The Palm Jumeirah in Dubai is a man-made archipelago built in the shape of a palm tree. It was an audacious engineering project that took over 8 years to complete. To build the massive artificial island, engineers had to overcome many challenges like stabilizing the sandy seabed, withstanding violent storms, and preventing stagnant water. They utilized advanced technologies and expertise from around the world. By compacting the island's base and adding openings to the breakwater, they ensured the structure could withstand earthquakes. Once stabilized, over 40,000 workers constructed the infrastructure to form an entire city with homes, hotels, shops, and amenities. When completed, the Palm Jumeirah had increased Dubai
Hello readers,
In this presentation, i am sharing Concept & Construction of Palm Island.
The following parameters are discussed in the presentation:
Where?
Why?
When?
Construction Machinery
Construction Steps
Conclusion.
basics on why the islands were planned , only palm jumeirah is completed and others are progressing , how they are being made and due to that the environmental impacts on sand , water , flora & fauna
Hello readers,
In this presentation, i am sharing Concept & Construction of Palm Island.
The following parameters are discussed in the presentation:
Where?
Why?
When?
Construction Machinery
Construction Steps
Conclusion.
basics on why the islands were planned , only palm jumeirah is completed and others are progressing , how they are being made and due to that the environmental impacts on sand , water , flora & fauna
Sea Port Construction, Project Execution PlanDavid H Moloney
Details of how a Sea Port is constructed, and how the progress, safety and quality will be monitored and controlled. Also the measures to ensure that the site is environmentally friendly.
For innovation in construction, use video presentations with 3D animations to plan and communicate how a project will be carried out and the timeline. This presentation can be used to communicate with the Client, Stakeholders and Site Team.
This presentation covers the civil engineering aspects of the construction and other challenges faced during the construction of the World Archipelago, Dubai.
An artificial island is an application of various engineering concepts that has brought a drastic change in construction technology. The artificial island is built in the sea, and the rig, oil and gas production equipment, public facilities, storage tank, and unloading terminal can be set on the island. Artificial island construction technology, which is based on civil engineering technology, is also closely related to marine engineering technology.
An artificial island is an island constructed by man rather than created by natural means. They are constructed by expanding the existing islets and by construction on existing reefs or merging some natural islets into a bigger island. They are usually constructed by land reclamation, but some are formed by the incidental isolation of an existing piece of land during canal construction. Land reclamation is a process where new land is created from oceans, river beds and lake beds. The land which is reclaimed is called reclamation ground. These types of structures help in the development of a nation and also become a source of income as a place of tourism. In countries like Japan the land space is usually less and artificial islands are thus helpful to such countries for avoiding crowd settlement of houses. The artificial islands are part of urbanization but they also create disorder to the balanced marine ecosystem.
Certificate
This is to certify that Tanishq Patil of class 12 of Sri Sri Ravishankar Vidya Mandir has successfully completed his project work for the subject ‘Chemistry’ for class XII practical examination of central board secondary education in the year 2022-23 . I further certify that this project is individual work of the student.
Internal
(Shailendra Patidar)
PGT Chemistry
External examiner:
Number:
External signature Principal’s signature
SAINIK SCHOOL AMARAVATHINAGAR
ACADEMIC YEAR : 2020-21
PROJECT REPORT ON
AUTO MOBILE SERVICE STATION
ROLL NO : 5973
NAME : S.SELVAKUMAR
CLASS : XII - A
SUBJECT : COMPUTER SCIENCE
SUB CODE : 083
PROJECT GUIDE: Mr PM JIGAJINNI
PGT (CS)
SAINIK SCHOOL AMARAVATHINAGAR
TIRUPPUR DIST
TAMILNADU
SAINIK SCHOOL AMARAVATHINAGAR
CERTIFICATE
This is to certify that Cadet S.SELVAKUMAR Roll No: 5973 has successfully completed the project Work entitledAUTO MOBILE SERVICESTATION in the subject Computer Science (083) laid down in the regulations of CBSE for the purpose of Practical Examination in Class XII to be held in Sainik School Amaravathinagaron______________.
(PM Jigajinni)
PGT Comp Sci
Master IC
Examiner:
Name: _______________
Signature:
TABLE OF CONTENTS [ T O C ]
SER DESCRIPTION PAGE NO
01 ACKNOWLEDGEMENT 04
02 INTRODUCTION 05
03 OBJECTIVES OF THE PROJECT 05
04 PROPOSED SYSTEM 06
05 SYSTEM DEVELOPMENT LIFE CYCLE (SDLC) 07
06 PHASES OF SYSTEM DEVELOPMENT LIFE CYCLE 08
07 FLOW CHART 15
08 SOURCE CODE 16
09 OUTPUT 19
10 TESTING 20
11 HARDWARE AND SOFTWARE REQUIREMENTS 23
12 BIBLIOGRAPHY 24
ACKNOWLEDGEMENT
Apart from the efforts of me, the success of any project depends largely on the encouragement and guidelines of many others. I take this opportunity to express my gratitude to the people who have been instrumental in the successful completion of this project.
I express deep sense of gratitude to almighty God for giving me strength for the successful completion of the project.
I express my heartfelt gratitude to my parents for constant encouragement while carrying out this project.
I gratefully acknowledge the contribution of the individuals who contributed in bringing this project up to this level, who continues to look after me despite my flaws,
I express my deep sense of gratitude to the luminary The Principal, Sainik School Amaravathinagar who has been continuously motivating and extending their helping hand to us.
I express my sincere thanks to the academician The Vice Principal, Sainik School Amaravathinagar, for constant encouragement and the guidance provided during this project
I am overwhelmed to express my thanks to The Administrative Officer for providing me an infrastructure and moral support while carrying out this project in the school.
My sincere thanks to Mr. Praveen M Jigajinni, Master In-charge, A guide, Mentor all the above a friend, who critiva
Deep sea mining is a new frontier for mining engineers. Sea floor holds the potential mineral that are vital for development which is not even explored, the advancement of technology in the time will enable to access reliable infrastructure and methods to extract sea floor without compromising the sustainability and eco friendly.
Technology is the usage and knowledge of tools, techniques, and crafts, or is systems or methods of organization, or is a material product (such as clothing) of these things.
Similar to Palm island Construction with Management 5 Ms (20)
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...BBPMedia1
Marvin neemt je in deze presentatie mee in de voordelen van non-endemic advertising op retail media netwerken. Hij brengt ook de uitdagingen in beeld die de markt op dit moment heeft op het gebied van retail media voor niet-leveranciers.
Retail media wordt gezien als het nieuwe advertising-medium en ook mediabureaus richten massaal retail media-afdelingen op. Merken die niet in de betreffende winkel liggen staan ook nog niet in de rij om op de retail media netwerken te adverteren. Marvin belicht de uitdagingen die er zijn om echt aansluiting te vinden op die markt van non-endemic advertising.
Tata Group Dials Taiwan for Its Chipmaking Ambition in Gujarat’s DholeraAvirahi City Dholera
The Tata Group, a titan of Indian industry, is making waves with its advanced talks with Taiwanese chipmakers Powerchip Semiconductor Manufacturing Corporation (PSMC) and UMC Group. The goal? Establishing a cutting-edge semiconductor fabrication unit (fab) in Dholera, Gujarat. This isn’t just any project; it’s a potential game changer for India’s chipmaking aspirations and a boon for investors seeking promising residential projects in dholera sir.
Visit : https://www.avirahi.com/blog/tata-group-dials-taiwan-for-its-chipmaking-ambition-in-gujarats-dholera/
Cracking the Workplace Discipline Code Main.pptxWorkforce Group
Cultivating and maintaining discipline within teams is a critical differentiator for successful organisations.
Forward-thinking leaders and business managers understand the impact that discipline has on organisational success. A disciplined workforce operates with clarity, focus, and a shared understanding of expectations, ultimately driving better results, optimising productivity, and facilitating seamless collaboration.
Although discipline is not a one-size-fits-all approach, it can help create a work environment that encourages personal growth and accountability rather than solely relying on punitive measures.
In this deck, you will learn the significance of workplace discipline for organisational success. You’ll also learn
• Four (4) workplace discipline methods you should consider
• The best and most practical approach to implementing workplace discipline.
• Three (3) key tips to maintain a disciplined workplace.
What are the main advantages of using HR recruiter services.pdfHumanResourceDimensi1
HR recruiter services offer top talents to companies according to their specific needs. They handle all recruitment tasks from job posting to onboarding and help companies concentrate on their business growth. With their expertise and years of experience, they streamline the hiring process and save time and resources for the company.
Personal Brand Statement:
As an Army veteran dedicated to lifelong learning, I bring a disciplined, strategic mindset to my pursuits. I am constantly expanding my knowledge to innovate and lead effectively. My journey is driven by a commitment to excellence, and to make a meaningful impact in the world.
[Note: This is a partial preview. To download this presentation, visit:
https://www.oeconsulting.com.sg/training-presentations]
Sustainability has become an increasingly critical topic as the world recognizes the need to protect our planet and its resources for future generations. Sustainability means meeting our current needs without compromising the ability of future generations to meet theirs. It involves long-term planning and consideration of the consequences of our actions. The goal is to create strategies that ensure the long-term viability of People, Planet, and Profit.
Leading companies such as Nike, Toyota, and Siemens are prioritizing sustainable innovation in their business models, setting an example for others to follow. In this Sustainability training presentation, you will learn key concepts, principles, and practices of sustainability applicable across industries. This training aims to create awareness and educate employees, senior executives, consultants, and other key stakeholders, including investors, policymakers, and supply chain partners, on the importance and implementation of sustainability.
LEARNING OBJECTIVES
1. Develop a comprehensive understanding of the fundamental principles and concepts that form the foundation of sustainability within corporate environments.
2. Explore the sustainability implementation model, focusing on effective measures and reporting strategies to track and communicate sustainability efforts.
3. Identify and define best practices and critical success factors essential for achieving sustainability goals within organizations.
CONTENTS
1. Introduction and Key Concepts of Sustainability
2. Principles and Practices of Sustainability
3. Measures and Reporting in Sustainability
4. Sustainability Implementation & Best Practices
To download the complete presentation, visit: https://www.oeconsulting.com.sg/training-presentations
Falcon stands out as a top-tier P2P Invoice Discounting platform in India, bridging esteemed blue-chip companies and eager investors. Our goal is to transform the investment landscape in India by establishing a comprehensive destination for borrowers and investors with diverse profiles and needs, all while minimizing risk. What sets Falcon apart is the elimination of intermediaries such as commercial banks and depository institutions, allowing investors to enjoy higher yields.
VAT Registration Outlined In UAE: Benefits and Requirementsuae taxgpt
Vat Registration is a legal obligation for businesses meeting the threshold requirement, helping companies avoid fines and ramifications. Contact now!
https://viralsocialtrends.com/vat-registration-outlined-in-uae/
LA HUG - Video Testimonials with Chynna Morgan - June 2024Lital Barkan
Have you ever heard that user-generated content or video testimonials can take your brand to the next level? We will explore how you can effectively use video testimonials to leverage and boost your sales, content strategy, and increase your CRM data.🤯
We will dig deeper into:
1. How to capture video testimonials that convert from your audience 🎥
2. How to leverage your testimonials to boost your sales 💲
3. How you can capture more CRM data to understand your audience better through video testimonials. 📊
Putting the SPARK into Virtual Training.pptxCynthia Clay
This 60-minute webinar, sponsored by Adobe, was delivered for the Training Mag Network. It explored the five elements of SPARK: Storytelling, Purpose, Action, Relationships, and Kudos. Knowing how to tell a well-structured story is key to building long-term memory. Stating a clear purpose that doesn't take away from the discovery learning process is critical. Ensuring that people move from theory to practical application is imperative. Creating strong social learning is the key to commitment and engagement. Validating and affirming participants' comments is the way to create a positive learning environment.
4. 5 Important Resources for any Business:5
M’s
Man
Material
MachineMoney
Market
5 M’s
A resource is a source or supply from which
benefit is produced.
For any Business,
there should be
the right innovations,
and these 5M’s are
important for the
overall achievement
of innovations.
+ 6th M
5. PALM
JUMEIRAH:
THE MAN-MADE ARTIFICIAL
ISLAND
• DUBAI : Stretching 5 1/2 kms from the Arabian
Gulf lies the most Audacious Engineering Project the
world has ever seen.
Palm Jumeirah is so vast it can be seen
from Space.
6. PURPOSE:
• Middle East, Dubai :
Jewel of the Arab World.
• Richest places built on
the Profit of its Oil
Reserves.
• Problem on the Horizon:
Oil Run Out.
• Disaster for the
Economy.
• New Source of
Income.
7. VISION:
• $2 Billion Plan – to save his
country.
• Ordered his Kingdom to
transform into Worlds No. 1
Luxury Tourist Destination.
• 5th M : Market
• Perfect Spot – Mass Tourism
• 5 million Tourists Annually
• Triple it to 15 million.
• 4th M : Money
8. OBJECTIVE
• Building a CITY at SEA.
• Covered with – Luxury Villas,
Apartment and Town homes,
Entertainment Areas,
Shopping Malls,
Restaurants, etc..
9. PROBLEM
• Coastline of Dubai –
72 kms long
• No enough space
– for extra 10 million
people
10. SOLUTION
• Extend Coastline
• Task – Nakheel
Constructions (held by
government of Dubai)
• Circular Island –
Increases Coastline by
7kms
11. HIGHER VISION
• Circular Island – extra 7
kms
• Why not 70 kms?
• Back to Drawing Board
• Prince works on Design- to
increase beachfront
12. THE DESIGN
• Paradise Island – shape
of a Palm Tree with
Crescent shape
Breakwater
• Coastline – Increased by
56 kms
• 9 times more than
circular island.
13. THE CHALLENGE
• To Blend with surroundings –
island must be entirely made of
natural materials, SAND and
ROCKs.
• Engineers must race against
time and battle constantly
against nature
byearthquakes, violent
storms and erosion from
the sea.
• Every day, engineers tried to
prevent the destruction of what
15. Breakwater Construction:
Man
• Coastal Researchers and Environmentalists
• Experts in Land Reclamation – The Dutch Team
• Developers - Nakheel Properties and Project Manager – Robert Berger
• Engineers – Best from Northern Europe and Holland
• Laborers – All over the globe
Materials
• Sand - 94 million cu. Mts.
• Rock - 5.5 million cu. Mts.
Machines
• Barges, Tugboats, Dredgers, Heavy Land based Machine, Floating
Cranes, etc
• Satellite
• GPS Technology
16. Coastal Research Team
• The Arabian Gulf: Perfect place to build this
mega structure.
• 160kms wide : too short
• 30m deep : too shallow
• Final Calculations : Breakwater must be 3m
high above the waves and 11 ½ kms long
For catastrophic waves
17. August 2001: Beginning
• Massive island is being
constructed out at sea, using
only natural materials, sand and
rock.
• Water causes erosion of sand
and rock..
• Every day, engineers were trying
to prevent the destruction of
what they built.
• They've only 2 years to build this
massive 11 ½ kms sea wall.
18. • 1st step: Build up the Sea
Floor.
• Machines required :
9barges, 15
tugboats, 4dredgers, 30
heavy land-based
machines and 10 floating
cranes.
Barges
Tugboats
Dredgers
heavy land
based
machines
19. • 3 massive dredgers take
up a thin layer of sand
from the barren sea bed
nearby.
• Dump the sand in a
layer up to 7.4 mts thick.
• This is done while the
sea is at its calmest.
20. To keep it in place, barge-loads of rubble are dropped on top of this.
This bed of rock will raise the breakwater from 4m below sea level to 3m above.
21. Need of Rocks:
• Sourcing Rock - blasted out of the
mountains.
• Rocks are piled onto barges and
shipped to the construction site.
• Each Rock - 6 tons.
• 40,000 tons of rocks are delivered per
day.
• The density, size, strength and
permeability of each boulder is crucial.
• Positioned by cranes, each rock must
interlock with the next to withstand the
full force of the sea.
• This stone wall must last for centuries.
22. Constant Check:
• Breakwater is in the right
place and the rocks are stable.
• Send in divers to pinpoint and
check every meter of it.
• A detailed study of the
breakwater rocks below the
water is noted.
• Every 27 mts, a diver surfaces
to record the location of the
rocks they're checking.
• The reading is taken from a
man based on land.
23. April 2002: Need for Sand
• Desert sand - wrong material,
too fine particles to cling
together.
• Sand: coarse, packs densely and
is more resistant to wave impact.
• Sand found at 6 miles out at sea.
• Pumped through a pipe and
sprayed into place at 10 mps.
• This process is called
Rainbowing.
• The rainbowed sand builds into a
sandbar, rising up to 4mt out of
the water.
24. The Fear: Is the Palm going in shape?
• Doubt on construction
- Dubai has a trick 676
kms up in space.
• Access to the only
privately-owned
satellite in the world.
• The satellite, IKONOS,
orbits the Earth, taking
pictures that prove the
island is totally on
track.
25. August 2002: Mould Palm Shape Accurately
• Shaping Accurately – using
state-of-the-art technology.
• Team of five men - walks
the perimeter of the island
every day as it takes shape.
• Heavy packs strapped at
back, these mobile
receivers create a grid
reference for the island.
26. GPS Technology:
• Receiving signals from
space and a fixed
position on land, the
height and position of
the sand bars is
recorded.
• With these coordinates,
dredgers can sail into
the exact position and
rainbow the sand with
pinpoint accuracy.
27. October 2002: Water Stagnant
• Sea not circulating
around.
• Tides are not flushing
the system properly.
• Clean water is not
moving fast enough
round the inner
waterway.
• The water is in serious
danger of becoming
stagnant.
28. A Small Change:
• 2 Breaks in sea wall.
• 2 four-lane bridges link the
sections of the breakwater.
• 2 openings - enough fresh
flowing water can get into
system.
• Twice a day, the tide enters
the structure, pushing
clean water around the
fronds.
• 2 weeks - the entire
waterway is replenished.
29. Testing Water
• Environmentalists - test
the water every day to
check that the system is
working.
• The return of algae and
stagnant water is
something they can't
allow.
• With the water quality
assured, the project is
back on track.
30. August 2003: Breakwater Completed
• The island reclamation
is finished.
• Palm Island has 3 major
parts : The
Crescent, The Trunk
and The Fronds.
31. Long Way to Go
• Stage 1 is only
completed.
• Now to fulfill the
crown prince's
dream.
• This sand island must
support an entire city.
32. December 2003: Wake-up Call
• Bam in Iran - earthquake
measuring a massive 6.6
• Multiple quakes hit Dubai
480 kms across the
Arabian Gulf.
• It's a wake-up call to the
palm island project.
• If the epicentre hit Dubai,
it could spell disaster.
33. Liquefaction
• Lateral forces of an earthquake can
make the island disappear.
• This terrifying phenomenon is called
liquefaction.
• It happens when a quake shakes the
Earth's surface, causing sand particles
to move.
• As the sand compacts, it pushes the
water between the particles
upwards, making the ground liquefy.
• It means the island would sink back
into the sea.
34. Strong Base:
• Support this city at sea.
• Before any houses can be built,
Island must be made strong
enough to prevent it from
liquefaction.
• The engineers work out, they need
to compact a layer of sand 12 mts
deep, too deep to compact by
normal road roller.
• The only solution is a process
called Vibrocompaction.
35. January 2004: Vibrocompaction
• 15 machines - to firm up the land.
• Probes drill over 200,000 holes
into the ground across the surface
of the island.
• High-pressure water and air drives
each probe deep into the earth.
• This shaft then vibrates, shaking
the ground around it.
• The earth is compacted.
• As the sand compacts and
sinks, more sand is poured in until
the area around the probes is rock
solid.
• It takes the team 8 months to
stabilize the 17 palm fronds, but it
has to be done to ensure the
safety of 120,000 people who will
live and work here.
36. March 2004: Building Site
• Thousands of trucks
and cranes, tons of
supplies, and 2,000
labourers descend on
the island.
• This is the most
complicated part of the
project, the installation
of the infrastructure.
• Gas pipes, electricity
cables, water supply
and buildings.
• In two years, they must
build an entire city at
sea.
37. January 2005: Critical Stage
• Now engineers turn their
attention from sand and rock
to concrete, glass and steel.
• 850 buses ferry the 40,000-
strong Asian workforce on and
off the island in two 12-hour
shifts. They'll work in gruelling
temperatures of up to 48
degrees Celsius.
• As well as thousands of people,
millions of tons of concrete
and steel are shipped in from
around the world and driven
onto the palm.
• Fifty-one different contractors
build houses, roads, canals,
shopping centres, sewage
plants, and each part of the
jigsaw must meet the next
perfectly.
38. August 2006: The First Release
• The 3rd stage of the Project.
• When the palm was first
released to the public, all the
houses were sold in just 3
days.
• The most expensive go for
$1.2 million.
• David Beckham and the
England football team are
amongst the owners.
• There are over 1800 villas still
to build on the palm fronds.
• The deadline of 2008 should
be met.
44. The 17 Fronts: These
are leaf shaped part
of the island
consisting thousands
of villas on the two
sides with private
beach and a road in
the middle.
46. The Crescent: It
is the curved
shape around the
palm island
whose total
length is of
12kms. The
famous hotel
ATLANTIS is
located at the
middle of the
crescent.
54. • The palm island puts DUBAI on the MAP.
• So far, the palm island is completely SOLD OUT.
• The island stands here against the nature, proving
that engineers can and will continually push the
boundaries of engineering technology, and how a
perfect management and effective utilization of all
resources can create wonders in world.
• The palm island is truly an awesome mega
structure the world have ever seen.