SlideShare a Scribd company logo
STEP BY STEP PROCEDURE FOR
SYNTHESIS CATALYST UNLOADING
COOLING DOWN & PURGING OF THE CONVERTER
Once the bed activity is brought down after stopping the synthesis gas flow to the converter,
try to cool down the catalyst bed to ambient temperature. This can be achieved by quenching the
converter with the same synthesis gas or by circulating an inert gas in the synthesis loop. Plan out
for purging the synthesis loop with inert gas without any time delay considering the time allotted
and capital invested for the project. Isolate the synthesis converter properly to do purging more
efficiently (This includes spading/blinding/blanking off). Use fresh inert gas (inert gas used over
here was nitrogen) for purging and avoid reutilization of used inert gas. Purging result can be
tested by checking the ammonia and hydrogen concentration at the vent point when the system is
at minimum pressure. Recommended result to be achieved for confirmation of purging for
hydrogen should be less than 0.2% and ammonia should be less than 5ppm.
DISMANTLING THE OBJECTING PIPELINES AND CONTROL VALVES
When the purging of synthesis loop is achieved, drop the control valves connected to
converter for servicing and box up blinds on the open ends. Process pipelines projecting at the top
of the converter have to be dismantled as an open area is needed during loading of the catalyst.
Converter catalyst loading is a very rare opportunity for an ammonia engineer. Inert gas bleed
should kept on to the converter continuously to avoid temperature spikes in the catalyst beds due
to oxygen ingression. Make sure that maintenance personals are looking after the top channel cover
stud bolt loosening and availability of the spares in case of gas cutting is needed for stud bolt
removal. At the bottom of the converter, release the converter connected boiler/heat exchanger for
proper separation of converter from synthesis loop. After dismantling the converter connected
pipelines, release the bellows which are welded to the ring gaskets for every opening (in some
cases bellows might not be available in the main design). After releasing the bellows do blank off
the open ends possibly with duct tapes. Remove the long thermowell from the guide tube cavity
with the help of the crane.
PREPARATION FOR FIRST BASKET CATALYST EXTRACTION
Arrangement has to be done for accommodating vacuum system for catalyst removal at the
nearby area. After loosening the top channel cover, drop it with the help of crane. Don’t forget to
blank off the open ends for the main central product outlet pipe as well as the concentric openings
adjacent to it. Inert gas bleed off with minimum positive pressure to the converter remains on
throughout the catalyst removal process because the catalyst is pyrophoric in its active form. From
now on the persons working inside the converter will be on lifelines on continuous basis till the
catalyst extraction is totally completed. It will be better if catalyst replacement job is taken up in
summer season.
After top channel cover dropping, (at the topmost part of the converter) pipelines for
guiding the synthesis gas into respective zones are present with bellows at bends helpful for
adjusting to the thermal and pressure fluctuations. Vendor will provide a temporary lid/cover to
accommodate the camera wire, breathing and exhaling lines for person working inside, safety rope
to pullout & a manway for man entry. Remove the pipelines and the first cover is visible which is
bolted to the LP shell. Loosen the bolts and remove the first cover with help of a crane. The first
basket is visible. Remove the second cover which is bolted to the first basket and the inter-bed heat
exchanger. First basket catalyst is visible and extraction can be initiated. Sufficient inert gas supply
should be available for the converter because extraction of catalyst using vacuum system leads to
excess inert gas requirement to avoid oxygen ingression.
FIRST BASKET CATALYST EXTRACTION
Catalyst extraction should be coordinated in a proper manner. A breathing apparatus
assembly with inbuilt communicating device (walkie-talkie) has to be provided to the person
working inside. A safety rope should be tied to the same person to evacuate him in case of
emergency and a rope ladder for proper entry and exit. A person should stand at the top and
supervise/communicate to the person working inside with a continuous watch on him. Three spare
persons should be present at top for pulling the person out in case of emergency. A person was able
to work inside the first basket for removal of catalyst for a period of 45-60 minutes. To
continuously monitor the camera’s live feed to give suggestions and maintain the breathing
apparatus assembly, sufficient persons should be allotted. To loosen the catalyst for extraction,
make use of drilling machine with pressurized inert gas supply. Avoid pressurized air usage for
pneumatic drilling.
There should be a proper disposal plan for the spent catalyst. Once the spent catalyst
collecting trailer is filled, it should be discarded in an open area and water should be sprayed on it
continuously to avoid catching fire. Try to spray water and avoid submerging with excess water to
abide pollution control norms.
To make it possible for separation of first basket, the thermowell guide tube has to be cut at
the first basket bottom before lifting it. When catalyst extraction for the first basket is completed,
box up the second cover to the first basket (as it has hooks for lifting) and remove the bolts
connecting the first basket to LP shell. Now it is possible to lift the first basket and place it at ground
level for inspection and speculation.
SECOND BASKET CATALYST EXTRACTION
The third cover has to be dismantled and removed for accessing the catalyst in second
basket for extraction. Similar procedure has to be followed for second basket catalyst extraction as
mentioned for first basket catalyst extraction. After catalyst extraction completion, inert gas supply
should be maintained because catalyst dust is still present inside the second basket. It is better to
remove the second basket with the LP shell as it is time saving. Now the inert gas supply can be cut
off. Later main vessel related inspection and engineering activities can be initiated.

More Related Content

What's hot

Relief and blowdown in
Relief and blowdown           inRelief and blowdown           in
Relief and blowdown in
Akshay Kotkar
 
Reduction and Start-Up of Steam Reforming Catalyst
Reduction and Start-Up of Steam Reforming CatalystReduction and Start-Up of Steam Reforming Catalyst
Reduction and Start-Up of Steam Reforming Catalyst
Gerard B. Hawkins
 
Separator sizing and droplet sizes low shear school - 2017
Separator sizing and droplet sizes   low shear school - 2017Separator sizing and droplet sizes   low shear school - 2017
Separator sizing and droplet sizes low shear school - 2017
Low Shear School
 
Secondary Reforming Burners
Secondary Reforming BurnersSecondary Reforming Burners
Secondary Reforming Burners
Gerard B. Hawkins
 
CENTRIFUGAL COMPRESSOR SETTLE OUT CONDITIONS TUTORIAL
CENTRIFUGAL COMPRESSOR SETTLE OUT CONDITIONS TUTORIALCENTRIFUGAL COMPRESSOR SETTLE OUT CONDITIONS TUTORIAL
CENTRIFUGAL COMPRESSOR SETTLE OUT CONDITIONS TUTORIAL
Vijay Sarathy
 
Pressure safety valves
Pressure safety valvesPressure safety valves
Pressure safety valvesAmol Dudhate
 
Pressure Reliveing Devices1
Pressure Reliveing Devices1Pressure Reliveing Devices1
Pressure Reliveing Devices1Om Pratap Singh
 
Fired Heater Operation and Trouble Shooting.pdf
Fired Heater  Operation and Trouble Shooting.pdfFired Heater  Operation and Trouble Shooting.pdf
Fired Heater Operation and Trouble Shooting.pdf
MuhammadNaeem191352
 
Steam Reforming - Common Problems
Steam Reforming - Common ProblemsSteam Reforming - Common Problems
Steam Reforming - Common Problems
Gerard B. Hawkins
 
(HTS) High Temperature Shift Catalyst (VSG-F101) - Comprehensiev Overview
(HTS) High Temperature Shift Catalyst (VSG-F101) - Comprehensiev Overview(HTS) High Temperature Shift Catalyst (VSG-F101) - Comprehensiev Overview
(HTS) High Temperature Shift Catalyst (VSG-F101) - Comprehensiev Overview
Gerard B. Hawkins
 
Steam Reforming - Carbon Formation
Steam Reforming - Carbon FormationSteam Reforming - Carbon Formation
Steam Reforming - Carbon Formation
Gerard B. Hawkins
 
Gas Plant Separator Design
Gas Plant Separator DesignGas Plant Separator Design
Gas Plant Separator Design
iyaselex
 
Accumulation and Over-pressure: difference between accumulation and overpressure
Accumulation and Over-pressure: difference between accumulation and overpressureAccumulation and Over-pressure: difference between accumulation and overpressure
Accumulation and Over-pressure: difference between accumulation and overpressure
Varun Patel
 
Overpressure scenarios overview final
Overpressure scenarios overview finalOverpressure scenarios overview final
Overpressure scenarios overview finalRajiv Natkar
 
Start Up Procedures for Primary Reforming Catalyst
Start Up Procedures for Primary Reforming CatalystStart Up Procedures for Primary Reforming Catalyst
Start Up Procedures for Primary Reforming Catalyst
Gerard B. Hawkins
 
Calculation of an Ammonia Plant Energy Consumption:
Calculation of an Ammonia Plant Energy Consumption:  Calculation of an Ammonia Plant Energy Consumption:
Calculation of an Ammonia Plant Energy Consumption:
Gerard B. Hawkins
 
PROCESS STORAGE TANK LAH & LAHH LEVEL CALCULATION
PROCESS STORAGE TANK LAH & LAHH LEVEL CALCULATIONPROCESS STORAGE TANK LAH & LAHH LEVEL CALCULATION
PROCESS STORAGE TANK LAH & LAHH LEVEL CALCULATION
Vijay Sarathy
 
Troubleshooting in Distillation Columns
Troubleshooting in Distillation ColumnsTroubleshooting in Distillation Columns
Troubleshooting in Distillation Columns
Gerard B. Hawkins
 
Pressure Relief valve sizing and design
Pressure Relief valve sizing and designPressure Relief valve sizing and design
Pressure Relief valve sizing and design
Héctor Nguema Ondo
 

What's hot (20)

Relief and blowdown in
Relief and blowdown           inRelief and blowdown           in
Relief and blowdown in
 
Reduction and Start-Up of Steam Reforming Catalyst
Reduction and Start-Up of Steam Reforming CatalystReduction and Start-Up of Steam Reforming Catalyst
Reduction and Start-Up of Steam Reforming Catalyst
 
Separator sizing and droplet sizes low shear school - 2017
Separator sizing and droplet sizes   low shear school - 2017Separator sizing and droplet sizes   low shear school - 2017
Separator sizing and droplet sizes low shear school - 2017
 
Secondary Reforming Burners
Secondary Reforming BurnersSecondary Reforming Burners
Secondary Reforming Burners
 
CENTRIFUGAL COMPRESSOR SETTLE OUT CONDITIONS TUTORIAL
CENTRIFUGAL COMPRESSOR SETTLE OUT CONDITIONS TUTORIALCENTRIFUGAL COMPRESSOR SETTLE OUT CONDITIONS TUTORIAL
CENTRIFUGAL COMPRESSOR SETTLE OUT CONDITIONS TUTORIAL
 
Pressure safety valves
Pressure safety valvesPressure safety valves
Pressure safety valves
 
Pressure Reliveing Devices1
Pressure Reliveing Devices1Pressure Reliveing Devices1
Pressure Reliveing Devices1
 
Fired Heater Operation and Trouble Shooting.pdf
Fired Heater  Operation and Trouble Shooting.pdfFired Heater  Operation and Trouble Shooting.pdf
Fired Heater Operation and Trouble Shooting.pdf
 
Steam Reforming - Common Problems
Steam Reforming - Common ProblemsSteam Reforming - Common Problems
Steam Reforming - Common Problems
 
(HTS) High Temperature Shift Catalyst (VSG-F101) - Comprehensiev Overview
(HTS) High Temperature Shift Catalyst (VSG-F101) - Comprehensiev Overview(HTS) High Temperature Shift Catalyst (VSG-F101) - Comprehensiev Overview
(HTS) High Temperature Shift Catalyst (VSG-F101) - Comprehensiev Overview
 
Steam Reforming - Carbon Formation
Steam Reforming - Carbon FormationSteam Reforming - Carbon Formation
Steam Reforming - Carbon Formation
 
Gas Plant Separator Design
Gas Plant Separator DesignGas Plant Separator Design
Gas Plant Separator Design
 
Accumulation and Over-pressure: difference between accumulation and overpressure
Accumulation and Over-pressure: difference between accumulation and overpressureAccumulation and Over-pressure: difference between accumulation and overpressure
Accumulation and Over-pressure: difference between accumulation and overpressure
 
Overpressure scenarios overview final
Overpressure scenarios overview finalOverpressure scenarios overview final
Overpressure scenarios overview final
 
Start Up Procedures for Primary Reforming Catalyst
Start Up Procedures for Primary Reforming CatalystStart Up Procedures for Primary Reforming Catalyst
Start Up Procedures for Primary Reforming Catalyst
 
Three Phase Separators
Three Phase SeparatorsThree Phase Separators
Three Phase Separators
 
Calculation of an Ammonia Plant Energy Consumption:
Calculation of an Ammonia Plant Energy Consumption:  Calculation of an Ammonia Plant Energy Consumption:
Calculation of an Ammonia Plant Energy Consumption:
 
PROCESS STORAGE TANK LAH & LAHH LEVEL CALCULATION
PROCESS STORAGE TANK LAH & LAHH LEVEL CALCULATIONPROCESS STORAGE TANK LAH & LAHH LEVEL CALCULATION
PROCESS STORAGE TANK LAH & LAHH LEVEL CALCULATION
 
Troubleshooting in Distillation Columns
Troubleshooting in Distillation ColumnsTroubleshooting in Distillation Columns
Troubleshooting in Distillation Columns
 
Pressure Relief valve sizing and design
Pressure Relief valve sizing and designPressure Relief valve sizing and design
Pressure Relief valve sizing and design
 

Viewers also liked

SOUTHERN PETROCHEMICALS INDUSTRIES CORPORATION LIMITED
SOUTHERN PETROCHEMICALS INDUSTRIES CORPORATION LIMITEDSOUTHERN PETROCHEMICALS INDUSTRIES CORPORATION LIMITED
SOUTHERN PETROCHEMICALS INDUSTRIES CORPORATION LIMITEDDharmaraj Daddikar
 
Finalized readings (mcfl rig).
Finalized readings (mcfl rig).Finalized readings (mcfl rig).
Finalized readings (mcfl rig).
Dharmaraj Daddikar
 
PREPARATION FOR BOILER FEED WATER PRODUCTION
PREPARATION FOR BOILER FEED WATER PRODUCTIONPREPARATION FOR BOILER FEED WATER PRODUCTION
PREPARATION FOR BOILER FEED WATER PRODUCTIONDharmaraj Daddikar
 
Synthesis catalyst converter explanation
Synthesis catalyst converter explanationSynthesis catalyst converter explanation
Synthesis catalyst converter explanation
Dharmaraj Daddikar
 
Reformer Catalyst Report
Reformer Catalyst ReportReformer Catalyst Report
Reformer Catalyst Report
Dharmaraj Daddikar
 
The Benefits and Disadvantages of Potash in Steam Reforming
The Benefits and Disadvantages of Potash in Steam ReformingThe Benefits and Disadvantages of Potash in Steam Reforming
The Benefits and Disadvantages of Potash in Steam Reforming
Gerard B. Hawkins
 
Steam Reformer Surveys - Techniques for Optimization of Primary Reformer Oper...
Steam Reformer Surveys - Techniques for Optimization of Primary Reformer Oper...Steam Reformer Surveys - Techniques for Optimization of Primary Reformer Oper...
Steam Reformer Surveys - Techniques for Optimization of Primary Reformer Oper...
Gerard B. Hawkins
 
Safety valve in process industry1
Safety valve in process industry1Safety valve in process industry1
Safety valve in process industry1
Nitesh Chauhan
 
Normal Operation of Steam Reformers on Hydrogen Plants
Normal Operation of Steam Reformers on Hydrogen PlantsNormal Operation of Steam Reformers on Hydrogen Plants
Normal Operation of Steam Reformers on Hydrogen Plants
Gerard B. Hawkins
 
Reformer Tube Metallurgy: Design Considerations; Failure Mechanisms; Inspecti...
Reformer Tube Metallurgy: Design Considerations; Failure Mechanisms; Inspecti...Reformer Tube Metallurgy: Design Considerations; Failure Mechanisms; Inspecti...
Reformer Tube Metallurgy: Design Considerations; Failure Mechanisms; Inspecti...
Gerard B. Hawkins
 
14 Tips for Process Safety Management
14 Tips for Process Safety Management14 Tips for Process Safety Management
14 Tips for Process Safety Management
Verde Ventures Pvt. Ltd.
 
Process Safety Kpi
Process Safety KpiProcess Safety Kpi
Process Safety Kpi
ArthurGroot
 
101 Things That Can Go Wrong on a Primary Reformer - Best Practices Guide
101 Things That Can Go Wrong on a Primary Reformer -  Best Practices Guide101 Things That Can Go Wrong on a Primary Reformer -  Best Practices Guide
101 Things That Can Go Wrong on a Primary Reformer - Best Practices Guide
Gerard B. Hawkins
 
Pre-reformer Operations Technical Supplement
Pre-reformer Operations Technical SupplementPre-reformer Operations Technical Supplement
Pre-reformer Operations Technical Supplement
Gerard B. Hawkins
 

Viewers also liked (19)

HALDIA PETROCHEMICALS LIMITED
HALDIA PETROCHEMICALS LIMITEDHALDIA PETROCHEMICALS LIMITED
HALDIA PETROCHEMICALS LIMITED
 
SOUTHERN PETROCHEMICALS INDUSTRIES CORPORATION LIMITED
SOUTHERN PETROCHEMICALS INDUSTRIES CORPORATION LIMITEDSOUTHERN PETROCHEMICALS INDUSTRIES CORPORATION LIMITED
SOUTHERN PETROCHEMICALS INDUSTRIES CORPORATION LIMITED
 
Finalized readings (mcfl rig).
Finalized readings (mcfl rig).Finalized readings (mcfl rig).
Finalized readings (mcfl rig).
 
Hydrogen Recovery
Hydrogen RecoveryHydrogen Recovery
Hydrogen Recovery
 
PREPARATION FOR BOILER FEED WATER PRODUCTION
PREPARATION FOR BOILER FEED WATER PRODUCTIONPREPARATION FOR BOILER FEED WATER PRODUCTION
PREPARATION FOR BOILER FEED WATER PRODUCTION
 
Synthesis catalyst converter explanation
Synthesis catalyst converter explanationSynthesis catalyst converter explanation
Synthesis catalyst converter explanation
 
Reformer Catalyst Report
Reformer Catalyst ReportReformer Catalyst Report
Reformer Catalyst Report
 
The Benefits and Disadvantages of Potash in Steam Reforming
The Benefits and Disadvantages of Potash in Steam ReformingThe Benefits and Disadvantages of Potash in Steam Reforming
The Benefits and Disadvantages of Potash in Steam Reforming
 
Steam Reformer Surveys - Techniques for Optimization of Primary Reformer Oper...
Steam Reformer Surveys - Techniques for Optimization of Primary Reformer Oper...Steam Reformer Surveys - Techniques for Optimization of Primary Reformer Oper...
Steam Reformer Surveys - Techniques for Optimization of Primary Reformer Oper...
 
Safety valve in process industry1
Safety valve in process industry1Safety valve in process industry1
Safety valve in process industry1
 
REFERENCE 2015
REFERENCE 2015REFERENCE 2015
REFERENCE 2015
 
Normal Operation of Steam Reformers on Hydrogen Plants
Normal Operation of Steam Reformers on Hydrogen PlantsNormal Operation of Steam Reformers on Hydrogen Plants
Normal Operation of Steam Reformers on Hydrogen Plants
 
1.1 intro process_safety
1.1 intro process_safety1.1 intro process_safety
1.1 intro process_safety
 
Hydraulic valves
Hydraulic valvesHydraulic valves
Hydraulic valves
 
Reformer Tube Metallurgy: Design Considerations; Failure Mechanisms; Inspecti...
Reformer Tube Metallurgy: Design Considerations; Failure Mechanisms; Inspecti...Reformer Tube Metallurgy: Design Considerations; Failure Mechanisms; Inspecti...
Reformer Tube Metallurgy: Design Considerations; Failure Mechanisms; Inspecti...
 
14 Tips for Process Safety Management
14 Tips for Process Safety Management14 Tips for Process Safety Management
14 Tips for Process Safety Management
 
Process Safety Kpi
Process Safety KpiProcess Safety Kpi
Process Safety Kpi
 
101 Things That Can Go Wrong on a Primary Reformer - Best Practices Guide
101 Things That Can Go Wrong on a Primary Reformer -  Best Practices Guide101 Things That Can Go Wrong on a Primary Reformer -  Best Practices Guide
101 Things That Can Go Wrong on a Primary Reformer - Best Practices Guide
 
Pre-reformer Operations Technical Supplement
Pre-reformer Operations Technical SupplementPre-reformer Operations Technical Supplement
Pre-reformer Operations Technical Supplement
 

Similar to Catalyst unloading details

Steam Blow
Steam BlowSteam Blow
Steam Blow
S V Nagesh
 
Safety in welding
Safety in weldingSafety in welding
Safety in welding
IlhamR222
 
Ac4506156158
Ac4506156158Ac4506156158
Ac4506156158
IJERA Editor
 
Leak Tests.pptx
Leak Tests.pptxLeak Tests.pptx
Leak Tests.pptx
HassamZulfiqar1
 
Api682
Api682Api682
Gas street
Gas streetGas street
Gas street
Farhad Ahmed
 
Medical gas supply.pipelines and cylinders
Medical gas supply.pipelines and cylindersMedical gas supply.pipelines and cylinders
Medical gas supply.pipelines and cylinders
drsauravdas1977
 
8013 _0
8013  _08013  _0
8013 _0
Preeti Joshi
 
API682 Mechanical Seal Plan and Requirements of Mechanical Seals
API682 Mechanical Seal Plan and Requirements of Mechanical SealsAPI682 Mechanical Seal Plan and Requirements of Mechanical Seals
API682 Mechanical Seal Plan and Requirements of Mechanical Seals
Elango Palaniappan
 
API 682 Seal piping plans.pdf
API 682 Seal piping plans.pdfAPI 682 Seal piping plans.pdf
API 682 Seal piping plans.pdf
Teddy Setiady
 
Review paper on study and implementation of steam traps
Review paper on study and implementation of steam trapsReview paper on study and implementation of steam traps
Review paper on study and implementation of steam traps
IRJET Journal
 
Understanding & Solving Heat Transfer Equipment Stall
Understanding & Solving Heat Transfer Equipment StallUnderstanding & Solving Heat Transfer Equipment Stall
Understanding & Solving Heat Transfer Equipment Stall
Mead O'Brien, Inc.
 
Non return valves
Non return valvesNon return valves
Non return valves
narasimha reddy
 
Oxygen MANUFACTRE STORAGE PREPERATION AND CLINICAL ASPECT
Oxygen  MANUFACTRE STORAGE PREPERATION AND CLINICAL ASPECTOxygen  MANUFACTRE STORAGE PREPERATION AND CLINICAL ASPECT
Oxygen MANUFACTRE STORAGE PREPERATION AND CLINICAL ASPECT
Dr.RMLIMS lucknow
 
Maggie One Core Magnetic Separator
Maggie One Core Magnetic SeparatorMaggie One Core Magnetic Separator
Maggie One Core Magnetic SeparatorDwayne Deziel
 
Sop for air compressors
Sop for air compressorsSop for air compressors
Sop for air compressors
chaosbrigade
 

Similar to Catalyst unloading details (20)

Steam Blow
Steam BlowSteam Blow
Steam Blow
 
Safety in welding
Safety in weldingSafety in welding
Safety in welding
 
Assignment 1 SOP (1)
Assignment 1 SOP (1)Assignment 1 SOP (1)
Assignment 1 SOP (1)
 
Ac4506156158
Ac4506156158Ac4506156158
Ac4506156158
 
Leak Tests.pptx
Leak Tests.pptxLeak Tests.pptx
Leak Tests.pptx
 
Operation of Ozone Equipment
Operation of Ozone EquipmentOperation of Ozone Equipment
Operation of Ozone Equipment
 
Api682
Api682Api682
Api682
 
Gas street
Gas streetGas street
Gas street
 
Medical gas supply.pipelines and cylinders
Medical gas supply.pipelines and cylindersMedical gas supply.pipelines and cylinders
Medical gas supply.pipelines and cylinders
 
8013 _0
8013  _08013  _0
8013 _0
 
API682 Mechanical Seal Plan and Requirements of Mechanical Seals
API682 Mechanical Seal Plan and Requirements of Mechanical SealsAPI682 Mechanical Seal Plan and Requirements of Mechanical Seals
API682 Mechanical Seal Plan and Requirements of Mechanical Seals
 
API 682 Seal piping plans.pdf
API 682 Seal piping plans.pdfAPI 682 Seal piping plans.pdf
API 682 Seal piping plans.pdf
 
Review paper on study and implementation of steam traps
Review paper on study and implementation of steam trapsReview paper on study and implementation of steam traps
Review paper on study and implementation of steam traps
 
SPM FHS SHUT DOWN REPORT
SPM FHS SHUT DOWN REPORTSPM FHS SHUT DOWN REPORT
SPM FHS SHUT DOWN REPORT
 
Understanding & Solving Heat Transfer Equipment Stall
Understanding & Solving Heat Transfer Equipment StallUnderstanding & Solving Heat Transfer Equipment Stall
Understanding & Solving Heat Transfer Equipment Stall
 
Boiler Mountings
Boiler MountingsBoiler Mountings
Boiler Mountings
 
Non return valves
Non return valvesNon return valves
Non return valves
 
Oxygen MANUFACTRE STORAGE PREPERATION AND CLINICAL ASPECT
Oxygen  MANUFACTRE STORAGE PREPERATION AND CLINICAL ASPECTOxygen  MANUFACTRE STORAGE PREPERATION AND CLINICAL ASPECT
Oxygen MANUFACTRE STORAGE PREPERATION AND CLINICAL ASPECT
 
Maggie One Core Magnetic Separator
Maggie One Core Magnetic SeparatorMaggie One Core Magnetic Separator
Maggie One Core Magnetic Separator
 
Sop for air compressors
Sop for air compressorsSop for air compressors
Sop for air compressors
 

Recently uploaded

Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
Kamal Acharya
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
Vaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdfVaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdf
Kamal Acharya
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
addressing modes in computer architecture
addressing modes  in computer architectureaddressing modes  in computer architecture
addressing modes in computer architecture
ShahidSultan24
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 

Recently uploaded (20)

Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
Vaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdfVaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdf
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
addressing modes in computer architecture
addressing modes  in computer architectureaddressing modes  in computer architecture
addressing modes in computer architecture
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 

Catalyst unloading details

  • 1. STEP BY STEP PROCEDURE FOR SYNTHESIS CATALYST UNLOADING COOLING DOWN & PURGING OF THE CONVERTER Once the bed activity is brought down after stopping the synthesis gas flow to the converter, try to cool down the catalyst bed to ambient temperature. This can be achieved by quenching the converter with the same synthesis gas or by circulating an inert gas in the synthesis loop. Plan out for purging the synthesis loop with inert gas without any time delay considering the time allotted and capital invested for the project. Isolate the synthesis converter properly to do purging more efficiently (This includes spading/blinding/blanking off). Use fresh inert gas (inert gas used over here was nitrogen) for purging and avoid reutilization of used inert gas. Purging result can be tested by checking the ammonia and hydrogen concentration at the vent point when the system is at minimum pressure. Recommended result to be achieved for confirmation of purging for hydrogen should be less than 0.2% and ammonia should be less than 5ppm. DISMANTLING THE OBJECTING PIPELINES AND CONTROL VALVES When the purging of synthesis loop is achieved, drop the control valves connected to converter for servicing and box up blinds on the open ends. Process pipelines projecting at the top of the converter have to be dismantled as an open area is needed during loading of the catalyst. Converter catalyst loading is a very rare opportunity for an ammonia engineer. Inert gas bleed should kept on to the converter continuously to avoid temperature spikes in the catalyst beds due to oxygen ingression. Make sure that maintenance personals are looking after the top channel cover stud bolt loosening and availability of the spares in case of gas cutting is needed for stud bolt removal. At the bottom of the converter, release the converter connected boiler/heat exchanger for proper separation of converter from synthesis loop. After dismantling the converter connected pipelines, release the bellows which are welded to the ring gaskets for every opening (in some cases bellows might not be available in the main design). After releasing the bellows do blank off the open ends possibly with duct tapes. Remove the long thermowell from the guide tube cavity with the help of the crane. PREPARATION FOR FIRST BASKET CATALYST EXTRACTION Arrangement has to be done for accommodating vacuum system for catalyst removal at the nearby area. After loosening the top channel cover, drop it with the help of crane. Don’t forget to blank off the open ends for the main central product outlet pipe as well as the concentric openings adjacent to it. Inert gas bleed off with minimum positive pressure to the converter remains on throughout the catalyst removal process because the catalyst is pyrophoric in its active form. From now on the persons working inside the converter will be on lifelines on continuous basis till the catalyst extraction is totally completed. It will be better if catalyst replacement job is taken up in summer season.
  • 2. After top channel cover dropping, (at the topmost part of the converter) pipelines for guiding the synthesis gas into respective zones are present with bellows at bends helpful for adjusting to the thermal and pressure fluctuations. Vendor will provide a temporary lid/cover to accommodate the camera wire, breathing and exhaling lines for person working inside, safety rope to pullout & a manway for man entry. Remove the pipelines and the first cover is visible which is bolted to the LP shell. Loosen the bolts and remove the first cover with help of a crane. The first basket is visible. Remove the second cover which is bolted to the first basket and the inter-bed heat exchanger. First basket catalyst is visible and extraction can be initiated. Sufficient inert gas supply should be available for the converter because extraction of catalyst using vacuum system leads to excess inert gas requirement to avoid oxygen ingression. FIRST BASKET CATALYST EXTRACTION Catalyst extraction should be coordinated in a proper manner. A breathing apparatus assembly with inbuilt communicating device (walkie-talkie) has to be provided to the person working inside. A safety rope should be tied to the same person to evacuate him in case of emergency and a rope ladder for proper entry and exit. A person should stand at the top and supervise/communicate to the person working inside with a continuous watch on him. Three spare persons should be present at top for pulling the person out in case of emergency. A person was able to work inside the first basket for removal of catalyst for a period of 45-60 minutes. To continuously monitor the camera’s live feed to give suggestions and maintain the breathing apparatus assembly, sufficient persons should be allotted. To loosen the catalyst for extraction, make use of drilling machine with pressurized inert gas supply. Avoid pressurized air usage for pneumatic drilling. There should be a proper disposal plan for the spent catalyst. Once the spent catalyst collecting trailer is filled, it should be discarded in an open area and water should be sprayed on it continuously to avoid catching fire. Try to spray water and avoid submerging with excess water to abide pollution control norms. To make it possible for separation of first basket, the thermowell guide tube has to be cut at the first basket bottom before lifting it. When catalyst extraction for the first basket is completed, box up the second cover to the first basket (as it has hooks for lifting) and remove the bolts connecting the first basket to LP shell. Now it is possible to lift the first basket and place it at ground level for inspection and speculation. SECOND BASKET CATALYST EXTRACTION The third cover has to be dismantled and removed for accessing the catalyst in second basket for extraction. Similar procedure has to be followed for second basket catalyst extraction as mentioned for first basket catalyst extraction. After catalyst extraction completion, inert gas supply should be maintained because catalyst dust is still present inside the second basket. It is better to remove the second basket with the LP shell as it is time saving. Now the inert gas supply can be cut off. Later main vessel related inspection and engineering activities can be initiated.