SlideShare a Scribd company logo
Horseshoe Casino Construction
Cincinnati, OH
Ever wanted a tour of a construction site
for a concrete structure?
Don’t just stare at the skyline, come on
and take a closer look…
Often, parking garages have one or more levels below grade, so
excavation is a big part of the project, and occurs before work on
the structure ever begins.
Excavation on this project went down more than 50 feet in some locations.
At RedBuilt's facility in Delaware, OH, form
tables were fabricated on a leveled jig in a
climate-controlled environment.
This can improve safety and productivity during
form table fabrication, and can have a
substantial impact on the consistency and
quality of workmanship in building the forms.
Just-in time delivery of form tables can be arranged
so that material arrives on the truck bed ready to
be moved immediately onto the shoring towers.
Tables can be moved in stacks directly to the
shoring, either by crane or by forklift.
Preattached dunnage simplifies movement and
stacking of tables.
Tables can then be set into place one at a time and
aligned by workers using the steel beam forms to
access tables.
I-Joists for the deck form are often supported
by a steel W8x10.
This configuration works well where the I-Joists
cantilever out beyond the supporting member,
because full bearing can be consistently
achieved when slight changes in table length
occur (small plan changes to beam layout,
ramp areas, etc.).
When a table is set adjacent to an already installed
table, they need to be butted tight. Plyform is typically
cantilevered past the last joist, and the cantilevered
edge of the plyform is supported by leading joist of the
prior table.
It is common to butt the plyform sheets directly over
the center of the flange on the leading joist. A 2x4 is
often used to stiffen and align the cantilevered plyform.
Protective guardrailing may either be mounted to the beam forms—as
shown here—or may be directly attached to the deck form tables.
While parking garages are often notorious for their low ceiling profiles, the
system can also be used similarly where ceiling height is much higher. In cases
like this, additional shoring is required.
Alignment of the forming tables can
help determine the aesthetics of the
beam-to-slab intersection.
Table length, table squareness and
installation of tables are important
in order to get consistent
aesthetics here.
Construction on the Horseshoe Casino continues
with the Cincinnati skyline in the background.
Since RedForm I-Joists are available in depths up
to 20” and can be manufactured with camber, they
can often be used for up to 30’ bay widths to carry
slabs without any center supports.
This can make for a very clean jobsite that is fast
and efficient for both the formwork contractor and
subsequent trades.
When a perpendicular beam runs through the
building, steel beam forms can be run parallel to
the form deck tables. This may require additional
detailing to support the adjacent deck table(s) and
transition from the I-Joists to the steel beam form.
Once forming tables are placed, setting of post tensioning cables and rebar
can begin.
Alignment of adjacent tables can be important to maintain
aesthetics of the finished slab and to prevent mortar
leakage that can bind to the underside of the formwork.
The deck panel inserts are attached to a threaded rod
that is used to temporarily support the formwork tables
during the stripping process.
The inserts shown here are cast into the concrete slab.
Fabrication of the beam’s rebar
cage can be simplified by building
it above the deck.
Once the rebar cage is fabricated above the
deck, it can be dropped down into the beam form.
Now the “real fun” begins. Concrete is now ready to be placed on the formed-out
deck. Beams and slabs are cast together in the same pour.
During an active pour, workers move concrete out
to prevent it from piling up in one area.
Relatively uniform placement of concrete during
the pour can help prevent undue stress or
deflection on forming and shoring below.
After the concrete slab has been poured, leveled
and screened, the concrete is allowed to cure
undisturbed until the concrete has gained sufficient
strength to carry its own weight.
On larger projects, it is common to pour a portion of each deck level.
The subsequent pour is then connected to the prior pour through rebar
and stressing tendons.
Once concrete has obtained enough strength to be self-supporting,
the forming and shoring can be removed.
Here, the shoring and steel beam form are being removed first. The
deck form is now being held in place by the anchor bolt inserted into
the concrete slab.
Reshoring will be added per the reshoring plan prior to placement of
concrete at the next level.
Tables hang from the anchor bolt in the slab until they
are ready to be dropped and relocated. Here the forklift
driver uses a "stripping truss" to lower the table.
Quality of the finished concrete structure can be affected by the quality and
condition of forming materials used, fabrication and installation of tables,
form maintenance, handling and inspection.
Depending on the project, some imperfections in the concrete are
permitted to an extent, but some require repair work to meet project
requirements.
Once the deck is poured, fabrication of rebar cages and formwork for columns
on the next level can begin.

More Related Content

What's hot

Construction joint for rigid pavement
Construction joint for rigid pavementConstruction joint for rigid pavement
Construction joint for rigid pavement
Mai Azuna
 
Steel structures
Steel structuresSteel structures
Steel structures
Sukhdarshan Singh
 
Measurements in construction
Measurements in constructionMeasurements in construction
Measurements in construction
EVERSENDAI ENGINEERING (L.L.C.)
 
Contruction Technology Report (Scaffolding)
Contruction Technology Report (Scaffolding)Contruction Technology Report (Scaffolding)
Contruction Technology Report (Scaffolding)
ZIyeeTan
 
SCAFFOLDING SHORING & UNDERPINNING
SCAFFOLDING SHORING & UNDERPINNINGSCAFFOLDING SHORING & UNDERPINNING
SCAFFOLDING SHORING & UNDERPINNING
VISHNU VIJAYAN
 
Kavya12
Kavya12Kavya12
Kavya12
Karthi Kavya
 
SAR_OCTOBER_2014_LCP
SAR_OCTOBER_2014_LCPSAR_OCTOBER_2014_LCP
SAR_OCTOBER_2014_LCP
Lyndsay Cotton
 
Beam and column and its types in detail
Beam and column and its types in detailBeam and column and its types in detail
Beam and column and its types in detail
Bilal Rahman
 
Scaffolding Shuttering Material Suppliers in India
Scaffolding Shuttering Material Suppliers in IndiaScaffolding Shuttering Material Suppliers in India
Scaffolding Shuttering Material Suppliers in India
Baba Jagta Shuttering
 
Applications of beams and girders
Applications of beams and girdersApplications of beams and girders
Applications of beams and girders
mukundapriya
 
Site report 1
Site report 1Site report 1
Site report 1
Jenny Huoy Miin
 
Slipform construction
Slipform constructionSlipform construction
Slipform construction
tivar rose
 
Site Report
Site ReportSite Report
Site Report
khaikeat16
 
Connection and Bracing
Connection and BracingConnection and Bracing
Connection and Bracing
suddal
 
Scaffolding
ScaffoldingScaffolding
Scaffolding
stooty s
 
Steel structures failure
Steel structures failureSteel structures failure
Steel structures failure
Service_supportAssignment
 
Report
ReportReport
Report
jefrineo96
 
Pilework
PileworkPilework
Pilework
Rajiva Gupta
 
Shaft and resistance of bored piles
Shaft and resistance of bored pilesShaft and resistance of bored piles
Shaft and resistance of bored piles
Rizwan Khurram
 

What's hot (19)

Construction joint for rigid pavement
Construction joint for rigid pavementConstruction joint for rigid pavement
Construction joint for rigid pavement
 
Steel structures
Steel structuresSteel structures
Steel structures
 
Measurements in construction
Measurements in constructionMeasurements in construction
Measurements in construction
 
Contruction Technology Report (Scaffolding)
Contruction Technology Report (Scaffolding)Contruction Technology Report (Scaffolding)
Contruction Technology Report (Scaffolding)
 
SCAFFOLDING SHORING & UNDERPINNING
SCAFFOLDING SHORING & UNDERPINNINGSCAFFOLDING SHORING & UNDERPINNING
SCAFFOLDING SHORING & UNDERPINNING
 
Kavya12
Kavya12Kavya12
Kavya12
 
SAR_OCTOBER_2014_LCP
SAR_OCTOBER_2014_LCPSAR_OCTOBER_2014_LCP
SAR_OCTOBER_2014_LCP
 
Beam and column and its types in detail
Beam and column and its types in detailBeam and column and its types in detail
Beam and column and its types in detail
 
Scaffolding Shuttering Material Suppliers in India
Scaffolding Shuttering Material Suppliers in IndiaScaffolding Shuttering Material Suppliers in India
Scaffolding Shuttering Material Suppliers in India
 
Applications of beams and girders
Applications of beams and girdersApplications of beams and girders
Applications of beams and girders
 
Site report 1
Site report 1Site report 1
Site report 1
 
Slipform construction
Slipform constructionSlipform construction
Slipform construction
 
Site Report
Site ReportSite Report
Site Report
 
Connection and Bracing
Connection and BracingConnection and Bracing
Connection and Bracing
 
Scaffolding
ScaffoldingScaffolding
Scaffolding
 
Steel structures failure
Steel structures failureSteel structures failure
Steel structures failure
 
Report
ReportReport
Report
 
Pilework
PileworkPilework
Pilework
 
Shaft and resistance of bored piles
Shaft and resistance of bored pilesShaft and resistance of bored piles
Shaft and resistance of bored piles
 

Viewers also liked

Skillaware presentazione italia agosto 2015
Skillaware presentazione italia agosto 2015Skillaware presentazione italia agosto 2015
Skillaware presentazione italia agosto 2015
Skillaware™ Company of sedApta Group
 
SedApta automotive case study
SedApta automotive case studySedApta automotive case study
SedApta automotive case study
Skillaware™ Company of sedApta Group
 
Skillaware Intro slide deck - U.S. launch
Skillaware Intro slide deck - U.S. launchSkillaware Intro slide deck - U.S. launch
Skillaware Intro slide deck - U.S. launch
Skillaware™ Company of sedApta Group
 
October trends
October trends October trends
ΜΕΡΗ ΣΥΜΒΑΤΙΚΟΥ ΣΥΣΤΗΜΑΤΟΣ ΤΡΟΦΟΔΟΣΙΑΣ ΒΕΝΖΙΝΟΚΙΝΗΤΗΡΑ ΜΙΚΡΟΔΙΔΑΣΚΑΛΙΑ
ΜΕΡΗ ΣΥΜΒΑΤΙΚΟΥ ΣΥΣΤΗΜΑΤΟΣ ΤΡΟΦΟΔΟΣΙΑΣ ΒΕΝΖΙΝΟΚΙΝΗΤΗΡΑ ΜΙΚΡΟΔΙΔΑΣΚΑΛΙΑΜΕΡΗ ΣΥΜΒΑΤΙΚΟΥ ΣΥΣΤΗΜΑΤΟΣ ΤΡΟΦΟΔΟΣΙΑΣ ΒΕΝΖΙΝΟΚΙΝΗΤΗΡΑ ΜΙΚΡΟΔΙΔΑΣΚΑΛΙΑ
ΜΕΡΗ ΣΥΜΒΑΤΙΚΟΥ ΣΥΣΤΗΜΑΤΟΣ ΤΡΟΦΟΔΟΣΙΑΣ ΒΕΝΖΙΝΟΚΙΝΗΤΗΡΑ ΜΙΚΡΟΔΙΔΑΣΚΑΛΙΑ
gatziosk
 
麥肯錫教我的思考武器心得摘錄
麥肯錫教我的思考武器心得摘錄麥肯錫教我的思考武器心得摘錄
麥肯錫教我的思考武器心得摘錄
Shannon Wu
 
ΕΚΚΕΝΤΡΟΦΟΡΟΣ ΜΙΚΡΟΔΙΔΑΣΚΑΛΙΑ
ΕΚΚΕΝΤΡΟΦΟΡΟΣ ΜΙΚΡΟΔΙΔΑΣΚΑΛΙΑΕΚΚΕΝΤΡΟΦΟΡΟΣ ΜΙΚΡΟΔΙΔΑΣΚΑΛΙΑ
ΕΚΚΕΝΤΡΟΦΟΡΟΣ ΜΙΚΡΟΔΙΔΑΣΚΑΛΙΑ
gatziosk
 
portfoliolayouts
portfoliolayoutsportfoliolayouts
portfoliolayouts
Hannah Hennessy
 
Affordable Care Act 101
Affordable Care Act 101Affordable Care Act 101
Affordable Care Act 101
emagnuson11
 
Market Trends - What's important to Top Talent in Asia
Market Trends - What's important to Top Talent in AsiaMarket Trends - What's important to Top Talent in Asia
Market Trends - What's important to Top Talent in Asia
mrakhra
 
November trends
November trendsNovember trends
MOOC ITSMF España "Gestión de Servicios": Introducción al Service Desk y Gest...
MOOC ITSMF España "Gestión de Servicios": Introducción al Service Desk y Gest...MOOC ITSMF España "Gestión de Servicios": Introducción al Service Desk y Gest...
MOOC ITSMF España "Gestión de Servicios": Introducción al Service Desk y Gest...
Gabriel Martínez Martínez
 
Tendencias en un Service Desk (Jornadas de Excelencia Virtuales ITSM (JEVi) 2...
Tendencias en un Service Desk (Jornadas de Excelencia Virtuales ITSM (JEVi) 2...Tendencias en un Service Desk (Jornadas de Excelencia Virtuales ITSM (JEVi) 2...
Tendencias en un Service Desk (Jornadas de Excelencia Virtuales ITSM (JEVi) 2...
Gabriel Martínez Martínez
 
jnk
jnkjnk
September trends
September trendsSeptember trends
208 class procedures
208 class procedures208 class procedures
208 class procedures
chandlerrowland
 
Rehabilitating Homes Immersive Project
Rehabilitating Homes Immersive ProjectRehabilitating Homes Immersive Project
Rehabilitating Homes Immersive Project
Juan Castillo
 
Rehabilitating Homes Immersive Course Final
Rehabilitating Homes Immersive Course FinalRehabilitating Homes Immersive Course Final
Rehabilitating Homes Immersive Course Final
Juan Castillo
 
case_study-2
case_study-2case_study-2
case_study-2
Alexis Pike
 
Dissertation_Final_Report
Dissertation_Final_ReportDissertation_Final_Report
Dissertation_Final_Report
Tom Day
 

Viewers also liked (20)

Skillaware presentazione italia agosto 2015
Skillaware presentazione italia agosto 2015Skillaware presentazione italia agosto 2015
Skillaware presentazione italia agosto 2015
 
SedApta automotive case study
SedApta automotive case studySedApta automotive case study
SedApta automotive case study
 
Skillaware Intro slide deck - U.S. launch
Skillaware Intro slide deck - U.S. launchSkillaware Intro slide deck - U.S. launch
Skillaware Intro slide deck - U.S. launch
 
October trends
October trends October trends
October trends
 
ΜΕΡΗ ΣΥΜΒΑΤΙΚΟΥ ΣΥΣΤΗΜΑΤΟΣ ΤΡΟΦΟΔΟΣΙΑΣ ΒΕΝΖΙΝΟΚΙΝΗΤΗΡΑ ΜΙΚΡΟΔΙΔΑΣΚΑΛΙΑ
ΜΕΡΗ ΣΥΜΒΑΤΙΚΟΥ ΣΥΣΤΗΜΑΤΟΣ ΤΡΟΦΟΔΟΣΙΑΣ ΒΕΝΖΙΝΟΚΙΝΗΤΗΡΑ ΜΙΚΡΟΔΙΔΑΣΚΑΛΙΑΜΕΡΗ ΣΥΜΒΑΤΙΚΟΥ ΣΥΣΤΗΜΑΤΟΣ ΤΡΟΦΟΔΟΣΙΑΣ ΒΕΝΖΙΝΟΚΙΝΗΤΗΡΑ ΜΙΚΡΟΔΙΔΑΣΚΑΛΙΑ
ΜΕΡΗ ΣΥΜΒΑΤΙΚΟΥ ΣΥΣΤΗΜΑΤΟΣ ΤΡΟΦΟΔΟΣΙΑΣ ΒΕΝΖΙΝΟΚΙΝΗΤΗΡΑ ΜΙΚΡΟΔΙΔΑΣΚΑΛΙΑ
 
麥肯錫教我的思考武器心得摘錄
麥肯錫教我的思考武器心得摘錄麥肯錫教我的思考武器心得摘錄
麥肯錫教我的思考武器心得摘錄
 
ΕΚΚΕΝΤΡΟΦΟΡΟΣ ΜΙΚΡΟΔΙΔΑΣΚΑΛΙΑ
ΕΚΚΕΝΤΡΟΦΟΡΟΣ ΜΙΚΡΟΔΙΔΑΣΚΑΛΙΑΕΚΚΕΝΤΡΟΦΟΡΟΣ ΜΙΚΡΟΔΙΔΑΣΚΑΛΙΑ
ΕΚΚΕΝΤΡΟΦΟΡΟΣ ΜΙΚΡΟΔΙΔΑΣΚΑΛΙΑ
 
portfoliolayouts
portfoliolayoutsportfoliolayouts
portfoliolayouts
 
Affordable Care Act 101
Affordable Care Act 101Affordable Care Act 101
Affordable Care Act 101
 
Market Trends - What's important to Top Talent in Asia
Market Trends - What's important to Top Talent in AsiaMarket Trends - What's important to Top Talent in Asia
Market Trends - What's important to Top Talent in Asia
 
November trends
November trendsNovember trends
November trends
 
MOOC ITSMF España "Gestión de Servicios": Introducción al Service Desk y Gest...
MOOC ITSMF España "Gestión de Servicios": Introducción al Service Desk y Gest...MOOC ITSMF España "Gestión de Servicios": Introducción al Service Desk y Gest...
MOOC ITSMF España "Gestión de Servicios": Introducción al Service Desk y Gest...
 
Tendencias en un Service Desk (Jornadas de Excelencia Virtuales ITSM (JEVi) 2...
Tendencias en un Service Desk (Jornadas de Excelencia Virtuales ITSM (JEVi) 2...Tendencias en un Service Desk (Jornadas de Excelencia Virtuales ITSM (JEVi) 2...
Tendencias en un Service Desk (Jornadas de Excelencia Virtuales ITSM (JEVi) 2...
 
jnk
jnkjnk
jnk
 
September trends
September trendsSeptember trends
September trends
 
208 class procedures
208 class procedures208 class procedures
208 class procedures
 
Rehabilitating Homes Immersive Project
Rehabilitating Homes Immersive ProjectRehabilitating Homes Immersive Project
Rehabilitating Homes Immersive Project
 
Rehabilitating Homes Immersive Course Final
Rehabilitating Homes Immersive Course FinalRehabilitating Homes Immersive Course Final
Rehabilitating Homes Immersive Course Final
 
case_study-2
case_study-2case_study-2
case_study-2
 
Dissertation_Final_Report
Dissertation_Final_ReportDissertation_Final_Report
Dissertation_Final_Report
 

Similar to Horseshoe Casino Construction

Master template for MEC 2014 Workshop
Master template for MEC 2014 WorkshopMaster template for MEC 2014 Workshop
Master template for MEC 2014 Workshop
Mohamed Zayed ,CEng,M.ASCE
 
ALL ABOUT ERECTION
ALL ABOUT ERECTIONALL ABOUT ERECTION
ALL ABOUT ERECTION
AxtellaStructures
 
PRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptxPRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptx
LokeswarSaha1
 
ALL ABOUT ERECTION
ALL ABOUT ERECTIONALL ABOUT ERECTION
ALL ABOUT ERECTION
AxtellaStructures
 
High rise building design
High rise building design High rise building design
High rise building design
Somesh Siddharth
 
PRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptxPRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptx
Vinayak247538
 
High-rise structural systems
High-rise structural systemsHigh-rise structural systems
High-rise structural systems
Akshay Revekar
 
high rise building
high rise buildinghigh rise building
high rise building
Aditya Sanyal
 
Finalppthighrise 130504010636-phpapp02
Finalppthighrise 130504010636-phpapp02Finalppthighrise 130504010636-phpapp02
Finalppthighrise 130504010636-phpapp02
satwik345
 
Tilt up concrete structures
Tilt up concrete structuresTilt up concrete structures
Tilt up concrete structures
MECandPMV
 
High rise structure
High rise structureHigh rise structure
High rise structure
Anuj Singhal
 
Acm Unit 1
Acm Unit 1Acm Unit 1
Acm Unit 1
Aaqib Iqbal
 
PRE-CAST-CONSTRUCTION-Expertcivil.pptx
PRE-CAST-CONSTRUCTION-Expertcivil.pptxPRE-CAST-CONSTRUCTION-Expertcivil.pptx
PRE-CAST-CONSTRUCTION-Expertcivil.pptx
atiulla001
 
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docxRunning Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
toddr4
 
Precast concrete
Precast concretePrecast concrete
Precast concrete
SnehaKothari13
 
Case Study: High Rise Buildings
Case Study: High Rise BuildingsCase Study: High Rise Buildings
Case Study: High Rise Buildings
Prasad Thanthratey
 
RCC Floor
RCC FloorRCC Floor
RCC Floor
Hrishi Desai
 
Flat Grid / Waffle Slab
Flat Grid / Waffle SlabFlat Grid / Waffle Slab
Flat Grid / Waffle Slab
Akshay Gawade
 
SAR_MAY_2015_LCP_PRINTED
SAR_MAY_2015_LCP_PRINTEDSAR_MAY_2015_LCP_PRINTED
SAR_MAY_2015_LCP_PRINTED
Lyndsay Cotton
 
04. superstructure
04. superstructure04. superstructure
04. superstructure
Thien Hee
 

Similar to Horseshoe Casino Construction (20)

Master template for MEC 2014 Workshop
Master template for MEC 2014 WorkshopMaster template for MEC 2014 Workshop
Master template for MEC 2014 Workshop
 
ALL ABOUT ERECTION
ALL ABOUT ERECTIONALL ABOUT ERECTION
ALL ABOUT ERECTION
 
PRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptxPRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptx
 
ALL ABOUT ERECTION
ALL ABOUT ERECTIONALL ABOUT ERECTION
ALL ABOUT ERECTION
 
High rise building design
High rise building design High rise building design
High rise building design
 
PRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptxPRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptx
 
High-rise structural systems
High-rise structural systemsHigh-rise structural systems
High-rise structural systems
 
high rise building
high rise buildinghigh rise building
high rise building
 
Finalppthighrise 130504010636-phpapp02
Finalppthighrise 130504010636-phpapp02Finalppthighrise 130504010636-phpapp02
Finalppthighrise 130504010636-phpapp02
 
Tilt up concrete structures
Tilt up concrete structuresTilt up concrete structures
Tilt up concrete structures
 
High rise structure
High rise structureHigh rise structure
High rise structure
 
Acm Unit 1
Acm Unit 1Acm Unit 1
Acm Unit 1
 
PRE-CAST-CONSTRUCTION-Expertcivil.pptx
PRE-CAST-CONSTRUCTION-Expertcivil.pptxPRE-CAST-CONSTRUCTION-Expertcivil.pptx
PRE-CAST-CONSTRUCTION-Expertcivil.pptx
 
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docxRunning Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
 
Precast concrete
Precast concretePrecast concrete
Precast concrete
 
Case Study: High Rise Buildings
Case Study: High Rise BuildingsCase Study: High Rise Buildings
Case Study: High Rise Buildings
 
RCC Floor
RCC FloorRCC Floor
RCC Floor
 
Flat Grid / Waffle Slab
Flat Grid / Waffle SlabFlat Grid / Waffle Slab
Flat Grid / Waffle Slab
 
SAR_MAY_2015_LCP_PRINTED
SAR_MAY_2015_LCP_PRINTEDSAR_MAY_2015_LCP_PRINTED
SAR_MAY_2015_LCP_PRINTED
 
04. superstructure
04. superstructure04. superstructure
04. superstructure
 

Recently uploaded

Innovation Management Frameworks: Your Guide to Creativity & Innovation
Innovation Management Frameworks: Your Guide to Creativity & InnovationInnovation Management Frameworks: Your Guide to Creativity & Innovation
Innovation Management Frameworks: Your Guide to Creativity & Innovation
Operational Excellence Consulting
 
Organizational Change Leadership Agile Tour Geneve 2024
Organizational Change Leadership Agile Tour Geneve 2024Organizational Change Leadership Agile Tour Geneve 2024
Organizational Change Leadership Agile Tour Geneve 2024
Kirill Klimov
 
Event Report - SAP Sapphire 2024 Orlando - lots of innovation and old challenges
Event Report - SAP Sapphire 2024 Orlando - lots of innovation and old challengesEvent Report - SAP Sapphire 2024 Orlando - lots of innovation and old challenges
Event Report - SAP Sapphire 2024 Orlando - lots of innovation and old challenges
Holger Mueller
 
Creative Web Design Company in Singapore
Creative Web Design Company in SingaporeCreative Web Design Company in Singapore
Creative Web Design Company in Singapore
techboxsqauremedia
 
Hamster Kombat' Telegram Game Surpasses 100 Million Players—Token Release Sch...
Hamster Kombat' Telegram Game Surpasses 100 Million Players—Token Release Sch...Hamster Kombat' Telegram Game Surpasses 100 Million Players—Token Release Sch...
Hamster Kombat' Telegram Game Surpasses 100 Million Players—Token Release Sch...
SOFTTECHHUB
 
Unveiling the Dynamic Personalities, Key Dates, and Horoscope Insights: Gemin...
Unveiling the Dynamic Personalities, Key Dates, and Horoscope Insights: Gemin...Unveiling the Dynamic Personalities, Key Dates, and Horoscope Insights: Gemin...
Unveiling the Dynamic Personalities, Key Dates, and Horoscope Insights: Gemin...
my Pandit
 
Satta Matka Dpboss Matka Guessing Kalyan Chart Indian Matka Kalyan panel Chart
Satta Matka Dpboss Matka Guessing Kalyan Chart Indian Matka Kalyan panel ChartSatta Matka Dpboss Matka Guessing Kalyan Chart Indian Matka Kalyan panel Chart
Satta Matka Dpboss Matka Guessing Kalyan Chart Indian Matka Kalyan panel Chart
➒➌➎➏➑➐➋➑➐➐Dpboss Matka Guessing Satta Matka Kalyan Chart Indian Matka
 
Best practices for project execution and delivery
Best practices for project execution and deliveryBest practices for project execution and delivery
Best practices for project execution and delivery
CLIVE MINCHIN
 
Income Tax exemption for Start up : Section 80 IAC
Income Tax  exemption for Start up : Section 80 IACIncome Tax  exemption for Start up : Section 80 IAC
Income Tax exemption for Start up : Section 80 IAC
CA Dr. Prithvi Ranjan Parhi
 
Business storytelling: key ingredients to a story
Business storytelling: key ingredients to a storyBusiness storytelling: key ingredients to a story
Business storytelling: key ingredients to a story
Alexandra Fulford
 
Top mailing list providers in the USA.pptx
Top mailing list providers in the USA.pptxTop mailing list providers in the USA.pptx
Top mailing list providers in the USA.pptx
JeremyPeirce1
 
Part 2 Deep Dive: Navigating the 2024 Slowdown
Part 2 Deep Dive: Navigating the 2024 SlowdownPart 2 Deep Dive: Navigating the 2024 Slowdown
Part 2 Deep Dive: Navigating the 2024 Slowdown
jeffkluth1
 
The Genesis of BriansClub.cm Famous Dark WEb Platform
The Genesis of BriansClub.cm Famous Dark WEb PlatformThe Genesis of BriansClub.cm Famous Dark WEb Platform
The Genesis of BriansClub.cm Famous Dark WEb Platform
SabaaSudozai
 
2024-6-01-IMPACTSilver-Corp-Presentation.pdf
2024-6-01-IMPACTSilver-Corp-Presentation.pdf2024-6-01-IMPACTSilver-Corp-Presentation.pdf
2024-6-01-IMPACTSilver-Corp-Presentation.pdf
hartfordclub1
 
Brian Fitzsimmons on the Business Strategy and Content Flywheel of Barstool S...
Brian Fitzsimmons on the Business Strategy and Content Flywheel of Barstool S...Brian Fitzsimmons on the Business Strategy and Content Flywheel of Barstool S...
Brian Fitzsimmons on the Business Strategy and Content Flywheel of Barstool S...
Neil Horowitz
 
Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Satta Matka
Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Satta MatkaDpboss Matka Guessing Satta Matta Matka Kalyan Chart Satta Matka
Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Satta Matka
➒➌➎➏➑➐➋➑➐➐Dpboss Matka Guessing Satta Matka Kalyan Chart Indian Matka
 
Authentically Social by Corey Perlman - EO Puerto Rico
Authentically Social by Corey Perlman - EO Puerto RicoAuthentically Social by Corey Perlman - EO Puerto Rico
Authentically Social by Corey Perlman - EO Puerto Rico
Corey Perlman, Social Media Speaker and Consultant
 
BeMetals Investor Presentation_June 1, 2024.pdf
BeMetals Investor Presentation_June 1, 2024.pdfBeMetals Investor Presentation_June 1, 2024.pdf
BeMetals Investor Presentation_June 1, 2024.pdf
DerekIwanaka1
 
Taurus Zodiac Sign: Unveiling the Traits, Dates, and Horoscope Insights of th...
Taurus Zodiac Sign: Unveiling the Traits, Dates, and Horoscope Insights of th...Taurus Zodiac Sign: Unveiling the Traits, Dates, and Horoscope Insights of th...
Taurus Zodiac Sign: Unveiling the Traits, Dates, and Horoscope Insights of th...
my Pandit
 
How to Implement a Strategy: Transform Your Strategy with BSC Designer's Comp...
How to Implement a Strategy: Transform Your Strategy with BSC Designer's Comp...How to Implement a Strategy: Transform Your Strategy with BSC Designer's Comp...
How to Implement a Strategy: Transform Your Strategy with BSC Designer's Comp...
Aleksey Savkin
 

Recently uploaded (20)

Innovation Management Frameworks: Your Guide to Creativity & Innovation
Innovation Management Frameworks: Your Guide to Creativity & InnovationInnovation Management Frameworks: Your Guide to Creativity & Innovation
Innovation Management Frameworks: Your Guide to Creativity & Innovation
 
Organizational Change Leadership Agile Tour Geneve 2024
Organizational Change Leadership Agile Tour Geneve 2024Organizational Change Leadership Agile Tour Geneve 2024
Organizational Change Leadership Agile Tour Geneve 2024
 
Event Report - SAP Sapphire 2024 Orlando - lots of innovation and old challenges
Event Report - SAP Sapphire 2024 Orlando - lots of innovation and old challengesEvent Report - SAP Sapphire 2024 Orlando - lots of innovation and old challenges
Event Report - SAP Sapphire 2024 Orlando - lots of innovation and old challenges
 
Creative Web Design Company in Singapore
Creative Web Design Company in SingaporeCreative Web Design Company in Singapore
Creative Web Design Company in Singapore
 
Hamster Kombat' Telegram Game Surpasses 100 Million Players—Token Release Sch...
Hamster Kombat' Telegram Game Surpasses 100 Million Players—Token Release Sch...Hamster Kombat' Telegram Game Surpasses 100 Million Players—Token Release Sch...
Hamster Kombat' Telegram Game Surpasses 100 Million Players—Token Release Sch...
 
Unveiling the Dynamic Personalities, Key Dates, and Horoscope Insights: Gemin...
Unveiling the Dynamic Personalities, Key Dates, and Horoscope Insights: Gemin...Unveiling the Dynamic Personalities, Key Dates, and Horoscope Insights: Gemin...
Unveiling the Dynamic Personalities, Key Dates, and Horoscope Insights: Gemin...
 
Satta Matka Dpboss Matka Guessing Kalyan Chart Indian Matka Kalyan panel Chart
Satta Matka Dpboss Matka Guessing Kalyan Chart Indian Matka Kalyan panel ChartSatta Matka Dpboss Matka Guessing Kalyan Chart Indian Matka Kalyan panel Chart
Satta Matka Dpboss Matka Guessing Kalyan Chart Indian Matka Kalyan panel Chart
 
Best practices for project execution and delivery
Best practices for project execution and deliveryBest practices for project execution and delivery
Best practices for project execution and delivery
 
Income Tax exemption for Start up : Section 80 IAC
Income Tax  exemption for Start up : Section 80 IACIncome Tax  exemption for Start up : Section 80 IAC
Income Tax exemption for Start up : Section 80 IAC
 
Business storytelling: key ingredients to a story
Business storytelling: key ingredients to a storyBusiness storytelling: key ingredients to a story
Business storytelling: key ingredients to a story
 
Top mailing list providers in the USA.pptx
Top mailing list providers in the USA.pptxTop mailing list providers in the USA.pptx
Top mailing list providers in the USA.pptx
 
Part 2 Deep Dive: Navigating the 2024 Slowdown
Part 2 Deep Dive: Navigating the 2024 SlowdownPart 2 Deep Dive: Navigating the 2024 Slowdown
Part 2 Deep Dive: Navigating the 2024 Slowdown
 
The Genesis of BriansClub.cm Famous Dark WEb Platform
The Genesis of BriansClub.cm Famous Dark WEb PlatformThe Genesis of BriansClub.cm Famous Dark WEb Platform
The Genesis of BriansClub.cm Famous Dark WEb Platform
 
2024-6-01-IMPACTSilver-Corp-Presentation.pdf
2024-6-01-IMPACTSilver-Corp-Presentation.pdf2024-6-01-IMPACTSilver-Corp-Presentation.pdf
2024-6-01-IMPACTSilver-Corp-Presentation.pdf
 
Brian Fitzsimmons on the Business Strategy and Content Flywheel of Barstool S...
Brian Fitzsimmons on the Business Strategy and Content Flywheel of Barstool S...Brian Fitzsimmons on the Business Strategy and Content Flywheel of Barstool S...
Brian Fitzsimmons on the Business Strategy and Content Flywheel of Barstool S...
 
Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Satta Matka
Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Satta MatkaDpboss Matka Guessing Satta Matta Matka Kalyan Chart Satta Matka
Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Satta Matka
 
Authentically Social by Corey Perlman - EO Puerto Rico
Authentically Social by Corey Perlman - EO Puerto RicoAuthentically Social by Corey Perlman - EO Puerto Rico
Authentically Social by Corey Perlman - EO Puerto Rico
 
BeMetals Investor Presentation_June 1, 2024.pdf
BeMetals Investor Presentation_June 1, 2024.pdfBeMetals Investor Presentation_June 1, 2024.pdf
BeMetals Investor Presentation_June 1, 2024.pdf
 
Taurus Zodiac Sign: Unveiling the Traits, Dates, and Horoscope Insights of th...
Taurus Zodiac Sign: Unveiling the Traits, Dates, and Horoscope Insights of th...Taurus Zodiac Sign: Unveiling the Traits, Dates, and Horoscope Insights of th...
Taurus Zodiac Sign: Unveiling the Traits, Dates, and Horoscope Insights of th...
 
How to Implement a Strategy: Transform Your Strategy with BSC Designer's Comp...
How to Implement a Strategy: Transform Your Strategy with BSC Designer's Comp...How to Implement a Strategy: Transform Your Strategy with BSC Designer's Comp...
How to Implement a Strategy: Transform Your Strategy with BSC Designer's Comp...
 

Horseshoe Casino Construction

  • 2. Ever wanted a tour of a construction site for a concrete structure? Don’t just stare at the skyline, come on and take a closer look…
  • 3. Often, parking garages have one or more levels below grade, so excavation is a big part of the project, and occurs before work on the structure ever begins. Excavation on this project went down more than 50 feet in some locations.
  • 4. At RedBuilt's facility in Delaware, OH, form tables were fabricated on a leveled jig in a climate-controlled environment. This can improve safety and productivity during form table fabrication, and can have a substantial impact on the consistency and quality of workmanship in building the forms. Just-in time delivery of form tables can be arranged so that material arrives on the truck bed ready to be moved immediately onto the shoring towers.
  • 5. Tables can be moved in stacks directly to the shoring, either by crane or by forklift. Preattached dunnage simplifies movement and stacking of tables. Tables can then be set into place one at a time and aligned by workers using the steel beam forms to access tables.
  • 6. I-Joists for the deck form are often supported by a steel W8x10. This configuration works well where the I-Joists cantilever out beyond the supporting member, because full bearing can be consistently achieved when slight changes in table length occur (small plan changes to beam layout, ramp areas, etc.). When a table is set adjacent to an already installed table, they need to be butted tight. Plyform is typically cantilevered past the last joist, and the cantilevered edge of the plyform is supported by leading joist of the prior table. It is common to butt the plyform sheets directly over the center of the flange on the leading joist. A 2x4 is often used to stiffen and align the cantilevered plyform.
  • 7. Protective guardrailing may either be mounted to the beam forms—as shown here—or may be directly attached to the deck form tables.
  • 8. While parking garages are often notorious for their low ceiling profiles, the system can also be used similarly where ceiling height is much higher. In cases like this, additional shoring is required.
  • 9. Alignment of the forming tables can help determine the aesthetics of the beam-to-slab intersection. Table length, table squareness and installation of tables are important in order to get consistent aesthetics here. Construction on the Horseshoe Casino continues with the Cincinnati skyline in the background.
  • 10. Since RedForm I-Joists are available in depths up to 20” and can be manufactured with camber, they can often be used for up to 30’ bay widths to carry slabs without any center supports. This can make for a very clean jobsite that is fast and efficient for both the formwork contractor and subsequent trades. When a perpendicular beam runs through the building, steel beam forms can be run parallel to the form deck tables. This may require additional detailing to support the adjacent deck table(s) and transition from the I-Joists to the steel beam form.
  • 11. Once forming tables are placed, setting of post tensioning cables and rebar can begin.
  • 12. Alignment of adjacent tables can be important to maintain aesthetics of the finished slab and to prevent mortar leakage that can bind to the underside of the formwork. The deck panel inserts are attached to a threaded rod that is used to temporarily support the formwork tables during the stripping process. The inserts shown here are cast into the concrete slab.
  • 13. Fabrication of the beam’s rebar cage can be simplified by building it above the deck. Once the rebar cage is fabricated above the deck, it can be dropped down into the beam form.
  • 14. Now the “real fun” begins. Concrete is now ready to be placed on the formed-out deck. Beams and slabs are cast together in the same pour.
  • 15. During an active pour, workers move concrete out to prevent it from piling up in one area. Relatively uniform placement of concrete during the pour can help prevent undue stress or deflection on forming and shoring below. After the concrete slab has been poured, leveled and screened, the concrete is allowed to cure undisturbed until the concrete has gained sufficient strength to carry its own weight.
  • 16. On larger projects, it is common to pour a portion of each deck level. The subsequent pour is then connected to the prior pour through rebar and stressing tendons.
  • 17. Once concrete has obtained enough strength to be self-supporting, the forming and shoring can be removed. Here, the shoring and steel beam form are being removed first. The deck form is now being held in place by the anchor bolt inserted into the concrete slab. Reshoring will be added per the reshoring plan prior to placement of concrete at the next level. Tables hang from the anchor bolt in the slab until they are ready to be dropped and relocated. Here the forklift driver uses a "stripping truss" to lower the table. Quality of the finished concrete structure can be affected by the quality and condition of forming materials used, fabrication and installation of tables, form maintenance, handling and inspection. Depending on the project, some imperfections in the concrete are permitted to an extent, but some require repair work to meet project requirements.
  • 18. Once the deck is poured, fabrication of rebar cages and formwork for columns on the next level can begin.