PRODUCTION
SCHEDULING
Unit-4
Functions of Production Control and
Scheduling
Release Order – to the system
Assign Work – to work Centers
Sequencing priority Jobs
Control – the manufac. Lead Time
Monitor Priority Status
Monitor Capacity Status
Six Key
Functio
ns
Production Scheduling & Control Function
PRODUCTION CONTROL
LOADING AND SCHEDULING
LOADING
• Once the route has been established, the work required can
be loaded against the selected machine or workstation.
• The total time required to perform the operation is computed
by multiplying the unit operation times given on the standard
process sheet by the number of parts to be processed.
• This total time is then added to the work already planned for
the workstation.
• This is the function of loading, and it results in a tabulated list
or chart showing the planned utilization of the machines or
workstations in the plant
SCHEDULING
• Scheduling is the last of the planning functions.
• It determines when an operation is to be performed, or when
work is to be completed; the difference lies in the detail of the
scheduling procedure.
• In a centralized control situation - where all process planning,
loading, and scheduling for the plant are done in a central
office- the details of the schedule may specify the starting and
finishing time for an operation.
• On the other hand, the central schedule may simply give a
completion time for the work in a given department.
MASTER SCHEDULING
SCHEDULING -BENEFITS
• Inventory reduction,
• Process change-over reduction
• leveling
• Reduced scheduling effort
• Increased production efficiency
• Labor load leveling
• Accurate delivery date quotes
• Real time information
GANTT CHART
•A Gantt chart is a type of bar chart, developed by Henry Gantt,
that illustrates a project schedule.
• Gantt charts illustrate the start
and finish dates of the terminal elements and summary elements
of a project. Terminal elements and summary elements comprise
the work breakdown structure of the project.
•Some Gantt charts also show the dependency (i.e., precedence network)
relationships between activities.
Production Control
• Perpetual loading
– Tabulation of the time necessary to finish unfulfilled orders and
determine how long it will take to finish this work.
Perpetual loading
LINE OF BALANCE
• Find a feasible defined replacement for all undefined
(‘ANY’) ergonomic constraints on workstations, i.e. one
compatible with the ergonomic constraints and
precedence constraints defined on operations, as well as
zoning constraints and possible drifting operations
• Solve the within-workstation scheduling problem on all
workstations, for all products being assembled on the line
• Assign the operations to workstations to achieve the best
average balance, while keeping the peak times at a
manageable level.
Linear Scheduling Method
• Linear Scheduling Method (LSM) is a graphical scheduling method
focusing on continuous resource utilization in repetitive activities. It is
believed that it originally adopted the idea of Line-Of-Balance method.
• The main advantages of LSM over Critical Path Method (CPM) is its
underlying idea of keeping resources continuously at work. In other
words, it schedules activities in such a way that:
1. resource utilization is maximized;
2. interruption in on-going process is minimized, including hiring-and-
firing; and
3. the effect of the learning curve phenomenon is minimized
BATCH PRODUCTION SCHEDULING
• Batch production scheduling is the practice of planning and
scheduling of batch manufacturing processes.
• Although, scheduling may apply to traditionally continuous
processes, such as refining, it is especially important for batch
processes such as those for pharmaceutical active ingredients,
biotechnology processes and many specialty chemical
processes.
• Batch production scheduling shares some concepts and
techniques with finite capacity scheduling which has been
applied to many manufacturing problems.
• The specific issues of scheduling batch manufacturing
processes have generated considerable industrial and
academic interest
MRP
KANBAN
DISPATCHING
• Authorizing the start of an operation on the shop
floor is the function of dispatching.
• This function may be centralized or decentralized.
• The departmental dispatcher would authorize the
start of each of the machine operations – the
dispatch actions are based on the foreman’s routing
and scheduling of the work through his department.
This is decentralized dispatching.
PROGRESS REPORTING AND EXPEDITING
• The manufacturing activity of a plant is said to be “in
control” when the actual performance is within the
objectives of the planned performance.
• When jobs are started and completed on schedule,
there should be very little, if any, concern about the
meeting of commitments.
• Optimum operation of the plant, however, is attained
only if the original plan has been carefully prepared
to utilize the manufacturing facilities fully and
effectively.
Mfg. lead time
Mfg. lead time

More Related Content

What's hot

Scheduling and sequencing
Scheduling and sequencingScheduling and sequencing
Scheduling and sequencingAkanksha Gupta
 
What is forward and backward scheduling
What is forward and backward schedulingWhat is forward and backward scheduling
What is forward and backward schedulingNaresh Gupta
 
UNIT 4 - PRODUCTION SCHEDULING
UNIT 4 - PRODUCTION SCHEDULINGUNIT 4 - PRODUCTION SCHEDULING
Unit 2
Unit 2Unit 2
Unit 2
dinesh babu
 
Scheduling ppt @ DOMS
Scheduling ppt @ DOMSScheduling ppt @ DOMS
Scheduling ppt @ DOMS
Babasab Patil
 
Work Center Scheduling
Work Center Scheduling Work Center Scheduling
Work Center Scheduling
Shivangi Singh
 
Unit 1
Unit 1Unit 1
Unit 1
dinesh babu
 
Ppc unit -1
Ppc  unit -1Ppc  unit -1
Ppc unit -1
DineshS141
 
Scheduling production
Scheduling   productionScheduling   production
Scheduling production
Aditya Powale
 
Production planning and control and computerised process planning
Production planning and control and computerised process planningProduction planning and control and computerised process planning
Production planning and control and computerised process planning
Aravindh Muralidharan
 
Unit 1 PPC
Unit 1 PPCUnit 1 PPC
Unit 1 PPC
Aravind Ra
 
7. scheduling
7. scheduling7. scheduling
7. scheduling
Sudipta Saha
 
Scheduling
SchedulingScheduling
Production management
Production managementProduction management
Production management
Purnesh Aloni
 
Unit 2
Unit 2Unit 2
Unit 2
Aravind Ra
 
Loading jobs and methods definitivo
Loading jobs and methods definitivo Loading jobs and methods definitivo
Loading jobs and methods definitivo
Jorge Fuentes
 
Planing and control in general 1
Planing and control in general 1Planing and control in general 1
Planing and control in general 1Crina Feier
 
Operations Scheduling
Operations SchedulingOperations Scheduling
Operations Scheduling
Ashish Jain
 
Unit 3
Unit 3Unit 3
Unit 3
Aravind Ra
 

What's hot (19)

Scheduling and sequencing
Scheduling and sequencingScheduling and sequencing
Scheduling and sequencing
 
What is forward and backward scheduling
What is forward and backward schedulingWhat is forward and backward scheduling
What is forward and backward scheduling
 
UNIT 4 - PRODUCTION SCHEDULING
UNIT 4 - PRODUCTION SCHEDULINGUNIT 4 - PRODUCTION SCHEDULING
UNIT 4 - PRODUCTION SCHEDULING
 
Unit 2
Unit 2Unit 2
Unit 2
 
Scheduling ppt @ DOMS
Scheduling ppt @ DOMSScheduling ppt @ DOMS
Scheduling ppt @ DOMS
 
Work Center Scheduling
Work Center Scheduling Work Center Scheduling
Work Center Scheduling
 
Unit 1
Unit 1Unit 1
Unit 1
 
Ppc unit -1
Ppc  unit -1Ppc  unit -1
Ppc unit -1
 
Scheduling production
Scheduling   productionScheduling   production
Scheduling production
 
Production planning and control and computerised process planning
Production planning and control and computerised process planningProduction planning and control and computerised process planning
Production planning and control and computerised process planning
 
Unit 1 PPC
Unit 1 PPCUnit 1 PPC
Unit 1 PPC
 
7. scheduling
7. scheduling7. scheduling
7. scheduling
 
Scheduling
SchedulingScheduling
Scheduling
 
Production management
Production managementProduction management
Production management
 
Unit 2
Unit 2Unit 2
Unit 2
 
Loading jobs and methods definitivo
Loading jobs and methods definitivo Loading jobs and methods definitivo
Loading jobs and methods definitivo
 
Planing and control in general 1
Planing and control in general 1Planing and control in general 1
Planing and control in general 1
 
Operations Scheduling
Operations SchedulingOperations Scheduling
Operations Scheduling
 
Unit 3
Unit 3Unit 3
Unit 3
 

Similar to Ppc unit-4-production scheduling

Unit 4 PPC
Unit 4 PPCUnit 4 PPC
Unit 4 PPC
sivaprakash250
 
Unit 4
Unit 4Unit 4
Unit 4
MeganathanJ4
 
Unit 4-IE6605 & PRODUCTION PLANNING AND CONTROL
Unit 4-IE6605 & PRODUCTION PLANNING AND CONTROLUnit 4-IE6605 & PRODUCTION PLANNING AND CONTROL
Unit 4-IE6605 & PRODUCTION PLANNING AND CONTROL
Mohanumar S
 
PRODUCTION PLANNING AND CONTROL
PRODUCTION PLANNING AND CONTROLPRODUCTION PLANNING AND CONTROL
PRODUCTION PLANNING AND CONTROL
SIVASHANKAR N
 
unit 4.ppt
unit 4.pptunit 4.ppt
unit 4.ppt
rknatarajan
 
Production planning and control
Production planning and controlProduction planning and control
Production planning and controlLaxmikant Deshmukh
 
production scheduling
production schedulingproduction scheduling
production scheduling
PraveenManickam2
 
Unit 7 production scheduling
Unit 7 production scheduling Unit 7 production scheduling
Unit 7 production scheduling
RASHMIPANWAR10
 
scheduling in operations Management PPT O and M
scheduling in operations Management PPT O and Mscheduling in operations Management PPT O and M
scheduling in operations Management PPT O and M
ProfessionalDeeksha
 
MIn-218_chap 1.pptx
MIn-218_chap 1.pptxMIn-218_chap 1.pptx
MIn-218_chap 1.pptx
ArpanKumar79
 
PRODUCTION AND OPERATIONS MANAGEMENT (304) SEM3 NOV2021.pdf
PRODUCTION AND OPERATIONS MANAGEMENT (304) SEM3 NOV2021.pdfPRODUCTION AND OPERATIONS MANAGEMENT (304) SEM3 NOV2021.pdf
PRODUCTION AND OPERATIONS MANAGEMENT (304) SEM3 NOV2021.pdf
PratikDalvi17
 
schedulingandsequencing-140424065526-phpapp02__1_.ppt
schedulingandsequencing-140424065526-phpapp02__1_.pptschedulingandsequencing-140424065526-phpapp02__1_.ppt
schedulingandsequencing-140424065526-phpapp02__1_.ppt
VELMURUGANM19
 
MMS PRESENTAION.pptx
MMS PRESENTAION.pptxMMS PRESENTAION.pptx
MMS PRESENTAION.pptx
bankarimjhimkumari
 
Operation scheduling
Operation schedulingOperation scheduling
Operation schedulingsai precious
 
Production Planning & Control
Production Planning & ControlProduction Planning & Control
Production Planning & Control
KunalJagtap5
 
Computer integrated production planning
Computer integrated production planningComputer integrated production planning
Computer integrated production planning
Venu Yadav
 
Scheduling Topic of Production and Operations
Scheduling Topic of Production and OperationsScheduling Topic of Production and Operations
Scheduling Topic of Production and Operations
ProfessionalDeeksha
 
Presentation on scheduling
Presentation on schedulingPresentation on scheduling
Presentation on scheduling
Gunjan Lal
 

Similar to Ppc unit-4-production scheduling (20)

Unit 4 PPC
Unit 4 PPCUnit 4 PPC
Unit 4 PPC
 
Unit 4
Unit 4Unit 4
Unit 4
 
Unit 4-IE6605 & PRODUCTION PLANNING AND CONTROL
Unit 4-IE6605 & PRODUCTION PLANNING AND CONTROLUnit 4-IE6605 & PRODUCTION PLANNING AND CONTROL
Unit 4-IE6605 & PRODUCTION PLANNING AND CONTROL
 
PRODUCTION PLANNING AND CONTROL
PRODUCTION PLANNING AND CONTROLPRODUCTION PLANNING AND CONTROL
PRODUCTION PLANNING AND CONTROL
 
unit 4.ppt
unit 4.pptunit 4.ppt
unit 4.ppt
 
Production planning and control
Production planning and controlProduction planning and control
Production planning and control
 
production scheduling
production schedulingproduction scheduling
production scheduling
 
Unit 7 production scheduling
Unit 7 production scheduling Unit 7 production scheduling
Unit 7 production scheduling
 
scheduling in operations Management PPT O and M
scheduling in operations Management PPT O and Mscheduling in operations Management PPT O and M
scheduling in operations Management PPT O and M
 
Unit 3 Manufacturing system design
Unit   3 Manufacturing system designUnit   3 Manufacturing system design
Unit 3 Manufacturing system design
 
MIn-218_chap 1.pptx
MIn-218_chap 1.pptxMIn-218_chap 1.pptx
MIn-218_chap 1.pptx
 
PRODUCTION AND OPERATIONS MANAGEMENT (304) SEM3 NOV2021.pdf
PRODUCTION AND OPERATIONS MANAGEMENT (304) SEM3 NOV2021.pdfPRODUCTION AND OPERATIONS MANAGEMENT (304) SEM3 NOV2021.pdf
PRODUCTION AND OPERATIONS MANAGEMENT (304) SEM3 NOV2021.pdf
 
schedulingandsequencing-140424065526-phpapp02__1_.ppt
schedulingandsequencing-140424065526-phpapp02__1_.pptschedulingandsequencing-140424065526-phpapp02__1_.ppt
schedulingandsequencing-140424065526-phpapp02__1_.ppt
 
MMS PRESENTAION.pptx
MMS PRESENTAION.pptxMMS PRESENTAION.pptx
MMS PRESENTAION.pptx
 
Operation scheduling
Operation schedulingOperation scheduling
Operation scheduling
 
Production Planning & Control
Production Planning & ControlProduction Planning & Control
Production Planning & Control
 
Computer integrated production planning
Computer integrated production planningComputer integrated production planning
Computer integrated production planning
 
Scheduling Topic of Production and Operations
Scheduling Topic of Production and OperationsScheduling Topic of Production and Operations
Scheduling Topic of Production and Operations
 
Seminar on cim 02
Seminar on cim 02Seminar on cim 02
Seminar on cim 02
 
Presentation on scheduling
Presentation on schedulingPresentation on scheduling
Presentation on scheduling
 

More from karthi keyan

UNIT-V FIRE SAFETY INSTALLATION
UNIT-V    FIRE SAFETY INSTALLATIONUNIT-V    FIRE SAFETY INSTALLATION
UNIT-V FIRE SAFETY INSTALLATION
karthi keyan
 
UNIT IV REFRIGERATION PRINCIPLES ...
UNIT IV	REFRIGERATION PRINCIPLES                                             ...UNIT IV	REFRIGERATION PRINCIPLES                                             ...
UNIT IV REFRIGERATION PRINCIPLES ...
karthi keyan
 
UNIT III PRINCIPLES OF ILLUMINATION
UNIT III	PRINCIPLES OF ILLUMINATION	UNIT III	PRINCIPLES OF ILLUMINATION
UNIT III PRINCIPLES OF ILLUMINATION
karthi keyan
 
UNII II ELECTRICAL SYSTEMS IN BUILDINGS
UNII II		ELECTRICAL SYSTEMS IN BUILDINGS	UNII II		ELECTRICAL SYSTEMS IN BUILDINGS
UNII II ELECTRICAL SYSTEMS IN BUILDINGS
karthi keyan
 
UNIT 1 MACHINERIES
UNIT 1       	MACHINERIES             UNIT 1       	MACHINERIES
UNIT 1 MACHINERIES
karthi keyan
 
UNIT-1--STEADY STRESSES AND VARIABLE STRESSES IN MACHINE MEMBERS.pptx
UNIT-1--STEADY STRESSES AND VARIABLE STRESSES IN MACHINE MEMBERS.pptxUNIT-1--STEADY STRESSES AND VARIABLE STRESSES IN MACHINE MEMBERS.pptx
UNIT-1--STEADY STRESSES AND VARIABLE STRESSES IN MACHINE MEMBERS.pptx
karthi keyan
 
UNIT-4-ENERGY STORING ELEMENTS AND ENGINE COMPONENTS.pptx
UNIT-4-ENERGY STORING ELEMENTS AND ENGINE COMPONENTS.pptxUNIT-4-ENERGY STORING ELEMENTS AND ENGINE COMPONENTS.pptx
UNIT-4-ENERGY STORING ELEMENTS AND ENGINE COMPONENTS.pptx
karthi keyan
 
UNIT-2-SHAFTS AND COUPLINGS.pptx
UNIT-2-SHAFTS AND COUPLINGS.pptxUNIT-2-SHAFTS AND COUPLINGS.pptx
UNIT-2-SHAFTS AND COUPLINGS.pptx
karthi keyan
 
UNIT-5-BEARINGS AND ENGINE COMPONENTS.pptx
UNIT-5-BEARINGS AND ENGINE COMPONENTS.pptxUNIT-5-BEARINGS AND ENGINE COMPONENTS.pptx
UNIT-5-BEARINGS AND ENGINE COMPONENTS.pptx
karthi keyan
 
UNIT-3-TEMPORARY AND PERMANENT JOINTS.pptx
UNIT-3-TEMPORARY AND PERMANENT JOINTS.pptxUNIT-3-TEMPORARY AND PERMANENT JOINTS.pptx
UNIT-3-TEMPORARY AND PERMANENT JOINTS.pptx
karthi keyan
 
UNIT-1-BASICS OF MECHANISMS.ppt
UNIT-1-BASICS OF MECHANISMS.pptUNIT-1-BASICS OF MECHANISMS.ppt
UNIT-1-BASICS OF MECHANISMS.ppt
karthi keyan
 
UNIT-5 - FRICTION IN MACHINE ELEMENTS.pptx
UNIT-5 - FRICTION IN MACHINE ELEMENTS.pptxUNIT-5 - FRICTION IN MACHINE ELEMENTS.pptx
UNIT-5 - FRICTION IN MACHINE ELEMENTS.pptx
karthi keyan
 
UNIT-2 -KINEMATICS OF LINKAGE MECHANISM.pptx
UNIT-2 -KINEMATICS OF LINKAGE MECHANISM.pptxUNIT-2 -KINEMATICS OF LINKAGE MECHANISM.pptx
UNIT-2 -KINEMATICS OF LINKAGE MECHANISM.pptx
karthi keyan
 
UNIT-4 - GEARS AND GEAR TRAINS.pptx
UNIT-4 - GEARS AND GEAR TRAINS.pptxUNIT-4 - GEARS AND GEAR TRAINS.pptx
UNIT-4 - GEARS AND GEAR TRAINS.pptx
karthi keyan
 
UNIT -3 -KINEMATICS OF CAM MECHANISMS.ppt
UNIT -3 -KINEMATICS OF CAM MECHANISMS.pptUNIT -3 -KINEMATICS OF CAM MECHANISMS.ppt
UNIT -3 -KINEMATICS OF CAM MECHANISMS.ppt
karthi keyan
 
UNIT V ALTERNATIVE ENERGY SOURCES
UNIT V ALTERNATIVE ENERGY SOURCES UNIT V ALTERNATIVE ENERGY SOURCES
UNIT V ALTERNATIVE ENERGY SOURCES
karthi keyan
 
UNIT IV STEERING, BRAKES AND SUSPENSION SYSTEMS
UNIT IV    STEERING, BRAKES AND SUSPENSION SYSTEMS	UNIT IV    STEERING, BRAKES AND SUSPENSION SYSTEMS
UNIT IV STEERING, BRAKES AND SUSPENSION SYSTEMS
karthi keyan
 
UNIT III TRANSMISSION SYSTEMS
UNIT III TRANSMISSION SYSTEMSUNIT III TRANSMISSION SYSTEMS
UNIT III TRANSMISSION SYSTEMS
karthi keyan
 
UNIT II ENGINE AUXILIARY SYSTEMS
UNIT II ENGINE AUXILIARY SYSTEMS UNIT II ENGINE AUXILIARY SYSTEMS
UNIT II ENGINE AUXILIARY SYSTEMS
karthi keyan
 
Unit 1--VEHICLE STRUCTURE AND ENGINES
Unit 1--VEHICLE STRUCTURE AND ENGINESUnit 1--VEHICLE STRUCTURE AND ENGINES
Unit 1--VEHICLE STRUCTURE AND ENGINES
karthi keyan
 

More from karthi keyan (20)

UNIT-V FIRE SAFETY INSTALLATION
UNIT-V    FIRE SAFETY INSTALLATIONUNIT-V    FIRE SAFETY INSTALLATION
UNIT-V FIRE SAFETY INSTALLATION
 
UNIT IV REFRIGERATION PRINCIPLES ...
UNIT IV	REFRIGERATION PRINCIPLES                                             ...UNIT IV	REFRIGERATION PRINCIPLES                                             ...
UNIT IV REFRIGERATION PRINCIPLES ...
 
UNIT III PRINCIPLES OF ILLUMINATION
UNIT III	PRINCIPLES OF ILLUMINATION	UNIT III	PRINCIPLES OF ILLUMINATION
UNIT III PRINCIPLES OF ILLUMINATION
 
UNII II ELECTRICAL SYSTEMS IN BUILDINGS
UNII II		ELECTRICAL SYSTEMS IN BUILDINGS	UNII II		ELECTRICAL SYSTEMS IN BUILDINGS
UNII II ELECTRICAL SYSTEMS IN BUILDINGS
 
UNIT 1 MACHINERIES
UNIT 1       	MACHINERIES             UNIT 1       	MACHINERIES
UNIT 1 MACHINERIES
 
UNIT-1--STEADY STRESSES AND VARIABLE STRESSES IN MACHINE MEMBERS.pptx
UNIT-1--STEADY STRESSES AND VARIABLE STRESSES IN MACHINE MEMBERS.pptxUNIT-1--STEADY STRESSES AND VARIABLE STRESSES IN MACHINE MEMBERS.pptx
UNIT-1--STEADY STRESSES AND VARIABLE STRESSES IN MACHINE MEMBERS.pptx
 
UNIT-4-ENERGY STORING ELEMENTS AND ENGINE COMPONENTS.pptx
UNIT-4-ENERGY STORING ELEMENTS AND ENGINE COMPONENTS.pptxUNIT-4-ENERGY STORING ELEMENTS AND ENGINE COMPONENTS.pptx
UNIT-4-ENERGY STORING ELEMENTS AND ENGINE COMPONENTS.pptx
 
UNIT-2-SHAFTS AND COUPLINGS.pptx
UNIT-2-SHAFTS AND COUPLINGS.pptxUNIT-2-SHAFTS AND COUPLINGS.pptx
UNIT-2-SHAFTS AND COUPLINGS.pptx
 
UNIT-5-BEARINGS AND ENGINE COMPONENTS.pptx
UNIT-5-BEARINGS AND ENGINE COMPONENTS.pptxUNIT-5-BEARINGS AND ENGINE COMPONENTS.pptx
UNIT-5-BEARINGS AND ENGINE COMPONENTS.pptx
 
UNIT-3-TEMPORARY AND PERMANENT JOINTS.pptx
UNIT-3-TEMPORARY AND PERMANENT JOINTS.pptxUNIT-3-TEMPORARY AND PERMANENT JOINTS.pptx
UNIT-3-TEMPORARY AND PERMANENT JOINTS.pptx
 
UNIT-1-BASICS OF MECHANISMS.ppt
UNIT-1-BASICS OF MECHANISMS.pptUNIT-1-BASICS OF MECHANISMS.ppt
UNIT-1-BASICS OF MECHANISMS.ppt
 
UNIT-5 - FRICTION IN MACHINE ELEMENTS.pptx
UNIT-5 - FRICTION IN MACHINE ELEMENTS.pptxUNIT-5 - FRICTION IN MACHINE ELEMENTS.pptx
UNIT-5 - FRICTION IN MACHINE ELEMENTS.pptx
 
UNIT-2 -KINEMATICS OF LINKAGE MECHANISM.pptx
UNIT-2 -KINEMATICS OF LINKAGE MECHANISM.pptxUNIT-2 -KINEMATICS OF LINKAGE MECHANISM.pptx
UNIT-2 -KINEMATICS OF LINKAGE MECHANISM.pptx
 
UNIT-4 - GEARS AND GEAR TRAINS.pptx
UNIT-4 - GEARS AND GEAR TRAINS.pptxUNIT-4 - GEARS AND GEAR TRAINS.pptx
UNIT-4 - GEARS AND GEAR TRAINS.pptx
 
UNIT -3 -KINEMATICS OF CAM MECHANISMS.ppt
UNIT -3 -KINEMATICS OF CAM MECHANISMS.pptUNIT -3 -KINEMATICS OF CAM MECHANISMS.ppt
UNIT -3 -KINEMATICS OF CAM MECHANISMS.ppt
 
UNIT V ALTERNATIVE ENERGY SOURCES
UNIT V ALTERNATIVE ENERGY SOURCES UNIT V ALTERNATIVE ENERGY SOURCES
UNIT V ALTERNATIVE ENERGY SOURCES
 
UNIT IV STEERING, BRAKES AND SUSPENSION SYSTEMS
UNIT IV    STEERING, BRAKES AND SUSPENSION SYSTEMS	UNIT IV    STEERING, BRAKES AND SUSPENSION SYSTEMS
UNIT IV STEERING, BRAKES AND SUSPENSION SYSTEMS
 
UNIT III TRANSMISSION SYSTEMS
UNIT III TRANSMISSION SYSTEMSUNIT III TRANSMISSION SYSTEMS
UNIT III TRANSMISSION SYSTEMS
 
UNIT II ENGINE AUXILIARY SYSTEMS
UNIT II ENGINE AUXILIARY SYSTEMS UNIT II ENGINE AUXILIARY SYSTEMS
UNIT II ENGINE AUXILIARY SYSTEMS
 
Unit 1--VEHICLE STRUCTURE AND ENGINES
Unit 1--VEHICLE STRUCTURE AND ENGINESUnit 1--VEHICLE STRUCTURE AND ENGINES
Unit 1--VEHICLE STRUCTURE AND ENGINES
 

Recently uploaded

WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
Pipe Restoration Solutions
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
AmarGB2
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 

Recently uploaded (20)

WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 

Ppc unit-4-production scheduling

  • 2. Functions of Production Control and Scheduling Release Order – to the system Assign Work – to work Centers Sequencing priority Jobs Control – the manufac. Lead Time Monitor Priority Status Monitor Capacity Status Six Key Functio ns
  • 3. Production Scheduling & Control Function
  • 6. LOADING • Once the route has been established, the work required can be loaded against the selected machine or workstation. • The total time required to perform the operation is computed by multiplying the unit operation times given on the standard process sheet by the number of parts to be processed. • This total time is then added to the work already planned for the workstation. • This is the function of loading, and it results in a tabulated list or chart showing the planned utilization of the machines or workstations in the plant
  • 7. SCHEDULING • Scheduling is the last of the planning functions. • It determines when an operation is to be performed, or when work is to be completed; the difference lies in the detail of the scheduling procedure. • In a centralized control situation - where all process planning, loading, and scheduling for the plant are done in a central office- the details of the schedule may specify the starting and finishing time for an operation. • On the other hand, the central schedule may simply give a completion time for the work in a given department.
  • 9. SCHEDULING -BENEFITS • Inventory reduction, • Process change-over reduction • leveling • Reduced scheduling effort • Increased production efficiency • Labor load leveling • Accurate delivery date quotes • Real time information
  • 10. GANTT CHART •A Gantt chart is a type of bar chart, developed by Henry Gantt, that illustrates a project schedule. • Gantt charts illustrate the start and finish dates of the terminal elements and summary elements of a project. Terminal elements and summary elements comprise the work breakdown structure of the project. •Some Gantt charts also show the dependency (i.e., precedence network) relationships between activities.
  • 11. Production Control • Perpetual loading – Tabulation of the time necessary to finish unfulfilled orders and determine how long it will take to finish this work. Perpetual loading
  • 12. LINE OF BALANCE • Find a feasible defined replacement for all undefined (‘ANY’) ergonomic constraints on workstations, i.e. one compatible with the ergonomic constraints and precedence constraints defined on operations, as well as zoning constraints and possible drifting operations • Solve the within-workstation scheduling problem on all workstations, for all products being assembled on the line • Assign the operations to workstations to achieve the best average balance, while keeping the peak times at a manageable level.
  • 13. Linear Scheduling Method • Linear Scheduling Method (LSM) is a graphical scheduling method focusing on continuous resource utilization in repetitive activities. It is believed that it originally adopted the idea of Line-Of-Balance method. • The main advantages of LSM over Critical Path Method (CPM) is its underlying idea of keeping resources continuously at work. In other words, it schedules activities in such a way that: 1. resource utilization is maximized; 2. interruption in on-going process is minimized, including hiring-and- firing; and 3. the effect of the learning curve phenomenon is minimized
  • 14. BATCH PRODUCTION SCHEDULING • Batch production scheduling is the practice of planning and scheduling of batch manufacturing processes. • Although, scheduling may apply to traditionally continuous processes, such as refining, it is especially important for batch processes such as those for pharmaceutical active ingredients, biotechnology processes and many specialty chemical processes. • Batch production scheduling shares some concepts and techniques with finite capacity scheduling which has been applied to many manufacturing problems. • The specific issues of scheduling batch manufacturing processes have generated considerable industrial and academic interest
  • 15. MRP
  • 17. DISPATCHING • Authorizing the start of an operation on the shop floor is the function of dispatching. • This function may be centralized or decentralized. • The departmental dispatcher would authorize the start of each of the machine operations – the dispatch actions are based on the foreman’s routing and scheduling of the work through his department. This is decentralized dispatching.
  • 18. PROGRESS REPORTING AND EXPEDITING • The manufacturing activity of a plant is said to be “in control” when the actual performance is within the objectives of the planned performance. • When jobs are started and completed on schedule, there should be very little, if any, concern about the meeting of commitments. • Optimum operation of the plant, however, is attained only if the original plan has been carefully prepared to utilize the manufacturing facilities fully and effectively.