SlideShare a Scribd company logo
1 of 18
PRODUCTION
SCHEDULING
Unit-4
PRODUCTION CONTROL
LOADING AND SCHEDULING
LOADING
• Once the route has been established, the work required can
be loaded against the selected machine or workstation.
• The total time required to perform the operation is computed
by multiplying the unit operation times given on the standard
process sheet by the number of parts to be processed.
• This total time is then added to the work already planned for
the workstation.
• This is the function of loading, and it results in a tabulated list
or chart showing the planned utilization of the machines or
workstations in the plant
SCHEDULING
• Scheduling is the last of the planning functions.
• It determines when an operation is to be performed, or when
work is to be completed; the difference lies in the detail of the
scheduling procedure.
• In a centralized control situation - where all process planning,
loading, and scheduling for the plant are done in a central
office- the details of the schedule may specify the starting and
finishing time for an operation.
• On the other hand, the central schedule may simply give a
completion time for the work in a given department.
MASTER SCHEDULING
SCHEDULING -BENEFITS
• Inventory reduction,
• Process change-over reduction
• leveling
• Reduced scheduling effort
• Increased production efficiency
• Labor load leveling
• Accurate delivery date quotes
• Real time information
GANTT CHART
•A Gantt chart is a type of bar chart, developed by Henry Gantt,
that illustrates a project schedule.
• Gantt charts illustrate the start
and finish dates of the terminal elements and summary elements
of a project. Terminal elements and summary elements comprise
the work breakdown structure of the project.
•Some Gantt charts also show the dependency (i.e., precedence network)
relationships between activities.
Production Control
• Perpetual loading
– Tabulation of the time necessary to finish unfulfilled orders and
determine how long it will take to finish this work.
Perpetual loading
LINE OF BALANCE
• Find a feasible defined replacement for all undefined
(‘ANY’) ergonomic constraints on workstations, i.e. one
compatible with the ergonomic constraints and
precedence constraints defined on operations, as well as
zoning constraints and possible drifting operations
• Solve the within-workstation scheduling problem on all
workstations, for all products being assembled on the line
• Assign the operations to workstations to achieve the best
average balance, while keeping the peak times at a
manageable level.
Linear Scheduling Method
• Linear Scheduling Method (LSM) is a graphical scheduling method
focusing on continuous resource utilization in repetitive activities. It is
believed that it originally adopted the idea of Line-Of-Balance method.
• The main advantages of LSM over Critical Path Method (CPM) is its
underlying idea of keeping resources continuously at work. In other
words, it schedules activities in such a way that:
1. resource utilization is maximized;
2. interruption in on-going process is minimized, including hiring-and-
firing; and
3. the effect of the learning curve phenomenon is minimized
BATCH PRODUCTION SCHEDULING
• Batch production scheduling is the practice of planning and
scheduling of batch manufacturing processes.
• Although, scheduling may apply to traditionally continuous
processes, such as refining, it is especially important for batch
processes such as those for pharmaceutical active ingredients,
biotechnology processes and many specialty chemical
processes.
• Batch production scheduling shares some concepts and
techniques with finite capacity scheduling which has been
applied to many manufacturing problems.
• The specific issues of scheduling batch manufacturing
processes have generated considerable industrial and
academic interest
MRP
KANBAN
DISPATCHING
• Authorizing the start of an operation on the shop
floor is the function of dispatching.
• This function may be centralized or decentralized.
• The departmental dispatcher would authorize the
start of each of the machine operations – the
dispatch actions are based on the foreman’s routing
and scheduling of the work through his department.
This is decentralized dispatching.
PROGRESS REPORTING AND EXPEDITING
• The manufacturing activity of a plant is said to be “in
control” when the actual performance is within the
objectives of the planned performance.
• When jobs are started and completed on schedule,
there should be very little, if any, concern about the
meeting of commitments.
• Optimum operation of the plant, however, is attained
only if the original plan has been carefully prepared
to utilize the manufacturing facilities fully and
effectively.
Mfg. lead time
Mfg. lead time

More Related Content

What's hot

PRODUCTION PLANNING AND CONTROL-Unit 4
PRODUCTION PLANNING AND CONTROL-Unit 4PRODUCTION PLANNING AND CONTROL-Unit 4
PRODUCTION PLANNING AND CONTROL-Unit 4prakash0712
 
Ppc unit-1-production planning and control
Ppc   unit-1-production planning and controlPpc   unit-1-production planning and control
Ppc unit-1-production planning and controlkarthi keyan
 
Work measurement increases productivityand role of jit om
Work measurement increases productivityand role of jit   omWork measurement increases productivityand role of jit   om
Work measurement increases productivityand role of jit omHallmark B-school
 
4.types of manufacturing system and layouts
4.types of manufacturing system and layouts4.types of manufacturing system and layouts
4.types of manufacturing system and layoutsAkash Bakshi
 
PPCE unit 3 (ME8793 – PROCESS PLANNING AND COST ESTIMATION)
 PPCE  unit 3 (ME8793 – PROCESS PLANNING AND COST ESTIMATION)  PPCE  unit 3 (ME8793 – PROCESS PLANNING AND COST ESTIMATION)
PPCE unit 3 (ME8793 – PROCESS PLANNING AND COST ESTIMATION) TAMILMECHKIT
 
Inventory production and Recent trends in PPC
Inventory production and Recent trends in PPCInventory production and Recent trends in PPC
Inventory production and Recent trends in PPCPraveenManickam2
 
Production Planning and Process Planning
Production Planning and Process PlanningProduction Planning and Process Planning
Production Planning and Process PlanningPraveenManickam2
 

What's hot (15)

Unit 4
Unit 4Unit 4
Unit 4
 
PRODUCTION PLANNING AND CONTROL-Unit 4
PRODUCTION PLANNING AND CONTROL-Unit 4PRODUCTION PLANNING AND CONTROL-Unit 4
PRODUCTION PLANNING AND CONTROL-Unit 4
 
Unit 2
Unit 2Unit 2
Unit 2
 
Unit 1
Unit 1Unit 1
Unit 1
 
Unit 4
Unit 4Unit 4
Unit 4
 
Unit 3
Unit 3Unit 3
Unit 3
 
Unit 2
Unit 2Unit 2
Unit 2
 
Unit 1 PPC
Unit 1 PPCUnit 1 PPC
Unit 1 PPC
 
Ppc unit-1-production planning and control
Ppc   unit-1-production planning and controlPpc   unit-1-production planning and control
Ppc unit-1-production planning and control
 
Work measurement increases productivityand role of jit om
Work measurement increases productivityand role of jit   omWork measurement increases productivityand role of jit   om
Work measurement increases productivityand role of jit om
 
4.types of manufacturing system and layouts
4.types of manufacturing system and layouts4.types of manufacturing system and layouts
4.types of manufacturing system and layouts
 
Unit 2
Unit 2Unit 2
Unit 2
 
PPCE unit 3 (ME8793 – PROCESS PLANNING AND COST ESTIMATION)
 PPCE  unit 3 (ME8793 – PROCESS PLANNING AND COST ESTIMATION)  PPCE  unit 3 (ME8793 – PROCESS PLANNING AND COST ESTIMATION)
PPCE unit 3 (ME8793 – PROCESS PLANNING AND COST ESTIMATION)
 
Inventory production and Recent trends in PPC
Inventory production and Recent trends in PPCInventory production and Recent trends in PPC
Inventory production and Recent trends in PPC
 
Production Planning and Process Planning
Production Planning and Process PlanningProduction Planning and Process Planning
Production Planning and Process Planning
 

Similar to Unit 4-IE6605 & PRODUCTION PLANNING AND CONTROL

Ppc unit-4-production scheduling
Ppc   unit-4-production schedulingPpc   unit-4-production scheduling
Ppc unit-4-production schedulingkarthi keyan
 
Production planning and control
Production planning and controlProduction planning and control
Production planning and controlLaxmikant Deshmukh
 
scheduling in operations Management PPT O and M
scheduling in operations Management PPT O and Mscheduling in operations Management PPT O and M
scheduling in operations Management PPT O and MProfessionalDeeksha
 
Operation scheduling
Operation schedulingOperation scheduling
Operation schedulingsai precious
 
Scheduling Topic of Production and Operations
Scheduling Topic of Production and OperationsScheduling Topic of Production and Operations
Scheduling Topic of Production and OperationsProfessionalDeeksha
 
Unit 7 production scheduling
Unit 7 production scheduling Unit 7 production scheduling
Unit 7 production scheduling RASHMIPANWAR10
 
Presentation on scheduling
Presentation on schedulingPresentation on scheduling
Presentation on schedulingGunjan Lal
 
MIn-218_chap 1.pptx
MIn-218_chap 1.pptxMIn-218_chap 1.pptx
MIn-218_chap 1.pptxArpanKumar79
 
Scheduling and sequencing
Scheduling and sequencingScheduling and sequencing
Scheduling and sequencingAkanksha Gupta
 
Operations Scheduling
Operations SchedulingOperations Scheduling
Operations SchedulingAshish Jain
 
Production management
Production managementProduction management
Production managementPurnesh Aloni
 
Production Planning & Control
Production Planning & ControlProduction Planning & Control
Production Planning & ControlKunalJagtap5
 
PRODUCTION AND OPERATIONS MANAGEMENT (304) SEM3 NOV2021.pdf
PRODUCTION AND OPERATIONS MANAGEMENT (304) SEM3 NOV2021.pdfPRODUCTION AND OPERATIONS MANAGEMENT (304) SEM3 NOV2021.pdf
PRODUCTION AND OPERATIONS MANAGEMENT (304) SEM3 NOV2021.pdfPratikDalvi17
 
Computer integrated production planning
Computer integrated production planningComputer integrated production planning
Computer integrated production planningVenu Yadav
 

Similar to Unit 4-IE6605 & PRODUCTION PLANNING AND CONTROL (20)

Ppc unit-4-production scheduling
Ppc   unit-4-production schedulingPpc   unit-4-production scheduling
Ppc unit-4-production scheduling
 
UNIT 4 - PRODUCTION SCHEDULING
UNIT 4 - PRODUCTION SCHEDULINGUNIT 4 - PRODUCTION SCHEDULING
UNIT 4 - PRODUCTION SCHEDULING
 
Production planning and control
Production planning and controlProduction planning and control
Production planning and control
 
scheduling in operations Management PPT O and M
scheduling in operations Management PPT O and Mscheduling in operations Management PPT O and M
scheduling in operations Management PPT O and M
 
Operation scheduling
Operation schedulingOperation scheduling
Operation scheduling
 
Scheduling Topic of Production and Operations
Scheduling Topic of Production and OperationsScheduling Topic of Production and Operations
Scheduling Topic of Production and Operations
 
Unit 7 production scheduling
Unit 7 production scheduling Unit 7 production scheduling
Unit 7 production scheduling
 
Presentation on scheduling
Presentation on schedulingPresentation on scheduling
Presentation on scheduling
 
production scheduling
production schedulingproduction scheduling
production scheduling
 
MIn-218_chap 1.pptx
MIn-218_chap 1.pptxMIn-218_chap 1.pptx
MIn-218_chap 1.pptx
 
Scheduling and sequencing
Scheduling and sequencingScheduling and sequencing
Scheduling and sequencing
 
Operations Scheduling
Operations SchedulingOperations Scheduling
Operations Scheduling
 
Production management
Production managementProduction management
Production management
 
Unit 3 Manufacturing system design
Unit   3 Manufacturing system designUnit   3 Manufacturing system design
Unit 3 Manufacturing system design
 
MMS PRESENTAION.pptx
MMS PRESENTAION.pptxMMS PRESENTAION.pptx
MMS PRESENTAION.pptx
 
Operations management
Operations managementOperations management
Operations management
 
Production Planning & Control
Production Planning & ControlProduction Planning & Control
Production Planning & Control
 
Scheduling
SchedulingScheduling
Scheduling
 
PRODUCTION AND OPERATIONS MANAGEMENT (304) SEM3 NOV2021.pdf
PRODUCTION AND OPERATIONS MANAGEMENT (304) SEM3 NOV2021.pdfPRODUCTION AND OPERATIONS MANAGEMENT (304) SEM3 NOV2021.pdf
PRODUCTION AND OPERATIONS MANAGEMENT (304) SEM3 NOV2021.pdf
 
Computer integrated production planning
Computer integrated production planningComputer integrated production planning
Computer integrated production planning
 

More from Mohanumar S

20CE501PE – INDUSTRIAL WASTE MANAGEMENT.ppt
20CE501PE – INDUSTRIAL WASTE MANAGEMENT.ppt20CE501PE – INDUSTRIAL WASTE MANAGEMENT.ppt
20CE501PE – INDUSTRIAL WASTE MANAGEMENT.pptMohanumar S
 
20ME702– MECHATRONICS -UNIT-4.ppt
20ME702– MECHATRONICS -UNIT-4.ppt20ME702– MECHATRONICS -UNIT-4.ppt
20ME702– MECHATRONICS -UNIT-4.pptMohanumar S
 
20ME702– MECHATRONICS -UNIT-3.ppt
20ME702– MECHATRONICS -UNIT-3.ppt20ME702– MECHATRONICS -UNIT-3.ppt
20ME702– MECHATRONICS -UNIT-3.pptMohanumar S
 
20ME702– MECHATRONICS -UNIT-2.pptx
20ME702– MECHATRONICS -UNIT-2.pptx20ME702– MECHATRONICS -UNIT-2.pptx
20ME702– MECHATRONICS -UNIT-2.pptxMohanumar S
 
20ME702– MECHATRONICS -UNIT-5-Motor.ppt
20ME702– MECHATRONICS -UNIT-5-Motor.ppt20ME702– MECHATRONICS -UNIT-5-Motor.ppt
20ME702– MECHATRONICS -UNIT-5-Motor.pptMohanumar S
 
20ME702– MECHATRONICS -UNIT-1-Sensor and transducers.ppt
20ME702– MECHATRONICS -UNIT-1-Sensor and transducers.ppt20ME702– MECHATRONICS -UNIT-1-Sensor and transducers.ppt
20ME702– MECHATRONICS -UNIT-1-Sensor and transducers.pptMohanumar S
 
M.P- II-UNIT II CENTRE LATHE AND SPECIAL PURPOSE LATHES..ppt
M.P- II-UNIT II  CENTRE LATHE AND SPECIAL PURPOSE  LATHES..pptM.P- II-UNIT II  CENTRE LATHE AND SPECIAL PURPOSE  LATHES..ppt
M.P- II-UNIT II CENTRE LATHE AND SPECIAL PURPOSE LATHES..pptMohanumar S
 
M.P- II-UNIT I -THEORY OF METAL CUTTING.ppt
M.P- II-UNIT I -THEORY OF METAL CUTTING.pptM.P- II-UNIT I -THEORY OF METAL CUTTING.ppt
M.P- II-UNIT I -THEORY OF METAL CUTTING.pptMohanumar S
 
M.P- II-UNIT III-SHAPER, MILLING AND BROACHING MACHINES.ppt
M.P- II-UNIT III-SHAPER, MILLING AND BROACHING MACHINES.pptM.P- II-UNIT III-SHAPER, MILLING AND BROACHING MACHINES.ppt
M.P- II-UNIT III-SHAPER, MILLING AND BROACHING MACHINES.pptMohanumar S
 
M.P- II-UNIT IV - ABRASIVE PROCESSES AND GEAR CUTTING.pptx
M.P- II-UNIT IV - ABRASIVE PROCESSES AND GEAR CUTTING.pptxM.P- II-UNIT IV - ABRASIVE PROCESSES AND GEAR CUTTING.pptx
M.P- II-UNIT IV - ABRASIVE PROCESSES AND GEAR CUTTING.pptxMohanumar S
 
M.P- II-UNIT V - CNC MACHINE TOOLS AND PART PROGRAMMING.ppt
M.P- II-UNIT V - CNC MACHINE TOOLS AND PART PROGRAMMING.pptM.P- II-UNIT V - CNC MACHINE TOOLS AND PART PROGRAMMING.ppt
M.P- II-UNIT V - CNC MACHINE TOOLS AND PART PROGRAMMING.pptMohanumar S
 
EM-Unit-V-Mechanical properties
EM-Unit-V-Mechanical propertiesEM-Unit-V-Mechanical properties
EM-Unit-V-Mechanical propertiesMohanumar S
 
EM-UNIT-V-Testing utm-hardness-impact
EM-UNIT-V-Testing  utm-hardness-impactEM-UNIT-V-Testing  utm-hardness-impact
EM-UNIT-V-Testing utm-hardness-impactMohanumar S
 
EM-Unit-IV- Vacuum plasma hardening
EM-Unit-IV- Vacuum plasma hardeningEM-Unit-IV- Vacuum plasma hardening
EM-Unit-IV- Vacuum plasma hardeningMohanumar S
 
EM-Unit-IV- Ttt diagram
EM-Unit-IV- Ttt diagramEM-Unit-IV- Ttt diagram
EM-Unit-IV- Ttt diagramMohanumar S
 
EM-Unit-IV- Cct diagram
EM-Unit-IV- Cct diagramEM-Unit-IV- Cct diagram
EM-Unit-IV- Cct diagramMohanumar S
 
EM-Unit-IV- Case hardening
EM-Unit-IV- Case hardeningEM-Unit-IV- Case hardening
EM-Unit-IV- Case hardeningMohanumar S
 
EM-Unit-IV- case hardening
EM-Unit-IV- case hardeningEM-Unit-IV- case hardening
EM-Unit-IV- case hardeningMohanumar S
 
EM-Unit-IV- heat treatment
EM-Unit-IV- heat treatmentEM-Unit-IV- heat treatment
EM-Unit-IV- heat treatmentMohanumar S
 
EM-UNIT III -ceramics & composites
EM-UNIT III -ceramics & compositesEM-UNIT III -ceramics & composites
EM-UNIT III -ceramics & compositesMohanumar S
 

More from Mohanumar S (20)

20CE501PE – INDUSTRIAL WASTE MANAGEMENT.ppt
20CE501PE – INDUSTRIAL WASTE MANAGEMENT.ppt20CE501PE – INDUSTRIAL WASTE MANAGEMENT.ppt
20CE501PE – INDUSTRIAL WASTE MANAGEMENT.ppt
 
20ME702– MECHATRONICS -UNIT-4.ppt
20ME702– MECHATRONICS -UNIT-4.ppt20ME702– MECHATRONICS -UNIT-4.ppt
20ME702– MECHATRONICS -UNIT-4.ppt
 
20ME702– MECHATRONICS -UNIT-3.ppt
20ME702– MECHATRONICS -UNIT-3.ppt20ME702– MECHATRONICS -UNIT-3.ppt
20ME702– MECHATRONICS -UNIT-3.ppt
 
20ME702– MECHATRONICS -UNIT-2.pptx
20ME702– MECHATRONICS -UNIT-2.pptx20ME702– MECHATRONICS -UNIT-2.pptx
20ME702– MECHATRONICS -UNIT-2.pptx
 
20ME702– MECHATRONICS -UNIT-5-Motor.ppt
20ME702– MECHATRONICS -UNIT-5-Motor.ppt20ME702– MECHATRONICS -UNIT-5-Motor.ppt
20ME702– MECHATRONICS -UNIT-5-Motor.ppt
 
20ME702– MECHATRONICS -UNIT-1-Sensor and transducers.ppt
20ME702– MECHATRONICS -UNIT-1-Sensor and transducers.ppt20ME702– MECHATRONICS -UNIT-1-Sensor and transducers.ppt
20ME702– MECHATRONICS -UNIT-1-Sensor and transducers.ppt
 
M.P- II-UNIT II CENTRE LATHE AND SPECIAL PURPOSE LATHES..ppt
M.P- II-UNIT II  CENTRE LATHE AND SPECIAL PURPOSE  LATHES..pptM.P- II-UNIT II  CENTRE LATHE AND SPECIAL PURPOSE  LATHES..ppt
M.P- II-UNIT II CENTRE LATHE AND SPECIAL PURPOSE LATHES..ppt
 
M.P- II-UNIT I -THEORY OF METAL CUTTING.ppt
M.P- II-UNIT I -THEORY OF METAL CUTTING.pptM.P- II-UNIT I -THEORY OF METAL CUTTING.ppt
M.P- II-UNIT I -THEORY OF METAL CUTTING.ppt
 
M.P- II-UNIT III-SHAPER, MILLING AND BROACHING MACHINES.ppt
M.P- II-UNIT III-SHAPER, MILLING AND BROACHING MACHINES.pptM.P- II-UNIT III-SHAPER, MILLING AND BROACHING MACHINES.ppt
M.P- II-UNIT III-SHAPER, MILLING AND BROACHING MACHINES.ppt
 
M.P- II-UNIT IV - ABRASIVE PROCESSES AND GEAR CUTTING.pptx
M.P- II-UNIT IV - ABRASIVE PROCESSES AND GEAR CUTTING.pptxM.P- II-UNIT IV - ABRASIVE PROCESSES AND GEAR CUTTING.pptx
M.P- II-UNIT IV - ABRASIVE PROCESSES AND GEAR CUTTING.pptx
 
M.P- II-UNIT V - CNC MACHINE TOOLS AND PART PROGRAMMING.ppt
M.P- II-UNIT V - CNC MACHINE TOOLS AND PART PROGRAMMING.pptM.P- II-UNIT V - CNC MACHINE TOOLS AND PART PROGRAMMING.ppt
M.P- II-UNIT V - CNC MACHINE TOOLS AND PART PROGRAMMING.ppt
 
EM-Unit-V-Mechanical properties
EM-Unit-V-Mechanical propertiesEM-Unit-V-Mechanical properties
EM-Unit-V-Mechanical properties
 
EM-UNIT-V-Testing utm-hardness-impact
EM-UNIT-V-Testing  utm-hardness-impactEM-UNIT-V-Testing  utm-hardness-impact
EM-UNIT-V-Testing utm-hardness-impact
 
EM-Unit-IV- Vacuum plasma hardening
EM-Unit-IV- Vacuum plasma hardeningEM-Unit-IV- Vacuum plasma hardening
EM-Unit-IV- Vacuum plasma hardening
 
EM-Unit-IV- Ttt diagram
EM-Unit-IV- Ttt diagramEM-Unit-IV- Ttt diagram
EM-Unit-IV- Ttt diagram
 
EM-Unit-IV- Cct diagram
EM-Unit-IV- Cct diagramEM-Unit-IV- Cct diagram
EM-Unit-IV- Cct diagram
 
EM-Unit-IV- Case hardening
EM-Unit-IV- Case hardeningEM-Unit-IV- Case hardening
EM-Unit-IV- Case hardening
 
EM-Unit-IV- case hardening
EM-Unit-IV- case hardeningEM-Unit-IV- case hardening
EM-Unit-IV- case hardening
 
EM-Unit-IV- heat treatment
EM-Unit-IV- heat treatmentEM-Unit-IV- heat treatment
EM-Unit-IV- heat treatment
 
EM-UNIT III -ceramics & composites
EM-UNIT III -ceramics & compositesEM-UNIT III -ceramics & composites
EM-UNIT III -ceramics & composites
 

Recently uploaded

Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 

Recently uploaded (20)

Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 

Unit 4-IE6605 & PRODUCTION PLANNING AND CONTROL

  • 4. LOADING • Once the route has been established, the work required can be loaded against the selected machine or workstation. • The total time required to perform the operation is computed by multiplying the unit operation times given on the standard process sheet by the number of parts to be processed. • This total time is then added to the work already planned for the workstation. • This is the function of loading, and it results in a tabulated list or chart showing the planned utilization of the machines or workstations in the plant
  • 5. SCHEDULING • Scheduling is the last of the planning functions. • It determines when an operation is to be performed, or when work is to be completed; the difference lies in the detail of the scheduling procedure. • In a centralized control situation - where all process planning, loading, and scheduling for the plant are done in a central office- the details of the schedule may specify the starting and finishing time for an operation. • On the other hand, the central schedule may simply give a completion time for the work in a given department.
  • 7. SCHEDULING -BENEFITS • Inventory reduction, • Process change-over reduction • leveling • Reduced scheduling effort • Increased production efficiency • Labor load leveling • Accurate delivery date quotes • Real time information
  • 8. GANTT CHART •A Gantt chart is a type of bar chart, developed by Henry Gantt, that illustrates a project schedule. • Gantt charts illustrate the start and finish dates of the terminal elements and summary elements of a project. Terminal elements and summary elements comprise the work breakdown structure of the project. •Some Gantt charts also show the dependency (i.e., precedence network) relationships between activities.
  • 9. Production Control • Perpetual loading – Tabulation of the time necessary to finish unfulfilled orders and determine how long it will take to finish this work. Perpetual loading
  • 10. LINE OF BALANCE • Find a feasible defined replacement for all undefined (‘ANY’) ergonomic constraints on workstations, i.e. one compatible with the ergonomic constraints and precedence constraints defined on operations, as well as zoning constraints and possible drifting operations • Solve the within-workstation scheduling problem on all workstations, for all products being assembled on the line • Assign the operations to workstations to achieve the best average balance, while keeping the peak times at a manageable level.
  • 11. Linear Scheduling Method • Linear Scheduling Method (LSM) is a graphical scheduling method focusing on continuous resource utilization in repetitive activities. It is believed that it originally adopted the idea of Line-Of-Balance method. • The main advantages of LSM over Critical Path Method (CPM) is its underlying idea of keeping resources continuously at work. In other words, it schedules activities in such a way that: 1. resource utilization is maximized; 2. interruption in on-going process is minimized, including hiring-and- firing; and 3. the effect of the learning curve phenomenon is minimized
  • 12. BATCH PRODUCTION SCHEDULING • Batch production scheduling is the practice of planning and scheduling of batch manufacturing processes. • Although, scheduling may apply to traditionally continuous processes, such as refining, it is especially important for batch processes such as those for pharmaceutical active ingredients, biotechnology processes and many specialty chemical processes. • Batch production scheduling shares some concepts and techniques with finite capacity scheduling which has been applied to many manufacturing problems. • The specific issues of scheduling batch manufacturing processes have generated considerable industrial and academic interest
  • 13. MRP
  • 15. DISPATCHING • Authorizing the start of an operation on the shop floor is the function of dispatching. • This function may be centralized or decentralized. • The departmental dispatcher would authorize the start of each of the machine operations – the dispatch actions are based on the foreman’s routing and scheduling of the work through his department. This is decentralized dispatching.
  • 16. PROGRESS REPORTING AND EXPEDITING • The manufacturing activity of a plant is said to be “in control” when the actual performance is within the objectives of the planned performance. • When jobs are started and completed on schedule, there should be very little, if any, concern about the meeting of commitments. • Optimum operation of the plant, however, is attained only if the original plan has been carefully prepared to utilize the manufacturing facilities fully and effectively.