SlideShare a Scribd company logo
Construction Technology_Unit 3.2
1
Unit VI (6 hours)
High rise construction techniques: Various types and
erection methods of shuttering/form work, Operation and
erection of Ready Mix Concrete Plant, special techniques
required for construction and maintenance of high rise
construction like Pumped Concrete, slip form.
2
1. Slip form
2. Jump form
3. Climbing formwork
4.Table form/ flying form
5. Column system formwork
6.Tunnel form
Introduction to Construction formwork system
 Slip forming is a type of movable
formwork which is slowly raised.
Slip form construction, concrete
is poured into a continuously
moving form.
 Basically, this method involves the
continuous placing of concrete in
a shallow mould having the same
plan as the building to be
constructed.
 This rigid mould , or "slipform“
as it is called, forms the working
deck which is jacked slowly
upwards at a controlled rate until
the required elevation is reached.
Slip form technique
3
 Generally, jump form systems comprise the
formwork and working platforms for
cleaning/fixing of the formwork, steel
fixing and concreting.
 Jump form, often described as climbing
form. It is suitable for construction of
multi-floor vertical concrete elements in
high-rise structures, such as shear walls,
core walls, lift shafts, stair shafts and bridge
pylons.
 It is a highly productive system designed to
increase speed and efficiency while
minimizing labor and time.
Jump form technique
4
 Types:
 Normal jump/climbing form –units are
individually lifted off the structure and relocated
at the next construction level using a crane.
 Guided-climbing jump form – also uses a
crane but offers greater safety and control during
lifting as units remain anchored/guided by the
structure.
 Self-climbing jump form – does not require a
crane as it climbs on rails up the building by
means of hydraulic jacks, or by jacking the
platforms off internal recesses in the structure. It
is possible to link the hydraulic jacks and lift
multiple units in a single operation.
Jump form technique
5
 It is an economical, rapid and
accurate method of constructing
reinforced concrete, or post-
tensioned concrete structures.
 At its most basic level, slip forming is
a type of movable formwork which is
slowly raised, allowing the continuous
extrusion of concrete.
Climb form technique
6
 Tunnel form is used to form
repetitive cellular structures, and is
widely recognised as a modern
innovation that enables the
construction of horizontal and
vertical elements (walls and floors)
together.
 Significant productivity benefits have
been achieved by using tunnel form
to construct cellular buildings such as
hotels, low and high-rise housing,
hostels, student accommodation,
prison and barracks accommodation.
Tunnel form technique
7
 A table form/flying form is a large
preassembled formwork and
falsework unit, often forming a
complete bay of suspended floor slab.
 It offers mobility and quick
installation for construction projects
with regular plan layouts or long
repetitive structures, so is highly
suitable for flat slab, and beam and
slab layouts.
Table form technique
8
9
1. Mivan Construction System
2. Coffor formwork system
3. Doka formwork system(Table formwork system)
4. PERI formwork system
Construction formwork system in Market
10
Doka formwork system(Table formwork system)
SBG Department of Civil PCCoE,2020-21
11
Doka formwork system
SBG Department of Civil PCCoE,2020-21
12
Doka formwork system
SBG Department of Civil PCCoE,2020-21
13
Doka formwork system
SBG Department of Civil PCCoE,2020-21
14
Doka formwork system(Table formwork system)
SBG Department of Civil PCCoE,2020-21
15
Doka formwork system(Table formwork system)
SBG Department of Civil PCCoE,2020-21
16
Doka formwork system(Table formwork system)
SBG Department of Civil PCCoE,2020-21
17
Doka formwork system(Table formwork system)
18
Doka formwork system(Table formwork system)
ADVANTAGES
● HIGH LABOR PRODUCTIVITY (APPROX 8TO 10 SQ.M PER MAN-
DAY)
● SIMPLE DESHUTTERING OPERATION
● MINIMIZES MAKING /ASSEMBLYTIME AND COST AT SITE
● ENTIREASSEMBLY CAN BE LIFTEDWITH CRANE
● SYSTEM IS RIGIDAND STABLE
● CLEANACCURATEAND SMOOTH CONCRETE FINISH
19
COFFOR formwork system
COFFOR is a patented structural stay in place formwork system to build
load bearing monolithic structures.
It is composed of 2 filtering grids made of rib lathe reinforced by vertical
stiffeners.
The grids are connected by articulated rebar loops and connectors that fold
for cost effective transportation.
20
COFFOR formwork system
21
COFFOR formwork system-Applications
Storm water System
22
COFFOR formwork system-Applications
Individual Bungalow
23
COFFOR formwork system-Applications
P+5Appartments
24
COFFOR formwork system-Applications
Under ground water tank Under ground Utility chamber
25
COFFOR formwork system-Applications
26
COFFOR formwork system-Applications
Advantages-
• LessVolume Required
•No Shuttering Required
•No Crane Required
•Minimum Reinforcement
•Less allied accessories required
•Multiple Creative possibilities
•Semi-skilled labour’s required
•Less no of labour’s required
•No honey comb in concrete
•Easy installation of Electric and plumbing lines
•Rapid Concrete Shrinkage
27
PERI formwork system
28
PERI formwork system
29
PERI formwork system
30
PERI aluminum formwork system
31
Mivan formwork system
MIVAN technology is suitable for constructing large number of houses within
short time using room size forms to construct walls and slabs in one
continuous pour on concrete.
PRE – CONCRETE ACTIVITIES:
a) Receipt of Equipment on Site –The equipments is received in the site as
ordered.
b) Level Surveys – Level checking are made to maintain horizontal level
check.
c) Setting Out –The setting out of the formwork is done.
d) Control / Correction of Deviation – Deviation or any correction are
carried out.
e) Erect Formwork –The formwork is erected on site.
f) Erect Deck Formwork – Deck is erected for labours to work.
g) Setting Kickers – kickers are provided over the beam.
32
Mivan formwork system
On Concrete Activities-
i. Dislodging of pins/wedges due to vibration.
ii. Beam/deck props adjacent to drop areas slipping due to vibration.
iii. Ensure all bracing at special areas slipping due to vibration.
iv. Overspill of concrete at window opening etc.
Post Concrete Activities-
A) CLEANING:
•All components should be cleaned with scrapers and wire brushes as soon as they are
struck.Wire brush is to be used on side rails only.
B)TRANSPORTING:
•The heaviest and the longest, which is a full height of wall panel, can be carried up the
nearest stairway. Passes through void areas.
C) STRIKING:
• Once cleaned and transported to the next point of erection, panels should be stacked at
right place and in right order.
D) Erecting of Formwork:
•After that formwork is erect again on the next floor.
33
Mivan formwork system
34
Mivan formwork system
ADVANTAGES-
The MIVAN formwork is specifically designed to allow rapid construction
of all types of architectural layouts.
1) Cost effective.
2) It is more effective for mass housing to be done quickly.
3) Great construction speed.
4) High quality finish.
5) Erected using unskilled labor.
6) Panels can be reused up to 250 times.
35
Mivan formwork system
Limitation of Mivan Formwork:
1) Because of small sizes finishing lines are seen on the concrete surfaces.
2) It requires uniform planning as well as uniform elevations to be cost
effective.
3) Modifications are not possible as all members are caste in RCC.
4) Due to box-type construction shrinkage cracks are likely to appear.
5) Heat of Hydration is high due to shear walls.

More Related Content

Similar to Construction Technology

Slipform construction
Slipform constructionSlipform construction
Slipform construction
tivar rose
 
Prefabricated Column
Prefabricated ColumnPrefabricated Column
Prefabricated Column
Anees Khan
 
Sub Structure Construction.pptx
Sub Structure Construction.pptxSub Structure Construction.pptx
Sub Structure Construction.pptx
Ananthakumar75
 
Slip formwork for chimney
Slip formwork for chimneySlip formwork for chimney
Slip formwork for chimney
Axay Sharma
 
Jump Formwork
Jump FormworkJump Formwork
CT III IBS Formwork System
CT III IBS Formwork System CT III IBS Formwork System
CT III IBS Formwork System
ashleyyeap
 
Chapters-3,4,5.pptx
Chapters-3,4,5.pptxChapters-3,4,5.pptx
Chapters-3,4,5.pptx
ssuserc0bf9b
 
study of usage factor in low cost construction
study of usage factor in low cost constructionstudy of usage factor in low cost construction
study of usage factor in low cost construction
Manisha Singh
 
Modern Formwork: Mivan
Modern Formwork: Mivan Modern Formwork: Mivan
Modern Formwork: Mivan
RPNarwade
 
Form-woks-additional.pptx
Form-woks-additional.pptxForm-woks-additional.pptx
Form-woks-additional.pptx
ssuserc0bf9b
 
Construction portfolio (manvi)
Construction portfolio (manvi)Construction portfolio (manvi)
Construction portfolio (manvi)
ManviVarshney2
 
Presentation on MIVAN -- A versatile aluminum formwork construction technique
Presentation on MIVAN -- A versatile aluminum formwork construction techniquePresentation on MIVAN -- A versatile aluminum formwork construction technique
Presentation on MIVAN -- A versatile aluminum formwork construction technique
IEI GSC
 
Mivan aluminium formwork
Mivan aluminium formworkMivan aluminium formwork
Mivan aluminium formwork
Mumtaz Alam
 
CONSTRUCTION TECHNOLOGY
CONSTRUCTION TECHNOLOGY CONSTRUCTION TECHNOLOGY
CONSTRUCTION TECHNOLOGY
VISHNU VIJAYAN
 
Precast Construction technology
Precast Construction technologyPrecast Construction technology
Precast Construction technology
GedalaJairam
 
Pre-Cast Technology: An Initial Step to Sustainable Development
Pre-Cast Technology: An Initial Step to Sustainable DevelopmentPre-Cast Technology: An Initial Step to Sustainable Development
Pre-Cast Technology: An Initial Step to Sustainable Development
ijsrd.com
 
accelerated bridge construction(ABC)
accelerated bridge construction(ABC)accelerated bridge construction(ABC)
accelerated bridge construction(ABC)
varun km
 
TALL BUILDINGS
TALL BUILDINGSTALL BUILDINGS
TALL BUILDINGS
Abhijit Pal
 
JUMP FORM WORK
JUMP FORM WORKJUMP FORM WORK
JUMP FORM WORK
Pranay Kumar Tode
 
Precast segmental construction of bridges
Precast segmental construction of bridgesPrecast segmental construction of bridges
Precast segmental construction of bridges
mukul srivastava
 

Similar to Construction Technology (20)

Slipform construction
Slipform constructionSlipform construction
Slipform construction
 
Prefabricated Column
Prefabricated ColumnPrefabricated Column
Prefabricated Column
 
Sub Structure Construction.pptx
Sub Structure Construction.pptxSub Structure Construction.pptx
Sub Structure Construction.pptx
 
Slip formwork for chimney
Slip formwork for chimneySlip formwork for chimney
Slip formwork for chimney
 
Jump Formwork
Jump FormworkJump Formwork
Jump Formwork
 
CT III IBS Formwork System
CT III IBS Formwork System CT III IBS Formwork System
CT III IBS Formwork System
 
Chapters-3,4,5.pptx
Chapters-3,4,5.pptxChapters-3,4,5.pptx
Chapters-3,4,5.pptx
 
study of usage factor in low cost construction
study of usage factor in low cost constructionstudy of usage factor in low cost construction
study of usage factor in low cost construction
 
Modern Formwork: Mivan
Modern Formwork: Mivan Modern Formwork: Mivan
Modern Formwork: Mivan
 
Form-woks-additional.pptx
Form-woks-additional.pptxForm-woks-additional.pptx
Form-woks-additional.pptx
 
Construction portfolio (manvi)
Construction portfolio (manvi)Construction portfolio (manvi)
Construction portfolio (manvi)
 
Presentation on MIVAN -- A versatile aluminum formwork construction technique
Presentation on MIVAN -- A versatile aluminum formwork construction techniquePresentation on MIVAN -- A versatile aluminum formwork construction technique
Presentation on MIVAN -- A versatile aluminum formwork construction technique
 
Mivan aluminium formwork
Mivan aluminium formworkMivan aluminium formwork
Mivan aluminium formwork
 
CONSTRUCTION TECHNOLOGY
CONSTRUCTION TECHNOLOGY CONSTRUCTION TECHNOLOGY
CONSTRUCTION TECHNOLOGY
 
Precast Construction technology
Precast Construction technologyPrecast Construction technology
Precast Construction technology
 
Pre-Cast Technology: An Initial Step to Sustainable Development
Pre-Cast Technology: An Initial Step to Sustainable DevelopmentPre-Cast Technology: An Initial Step to Sustainable Development
Pre-Cast Technology: An Initial Step to Sustainable Development
 
accelerated bridge construction(ABC)
accelerated bridge construction(ABC)accelerated bridge construction(ABC)
accelerated bridge construction(ABC)
 
TALL BUILDINGS
TALL BUILDINGSTALL BUILDINGS
TALL BUILDINGS
 
JUMP FORM WORK
JUMP FORM WORKJUMP FORM WORK
JUMP FORM WORK
 
Precast segmental construction of bridges
Precast segmental construction of bridgesPrecast segmental construction of bridges
Precast segmental construction of bridges
 

More from SwapnilGorade1

ConstTech_Unit1.6.pptx
ConstTech_Unit1.6.pptxConstTech_Unit1.6.pptx
ConstTech_Unit1.6.pptx
SwapnilGorade1
 
CTRS unit 2_Lect 1.pptx
CTRS unit 2_Lect 1.pptxCTRS unit 2_Lect 1.pptx
CTRS unit 2_Lect 1.pptx
SwapnilGorade1
 
Virtual design element.ppt
Virtual design element.pptVirtual design element.ppt
Virtual design element.ppt
SwapnilGorade1
 
Virtual design element.ppt
Virtual design element.pptVirtual design element.ppt
Virtual design element.ppt
SwapnilGorade1
 
Road-Note-Method-No-4.ppt
Road-Note-Method-No-4.pptRoad-Note-Method-No-4.ppt
Road-Note-Method-No-4.ppt
SwapnilGorade1
 
ACT_unit1_3 QA QC_green conc.pdf
ACT_unit1_3 QA QC_green conc.pdfACT_unit1_3 QA QC_green conc.pdf
ACT_unit1_3 QA QC_green conc.pdf
SwapnilGorade1
 
ACT_unit1_2concrete properties_updated.pdf
ACT_unit1_2concrete properties_updated.pdfACT_unit1_2concrete properties_updated.pdf
ACT_unit1_2concrete properties_updated.pdf
SwapnilGorade1
 
Advance concrete technology.pdf
Advance concrete technology.pdfAdvance concrete technology.pdf
Advance concrete technology.pdf
SwapnilGorade1
 
ACT_unit2_1.pdf
ACT_unit2_1.pdfACT_unit2_1.pdf
ACT_unit2_1.pdf
SwapnilGorade1
 
scope of Infrastructure Engineering.pptx
scope of Infrastructure Engineering.pptxscope of Infrastructure Engineering.pptx
scope of Infrastructure Engineering.pptx
SwapnilGorade1
 
UNIT 2 Railway Engg.ppt
UNIT 2 Railway Engg.pptUNIT 2 Railway Engg.ppt
UNIT 2 Railway Engg.ppt
SwapnilGorade1
 
RTH_3.1.pdf
RTH_3.1.pdfRTH_3.1.pdf
RTH_3.1.pdf
SwapnilGorade1
 
ConstTech_Unit 4.4.pdf
ConstTech_Unit 4.4.pdfConstTech_Unit 4.4.pdf
ConstTech_Unit 4.4.pdf
SwapnilGorade1
 
1_Project ID_01 poster.pdf
1_Project ID_01 poster.pdf1_Project ID_01 poster.pdf
1_Project ID_01 poster.pdf
SwapnilGorade1
 
Railway_Bridge_and_Tunnel_Engineering.pdf
Railway_Bridge_and_Tunnel_Engineering.pdfRailway_Bridge_and_Tunnel_Engineering.pdf
Railway_Bridge_and_Tunnel_Engineering.pdf
SwapnilGorade1
 

More from SwapnilGorade1 (15)

ConstTech_Unit1.6.pptx
ConstTech_Unit1.6.pptxConstTech_Unit1.6.pptx
ConstTech_Unit1.6.pptx
 
CTRS unit 2_Lect 1.pptx
CTRS unit 2_Lect 1.pptxCTRS unit 2_Lect 1.pptx
CTRS unit 2_Lect 1.pptx
 
Virtual design element.ppt
Virtual design element.pptVirtual design element.ppt
Virtual design element.ppt
 
Virtual design element.ppt
Virtual design element.pptVirtual design element.ppt
Virtual design element.ppt
 
Road-Note-Method-No-4.ppt
Road-Note-Method-No-4.pptRoad-Note-Method-No-4.ppt
Road-Note-Method-No-4.ppt
 
ACT_unit1_3 QA QC_green conc.pdf
ACT_unit1_3 QA QC_green conc.pdfACT_unit1_3 QA QC_green conc.pdf
ACT_unit1_3 QA QC_green conc.pdf
 
ACT_unit1_2concrete properties_updated.pdf
ACT_unit1_2concrete properties_updated.pdfACT_unit1_2concrete properties_updated.pdf
ACT_unit1_2concrete properties_updated.pdf
 
Advance concrete technology.pdf
Advance concrete technology.pdfAdvance concrete technology.pdf
Advance concrete technology.pdf
 
ACT_unit2_1.pdf
ACT_unit2_1.pdfACT_unit2_1.pdf
ACT_unit2_1.pdf
 
scope of Infrastructure Engineering.pptx
scope of Infrastructure Engineering.pptxscope of Infrastructure Engineering.pptx
scope of Infrastructure Engineering.pptx
 
UNIT 2 Railway Engg.ppt
UNIT 2 Railway Engg.pptUNIT 2 Railway Engg.ppt
UNIT 2 Railway Engg.ppt
 
RTH_3.1.pdf
RTH_3.1.pdfRTH_3.1.pdf
RTH_3.1.pdf
 
ConstTech_Unit 4.4.pdf
ConstTech_Unit 4.4.pdfConstTech_Unit 4.4.pdf
ConstTech_Unit 4.4.pdf
 
1_Project ID_01 poster.pdf
1_Project ID_01 poster.pdf1_Project ID_01 poster.pdf
1_Project ID_01 poster.pdf
 
Railway_Bridge_and_Tunnel_Engineering.pdf
Railway_Bridge_and_Tunnel_Engineering.pdfRailway_Bridge_and_Tunnel_Engineering.pdf
Railway_Bridge_and_Tunnel_Engineering.pdf
 

Recently uploaded

一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理
一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理
一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理
sydezfe
 
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by AnantLLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
Anant Corporation
 
一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理
一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理
一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理
upoux
 
Mechatronics material . Mechanical engineering
Mechatronics material . Mechanical engineeringMechatronics material . Mechanical engineering
Mechatronics material . Mechanical engineering
sachin chaurasia
 
Digital Twins Computer Networking Paper Presentation.pptx
Digital Twins Computer Networking Paper Presentation.pptxDigital Twins Computer Networking Paper Presentation.pptx
Digital Twins Computer Networking Paper Presentation.pptx
aryanpankaj78
 
1FIDIC-CONSTRUCTION-CONTRACT-2ND-ED-2017-RED-BOOK.pdf
1FIDIC-CONSTRUCTION-CONTRACT-2ND-ED-2017-RED-BOOK.pdf1FIDIC-CONSTRUCTION-CONTRACT-2ND-ED-2017-RED-BOOK.pdf
1FIDIC-CONSTRUCTION-CONTRACT-2ND-ED-2017-RED-BOOK.pdf
MadhavJungKarki
 
Null Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAMNull Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAM
Divyanshu
 
5G Radio Network Througput Problem Analysis HCIA.pdf
5G Radio Network Througput Problem Analysis HCIA.pdf5G Radio Network Througput Problem Analysis HCIA.pdf
5G Radio Network Througput Problem Analysis HCIA.pdf
AlvianRamadhani5
 
Data Driven Maintenance | UReason Webinar
Data Driven Maintenance | UReason WebinarData Driven Maintenance | UReason Webinar
Data Driven Maintenance | UReason Webinar
UReason
 
Applications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdfApplications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdf
Atif Razi
 
Software Engineering and Project Management - Introduction, Modeling Concepts...
Software Engineering and Project Management - Introduction, Modeling Concepts...Software Engineering and Project Management - Introduction, Modeling Concepts...
Software Engineering and Project Management - Introduction, Modeling Concepts...
Prakhyath Rai
 
AI + Data Community Tour - Build the Next Generation of Apps with the Einstei...
AI + Data Community Tour - Build the Next Generation of Apps with the Einstei...AI + Data Community Tour - Build the Next Generation of Apps with the Einstei...
AI + Data Community Tour - Build the Next Generation of Apps with the Einstei...
Paris Salesforce Developer Group
 
Height and depth gauge linear metrology.pdf
Height and depth gauge linear metrology.pdfHeight and depth gauge linear metrology.pdf
Height and depth gauge linear metrology.pdf
q30122000
 
Object Oriented Analysis and Design - OOAD
Object Oriented Analysis and Design - OOADObject Oriented Analysis and Design - OOAD
Object Oriented Analysis and Design - OOAD
PreethaV16
 
ITSM Integration with MuleSoft.pptx
ITSM  Integration with MuleSoft.pptxITSM  Integration with MuleSoft.pptx
ITSM Integration with MuleSoft.pptx
VANDANAMOHANGOUDA
 
OOPS_Lab_Manual - programs using C++ programming language
OOPS_Lab_Manual - programs using C++ programming languageOOPS_Lab_Manual - programs using C++ programming language
OOPS_Lab_Manual - programs using C++ programming language
PreethaV16
 
Pressure Relief valve used in flow line to release the over pressure at our d...
Pressure Relief valve used in flow line to release the over pressure at our d...Pressure Relief valve used in flow line to release the over pressure at our d...
Pressure Relief valve used in flow line to release the over pressure at our d...
cannyengineerings
 
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
ecqow
 
Tools & Techniques for Commissioning and Maintaining PV Systems W-Animations ...
Tools & Techniques for Commissioning and Maintaining PV Systems W-Animations ...Tools & Techniques for Commissioning and Maintaining PV Systems W-Animations ...
Tools & Techniques for Commissioning and Maintaining PV Systems W-Animations ...
Transcat
 
SCALING OF MOS CIRCUITS m .pptx
SCALING OF MOS CIRCUITS m                 .pptxSCALING OF MOS CIRCUITS m                 .pptx
SCALING OF MOS CIRCUITS m .pptx
harshapolam10
 

Recently uploaded (20)

一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理
一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理
一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理
 
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by AnantLLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
 
一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理
一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理
一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理
 
Mechatronics material . Mechanical engineering
Mechatronics material . Mechanical engineeringMechatronics material . Mechanical engineering
Mechatronics material . Mechanical engineering
 
Digital Twins Computer Networking Paper Presentation.pptx
Digital Twins Computer Networking Paper Presentation.pptxDigital Twins Computer Networking Paper Presentation.pptx
Digital Twins Computer Networking Paper Presentation.pptx
 
1FIDIC-CONSTRUCTION-CONTRACT-2ND-ED-2017-RED-BOOK.pdf
1FIDIC-CONSTRUCTION-CONTRACT-2ND-ED-2017-RED-BOOK.pdf1FIDIC-CONSTRUCTION-CONTRACT-2ND-ED-2017-RED-BOOK.pdf
1FIDIC-CONSTRUCTION-CONTRACT-2ND-ED-2017-RED-BOOK.pdf
 
Null Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAMNull Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAM
 
5G Radio Network Througput Problem Analysis HCIA.pdf
5G Radio Network Througput Problem Analysis HCIA.pdf5G Radio Network Througput Problem Analysis HCIA.pdf
5G Radio Network Througput Problem Analysis HCIA.pdf
 
Data Driven Maintenance | UReason Webinar
Data Driven Maintenance | UReason WebinarData Driven Maintenance | UReason Webinar
Data Driven Maintenance | UReason Webinar
 
Applications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdfApplications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdf
 
Software Engineering and Project Management - Introduction, Modeling Concepts...
Software Engineering and Project Management - Introduction, Modeling Concepts...Software Engineering and Project Management - Introduction, Modeling Concepts...
Software Engineering and Project Management - Introduction, Modeling Concepts...
 
AI + Data Community Tour - Build the Next Generation of Apps with the Einstei...
AI + Data Community Tour - Build the Next Generation of Apps with the Einstei...AI + Data Community Tour - Build the Next Generation of Apps with the Einstei...
AI + Data Community Tour - Build the Next Generation of Apps with the Einstei...
 
Height and depth gauge linear metrology.pdf
Height and depth gauge linear metrology.pdfHeight and depth gauge linear metrology.pdf
Height and depth gauge linear metrology.pdf
 
Object Oriented Analysis and Design - OOAD
Object Oriented Analysis and Design - OOADObject Oriented Analysis and Design - OOAD
Object Oriented Analysis and Design - OOAD
 
ITSM Integration with MuleSoft.pptx
ITSM  Integration with MuleSoft.pptxITSM  Integration with MuleSoft.pptx
ITSM Integration with MuleSoft.pptx
 
OOPS_Lab_Manual - programs using C++ programming language
OOPS_Lab_Manual - programs using C++ programming languageOOPS_Lab_Manual - programs using C++ programming language
OOPS_Lab_Manual - programs using C++ programming language
 
Pressure Relief valve used in flow line to release the over pressure at our d...
Pressure Relief valve used in flow line to release the over pressure at our d...Pressure Relief valve used in flow line to release the over pressure at our d...
Pressure Relief valve used in flow line to release the over pressure at our d...
 
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
 
Tools & Techniques for Commissioning and Maintaining PV Systems W-Animations ...
Tools & Techniques for Commissioning and Maintaining PV Systems W-Animations ...Tools & Techniques for Commissioning and Maintaining PV Systems W-Animations ...
Tools & Techniques for Commissioning and Maintaining PV Systems W-Animations ...
 
SCALING OF MOS CIRCUITS m .pptx
SCALING OF MOS CIRCUITS m                 .pptxSCALING OF MOS CIRCUITS m                 .pptx
SCALING OF MOS CIRCUITS m .pptx
 

Construction Technology

  • 1. Construction Technology_Unit 3.2 1 Unit VI (6 hours) High rise construction techniques: Various types and erection methods of shuttering/form work, Operation and erection of Ready Mix Concrete Plant, special techniques required for construction and maintenance of high rise construction like Pumped Concrete, slip form.
  • 2. 2 1. Slip form 2. Jump form 3. Climbing formwork 4.Table form/ flying form 5. Column system formwork 6.Tunnel form Introduction to Construction formwork system
  • 3.  Slip forming is a type of movable formwork which is slowly raised. Slip form construction, concrete is poured into a continuously moving form.  Basically, this method involves the continuous placing of concrete in a shallow mould having the same plan as the building to be constructed.  This rigid mould , or "slipform“ as it is called, forms the working deck which is jacked slowly upwards at a controlled rate until the required elevation is reached. Slip form technique 3
  • 4.  Generally, jump form systems comprise the formwork and working platforms for cleaning/fixing of the formwork, steel fixing and concreting.  Jump form, often described as climbing form. It is suitable for construction of multi-floor vertical concrete elements in high-rise structures, such as shear walls, core walls, lift shafts, stair shafts and bridge pylons.  It is a highly productive system designed to increase speed and efficiency while minimizing labor and time. Jump form technique 4
  • 5.  Types:  Normal jump/climbing form –units are individually lifted off the structure and relocated at the next construction level using a crane.  Guided-climbing jump form – also uses a crane but offers greater safety and control during lifting as units remain anchored/guided by the structure.  Self-climbing jump form – does not require a crane as it climbs on rails up the building by means of hydraulic jacks, or by jacking the platforms off internal recesses in the structure. It is possible to link the hydraulic jacks and lift multiple units in a single operation. Jump form technique 5
  • 6.  It is an economical, rapid and accurate method of constructing reinforced concrete, or post- tensioned concrete structures.  At its most basic level, slip forming is a type of movable formwork which is slowly raised, allowing the continuous extrusion of concrete. Climb form technique 6
  • 7.  Tunnel form is used to form repetitive cellular structures, and is widely recognised as a modern innovation that enables the construction of horizontal and vertical elements (walls and floors) together.  Significant productivity benefits have been achieved by using tunnel form to construct cellular buildings such as hotels, low and high-rise housing, hostels, student accommodation, prison and barracks accommodation. Tunnel form technique 7
  • 8.  A table form/flying form is a large preassembled formwork and falsework unit, often forming a complete bay of suspended floor slab.  It offers mobility and quick installation for construction projects with regular plan layouts or long repetitive structures, so is highly suitable for flat slab, and beam and slab layouts. Table form technique 8
  • 9. 9 1. Mivan Construction System 2. Coffor formwork system 3. Doka formwork system(Table formwork system) 4. PERI formwork system Construction formwork system in Market
  • 10. 10 Doka formwork system(Table formwork system)
  • 11. SBG Department of Civil PCCoE,2020-21 11 Doka formwork system
  • 12. SBG Department of Civil PCCoE,2020-21 12 Doka formwork system
  • 13. SBG Department of Civil PCCoE,2020-21 13 Doka formwork system
  • 14. SBG Department of Civil PCCoE,2020-21 14 Doka formwork system(Table formwork system)
  • 15. SBG Department of Civil PCCoE,2020-21 15 Doka formwork system(Table formwork system)
  • 16. SBG Department of Civil PCCoE,2020-21 16 Doka formwork system(Table formwork system)
  • 17. SBG Department of Civil PCCoE,2020-21 17 Doka formwork system(Table formwork system)
  • 18. 18 Doka formwork system(Table formwork system) ADVANTAGES ● HIGH LABOR PRODUCTIVITY (APPROX 8TO 10 SQ.M PER MAN- DAY) ● SIMPLE DESHUTTERING OPERATION ● MINIMIZES MAKING /ASSEMBLYTIME AND COST AT SITE ● ENTIREASSEMBLY CAN BE LIFTEDWITH CRANE ● SYSTEM IS RIGIDAND STABLE ● CLEANACCURATEAND SMOOTH CONCRETE FINISH
  • 19. 19 COFFOR formwork system COFFOR is a patented structural stay in place formwork system to build load bearing monolithic structures. It is composed of 2 filtering grids made of rib lathe reinforced by vertical stiffeners. The grids are connected by articulated rebar loops and connectors that fold for cost effective transportation.
  • 24. 24 COFFOR formwork system-Applications Under ground water tank Under ground Utility chamber
  • 26. 26 COFFOR formwork system-Applications Advantages- • LessVolume Required •No Shuttering Required •No Crane Required •Minimum Reinforcement •Less allied accessories required •Multiple Creative possibilities •Semi-skilled labour’s required •Less no of labour’s required •No honey comb in concrete •Easy installation of Electric and plumbing lines •Rapid Concrete Shrinkage
  • 31. 31 Mivan formwork system MIVAN technology is suitable for constructing large number of houses within short time using room size forms to construct walls and slabs in one continuous pour on concrete. PRE – CONCRETE ACTIVITIES: a) Receipt of Equipment on Site –The equipments is received in the site as ordered. b) Level Surveys – Level checking are made to maintain horizontal level check. c) Setting Out –The setting out of the formwork is done. d) Control / Correction of Deviation – Deviation or any correction are carried out. e) Erect Formwork –The formwork is erected on site. f) Erect Deck Formwork – Deck is erected for labours to work. g) Setting Kickers – kickers are provided over the beam.
  • 32. 32 Mivan formwork system On Concrete Activities- i. Dislodging of pins/wedges due to vibration. ii. Beam/deck props adjacent to drop areas slipping due to vibration. iii. Ensure all bracing at special areas slipping due to vibration. iv. Overspill of concrete at window opening etc. Post Concrete Activities- A) CLEANING: •All components should be cleaned with scrapers and wire brushes as soon as they are struck.Wire brush is to be used on side rails only. B)TRANSPORTING: •The heaviest and the longest, which is a full height of wall panel, can be carried up the nearest stairway. Passes through void areas. C) STRIKING: • Once cleaned and transported to the next point of erection, panels should be stacked at right place and in right order. D) Erecting of Formwork: •After that formwork is erect again on the next floor.
  • 34. 34 Mivan formwork system ADVANTAGES- The MIVAN formwork is specifically designed to allow rapid construction of all types of architectural layouts. 1) Cost effective. 2) It is more effective for mass housing to be done quickly. 3) Great construction speed. 4) High quality finish. 5) Erected using unskilled labor. 6) Panels can be reused up to 250 times.
  • 35. 35 Mivan formwork system Limitation of Mivan Formwork: 1) Because of small sizes finishing lines are seen on the concrete surfaces. 2) It requires uniform planning as well as uniform elevations to be cost effective. 3) Modifications are not possible as all members are caste in RCC. 4) Due to box-type construction shrinkage cracks are likely to appear. 5) Heat of Hydration is high due to shear walls.