SlideShare a Scribd company logo
ANNUAL TURNAROUND JUNE 2015 Page | 1
REPORT ON PRIMARY
REFORMER
CATALYST
UNLOADING AND
LOADING
ANNUAL TURNAROUND JUNE 2015 Page | 2
PRIMARY REFORMER CATALYST REPLACEMENT PLANNED JOB FOR
ANNUAL TURNAROUND 2015 AT MANGALORE CHEMICALS AND
FERTILIZERS LIMITED, PANAMBUR, MANGALORE, KARNATAKA- 575010.
PROCESS CREW MEMBERS
 K. SELVAN
 DHARMARAJ. D. D
 K. P. DEVADIGA
 PRASHANT. A
 SHARATH. A
 SILAMBARASAN
 PRASHANTH. K
 VINAYA
 ABHAY
 ABDUL
 ROHIT
 BHARATH
 JEEVAN
 YASHWANTH
 SACHIN
ANNUAL TURNAROUND JUNE 2015 Page | 3
SUMMARY
After the successful operational period for the year 2014-2015, inspection of
primary reformer tubes and replacement of primary reformer catalyst was planned to
provide solution for the high reformer tube skin temperatures.
Sud Chemie (Catalyst Supplying Firm) took the initiative of supplying the two
layered catalyst for the primary reformer. Catalyst was made available as per our
requirement with bottom layer having 42% of Ni Catalyst (Reformax 330 G90 LDP- 10
hole- 19*16mm) and 58% of NiK Catalyst (Reformax 250- 5 hole- 16*16mm).
Bottom layer catalyst:
REFORMAX 330 G90 LDP (10 hole) - 19*16mm
49 drums of new catalyst and 1 drum of old catalyst were available.
Drum info- Net weight- 156 kgs/Gross weight- 176 kgs/Volume- 200 liters.
Density- 780 kg/m3.
ANNUAL TURNAROUND JUNE 2015 Page | 4
Top layer catalyst:
REFORMAX 250 (5 hole)- 16*16mm
68 drums of new catalyst were available.
Drum info- Net weight- 216 kgs/Gross weight- 236 kgs/Volume- 200 liters.
Density- 1080 kg/m3.
CR- Asia was given the contract for unloading and uniform loading of primary
reformer catalysts. Services included reformer tubes counter weight adjustment, tube
flanges bolt loosening/tightening (without hammer- pneumatic torque allowed), shifting of
spent/new catalyst drums, visual display of individual reformer tube internal surface with
video cam assembly, for spent catalyst sampling, empty/loaded catalyst dip and differential
pressure (DP) checking, catalyst unloading by BIVAC pump and loading by UNIDENSE
method.
ANNUAL TURNAROUND JUNE 2015 Page | 5
DETAILED REPORT
After planned ammonia plant shutdown, reformer cooling using inert gas (Nitrogen)
was prolonged for LTCO convertor bed cooling (@1000 hours on 10th June, 2015).
Depressurization of front end was done at HT guard inlet vent point after isolating HTCO
convertor inlet isolation valve. After depressurizing, following jobs were done in the
mentioned order (Jobs completed in approximately 8 hours)-
 Reformer feed spaded (FRRC-203 d/s)
 Make gas boiler(H201) outlet spaded
 Reformer furnace man way covers opened
 Reformer outlet T-plug removed
 All reformer burner guns removed
 Demineralized water flushing done for fuel naphtha header towards raw naphtha
storage tank
 Reformer fuel naphtha strainer spaded (SM1 u/s)
 Reformer tube counter weight locked
 Reformer tube and pigtail flanges insulation removed
All 224 tube flanges bolt removal initiated. Long pigtail to short pigtail flange
removed and respective orifices positions were marked and tied to the same flanges (Jobs
completed in approximately 24 hours).
Unloading of primary reformer was started at 1825 hours on 10th June, 2015. CR-
Asia BIVAC with a single hose was used for unloading with vacuum reading of -350 mm
Hg/-0.135 inch Hg. Dust sample was collected from bottom T- plug and handed over to Q/C
& Lab for analyzing. With completion of catalyst unloading for “A” & “B” row, rigs for
measuring differential pressure across tubes were being made ready for MCFL rig. [Note: A
second vacuum hose was made ready and utilized to accelerate the catalyst unloading
process. A metal tip nozzle was being used in case of compacted spent catalyst unloading. A
mark with tape was made on each hose being inserted into tubes to make sure the catalyst
support grid was not being damaged for every tube.]
ANNUAL TURNAROUND JUNE 2015 Page | 6
Spent catalyst sampling was done for the following tubes A24, A44, A48, B16 and
D16. As decided, samples were collected at heights of 3m, 6m and 9m for all the 5 tubes.
Reformer catalyst unloading for all 224 tubes was completed on 12th June, 2015 (Job
completed in approximately 48 hours). The spent catalyst was being collected in the
provided Mangala Urea bags and shifted to the reformer bottom shed. All 224 tubes empty
dip readings were noted down. Later that night at 2230 hours, all reformer tubes inner
surface cleaning by stainless steel wire mesh was initiated. To extract the excess scale
formation inside the reformer tubes, arrangement was made with a buffing plate (Diameter
100mm) having connected rods (threaded with nut and bolt) for extension as the plate
moves inside the tube. As the assembly was not much efficient and the potential risk of it
getting clogged was more, the arrangement was rejected.
Simultaneously bottom layer Ni catalyst drums were being shifted from the storage
area to shed (reformer bottom area) and top layer NiK catalyst to shed (stores area). [Note:
Catalyst drums were being shifted in absence of rain. Drum rolling to be avoided. Keep the
drums on wooden pallets, avoid stacking them up. Protect from rain and stagnant water by
providing tarpaulin cover. Keep the lids on, avoid catalyst exposure and do not damage the
drums.]
DP measurement details:
CR-ASIA DP apparatus orifice diameter: 8mm.
MCF DP rig orifice downstream hose length/diameter: 6.00mts/ 0.75”.
Orifice u/s instrument air maintained pressure: 4.00 kg/cm2. (Transmitter range: 0-10
kg/cm2.g).
Orifice d/s pressure indicates DP. (Transmitter range: 0-4 kg/cm2.g).
ANNUAL TURNAROUND JUNE 2015 Page | 7
Inner deposits collected from some of
the reformer tubes.
Composition:
Nickel 33.91%
Iron 18.65%
Chromium 05.16%
Aluminum 0.42%
Calcium 0.12%
Magnesium 0.062%
Copper 0.08%
Potash 0.062%
Vanadium 0.035%
Lead ND
Sulfides as S <10ppm
Chloride <1ppm
Sulfate <1ppm
Phosphate <1ppm
After the cleaning of tubes, visual inspection was done using the video cam and
remote display. D31 reformer tube catalyst grid support was found damaged (On 16th
June, 2015). At the same time dip readings and DP checking across empty tube (with MCFL
rig) was initiated and completed. It was replaced with a new grid support and was cross
checked with the old dip and DP readings. CR-Asia rig connections were made ready and
DP checking for each reformer tube was initiated.
At reformer top; arrangement were being made for catalyst weighing, catalyst dust
blowing, protection from rain and provision of breeze free surroundings. Some reformer
tubes (49 in nos.) having DP values (with CR-Asia rig) more than 0.04kg/cm2.g were
decided to be cleaned again by removal of catalyst grid support. After tube cleaning and
checking the improved DP readings for the respective tubes, catalyst grid supports were
boxed up and clearance was given for catalyst loading (On 1600 hrs on 19th June, 2015).
ANNUAL TURNAROUND JUNE 2015 Page | 8
Test loading of first layer (Ni) catalyst was done for the first tube of each row i.e. A1,
B1, C1 and D1 in presence of Sud Chemie representative. Dip and DP readings were noted
down as a reference value for rest of the tubes. It was decided to go ahead with 5 buckets of
catalyst for each tube weighing 7kgs. Supervision was deputed to employees to follow up
the catalyst weighing, catalyst drum being utilized and correctional weight for each tube.
[Note- Weighing machine was deployed from ABC plant to weigh catalyst for loading.
Instrument air connection was provided from PICV-2211 tapping for checking reformer tube
DP and catalyst dust blowing. A separate instrument air connection was provided from F-
4210 area for air wench to lift catalyst drums.]
As catalyst available was close to the amount needed after loading “A” and “B” row
tubes, it was decided to load remaining tubes with maximum of 36kgs till all tubes are
covered. Dip readings were noted of all reformer tubes filled with Ni catalyst. Later dip
corrections were done by additional top up for selective tubes to get the dip reading closer
to 7.2m (Completed by 0700hrs on 21st June, 2015). DP readings for all tubes with Ni
catalyst were noted down with CR-Asia rig and later with MCFL rig. As for the Ni catalyst
loading, all new catalyst was utilized and 1 drum old catalyst weighing 112.8kg/141liters
was unutilized which was shifted to DAP plant storage.
After getting approval of DP and dip readings, clearance was given for loading of
second layer (NiK) catalyst. Test loading was done for first tube of each row i.e. A1, B1, C1
and D1. Dip and DP readings were noted down as a reference value for the rest of the tubes.
It was decided to go ahead with 7 buckets for each tube weighing 10kgs. After loading of
NiK catalyst for all tubes, dip readings were noted down and correction were done by
additional top up for selective tubes to get the dip reading closer to 0.8m (Completed by
0600hrs on 23rd June, 2015). DP readings for NiK catalyst were noted down using CR-Asia
and later with MCFL rig. DP correction was done for B1 and B49 tubes as the respective DP
readings were on the lower side. For NiK catalyst, 3 full drums of catalyst and a partly filled
drum was shifted to catalyst storage (725 liters in total).
ANNUAL TURNAROUND JUNE 2015 Page | 9
After getting of approval of DP and dip readings, it was decided to box up all
reformer tube flanges. Later orifices and long pigtail to short pigtail flanges were boxed up.
Reformer tubes counter weights were released properly. Housekeeping was done at
reformer top and insulation job was kept pending as high pressure leak test and flange
bolts hot tightening had to be done. Instrument air connections were normalized for TICV-
211 and TI-231. Empty drums were filled with spent catalyst and content displaying
hazardous sticker was pasted on each drum.
DIP HEIGHTS FIXED FOR LOADING
 Empty dip height from tube top flange to the catalyst support grid- 11.83 meters.
 Empty dip height from tube top flange to the top surface of Reformax330 (G90 LDP-
10 holed) catalyst- 7.20 meters.
 Empty dip height from tube top flange to the top surface of Reformax250 (5 holed)
catalyst- 0.80 meters.
 Allowable DP variation from average DP of 224 tubes- +3% to -3%.
AVERAGE TUBE DP AFTER EACH LAYER OF CATALYST LOADING WITH CR-ASIA RIG
Average tube DP after loading Reformax 330-G90 LDP catalyst- 0.1837 bar.g
Average tube DP after loading Reformax 250 catalyst- 0.5462 bar.g
CATALYST CONSUMPTION FOR ALL 224 TUBES
Total Reformax 330-G90 LDP catalyst utilized- 8138.156 kilograms.
Total Reformax 250 catalyst utilized- 15160.843 kilograms.
Hence, total catalyst utilized- 23298.999 kilograms.
ANNUAL TURNAROUND JUNE 2015 Page | 10
APPROXIMATE TIME REQUIREMENT:
 Time required for T plug dropping. : 05 hrs
 Time required for reformer tube to : 25.50 hrs
short pigtail flange & short pigtail.
to long pigtail flange disconnection.
 Time required for catalyst unloading. : 52.50 hrs
 Time require for tube inner surface cleaning
and tube visual inspection. : 88 hrs.
 Dead time due to reformer tube inspection : 06 hrs.
 Time required for catalyst support grid
removal, cleaning and box up. Empty tube
DP measurement was done simultaneously. : 56 hrs.
 Time required for Reformax-330-G90 LDP
catalyst loading. : 30 hrs
 Dead time due to power failure. : 01 hrs.
 Time required for 1st layer catalyst
dip and DP measurement/adjustment. : 08 hrs.
 Time required for Reformax-250 catalyst
loading. : 48.50hrs
 Time required for 2nd layer catalyst
dip and DP measurement/adjustment. : 12 hrs.
 Time required for tubes boxing up. : 36 hrs
 Time required for t plug boxing up. : 05hrs
 Dead time due to radiography. : 08 hrs
 Total time required. : 381.50 hrs

More Related Content

What's hot

Theory and Operation - Secondary Reformers -
Theory and Operation - Secondary Reformers - Theory and Operation - Secondary Reformers -
Theory and Operation - Secondary Reformers -
Gerard B. Hawkins
 
Reduction & Startup of Pre-reforming Catalysts
Reduction & Startup of Pre-reforming CatalystsReduction & Startup of Pre-reforming Catalysts
Reduction & Startup of Pre-reforming Catalysts
Gerard B. Hawkins
 
Ammonia Plant - Secondary Reforming
Ammonia Plant - Secondary ReformingAmmonia Plant - Secondary Reforming
Ammonia Plant - Secondary Reforming
Gerard B. Hawkins
 
Ammonia Formation over Steam Reforming Catalysts
Ammonia Formation over Steam Reforming CatalystsAmmonia Formation over Steam Reforming Catalysts
Ammonia Formation over Steam Reforming Catalysts
Gerard B. Hawkins
 
Shift Conversion Catalysts - Operating Manual
Shift Conversion Catalysts - Operating ManualShift Conversion Catalysts - Operating Manual
Shift Conversion Catalysts - Operating Manual
Gerard B. Hawkins
 
Steam Reforming - Catalyst Loading
Steam Reforming - Catalyst LoadingSteam Reforming - Catalyst Loading
Steam Reforming - Catalyst Loading
Gerard B. Hawkins
 
A presentation on reformer new
A presentation on reformer newA presentation on reformer new
A presentation on reformer new
Gowri Shankar
 
Steam Reforming - Poisons
Steam Reforming - PoisonsSteam Reforming - Poisons
Steam Reforming - Poisons
Gerard B. Hawkins
 
Steam Reforming - Common Problems
Steam Reforming - Common ProblemsSteam Reforming - Common Problems
Steam Reforming - Common Problems
Gerard B. Hawkins
 
Feedstock Purfication in Hydrogen Plants
Feedstock Purfication in Hydrogen PlantsFeedstock Purfication in Hydrogen Plants
Feedstock Purfication in Hydrogen Plants
Gerard B. Hawkins
 
Pressure Relief Systems Vol 2
Pressure Relief Systems   Vol 2Pressure Relief Systems   Vol 2
Pressure Relief Systems Vol 2
Gerard B. Hawkins
 
Ammonia plant fundamentals
Ammonia plant fundamentalsAmmonia plant fundamentals
Ammonia plant fundamentals
Prem Baboo
 
Amine Gas Treating Unit - Best Practices - Troubleshooting Guide
Amine Gas Treating Unit  - Best Practices - Troubleshooting Guide Amine Gas Treating Unit  - Best Practices - Troubleshooting Guide
Amine Gas Treating Unit - Best Practices - Troubleshooting Guide
Gerard B. Hawkins
 
The Benefits and Disadvantages of Potash in Steam Reforming
The Benefits and Disadvantages of Potash in Steam ReformingThe Benefits and Disadvantages of Potash in Steam Reforming
The Benefits and Disadvantages of Potash in Steam Reforming
Gerard B. Hawkins
 
Ammonia Synthesis Flowsheet - Operator training
Ammonia Synthesis Flowsheet - Operator trainingAmmonia Synthesis Flowsheet - Operator training
Ammonia Synthesis Flowsheet - Operator training
Gerard B. Hawkins
 
Ammonia CO2 Removal Systems
Ammonia CO2 Removal SystemsAmmonia CO2 Removal Systems
Ammonia CO2 Removal Systems
Gerard B. Hawkins
 
Steam Reforming - Types of Reformer Design
Steam Reforming - Types of Reformer DesignSteam Reforming - Types of Reformer Design
Steam Reforming - Types of Reformer Design
Gerard B. Hawkins
 
Start Up Procedures for Primary Reforming Catalyst
Start Up Procedures for Primary Reforming CatalystStart Up Procedures for Primary Reforming Catalyst
Start Up Procedures for Primary Reforming Catalyst
Gerard B. Hawkins
 
Normal Operation of Steam Reformers on Hydrogen Plants
Normal Operation of Steam Reformers on Hydrogen PlantsNormal Operation of Steam Reformers on Hydrogen Plants
Normal Operation of Steam Reformers on Hydrogen Plants
Gerard B. Hawkins
 
Hydrocarbon Feed Purification for Ammonia Plants
Hydrocarbon Feed Purification for Ammonia PlantsHydrocarbon Feed Purification for Ammonia Plants
Hydrocarbon Feed Purification for Ammonia Plants
Gerard B. Hawkins
 

What's hot (20)

Theory and Operation - Secondary Reformers -
Theory and Operation - Secondary Reformers - Theory and Operation - Secondary Reformers -
Theory and Operation - Secondary Reformers -
 
Reduction & Startup of Pre-reforming Catalysts
Reduction & Startup of Pre-reforming CatalystsReduction & Startup of Pre-reforming Catalysts
Reduction & Startup of Pre-reforming Catalysts
 
Ammonia Plant - Secondary Reforming
Ammonia Plant - Secondary ReformingAmmonia Plant - Secondary Reforming
Ammonia Plant - Secondary Reforming
 
Ammonia Formation over Steam Reforming Catalysts
Ammonia Formation over Steam Reforming CatalystsAmmonia Formation over Steam Reforming Catalysts
Ammonia Formation over Steam Reforming Catalysts
 
Shift Conversion Catalysts - Operating Manual
Shift Conversion Catalysts - Operating ManualShift Conversion Catalysts - Operating Manual
Shift Conversion Catalysts - Operating Manual
 
Steam Reforming - Catalyst Loading
Steam Reforming - Catalyst LoadingSteam Reforming - Catalyst Loading
Steam Reforming - Catalyst Loading
 
A presentation on reformer new
A presentation on reformer newA presentation on reformer new
A presentation on reformer new
 
Steam Reforming - Poisons
Steam Reforming - PoisonsSteam Reforming - Poisons
Steam Reforming - Poisons
 
Steam Reforming - Common Problems
Steam Reforming - Common ProblemsSteam Reforming - Common Problems
Steam Reforming - Common Problems
 
Feedstock Purfication in Hydrogen Plants
Feedstock Purfication in Hydrogen PlantsFeedstock Purfication in Hydrogen Plants
Feedstock Purfication in Hydrogen Plants
 
Pressure Relief Systems Vol 2
Pressure Relief Systems   Vol 2Pressure Relief Systems   Vol 2
Pressure Relief Systems Vol 2
 
Ammonia plant fundamentals
Ammonia plant fundamentalsAmmonia plant fundamentals
Ammonia plant fundamentals
 
Amine Gas Treating Unit - Best Practices - Troubleshooting Guide
Amine Gas Treating Unit  - Best Practices - Troubleshooting Guide Amine Gas Treating Unit  - Best Practices - Troubleshooting Guide
Amine Gas Treating Unit - Best Practices - Troubleshooting Guide
 
The Benefits and Disadvantages of Potash in Steam Reforming
The Benefits and Disadvantages of Potash in Steam ReformingThe Benefits and Disadvantages of Potash in Steam Reforming
The Benefits and Disadvantages of Potash in Steam Reforming
 
Ammonia Synthesis Flowsheet - Operator training
Ammonia Synthesis Flowsheet - Operator trainingAmmonia Synthesis Flowsheet - Operator training
Ammonia Synthesis Flowsheet - Operator training
 
Ammonia CO2 Removal Systems
Ammonia CO2 Removal SystemsAmmonia CO2 Removal Systems
Ammonia CO2 Removal Systems
 
Steam Reforming - Types of Reformer Design
Steam Reforming - Types of Reformer DesignSteam Reforming - Types of Reformer Design
Steam Reforming - Types of Reformer Design
 
Start Up Procedures for Primary Reforming Catalyst
Start Up Procedures for Primary Reforming CatalystStart Up Procedures for Primary Reforming Catalyst
Start Up Procedures for Primary Reforming Catalyst
 
Normal Operation of Steam Reformers on Hydrogen Plants
Normal Operation of Steam Reformers on Hydrogen PlantsNormal Operation of Steam Reformers on Hydrogen Plants
Normal Operation of Steam Reformers on Hydrogen Plants
 
Hydrocarbon Feed Purification for Ammonia Plants
Hydrocarbon Feed Purification for Ammonia PlantsHydrocarbon Feed Purification for Ammonia Plants
Hydrocarbon Feed Purification for Ammonia Plants
 

Viewers also liked

Steam Reformer Surveys - Techniques for Optimization of Primary Reformer Oper...
Steam Reformer Surveys - Techniques for Optimization of Primary Reformer Oper...Steam Reformer Surveys - Techniques for Optimization of Primary Reformer Oper...
Steam Reformer Surveys - Techniques for Optimization of Primary Reformer Oper...
Gerard B. Hawkins
 
Catalyst Selection - Buy Model Overview
Catalyst Selection - Buy Model OverviewCatalyst Selection - Buy Model Overview
Catalyst Selection - Buy Model Overview
arisy
 
Pooja joshy organiations study at sud chemie
Pooja joshy organiations study at sud chemiePooja joshy organiations study at sud chemie
Pooja joshy organiations study at sud chemieLibu Thomas
 
60167331 secondary-reformer
60167331 secondary-reformer60167331 secondary-reformer
60167331 secondary-reformer
Khai Huynh
 
Finalized readings (mcfl rig).
Finalized readings (mcfl rig).Finalized readings (mcfl rig).
Finalized readings (mcfl rig).
Dharmaraj Daddikar
 
Catalyst unloading details
Catalyst unloading detailsCatalyst unloading details
Catalyst unloading details
Dharmaraj Daddikar
 
SOUTHERN PETROCHEMICALS INDUSTRIES CORPORATION LIMITED
SOUTHERN PETROCHEMICALS INDUSTRIES CORPORATION LIMITEDSOUTHERN PETROCHEMICALS INDUSTRIES CORPORATION LIMITED
SOUTHERN PETROCHEMICALS INDUSTRIES CORPORATION LIMITEDDharmaraj Daddikar
 
PREPARATION FOR BOILER FEED WATER PRODUCTION
PREPARATION FOR BOILER FEED WATER PRODUCTIONPREPARATION FOR BOILER FEED WATER PRODUCTION
PREPARATION FOR BOILER FEED WATER PRODUCTIONDharmaraj Daddikar
 
Chapter 6c -_ht_design_consideration_-_latest
Chapter 6c -_ht_design_consideration_-_latestChapter 6c -_ht_design_consideration_-_latest
Chapter 6c -_ht_design_consideration_-_latest
Helena Francis
 
Chapter 6b -_hydrotreating_hds_catalyst
Chapter 6b -_hydrotreating_hds_catalystChapter 6b -_hydrotreating_hds_catalyst
Chapter 6b -_hydrotreating_hds_catalyst
Helena Francis
 
Key Considerations for a Reforming Unit Revamp
Key Considerations for a Reforming Unit RevampKey Considerations for a Reforming Unit Revamp
Key Considerations for a Reforming Unit Revamp
Gerard B. Hawkins
 
Synthesis catalyst converter explanation
Synthesis catalyst converter explanationSynthesis catalyst converter explanation
Synthesis catalyst converter explanation
Dharmaraj Daddikar
 
Catalysis in hydtotreating and hydrocracking
Catalysis in hydtotreating and hydrocrackingCatalysis in hydtotreating and hydrocracking
Catalysis in hydtotreating and hydrocracking
Kaneti Pramod
 
PD230 Catalytic Reforming
PD230 Catalytic ReformingPD230 Catalytic Reforming
PD230 Catalytic Reforming
petroEDGE
 
VULCAN VGP-1000 High Temperature Mn Sulfur Guard Technology
VULCAN VGP-1000 High Temperature Mn Sulfur Guard TechnologyVULCAN VGP-1000 High Temperature Mn Sulfur Guard Technology
VULCAN VGP-1000 High Temperature Mn Sulfur Guard Technology
Gerard B. Hawkins
 
final thesis
final thesisfinal thesis
final thesisAli Raza
 

Viewers also liked (19)

Steam Reformer Surveys - Techniques for Optimization of Primary Reformer Oper...
Steam Reformer Surveys - Techniques for Optimization of Primary Reformer Oper...Steam Reformer Surveys - Techniques for Optimization of Primary Reformer Oper...
Steam Reformer Surveys - Techniques for Optimization of Primary Reformer Oper...
 
Catalyst Selection - Buy Model Overview
Catalyst Selection - Buy Model OverviewCatalyst Selection - Buy Model Overview
Catalyst Selection - Buy Model Overview
 
Pooja joshy organiations study at sud chemie
Pooja joshy organiations study at sud chemiePooja joshy organiations study at sud chemie
Pooja joshy organiations study at sud chemie
 
60167331 secondary-reformer
60167331 secondary-reformer60167331 secondary-reformer
60167331 secondary-reformer
 
Finalized readings (mcfl rig).
Finalized readings (mcfl rig).Finalized readings (mcfl rig).
Finalized readings (mcfl rig).
 
Catalyst unloading details
Catalyst unloading detailsCatalyst unloading details
Catalyst unloading details
 
HALDIA PETROCHEMICALS LIMITED
HALDIA PETROCHEMICALS LIMITEDHALDIA PETROCHEMICALS LIMITED
HALDIA PETROCHEMICALS LIMITED
 
SOUTHERN PETROCHEMICALS INDUSTRIES CORPORATION LIMITED
SOUTHERN PETROCHEMICALS INDUSTRIES CORPORATION LIMITEDSOUTHERN PETROCHEMICALS INDUSTRIES CORPORATION LIMITED
SOUTHERN PETROCHEMICALS INDUSTRIES CORPORATION LIMITED
 
Hydrogen Recovery
Hydrogen RecoveryHydrogen Recovery
Hydrogen Recovery
 
PREPARATION FOR BOILER FEED WATER PRODUCTION
PREPARATION FOR BOILER FEED WATER PRODUCTIONPREPARATION FOR BOILER FEED WATER PRODUCTION
PREPARATION FOR BOILER FEED WATER PRODUCTION
 
Chapter 6c -_ht_design_consideration_-_latest
Chapter 6c -_ht_design_consideration_-_latestChapter 6c -_ht_design_consideration_-_latest
Chapter 6c -_ht_design_consideration_-_latest
 
Chapter 6b -_hydrotreating_hds_catalyst
Chapter 6b -_hydrotreating_hds_catalystChapter 6b -_hydrotreating_hds_catalyst
Chapter 6b -_hydrotreating_hds_catalyst
 
Key Considerations for a Reforming Unit Revamp
Key Considerations for a Reforming Unit RevampKey Considerations for a Reforming Unit Revamp
Key Considerations for a Reforming Unit Revamp
 
Synthesis catalyst converter explanation
Synthesis catalyst converter explanationSynthesis catalyst converter explanation
Synthesis catalyst converter explanation
 
Catalysis in hydtotreating and hydrocracking
Catalysis in hydtotreating and hydrocrackingCatalysis in hydtotreating and hydrocracking
Catalysis in hydtotreating and hydrocracking
 
catalytic reforming
catalytic reformingcatalytic reforming
catalytic reforming
 
PD230 Catalytic Reforming
PD230 Catalytic ReformingPD230 Catalytic Reforming
PD230 Catalytic Reforming
 
VULCAN VGP-1000 High Temperature Mn Sulfur Guard Technology
VULCAN VGP-1000 High Temperature Mn Sulfur Guard TechnologyVULCAN VGP-1000 High Temperature Mn Sulfur Guard Technology
VULCAN VGP-1000 High Temperature Mn Sulfur Guard Technology
 
final thesis
final thesisfinal thesis
final thesis
 

Similar to Reformer Catalyst Report

Nitrogen purging
Nitrogen  purgingNitrogen  purging
Nitrogen purging
Dermawan Tarigan
 
Stakeholder weekly report-20th May 2023.pptx
Stakeholder weekly report-20th May 2023.pptxStakeholder weekly report-20th May 2023.pptx
Stakeholder weekly report-20th May 2023.pptx
balajikollu3
 
Experimental Analysis of Heat Transfer Enhancement in a Double Pipe Heat Exch...
Experimental Analysis of Heat Transfer Enhancement in a Double Pipe Heat Exch...Experimental Analysis of Heat Transfer Enhancement in a Double Pipe Heat Exch...
Experimental Analysis of Heat Transfer Enhancement in a Double Pipe Heat Exch...
IRJET Journal
 
A case study of thinning of ng (natural gas) injection line in mp section bef...
A case study of thinning of ng (natural gas) injection line in mp section bef...A case study of thinning of ng (natural gas) injection line in mp section bef...
A case study of thinning of ng (natural gas) injection line in mp section bef...
Prem Baboo
 
Report steffones
Report steffonesReport steffones
Report steffones
Steffones K
 
GNFC problems.pdf
GNFC problems.pdfGNFC problems.pdf
GNFC problems.pdf
ManishaRathee3
 
ADC PRS Study-Paper OGJ- June 2014
ADC PRS Study-Paper OGJ- June 2014ADC PRS Study-Paper OGJ- June 2014
ADC PRS Study-Paper OGJ- June 2014Xavier MICHEL
 
TA-2015 GE Frame-V Field Instrumentation Overhaul
TA-2015 GE Frame-V Field Instrumentation OverhaulTA-2015 GE Frame-V Field Instrumentation Overhaul
TA-2015 GE Frame-V Field Instrumentation OverhaulMuhammad Asad Ullah
 
Optimal Design of a natural gas transmission system
Optimal Design of a natural gas transmission systemOptimal Design of a natural gas transmission system
Optimal Design of a natural gas transmission systemCini Gekpe
 
Transformer Bladder Replacement work Report
Transformer Bladder Replacement work ReportTransformer Bladder Replacement work Report
Transformer Bladder Replacement work ReportDanish Aslam
 
Compressor Valves
Compressor ValvesCompressor Valves
Compressor Valves
AmericanMillwright
 
Presentation1
Presentation1Presentation1
Presentation1
kanhaiya lal
 
Felton LNG Tour Presentation (PG&E)
Felton LNG Tour Presentation (PG&E)Felton LNG Tour Presentation (PG&E)
Felton LNG Tour Presentation (PG&E)
Robert Singleton
 
EC6 design improvements and confirmatory testing
EC6 design improvements and confirmatory testingEC6 design improvements and confirmatory testing
EC6 design improvements and confirmatory testing
SNC-Lavalin
 
Sathiyaprabhu Piping Stress Engineer CV 2015
Sathiyaprabhu Piping Stress Engineer CV 2015Sathiyaprabhu Piping Stress Engineer CV 2015
Sathiyaprabhu Piping Stress Engineer CV 2015sathiya prabhu
 
Urea 2000plus
Urea 2000plusUrea 2000plus
Urea 2000plus
Prem Baboo
 
RV Thuwal - Refit project overview by Maritime Survey Australia
RV Thuwal - Refit project overview by Maritime Survey AustraliaRV Thuwal - Refit project overview by Maritime Survey Australia
RV Thuwal - Refit project overview by Maritime Survey Australia
MichaelUberti
 
Boiler Operation and Maintenance Experiences
Boiler Operation and Maintenance ExperiencesBoiler Operation and Maintenance Experiences
Boiler Operation and Maintenance Experiences
National Productivity Council, Hyderabad, India
 
IPTC 16192 Manuscript
IPTC 16192 ManuscriptIPTC 16192 Manuscript
IPTC 16192 ManuscriptNghi Nguyen
 

Similar to Reformer Catalyst Report (20)

Nitrogen purging
Nitrogen  purgingNitrogen  purging
Nitrogen purging
 
Stakeholder weekly report-20th May 2023.pptx
Stakeholder weekly report-20th May 2023.pptxStakeholder weekly report-20th May 2023.pptx
Stakeholder weekly report-20th May 2023.pptx
 
Presentation On Boiler Analysis
Presentation On Boiler AnalysisPresentation On Boiler Analysis
Presentation On Boiler Analysis
 
Experimental Analysis of Heat Transfer Enhancement in a Double Pipe Heat Exch...
Experimental Analysis of Heat Transfer Enhancement in a Double Pipe Heat Exch...Experimental Analysis of Heat Transfer Enhancement in a Double Pipe Heat Exch...
Experimental Analysis of Heat Transfer Enhancement in a Double Pipe Heat Exch...
 
A case study of thinning of ng (natural gas) injection line in mp section bef...
A case study of thinning of ng (natural gas) injection line in mp section bef...A case study of thinning of ng (natural gas) injection line in mp section bef...
A case study of thinning of ng (natural gas) injection line in mp section bef...
 
Report steffones
Report steffonesReport steffones
Report steffones
 
GNFC problems.pdf
GNFC problems.pdfGNFC problems.pdf
GNFC problems.pdf
 
ADC PRS Study-Paper OGJ- June 2014
ADC PRS Study-Paper OGJ- June 2014ADC PRS Study-Paper OGJ- June 2014
ADC PRS Study-Paper OGJ- June 2014
 
TA-2015 GE Frame-V Field Instrumentation Overhaul
TA-2015 GE Frame-V Field Instrumentation OverhaulTA-2015 GE Frame-V Field Instrumentation Overhaul
TA-2015 GE Frame-V Field Instrumentation Overhaul
 
Optimal Design of a natural gas transmission system
Optimal Design of a natural gas transmission systemOptimal Design of a natural gas transmission system
Optimal Design of a natural gas transmission system
 
Transformer Bladder Replacement work Report
Transformer Bladder Replacement work ReportTransformer Bladder Replacement work Report
Transformer Bladder Replacement work Report
 
Compressor Valves
Compressor ValvesCompressor Valves
Compressor Valves
 
Presentation1
Presentation1Presentation1
Presentation1
 
Felton LNG Tour Presentation (PG&E)
Felton LNG Tour Presentation (PG&E)Felton LNG Tour Presentation (PG&E)
Felton LNG Tour Presentation (PG&E)
 
EC6 design improvements and confirmatory testing
EC6 design improvements and confirmatory testingEC6 design improvements and confirmatory testing
EC6 design improvements and confirmatory testing
 
Sathiyaprabhu Piping Stress Engineer CV 2015
Sathiyaprabhu Piping Stress Engineer CV 2015Sathiyaprabhu Piping Stress Engineer CV 2015
Sathiyaprabhu Piping Stress Engineer CV 2015
 
Urea 2000plus
Urea 2000plusUrea 2000plus
Urea 2000plus
 
RV Thuwal - Refit project overview by Maritime Survey Australia
RV Thuwal - Refit project overview by Maritime Survey AustraliaRV Thuwal - Refit project overview by Maritime Survey Australia
RV Thuwal - Refit project overview by Maritime Survey Australia
 
Boiler Operation and Maintenance Experiences
Boiler Operation and Maintenance ExperiencesBoiler Operation and Maintenance Experiences
Boiler Operation and Maintenance Experiences
 
IPTC 16192 Manuscript
IPTC 16192 ManuscriptIPTC 16192 Manuscript
IPTC 16192 Manuscript
 

Recently uploaded

Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
abh.arya
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
DuvanRamosGarzon1
 
addressing modes in computer architecture
addressing modes  in computer architectureaddressing modes  in computer architecture
addressing modes in computer architecture
ShahidSultan24
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
Vaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdfVaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdf
Kamal Acharya
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
Intella Parts
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdfCOLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
Kamal Acharya
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 

Recently uploaded (20)

Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
 
addressing modes in computer architecture
addressing modes  in computer architectureaddressing modes  in computer architecture
addressing modes in computer architecture
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
Vaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdfVaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdf
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdfCOLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 

Reformer Catalyst Report

  • 1. ANNUAL TURNAROUND JUNE 2015 Page | 1 REPORT ON PRIMARY REFORMER CATALYST UNLOADING AND LOADING
  • 2. ANNUAL TURNAROUND JUNE 2015 Page | 2 PRIMARY REFORMER CATALYST REPLACEMENT PLANNED JOB FOR ANNUAL TURNAROUND 2015 AT MANGALORE CHEMICALS AND FERTILIZERS LIMITED, PANAMBUR, MANGALORE, KARNATAKA- 575010. PROCESS CREW MEMBERS  K. SELVAN  DHARMARAJ. D. D  K. P. DEVADIGA  PRASHANT. A  SHARATH. A  SILAMBARASAN  PRASHANTH. K  VINAYA  ABHAY  ABDUL  ROHIT  BHARATH  JEEVAN  YASHWANTH  SACHIN
  • 3. ANNUAL TURNAROUND JUNE 2015 Page | 3 SUMMARY After the successful operational period for the year 2014-2015, inspection of primary reformer tubes and replacement of primary reformer catalyst was planned to provide solution for the high reformer tube skin temperatures. Sud Chemie (Catalyst Supplying Firm) took the initiative of supplying the two layered catalyst for the primary reformer. Catalyst was made available as per our requirement with bottom layer having 42% of Ni Catalyst (Reformax 330 G90 LDP- 10 hole- 19*16mm) and 58% of NiK Catalyst (Reformax 250- 5 hole- 16*16mm). Bottom layer catalyst: REFORMAX 330 G90 LDP (10 hole) - 19*16mm 49 drums of new catalyst and 1 drum of old catalyst were available. Drum info- Net weight- 156 kgs/Gross weight- 176 kgs/Volume- 200 liters. Density- 780 kg/m3.
  • 4. ANNUAL TURNAROUND JUNE 2015 Page | 4 Top layer catalyst: REFORMAX 250 (5 hole)- 16*16mm 68 drums of new catalyst were available. Drum info- Net weight- 216 kgs/Gross weight- 236 kgs/Volume- 200 liters. Density- 1080 kg/m3. CR- Asia was given the contract for unloading and uniform loading of primary reformer catalysts. Services included reformer tubes counter weight adjustment, tube flanges bolt loosening/tightening (without hammer- pneumatic torque allowed), shifting of spent/new catalyst drums, visual display of individual reformer tube internal surface with video cam assembly, for spent catalyst sampling, empty/loaded catalyst dip and differential pressure (DP) checking, catalyst unloading by BIVAC pump and loading by UNIDENSE method.
  • 5. ANNUAL TURNAROUND JUNE 2015 Page | 5 DETAILED REPORT After planned ammonia plant shutdown, reformer cooling using inert gas (Nitrogen) was prolonged for LTCO convertor bed cooling (@1000 hours on 10th June, 2015). Depressurization of front end was done at HT guard inlet vent point after isolating HTCO convertor inlet isolation valve. After depressurizing, following jobs were done in the mentioned order (Jobs completed in approximately 8 hours)-  Reformer feed spaded (FRRC-203 d/s)  Make gas boiler(H201) outlet spaded  Reformer furnace man way covers opened  Reformer outlet T-plug removed  All reformer burner guns removed  Demineralized water flushing done for fuel naphtha header towards raw naphtha storage tank  Reformer fuel naphtha strainer spaded (SM1 u/s)  Reformer tube counter weight locked  Reformer tube and pigtail flanges insulation removed All 224 tube flanges bolt removal initiated. Long pigtail to short pigtail flange removed and respective orifices positions were marked and tied to the same flanges (Jobs completed in approximately 24 hours). Unloading of primary reformer was started at 1825 hours on 10th June, 2015. CR- Asia BIVAC with a single hose was used for unloading with vacuum reading of -350 mm Hg/-0.135 inch Hg. Dust sample was collected from bottom T- plug and handed over to Q/C & Lab for analyzing. With completion of catalyst unloading for “A” & “B” row, rigs for measuring differential pressure across tubes were being made ready for MCFL rig. [Note: A second vacuum hose was made ready and utilized to accelerate the catalyst unloading process. A metal tip nozzle was being used in case of compacted spent catalyst unloading. A mark with tape was made on each hose being inserted into tubes to make sure the catalyst support grid was not being damaged for every tube.]
  • 6. ANNUAL TURNAROUND JUNE 2015 Page | 6 Spent catalyst sampling was done for the following tubes A24, A44, A48, B16 and D16. As decided, samples were collected at heights of 3m, 6m and 9m for all the 5 tubes. Reformer catalyst unloading for all 224 tubes was completed on 12th June, 2015 (Job completed in approximately 48 hours). The spent catalyst was being collected in the provided Mangala Urea bags and shifted to the reformer bottom shed. All 224 tubes empty dip readings were noted down. Later that night at 2230 hours, all reformer tubes inner surface cleaning by stainless steel wire mesh was initiated. To extract the excess scale formation inside the reformer tubes, arrangement was made with a buffing plate (Diameter 100mm) having connected rods (threaded with nut and bolt) for extension as the plate moves inside the tube. As the assembly was not much efficient and the potential risk of it getting clogged was more, the arrangement was rejected. Simultaneously bottom layer Ni catalyst drums were being shifted from the storage area to shed (reformer bottom area) and top layer NiK catalyst to shed (stores area). [Note: Catalyst drums were being shifted in absence of rain. Drum rolling to be avoided. Keep the drums on wooden pallets, avoid stacking them up. Protect from rain and stagnant water by providing tarpaulin cover. Keep the lids on, avoid catalyst exposure and do not damage the drums.] DP measurement details: CR-ASIA DP apparatus orifice diameter: 8mm. MCF DP rig orifice downstream hose length/diameter: 6.00mts/ 0.75”. Orifice u/s instrument air maintained pressure: 4.00 kg/cm2. (Transmitter range: 0-10 kg/cm2.g). Orifice d/s pressure indicates DP. (Transmitter range: 0-4 kg/cm2.g).
  • 7. ANNUAL TURNAROUND JUNE 2015 Page | 7 Inner deposits collected from some of the reformer tubes. Composition: Nickel 33.91% Iron 18.65% Chromium 05.16% Aluminum 0.42% Calcium 0.12% Magnesium 0.062% Copper 0.08% Potash 0.062% Vanadium 0.035% Lead ND Sulfides as S <10ppm Chloride <1ppm Sulfate <1ppm Phosphate <1ppm After the cleaning of tubes, visual inspection was done using the video cam and remote display. D31 reformer tube catalyst grid support was found damaged (On 16th June, 2015). At the same time dip readings and DP checking across empty tube (with MCFL rig) was initiated and completed. It was replaced with a new grid support and was cross checked with the old dip and DP readings. CR-Asia rig connections were made ready and DP checking for each reformer tube was initiated. At reformer top; arrangement were being made for catalyst weighing, catalyst dust blowing, protection from rain and provision of breeze free surroundings. Some reformer tubes (49 in nos.) having DP values (with CR-Asia rig) more than 0.04kg/cm2.g were decided to be cleaned again by removal of catalyst grid support. After tube cleaning and checking the improved DP readings for the respective tubes, catalyst grid supports were boxed up and clearance was given for catalyst loading (On 1600 hrs on 19th June, 2015).
  • 8. ANNUAL TURNAROUND JUNE 2015 Page | 8 Test loading of first layer (Ni) catalyst was done for the first tube of each row i.e. A1, B1, C1 and D1 in presence of Sud Chemie representative. Dip and DP readings were noted down as a reference value for rest of the tubes. It was decided to go ahead with 5 buckets of catalyst for each tube weighing 7kgs. Supervision was deputed to employees to follow up the catalyst weighing, catalyst drum being utilized and correctional weight for each tube. [Note- Weighing machine was deployed from ABC plant to weigh catalyst for loading. Instrument air connection was provided from PICV-2211 tapping for checking reformer tube DP and catalyst dust blowing. A separate instrument air connection was provided from F- 4210 area for air wench to lift catalyst drums.] As catalyst available was close to the amount needed after loading “A” and “B” row tubes, it was decided to load remaining tubes with maximum of 36kgs till all tubes are covered. Dip readings were noted of all reformer tubes filled with Ni catalyst. Later dip corrections were done by additional top up for selective tubes to get the dip reading closer to 7.2m (Completed by 0700hrs on 21st June, 2015). DP readings for all tubes with Ni catalyst were noted down with CR-Asia rig and later with MCFL rig. As for the Ni catalyst loading, all new catalyst was utilized and 1 drum old catalyst weighing 112.8kg/141liters was unutilized which was shifted to DAP plant storage. After getting approval of DP and dip readings, clearance was given for loading of second layer (NiK) catalyst. Test loading was done for first tube of each row i.e. A1, B1, C1 and D1. Dip and DP readings were noted down as a reference value for the rest of the tubes. It was decided to go ahead with 7 buckets for each tube weighing 10kgs. After loading of NiK catalyst for all tubes, dip readings were noted down and correction were done by additional top up for selective tubes to get the dip reading closer to 0.8m (Completed by 0600hrs on 23rd June, 2015). DP readings for NiK catalyst were noted down using CR-Asia and later with MCFL rig. DP correction was done for B1 and B49 tubes as the respective DP readings were on the lower side. For NiK catalyst, 3 full drums of catalyst and a partly filled drum was shifted to catalyst storage (725 liters in total).
  • 9. ANNUAL TURNAROUND JUNE 2015 Page | 9 After getting of approval of DP and dip readings, it was decided to box up all reformer tube flanges. Later orifices and long pigtail to short pigtail flanges were boxed up. Reformer tubes counter weights were released properly. Housekeeping was done at reformer top and insulation job was kept pending as high pressure leak test and flange bolts hot tightening had to be done. Instrument air connections were normalized for TICV- 211 and TI-231. Empty drums were filled with spent catalyst and content displaying hazardous sticker was pasted on each drum. DIP HEIGHTS FIXED FOR LOADING  Empty dip height from tube top flange to the catalyst support grid- 11.83 meters.  Empty dip height from tube top flange to the top surface of Reformax330 (G90 LDP- 10 holed) catalyst- 7.20 meters.  Empty dip height from tube top flange to the top surface of Reformax250 (5 holed) catalyst- 0.80 meters.  Allowable DP variation from average DP of 224 tubes- +3% to -3%. AVERAGE TUBE DP AFTER EACH LAYER OF CATALYST LOADING WITH CR-ASIA RIG Average tube DP after loading Reformax 330-G90 LDP catalyst- 0.1837 bar.g Average tube DP after loading Reformax 250 catalyst- 0.5462 bar.g CATALYST CONSUMPTION FOR ALL 224 TUBES Total Reformax 330-G90 LDP catalyst utilized- 8138.156 kilograms. Total Reformax 250 catalyst utilized- 15160.843 kilograms. Hence, total catalyst utilized- 23298.999 kilograms.
  • 10. ANNUAL TURNAROUND JUNE 2015 Page | 10 APPROXIMATE TIME REQUIREMENT:  Time required for T plug dropping. : 05 hrs  Time required for reformer tube to : 25.50 hrs short pigtail flange & short pigtail. to long pigtail flange disconnection.  Time required for catalyst unloading. : 52.50 hrs  Time require for tube inner surface cleaning and tube visual inspection. : 88 hrs.  Dead time due to reformer tube inspection : 06 hrs.  Time required for catalyst support grid removal, cleaning and box up. Empty tube DP measurement was done simultaneously. : 56 hrs.  Time required for Reformax-330-G90 LDP catalyst loading. : 30 hrs  Dead time due to power failure. : 01 hrs.  Time required for 1st layer catalyst dip and DP measurement/adjustment. : 08 hrs.  Time required for Reformax-250 catalyst loading. : 48.50hrs  Time required for 2nd layer catalyst dip and DP measurement/adjustment. : 12 hrs.  Time required for tubes boxing up. : 36 hrs  Time required for t plug boxing up. : 05hrs  Dead time due to radiography. : 08 hrs  Total time required. : 381.50 hrs