrical Ongoing Advice Cost CostModel Electrical Cost CostModel Electrical Alignment Estimate Estimate Cost Parameter Cost Parameter Cost Parameter Targets Targets Targets Targets Targets Targets Equipment/Special Equipment/Special Equipment/Special Criteria & Site & Phasing & Life Cycle Materials & Life Cycle Standards Configuration Cost Parameter Schedule Performance & Cost Parameter Systems Performance & Cost Parameter Targets Targets Sustainability Targets Targets Sustainability Targets Targets Site Site Site Cost Parameter Cost Parameter Cost Parameter Alternates Targets Targets Concepts Systems Targets Targets Targets Targets Value Value Value Planning Engineering Engineering Delivery System Components Approaches Alternates Project History Concept Development & Schematic Design Development & Construction Planning and Programming Design Documents
  • 40. Summary of Estimating Methods (1) Single Unit Rate (2) Parametric/Cost Modeling (3) System Elemental Cost Analysis (4) Quantity Survey Application of Cost Estimating Techniques Pre-Design Schematic Design Development Construction Documents Pre-Bid SUR Parametric System Quantity Survey
  • 41. Cost Management Tracking Example PROJECT COST COMPARISON SUMMARY PROJECT: MODERNIZATION OF USCS/ICC/CW BUILDINGS COMPLEX PROJECT NO: IDC28143/IDC28144/IDC28145 SHEET NO: 1A of 3 LOCATION: WASHINGTON, D.C. COST MANAGER: HANSCOMB INC. A/E ESTIMATE Original PDS Adjusted PDS Concept Concept Tentative (Rev.)Tentative (Rev.) 5% 7 Construction Cost (ECCA) Option "A" Option "A" Pre-VE After VE Pre VE After VE Intermediate Final (Level 2) Date: Jan.1992 Date: 12/6/94 Date: 07/10/95 Date: 10/10/95 Date: 11/14/95 Date: 11/28/95 Date: 12/18/95 Date:5/9/96 01 FOUNDATIONS $0 $0 $0 $0 $0 $0 $0 02 SUBSTRUCTURE $5,000 $0 $0 $0 $0 $0 $0 03 SUPERSTRUCTURE $385,000 $310,105 $307,585 $844,847 $844,847 $1,349,596 $1,585,575 04 EXTERIOR CLOSURE $3,029,927 $4,715,882 $4,610,867 $6,680,867 $6,974,868 $5,618,130 $6,105,491 05 ROOFING $2,937,360 $4,330,642 $4,330,642 $3,530,665 $3,530,665 $1,748,414 $1,654,206 06 INTERIOR CONSTRUCTION $36,603,983 $18,051,709 $15,079,374 $21,301,147 $21,103,312 $24,972,056 $27,880,252 07 CONVEYING SYSTEMS $2,097,500 $1,389,000 $1,321,791 $1,708,610 $1,708,610 $1,773,203 $1,862,732 08 MECHANICAL $27,926,204 $28,706,881 $27,213,152 $21,973,075 $21,994,952 $24,526,254 $23,523,509 09 ELECTRICAL $17,566,534 $24,187,059 $22,691,650 $21,106,943 $21,606,943 $20,298,145 $21,178,345 10 GENERAL CONDITIONS AND PROFIT $15,591,418 $15,321,706 $14,225,258 $15,986,755 $16,016,755 $15,802,655 $17,077,336 11 EQUIPMENT $548,800 $814,013 $814,013 $995,113 $995,113 $1,496,265 $1,434,306 12 SITEWORK $6,042,481 $13,255,375 $12,182,236 $15,279,927 $16,142,148 $8,281,772 $8,114,647 SUBTOTAL $112,734,207 $111,082,372 $102,776,568 $109,407,949 $110,918,213 $105,866,490 $110,416,399 DESIGN CONTINGENCY Incl. in 01-12 $11,108,237 $10,277,657 $10,940,795 $11,091,821 $7,939,987 $0 SUBTOTAL $112,734,207 $122,190,609 $113,054,225 $120,348,744 $122,010,034 $113,806,477 $110,416,399 ESCALATION : $26,632,920 $10,031,849 $9,281,752 TO START OF CC# 1 - 9/96 $206,739 $206,739 $180,888 $105,399 TO START OF CC# 2 - 2/97 $2,080,767 $2,561,242 $1,779,027 $1,020,008 TO START OF CC# 3 - 12/97 $4,459,648 $5,489,433 $3,860,835 $2,749,961 SUBTOTAL (ECCA) - CC # 1, 2 and 3 $139,367,127 $130,588,000 $132,222,458 $122,335,977 $127,095,898 $130,267,448 $119,627,227 $114,291,767 (including reimbursable items) CONSTRUCTION CONTINGENCY @ 7% $6,799,995 $9,141,000 $9,255,572 $8,563,518 $8,896,713 $9,118,721 $8,373,906 $8,000,424 ESTIMATED CONSTRUCTION COST (ECC) $146,167,122 $139,729,000 $141,478,030 $130,899,495 $135,992,611 $139,386,170 $128,001,133 $122,292,191 Cost per SM $1,253.16 $1,159.46 $1,204.57 $1,234.63 $1,133.79 $1,083.22 Gross Floor Area (M2) 112,897 112,897 112,897 112,897 112,897 112,897 CONSTRUCTION CONTRACT No. 1 (ECC) $7,907,207 $7,955,000 $9,362,167 $9,362,167 $10,119,187 $7,890,514 CONSTRUCTION CONTRACT No. 2 (ECC) $53,613,049 $55,208,000 $50,209,613 $51,295,552 $47,334,557 $51,156,045 CONSTRUCTION CONTRACT No. 3 (ECC) + SITE $84,646,866 $76,566,000 $76,420,830 $78,728,451 $70,547,388 $63,245,632
  • 42. Historical Cost Model Database BUILDING COST SUMMARY - ALL PROJECTS (Adjusted to April 2001) Project Description: Elementary Schools Bid Date 11/96 8/95 10/93 1/97 9/94 Adjusted Adjusted Project Type: School Constr Time 14 15 14 14 16 Average Average Market good good excellent good good of All of All UNIFORMAT Example 1 Adjusted Example 2 Adjusted Example 3 Adjusted Example 4 Adjusted Example 5 Adjusted SYSTEM / ELEMENT DESCRIPTION REFERENCE TOTAL COST $/sf by: TOTAL COST $/sf by: TOTAL COST $/sf by: TOTAL COST $/sf by: TOTAL COST $/sf by: ($/SF) ($/Parameter) BUILDING: b 1.14 b 1.18 b 1.32 b 1.13 b 1.21 1 Foundations (A10) 506,192 7.47 485,255 6.83 397,823 7.80 561,768 8.13 385,840 7.01 7.45 Ground Floor Area 74,780 SF 7.45 2 Standard Foundations (A1010) 302,142 4.46 277,228 3.90 219,741 4.31 348,071 5.04 230,305 4.18 4.38 Ground Floor Area 74,780 SF 4.38 3 Other Foundations (A1020) - - - - - - - - - - - Ground Floor Area 74,780 SF - 4 Slab on Grade (A1030) 204,050 3.01 208,027 2.93 178,081 3.49 213,698 3.09 155,535 2.82 3.07 Ground Floor Area 74,780 SF 3.07 5 Basement Construction (A20) - - - - - - - - - - - Ground Floor Area 74,780 SF - 6 Substructure - Sub-Total (A) 506,192 7.47 485,255 6.83 397,823 7.80 561,768 8.13 385,840 7.01 7.45 Ground Floor Area 74,780 SF 7.45 7 Superstructure (B10) 400,900 5.92 408,714 5.75 291,566 5.72 461,841 6.69 305,582 5.55 5.92 Gross Bldg. Area 74,780 SF 5.92 8 Exterior Enclosure (B20) 537,917 7.94 504,529 7.10 391,216 7.67 563,351 8.16 360,819 6.55 7.48 Gross Enclosure Area 30,646 SF 18.25 9 Roofing (B30) 273,275 4.03 278,601 3.92 198,747 3.90 329,125 4.77 208,301 3.78 4.08 Roof Surface Area 77,492 SF 3.94 10 Shell - Sub-Total (B) 1,212,092 17.89 1,191,845 16.78 881,529 17.28 1,354,317 19.61 874,703 15.88 17.49 Gross Bldg. Area 74,780 SF 17.49 11 Interior Construction (C10) 560,523 8.27 571,448 8.04 346,508 6.79 587,025 8.50 405,890 7.37 7.80 Gross Bldg. Area 74,780 SF 7.80 12 Stairs (C20) - - - - - - - - - - - Gross Bldg. Area 74,780 SF - 13 Interior Finishes (C30) 394,833 5.83 483,034 6.80 258,438 5.07 413,501 5.99 361,149 6.56 6.05 Gross Bldg. Area 74,780 SF 6.05 14 Interiors - Sub-Total (C) 955,356 14.10 1,054,482 14.84 604,946 11.86 1,000,526 14.49 767,040 13.93 13.84 Gross Bldg. Area 74,780 SF 13.84 15 Conveying Systems (D10) 7,288 0.11 7,430 0.10 5,300 0.10 7,633 0.11 5,555 0.10 0.11 Total No. of Stops 1 EA 7,901 16 Plumbing (D20) 447,800 6.61 456,528 6.43 325,675 6.38 468,973 6.79 341,331 6.20 6.48 No. of Fixtures 144 EA 3,365 17 HVAC (D30) 1,049,400 15.49 1,283,824 18.07 763,206 14.96 1,099,017 15.91 799,895 14.53 15.79 Tons (or MBH) 208 EA 5,689 18 Fire Protection (D40) 151,800 2.24 154,759 2.18 110,401 2.16 158,977 2.30 115,708 2.10 2.20 Protected Area 74,780 SF 2.20 19 Electrical (D50) 859,866 12.69 859,866 12.10 859,866 16.86 859,866 12.45 859,866 15.62 13.94 Gross Bldg. Area 74,780 SF 13.94 20 Electrical Service & Distribution (D5010) 182,120 2.69 185,670 2.61 132,452 2.60 190,731 2.76 138,819 2.52 2.64 Connected KW 660 KW 299 21 Lighting & Branch Wiring (D5020) 286,132 4.22 291,709 4.11 208,098 4.08 344,610 4.99 218,101 3.96 4.27 Gross Bldg. Area 74,780 SF 4.27 22 Communications & Security (D5030) 205,778 3.04 209,789 2.95 149,658 2.93 269,384 3.90 156,852 2.85 3.13 Gross Bldg. Area 74,780 SF 3.13 23 Other Electrical Systems (D5040) 185,836 2.74 189,458 2.67 135,155 2.65 194,623 2.82 141,652 2.57 2.69 Gross Bldg. Area 74,780 SF 2.69 24 Services - Sub-Total (D) 2,516,154 37.14 2,762,407 38.89 2,064,449 40.47 2,594,466 37.57 2,122,355 38.54 38.52 Gross Bldg. Area 74,780 SF 38.52 25 Equip. & Furnishings - Sub-Total (E) 211,210 3.12 215,327 3.03 153,609 3.01 221,196 3.20 193,191 3.51 3.17 Gross Bldg. Area 74,780 SF 3.17 26 Spec. Construct. & Demo - Sub-Total (F) 28,500 0.42 29,055 0.41 20,727 0.41 29,848 0.43 21,724 0.39 0.41 Gross Bldg. Area 74,780 SF 0.41 27 TOTAL BUILDING $ 5,429,504 80.14 $ 5,738,371 80.78 $ 4,123,083 80.83 $ 5,762,121 83.44 $ 4,364,853 79.27 80.89 Accomodation Units 700 EA $ 8,675 28 SITEWORK & UTILITIES: - - - - - - - 29 Site Preparation (G10) 467,598 6.90 657,181 9.25 375,979 7.37 482,827 6.99 527,489 9.58 8.02 Gross Site Area 620,000 SF 0.96 30 Site Improvements (G20) 85,122 1.26 99,695 1.40 88,977 1.74 87,894 1.27 71,129 1.29 1.39 Gross Site Area 620,000 SF 0.17 31 Site Mechanical Utilities (G30) 301,500 4.45 353,117 4.97 242,426 4.75 311,319 4.51 214,147 3.89 4.51 Gross Site Area 620,000 SF 0.55 32 Site Electrical Utilities (G40) - - - - - - - - - - - Gross Site Area 620,000 SF - 33 Other Site Construction (G50) - - - - - - - - - - - Gross Site Area 620,000 SF - 34 TOTAL SITEWORK & UTILITIES: (G) 854,220 12.61 1,109,993 15.63 707,382 13.87 882,041 12.77 812,765 14.76 13.93 Gross Site Area 620,000 SF 1.68 35 General Conditions, Overhead & Profit @ 5.1% 322,647 4.76 351,639 4.95 248,027 4.86 341,154 4.94 265,852 4.83 4.87 - 36 TOTAL FACILITY COST - CURRENT $ 6,606,371 97.51 $ 7,200,003 101.36 $ 5,078,492 99.56 $ 6,985,316 101.15 $ 5,443,470 98.86 99.69 Accomodation Units 700 EA $ 10,692 37 Contingency @ - - - - - - - - - - - - 38 Escalation @ - - - - - - - - - - - - 39 - - - - - - - 40 TOTAL FACILITY COST - PROJECTED $ 6,606,371 97.51 $ 7,200,003 101.36 $ 5,078,492 99.56 $ 6,985,316 101.15 $ 5,443,470 98.86 99.69 Accomodation Units 700 EA $ 10,692 41 TOTAL FACILITY COST/SF - PROJECTED $ 85.57 97.51 $ 85.71 101.36 $ 75.24 99.56 $ 89.21 101.15 $ 81.37 98.86 99.69 - Parameters: Measure Value Value Value Value Value Value 1 Gross Bldg. Area SF 77,200 84,000 67,500 78,300 66,900 74,780 2 Ground Floor Area SF 77,200 84,000 67,500 78,300 66,900 74,780 3 Gross Enclosure Area SF 31,000 33,731 28,000 32,500 28,000 30,646 4 Percent Fenestration % 12% 12% 15% 12% 15% 13% 5 Roof Surface Area SF 80,000 87,047 69,948 81,140 69,326 77,492 6 Total No.of Conveying Stops STOPS 1 1 1 1 1 1 7 Tons Cooling (or MBH Htg) TONS 200 240 200 200 200 208 8 No. of PlumbingFixtures EA 150 160 130 150 130 144 9 Fire Protected Area SF 77,200 84,000 67,500 78,300 66,900 74,780 10 Connected KW KW 650 750 600 700 600 660 11 Accomodation Units EA 750 800 600 750 600 700 12 Floor to Floor Height (Avg.) LF 12 12 12 12 12 12 13 Gross Site Area SF 600,000 750,000 580,000 600,000 570,000 620,000 14 Gross Bldg. Area per Accomod Unit SF/EA 103 105 113 104 112 107
  • 43. Hospital Cost Model Based on Historical Data from Other Hospitals • Compare/benchmark other hospitals • Adjust for OSHPD V non-OSHPD criteria • Adjust for location • Adjust for central plant V no central plant • Adjust for size factor • Adjust for phasing/links • Adjust for time/escalation • Adjust for unique costs • Adjust for shelled space • Adjust for medical equipment with hard cost
  • 44. Sensitivity to Life Cycle Impact Transportation Construction 18% 2% Other Support Costs 5% 1% School Allotment 1% Textbooks Furnishings / Fitout 4% Benefits / Overhead Fees 1% 14% Other Project Costs 1% ConstructionContingency 1% Major Capital Replacements 5% Maintenance 3% Support Staffing 11% Energy 2% Educational Staffing 31%
  • 45. Life Cycle Costing Example Life Cycle Cost Analysis Alternative 1 Alternative 2 Alternative 3 Alternative 4 General Purpose Worksheet Individual Rooftop Central Plant with Units 4 - Pipe Fan Coil Units Study Title: HVAC System Analysis Estimated Present Estimated Present Estimated Present Estimated Present Discount Rate : 8% Date: 12/17/97 Costs Worth Costs Worth Costs Worth Costs Worth Life Cycle (Yrs.) 30 Initial/Collateral Costs INITIAL / COLLATERAL COSTS A. Equipment 1,212,354 1,212,354 2,803,000 2,803,000 B. Screening 55,501 55,501 40,000 40,000 C. Plant Space 128,000 128,000 D. E. F. G. Total Initial/Collateral Costs $1,267,855 $1,267,855 $2,971,000 $2,971,000 Difference ($1,703,145) Replacement/Salvage PW REPLACEMENT / SALVAGE (Single Expenditures) Year Facto r A. Rooftop Units (70%) 8 0.540 770,000 416,007 B. Rooftop Units (70%) 16 0.292 770,000 224,756 COSTS C. Rooftop Units (70%) 24 0.158 770,000 121,428 D. Fan Coils(100%) 15 0.315 408,888 128,899 E. Central Plant Equipment 20 0.215 600,000 128,729 F. G. Total Replacement/Salvage Costs $762,191 $257,627 Annual Costs Differential PW Escal. Rate Facto r ANNUAL COSTS A. Maintenance - Rooftops 1% 12.496 75,360 941,693 B. Maintenance - Fan Coils 1% 12.496 37,680 470,847 C. Maintenance - Central Plant & Distrib. 1% 12.496 28,800 359,883 D. Energy 3% 15.631 468,000 7,315,296 192,000 3,001,147 E. F. G. Total Annual Costs $543,360 $8,256,989 $258,480 $3,831,876 Total Life Cycle Costs (Present Worth) $10,287,035 $7,060,504 LIFE CYCLE COSTS Life Cycle Cost PW Difference $3,226,531 Discounted Payback (Alt. 2,3,4 vs. Alt. 1) 3.9 Total Life Cycle Costs - Annualized Per Year: $913,771 Per Year: $627,166 Per Year: Per Year:
  • 46. LEED Checklist Excerpted from LEED Green Building Rating System™
  • 47. Industry Trends • Variety of delivery systems • New risk sharing approaches • Increasing interest in sustainability/green • Increase in security measures • Protectionist legislation to protect certain industries (steel, concrete, lumber) • Demand for speed • Outsourcing of management skills • Local Factors
  • 48. Industry Trends (cont.) • Sector Corrections – • Volume up Medical, schools, housing • Volume down Office, hi-tech, most other sectors • Materials/Union Wages • Union wage rates are increasing 3-4% per annum. • Materials are pretty erratic with some exceptions. • Awareness of bidding climate
  • 49. Helpful Cost Management Hints • The budget must be aligned • Apportion budgets by discipline …and manage them • Manage scope • Manage quality and performance • Define and adhere to key parameter measures • “Buy in” to all estimates – share responsibility • If necessary, get a second opinion • Use value engineering/value analysis • Be willing to learn lessons and share results
  • 50. Understanding Costs UC Irvine Replacement Hospital Project – Recent Example
  • 51. UCI Replacement Hospital Change Order Review scope - ”…manage what?”
  • 52. UCI Replacement Hospital • Design/Build Hospital project – Estimating & D/B oversight initial charge • Charge from Campus for Cost Management – Real time review – but comprehensive – Transparent process – OSHPD aware – Organize Project Managers – Integrate “field” & design • Importance to Campus – Audit trail – Simple organization - One source of information – Understanding of “where the money went”
  • 53. UCI Replacement Hospital • How UCI chose to Manage Cost – Replacement Hospital – I/M system integration – “Prolog” based • HP Database + UCI Database = Collaboration – PM meetings – monthly scope/OSHPD/field review – Integrating “all” contracts – D/B + others + UCI provided material – Reporting - integrated – Document Control – RFI/Bulletin/Ltr of Instruction/CO’s
  • 54. Alignment Scope Ongoing Effort Expectations Budget Projects need to start right to finish right
  • 55. Project and Cost Management A Quantity Surveying Approach Carin Rautenbach – Vice President John Merkler AIA – Executive Services Manager
  • 56. Market Inflation Indices (Based on a 100 Value in 1977) 300.00 CPI Basic Means Index 250.00 200.00 150.00 100.00 50.00 1980 1988 1998 1977 1978 1979 1981 1982 1983 1984 1985 1986 1987 1989 1990 1991 1992 1993 1994 1995 1996 1997 1999 -
  • 57. Index History (Yearly Percent Change) 16.00% 14.00% 12.00% 10.00% GDP CPI Basic Means Index 8.00% 6.00% 4.00% 3% 2.00% 0.00% -2.00% Recession Recession -4.00% 1978 1980 1981 1982 1983 1984 1985 1986 1987 1988 1989 1990 1991 1992 1993 1994 1995 1996 1997 1998 1979 1999
  • 58. Integrated Cost Management Process - Planning & Programming Cost Plan by Discipline Architectural Cost Parameter Targets Targets Structural Cost Parameter Historical Targets Targets Scope Expectations Benchmarks Mechanical Cost Parameter Targets Targets Cost Analysis & Cost Model Electrical Alignment Cost Parameter Targets Targets Equipment/Special Criteria & Site & Standards Configuration Cost Parameter Targets Targets Site Cost Parameter Alternates Targets Targets Value Planning Delivery Approaches Planning and Programming
  • 59. Facility Value Target 01 Foundations 02 Substructure 03 Superstructure Sensible Trade-Offs 04 Exterior Closures 05 Roofing 06 Interior Construction 07 Conveying 08 Mechanical 09 Electrical 10 General Conditions 11 Sitework
  • 61. Traditional Design-Bid-Build Delivery Fundamental Approach • Prime contracts directly with owner • A/E selected by qualifications or qualifications/price. • A/E prepares design to 100%. • Open bidding to general contractors (may be prequalified). • Awarded of contract to lowest responsive bidder
  • 63. Construction Manager at Risk Delivery Approach • CM (at risk) has direct contract with owner, as does A/E. • A/E selected by qualifications or qualifications/price. • CM (at risk) selected on qualifications or qualifications and fee for general conditions and profit. • CM (at risk) responsible for work scheduling and means/methods.
  • 64. Construction Manager at Risk Delivery Variations • CM (PM) can be retained in an agency relationship to coordinate process. • GMP can be followed with CM (at risk) open bidding to subcontractors.  Final price can “float” up to GMP.  Or “shared savings” up to GMP with owner.  Or a firm fixed price can be negotiated.
  • 65. Design – Build Delivery
  • 66. Advantage and Disadvantages of Delivery Systems Traditional Design-Bid Build ISSUES ADVANTAGES DISADVANTAGES Cost and Budget “Best price” potential. Cost not finalized until Management Perception of “best price”. bids. Cost overruns after bid require expensive redesign. Bidders may seek to “get low” by omitting work not clearly shown. Schedule Impact Delivery schedule Construction difficult to and Management stipulated in start contract. before design is finished. Extended/compressed schedules may add cost
  • 67. Advantage and Disadvantages of Delivery Systems Construction Manager at Risk ISSUES ADVANTAGES DISADVANTAGES Cost and Budget Cost “guarantee” prior to After GMP, costs may Management design completion. increase Improved perception of due to detailing not control. correctly Cost saving incentives are • reflected in the GMP. feasible. CM may “expand” budget to create opportunity for future savings”. Schedule Impact Construction can start Schedule changes during and Management before construction difficult to design is complete. implement. Cost of impact of extended/compressed
  • 68. Advantage and Disadvantages of Delivery Systems Design-Build ISSUES ADVANTAGES DISADVANTAGES Cost and Budget Early cost guarantee. Fair price competition difficult Management Price tends to match to quality. verify. Can obtain best price for Cost impact of risk issues performance. may not be evident in initial pricing. Owner overemphasis on price as a selection criterion may force the design-builder to compromise quality to reduce price. Schedule Impact Construction can start Schedule changes at any and Management after point
  • 69. Price Index / Cost Index