SlideShare a Scribd company logo
1
TAYLOR’S UNIVERSITY
SCHOOL OF ARCHITECTURE, BUILDING AND DESIGN (SABD)
BUILDING TECHNOLOGY I
BLD 61403
INDUSTRIALIZED BUILDING SYSTEM
320213 MOHAMAD ANWAR B FAUZI
324705 TEO CHIA YEE
3225517 NICOLE FOO SHULI
325069 HARASHADEEP KAUR
321409 DANIAL MAZLAN
325736 ASHROFF B ABD WAHAB
TUTOR : M R KH A I ROOL
2
INTRODUCTION
ACKNOWLEDGMENT 4
OBJECTIVE 4
PROPOSED IBS SYSTEM
PRECAST CONCRETE 5
PREFABRICATED TIMBER 5
BUILDING COMPONENTS
PRECAST FOUNDATION 6
PRECAST COLUMNS 6
PRECAST BEAMS 7
PRECAST FLOOR SLAB 7
PRECAST WALLS 8
PRECAST STAIRCASE 8
PREFABRICATED ROOF FRAME 8
JOINING METHODS
COLUMN TO COLUMN 9
COLUMN TO BEAM 9
BEAM TO WALL 10
BEAM TO SLAB 10
STAIRS AND CONNECTION 11
TRUSSES TO ROOF BEAM 12
ROOF FINISHES 12
CONTENTS
3
PROCEDURE 13
DRAWINGS 18
SCHEDULE 36
IBS SCORE 41
REFERENCES 44
4
ACKNOWLEDGMENT
Various parties have made the completion of this projection possible and hopefully a success. We would like to thank our lecturer Mr Rizal who had provided us
with the necessary theory in order to understand the Industrialized Building System (IBS), including organizing field trips for us   More importantly, we would like to
thank Mr Khairool our tutor for being willing to answer our questions even outside tutorial-designated hours. Mr Khairool’s suggestions definitely gave us new
perspective and made the writing of the report more concise.  I heartily thank the School of Architecture Building and Design (SABD) at Taylor’s University for giving
us this opportunity to carry out research on a topic that is going to become very important both locally and internationally when more and more prefabricated forms
of construction will be preferred.
We are also thankful to and fortunate enough to get constant encouragement, support and guidance from each other as group members, whom, without our various
contributions, would not be able to produce a report of quality.
OBJECTIVE
We would like to determine the many methods of constructing a building out of standardized system known as Industrial Building System (IBS), only very recently
implemented in our country. In Malaysia, the prefabrication technology is known as industrialized building system (IBS) which is defined as a complete process
system of construction works where almost all the component structures is manufactured onsite or offsite, and the product is transported to the site and to be
installed in the high precision coordinate joint as well as achieve high quality works, and accelerate the time of completion of the projects. The benefits of
prefabrication helped the Housing Ministries in various countries to fulfill the high demand for housing inMalaysia. Providing affordable homes are becoming a vital
issue to meet the increasing demand for houses with the increase in the population growth. The most popular IBS component used in Malaysia is precast
components. Over the years, the total number of IBS precast manufacturing has increased from 15 in 2009 to 36 factories in the year 2011.As a group, we would like
to demonstrate that creating a structure according to IBS is not impossible , this increasing this upward trend in the usage of IBS systems as it is extremely
efficient.
5
PRECAST CONCRETE
Our apartment block comprises of a hybrid system ; a combination of precast concrete system as well as a prefabricated timber framing. The prefabricated timber
will be used exclusively for the structure of the roof trusses as well as rafters whereas the rest of the structure is precast. This includes the foundation, external and
internal walling, flooring, columns and beams, as well as staircase.
PREFABRICATED TIMBER
Precast concrete is a construction product produced by casting concrete in reusable mould or form which is then cured in a controlled environment, transported to
the construction site a lifted to be set into place. A fully precast building is constructed by using various prefabricated elements required in the building structure.
PROPOSED IBS SYSTEM
ADVANTAGES DISADVANTAGES
Quality and strength assured since produced in controlled factory conditions Difficult to produce non-regular organic shapes
Quality also easily monitored Requires transportation to site that may be costly
Material for production is cheap since material can be bought in bulk Some components are heavy and cranes are required to install
Same result in any weather conditions so appropriate mixes are achieved.
No setting time and immediate installation can take place.
Modularity of components is achieved very quickly
Less labour required
ADVANTAGES DISADVANTAGES
Lower cost than steel if finishes and wood type are not expensive Extra measures like waterproofing must be taken
Higher aesthetic value and gives warmer impression especially for residential homes. Subject to rot and quicker decay
Do not require extra carpentry space on site Wood is flammable so extra measures must be taken for fire proofing
Environmentally friendly material
Little limits on design
A roof truss consists of one or more triangular units constructed of pieces that are connected by joints. The triangular shape of the truss adds stability and support by
distributing weight away from the exterior walls. Timber roof trusses may be used in commercial applications, but they are generally used for residential construction,
which is why we considered it for our roof structure.
6
PRECAST FOUNDATION
PRECAST COLUMNS
BUILDING COMPONENTS
Precast columns These can be produced to have either single or multiple story corbel
to allow multiple levels of components such as walls and beams to sit on the
columns. This reduces installation time. However, we have chosen to utilize single
story corbel-columns of solid rectangular section.
Precast foundation was economical choice for us as the foundation footing has
reinforcement bars and regulators already present inside. Foundation is placed
directly on ground and brought to the appropriate height through the use of these
regulators (as noted in diagram) No concrete underpinning needs to be poured
since the regulators also lift the rebar from the terrain
Regulator
Our column choice
Precast components
• Foundation
• Columns
• Beams
• Slabs
• Walls
• Staircase
Prefabricated Timber components
• Roof Truss
Additional Components
• Standardized window size
• Standardized door size
• Standardized use of railings
• Toilet pods
7
PRECAST BEAM
PRECAST FLOOR SLABS
Hollow core slabs are prestressed concrete elements that are commonly used for floorings in homes and commercial buildings. As the name suggests, this type of
slab possesses voids called ‘cores’ that run through its entire length, with the main intention of reducing the overall slab weight. These cores can also be used as
service ducts. Steel strands are placed within the slabs running longitudinally as reinforcements, which allows slabs to have long spans without propping.
Furthermore, hollow core slabs possess high flexibility in design, and are available with a variety of notches, slots, and reinforcement arrangements.
L-Beams/ Spandrel
L-beams are prestressed concrete elements that, together with inverted
tee-beams, make up a flooring system. They are characterized by the L-
shaped cross-section from which the name is derived. Like inverted tee-
beams, L-beams provide ledgers for precast slab units to sit on. They are
commonly found at the external walls (the edges of the floor unit) or
around the staircase.
Solid Rectangular Beam
Solid Beams are some of the most commonly used type of beams used in both
smaller and larger scale construction. These come usually prestressed and in a
wide range of dimensions. These may not be conducive when high bending moment
is present as the shape is makes it inflexible. We have utilized these in our ground
floor whereby it is connection to the pad footing of the foundation.
We have used a combination of L-beans and solid beams after many changes to our structure throughout the design process. We had used L-beams for the ground
floor whereas the L-shape beams throughout the other floors. We found this shape to be versatile as it suited our design where we needed both walls and slab to sit
on the beams.
ADVANTAGES DISADVANTAGES
Maximum structural efficiency for every slab thickness Expensive transportation to site and erection
Variety of shapes and sizes available, with long spans Large and heavy
Eliminates ducting work as system components can be hidden
Less vibration and strong acoustical performance
8
PRECAST WALLS
Our walls are solid rectangular-section walls. Some have prefabricated openings in order to allow for placement of window to be installed on site Cranes will be
needed to erect these walls and transportation to site can be quite costly. There are other types of precast walls like ribbed, double tee and mullion0ed but
PRECAST STAIRCASE
ADVANTAGES DISADVANTAGES
Rapid speed of erection Small margin for error
Maintaining cleanliness of site as production materials not
needed
Economics of scale demand regularly shaped buildings
Higher quality due to controlled measures taken in factory
ROOF FRAME
Our roof frame will be constructed with a series of prefabricated timber trusses. The primary shape
of the truss is a typical long-bearing truss shape which is ideal for longer spans of roof. Many of the
advantages and benefits are similar to that of using prefab timber in general
ADVANTAGES DISADVANTAGES
Higher quality due to controlled measures taken in factory Can be expensive to transport
Can be installed much faster than in-situ stairs Difficult to produce complex shapes like spiral or curve
Unlike in situ stairs, precast stairs can be used directly
after installation by workers as no drying time is required.
The shape of our primary timber truss
9
COLUMN TO COLUMN
COLUMN TO BEAM
JOINING METHODS
Metal bearing plates and embedded anchor bolts are cast into the ends of
the columns. After column is mechanically joined, the connection is grouted
to ensure full load bearing between elements and to protect metal
components from corrosion.
With accurate placement, the weld plates are casted into beams and columns
respectively. A bearing plate is placed between the beam and column
connection. It is used to transfer concentrated compressive forces between
the two structural elements. The weld plates are welded after the beams and
columns are held into place, this is to fully secure the said connection.
Anchor bolts
connected to bearing
plates
COLUMN TO COLUMN
COLUMN
BEAM
METAL BEARING PLATES
METAL BEARING PLATES
SHIM
GROUT
CONCRETE
ANCHOR BOLT
WELD PLATES
BEARING
PLATES
COLUMN TO COLUMN
METAL BEARING PLATES
METAL BEARING PLATES
SHIM
GROUT
CONCRETE
ANCHOR BOLT
10
BEAM TO WALL
BEAM TO SLAB
Precast walls are casted with connecting rebars left protruding which will
eventually connect to the holes casted into beams. After the elements are put
into place, the connection is grouted in order to secure its standing.
Precast hollow core slabs are placed onto the ledge of the L-shaped beam
and then the connection is grouted to hold it into place.
Diagram to show how L-beam, hollow core slab and
column is connected within our structure
11
STAIRCASE CONNECTIONS
Landing to wall connection - The landing slab sits on a
RSA (Rolled Steel Angle) that is bolted to the wall. A
Structural shim packer is placed between the RSA and
landing slab, it serves to level the landing slab before
commitment.
Stairs to slab connection - The stairs sits on a structural shim packer which sits on
the ledge casted into the floor slab. A hole is then bored through the step of the of
the stairs and the shim packer and stops when it reaches into the slab. A metal
dowel piece is then inserted into the hole and the hole is then sealed by grout.
LANDING TO WALL CONNECTION
STAIRS TO SLAB CONNECTION
FLOOR SLAB
FLOOR SLAB
CONNECT TO WALL
CONNECT TO WALL
CONNECT TO WALL
LANDING SLAB
WALL
ANCHOR BOLT
RSA (ROLLED STEEL ANGLE)
STRUCTURAL SHIM PACKERS
(10MM THICK)
STAIRS
FLOOR SLAB
STRUCTURAL SHIM PACKERS
(10MM THICK)
DOWEL HOLE
(30MM DIA.)
LANDING TO WALL
STAIRS TO SLAB
Due to our usage of straight flight staircase, we do not
have any integral landing connected at the factory.
Hence the two floor slabs and one landing slab are
needed
Straight flight stairs
The connection between the stairs and slab is of a typical notch joint as seen in
typical precast stairs
Example of notch joint at the
upper floor slab
12
TRUSSES TO ROOF BEAM
ROOF FINISHES
Two metal weld plates sandwiches the wooden rafter and is held together by
two-sided bolts. Weld plates are casted into concrete roof beam with
accurate placement. After the rafter sits in place on the beam, the weld
plates are welded together, the securing its placement allowing the rafter to
transfer loads to beam well.
Two metal weld plates sandwiches the
wooden rafter and is held together by
two-sided bolts. Weld plates are casted
into concrete roof beam with accurate
placement. After the rafter sits in place
on the beam, the weld plates are welded
together, the securing its placement
allowing the rafter to transfer loads to
beam well.
Example of joining between
timber battens and roof
tiles
13
PRODUCTION OF PRECAST CONCRETE PIECES
PROCEDURE
STEP 1 : Producing the reinforced-bar cages
for each component needed. Welding is
needed to join the parts
STEP 2 The reinforced cage is placed inside
a mould that is partially complete and
usually made of timber. Then the mould is
closed up
STEP 3 The specified concrete mix is poured
into the wooden mould. Sometimes
computers replace manual methods in
determining the amount needed
STEP 4 Compaction of concrete
using vibrator to achieve optimum
density. High frequency vibrators or
pokers may be used.
STEP 5 Moving precast
into storage area
STEP 6 Storage of high quality units
in order to prepare to be transported
STEP 7 AND 8 Transportation to site is done in a predetermined
sequence so construction can take place according to arrangement
INSTALLATION
PRODUCTION OF PREFABRICATED WOOD FRAME
STEP 1 : Custom
profiling
STEP 2 : Custom
milling
STEP 3 : Test fit
connections
STEP 4 : Factory
prestaining
STEP 5 : Testing
structural integrity of
joinery
STEP 6 : Completion
of joinery
STEP 7 :
Transportation to
site
14 STEP 11 STEP 12
STEP 13 STEP 14
Prefabricated pad foundation is placed on top of
excavated terrain with the installation of padfooting
columns with corbels
Rectangular section beams are placed on top of
corbels of columns accordingly
Hollow core precast slabs are then placed on top of
the rectangular beams. For the ground floor, cranes
may not be needed to install these
Precast walls are then installed on top of beams and
floor slabs of the ground floor. Usually a crane is
needed to place these with some manual assistance.
Toilet pod for ground floor also installed.
15
STEP 5 STEP 11
STEP 7 STEP 8
5 6
7 8
Columns with single story corbel are then placed on
top of the pad-footing columns
Crane is used to installed precast L shape / Spandrel
beams on top of columns
Staircase is installed using a crane to connect the
ground and first floor landing .
A crane will be needed to lift these heavy hollow core
slabs on to the beams and columns of the ground
floor.
16 STEP 9 STEP 01
STEP 11 STEP 12
9 10
11 12
Repetition of step 4 whereby windows are installed
using crane
Repetition of step 5 but instead ground floor columns
are connection to first floor columns
Repetition of step 6 but instead first floor L beams
are not placed on to first floor columns
Repetition of step 7. This time stairs used to connect
first floor to landing of second floor
17
STEP 13 STEP 14
STEP 15
After repeating steps 4 to 6 yet again, beams of the
second floor are then placed on to the walls.
The roof trusses are then installed on to the beams of
the upper floor. Rafters are installed also
The roof bracing is installed within the roof truss.
Additional components like doors and windows are
also installed via crane or manually. In addition, metal
railings are installed throughout areas without
external wall and by the staircase.
13 14
15
18
DRAWINGS
19
BEDROOM 1
TOILET 1
BEDROOM 2
BEDROOM 3
TOILET2
KITCHEN
DINING
ROOM
LIVING
ROOM
BEDROOM 1
TOILET 1
BEDROOM 2
BEDROOM 3
TOILET 2
KITCHEN
DINING
ROOM
LIVING
ROOM
UP
1 2 3 4 5 6 7 8 9
A
B
C
D
E
F
ARCHITECTURAL GROUND FLOOR PLAN
SCALE 1:100
3000 3000 3000 3000 3000 3000
1500 1500
21000
30003000300030003000
1225
1500 1500
A
A
20
BEDROOM 1
TOILET 1
BEDROOM 2
BEDROOM 3
TOILET 2
KITCHEN
DINING
ROOM
LIVING
ROOM
BEDROOM 1
TOILET 1
BEDROOM 2
BEDROOM 3
TOILET 2
KITCHEN
DINING
ROOM
LIVING
ROOM
UP
ARCHITECTURAL FIRST FLOOR PLAN
SCALE 1:100
1 2 3 4 5 6 7 8 9
A
B
C
D
E
F
3000 3000 3000 3000 3000 3000
1500 1500
21000
30003000300030003000
1225
1500 1500
A
A
21
BEDROOM 1
TOILET 1
BEDROOM 2
BEDROOM 3
TOILET 2
KITCHEN
DINING
ROOM
LIVING
ROOM
BEDROOM 1
TOILET 1
BEDROOM 2
BEDROOM 3
TOILET 2
KITCHEN
DINING
ROOM
LIVING
ROOM
DOWN
ARCHITECTURAL SECOND FLOOR PLAN
SCALE 1:100
1 2 3 4 5 6 7 8 9
A
B
C
D
E
F
3000 3000 3000 3000 3000 3000
1500 1500
21000
30003000300030003000
1225
1500 1500
A
A
22
ROOF PLAN
SCALE 1:100
1 2 3 4 5 6 7 8 9
A
B
C
D
E
F
20100
17100
8100
23100
1500 1500
A
A
23
1 2 3 4 5 6 7 8 9
A
B
C
D
E
F
STRUCTURAL PLAN
SCALE 1:100
21000
30003000300030003000
1500 3000 3000 3000 3000 3000 3000 1500
4500 1500 4500 1500
24
1 2 3 4 5 6 7 8 9
A
B
C
D
E
F
STRUCTURAL FOUNDATION PLAN
SCALE 1:100
21000
30003000300030003000
1500 3000 3000 3000 3000 3000 3000 1500
4500 1500 4500 1500
25
1 2 3 4 5 6 7 8 9
A
B
C
D
E
F
STRUCTURAL FLOOR PLAN WITH FLOOR SLABS
SCALE 1:100
21000
30003000300030003000
1500 3000 3000 3000 3000 3000 3000 1500
4500 1500 4500 1500
void
26
B5
B5
STRUCTURAL FOUNDATION PLAN (COMPONENTS INDICATED)
SCALE 1:100
B6
B6 B6
B6
B5B7
B11
B7
B10
C1 C1 B5
B7
B5
B6
B6
B6
B5 B7
B11B10
B10
B10
27
STRUCTURAL PLAN 1 (INDICATED COMPONENTS)
SCALE 1:100
COMMON
GROUND FLOOR
FIRST FLOOR
SECOND FLOOR
B5
B5
B2
B2 B6
B6
B11
B7
B10
C1
B10
B10
B10
B6
B6
B4
B7B3 B5 B1
C1
C1
C1
C1
C2C2
C2
C3
C3 C3 C3
C3
C3
C3
C3
C3
C4
C4
C6
C5
C7
C7
C7
C8C8
C8
C7
C9
C9
C9
C9
C9C9
C10
C10
C9
C11
C9
C12
C13
C15
C15
C15
C15
C15
C15 C15
C15
C16
C16
C17
C18
C9
C15
C13
C13
C13
C14 C14
C14
28
STRUCTURAL PLAN 2 (INDICATED COMPONENTS)
SCALE 1:100
COMMON
GROUND FLOOR
FIRST FLOOR
SECOND FLOOR
W1
W1
W7
W7
W4
W10
W3
W9
W3
W9
W2
W8
W2
W2
W8
W8
W6
W12
W5
W11
W7
W7W7
W7
W7W6
W12
W5
W11
W4
W4
W4
W7
29
void
STRUCTURAL PLAN WITH FLOOR SLABS (INDICATED COMPONENTS)
SCALE 1:100
F1 F1 F1 F1 F1 F1F1 F1
F1 F1
F1 F1 F1
F1 F1
F2
F2
F3
F3F1 F1 F1 F1
F1F1F1 F1
F4
F4 F4
F4
F1 F1
F1 F1
F1F1
F1F1
F1
F1
F1
F1F1
F1
F1
F1
F1F1
F1 F1F3
30
BEDROOM 1
TOILET 1
BEDROOM 2
BEDROOM 3
TOILET 2
KITCHEN
DINING
ROOM
LIVING
ROOM
BEDROOM 1
TOILET 1
BEDROOM 2
BEDROOM 3
TOILET 2
KITCHEN
DINING
ROOM
LIVING
ROOM
UP
FLOOR PLAN (INDICATED COMPONENTS)
SCALE 1:100
T1T1
T4
T4
T2T2
T3 T3
D1D1
D1D1
D1
D1 D1
D1
D1D1
D2 D2
D3 D3
D3
D3
D3
D3
D4 D4 D4 D4
D4
D4D4
D4
31
FRONT ELEVATION
SCALE 1:100
1 2 3 4 5 6 7 8 9
3000 3000 3000 3000 3000 3000
1500 1500
21300
340032003000
ROOF LEVEL
1940
GROUND FLOOR LEVEL
FIRST FLOOR LEVEL
SECOND FLOOR LEVEL
32
SIDE ELEVATION
SCALE 1:100
A B C D E F
340032003000
ROOF LEVEL
1940
FIRST FLOOR LEVEL
SECOND FLOOR LEVEL
GROUND FLOOR LEVEL
33
340032003000
ROOF LEVEL
1940
FIRST FLOOR LEVEL
SECOND FLOOR LEVEL
GROUND FLOOR LEVEL
SECTION A-A
SCALE 1:100
ABCDEF
34
EXTERIOR PERSPECTIVE
SCALE : N/A
35
SCHEDULE
36
DESCRIPTION
LENGTH (L x W x H)
GROUND FLOOR COLUMNS
300 x 300 x 3400
QUANTITY 24
LOCATION
3400
500200
300 300
300
300
DESCRIPTION
LENGTH (L x W x H)
QUANTITY
LOCATION
300
300
DESCRIPTION
LENGTH (L x W x H)
QUANTITY
LOCATION
300
300
DESCRIPTION
LENGTH (L x W x H)
QUANTITY
LOCATION
300
200
500
3400
300 300
500
200
3400
300 300
500
200
3400
250
100
150
300
150
GROUND FLOOR COLUMNS
300 x 300 x 3400
GROUND FLOOR COLUMNS
300 x 300 x 3400
GROUND FLOOR COLUMNS
300 x 150 x 3400
18
48
12
A2, D1, D3, E1, A8, D7, D9, F 9
A3, A4, F3, A6, A7, F7
A5, B2, B3, B4, B5, C2, C3, D2, E1, B6
B7, B8, C7, C8, D8, E9
C4, D4, C6, D6
DESCRIPTION
LENGTH (L x W x H)
QUANTITY
LOCATION
DESCRIPTION
LENGTH (L x W x H)
QUANTITY
LOCATION
300
150
300
150
500
3400
300 150
200
100250
200 300 150
200
250
500
3400
100
GROUND FLOOR COLUMNSGROUND FLOOR COLUMNS
300 x 150 x 3400
GROUND FLOOR COLUMNS
300 x 150 x 3400
6
6
F4, F6
E4, E6
DESCRIPTION
LENGTH (L x W x H)
FIRST FLOOR COLUMNS
QUANTITY
LOCATION
300
300
DESCRIPTION
LENGTH (L x W x H)
QUANTITY
LOCATION
300
300
DESCRIPTION
LENGTH (L x W x H)
QUANTITY
LOCATION
300
300
DESCRIPTION
LENGTH (L x W x H)
QUANTITY
LOCATION
300
150
3200
200
300300
500
3200
200
300 300
500
300 300
3200
200
500
3200
200
500
300
150
300250
300 x 300 x 3200
FIRST FLOOR COLUMNS
300 x 300 x 3200
FIRST FLOOR COLUMNS
300 x 300 x 3200
FIRST FLOOR COLUMNS
300 x 300 x 3200
FIRST FLOOR COLUMNSFIRST FLOOR COLUMNS
300 x 150 x 3200
18
24
48
12
A2, D1, D3, E1, A8, D7, D9, F 9
A3, A4, F3, A6, A7, F7
A5, B2, B3, B4, B5, C2, C3, D2, E1, B6
B7, B8, C7, C8, D8, E9
C4, D4, C6, D6
200
DESCRIPTION
LENGTH (L x W x H)
QUANTITY
LOCATION
DESCRIPTION
LENGTH (L x W x H)
QUANTITY
LOCATION
300
150
300
150
3200
150
300
250
300
3200
500200
300
250
150300
FIRST FLOOR COLUMNS
300 x 150 x 3200
FIRST FLOOR COLUMNS
300 x 150 x 3200
6
6
F4, F6
E4, E6
C1
C2
C3
C4
C5
C6
C7
C8
C9
C10
C11
C12
COLUMNS
GROUND FLOOR COLUMNS FIRST FLOOR COLUMNS
37
DESCRIPTION
LENGTH (L x W x H)
QUANTITY
LOCATION A2, D1, D3, E1, A8, D7, D9, F 9
300
300
DESCRIPTION
LENGTH (L x W x H)
QUANTITY
LOCATION
300
300
DESCRIPTION
LENGTH (L x W x H)
QUANTITY
LOCATION
300
300
DESCRIPTION
LENGTH (L x W x H)
QUANTITY
LOCATION
300
150
300 300
200
3000
3000
200
300 300
3000
200
300300
3000
250
200
300
300
300
300
200
300
300
150
SECOND FLOOR COLUMNS
300 x 300 x 3000
SECOND FLOOR COLUMNS
300 x 300 x 3000
SECOND FLOOR COLUMNS
300 x 300 x 3000
SECOND FLOOR COLUMNS
300 x 150 x 3000
18
24
48
12
A3, A4, F3, A6, A7, F7
A5, B2, B3, B4, B5, C2, C3, D2, E1, B6
B7, B8, C7, C8, D8, E9
C4, D4, C6, D6
DESCRIPTION
LENGTH (L x W x H)
QUANTITY
LOCATION
DESCRIPTION
LENGTH (L x W x H)
QUANTITY
LOCATION
300
150
300
150
300
200
250
200
300
150300
3000
3000
250
300
200
100
150300
SECOND FLOOR COLUMNS
300 x 150 x 3000
SECOND FLOOR COLUMNS
300 x 150 x 3000
6
6
F4, F6
E4, E6
C13
C14
C15
C16
C17
C18
COLUMNS
SECOND FLOOR COLUMNS
38
DESCRIPTION
LENGTH (L x W x W x H)
L-SHAPE BEAM
1200 x 300 x 150 x 500
QUANTITY 4
LOCATION
DESCRIPTION L - SHAPE BEAM
QUANTITY 36
LOCATION
DESCRIPTION L - SHAPE BEAM
QUANTITY 4
LOCATION
DESCRIPTION L - SHAPE BEAM
QUANTITY 2
LOCATION
LENGTH (L x W x W x H) 2700 x 300 x 150 x 500
LENGTH (L x W x W x H) 4200 x 300 x 150 x 500
LENGTH (L x W x W x H) 6000 x 300 x 150 x 500
1200
2700
4200
6000
500
150
150
500
150
150
500
150
150
500
150
150
B1
B2
B3
B4
D-F1'/A-D2/A-D8/D-F8'/A2-8/F3-4/F6-7
F 1'-3 / F 7-8'
D1' - D2 / D8 - D8'
GROUND & FIRST FLOOR
F 4 - 6
GROUND & FIRST FLOOR
GROUND & FIRST FLOOR
GROUND & FIRST FLOOR
DESCRIPTION
LENGTH (L x W x H)
SQUARE BEAM
1200 x 300 x 300
QUANTITY 12
LOCATION
DESCRIPTION
LENGTH (L x W x H)
SQUARE BEAM
2700 x 300 x 300
QUANTITY 96
LOCATION
DESCRIPTION
LENGTH (L x W x H)
SQUARE BEAM
4200 x 300 x 300
QUANTITY 28
LOCATION
DESCRIPTION
LENGTH (L x W x H)
SQUARE BEAM
4650 x 300 x 300
QUANTITY 2
LOCATION
1200
300
300
300
300
300
300
300
300
4650
300
4200
300
2700
B5
B7
B8
B6
B3'-4/B6-6'/D1'-D2/D8-D8'
FOUNDATION & SECOND FLOOR
FOUNDATION & SECOND FLOOR
D-F1'/A-D2/A-D8/D-F8'/A2-8/F3-4/F6-7
B4-5/ B5-6 /A6-B6/ B3'-3/ C3'-D3'/ B6'-C6'
C6'-D6'
FOUNDATION & SECOND FLOOR
F 1'-3 / F 7-8' / B2-3'/ B6'-8 /C2-3' / C6'-8
D2-3' / D6'-8
FOUNDATION & SECOND FLOOR
C4'-4
DESCRIPTION
LENGTH (L x W x H)
SQUARE BEAM
5700 x 300 x 300
QUANTITY 2
LOCATION
DESCRIPTION
LENGTH (L x W x H)
SQUARE BEAM
6000 x 300 x 300
QUANTITY 14
LOCATION
DESCRIPTION
LENGTH (L x W x H)
SQUARE BEAM
7200 x 300 x 300
QUANTITY 8
LOCATION
300
300
300
300
300
300
7200
6000
5700
B9
B10
B11
D4'-6
C4-6 / E4-6 /F4 - 6
E1'-1/ E6-8/
FOUNDATION & SECOND FLOOR
FOUNDATION & SECOND FLOOR
FOUNDATION & SECOND FLOOR
DESCRIPTION
LENGTH (L x W x H)
FLOOR SLAB
3000 x 1000 x 200
QUANTITY 262
LOCATION A2-A4-F4-F2, A6-A8-F8-F6, A4-A6-B6-B4
DESCRIPTION
LENGTH (L x W x H)
FLOOR SLAB
3213 x 1000 x 200
QUANTITY 2
LOCATION GROUND & FIRST E4-E4.5-F4.5-F4
DESCRIPTION
LENGTH (L x W x H)
FLOOR SLAB
3462 x 1000 x 200
QUANTITY 2
LOCATION B4-B4.5-C4.5-C4
DESCRIPTION
LENGTH (L x W x H)
FLOOR SLAB
3000 x 1500 x 200
QUANTITY 12
LOCATION D1-F1.5-F1.5-F1,D8-F9-F9-D8
3462
1000
3000
1500
3000
1000
200
200
200
3213
1000
200
B4-B6-F6-F4
F1
F2
F3
F4
BEAMS
L-SHAPE BEAM SOLID SQUARE BEAM
FLOOR SLABS
39
DESCRIPTION
LENGTH (L x W x H)
SOLID WALL
2700 x 150 x 2900
QUANTITY 4
LOCATION A2-B2,F3-F4,A8-B8,F6-F7
2700
2700
2900
150
DESCRIPTION
LENGTH (L x W x H)
SOLID WALL
2700 x 150 x 2900 - (1200 X 1200)
QUANTITY 6
LOCATION A2-A3,B2-C2,C2-D2,A7-A8,B8-C8.C8-D8
2700
2900
LENGTH (L x W x H) 2700 x 150 x 2900 - (2400 X 1200)
QUANTITY 8
LOCATION
2700
2900
A3-A4,A4-A5,D1-E1,E1-F1,A5-A6,A6-A7
D9-E9,E9-F9
DESCRIPTION SOLID WALL
1200750 750
150 2400 150
150
90012001200900
LENGTH (L x W x H)
SOLID WALL
4200 x 150 x 2900
QUANTITY 2
LOCATION F1-F3,F7-F9
DESCRIPTION
4200
150
2900
4200
150
LENGTH (L x W x H)
SOLID WALL
4200 x 150 x 2900
QUANTITY 2
LOCATION D1-D2,D8-D9
DESCRIPTION
2900
1200
150
1200
LENGTH (L x W x H)
SOLID WALL
4200 x 150 x 2900 - (2400x1200)
QUANTITY 2
LOCATION F1-F3,F7-F9
DESCRIPTION
150
2900
4200
900 2400 900
DESCRIPTION
LENGTH (L x W x H)
SOLID WALL
2700 x 150 x 2700
QUANTITY 35
LOCATION A2-B2,F3-F4,A8-B8,F6-F7, B4-C4,C4-D4
2700
2700
2700
150
DESCRIPTION
LENGTH (L x W x H)
SOLID WALL
2700 x 150 x 2700 - (1200 X 1200)
QUANTITY 12
LOCATION A2-A3,B2-C2,C2-D2,A7-A8,B8-C8.C8-D8
2700
2700
LENGTH (L x W x H) 2700 x 150 x 2700 - (2400 X 1200)
QUANTITY 16
LOCATION
2700
2700
A3-A4,A4-A5,D1-E1,E1-F1,A5-A6,A6-A7
D9-E9,E9-F9
DESCRIPTION SOLID WALL
1200750 750
150 2400 150
150
90012001200900
LENGTH (L x W x H)
SOLID WALL
4200 x 150 x 2700
QUANTITY 22
LOCATION F1-F3,F7-F9,B2-B3,C2-C3,D2-D3
DESCRIPTION
4200
150
2700
150
4200
D4-E4,E4-F4,B6-C6,C6-D6,D6-E6,E6-F6
A5-B5
LENGTH (L x W x H)
SOLID WALL
1200 x 150 x 2700
QUANTITY 2
LOCATION D1-D2.D8-D9
DESCRIPTION
2700
1200
150
1200
LENGTH (L x W x H)
SOLID WALL
2700 x 150 x 2700 - (900X2100)
QUANTITY 12
LOCATION B3-C3,C3-D3,B7-C7,V7-D7
DESCRIPTION
LENGTH (L x W x H)
SOLID WALL
1200 x 150 x 2700 - (1600X2100)
QUANTITY 6
LOCATION B4-B5,B5-B6
DESCRIPTION
LENGTH (L x W x H)
SOLID WALL
1200 x 150 x 2700 - (900X2100)
QUANTITY 6
LOCATION D3-D4,D6-D7
DESCRIPTION
2700
2700
501750 900
150
550 800 550
900
800
2700
2700
150
150900
50 900 250
2700
1200
W1
W2
W3
W4
W5
W6
W7
W8
W9
W10
W11
W12
W13
W14
WALLS
GROUND FLOOR (EXTERIOR) GROUND (INTERIOR) 1ST & 2ND FLOOR (INTERIOR +EXTERIOR)
40
LENGTH (L x W x H)
SOLID WALL
4200 x 150 x 2700 - (2400x1200)
QUANTITY 4
LOCATION F1-F3,F7-F9
DESCRIPTION
2700
4200
150
900 2400 900
DESCRIPTION
LENGTH (L x W x H)
DRY WALLING
1150 x 150 x 2700
QUANTITY 6
LOCATION A/B2-B2,A/B8-B8
1550 1150
2700
150
DESCRIPTION
LENGTH (L x W x H)
DRY WALLING
1150 x 150 x 2700 - (900x2100)
QUANTITY 6
LOCATION A/B3-B3,A/B7-B7
2700
2700
501750 900
150
900
DESCRIPTION
LENGTH (L x W x H)
DRY WALLING
2700 x 150 x 2700 - (900x2100)
QUANTITY 6
LOCATION E3-F3,E7-F7
150900
50 900 200
2700
1150
DESCRIPTION
LENGTH (L x W x H)
DRY WALLING
2700 x 150 x 2700
QUANTITY 30
LOCATION A/B2-A/B3,B2-B3,E3-E4,F3-F4,E4-F4
2700
2700
2700
150
A/B7-A/B8,B7-B8,E6-E7,E6-F6, F6-F7
DESCRIPTION
LENGTH (L x W x H)
SINGLE LEAF WINDOW
1200 x 150 x 1200
QUANTITY 18
LOCATION A2-A3,B2-C2,C2-D2,A7-A8,B8-C8.C8-D8
DESCRIPTION
LENGTH (L x W x H)
DOUBLE LEAF WINDOW
1200 x 150 x 2400
QUANTITY 30
LOCATION A3-A4,A4-A5,D1-E1,E1-F1,A5-A6,A6-A7
D9-E9,E9-F9
150
150
850200
850200
DESCRIPTION
LENGTH (L x W x H)
SINGLE LEAF DOOR
900 x 150 x 2100
QUANTITY 30
LOCATION A/B3-B3,B3-C3,C3-D3,D3-D4,E3-F3
DESCRIPTION
LENGTH (L x W x H)
DOUBLE LEAF DOOR
1600 x 150 x 2100
QUANTITY 6
LOCATION B4-B5,B5-B6
900
900
800
50 1001100 501100
50 501100
1200
2400
900
2100
1800
2100
A/B7-B7,B7-C7,C7-D7,D6-D7,E7-F7
800 800
W15
T1
T2
T3
T4
D3
D1
D2
D4
WALLS
GROUND (INTERIOR) 1ST & 2ND
FLOOR (INTERIOR +EXTERIOR)
TOILET POD DRY WALLING DOORS
ADDITIONAL COMPONENTS
WINDOWS
41
IBS SCORE
42
Elements Areas (m2) / Length (m) IBS Factor Coverage IBS Score
Part 1 : Structural ElementsPart 1 : Structural ElementsPart 1 : Structural ElementsPart 1 : Structural ElementsPart 1 : Structural Elements
GROUND FLOOR AREA
Precast beams + precast slabs + precast columns
FIRST FLOOR AREA
Precast beams + precast slabs + precast columns
SECOND FLOOR AREA
Precast beams + precast slabs + precast columns
ROOF AREA
Prefabricated timber roof truss
Part 1 Total
270m²
270m²
270m²
270m²
1082m²
1.0
1.0
1.0
1.0
270/ 1082
= 0.25
270/ 1082
= 0.25
270/ 1082
= 0.25
270/ 1082
= 0.25
1.0
50(0.25)(1.0)
=12.5
50(0.25)(1.0)
=12.5
50(0.25)(1.0)
=12.5
50(0.25)(1.0)
=12.5
50
Part 2 : Wall SystemsPart 2 : Wall SystemsPart 2 : Wall SystemsPart 2 : Wall SystemsPart 2 : Wall Systems
EXTERNAL WALL
GROUND FLOOR
Precast concrete panels
FIRST FLOOR
Precast concrete panels
SECOND FLOOR
Precast concrete panels
INTERNAL WALL
GROUND FLOOR
Dry Wall System
FIRST FLOOR
Dry Wall System
SECOND FLOOR
Dry Wall System
Part 2 Total
72m
72m
72m
270m
270m
270m
1026m
1.0
1.0
1.0
1.0
1.0
1.0
72/ 1026
= 0.07
72/ 1026
= 0.07
72/ 1026
= 0.07
270/ 1026
= 0.26
270/ 1026
= 0.26
270/ 1026
= 0.26
2.88
20(0.07)(1.0)
= 1.4
20(0.07)(1.0)
= 1.4
20(0.07)(1.0)
= 1.4
20(0.26)(1.0)
= 5.2
20(0.26)(1.0)
= 5.2
20(0.26)(1.0)
= 5.2
19.8
43
Part 3 : Other simplified construction solutions
Complies to MS1064
Part 3 : Other simplified construction solutions
Complies to MS1064
Part 3 : Other simplified construction solutions
Complies to MS1064
Part 3 : Other simplified construction solutions
Complies to MS1064
Part 3 : Other simplified construction solutions
Complies to MS1064
Beams (MS1064 Part 10)
Columns (MS1064 Part 10)
Slabs (MS 1064 Part 10)
Doors and Windows (MS 1064 Part 4)
Vertical repetition of structure
Part 3 total
60%
100%
60%
70%
100%
2
4
2
3
6
17
TOTAL IBS SCORE 86.8
Thus, CIDB had implemented the IBS Score in construction industry to measure the level of IBS usage in building and become part of the main monitor system of the IBS
construction industry. In the Budget 2005, the policies of the usage of IBS components in government building projects were increased from 30 percent currently to 50
percent commencing 2005. Housing developers who utilise IBS components exceeding 50 percent, will be given full exemption on levy imposed by CIDB. Government
requirement 70% of IBS components must be used in government projects. The two mandated policies cover for the housing (100% levy exemption with 50% IBS Score)
and government buildings (0.125% levy exemption with 70% IBS Score).
Since the IBS score for our apartment block is 86.8 > 70 , the levy will be exempted hypothetically.
44
1. Bhaddin Al-Naqshabandi, A study on the construction process (Precast
concrete, In-situ cast concrete, Shoring,
2. Underpinning) Retreived from https://www.slideshare.net/bhaddin/a-study-
on-the-construction-process-precast-concrete-insitu-cast-concrete-shoring-
underpinning on 3th October 2017
3. Retrieved from https://www.slideshare.net/shekhu001/precast-
construction on October 2nd 2017
4. Pujol, Products :Modular and  Industrial Construction : Columns, Retrieved
from http://eng.prefabricatspujol.com/products/modular-and-
industrialised-construction/health-center/columns.html on October 2nd
2017  
5. Hobbithouse Inc,  Glossary of Jointing Methods Retrieved from http://
www.hobbithouseinc.com/personal/woodpics/_joineryterms.htm on
October 2nd 2017
6. Retrieved from https://www.concretenetwork.com/concrete/
foundations.htm on October 1st 2017
7. Foundation Handbook, Construction Details, Retrieved from http://
foundationhandbook.ornl.gov/handbook/section4-1.shtml on October 1st
2017
8. http://preca.in/blog/9-uses-of-hollow-core-slab/
9. https://www.researchgate.net/publication/
225417520_Comparison_between_solid_and_hollow_reinforced_concrete_b
eams
10. http://www.yourhome.gov.au/materials/precast-concrete
11. http://research.iugaza.edu.ps/files/2142.PDF
12. IBSCentre. List of IBS Precast Concrete System Manufacturers [Online].
Available: http://ibsnet.econstruct.com.my/ibsnet_public/manufacturers/
index/page:4/manufact urer.keyword:Precast%20concrete%20system
13. A. Warszawski, Industrialized and Automated Building Systems. London: E &
FN Spon, 1999.
14. https://theconstructor.org/concrete/precast-concrete-process/6272/
REFERENCES

More Related Content

What's hot

Transformation of form
Transformation of formTransformation of form
Transformation of form
Hemant Diyalani
 
Hearst Tower, Manhattan, Dubai.
Hearst Tower, Manhattan, Dubai.Hearst Tower, Manhattan, Dubai.
Hearst Tower, Manhattan, Dubai.
Mayur Waghulde
 
Comparison between early christian and byzantine architecture
Comparison between early christian and byzantine architectureComparison between early christian and byzantine architecture
Comparison between early christian and byzantine architecture
Nguyễn Việt
 
Building technology 3
Building technology 3 Building technology 3
Building technology 3
GrkemDiken
 
Shell structure (basic concept)
Shell structure (basic concept)Shell structure (basic concept)
Shell structure (basic concept)
Ian Toisa
 
Concepts in Architecture
Concepts in ArchitectureConcepts in Architecture
Concepts in Architecture
Piloo Mody College of Architecture
 
Hoa1 lecture 6 early christian architecture
Hoa1 lecture 6 early christian architectureHoa1 lecture 6 early christian architecture
Hoa1 lecture 6 early christian architecture
Carla Faner
 
Circulation
CirculationCirculation
Circulation
Yungchang Yang
 
Basic Theory of Architecture
Basic Theory of Architecture Basic Theory of Architecture
Basic Theory of Architecture
Architecture Faculty
 
Building Technology 1
Building Technology 1Building Technology 1
Building Technology 1
Gertrude Lee
 
Byzantine architecture
 Byzantine architecture Byzantine architecture
Byzantine architectureBinumol Tom
 
History of arch...
History of arch...History of arch...
History of arch...
joannaPG
 
Case Study of Tropical Design of an Architect
Case Study of Tropical Design of an ArchitectCase Study of Tropical Design of an Architect
Case Study of Tropical Design of an Architect
Bryll Edison Par
 
Aluminum partition wall
Aluminum partition wallAluminum partition wall
Aluminum partition wall
Zuber Memon
 
Prehistorical architecture
Prehistorical architecturePrehistorical architecture
Prehistorical architecture
Yungchang Yang
 
Site analysis-example
Site analysis-exampleSite analysis-example
Site analysis-exampleAnu PA
 
Byzantine Architecture
Byzantine ArchitectureByzantine Architecture
Byzantine Architecture
Abhijeet Shinde
 
High-rise structural systems
High-rise structural systemsHigh-rise structural systems
High-rise structural systems
Akshay Revekar
 
Relevance of sociology to architecture
Relevance of sociology to architectureRelevance of sociology to architecture
Relevance of sociology to architecture
Barimah Ntow-kummi
 
Architectural Design Concepts Approaches - كونسيبت التصميم المعمارى و الفكرة ...
Architectural Design Concepts Approaches - كونسيبت التصميم المعمارى و الفكرة ...Architectural Design Concepts Approaches - كونسيبت التصميم المعمارى و الفكرة ...
Architectural Design Concepts Approaches - كونسيبت التصميم المعمارى و الفكرة ...
Galala University
 

What's hot (20)

Transformation of form
Transformation of formTransformation of form
Transformation of form
 
Hearst Tower, Manhattan, Dubai.
Hearst Tower, Manhattan, Dubai.Hearst Tower, Manhattan, Dubai.
Hearst Tower, Manhattan, Dubai.
 
Comparison between early christian and byzantine architecture
Comparison between early christian and byzantine architectureComparison between early christian and byzantine architecture
Comparison between early christian and byzantine architecture
 
Building technology 3
Building technology 3 Building technology 3
Building technology 3
 
Shell structure (basic concept)
Shell structure (basic concept)Shell structure (basic concept)
Shell structure (basic concept)
 
Concepts in Architecture
Concepts in ArchitectureConcepts in Architecture
Concepts in Architecture
 
Hoa1 lecture 6 early christian architecture
Hoa1 lecture 6 early christian architectureHoa1 lecture 6 early christian architecture
Hoa1 lecture 6 early christian architecture
 
Circulation
CirculationCirculation
Circulation
 
Basic Theory of Architecture
Basic Theory of Architecture Basic Theory of Architecture
Basic Theory of Architecture
 
Building Technology 1
Building Technology 1Building Technology 1
Building Technology 1
 
Byzantine architecture
 Byzantine architecture Byzantine architecture
Byzantine architecture
 
History of arch...
History of arch...History of arch...
History of arch...
 
Case Study of Tropical Design of an Architect
Case Study of Tropical Design of an ArchitectCase Study of Tropical Design of an Architect
Case Study of Tropical Design of an Architect
 
Aluminum partition wall
Aluminum partition wallAluminum partition wall
Aluminum partition wall
 
Prehistorical architecture
Prehistorical architecturePrehistorical architecture
Prehistorical architecture
 
Site analysis-example
Site analysis-exampleSite analysis-example
Site analysis-example
 
Byzantine Architecture
Byzantine ArchitectureByzantine Architecture
Byzantine Architecture
 
High-rise structural systems
High-rise structural systemsHigh-rise structural systems
High-rise structural systems
 
Relevance of sociology to architecture
Relevance of sociology to architectureRelevance of sociology to architecture
Relevance of sociology to architecture
 
Architectural Design Concepts Approaches - كونسيبت التصميم المعمارى و الفكرة ...
Architectural Design Concepts Approaches - كونسيبت التصميم المعمارى و الفكرة ...Architectural Design Concepts Approaches - كونسيبت التصميم المعمارى و الفكرة ...
Architectural Design Concepts Approaches - كونسيبت التصميم المعمارى و الفكرة ...
 

Similar to Building Technology 1 (P1)

Building technology report
Building technology reportBuilding technology report
Building technology report
Chong Yi Hui
 
PREFAB CONSTRUCTION .pdf
PREFAB CONSTRUCTION .pdfPREFAB CONSTRUCTION .pdf
PREFAB CONSTRUCTION .pdf
GourhariBiswas1
 
Presentation on MIVAN -- A versatile aluminum formwork construction technique
Presentation on MIVAN -- A versatile aluminum formwork construction techniquePresentation on MIVAN -- A versatile aluminum formwork construction technique
Presentation on MIVAN -- A versatile aluminum formwork construction technique
IEI GSC
 
Chapters-3,4,5.pptx
Chapters-3,4,5.pptxChapters-3,4,5.pptx
Chapters-3,4,5.pptx
ssuserc0bf9b
 
Types of modern construction formwork
Types of modern construction formwork Types of modern construction formwork
Types of modern construction formwork
adarshkaushik6
 
Precast concrete
Precast concretePrecast concrete
Precast concrete
SnehaKothari13
 
CONSTRUCTION METHODS BASICS BTCE-503-18
CONSTRUCTION METHODS BASICSBTCE-503-18CONSTRUCTION METHODS BASICSBTCE-503-18
CONSTRUCTION METHODS BASICS BTCE-503-18
SANJEEV Wazir
 
Case Study: High Rise Buildings
Case Study: High Rise BuildingsCase Study: High Rise Buildings
Case Study: High Rise Buildings
Prasad Thanthratey
 
Site Report
Site Report Site Report
Site Report
Sow Wei Henn
 
PREFABRICATED CONSTRUCTION
PREFABRICATED CONSTRUCTIONPREFABRICATED CONSTRUCTION
PREFABRICATED CONSTRUCTION
Anushka Bhargava
 
JUMP FORM WORK
JUMP FORM WORKJUMP FORM WORK
JUMP FORM WORK
Pranay Kumar Tode
 
Pre engineering building
Pre engineering buildingPre engineering building
Pre engineering building
narayanababu7
 
Portal Frame Construction & Pre Engineered Building System
Portal Frame Construction & Pre Engineered Building SystemPortal Frame Construction & Pre Engineered Building System
Portal Frame Construction & Pre Engineered Building System
Ian Toisa
 
08 - Portal Frame.pptx
08 - Portal Frame.pptx08 - Portal Frame.pptx
08 - Portal Frame.pptx
2022786965
 
PRECAST BUILDING SYSTEM
PRECAST BUILDING SYSTEMPRECAST BUILDING SYSTEM
PRECAST BUILDING SYSTEMSagar Shah
 
Flat Grid / Waffle Slab
Flat Grid / Waffle SlabFlat Grid / Waffle Slab
Flat Grid / Waffle Slab
Akshay Gawade
 
Btech i compressed
Btech i compressedBtech i compressed
Btech i compressed
Weng Chuan
 
Type of high rise building
Type of high rise buildingType of high rise building
Type of high rise building
Zabihullah Nasiri
 
Construction Site Report
Construction Site ReportConstruction Site Report
Construction Site Report
Shao Xun Sean Thun
 
Mivan form wok - aluminium formwork shuttering tecnology
Mivan form wok - aluminium formwork shuttering tecnologyMivan form wok - aluminium formwork shuttering tecnology
Mivan form wok - aluminium formwork shuttering tecnology
sravan kumar chilamakuri
 

Similar to Building Technology 1 (P1) (20)

Building technology report
Building technology reportBuilding technology report
Building technology report
 
PREFAB CONSTRUCTION .pdf
PREFAB CONSTRUCTION .pdfPREFAB CONSTRUCTION .pdf
PREFAB CONSTRUCTION .pdf
 
Presentation on MIVAN -- A versatile aluminum formwork construction technique
Presentation on MIVAN -- A versatile aluminum formwork construction techniquePresentation on MIVAN -- A versatile aluminum formwork construction technique
Presentation on MIVAN -- A versatile aluminum formwork construction technique
 
Chapters-3,4,5.pptx
Chapters-3,4,5.pptxChapters-3,4,5.pptx
Chapters-3,4,5.pptx
 
Types of modern construction formwork
Types of modern construction formwork Types of modern construction formwork
Types of modern construction formwork
 
Precast concrete
Precast concretePrecast concrete
Precast concrete
 
CONSTRUCTION METHODS BASICS BTCE-503-18
CONSTRUCTION METHODS BASICSBTCE-503-18CONSTRUCTION METHODS BASICSBTCE-503-18
CONSTRUCTION METHODS BASICS BTCE-503-18
 
Case Study: High Rise Buildings
Case Study: High Rise BuildingsCase Study: High Rise Buildings
Case Study: High Rise Buildings
 
Site Report
Site Report Site Report
Site Report
 
PREFABRICATED CONSTRUCTION
PREFABRICATED CONSTRUCTIONPREFABRICATED CONSTRUCTION
PREFABRICATED CONSTRUCTION
 
JUMP FORM WORK
JUMP FORM WORKJUMP FORM WORK
JUMP FORM WORK
 
Pre engineering building
Pre engineering buildingPre engineering building
Pre engineering building
 
Portal Frame Construction & Pre Engineered Building System
Portal Frame Construction & Pre Engineered Building SystemPortal Frame Construction & Pre Engineered Building System
Portal Frame Construction & Pre Engineered Building System
 
08 - Portal Frame.pptx
08 - Portal Frame.pptx08 - Portal Frame.pptx
08 - Portal Frame.pptx
 
PRECAST BUILDING SYSTEM
PRECAST BUILDING SYSTEMPRECAST BUILDING SYSTEM
PRECAST BUILDING SYSTEM
 
Flat Grid / Waffle Slab
Flat Grid / Waffle SlabFlat Grid / Waffle Slab
Flat Grid / Waffle Slab
 
Btech i compressed
Btech i compressedBtech i compressed
Btech i compressed
 
Type of high rise building
Type of high rise buildingType of high rise building
Type of high rise building
 
Construction Site Report
Construction Site ReportConstruction Site Report
Construction Site Report
 
Mivan form wok - aluminium formwork shuttering tecnology
Mivan form wok - aluminium formwork shuttering tecnologyMivan form wok - aluminium formwork shuttering tecnology
Mivan form wok - aluminium formwork shuttering tecnology
 

More from Nicole Foo

Theories of Urbanism
Theories of UrbanismTheories of Urbanism
Theories of Urbanism
Nicole Foo
 
Theories of Urbanism
Theories of Urbanism Theories of Urbanism
Theories of Urbanism
Nicole Foo
 
Building Science 2 (P2): Intergration Project
Building Science 2 (P2): Intergration ProjectBuilding Science 2 (P2): Intergration Project
Building Science 2 (P2): Intergration Project
Nicole Foo
 
Building Science 2 : A Case Study on Acoustic Design
Building Science 2 : A Case Study on Acoustic DesignBuilding Science 2 : A Case Study on Acoustic Design
Building Science 2 : A Case Study on Acoustic Design
Nicole Foo
 
Pitt Street - Asian Architecture
Pitt Street - Asian ArchitecturePitt Street - Asian Architecture
Pitt Street - Asian Architecture
Nicole Foo
 
Building Structure
Building Structure Building Structure
Building Structure
Nicole Foo
 

More from Nicole Foo (6)

Theories of Urbanism
Theories of UrbanismTheories of Urbanism
Theories of Urbanism
 
Theories of Urbanism
Theories of Urbanism Theories of Urbanism
Theories of Urbanism
 
Building Science 2 (P2): Intergration Project
Building Science 2 (P2): Intergration ProjectBuilding Science 2 (P2): Intergration Project
Building Science 2 (P2): Intergration Project
 
Building Science 2 : A Case Study on Acoustic Design
Building Science 2 : A Case Study on Acoustic DesignBuilding Science 2 : A Case Study on Acoustic Design
Building Science 2 : A Case Study on Acoustic Design
 
Pitt Street - Asian Architecture
Pitt Street - Asian ArchitecturePitt Street - Asian Architecture
Pitt Street - Asian Architecture
 
Building Structure
Building Structure Building Structure
Building Structure
 

Recently uploaded

一比一原版(UAL毕业证书)伦敦艺术大学毕业证成绩单如何办理
一比一原版(UAL毕业证书)伦敦艺术大学毕业证成绩单如何办理一比一原版(UAL毕业证书)伦敦艺术大学毕业证成绩单如何办理
一比一原版(UAL毕业证书)伦敦艺术大学毕业证成绩单如何办理
708pb191
 
RTUYUIJKLDSADAGHBDJNKSMAL,D
RTUYUIJKLDSADAGHBDJNKSMAL,DRTUYUIJKLDSADAGHBDJNKSMAL,D
RTUYUIJKLDSADAGHBDJNKSMAL,D
cy0krjxt
 
一比一原版(MMU毕业证书)曼彻斯特城市大学毕业证成绩单如何办理
一比一原版(MMU毕业证书)曼彻斯特城市大学毕业证成绩单如何办理一比一原版(MMU毕业证书)曼彻斯特城市大学毕业证成绩单如何办理
一比一原版(MMU毕业证书)曼彻斯特城市大学毕业证成绩单如何办理
7sd8fier
 
Borys Sutkowski portfolio interior design
Borys Sutkowski portfolio interior designBorys Sutkowski portfolio interior design
Borys Sutkowski portfolio interior design
boryssutkowski
 
一比一原版(LSE毕业证书)伦敦政治经济学院毕业证成绩单如何办理
一比一原版(LSE毕业证书)伦敦政治经济学院毕业证成绩单如何办理一比一原版(LSE毕业证书)伦敦政治经济学院毕业证成绩单如何办理
一比一原版(LSE毕业证书)伦敦政治经济学院毕业证成绩单如何办理
jyz59f4j
 
一比一原版(NCL毕业证书)纽卡斯尔大学毕业证成绩单如何办理
一比一原版(NCL毕业证书)纽卡斯尔大学毕业证成绩单如何办理一比一原版(NCL毕业证书)纽卡斯尔大学毕业证成绩单如何办理
一比一原版(NCL毕业证书)纽卡斯尔大学毕业证成绩单如何办理
7sd8fier
 
一比一原版(UCB毕业证书)伯明翰大学学院毕业证成绩单如何办理
一比一原版(UCB毕业证书)伯明翰大学学院毕业证成绩单如何办理一比一原版(UCB毕业证书)伯明翰大学学院毕业证成绩单如何办理
一比一原版(UCB毕业证书)伯明翰大学学院毕业证成绩单如何办理
h7j5io0
 
Portfolio.pdf
Portfolio.pdfPortfolio.pdf
Portfolio.pdf
garcese
 
Design Thinking Design thinking Design thinking
Design Thinking Design thinking Design thinkingDesign Thinking Design thinking Design thinking
Design Thinking Design thinking Design thinking
cy0krjxt
 
一比一原版(RHUL毕业证书)伦敦大学皇家霍洛威学院毕业证如何办理
一比一原版(RHUL毕业证书)伦敦大学皇家霍洛威学院毕业证如何办理一比一原版(RHUL毕业证书)伦敦大学皇家霍洛威学院毕业证如何办理
一比一原版(RHUL毕业证书)伦敦大学皇家霍洛威学院毕业证如何办理
9a93xvy
 
Research 20 slides Amelia gavryliuks.pdf
Research 20 slides Amelia gavryliuks.pdfResearch 20 slides Amelia gavryliuks.pdf
Research 20 slides Amelia gavryliuks.pdf
ameli25062005
 
Design Thinking Design thinking Design thinking
Design Thinking Design thinking Design thinkingDesign Thinking Design thinking Design thinking
Design Thinking Design thinking Design thinking
cy0krjxt
 
Book Formatting: Quality Control Checks for Designers
Book Formatting: Quality Control Checks for DesignersBook Formatting: Quality Control Checks for Designers
Book Formatting: Quality Control Checks for Designers
Confidence Ago
 
一比一原版(BU毕业证书)伯恩茅斯大学毕业证成绩单如何办理
一比一原版(BU毕业证书)伯恩茅斯大学毕业证成绩单如何办理一比一原版(BU毕业证书)伯恩茅斯大学毕业证成绩单如何办理
一比一原版(BU毕业证书)伯恩茅斯大学毕业证成绩单如何办理
h7j5io0
 
White wonder, Work developed by Eva Tschopp
White wonder, Work developed by Eva TschoppWhite wonder, Work developed by Eva Tschopp
White wonder, Work developed by Eva Tschopp
Mansi Shah
 
20 slides of research movie and artists .pdf
20 slides of research movie and artists .pdf20 slides of research movie and artists .pdf
20 slides of research movie and artists .pdf
ameli25062005
 
一比一原版(UNUK毕业证书)诺丁汉大学毕业证如何办理
一比一原版(UNUK毕业证书)诺丁汉大学毕业证如何办理一比一原版(UNUK毕业证书)诺丁汉大学毕业证如何办理
一比一原版(UNUK毕业证书)诺丁汉大学毕业证如何办理
7sd8fier
 
National-Learning-Camp 2024 deped....pptx
National-Learning-Camp 2024 deped....pptxNational-Learning-Camp 2024 deped....pptx
National-Learning-Camp 2024 deped....pptx
AlecAnidul
 
Common Designing Mistakes and How to avoid them
Common Designing Mistakes and How to avoid themCommon Designing Mistakes and How to avoid them
Common Designing Mistakes and How to avoid them
madhavlakhanpal29
 
一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理
一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理
一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理
smpc3nvg
 

Recently uploaded (20)

一比一原版(UAL毕业证书)伦敦艺术大学毕业证成绩单如何办理
一比一原版(UAL毕业证书)伦敦艺术大学毕业证成绩单如何办理一比一原版(UAL毕业证书)伦敦艺术大学毕业证成绩单如何办理
一比一原版(UAL毕业证书)伦敦艺术大学毕业证成绩单如何办理
 
RTUYUIJKLDSADAGHBDJNKSMAL,D
RTUYUIJKLDSADAGHBDJNKSMAL,DRTUYUIJKLDSADAGHBDJNKSMAL,D
RTUYUIJKLDSADAGHBDJNKSMAL,D
 
一比一原版(MMU毕业证书)曼彻斯特城市大学毕业证成绩单如何办理
一比一原版(MMU毕业证书)曼彻斯特城市大学毕业证成绩单如何办理一比一原版(MMU毕业证书)曼彻斯特城市大学毕业证成绩单如何办理
一比一原版(MMU毕业证书)曼彻斯特城市大学毕业证成绩单如何办理
 
Borys Sutkowski portfolio interior design
Borys Sutkowski portfolio interior designBorys Sutkowski portfolio interior design
Borys Sutkowski portfolio interior design
 
一比一原版(LSE毕业证书)伦敦政治经济学院毕业证成绩单如何办理
一比一原版(LSE毕业证书)伦敦政治经济学院毕业证成绩单如何办理一比一原版(LSE毕业证书)伦敦政治经济学院毕业证成绩单如何办理
一比一原版(LSE毕业证书)伦敦政治经济学院毕业证成绩单如何办理
 
一比一原版(NCL毕业证书)纽卡斯尔大学毕业证成绩单如何办理
一比一原版(NCL毕业证书)纽卡斯尔大学毕业证成绩单如何办理一比一原版(NCL毕业证书)纽卡斯尔大学毕业证成绩单如何办理
一比一原版(NCL毕业证书)纽卡斯尔大学毕业证成绩单如何办理
 
一比一原版(UCB毕业证书)伯明翰大学学院毕业证成绩单如何办理
一比一原版(UCB毕业证书)伯明翰大学学院毕业证成绩单如何办理一比一原版(UCB毕业证书)伯明翰大学学院毕业证成绩单如何办理
一比一原版(UCB毕业证书)伯明翰大学学院毕业证成绩单如何办理
 
Portfolio.pdf
Portfolio.pdfPortfolio.pdf
Portfolio.pdf
 
Design Thinking Design thinking Design thinking
Design Thinking Design thinking Design thinkingDesign Thinking Design thinking Design thinking
Design Thinking Design thinking Design thinking
 
一比一原版(RHUL毕业证书)伦敦大学皇家霍洛威学院毕业证如何办理
一比一原版(RHUL毕业证书)伦敦大学皇家霍洛威学院毕业证如何办理一比一原版(RHUL毕业证书)伦敦大学皇家霍洛威学院毕业证如何办理
一比一原版(RHUL毕业证书)伦敦大学皇家霍洛威学院毕业证如何办理
 
Research 20 slides Amelia gavryliuks.pdf
Research 20 slides Amelia gavryliuks.pdfResearch 20 slides Amelia gavryliuks.pdf
Research 20 slides Amelia gavryliuks.pdf
 
Design Thinking Design thinking Design thinking
Design Thinking Design thinking Design thinkingDesign Thinking Design thinking Design thinking
Design Thinking Design thinking Design thinking
 
Book Formatting: Quality Control Checks for Designers
Book Formatting: Quality Control Checks for DesignersBook Formatting: Quality Control Checks for Designers
Book Formatting: Quality Control Checks for Designers
 
一比一原版(BU毕业证书)伯恩茅斯大学毕业证成绩单如何办理
一比一原版(BU毕业证书)伯恩茅斯大学毕业证成绩单如何办理一比一原版(BU毕业证书)伯恩茅斯大学毕业证成绩单如何办理
一比一原版(BU毕业证书)伯恩茅斯大学毕业证成绩单如何办理
 
White wonder, Work developed by Eva Tschopp
White wonder, Work developed by Eva TschoppWhite wonder, Work developed by Eva Tschopp
White wonder, Work developed by Eva Tschopp
 
20 slides of research movie and artists .pdf
20 slides of research movie and artists .pdf20 slides of research movie and artists .pdf
20 slides of research movie and artists .pdf
 
一比一原版(UNUK毕业证书)诺丁汉大学毕业证如何办理
一比一原版(UNUK毕业证书)诺丁汉大学毕业证如何办理一比一原版(UNUK毕业证书)诺丁汉大学毕业证如何办理
一比一原版(UNUK毕业证书)诺丁汉大学毕业证如何办理
 
National-Learning-Camp 2024 deped....pptx
National-Learning-Camp 2024 deped....pptxNational-Learning-Camp 2024 deped....pptx
National-Learning-Camp 2024 deped....pptx
 
Common Designing Mistakes and How to avoid them
Common Designing Mistakes and How to avoid themCommon Designing Mistakes and How to avoid them
Common Designing Mistakes and How to avoid them
 
一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理
一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理
一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理
 

Building Technology 1 (P1)

  • 1. 1 TAYLOR’S UNIVERSITY SCHOOL OF ARCHITECTURE, BUILDING AND DESIGN (SABD) BUILDING TECHNOLOGY I BLD 61403 INDUSTRIALIZED BUILDING SYSTEM 320213 MOHAMAD ANWAR B FAUZI 324705 TEO CHIA YEE 3225517 NICOLE FOO SHULI 325069 HARASHADEEP KAUR 321409 DANIAL MAZLAN 325736 ASHROFF B ABD WAHAB TUTOR : M R KH A I ROOL
  • 2. 2 INTRODUCTION ACKNOWLEDGMENT 4 OBJECTIVE 4 PROPOSED IBS SYSTEM PRECAST CONCRETE 5 PREFABRICATED TIMBER 5 BUILDING COMPONENTS PRECAST FOUNDATION 6 PRECAST COLUMNS 6 PRECAST BEAMS 7 PRECAST FLOOR SLAB 7 PRECAST WALLS 8 PRECAST STAIRCASE 8 PREFABRICATED ROOF FRAME 8 JOINING METHODS COLUMN TO COLUMN 9 COLUMN TO BEAM 9 BEAM TO WALL 10 BEAM TO SLAB 10 STAIRS AND CONNECTION 11 TRUSSES TO ROOF BEAM 12 ROOF FINISHES 12 CONTENTS
  • 3. 3 PROCEDURE 13 DRAWINGS 18 SCHEDULE 36 IBS SCORE 41 REFERENCES 44
  • 4. 4 ACKNOWLEDGMENT Various parties have made the completion of this projection possible and hopefully a success. We would like to thank our lecturer Mr Rizal who had provided us with the necessary theory in order to understand the Industrialized Building System (IBS), including organizing field trips for us   More importantly, we would like to thank Mr Khairool our tutor for being willing to answer our questions even outside tutorial-designated hours. Mr Khairool’s suggestions definitely gave us new perspective and made the writing of the report more concise.  I heartily thank the School of Architecture Building and Design (SABD) at Taylor’s University for giving us this opportunity to carry out research on a topic that is going to become very important both locally and internationally when more and more prefabricated forms of construction will be preferred. We are also thankful to and fortunate enough to get constant encouragement, support and guidance from each other as group members, whom, without our various contributions, would not be able to produce a report of quality. OBJECTIVE We would like to determine the many methods of constructing a building out of standardized system known as Industrial Building System (IBS), only very recently implemented in our country. In Malaysia, the prefabrication technology is known as industrialized building system (IBS) which is defined as a complete process system of construction works where almost all the component structures is manufactured onsite or offsite, and the product is transported to the site and to be installed in the high precision coordinate joint as well as achieve high quality works, and accelerate the time of completion of the projects. The benefits of prefabrication helped the Housing Ministries in various countries to fulfill the high demand for housing inMalaysia. Providing affordable homes are becoming a vital issue to meet the increasing demand for houses with the increase in the population growth. The most popular IBS component used in Malaysia is precast components. Over the years, the total number of IBS precast manufacturing has increased from 15 in 2009 to 36 factories in the year 2011.As a group, we would like to demonstrate that creating a structure according to IBS is not impossible , this increasing this upward trend in the usage of IBS systems as it is extremely efficient.
  • 5. 5 PRECAST CONCRETE Our apartment block comprises of a hybrid system ; a combination of precast concrete system as well as a prefabricated timber framing. The prefabricated timber will be used exclusively for the structure of the roof trusses as well as rafters whereas the rest of the structure is precast. This includes the foundation, external and internal walling, flooring, columns and beams, as well as staircase. PREFABRICATED TIMBER Precast concrete is a construction product produced by casting concrete in reusable mould or form which is then cured in a controlled environment, transported to the construction site a lifted to be set into place. A fully precast building is constructed by using various prefabricated elements required in the building structure. PROPOSED IBS SYSTEM ADVANTAGES DISADVANTAGES Quality and strength assured since produced in controlled factory conditions Difficult to produce non-regular organic shapes Quality also easily monitored Requires transportation to site that may be costly Material for production is cheap since material can be bought in bulk Some components are heavy and cranes are required to install Same result in any weather conditions so appropriate mixes are achieved. No setting time and immediate installation can take place. Modularity of components is achieved very quickly Less labour required ADVANTAGES DISADVANTAGES Lower cost than steel if finishes and wood type are not expensive Extra measures like waterproofing must be taken Higher aesthetic value and gives warmer impression especially for residential homes. Subject to rot and quicker decay Do not require extra carpentry space on site Wood is flammable so extra measures must be taken for fire proofing Environmentally friendly material Little limits on design A roof truss consists of one or more triangular units constructed of pieces that are connected by joints. The triangular shape of the truss adds stability and support by distributing weight away from the exterior walls. Timber roof trusses may be used in commercial applications, but they are generally used for residential construction, which is why we considered it for our roof structure.
  • 6. 6 PRECAST FOUNDATION PRECAST COLUMNS BUILDING COMPONENTS Precast columns These can be produced to have either single or multiple story corbel to allow multiple levels of components such as walls and beams to sit on the columns. This reduces installation time. However, we have chosen to utilize single story corbel-columns of solid rectangular section. Precast foundation was economical choice for us as the foundation footing has reinforcement bars and regulators already present inside. Foundation is placed directly on ground and brought to the appropriate height through the use of these regulators (as noted in diagram) No concrete underpinning needs to be poured since the regulators also lift the rebar from the terrain Regulator Our column choice Precast components • Foundation • Columns • Beams • Slabs • Walls • Staircase Prefabricated Timber components • Roof Truss Additional Components • Standardized window size • Standardized door size • Standardized use of railings • Toilet pods
  • 7. 7 PRECAST BEAM PRECAST FLOOR SLABS Hollow core slabs are prestressed concrete elements that are commonly used for floorings in homes and commercial buildings. As the name suggests, this type of slab possesses voids called ‘cores’ that run through its entire length, with the main intention of reducing the overall slab weight. These cores can also be used as service ducts. Steel strands are placed within the slabs running longitudinally as reinforcements, which allows slabs to have long spans without propping. Furthermore, hollow core slabs possess high flexibility in design, and are available with a variety of notches, slots, and reinforcement arrangements. L-Beams/ Spandrel L-beams are prestressed concrete elements that, together with inverted tee-beams, make up a flooring system. They are characterized by the L- shaped cross-section from which the name is derived. Like inverted tee- beams, L-beams provide ledgers for precast slab units to sit on. They are commonly found at the external walls (the edges of the floor unit) or around the staircase. Solid Rectangular Beam Solid Beams are some of the most commonly used type of beams used in both smaller and larger scale construction. These come usually prestressed and in a wide range of dimensions. These may not be conducive when high bending moment is present as the shape is makes it inflexible. We have utilized these in our ground floor whereby it is connection to the pad footing of the foundation. We have used a combination of L-beans and solid beams after many changes to our structure throughout the design process. We had used L-beams for the ground floor whereas the L-shape beams throughout the other floors. We found this shape to be versatile as it suited our design where we needed both walls and slab to sit on the beams. ADVANTAGES DISADVANTAGES Maximum structural efficiency for every slab thickness Expensive transportation to site and erection Variety of shapes and sizes available, with long spans Large and heavy Eliminates ducting work as system components can be hidden Less vibration and strong acoustical performance
  • 8. 8 PRECAST WALLS Our walls are solid rectangular-section walls. Some have prefabricated openings in order to allow for placement of window to be installed on site Cranes will be needed to erect these walls and transportation to site can be quite costly. There are other types of precast walls like ribbed, double tee and mullion0ed but PRECAST STAIRCASE ADVANTAGES DISADVANTAGES Rapid speed of erection Small margin for error Maintaining cleanliness of site as production materials not needed Economics of scale demand regularly shaped buildings Higher quality due to controlled measures taken in factory ROOF FRAME Our roof frame will be constructed with a series of prefabricated timber trusses. The primary shape of the truss is a typical long-bearing truss shape which is ideal for longer spans of roof. Many of the advantages and benefits are similar to that of using prefab timber in general ADVANTAGES DISADVANTAGES Higher quality due to controlled measures taken in factory Can be expensive to transport Can be installed much faster than in-situ stairs Difficult to produce complex shapes like spiral or curve Unlike in situ stairs, precast stairs can be used directly after installation by workers as no drying time is required. The shape of our primary timber truss
  • 9. 9 COLUMN TO COLUMN COLUMN TO BEAM JOINING METHODS Metal bearing plates and embedded anchor bolts are cast into the ends of the columns. After column is mechanically joined, the connection is grouted to ensure full load bearing between elements and to protect metal components from corrosion. With accurate placement, the weld plates are casted into beams and columns respectively. A bearing plate is placed between the beam and column connection. It is used to transfer concentrated compressive forces between the two structural elements. The weld plates are welded after the beams and columns are held into place, this is to fully secure the said connection. Anchor bolts connected to bearing plates COLUMN TO COLUMN COLUMN BEAM METAL BEARING PLATES METAL BEARING PLATES SHIM GROUT CONCRETE ANCHOR BOLT WELD PLATES BEARING PLATES COLUMN TO COLUMN METAL BEARING PLATES METAL BEARING PLATES SHIM GROUT CONCRETE ANCHOR BOLT
  • 10. 10 BEAM TO WALL BEAM TO SLAB Precast walls are casted with connecting rebars left protruding which will eventually connect to the holes casted into beams. After the elements are put into place, the connection is grouted in order to secure its standing. Precast hollow core slabs are placed onto the ledge of the L-shaped beam and then the connection is grouted to hold it into place. Diagram to show how L-beam, hollow core slab and column is connected within our structure
  • 11. 11 STAIRCASE CONNECTIONS Landing to wall connection - The landing slab sits on a RSA (Rolled Steel Angle) that is bolted to the wall. A Structural shim packer is placed between the RSA and landing slab, it serves to level the landing slab before commitment. Stairs to slab connection - The stairs sits on a structural shim packer which sits on the ledge casted into the floor slab. A hole is then bored through the step of the of the stairs and the shim packer and stops when it reaches into the slab. A metal dowel piece is then inserted into the hole and the hole is then sealed by grout. LANDING TO WALL CONNECTION STAIRS TO SLAB CONNECTION FLOOR SLAB FLOOR SLAB CONNECT TO WALL CONNECT TO WALL CONNECT TO WALL LANDING SLAB WALL ANCHOR BOLT RSA (ROLLED STEEL ANGLE) STRUCTURAL SHIM PACKERS (10MM THICK) STAIRS FLOOR SLAB STRUCTURAL SHIM PACKERS (10MM THICK) DOWEL HOLE (30MM DIA.) LANDING TO WALL STAIRS TO SLAB Due to our usage of straight flight staircase, we do not have any integral landing connected at the factory. Hence the two floor slabs and one landing slab are needed Straight flight stairs The connection between the stairs and slab is of a typical notch joint as seen in typical precast stairs Example of notch joint at the upper floor slab
  • 12. 12 TRUSSES TO ROOF BEAM ROOF FINISHES Two metal weld plates sandwiches the wooden rafter and is held together by two-sided bolts. Weld plates are casted into concrete roof beam with accurate placement. After the rafter sits in place on the beam, the weld plates are welded together, the securing its placement allowing the rafter to transfer loads to beam well. Two metal weld plates sandwiches the wooden rafter and is held together by two-sided bolts. Weld plates are casted into concrete roof beam with accurate placement. After the rafter sits in place on the beam, the weld plates are welded together, the securing its placement allowing the rafter to transfer loads to beam well. Example of joining between timber battens and roof tiles
  • 13. 13 PRODUCTION OF PRECAST CONCRETE PIECES PROCEDURE STEP 1 : Producing the reinforced-bar cages for each component needed. Welding is needed to join the parts STEP 2 The reinforced cage is placed inside a mould that is partially complete and usually made of timber. Then the mould is closed up STEP 3 The specified concrete mix is poured into the wooden mould. Sometimes computers replace manual methods in determining the amount needed STEP 4 Compaction of concrete using vibrator to achieve optimum density. High frequency vibrators or pokers may be used. STEP 5 Moving precast into storage area STEP 6 Storage of high quality units in order to prepare to be transported STEP 7 AND 8 Transportation to site is done in a predetermined sequence so construction can take place according to arrangement INSTALLATION PRODUCTION OF PREFABRICATED WOOD FRAME STEP 1 : Custom profiling STEP 2 : Custom milling STEP 3 : Test fit connections STEP 4 : Factory prestaining STEP 5 : Testing structural integrity of joinery STEP 6 : Completion of joinery STEP 7 : Transportation to site
  • 14. 14 STEP 11 STEP 12 STEP 13 STEP 14 Prefabricated pad foundation is placed on top of excavated terrain with the installation of padfooting columns with corbels Rectangular section beams are placed on top of corbels of columns accordingly Hollow core precast slabs are then placed on top of the rectangular beams. For the ground floor, cranes may not be needed to install these Precast walls are then installed on top of beams and floor slabs of the ground floor. Usually a crane is needed to place these with some manual assistance. Toilet pod for ground floor also installed.
  • 15. 15 STEP 5 STEP 11 STEP 7 STEP 8 5 6 7 8 Columns with single story corbel are then placed on top of the pad-footing columns Crane is used to installed precast L shape / Spandrel beams on top of columns Staircase is installed using a crane to connect the ground and first floor landing . A crane will be needed to lift these heavy hollow core slabs on to the beams and columns of the ground floor.
  • 16. 16 STEP 9 STEP 01 STEP 11 STEP 12 9 10 11 12 Repetition of step 4 whereby windows are installed using crane Repetition of step 5 but instead ground floor columns are connection to first floor columns Repetition of step 6 but instead first floor L beams are not placed on to first floor columns Repetition of step 7. This time stairs used to connect first floor to landing of second floor
  • 17. 17 STEP 13 STEP 14 STEP 15 After repeating steps 4 to 6 yet again, beams of the second floor are then placed on to the walls. The roof trusses are then installed on to the beams of the upper floor. Rafters are installed also The roof bracing is installed within the roof truss. Additional components like doors and windows are also installed via crane or manually. In addition, metal railings are installed throughout areas without external wall and by the staircase. 13 14 15
  • 19. 19 BEDROOM 1 TOILET 1 BEDROOM 2 BEDROOM 3 TOILET2 KITCHEN DINING ROOM LIVING ROOM BEDROOM 1 TOILET 1 BEDROOM 2 BEDROOM 3 TOILET 2 KITCHEN DINING ROOM LIVING ROOM UP 1 2 3 4 5 6 7 8 9 A B C D E F ARCHITECTURAL GROUND FLOOR PLAN SCALE 1:100 3000 3000 3000 3000 3000 3000 1500 1500 21000 30003000300030003000 1225 1500 1500 A A
  • 20. 20 BEDROOM 1 TOILET 1 BEDROOM 2 BEDROOM 3 TOILET 2 KITCHEN DINING ROOM LIVING ROOM BEDROOM 1 TOILET 1 BEDROOM 2 BEDROOM 3 TOILET 2 KITCHEN DINING ROOM LIVING ROOM UP ARCHITECTURAL FIRST FLOOR PLAN SCALE 1:100 1 2 3 4 5 6 7 8 9 A B C D E F 3000 3000 3000 3000 3000 3000 1500 1500 21000 30003000300030003000 1225 1500 1500 A A
  • 21. 21 BEDROOM 1 TOILET 1 BEDROOM 2 BEDROOM 3 TOILET 2 KITCHEN DINING ROOM LIVING ROOM BEDROOM 1 TOILET 1 BEDROOM 2 BEDROOM 3 TOILET 2 KITCHEN DINING ROOM LIVING ROOM DOWN ARCHITECTURAL SECOND FLOOR PLAN SCALE 1:100 1 2 3 4 5 6 7 8 9 A B C D E F 3000 3000 3000 3000 3000 3000 1500 1500 21000 30003000300030003000 1225 1500 1500 A A
  • 22. 22 ROOF PLAN SCALE 1:100 1 2 3 4 5 6 7 8 9 A B C D E F 20100 17100 8100 23100 1500 1500 A A
  • 23. 23 1 2 3 4 5 6 7 8 9 A B C D E F STRUCTURAL PLAN SCALE 1:100 21000 30003000300030003000 1500 3000 3000 3000 3000 3000 3000 1500 4500 1500 4500 1500
  • 24. 24 1 2 3 4 5 6 7 8 9 A B C D E F STRUCTURAL FOUNDATION PLAN SCALE 1:100 21000 30003000300030003000 1500 3000 3000 3000 3000 3000 3000 1500 4500 1500 4500 1500
  • 25. 25 1 2 3 4 5 6 7 8 9 A B C D E F STRUCTURAL FLOOR PLAN WITH FLOOR SLABS SCALE 1:100 21000 30003000300030003000 1500 3000 3000 3000 3000 3000 3000 1500 4500 1500 4500 1500 void
  • 26. 26 B5 B5 STRUCTURAL FOUNDATION PLAN (COMPONENTS INDICATED) SCALE 1:100 B6 B6 B6 B6 B5B7 B11 B7 B10 C1 C1 B5 B7 B5 B6 B6 B6 B5 B7 B11B10 B10 B10
  • 27. 27 STRUCTURAL PLAN 1 (INDICATED COMPONENTS) SCALE 1:100 COMMON GROUND FLOOR FIRST FLOOR SECOND FLOOR B5 B5 B2 B2 B6 B6 B11 B7 B10 C1 B10 B10 B10 B6 B6 B4 B7B3 B5 B1 C1 C1 C1 C1 C2C2 C2 C3 C3 C3 C3 C3 C3 C3 C3 C3 C4 C4 C6 C5 C7 C7 C7 C8C8 C8 C7 C9 C9 C9 C9 C9C9 C10 C10 C9 C11 C9 C12 C13 C15 C15 C15 C15 C15 C15 C15 C15 C16 C16 C17 C18 C9 C15 C13 C13 C13 C14 C14 C14
  • 28. 28 STRUCTURAL PLAN 2 (INDICATED COMPONENTS) SCALE 1:100 COMMON GROUND FLOOR FIRST FLOOR SECOND FLOOR W1 W1 W7 W7 W4 W10 W3 W9 W3 W9 W2 W8 W2 W2 W8 W8 W6 W12 W5 W11 W7 W7W7 W7 W7W6 W12 W5 W11 W4 W4 W4 W7
  • 29. 29 void STRUCTURAL PLAN WITH FLOOR SLABS (INDICATED COMPONENTS) SCALE 1:100 F1 F1 F1 F1 F1 F1F1 F1 F1 F1 F1 F1 F1 F1 F1 F2 F2 F3 F3F1 F1 F1 F1 F1F1F1 F1 F4 F4 F4 F4 F1 F1 F1 F1 F1F1 F1F1 F1 F1 F1 F1F1 F1 F1 F1 F1F1 F1 F1F3
  • 30. 30 BEDROOM 1 TOILET 1 BEDROOM 2 BEDROOM 3 TOILET 2 KITCHEN DINING ROOM LIVING ROOM BEDROOM 1 TOILET 1 BEDROOM 2 BEDROOM 3 TOILET 2 KITCHEN DINING ROOM LIVING ROOM UP FLOOR PLAN (INDICATED COMPONENTS) SCALE 1:100 T1T1 T4 T4 T2T2 T3 T3 D1D1 D1D1 D1 D1 D1 D1 D1D1 D2 D2 D3 D3 D3 D3 D3 D3 D4 D4 D4 D4 D4 D4D4 D4
  • 31. 31 FRONT ELEVATION SCALE 1:100 1 2 3 4 5 6 7 8 9 3000 3000 3000 3000 3000 3000 1500 1500 21300 340032003000 ROOF LEVEL 1940 GROUND FLOOR LEVEL FIRST FLOOR LEVEL SECOND FLOOR LEVEL
  • 32. 32 SIDE ELEVATION SCALE 1:100 A B C D E F 340032003000 ROOF LEVEL 1940 FIRST FLOOR LEVEL SECOND FLOOR LEVEL GROUND FLOOR LEVEL
  • 33. 33 340032003000 ROOF LEVEL 1940 FIRST FLOOR LEVEL SECOND FLOOR LEVEL GROUND FLOOR LEVEL SECTION A-A SCALE 1:100 ABCDEF
  • 36. 36 DESCRIPTION LENGTH (L x W x H) GROUND FLOOR COLUMNS 300 x 300 x 3400 QUANTITY 24 LOCATION 3400 500200 300 300 300 300 DESCRIPTION LENGTH (L x W x H) QUANTITY LOCATION 300 300 DESCRIPTION LENGTH (L x W x H) QUANTITY LOCATION 300 300 DESCRIPTION LENGTH (L x W x H) QUANTITY LOCATION 300 200 500 3400 300 300 500 200 3400 300 300 500 200 3400 250 100 150 300 150 GROUND FLOOR COLUMNS 300 x 300 x 3400 GROUND FLOOR COLUMNS 300 x 300 x 3400 GROUND FLOOR COLUMNS 300 x 150 x 3400 18 48 12 A2, D1, D3, E1, A8, D7, D9, F 9 A3, A4, F3, A6, A7, F7 A5, B2, B3, B4, B5, C2, C3, D2, E1, B6 B7, B8, C7, C8, D8, E9 C4, D4, C6, D6 DESCRIPTION LENGTH (L x W x H) QUANTITY LOCATION DESCRIPTION LENGTH (L x W x H) QUANTITY LOCATION 300 150 300 150 500 3400 300 150 200 100250 200 300 150 200 250 500 3400 100 GROUND FLOOR COLUMNSGROUND FLOOR COLUMNS 300 x 150 x 3400 GROUND FLOOR COLUMNS 300 x 150 x 3400 6 6 F4, F6 E4, E6 DESCRIPTION LENGTH (L x W x H) FIRST FLOOR COLUMNS QUANTITY LOCATION 300 300 DESCRIPTION LENGTH (L x W x H) QUANTITY LOCATION 300 300 DESCRIPTION LENGTH (L x W x H) QUANTITY LOCATION 300 300 DESCRIPTION LENGTH (L x W x H) QUANTITY LOCATION 300 150 3200 200 300300 500 3200 200 300 300 500 300 300 3200 200 500 3200 200 500 300 150 300250 300 x 300 x 3200 FIRST FLOOR COLUMNS 300 x 300 x 3200 FIRST FLOOR COLUMNS 300 x 300 x 3200 FIRST FLOOR COLUMNS 300 x 300 x 3200 FIRST FLOOR COLUMNSFIRST FLOOR COLUMNS 300 x 150 x 3200 18 24 48 12 A2, D1, D3, E1, A8, D7, D9, F 9 A3, A4, F3, A6, A7, F7 A5, B2, B3, B4, B5, C2, C3, D2, E1, B6 B7, B8, C7, C8, D8, E9 C4, D4, C6, D6 200 DESCRIPTION LENGTH (L x W x H) QUANTITY LOCATION DESCRIPTION LENGTH (L x W x H) QUANTITY LOCATION 300 150 300 150 3200 150 300 250 300 3200 500200 300 250 150300 FIRST FLOOR COLUMNS 300 x 150 x 3200 FIRST FLOOR COLUMNS 300 x 150 x 3200 6 6 F4, F6 E4, E6 C1 C2 C3 C4 C5 C6 C7 C8 C9 C10 C11 C12 COLUMNS GROUND FLOOR COLUMNS FIRST FLOOR COLUMNS
  • 37. 37 DESCRIPTION LENGTH (L x W x H) QUANTITY LOCATION A2, D1, D3, E1, A8, D7, D9, F 9 300 300 DESCRIPTION LENGTH (L x W x H) QUANTITY LOCATION 300 300 DESCRIPTION LENGTH (L x W x H) QUANTITY LOCATION 300 300 DESCRIPTION LENGTH (L x W x H) QUANTITY LOCATION 300 150 300 300 200 3000 3000 200 300 300 3000 200 300300 3000 250 200 300 300 300 300 200 300 300 150 SECOND FLOOR COLUMNS 300 x 300 x 3000 SECOND FLOOR COLUMNS 300 x 300 x 3000 SECOND FLOOR COLUMNS 300 x 300 x 3000 SECOND FLOOR COLUMNS 300 x 150 x 3000 18 24 48 12 A3, A4, F3, A6, A7, F7 A5, B2, B3, B4, B5, C2, C3, D2, E1, B6 B7, B8, C7, C8, D8, E9 C4, D4, C6, D6 DESCRIPTION LENGTH (L x W x H) QUANTITY LOCATION DESCRIPTION LENGTH (L x W x H) QUANTITY LOCATION 300 150 300 150 300 200 250 200 300 150300 3000 3000 250 300 200 100 150300 SECOND FLOOR COLUMNS 300 x 150 x 3000 SECOND FLOOR COLUMNS 300 x 150 x 3000 6 6 F4, F6 E4, E6 C13 C14 C15 C16 C17 C18 COLUMNS SECOND FLOOR COLUMNS
  • 38. 38 DESCRIPTION LENGTH (L x W x W x H) L-SHAPE BEAM 1200 x 300 x 150 x 500 QUANTITY 4 LOCATION DESCRIPTION L - SHAPE BEAM QUANTITY 36 LOCATION DESCRIPTION L - SHAPE BEAM QUANTITY 4 LOCATION DESCRIPTION L - SHAPE BEAM QUANTITY 2 LOCATION LENGTH (L x W x W x H) 2700 x 300 x 150 x 500 LENGTH (L x W x W x H) 4200 x 300 x 150 x 500 LENGTH (L x W x W x H) 6000 x 300 x 150 x 500 1200 2700 4200 6000 500 150 150 500 150 150 500 150 150 500 150 150 B1 B2 B3 B4 D-F1'/A-D2/A-D8/D-F8'/A2-8/F3-4/F6-7 F 1'-3 / F 7-8' D1' - D2 / D8 - D8' GROUND & FIRST FLOOR F 4 - 6 GROUND & FIRST FLOOR GROUND & FIRST FLOOR GROUND & FIRST FLOOR DESCRIPTION LENGTH (L x W x H) SQUARE BEAM 1200 x 300 x 300 QUANTITY 12 LOCATION DESCRIPTION LENGTH (L x W x H) SQUARE BEAM 2700 x 300 x 300 QUANTITY 96 LOCATION DESCRIPTION LENGTH (L x W x H) SQUARE BEAM 4200 x 300 x 300 QUANTITY 28 LOCATION DESCRIPTION LENGTH (L x W x H) SQUARE BEAM 4650 x 300 x 300 QUANTITY 2 LOCATION 1200 300 300 300 300 300 300 300 300 4650 300 4200 300 2700 B5 B7 B8 B6 B3'-4/B6-6'/D1'-D2/D8-D8' FOUNDATION & SECOND FLOOR FOUNDATION & SECOND FLOOR D-F1'/A-D2/A-D8/D-F8'/A2-8/F3-4/F6-7 B4-5/ B5-6 /A6-B6/ B3'-3/ C3'-D3'/ B6'-C6' C6'-D6' FOUNDATION & SECOND FLOOR F 1'-3 / F 7-8' / B2-3'/ B6'-8 /C2-3' / C6'-8 D2-3' / D6'-8 FOUNDATION & SECOND FLOOR C4'-4 DESCRIPTION LENGTH (L x W x H) SQUARE BEAM 5700 x 300 x 300 QUANTITY 2 LOCATION DESCRIPTION LENGTH (L x W x H) SQUARE BEAM 6000 x 300 x 300 QUANTITY 14 LOCATION DESCRIPTION LENGTH (L x W x H) SQUARE BEAM 7200 x 300 x 300 QUANTITY 8 LOCATION 300 300 300 300 300 300 7200 6000 5700 B9 B10 B11 D4'-6 C4-6 / E4-6 /F4 - 6 E1'-1/ E6-8/ FOUNDATION & SECOND FLOOR FOUNDATION & SECOND FLOOR FOUNDATION & SECOND FLOOR DESCRIPTION LENGTH (L x W x H) FLOOR SLAB 3000 x 1000 x 200 QUANTITY 262 LOCATION A2-A4-F4-F2, A6-A8-F8-F6, A4-A6-B6-B4 DESCRIPTION LENGTH (L x W x H) FLOOR SLAB 3213 x 1000 x 200 QUANTITY 2 LOCATION GROUND & FIRST E4-E4.5-F4.5-F4 DESCRIPTION LENGTH (L x W x H) FLOOR SLAB 3462 x 1000 x 200 QUANTITY 2 LOCATION B4-B4.5-C4.5-C4 DESCRIPTION LENGTH (L x W x H) FLOOR SLAB 3000 x 1500 x 200 QUANTITY 12 LOCATION D1-F1.5-F1.5-F1,D8-F9-F9-D8 3462 1000 3000 1500 3000 1000 200 200 200 3213 1000 200 B4-B6-F6-F4 F1 F2 F3 F4 BEAMS L-SHAPE BEAM SOLID SQUARE BEAM FLOOR SLABS
  • 39. 39 DESCRIPTION LENGTH (L x W x H) SOLID WALL 2700 x 150 x 2900 QUANTITY 4 LOCATION A2-B2,F3-F4,A8-B8,F6-F7 2700 2700 2900 150 DESCRIPTION LENGTH (L x W x H) SOLID WALL 2700 x 150 x 2900 - (1200 X 1200) QUANTITY 6 LOCATION A2-A3,B2-C2,C2-D2,A7-A8,B8-C8.C8-D8 2700 2900 LENGTH (L x W x H) 2700 x 150 x 2900 - (2400 X 1200) QUANTITY 8 LOCATION 2700 2900 A3-A4,A4-A5,D1-E1,E1-F1,A5-A6,A6-A7 D9-E9,E9-F9 DESCRIPTION SOLID WALL 1200750 750 150 2400 150 150 90012001200900 LENGTH (L x W x H) SOLID WALL 4200 x 150 x 2900 QUANTITY 2 LOCATION F1-F3,F7-F9 DESCRIPTION 4200 150 2900 4200 150 LENGTH (L x W x H) SOLID WALL 4200 x 150 x 2900 QUANTITY 2 LOCATION D1-D2,D8-D9 DESCRIPTION 2900 1200 150 1200 LENGTH (L x W x H) SOLID WALL 4200 x 150 x 2900 - (2400x1200) QUANTITY 2 LOCATION F1-F3,F7-F9 DESCRIPTION 150 2900 4200 900 2400 900 DESCRIPTION LENGTH (L x W x H) SOLID WALL 2700 x 150 x 2700 QUANTITY 35 LOCATION A2-B2,F3-F4,A8-B8,F6-F7, B4-C4,C4-D4 2700 2700 2700 150 DESCRIPTION LENGTH (L x W x H) SOLID WALL 2700 x 150 x 2700 - (1200 X 1200) QUANTITY 12 LOCATION A2-A3,B2-C2,C2-D2,A7-A8,B8-C8.C8-D8 2700 2700 LENGTH (L x W x H) 2700 x 150 x 2700 - (2400 X 1200) QUANTITY 16 LOCATION 2700 2700 A3-A4,A4-A5,D1-E1,E1-F1,A5-A6,A6-A7 D9-E9,E9-F9 DESCRIPTION SOLID WALL 1200750 750 150 2400 150 150 90012001200900 LENGTH (L x W x H) SOLID WALL 4200 x 150 x 2700 QUANTITY 22 LOCATION F1-F3,F7-F9,B2-B3,C2-C3,D2-D3 DESCRIPTION 4200 150 2700 150 4200 D4-E4,E4-F4,B6-C6,C6-D6,D6-E6,E6-F6 A5-B5 LENGTH (L x W x H) SOLID WALL 1200 x 150 x 2700 QUANTITY 2 LOCATION D1-D2.D8-D9 DESCRIPTION 2700 1200 150 1200 LENGTH (L x W x H) SOLID WALL 2700 x 150 x 2700 - (900X2100) QUANTITY 12 LOCATION B3-C3,C3-D3,B7-C7,V7-D7 DESCRIPTION LENGTH (L x W x H) SOLID WALL 1200 x 150 x 2700 - (1600X2100) QUANTITY 6 LOCATION B4-B5,B5-B6 DESCRIPTION LENGTH (L x W x H) SOLID WALL 1200 x 150 x 2700 - (900X2100) QUANTITY 6 LOCATION D3-D4,D6-D7 DESCRIPTION 2700 2700 501750 900 150 550 800 550 900 800 2700 2700 150 150900 50 900 250 2700 1200 W1 W2 W3 W4 W5 W6 W7 W8 W9 W10 W11 W12 W13 W14 WALLS GROUND FLOOR (EXTERIOR) GROUND (INTERIOR) 1ST & 2ND FLOOR (INTERIOR +EXTERIOR)
  • 40. 40 LENGTH (L x W x H) SOLID WALL 4200 x 150 x 2700 - (2400x1200) QUANTITY 4 LOCATION F1-F3,F7-F9 DESCRIPTION 2700 4200 150 900 2400 900 DESCRIPTION LENGTH (L x W x H) DRY WALLING 1150 x 150 x 2700 QUANTITY 6 LOCATION A/B2-B2,A/B8-B8 1550 1150 2700 150 DESCRIPTION LENGTH (L x W x H) DRY WALLING 1150 x 150 x 2700 - (900x2100) QUANTITY 6 LOCATION A/B3-B3,A/B7-B7 2700 2700 501750 900 150 900 DESCRIPTION LENGTH (L x W x H) DRY WALLING 2700 x 150 x 2700 - (900x2100) QUANTITY 6 LOCATION E3-F3,E7-F7 150900 50 900 200 2700 1150 DESCRIPTION LENGTH (L x W x H) DRY WALLING 2700 x 150 x 2700 QUANTITY 30 LOCATION A/B2-A/B3,B2-B3,E3-E4,F3-F4,E4-F4 2700 2700 2700 150 A/B7-A/B8,B7-B8,E6-E7,E6-F6, F6-F7 DESCRIPTION LENGTH (L x W x H) SINGLE LEAF WINDOW 1200 x 150 x 1200 QUANTITY 18 LOCATION A2-A3,B2-C2,C2-D2,A7-A8,B8-C8.C8-D8 DESCRIPTION LENGTH (L x W x H) DOUBLE LEAF WINDOW 1200 x 150 x 2400 QUANTITY 30 LOCATION A3-A4,A4-A5,D1-E1,E1-F1,A5-A6,A6-A7 D9-E9,E9-F9 150 150 850200 850200 DESCRIPTION LENGTH (L x W x H) SINGLE LEAF DOOR 900 x 150 x 2100 QUANTITY 30 LOCATION A/B3-B3,B3-C3,C3-D3,D3-D4,E3-F3 DESCRIPTION LENGTH (L x W x H) DOUBLE LEAF DOOR 1600 x 150 x 2100 QUANTITY 6 LOCATION B4-B5,B5-B6 900 900 800 50 1001100 501100 50 501100 1200 2400 900 2100 1800 2100 A/B7-B7,B7-C7,C7-D7,D6-D7,E7-F7 800 800 W15 T1 T2 T3 T4 D3 D1 D2 D4 WALLS GROUND (INTERIOR) 1ST & 2ND FLOOR (INTERIOR +EXTERIOR) TOILET POD DRY WALLING DOORS ADDITIONAL COMPONENTS WINDOWS
  • 42. 42 Elements Areas (m2) / Length (m) IBS Factor Coverage IBS Score Part 1 : Structural ElementsPart 1 : Structural ElementsPart 1 : Structural ElementsPart 1 : Structural ElementsPart 1 : Structural Elements GROUND FLOOR AREA Precast beams + precast slabs + precast columns FIRST FLOOR AREA Precast beams + precast slabs + precast columns SECOND FLOOR AREA Precast beams + precast slabs + precast columns ROOF AREA Prefabricated timber roof truss Part 1 Total 270m² 270m² 270m² 270m² 1082m² 1.0 1.0 1.0 1.0 270/ 1082 = 0.25 270/ 1082 = 0.25 270/ 1082 = 0.25 270/ 1082 = 0.25 1.0 50(0.25)(1.0) =12.5 50(0.25)(1.0) =12.5 50(0.25)(1.0) =12.5 50(0.25)(1.0) =12.5 50 Part 2 : Wall SystemsPart 2 : Wall SystemsPart 2 : Wall SystemsPart 2 : Wall SystemsPart 2 : Wall Systems EXTERNAL WALL GROUND FLOOR Precast concrete panels FIRST FLOOR Precast concrete panels SECOND FLOOR Precast concrete panels INTERNAL WALL GROUND FLOOR Dry Wall System FIRST FLOOR Dry Wall System SECOND FLOOR Dry Wall System Part 2 Total 72m 72m 72m 270m 270m 270m 1026m 1.0 1.0 1.0 1.0 1.0 1.0 72/ 1026 = 0.07 72/ 1026 = 0.07 72/ 1026 = 0.07 270/ 1026 = 0.26 270/ 1026 = 0.26 270/ 1026 = 0.26 2.88 20(0.07)(1.0) = 1.4 20(0.07)(1.0) = 1.4 20(0.07)(1.0) = 1.4 20(0.26)(1.0) = 5.2 20(0.26)(1.0) = 5.2 20(0.26)(1.0) = 5.2 19.8
  • 43. 43 Part 3 : Other simplified construction solutions Complies to MS1064 Part 3 : Other simplified construction solutions Complies to MS1064 Part 3 : Other simplified construction solutions Complies to MS1064 Part 3 : Other simplified construction solutions Complies to MS1064 Part 3 : Other simplified construction solutions Complies to MS1064 Beams (MS1064 Part 10) Columns (MS1064 Part 10) Slabs (MS 1064 Part 10) Doors and Windows (MS 1064 Part 4) Vertical repetition of structure Part 3 total 60% 100% 60% 70% 100% 2 4 2 3 6 17 TOTAL IBS SCORE 86.8 Thus, CIDB had implemented the IBS Score in construction industry to measure the level of IBS usage in building and become part of the main monitor system of the IBS construction industry. In the Budget 2005, the policies of the usage of IBS components in government building projects were increased from 30 percent currently to 50 percent commencing 2005. Housing developers who utilise IBS components exceeding 50 percent, will be given full exemption on levy imposed by CIDB. Government requirement 70% of IBS components must be used in government projects. The two mandated policies cover for the housing (100% levy exemption with 50% IBS Score) and government buildings (0.125% levy exemption with 70% IBS Score). Since the IBS score for our apartment block is 86.8 > 70 , the levy will be exempted hypothetically.
  • 44. 44 1. Bhaddin Al-Naqshabandi, A study on the construction process (Precast concrete, In-situ cast concrete, Shoring, 2. Underpinning) Retreived from https://www.slideshare.net/bhaddin/a-study- on-the-construction-process-precast-concrete-insitu-cast-concrete-shoring- underpinning on 3th October 2017 3. Retrieved from https://www.slideshare.net/shekhu001/precast- construction on October 2nd 2017 4. Pujol, Products :Modular and  Industrial Construction : Columns, Retrieved from http://eng.prefabricatspujol.com/products/modular-and- industrialised-construction/health-center/columns.html on October 2nd 2017   5. Hobbithouse Inc,  Glossary of Jointing Methods Retrieved from http:// www.hobbithouseinc.com/personal/woodpics/_joineryterms.htm on October 2nd 2017 6. Retrieved from https://www.concretenetwork.com/concrete/ foundations.htm on October 1st 2017 7. Foundation Handbook, Construction Details, Retrieved from http:// foundationhandbook.ornl.gov/handbook/section4-1.shtml on October 1st 2017 8. http://preca.in/blog/9-uses-of-hollow-core-slab/ 9. https://www.researchgate.net/publication/ 225417520_Comparison_between_solid_and_hollow_reinforced_concrete_b eams 10. http://www.yourhome.gov.au/materials/precast-concrete 11. http://research.iugaza.edu.ps/files/2142.PDF 12. IBSCentre. List of IBS Precast Concrete System Manufacturers [Online]. Available: http://ibsnet.econstruct.com.my/ibsnet_public/manufacturers/ index/page:4/manufact urer.keyword:Precast%20concrete%20system 13. A. Warszawski, Industrialized and Automated Building Systems. London: E & FN Spon, 1999. 14. https://theconstructor.org/concrete/precast-concrete-process/6272/ REFERENCES