SlideShare a Scribd company logo
Management, Cost, and
Schedule
Team 3
DIOS - Deimos Impact & Observation Spacecraft
Jeff Anderson, Thomas Blachman, Andrew Fallon, John Franklin, Samuel Gaultney,
David Habashy, Brian Hardie, Brandon Hing, Zujia Huang, Sung Kim, Jonathan Saenger
2
Mission Concept
Mission Goal: Direct an impactor into Deimos at high velocities to launch a plume of
surface and subsurface debris into space. The plume will be analyzed by an infrared
spectrometer to determine the composition Deimos. This will determine whether
Deimos is a C or D type asteroid, or Mars ejecta. In addition, prebiotic volatile
concentrations will be analyzed to determine asteroid contributions to early life.
Mission Objectives:
- The impactor shall collide with Deimos’ surface and generate a plume sufficient enough in size for
the CubeSat Spectrometer to detect
- The impactor shall penetrate Deimos’ surface deep enough to expose volatile compounds including
oxygen, carbon dioxide, carbon monoxide, water, and ammonia
- The CubeSat shall analyze the plume with a spectrometer and determine the 1.3 µm absorption
levels, as well as the absorption levels of volatiles
3
Key Requirements
The two major design goals of the spacecraft are to generate a plume of Deimos subsurface
material, and to relay the composition of the material to Earth. The driving requirements serve to fulfill
these two goals either directly or secondarily.
1. Shall be ready for launch by July 20th 2020
2. Shall arrive at Deimos between February 19th 2021 and February 20th 2021
3. Shall not exceed 5.6 million dollars in total cost
4. Shall have an acceptable amount of risk.
4
DIOS Work Breakdown Structure Cost Element
6
Total Cost Profile
7
Cost Estimation Methodology
8
Cost Estimation Methodology for DSN
9
Project
Life Cycle
10
System Schedule, Critical Path, Schedule Margin
Pre-Phase A: 1/1/17 - 3/1/17 (2 months)
Phase A: 3/2/17 - 7/31/17 (5 months)
Phase B: 8/1/17 - 4/1/18 (8 months)
Phase C: 4/1/18 - 7/20/19 (15 months)
Phase D: 7/21/19 - 7/13/20 (12 months)
Phase E: 7/14/20 - 3/31/21 (9 months)
Phase F: 4/1/21 - 5/2/21 (1 month)
Total: 52 months
Margin: 8 months
11
Project Implementation Flowchart
15
Flight Schedule
Significant events during flight
Days Elapsed since Separation Seconds
Separation
Date
ΔVi ΔVc + ΔVo Impact Flyby
Observe
Time
21-Jul 2020 4 208.22667 210.80 210.85 248.72
22-Jul 2020 4 207.22667 209.81 209.86 260.54
23-Jul 2020 4 206.22667 208.82 208.86 257.12
24-Jul 2020 4 205.22667 207.83 207.87 255.70
16
Project Risk Areas and Mitigations
17
Risk Assessment
Likelihood
Consequence
1. Propulsion isn’t ready in time of launch
○ If so, we will have to find a new propulsion
system.
2. Production schedule surpasses time allotted until
launch
○ We have margins built into our production
schedule to account for more.
3. Components don’t meet testing standards
○ The schedule margin accounts for fixing
4. Costs are higher than expected
○ Total mission cost with contingency is still the
total allocated budget
1
2
6
4 3
5
Descopes
Reduce the amount of quality testing
Reduces build time but increases risks
Reduce the amount of employees
Reduces salary costs but increases build time
Reduce the amount of trips to conferences and design
review trips
Reduces costs but reduces centainity of design.
18

More Related Content

Viewers also liked

Final Presentation for Project A.D.I.O.S.
Final Presentation for Project A.D.I.O.S.Final Presentation for Project A.D.I.O.S.
Final Presentation for Project A.D.I.O.S.
Sung (Stephen) Kim
 
PMP Exam Preparation Course: 06 Project Cost Management
PMP Exam Preparation Course: 06 Project Cost ManagementPMP Exam Preparation Course: 06 Project Cost Management
PMP Exam Preparation Course: 06 Project Cost Management
B M Shahrier Majumder, PMP, CSM
 
Lecture 06 project_cost_management
Lecture 06 project_cost_managementLecture 06 project_cost_management
Lecture 06 project_cost_management
Sayed Ahmed
 
Cleopatra Enterprise Added Value
Cleopatra Enterprise Added ValueCleopatra Enterprise Added Value
Cleopatra Enterprise Added ValueLeendertdegeus
 
Spatio temporal modeling of snow flake crystals using packardªs cellular auto...
Spatio temporal modeling of snow flake crystals using packardªs cellular auto...Spatio temporal modeling of snow flake crystals using packardªs cellular auto...
Spatio temporal modeling of snow flake crystals using packardªs cellular auto...
eSAT Journals
 
Kozma Szilárd asztrológus: A Lilith inverzió és a keresztény asztrológia V.
Kozma Szilárd asztrológus: A Lilith inverzió és a keresztény asztrológia V.Kozma Szilárd asztrológus: A Lilith inverzió és a keresztény asztrológia V.
Kozma Szilárd asztrológus: A Lilith inverzió és a keresztény asztrológia V.
Szilárd Kozma
 
Copywriter's Workshop Certificate
Copywriter's Workshop CertificateCopywriter's Workshop Certificate
Copywriter's Workshop CertificateBridget Eng
 
As parábolas de jesus com joachim jeremias
As parábolas de jesus com joachim jeremiasAs parábolas de jesus com joachim jeremias
As parábolas de jesus com joachim jeremias
Wenderson Bernardo Faustino
 
PMP Training Project Cost Management Part 1
PMP Training Project Cost Management Part 1PMP Training Project Cost Management Part 1
PMP Training Project Cost Management Part 1
Skillogic Solutions
 
Maral
MaralMaral
03 2016 inail rischio chimico laboratori
03   2016  inail rischio chimico laboratori03   2016  inail rischio chimico laboratori
03 2016 inail rischio chimico laboratori
http://www.studioingvolpi.it
 
Jimmy delgado saia reingenieria
Jimmy delgado saia reingenieriaJimmy delgado saia reingenieria
Jimmy delgado saia reingenieria
Jimmy Delgado Vargas
 
ملاحظات مهمة عن تعجيل المشاريع
ملاحظات مهمة عن تعجيل المشاريعملاحظات مهمة عن تعجيل المشاريع
ملاحظات مهمة عن تعجيل المشاريع
Dr. Mahmoud Al-Naimi
 
Серводвигатели серии SQ Sicme motori
Серводвигатели серии SQ Sicme motoriСерводвигатели серии SQ Sicme motori
Серводвигатели серии SQ Sicme motori
Arve
 
Management, Cost, and Schedule Paper for Project A.D.I.O.S.
Management, Cost, and Schedule Paper for Project A.D.I.O.S.Management, Cost, and Schedule Paper for Project A.D.I.O.S.
Management, Cost, and Schedule Paper for Project A.D.I.O.S.
Sung (Stephen) Kim
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost ManagementSerdar Temiz
 
Total Cost Management - Synergy between Cost Estimating and Project Controls
Total Cost Management - Synergy between Cost Estimating and Project ControlsTotal Cost Management - Synergy between Cost Estimating and Project Controls
Total Cost Management - Synergy between Cost Estimating and Project Controls
Martin van Vliet
 
Qs Approach To Project Cost
Qs Approach To Project CostQs Approach To Project Cost
Qs Approach To Project Cost
Johannes J Merkler AIA
 
PMBoK, discussion #5: Project Cost Management
PMBoK, discussion #5: Project Cost ManagementPMBoK, discussion #5: Project Cost Management
PMBoK, discussion #5: Project Cost ManagementOleksandr Lutsaievskyi
 

Viewers also liked (20)

Final Presentation for Project A.D.I.O.S.
Final Presentation for Project A.D.I.O.S.Final Presentation for Project A.D.I.O.S.
Final Presentation for Project A.D.I.O.S.
 
PMP Exam Preparation Course: 06 Project Cost Management
PMP Exam Preparation Course: 06 Project Cost ManagementPMP Exam Preparation Course: 06 Project Cost Management
PMP Exam Preparation Course: 06 Project Cost Management
 
Lecture 06 project_cost_management
Lecture 06 project_cost_managementLecture 06 project_cost_management
Lecture 06 project_cost_management
 
Cleopatra Enterprise Added Value
Cleopatra Enterprise Added ValueCleopatra Enterprise Added Value
Cleopatra Enterprise Added Value
 
skydrive_word_doc
skydrive_word_docskydrive_word_doc
skydrive_word_doc
 
Spatio temporal modeling of snow flake crystals using packardªs cellular auto...
Spatio temporal modeling of snow flake crystals using packardªs cellular auto...Spatio temporal modeling of snow flake crystals using packardªs cellular auto...
Spatio temporal modeling of snow flake crystals using packardªs cellular auto...
 
Kozma Szilárd asztrológus: A Lilith inverzió és a keresztény asztrológia V.
Kozma Szilárd asztrológus: A Lilith inverzió és a keresztény asztrológia V.Kozma Szilárd asztrológus: A Lilith inverzió és a keresztény asztrológia V.
Kozma Szilárd asztrológus: A Lilith inverzió és a keresztény asztrológia V.
 
Copywriter's Workshop Certificate
Copywriter's Workshop CertificateCopywriter's Workshop Certificate
Copywriter's Workshop Certificate
 
As parábolas de jesus com joachim jeremias
As parábolas de jesus com joachim jeremiasAs parábolas de jesus com joachim jeremias
As parábolas de jesus com joachim jeremias
 
PMP Training Project Cost Management Part 1
PMP Training Project Cost Management Part 1PMP Training Project Cost Management Part 1
PMP Training Project Cost Management Part 1
 
Maral
MaralMaral
Maral
 
03 2016 inail rischio chimico laboratori
03   2016  inail rischio chimico laboratori03   2016  inail rischio chimico laboratori
03 2016 inail rischio chimico laboratori
 
Jimmy delgado saia reingenieria
Jimmy delgado saia reingenieriaJimmy delgado saia reingenieria
Jimmy delgado saia reingenieria
 
ملاحظات مهمة عن تعجيل المشاريع
ملاحظات مهمة عن تعجيل المشاريعملاحظات مهمة عن تعجيل المشاريع
ملاحظات مهمة عن تعجيل المشاريع
 
Серводвигатели серии SQ Sicme motori
Серводвигатели серии SQ Sicme motoriСерводвигатели серии SQ Sicme motori
Серводвигатели серии SQ Sicme motori
 
Management, Cost, and Schedule Paper for Project A.D.I.O.S.
Management, Cost, and Schedule Paper for Project A.D.I.O.S.Management, Cost, and Schedule Paper for Project A.D.I.O.S.
Management, Cost, and Schedule Paper for Project A.D.I.O.S.
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Total Cost Management - Synergy between Cost Estimating and Project Controls
Total Cost Management - Synergy between Cost Estimating and Project ControlsTotal Cost Management - Synergy between Cost Estimating and Project Controls
Total Cost Management - Synergy between Cost Estimating and Project Controls
 
Qs Approach To Project Cost
Qs Approach To Project CostQs Approach To Project Cost
Qs Approach To Project Cost
 
PMBoK, discussion #5: Project Cost Management
PMBoK, discussion #5: Project Cost ManagementPMBoK, discussion #5: Project Cost Management
PMBoK, discussion #5: Project Cost Management
 

Similar to Management, Cost, and Schedule Presentation for Project A.D.I.O.S.

Final Paper for Project A.D.I.O.S.
Final Paper for Project A.D.I.O.S.Final Paper for Project A.D.I.O.S.
Final Paper for Project A.D.I.O.S.
Sung (Stephen) Kim
 
Risk management paper
Risk management paperRisk management paper
Risk management paper
PMlynda17
 
C0.5: CEOS and Oceans - Chu Ishida, Alex Held
C0.5: CEOS and Oceans - Chu Ishida, Alex HeldC0.5: CEOS and Oceans - Chu Ishida, Alex Held
C0.5: CEOS and Oceans - Chu Ishida, Alex Held
Blue Planet Symposium
 
geo7_crafting_geoinformation
geo7_crafting_geoinformationgeo7_crafting_geoinformation
geo7_crafting_geoinformationMichael Williams
 
Inter fellous freilich
Inter fellous freilichInter fellous freilich
Inter fellous freilichNASAPMC
 
Inter fellous freilich
Inter fellous freilichInter fellous freilich
Inter fellous freilichNASAPMC
 
Risk management case study
Risk management case studyRisk management case study
Risk management case study
Eng.Ahmed Said Mohamed Refaei
 
Market Briefing. Japan part 2. 28th January
Market Briefing. Japan part 2. 28th JanuaryMarket Briefing. Japan part 2. 28th January
Market Briefing. Japan part 2. 28th JanuaryUKTI2014
 
KGrothe Capstone Project Final Presentation
KGrothe Capstone Project Final PresentationKGrothe Capstone Project Final Presentation
KGrothe Capstone Project Final PresentationKaren Grothe
 
Meterological Technology International, Nov 2010
Meterological Technology International, Nov 2010Meterological Technology International, Nov 2010
Meterological Technology International, Nov 2010
laurajairam
 
Algae blooms tracker
Algae blooms trackerAlgae blooms tracker
Algae blooms tracker
omarshehab9
 
WE2.L10 - NASA's Evolving Approaches to Maximizing Applications Return from o...
WE2.L10 - NASA's Evolving Approaches to Maximizing Applications Return from o...WE2.L10 - NASA's Evolving Approaches to Maximizing Applications Return from o...
WE2.L10 - NASA's Evolving Approaches to Maximizing Applications Return from o...grssieee
 
PHY 103 Final Project Guidelines and RubricOverviewThe final .docx
PHY 103 Final Project Guidelines and RubricOverviewThe final .docxPHY 103 Final Project Guidelines and RubricOverviewThe final .docx
PHY 103 Final Project Guidelines and RubricOverviewThe final .docx
mattjtoni51554
 
Mercator Ocean newsletter 24
Mercator Ocean newsletter 24Mercator Ocean newsletter 24
Mercator Ocean newsletter 24
Mercator Ocean International
 
Aben, Ilse: Using satellite observations to detect and quantify concentrated ...
Aben, Ilse: Using satellite observations to detect and quantify concentrated ...Aben, Ilse: Using satellite observations to detect and quantify concentrated ...
Aben, Ilse: Using satellite observations to detect and quantify concentrated ...
Integrated Carbon Observation System (ICOS)
 
NorthDakotaSYSTEMS
NorthDakotaSYSTEMSNorthDakotaSYSTEMS
NorthDakotaSYSTEMSAustin Cote
 
Mercator Ocean newsletter 31
Mercator Ocean newsletter 31Mercator Ocean newsletter 31
Mercator Ocean newsletter 31
Mercator Ocean International
 
Final Mission Proposal
Final Mission ProposalFinal Mission Proposal
Final Mission ProposalDaniel Hill
 
Internship
InternshipInternship
InternshipIsa Ma
 

Similar to Management, Cost, and Schedule Presentation for Project A.D.I.O.S. (20)

Final Paper for Project A.D.I.O.S.
Final Paper for Project A.D.I.O.S.Final Paper for Project A.D.I.O.S.
Final Paper for Project A.D.I.O.S.
 
Risk management paper
Risk management paperRisk management paper
Risk management paper
 
C0.5: CEOS and Oceans - Chu Ishida, Alex Held
C0.5: CEOS and Oceans - Chu Ishida, Alex HeldC0.5: CEOS and Oceans - Chu Ishida, Alex Held
C0.5: CEOS and Oceans - Chu Ishida, Alex Held
 
geo7_crafting_geoinformation
geo7_crafting_geoinformationgeo7_crafting_geoinformation
geo7_crafting_geoinformation
 
Inter fellous freilich
Inter fellous freilichInter fellous freilich
Inter fellous freilich
 
Inter fellous freilich
Inter fellous freilichInter fellous freilich
Inter fellous freilich
 
Risk management case study
Risk management case studyRisk management case study
Risk management case study
 
Market Briefing. Japan part 2. 28th January
Market Briefing. Japan part 2. 28th JanuaryMarket Briefing. Japan part 2. 28th January
Market Briefing. Japan part 2. 28th January
 
Ianson
IansonIanson
Ianson
 
KGrothe Capstone Project Final Presentation
KGrothe Capstone Project Final PresentationKGrothe Capstone Project Final Presentation
KGrothe Capstone Project Final Presentation
 
Meterological Technology International, Nov 2010
Meterological Technology International, Nov 2010Meterological Technology International, Nov 2010
Meterological Technology International, Nov 2010
 
Algae blooms tracker
Algae blooms trackerAlgae blooms tracker
Algae blooms tracker
 
WE2.L10 - NASA's Evolving Approaches to Maximizing Applications Return from o...
WE2.L10 - NASA's Evolving Approaches to Maximizing Applications Return from o...WE2.L10 - NASA's Evolving Approaches to Maximizing Applications Return from o...
WE2.L10 - NASA's Evolving Approaches to Maximizing Applications Return from o...
 
PHY 103 Final Project Guidelines and RubricOverviewThe final .docx
PHY 103 Final Project Guidelines and RubricOverviewThe final .docxPHY 103 Final Project Guidelines and RubricOverviewThe final .docx
PHY 103 Final Project Guidelines and RubricOverviewThe final .docx
 
Mercator Ocean newsletter 24
Mercator Ocean newsletter 24Mercator Ocean newsletter 24
Mercator Ocean newsletter 24
 
Aben, Ilse: Using satellite observations to detect and quantify concentrated ...
Aben, Ilse: Using satellite observations to detect and quantify concentrated ...Aben, Ilse: Using satellite observations to detect and quantify concentrated ...
Aben, Ilse: Using satellite observations to detect and quantify concentrated ...
 
NorthDakotaSYSTEMS
NorthDakotaSYSTEMSNorthDakotaSYSTEMS
NorthDakotaSYSTEMS
 
Mercator Ocean newsletter 31
Mercator Ocean newsletter 31Mercator Ocean newsletter 31
Mercator Ocean newsletter 31
 
Final Mission Proposal
Final Mission ProposalFinal Mission Proposal
Final Mission Proposal
 
Internship
InternshipInternship
Internship
 

More from Sung (Stephen) Kim

Project A.R.E.S. Outreach Program Presentation: Frederick Douglass High School
Project A.R.E.S. Outreach Program Presentation: Frederick Douglass High SchoolProject A.R.E.S. Outreach Program Presentation: Frederick Douglass High School
Project A.R.E.S. Outreach Program Presentation: Frederick Douglass High School
Sung (Stephen) Kim
 
Critical Design Review Paper for Project A.R.E.S.
Critical Design Review Paper for Project A.R.E.S.Critical Design Review Paper for Project A.R.E.S.
Critical Design Review Paper for Project A.R.E.S.
Sung (Stephen) Kim
 
Initial Proposal for Project A.R.E.S.
Initial Proposal for Project A.R.E.S.Initial Proposal for Project A.R.E.S.
Initial Proposal for Project A.R.E.S.
Sung (Stephen) Kim
 
Flight Readiness Review Presentation for Project A.R.E.S.
Flight Readiness Review Presentation for Project A.R.E.S.Flight Readiness Review Presentation for Project A.R.E.S.
Flight Readiness Review Presentation for Project A.R.E.S.
Sung (Stephen) Kim
 
Critical Design Review Presentation for Project A.R.E.S.
Critical Design Review Presentation for Project A.R.E.S.Critical Design Review Presentation for Project A.R.E.S.
Critical Design Review Presentation for Project A.R.E.S.
Sung (Stephen) Kim
 
Flight Readiness Review for Project A.R.E.S.
Flight Readiness Review for Project A.R.E.S.Flight Readiness Review for Project A.R.E.S.
Flight Readiness Review for Project A.R.E.S.
Sung (Stephen) Kim
 
Final Paper Avalanche Risk Assessment
Final Paper Avalanche Risk AssessmentFinal Paper Avalanche Risk Assessment
Final Paper Avalanche Risk Assessment
Sung (Stephen) Kim
 
Avalanche Risk Assessment Final Presentation
Avalanche Risk Assessment Final PresentationAvalanche Risk Assessment Final Presentation
Avalanche Risk Assessment Final Presentation
Sung (Stephen) Kim
 
NASA Tech Integration Georgia Tech Grand Challenge
NASA Tech Integration Georgia Tech Grand ChallengeNASA Tech Integration Georgia Tech Grand Challenge
NASA Tech Integration Georgia Tech Grand Challenge
Sung (Stephen) Kim
 
Mission Concept Presentation for Project A.D.I.O.S.
Mission Concept Presentation for Project A.D.I.O.S.Mission Concept Presentation for Project A.D.I.O.S.
Mission Concept Presentation for Project A.D.I.O.S.
Sung (Stephen) Kim
 
Payloads Presentation for Project A.D.I.O.S.
Payloads Presentation for Project A.D.I.O.S.Payloads Presentation for Project A.D.I.O.S.
Payloads Presentation for Project A.D.I.O.S.
Sung (Stephen) Kim
 
Mission Concept Paper for Project A.D.I.O.S.
Mission Concept Paper for Project A.D.I.O.S.Mission Concept Paper for Project A.D.I.O.S.
Mission Concept Paper for Project A.D.I.O.S.
Sung (Stephen) Kim
 

More from Sung (Stephen) Kim (12)

Project A.R.E.S. Outreach Program Presentation: Frederick Douglass High School
Project A.R.E.S. Outreach Program Presentation: Frederick Douglass High SchoolProject A.R.E.S. Outreach Program Presentation: Frederick Douglass High School
Project A.R.E.S. Outreach Program Presentation: Frederick Douglass High School
 
Critical Design Review Paper for Project A.R.E.S.
Critical Design Review Paper for Project A.R.E.S.Critical Design Review Paper for Project A.R.E.S.
Critical Design Review Paper for Project A.R.E.S.
 
Initial Proposal for Project A.R.E.S.
Initial Proposal for Project A.R.E.S.Initial Proposal for Project A.R.E.S.
Initial Proposal for Project A.R.E.S.
 
Flight Readiness Review Presentation for Project A.R.E.S.
Flight Readiness Review Presentation for Project A.R.E.S.Flight Readiness Review Presentation for Project A.R.E.S.
Flight Readiness Review Presentation for Project A.R.E.S.
 
Critical Design Review Presentation for Project A.R.E.S.
Critical Design Review Presentation for Project A.R.E.S.Critical Design Review Presentation for Project A.R.E.S.
Critical Design Review Presentation for Project A.R.E.S.
 
Flight Readiness Review for Project A.R.E.S.
Flight Readiness Review for Project A.R.E.S.Flight Readiness Review for Project A.R.E.S.
Flight Readiness Review for Project A.R.E.S.
 
Final Paper Avalanche Risk Assessment
Final Paper Avalanche Risk AssessmentFinal Paper Avalanche Risk Assessment
Final Paper Avalanche Risk Assessment
 
Avalanche Risk Assessment Final Presentation
Avalanche Risk Assessment Final PresentationAvalanche Risk Assessment Final Presentation
Avalanche Risk Assessment Final Presentation
 
NASA Tech Integration Georgia Tech Grand Challenge
NASA Tech Integration Georgia Tech Grand ChallengeNASA Tech Integration Georgia Tech Grand Challenge
NASA Tech Integration Georgia Tech Grand Challenge
 
Mission Concept Presentation for Project A.D.I.O.S.
Mission Concept Presentation for Project A.D.I.O.S.Mission Concept Presentation for Project A.D.I.O.S.
Mission Concept Presentation for Project A.D.I.O.S.
 
Payloads Presentation for Project A.D.I.O.S.
Payloads Presentation for Project A.D.I.O.S.Payloads Presentation for Project A.D.I.O.S.
Payloads Presentation for Project A.D.I.O.S.
 
Mission Concept Paper for Project A.D.I.O.S.
Mission Concept Paper for Project A.D.I.O.S.Mission Concept Paper for Project A.D.I.O.S.
Mission Concept Paper for Project A.D.I.O.S.
 

Recently uploaded

Basic Industrial Engineering terms for apparel
Basic Industrial Engineering terms for apparelBasic Industrial Engineering terms for apparel
Basic Industrial Engineering terms for apparel
top1002
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
ClaraZara1
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
aqil azizi
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
SyedAbiiAzazi1
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
ChristineTorrepenida1
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
BrazilAccount1
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
Vijay Dialani, PhD
 

Recently uploaded (20)

Basic Industrial Engineering terms for apparel
Basic Industrial Engineering terms for apparelBasic Industrial Engineering terms for apparel
Basic Industrial Engineering terms for apparel
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
 

Management, Cost, and Schedule Presentation for Project A.D.I.O.S.

  • 1. Management, Cost, and Schedule Team 3 DIOS - Deimos Impact & Observation Spacecraft Jeff Anderson, Thomas Blachman, Andrew Fallon, John Franklin, Samuel Gaultney, David Habashy, Brian Hardie, Brandon Hing, Zujia Huang, Sung Kim, Jonathan Saenger
  • 2. 2
  • 3. Mission Concept Mission Goal: Direct an impactor into Deimos at high velocities to launch a plume of surface and subsurface debris into space. The plume will be analyzed by an infrared spectrometer to determine the composition Deimos. This will determine whether Deimos is a C or D type asteroid, or Mars ejecta. In addition, prebiotic volatile concentrations will be analyzed to determine asteroid contributions to early life. Mission Objectives: - The impactor shall collide with Deimos’ surface and generate a plume sufficient enough in size for the CubeSat Spectrometer to detect - The impactor shall penetrate Deimos’ surface deep enough to expose volatile compounds including oxygen, carbon dioxide, carbon monoxide, water, and ammonia - The CubeSat shall analyze the plume with a spectrometer and determine the 1.3 µm absorption levels, as well as the absorption levels of volatiles 3
  • 4. Key Requirements The two major design goals of the spacecraft are to generate a plume of Deimos subsurface material, and to relay the composition of the material to Earth. The driving requirements serve to fulfill these two goals either directly or secondarily. 1. Shall be ready for launch by July 20th 2020 2. Shall arrive at Deimos between February 19th 2021 and February 20th 2021 3. Shall not exceed 5.6 million dollars in total cost 4. Shall have an acceptable amount of risk. 4
  • 5.
  • 6. DIOS Work Breakdown Structure Cost Element 6
  • 11. System Schedule, Critical Path, Schedule Margin Pre-Phase A: 1/1/17 - 3/1/17 (2 months) Phase A: 3/2/17 - 7/31/17 (5 months) Phase B: 8/1/17 - 4/1/18 (8 months) Phase C: 4/1/18 - 7/20/19 (15 months) Phase D: 7/21/19 - 7/13/20 (12 months) Phase E: 7/14/20 - 3/31/21 (9 months) Phase F: 4/1/21 - 5/2/21 (1 month) Total: 52 months Margin: 8 months 11
  • 12.
  • 13.
  • 14.
  • 16. Flight Schedule Significant events during flight Days Elapsed since Separation Seconds Separation Date ΔVi ΔVc + ΔVo Impact Flyby Observe Time 21-Jul 2020 4 208.22667 210.80 210.85 248.72 22-Jul 2020 4 207.22667 209.81 209.86 260.54 23-Jul 2020 4 206.22667 208.82 208.86 257.12 24-Jul 2020 4 205.22667 207.83 207.87 255.70 16
  • 17. Project Risk Areas and Mitigations 17 Risk Assessment Likelihood Consequence 1. Propulsion isn’t ready in time of launch ○ If so, we will have to find a new propulsion system. 2. Production schedule surpasses time allotted until launch ○ We have margins built into our production schedule to account for more. 3. Components don’t meet testing standards ○ The schedule margin accounts for fixing 4. Costs are higher than expected ○ Total mission cost with contingency is still the total allocated budget 1 2 6 4 3 5
  • 18. Descopes Reduce the amount of quality testing Reduces build time but increases risks Reduce the amount of employees Reduces salary costs but increases build time Reduce the amount of trips to conferences and design review trips Reduces costs but reduces centainity of design. 18

Editor's Notes

  1. Franklin
  2. Franklin
  3. franklin