SlideShare a Scribd company logo
SLIP FORM CONSTRUCTION
PRESENTED BY
AGLAIA
SLIP- FORM
Slip forming, continuous poured, continuously formed, or slip form construction is a
construction method in which concrete is poured into a continuously moving form.
 Slip forming is used for tall structures (such as bridges, towers, buildings, and dams), as well as
horizontal structures, such as roadways.
 Slip forming enables continuous, non-interrupted, cast-in-place "flawless" (i.e. no joints) concrete
structures which have superior performance characteristics to piecewise construction using discrete
form elements.
SLIP FORM
Slip forming relies on the quick-setting properties of concrete, and requires a balance between
quick-setting capacity and workability.
Concrete needs to be workable enough to be placed into the form and consolidated (via
vibration), yet quick-setting enough to emerge from the form with strength.
 This strength is needed because the freshly set concrete must not only permit the form to "slip"
by the concrete without disturbing it, but also support the pressure of the new concrete as well as
resist collapse caused by the vibration of the compaction machinery.
SLIP FORM
COMPONENTS OF SLIP-FORM
The slip form system is designed with varied features.
 Generally, it consist of yoke legs. Yoke legs are employed to lift and sustain the weight of the entire structure, so that
it behaves as a single unit. Yoke legs are also used to connect with the beams, scaffoldings and working platforms to
serve the supporting purpose.
To the yoke legs, walk-away brackets are connected. These walkway brackets will enable proper placement of the
concrete.
 The whole slip form assembly is lifted by means of strand rods and lifting jacks.
 These primary components are located at equal intervals so that the uniform and good distribution of weight is
performed.
 In some construction, lifting process are supported by means of hydraulic pump components.
SLIP FORM
SLIP FORM
PROCEDURE
Assembly can only start once the foundations are in place and the wall starter is in correct alignment.
Slip form shuttering is aligned with the help of yokes.Horizontal crossbeams connect these yokes.
Hydraulic jacks are attached to these crossbeams for simultaneous upward movement.
Height of the slip form ranges from 1.1 to 1.5 meters.
Yokes and crossbeams also used to support the working platform.
Structure should be rigid and shape maintained at all times. Make sure there is no lag or else it prevents
the structure from free upward movement.
 It is also possible to reduce wall thicknesses as the construction gains height and arrangements have to
be made in the slip form structure that will enable such reduction at regular intervals.
SLIP FORM
TYPES OF SLIP-FORM CONSTRUCTION
VERTICAL SLIP-FORM
HORIZONTAL SLIP-FORM
TAPERED SLIP-FORM
SLIP FORM
VERTICAL SLIP-FORM
In vertical slip forming, the concrete form may be surrounded by a platform on which workers
stand, placing steel reinforcing rods into the concrete and ensuring a smooth pour.
Together, the concrete form and working platform are raised by means of hydraulic jacks.
The slip-form rises at a rate which permits the concrete to harden by the time it emerges from
the bottom of the form.
SLIP FORM
SLIP FORM
HORIZONTAL SLIP FORM
In horizontal slip forming for pavement and traffic separation walls, concrete is cast, vibrated,
worked, and settled in place while the form itself slowly moves ahead.
This method was initially devised and utilized in Interstate Highway construction initiated during
the 1950s.
SLIP FORM
SLIP FORM
TAPERED SLIP-FORMING
Slip-forming is also used in the construction of conical chimneys, cooling towers, piers and
other tall concrete structures involving constant or changing thicknesses in walls, diameters
and/or shapes.
A form is used with sections which overlap so that one gradually slides over the other.
This is commonly done in chimney construction but it is not satisfactory for architectural
concrete because the lap shows.
While the tapered slip-forming process is similar to that used on the standard slip-forming,
it requires greater attention, contractor experience and expertise ensures the success of
such projects.
SLIP FORM
Slipform Construction of Collie Power Station, Western AustraliaSLIP FORM
Continuous slip formed gravity-based structure supports under construction in a Norwegian fjord. The visible jib
cranes would each be delivering buckets of concrete to the support cylinders during the continuous pour of
concrete creating seamless walls. SLIP FORM
FEATURES OF SLIPFORM CONSTRUCTION TECHNIQUE
The slip form construction technique is a rapid and a economic construction method compared to the
conventional formwork technique. This helps to achieve huge cost saving.
The technique is best suitable for large building structures and bridges. When small structures are
concerned, the projects with identical geometry can be easily completed by slip form construction.
Continuous movement of formwork in upward direction is performed in slip form technique. The
movement is facilitated by hydraulic jacks and jack rods.
 In the construction of vertical structures, the rate of rising the formwork upwards will be almost in the
rate of 300mm per hour. These rise with the help of the supports from other permanent parts of the
building.
The technique of slip form construction will vary based on the type of structure constructed. Based on
this the frameworks required to support the system will vary.
SLIP FORM
ADVANTAGES
 Height
This technology becomes very competitive starting at about 60 ft of height and continues to improve with
increasing height thereafter.
 Early Assembly
The slip form setup is very compact and can be pre-assembled ahead of time. Once the foundation is
ready, the slip form can quickly be placed on the foundation and construction can start almost immediately.
 Speed of Construction
Speeds of between 7 ft and 30 ft per 24 hours are possible. Many times, this speed allows reuse of
formwork on repetitive elements without impacting the overall schedule, thus reducing your total formwork
cost.
SLIP FORM
 No Form Ties
No ties are required because the limited concrete pressure is taken by the slipform yoke directly. Without
ties, there are also no form holes to fill, which reduces labor costs, improves appearance and makes for a
water-tight structure. This is particularly important for offshore structures such as gravity oil and gas
platforms.
 No Rebar Bolsters
Unlike in standard wall construction with panel forms, slip forming does not require lost rebar bolsters in
every pour to control the rebar cover. In slip form construction, sliding guides are mounted on top of the
slip form. These guides push the rebar into position and accurately control the rebar cover as the slip form
moves upwards.
SLIP FORM
 Safety
The slip form setup provides a safe and protected work environment for your crew. Relatively little
climbing is required, the work area is compact and unchanging and weather protection can easily be
added to the formwork setup. Enclosed spaces can be heated during the cold weather periods.
 Flexibility
A slip form is of low overall height and very compact. That makes it is easier to handle and modify for
changing concrete cross-sections. Also, the extension past the hardened concrete line is very short,
so very little wind force has to be considered in the formwork design.
SLIP FORM
 Easy To Stop
The slip form operation can be stopped and resumed at will, to suit the contractor’s schedule. Slip
form operations can be suspended for the weekend or during parts of the day as dictated by
external factors. This is done by climbing another 18 in. or so after the last concrete has been
poured. This gives the concrete time to set and helps to break the form adhesion to the fresh
concrete.
 Standard Concrete Mix
No special concrete is needed for a typical slip form project. For certain offshore structures,
advanced concrete mixes have been developed to improve the performance of the structure in the
ocean environment. However, these types of structures are rare and the vast majority of buildings
and towers can be slip formed with ordinary concrete mixes.
SLIP FORM
 Continuous Process
Slip forming is a continuous extrusion process. There is no need to set and strip forms every few
feet. You do not need to tie up a crane as for handling conventional formwork.
 Quality Finish
Slip forming provides a superior concrete finish with no form fins to clean up and without horizontal
joints. A sponge finish and other surface treatments are easy to apply from the second work
platform suspended from the slip form assembly
SLIP FORM
DISADVANTAGES
High –cost for initial setup.
Requires Specialized workers and expertise.
Need sophisticated Equipment.
Dimensional Accuracy can go low in certain conditions.
SLIP FORM
APPLICATIONS OF SLIP-FORM CONSTRUCTION
Slip-form construction is used for tall structures, such as towers, buildings, and dams, as
well as horizontal structures, such as roadway barriers.
 It enables continuous, non-interrupted, cast-in- place joint-less concrete structures which
have superior performance characteristics over construction methods using discrete form
elements.
Slip forming relies on the quick setting properties of concrete, and requires a balance
between quick-setting capacity and workability. Capital Gate Tower, Abu Dhabi King Abdul-
Aziz Airport Inn Canal, Germany
SLIP FORM
THANK YOU!!For more…. Mail to aglaiaconnect2018@gmail.com
SLIP FORM

More Related Content

What's hot

JUMP FORM WORK
JUMP FORM WORKJUMP FORM WORK
JUMP FORM WORK
Pranay Kumar Tode
 
Formwork
FormworkFormwork
Formwork
natesh0142
 
Precast construction
Precast constructionPrecast construction
Precast construction
Divya Vishnoi
 
Slip formwork for chimney
Slip formwork for chimneySlip formwork for chimney
Slip formwork for chimney
Axay Sharma
 
Formwork Presentation for Construction Technology
Formwork Presentation for Construction TechnologyFormwork Presentation for Construction Technology
Formwork Presentation for Construction Technology
I'mMiss Lily
 
Underpinning
UnderpinningUnderpinning
Underpinning
YingHongKang
 
Shoring
ShoringShoring
Slabs and types
Slabs and typesSlabs and types
Slabs and types
Surhan Fatima
 
presentation on slip formwork
presentation on slip formworkpresentation on slip formwork
presentation on slip formwork
nemilgandhi
 
Prefabrication construction
Prefabrication constructionPrefabrication construction
Prefabrication construction
Divya Vishnoi
 
Construction of diaphragm wall
Construction of diaphragm wallConstruction of diaphragm wall
Construction of diaphragm wall
Ghanashyam Prajapati
 
PRECAST BUILDING SYSTEM
PRECAST BUILDING SYSTEMPRECAST BUILDING SYSTEM
PRECAST BUILDING SYSTEMSagar Shah
 
Superstructure construction
Superstructure constructionSuperstructure construction
Superstructure construction
mohdasrimohdhasim
 
Prefabrication​ structure ppt
Prefabrication​ structure pptPrefabrication​ structure ppt
Prefabrication​ structure ppt
AbhishekM45
 
Steel formwork
Steel formworkSteel formwork
Steel formwork
Musahiddin Md Zainal
 
Prefabricated Structure and its installation process
Prefabricated Structure and its installation processPrefabricated Structure and its installation process
Prefabricated Structure and its installation process
Udayram Patil
 
Mivan shuttering
Mivan shutteringMivan shuttering
Mivan shuttering
Tharun Chowdary Mannava
 
Report on rigid frame structures
Report  on rigid frame structuresReport  on rigid frame structures
Report on rigid frame structures
Manisha Agarwal
 

What's hot (20)

JUMP FORM WORK
JUMP FORM WORKJUMP FORM WORK
JUMP FORM WORK
 
Formwork
FormworkFormwork
Formwork
 
Precast construction
Precast constructionPrecast construction
Precast construction
 
Slip formwork for chimney
Slip formwork for chimneySlip formwork for chimney
Slip formwork for chimney
 
Formwork
FormworkFormwork
Formwork
 
Formwork Presentation for Construction Technology
Formwork Presentation for Construction TechnologyFormwork Presentation for Construction Technology
Formwork Presentation for Construction Technology
 
Underpinning
UnderpinningUnderpinning
Underpinning
 
Jump Formwork
Jump FormworkJump Formwork
Jump Formwork
 
Shoring
ShoringShoring
Shoring
 
Slabs and types
Slabs and typesSlabs and types
Slabs and types
 
presentation on slip formwork
presentation on slip formworkpresentation on slip formwork
presentation on slip formwork
 
Prefabrication construction
Prefabrication constructionPrefabrication construction
Prefabrication construction
 
Construction of diaphragm wall
Construction of diaphragm wallConstruction of diaphragm wall
Construction of diaphragm wall
 
PRECAST BUILDING SYSTEM
PRECAST BUILDING SYSTEMPRECAST BUILDING SYSTEM
PRECAST BUILDING SYSTEM
 
Superstructure construction
Superstructure constructionSuperstructure construction
Superstructure construction
 
Prefabrication​ structure ppt
Prefabrication​ structure pptPrefabrication​ structure ppt
Prefabrication​ structure ppt
 
Steel formwork
Steel formworkSteel formwork
Steel formwork
 
Prefabricated Structure and its installation process
Prefabricated Structure and its installation processPrefabricated Structure and its installation process
Prefabricated Structure and its installation process
 
Mivan shuttering
Mivan shutteringMivan shuttering
Mivan shuttering
 
Report on rigid frame structures
Report  on rigid frame structuresReport  on rigid frame structures
Report on rigid frame structures
 

Similar to Slip form

Building construction report
Building construction  reportBuilding construction  report
Building construction report
Aprajeeta Singh
 
Case Study: High Rise Buildings
Case Study: High Rise BuildingsCase Study: High Rise Buildings
Case Study: High Rise Buildings
Prasad Thanthratey
 
High rise structure
High rise structureHigh rise structure
High rise structure
Anuj Singhal
 
High rise building design
High rise building design High rise building design
High rise building design
Somesh Siddharth
 
High-rise structural systems
High-rise structural systemsHigh-rise structural systems
High-rise structural systems
Akshay Revekar
 
high rise building
high rise buildinghigh rise building
high rise building
Aditya Sanyal
 
Finalppthighrise 130504010636-phpapp02
Finalppthighrise 130504010636-phpapp02Finalppthighrise 130504010636-phpapp02
Finalppthighrise 130504010636-phpapp02
satwik345
 
Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formwork
KHUSHBU SHAH
 
Super Structure Construction.pptx
Super Structure Construction.pptxSuper Structure Construction.pptx
Super Structure Construction.pptx
Ananthakumar75
 
Slipform construction
Slipform constructionSlipform construction
Slipform construction
ErankajKumar
 
Lift form slab construction
Lift form slab constructionLift form slab construction
Lift form slab construction
tivar rose
 
Presentation on MIVAN -- A versatile aluminum formwork construction technique
Presentation on MIVAN -- A versatile aluminum formwork construction techniquePresentation on MIVAN -- A versatile aluminum formwork construction technique
Presentation on MIVAN -- A versatile aluminum formwork construction technique
IEI GSC
 
Construction Technology
Construction TechnologyConstruction Technology
Construction Technology
SwapnilGorade1
 
TALL BUILDINGS
TALL BUILDINGSTALL BUILDINGS
TALL BUILDINGS
Abhijit Pal
 
Building Technology 1 (P1)
Building Technology 1 (P1)Building Technology 1 (P1)
Building Technology 1 (P1)
Nicole Foo
 
Mivan form wok - aluminium formwork shuttering tecnology
Mivan form wok - aluminium formwork shuttering tecnologyMivan form wok - aluminium formwork shuttering tecnology
Mivan form wok - aluminium formwork shuttering tecnology
sravan kumar chilamakuri
 
Flat Grid / Waffle Slab
Flat Grid / Waffle SlabFlat Grid / Waffle Slab
Flat Grid / Waffle Slab
Akshay Gawade
 
Speedy construction presentation
Speedy construction presentationSpeedy construction presentation
Speedy construction presentation
somitra bhardwaj
 
Horseshoe Casino Construction
Horseshoe Casino ConstructionHorseshoe Casino Construction
Horseshoe Casino Construction
RedBuilt LLC
 
PRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptxPRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptx
LokeswarSaha1
 

Similar to Slip form (20)

Building construction report
Building construction  reportBuilding construction  report
Building construction report
 
Case Study: High Rise Buildings
Case Study: High Rise BuildingsCase Study: High Rise Buildings
Case Study: High Rise Buildings
 
High rise structure
High rise structureHigh rise structure
High rise structure
 
High rise building design
High rise building design High rise building design
High rise building design
 
High-rise structural systems
High-rise structural systemsHigh-rise structural systems
High-rise structural systems
 
high rise building
high rise buildinghigh rise building
high rise building
 
Finalppthighrise 130504010636-phpapp02
Finalppthighrise 130504010636-phpapp02Finalppthighrise 130504010636-phpapp02
Finalppthighrise 130504010636-phpapp02
 
Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formwork
 
Super Structure Construction.pptx
Super Structure Construction.pptxSuper Structure Construction.pptx
Super Structure Construction.pptx
 
Slipform construction
Slipform constructionSlipform construction
Slipform construction
 
Lift form slab construction
Lift form slab constructionLift form slab construction
Lift form slab construction
 
Presentation on MIVAN -- A versatile aluminum formwork construction technique
Presentation on MIVAN -- A versatile aluminum formwork construction techniquePresentation on MIVAN -- A versatile aluminum formwork construction technique
Presentation on MIVAN -- A versatile aluminum formwork construction technique
 
Construction Technology
Construction TechnologyConstruction Technology
Construction Technology
 
TALL BUILDINGS
TALL BUILDINGSTALL BUILDINGS
TALL BUILDINGS
 
Building Technology 1 (P1)
Building Technology 1 (P1)Building Technology 1 (P1)
Building Technology 1 (P1)
 
Mivan form wok - aluminium formwork shuttering tecnology
Mivan form wok - aluminium formwork shuttering tecnologyMivan form wok - aluminium formwork shuttering tecnology
Mivan form wok - aluminium formwork shuttering tecnology
 
Flat Grid / Waffle Slab
Flat Grid / Waffle SlabFlat Grid / Waffle Slab
Flat Grid / Waffle Slab
 
Speedy construction presentation
Speedy construction presentationSpeedy construction presentation
Speedy construction presentation
 
Horseshoe Casino Construction
Horseshoe Casino ConstructionHorseshoe Casino Construction
Horseshoe Casino Construction
 
PRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptxPRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptx
 

More from Aglaia Connect

Underground construction
Underground constructionUnderground construction
Underground construction
Aglaia Connect
 
Self curing-concrete-
Self curing-concrete-Self curing-concrete-
Self curing-concrete-
Aglaia Connect
 
Trenchless technology
Trenchless technologyTrenchless technology
Trenchless technology
Aglaia Connect
 
Reactive powder-concrete
Reactive powder-concreteReactive powder-concrete
Reactive powder-concrete
Aglaia Connect
 
Stress ribbon-bridges
Stress ribbon-bridgesStress ribbon-bridges
Stress ribbon-bridges
Aglaia Connect
 
Self healing-material-bacterial-concrete
Self healing-material-bacterial-concreteSelf healing-material-bacterial-concrete
Self healing-material-bacterial-concrete
Aglaia Connect
 
Structural behavious-of-high-strength-concrete
Structural behavious-of-high-strength-concreteStructural behavious-of-high-strength-concrete
Structural behavious-of-high-strength-concrete
Aglaia Connect
 
Aerated autoclaved-concrete
Aerated autoclaved-concreteAerated autoclaved-concrete
Aerated autoclaved-concrete
Aglaia Connect
 
Transatlantic tunnel-floating-tunnel
Transatlantic tunnel-floating-tunnelTransatlantic tunnel-floating-tunnel
Transatlantic tunnel-floating-tunnel
Aglaia Connect
 
Tube structures
Tube structuresTube structures
Tube structures
Aglaia Connect
 
Marble and-quarry-dust-as-additives-in-concrete
Marble and-quarry-dust-as-additives-in-concrete Marble and-quarry-dust-as-additives-in-concrete
Marble and-quarry-dust-as-additives-in-concrete
Aglaia Connect
 
Computer ethics
Computer ethics Computer ethics
Computer ethics
Aglaia Connect
 
Plastic waste into fuel using pyrolysis process
Plastic waste into fuel using pyrolysis processPlastic waste into fuel using pyrolysis process
Plastic waste into fuel using pyrolysis process
Aglaia Connect
 
Geotextile for soil stabilization
Geotextile for soil stabilizationGeotextile for soil stabilization
Geotextile for soil stabilization
Aglaia Connect
 
Corrosion control of underwater piles
Corrosion control of underwater pilesCorrosion control of underwater piles
Corrosion control of underwater piles
Aglaia Connect
 
Constucted wetlands for waste water treatment
Constucted wetlands for waste water treatmentConstucted wetlands for waste water treatment
Constucted wetlands for waste water treatment
Aglaia Connect
 
Coconut shell as coarse aggregate in the concrete
Coconut shell as coarse aggregate in the concreteCoconut shell as coarse aggregate in the concrete
Coconut shell as coarse aggregate in the concrete
Aglaia Connect
 
Usage of geogrids in flexible pavement
Usage of geogrids in flexible pavementUsage of geogrids in flexible pavement
Usage of geogrids in flexible pavement
Aglaia Connect
 
Pervious concrete
Pervious concretePervious concrete
Pervious concrete
Aglaia Connect
 
Usage of geogrids in flexible pavement
Usage of geogrids in flexible pavementUsage of geogrids in flexible pavement
Usage of geogrids in flexible pavement
Aglaia Connect
 

More from Aglaia Connect (20)

Underground construction
Underground constructionUnderground construction
Underground construction
 
Self curing-concrete-
Self curing-concrete-Self curing-concrete-
Self curing-concrete-
 
Trenchless technology
Trenchless technologyTrenchless technology
Trenchless technology
 
Reactive powder-concrete
Reactive powder-concreteReactive powder-concrete
Reactive powder-concrete
 
Stress ribbon-bridges
Stress ribbon-bridgesStress ribbon-bridges
Stress ribbon-bridges
 
Self healing-material-bacterial-concrete
Self healing-material-bacterial-concreteSelf healing-material-bacterial-concrete
Self healing-material-bacterial-concrete
 
Structural behavious-of-high-strength-concrete
Structural behavious-of-high-strength-concreteStructural behavious-of-high-strength-concrete
Structural behavious-of-high-strength-concrete
 
Aerated autoclaved-concrete
Aerated autoclaved-concreteAerated autoclaved-concrete
Aerated autoclaved-concrete
 
Transatlantic tunnel-floating-tunnel
Transatlantic tunnel-floating-tunnelTransatlantic tunnel-floating-tunnel
Transatlantic tunnel-floating-tunnel
 
Tube structures
Tube structuresTube structures
Tube structures
 
Marble and-quarry-dust-as-additives-in-concrete
Marble and-quarry-dust-as-additives-in-concrete Marble and-quarry-dust-as-additives-in-concrete
Marble and-quarry-dust-as-additives-in-concrete
 
Computer ethics
Computer ethics Computer ethics
Computer ethics
 
Plastic waste into fuel using pyrolysis process
Plastic waste into fuel using pyrolysis processPlastic waste into fuel using pyrolysis process
Plastic waste into fuel using pyrolysis process
 
Geotextile for soil stabilization
Geotextile for soil stabilizationGeotextile for soil stabilization
Geotextile for soil stabilization
 
Corrosion control of underwater piles
Corrosion control of underwater pilesCorrosion control of underwater piles
Corrosion control of underwater piles
 
Constucted wetlands for waste water treatment
Constucted wetlands for waste water treatmentConstucted wetlands for waste water treatment
Constucted wetlands for waste water treatment
 
Coconut shell as coarse aggregate in the concrete
Coconut shell as coarse aggregate in the concreteCoconut shell as coarse aggregate in the concrete
Coconut shell as coarse aggregate in the concrete
 
Usage of geogrids in flexible pavement
Usage of geogrids in flexible pavementUsage of geogrids in flexible pavement
Usage of geogrids in flexible pavement
 
Pervious concrete
Pervious concretePervious concrete
Pervious concrete
 
Usage of geogrids in flexible pavement
Usage of geogrids in flexible pavementUsage of geogrids in flexible pavement
Usage of geogrids in flexible pavement
 

Recently uploaded

Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Christina Lin
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
Dr Ramhari Poudyal
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
symbo111
 
basic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdfbasic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdf
NidhalKahouli2
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
dxobcob
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
SUTEJAS
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
Fundamentals of Induction Motor Drives.pptx
Fundamentals of Induction Motor Drives.pptxFundamentals of Induction Motor Drives.pptx
Fundamentals of Induction Motor Drives.pptx
manasideore6
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
SyedAbiiAzazi1
 
An Approach to Detecting Writing Styles Based on Clustering Techniques
An Approach to Detecting Writing Styles Based on Clustering TechniquesAn Approach to Detecting Writing Styles Based on Clustering Techniques
An Approach to Detecting Writing Styles Based on Clustering Techniques
ambekarshweta25
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
Intella Parts
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
ClaraZara1
 

Recently uploaded (20)

Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
 
basic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdfbasic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdf
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
Fundamentals of Induction Motor Drives.pptx
Fundamentals of Induction Motor Drives.pptxFundamentals of Induction Motor Drives.pptx
Fundamentals of Induction Motor Drives.pptx
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
 
An Approach to Detecting Writing Styles Based on Clustering Techniques
An Approach to Detecting Writing Styles Based on Clustering TechniquesAn Approach to Detecting Writing Styles Based on Clustering Techniques
An Approach to Detecting Writing Styles Based on Clustering Techniques
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
 

Slip form

  • 2. SLIP- FORM Slip forming, continuous poured, continuously formed, or slip form construction is a construction method in which concrete is poured into a continuously moving form.  Slip forming is used for tall structures (such as bridges, towers, buildings, and dams), as well as horizontal structures, such as roadways.  Slip forming enables continuous, non-interrupted, cast-in-place "flawless" (i.e. no joints) concrete structures which have superior performance characteristics to piecewise construction using discrete form elements. SLIP FORM
  • 3. Slip forming relies on the quick-setting properties of concrete, and requires a balance between quick-setting capacity and workability. Concrete needs to be workable enough to be placed into the form and consolidated (via vibration), yet quick-setting enough to emerge from the form with strength.  This strength is needed because the freshly set concrete must not only permit the form to "slip" by the concrete without disturbing it, but also support the pressure of the new concrete as well as resist collapse caused by the vibration of the compaction machinery. SLIP FORM
  • 4. COMPONENTS OF SLIP-FORM The slip form system is designed with varied features.  Generally, it consist of yoke legs. Yoke legs are employed to lift and sustain the weight of the entire structure, so that it behaves as a single unit. Yoke legs are also used to connect with the beams, scaffoldings and working platforms to serve the supporting purpose. To the yoke legs, walk-away brackets are connected. These walkway brackets will enable proper placement of the concrete.  The whole slip form assembly is lifted by means of strand rods and lifting jacks.  These primary components are located at equal intervals so that the uniform and good distribution of weight is performed.  In some construction, lifting process are supported by means of hydraulic pump components. SLIP FORM
  • 6. PROCEDURE Assembly can only start once the foundations are in place and the wall starter is in correct alignment. Slip form shuttering is aligned with the help of yokes.Horizontal crossbeams connect these yokes. Hydraulic jacks are attached to these crossbeams for simultaneous upward movement. Height of the slip form ranges from 1.1 to 1.5 meters. Yokes and crossbeams also used to support the working platform. Structure should be rigid and shape maintained at all times. Make sure there is no lag or else it prevents the structure from free upward movement.  It is also possible to reduce wall thicknesses as the construction gains height and arrangements have to be made in the slip form structure that will enable such reduction at regular intervals. SLIP FORM
  • 7. TYPES OF SLIP-FORM CONSTRUCTION VERTICAL SLIP-FORM HORIZONTAL SLIP-FORM TAPERED SLIP-FORM SLIP FORM
  • 8. VERTICAL SLIP-FORM In vertical slip forming, the concrete form may be surrounded by a platform on which workers stand, placing steel reinforcing rods into the concrete and ensuring a smooth pour. Together, the concrete form and working platform are raised by means of hydraulic jacks. The slip-form rises at a rate which permits the concrete to harden by the time it emerges from the bottom of the form. SLIP FORM
  • 10. HORIZONTAL SLIP FORM In horizontal slip forming for pavement and traffic separation walls, concrete is cast, vibrated, worked, and settled in place while the form itself slowly moves ahead. This method was initially devised and utilized in Interstate Highway construction initiated during the 1950s. SLIP FORM
  • 12. TAPERED SLIP-FORMING Slip-forming is also used in the construction of conical chimneys, cooling towers, piers and other tall concrete structures involving constant or changing thicknesses in walls, diameters and/or shapes. A form is used with sections which overlap so that one gradually slides over the other. This is commonly done in chimney construction but it is not satisfactory for architectural concrete because the lap shows. While the tapered slip-forming process is similar to that used on the standard slip-forming, it requires greater attention, contractor experience and expertise ensures the success of such projects. SLIP FORM
  • 13. Slipform Construction of Collie Power Station, Western AustraliaSLIP FORM
  • 14. Continuous slip formed gravity-based structure supports under construction in a Norwegian fjord. The visible jib cranes would each be delivering buckets of concrete to the support cylinders during the continuous pour of concrete creating seamless walls. SLIP FORM
  • 15. FEATURES OF SLIPFORM CONSTRUCTION TECHNIQUE The slip form construction technique is a rapid and a economic construction method compared to the conventional formwork technique. This helps to achieve huge cost saving. The technique is best suitable for large building structures and bridges. When small structures are concerned, the projects with identical geometry can be easily completed by slip form construction. Continuous movement of formwork in upward direction is performed in slip form technique. The movement is facilitated by hydraulic jacks and jack rods.  In the construction of vertical structures, the rate of rising the formwork upwards will be almost in the rate of 300mm per hour. These rise with the help of the supports from other permanent parts of the building. The technique of slip form construction will vary based on the type of structure constructed. Based on this the frameworks required to support the system will vary. SLIP FORM
  • 16. ADVANTAGES  Height This technology becomes very competitive starting at about 60 ft of height and continues to improve with increasing height thereafter.  Early Assembly The slip form setup is very compact and can be pre-assembled ahead of time. Once the foundation is ready, the slip form can quickly be placed on the foundation and construction can start almost immediately.  Speed of Construction Speeds of between 7 ft and 30 ft per 24 hours are possible. Many times, this speed allows reuse of formwork on repetitive elements without impacting the overall schedule, thus reducing your total formwork cost. SLIP FORM
  • 17.  No Form Ties No ties are required because the limited concrete pressure is taken by the slipform yoke directly. Without ties, there are also no form holes to fill, which reduces labor costs, improves appearance and makes for a water-tight structure. This is particularly important for offshore structures such as gravity oil and gas platforms.  No Rebar Bolsters Unlike in standard wall construction with panel forms, slip forming does not require lost rebar bolsters in every pour to control the rebar cover. In slip form construction, sliding guides are mounted on top of the slip form. These guides push the rebar into position and accurately control the rebar cover as the slip form moves upwards. SLIP FORM
  • 18.  Safety The slip form setup provides a safe and protected work environment for your crew. Relatively little climbing is required, the work area is compact and unchanging and weather protection can easily be added to the formwork setup. Enclosed spaces can be heated during the cold weather periods.  Flexibility A slip form is of low overall height and very compact. That makes it is easier to handle and modify for changing concrete cross-sections. Also, the extension past the hardened concrete line is very short, so very little wind force has to be considered in the formwork design. SLIP FORM
  • 19.  Easy To Stop The slip form operation can be stopped and resumed at will, to suit the contractor’s schedule. Slip form operations can be suspended for the weekend or during parts of the day as dictated by external factors. This is done by climbing another 18 in. or so after the last concrete has been poured. This gives the concrete time to set and helps to break the form adhesion to the fresh concrete.  Standard Concrete Mix No special concrete is needed for a typical slip form project. For certain offshore structures, advanced concrete mixes have been developed to improve the performance of the structure in the ocean environment. However, these types of structures are rare and the vast majority of buildings and towers can be slip formed with ordinary concrete mixes. SLIP FORM
  • 20.  Continuous Process Slip forming is a continuous extrusion process. There is no need to set and strip forms every few feet. You do not need to tie up a crane as for handling conventional formwork.  Quality Finish Slip forming provides a superior concrete finish with no form fins to clean up and without horizontal joints. A sponge finish and other surface treatments are easy to apply from the second work platform suspended from the slip form assembly SLIP FORM
  • 21. DISADVANTAGES High –cost for initial setup. Requires Specialized workers and expertise. Need sophisticated Equipment. Dimensional Accuracy can go low in certain conditions. SLIP FORM
  • 22. APPLICATIONS OF SLIP-FORM CONSTRUCTION Slip-form construction is used for tall structures, such as towers, buildings, and dams, as well as horizontal structures, such as roadway barriers.  It enables continuous, non-interrupted, cast-in- place joint-less concrete structures which have superior performance characteristics over construction methods using discrete form elements. Slip forming relies on the quick setting properties of concrete, and requires a balance between quick-setting capacity and workability. Capital Gate Tower, Abu Dhabi King Abdul- Aziz Airport Inn Canal, Germany SLIP FORM
  • 23. THANK YOU!!For more…. Mail to aglaiaconnect2018@gmail.com SLIP FORM