SlideShare a Scribd company logo
Procedure for EIA
STEPS IN EIA
• Screening
• Scoping
• Baseline study
• Impact prediction
• Impact assessment
• Mitigation
• Producing the environmental impact
statement
• Public hearing
• Decision making
• Monitoring and implementation of
environmental management plan
• Assessment of Alternatives, Delineation
of Mitigation Measures and
Environmental Impact Assessment
Report
• Risk assessment
Screening
• The EIA process begins from the very start of a
project.
• Once a developer has identified a need and
assessed all the possible alternatives of project
design and sites to select a preferred alternative,
two important questions must be asked:
• 'What will be the effects of this development on
the environment?
• Are those effects significant?'
• If the answer to the second question is 'yes', an
EIA may be required. Answering this question is a
process known as screening and can be an
essential first step into a formal EIA.
• The EIA process is, it must be stressed, iterative.
• This is demonstrated at this early stage of
screening where the requirement for a formal
EIA and its associated cost implications can lead
the developer to reassess the project design
with a view to reducing the significant impacts
to a level where an EIA is not legally required
(Nielsen et al 2005).
Scoping
• Where it is decided that a formal EIA is required,
the next stage is to define the issues that need
to be addressed, that is, those impacts that have
a significant effect on the environment.
• This is known as scoping and is essential for
focusing the available resources on the relevant
issues.
Baseline study
• Following on from scoping, it is essential to
collect all relevant information on the current
status of the environment.
• This study is referred to as a baseline study as
it provides a baseline against which change
due to a development can be measured.
Impact prediction
• Once the baseline study information is
available, the important task of impact
prediction can begin.
• Impact prediction involves forecasting the
likely changes in the environment that will
occur as a result of the development.
Impact assessment
• The next phase involves the assessment of the
identified impacts - impact assessment.
• This requires interpretation of the importance
or significance of the impacts to provide a
conclusion, which can ultimately be used by
decision-makers in determining the fate of the
project application.
Mitigation
• Frequently, the assessment of impacts will
reveal damaging effects upon the environment.
• These may be alleviated
by mitigation measures.
• Mitigation involves taking measures to reduce
or remove environmental impacts and it can be
seen that the iterative nature of the EIA process
is well demonstrated here.
• For example, successful design of mitigation
measures could possibly result in the removal
of all significant impacts
• Hence a new screening exercise would reveal
that there might have been no need to carry
out a formal EIA had the mitigation measures
been included from the start.
The important aspects of EIA are
• risk assessment,
• environmental management and
• post product monitoring.
EIA is to
• serve as a primary environmental tool with clear provisions.
• apply consistently to all proposals with potential environmental impacts.
• use scientific practice and suggest strategies for mitigation.
• address all possible factors such as short term, long term, small scale and
large scale effects.
• consider sustainable aspects such as capacity for assimilation, carrying
capacity, biodiversity protection.
• lay down a flexible approach for public involvement.
• have in built mechanism of follow up and feedback.
• include mechanisms for monitoring, auditing and evaluation.
Environmental Components Of EIA
The EIA process looks into the following
components of the environment.
Air environment
• Quality of ambient air present and predicted.
• Meteorological data: Wind speed, direction,
humidity etc.
• Quantity of emission likely from project.
• Impact of the emission on the area.
• Pollution control desires/air quality standards
Noise
• Levels of noise present and predicted
• Strategies for reducing noise pollution.
Water environment
• Existing ground and surface water resources,
their quality and quantity within the zone.
• Impact of proposed project on water
resources
Biological environment
• Flora and fauna in impact zone.
• Potential damage (likely) due to project, due
to effluents, emissions and landscaping.
• Biological stress (prediction).
Land environment
• Study of soil characteristics, land use, and
drainage pattern, and the likely adverse
impact of the project.
• Impact on historical monuments and heritage
site.
Steps in Preparation of EIA report
• Collection of baseline data from primary and
secondary sources;
• Prediction of impacts based on past experience
and mathematical modelling;
• Evolution of impacts versus evaluation of net cost
benefit;
• Preparation of environmental management
plans to reduce the impacts to the minimum;
• Quantitative estimation of financial cost of
monitoring plan and the mitigation measures
Environment Management Plan
• Delineation of mitigation measures including
prevention and control for each
environmental component and rehabilitation
and resettlement plan.
Environmental Appraisal
• An Appraisal Committee constituted by the
Ministry of Environment and Forests will first
scrutinized a project based on the data
presented by the project authorities.
• If necessary, the MoEF may also hold
consultations with the investors and experts on
specific issues as and when necessary.
• After considering all the facets of a projects,
environmental clearance is accorded subject to
implementation of the stipulated environmental
safeguards.
• In case of projects where the project proponents
have submitted complete information, a decision is
taken within 90 days.
• The six regional offices of the Ministry functioning at
Shillong
 Bhubaneshwar
 Chandigarh
 Bangalore
 Lucknow and Bhopal
undertake monitoring of cleared projects.
EIA of Coasts
• Coastal Zone Management Plans (CZMPs) are
prepared by coastal states or Union Territories
as per rules set by CRZ notification 1991.
• CZMPs are prepared based on identification
and categorization of coastal areas for different
activities and then submitted to the MoEF for
approval.
• The ministry then forms a task force for
examining their plans.
Single window clearance
• Environmental clearance + Forestry clearance.
• When a project requires both environmental clearance as
well as approval under the Forest (Conservation) Act, 1980,
proposals for both are required to be given simultaneously to
the concerned divisions of the Ministry.
• The processing is done simultaneously for clearance or
rejection.
• If the project does not involve diversion of forestland, the
case is processed only for environmental clearance.
The Main Participants Of EIA
EIA applies to public and private sections. The six
main players are:
• Those who propose the project
• The environmental consultant who prepare EIA on
behalf of project proponent.
• Pollution Control Board (State or National).
• Public has the right to express their opinion.
• The Impact Assessment Agency.
• Regional centre of the Ministry of Environment and
Forest.
Benefits of EIA
• EIA links environment with development for
environmentally safe and sustainable development.
• EIA provides a cost effective method to eliminate or
minimize the adverse impact of developmental projects.
• EIA enables the decision makers to analyse the effect of
developmental activities on the environment well before
the developmental project is implemented.
• EIA encourages the adaptation of mitigation strategies in
the developmental plan.
• EIA makes sure that the developmental plan is
environmentally sound and within limits of the capacity of
assimilation and regeneration of the ecosystem.
Shortcomings of Environmental
Impact Assessment
Applicability
• There are several projects with significant
environmental impacts that are exempted
from the notification either because they are
not listed in schedule I, or their investments
are less than what is provided for in the
notification.
Composition of expert committees and standards
• It is being found that the team formed for
conducting EIA studies is lacking the expertise
in various fields such as environmentalists, wild
life experts, Anthropologists and Social
Scientists (to study the social impact of the
project).
Public hearing
• Public comments are not considered at the early
stage, which often leads to conflict at the later stage
of project clearance.
• A number of projects with significant environmental
and social impacts have been excluded from the
mandatory public hearing process.
• The documents which the public are entitled to are
seldom available on time.
• The data collectors do not pay respect to the
indigenous knowledge of local people
Quality of EIA
• One of the biggest concerns with the
environmental clearance process is related to the
quality of EIA report that are being carried out.
• The reports are generally incomplete and provided
with false data.
• Many EIA reports are based on single season data.
• The EIA document in itself is so bulky and technical,
which makes it very difficult to decipher so as to aid
in the decision making process.
Lack of Credibility
• It is the responsibility of the project proponent to
commission the preparation of the EIA for its project.
• The EIA is actually funded by an agency or individual
whose primary interest is to procure clearance for the
project proposed.
• There is little chance that the final assessment
presented is un biased, even if the consultant may
provide an unbiased assessment that is critical of the
proposed project.
• There are so many cases of fraudulent EIA
studies where erroneous data has been used,
same facts used for two totally different places
etc.
• There is no accreditation of EIA consultants,
therefore any such consultant with a track record
of fraudulent cases cannot be held liable for
discrepancies.
• It is hard to imagine any consultant after being
paid lakh of rupees, preparing a report for the
project proponents, indicating that the project is
not viable.
Case Study
• The MoEF constituted the Western Ghats Experts
Ecology Panel (WGEEP) in 2010 under the
Chairmanship of Prof. Madhav Gadgil.
• The Panel submitted its report in 2011 but it was not
made public immediately due to its stringent
assessment of the condition of Western Ghats.
• The report suggested many radical changes that
needs to be brought to conserve Western Ghats.
• The recommendation if implemented would
adversely affect mining mafia, sand mafia and local
encroachers.
• Under pressure from various stakeholders, MoEF
set up the High Level Working Group (HLWG)
under the Chairmanship of Dr. K. Kasturirangan
to study recommendations of WGEEP.
• The HLWG had diluted many recommendations
of WGEEP to satisfy the interests of various
mafia.

More Related Content

What's hot

Environmental Audit
Environmental AuditEnvironmental Audit
Environmental impact assessment
Environmental impact assessmentEnvironmental impact assessment
Environmental impact assessment
Sayyid Ina
 
Environmental Audit
Environmental AuditEnvironmental Audit
Environmental Audit
Dayana Mastura FCCA CA
 
Environment Impact Assessment
Environment Impact Assessment Environment Impact Assessment
Environment Impact Assessment
Istiak Asif
 
Stages of EIA
Stages of EIAStages of EIA
Stages of EIA
Kinza Irshad
 
Eia requirements
Eia requirementsEia requirements
Eia requirements
MOHTISHIM CH
 
Environmental impact assessment and importance of effective application in ba...
Environmental impact assessment and importance of effective application in ba...Environmental impact assessment and importance of effective application in ba...
Environmental impact assessment and importance of effective application in ba...
MdHaque78
 
Unit 7 eia and sd
Unit 7 eia and sd Unit 7 eia and sd
Unit 7 eia and sd Kumar
 
E2.KEY_ELEMENTS_OF_EIA_PROCESS-1
E2.KEY_ELEMENTS_OF_EIA_PROCESS-1E2.KEY_ELEMENTS_OF_EIA_PROCESS-1
E2.KEY_ELEMENTS_OF_EIA_PROCESS-1hirencd
 
Environmental Impact Assessment
Environmental Impact AssessmentEnvironmental Impact Assessment
Environmental Impact Assessment
Prateek Bansal
 
ENVIRONMENT IMPACT ASSESSMENT
ENVIRONMENT IMPACT ASSESSMENTENVIRONMENT IMPACT ASSESSMENT
ENVIRONMENT IMPACT ASSESSMENT
goswamikusum
 
PEISS
PEISSPEISS
PEISS
Mk Blanco
 
EIA Process
EIA ProcessEIA Process
Eia prediction, evaluation & mitigration
Eia prediction, evaluation & mitigrationEia prediction, evaluation & mitigration
Eia prediction, evaluation & mitigration
Mizanur R. Shohel
 
ENVIRONMENTAL IMPACTS ASSESMENT (EIA)
ENVIRONMENTAL  IMPACTS ASSESMENT (EIA)ENVIRONMENTAL  IMPACTS ASSESMENT (EIA)
ENVIRONMENTAL IMPACTS ASSESMENT (EIA)
Lucasrukona
 
Environmental impact assessment 2020
Environmental impact assessment 2020Environmental impact assessment 2020
Environmental impact assessment 2020
Chandrakant Singh
 
Effectiveness of Environmental Impact Assessment (EIA): Bangladesh Perspective
Effectiveness of Environmental Impact Assessment (EIA):  Bangladesh PerspectiveEffectiveness of Environmental Impact Assessment (EIA):  Bangladesh Perspective
Effectiveness of Environmental Impact Assessment (EIA): Bangladesh Perspective
Shahadat Hossain Shakil
 
Ecolabelling
EcolabellingEcolabelling
Ecolabelling
Suja S
 
Environmental Impact Assessment
Environmental Impact AssessmentEnvironmental Impact Assessment
Environmental Impact Assessment
Elly Brent Baldovino
 

What's hot (20)

Environmental Audit
Environmental AuditEnvironmental Audit
Environmental Audit
 
Environmental impact assessment
Environmental impact assessmentEnvironmental impact assessment
Environmental impact assessment
 
Environmental Audit
Environmental AuditEnvironmental Audit
Environmental Audit
 
Environment Impact Assessment
Environment Impact Assessment Environment Impact Assessment
Environment Impact Assessment
 
Stages of EIA
Stages of EIAStages of EIA
Stages of EIA
 
Eia requirements
Eia requirementsEia requirements
Eia requirements
 
Environmental impact assessment and importance of effective application in ba...
Environmental impact assessment and importance of effective application in ba...Environmental impact assessment and importance of effective application in ba...
Environmental impact assessment and importance of effective application in ba...
 
Unit 7 eia and sd
Unit 7 eia and sd Unit 7 eia and sd
Unit 7 eia and sd
 
E2.KEY_ELEMENTS_OF_EIA_PROCESS-1
E2.KEY_ELEMENTS_OF_EIA_PROCESS-1E2.KEY_ELEMENTS_OF_EIA_PROCESS-1
E2.KEY_ELEMENTS_OF_EIA_PROCESS-1
 
Environmental Impact Assessment
Environmental Impact AssessmentEnvironmental Impact Assessment
Environmental Impact Assessment
 
ENVIRONMENT IMPACT ASSESSMENT
ENVIRONMENT IMPACT ASSESSMENTENVIRONMENT IMPACT ASSESSMENT
ENVIRONMENT IMPACT ASSESSMENT
 
PEISS
PEISSPEISS
PEISS
 
EIA Process
EIA ProcessEIA Process
EIA Process
 
Eia prediction, evaluation & mitigration
Eia prediction, evaluation & mitigrationEia prediction, evaluation & mitigration
Eia prediction, evaluation & mitigration
 
ENVIRONMENTAL IMPACTS ASSESMENT (EIA)
ENVIRONMENTAL  IMPACTS ASSESMENT (EIA)ENVIRONMENTAL  IMPACTS ASSESMENT (EIA)
ENVIRONMENTAL IMPACTS ASSESMENT (EIA)
 
Environmental impact assessment 2020
Environmental impact assessment 2020Environmental impact assessment 2020
Environmental impact assessment 2020
 
Evs eia
Evs eiaEvs eia
Evs eia
 
Effectiveness of Environmental Impact Assessment (EIA): Bangladesh Perspective
Effectiveness of Environmental Impact Assessment (EIA):  Bangladesh PerspectiveEffectiveness of Environmental Impact Assessment (EIA):  Bangladesh Perspective
Effectiveness of Environmental Impact Assessment (EIA): Bangladesh Perspective
 
Ecolabelling
EcolabellingEcolabelling
Ecolabelling
 
Environmental Impact Assessment
Environmental Impact AssessmentEnvironmental Impact Assessment
Environmental Impact Assessment
 

Similar to Procedure for EIA.pptx

Environmental impact assessment (EIA)
Environmental impact assessment (EIA)Environmental impact assessment (EIA)
Environmental impact assessment (EIA)
School of planning and architecture
 
NALINI ( topic for M. Sc Ag. Agroforestry assigment EIA and ERA.pptx)
NALINI ( topic for M. Sc Ag. Agroforestry assigment EIA and ERA.pptx)NALINI ( topic for M. Sc Ag. Agroforestry assigment EIA and ERA.pptx)
NALINI ( topic for M. Sc Ag. Agroforestry assigment EIA and ERA.pptx)
HNaliniNirala
 
Ecw 579 week 13
Ecw 579 week 13Ecw 579 week 13
Ecw 579 week 13
Adilah Anuar
 
Environmental impact assessment
Environmental impact assessmentEnvironmental impact assessment
Environmental impact assessment
Nanyang Technological University, Singapore
 
EHS 504 - Environmental Impact Assessment - Lecture 3.ppt
EHS 504  - Environmental Impact Assessment - Lecture 3.pptEHS 504  - Environmental Impact Assessment - Lecture 3.ppt
EHS 504 - Environmental Impact Assessment - Lecture 3.ppt
AbdulmuizzMuktar1
 
Environment impact assessment
Environment impact assessmentEnvironment impact assessment
Environment impact assessment
Vinod Burdak
 
Environmental impact assessment (eia) By Mr Allah Dad Khan Visiting Professor...
Environmental impact assessment (eia) By Mr Allah Dad Khan Visiting Professor...Environmental impact assessment (eia) By Mr Allah Dad Khan Visiting Professor...
Environmental impact assessment (eia) By Mr Allah Dad Khan Visiting Professor...
Mr.Allah Dad Khan
 
Environment impact Assessment (EIA) in Uganda
Environment impact Assessment (EIA) in UgandaEnvironment impact Assessment (EIA) in Uganda
Environment impact Assessment (EIA) in Uganda
kayondo alex
 
Contemporary issues in environmental impact assessment
Contemporary issues in environmental impact assessmentContemporary issues in environmental impact assessment
Contemporary issues in environmental impact assessment
Nasiru Ibrahim Barda
 
Coastal Road Project
Coastal Road ProjectCoastal Road Project
Coastal Road Project
Ekonnect Knowledge Foundation
 
Environmental Impact Assessment
Environmental Impact AssessmentEnvironmental Impact Assessment
Environmental Impact AssessmentPrithvi Ghag
 
Eia sem 40_02
Eia sem 40_02Eia sem 40_02
Eia sem 40_02
prashant vadaliya
 
Environmental impact assessment
Environmental impact assessmentEnvironmental impact assessment
Environmental impact assessment
Kashmeera N.A.
 
manunath1-copy-170405123133 (1).pdf
manunath1-copy-170405123133 (1).pdfmanunath1-copy-170405123133 (1).pdf
manunath1-copy-170405123133 (1).pdf
ChandanLawrence
 
IEE and screening in EIA
IEE and screening in EIAIEE and screening in EIA
IEE and screening in EIA
bishal sapkota
 
environmental impact assessment
environmental impact assessment environmental impact assessment
environmental impact assessment
Pramoda Raj
 
Beige and Brown Aesthetic Group Project Presentation_20230920_011228_0000.pdf
Beige and Brown Aesthetic Group Project Presentation_20230920_011228_0000.pdfBeige and Brown Aesthetic Group Project Presentation_20230920_011228_0000.pdf
Beige and Brown Aesthetic Group Project Presentation_20230920_011228_0000.pdf
HajiraThabasum
 
environmentalimpactassessmenteia-210826024951.pdf
environmentalimpactassessmenteia-210826024951.pdfenvironmentalimpactassessmenteia-210826024951.pdf
environmentalimpactassessmenteia-210826024951.pdf
ssusereef268
 
Environmental impact assessment (eia)
Environmental impact assessment (eia)Environmental impact assessment (eia)
Environmental impact assessment (eia)
SANDEEP PATRE
 

Similar to Procedure for EIA.pptx (20)

Environmental impact assessment (EIA)
Environmental impact assessment (EIA)Environmental impact assessment (EIA)
Environmental impact assessment (EIA)
 
NALINI ( topic for M. Sc Ag. Agroforestry assigment EIA and ERA.pptx)
NALINI ( topic for M. Sc Ag. Agroforestry assigment EIA and ERA.pptx)NALINI ( topic for M. Sc Ag. Agroforestry assigment EIA and ERA.pptx)
NALINI ( topic for M. Sc Ag. Agroforestry assigment EIA and ERA.pptx)
 
Ecw 579 week 13
Ecw 579 week 13Ecw 579 week 13
Ecw 579 week 13
 
Environmental impact assessment
Environmental impact assessmentEnvironmental impact assessment
Environmental impact assessment
 
eia.ppt
eia.ppteia.ppt
eia.ppt
 
EHS 504 - Environmental Impact Assessment - Lecture 3.ppt
EHS 504  - Environmental Impact Assessment - Lecture 3.pptEHS 504  - Environmental Impact Assessment - Lecture 3.ppt
EHS 504 - Environmental Impact Assessment - Lecture 3.ppt
 
Environment impact assessment
Environment impact assessmentEnvironment impact assessment
Environment impact assessment
 
Environmental impact assessment (eia) By Mr Allah Dad Khan Visiting Professor...
Environmental impact assessment (eia) By Mr Allah Dad Khan Visiting Professor...Environmental impact assessment (eia) By Mr Allah Dad Khan Visiting Professor...
Environmental impact assessment (eia) By Mr Allah Dad Khan Visiting Professor...
 
Environment impact Assessment (EIA) in Uganda
Environment impact Assessment (EIA) in UgandaEnvironment impact Assessment (EIA) in Uganda
Environment impact Assessment (EIA) in Uganda
 
Contemporary issues in environmental impact assessment
Contemporary issues in environmental impact assessmentContemporary issues in environmental impact assessment
Contemporary issues in environmental impact assessment
 
Coastal Road Project
Coastal Road ProjectCoastal Road Project
Coastal Road Project
 
Environmental Impact Assessment
Environmental Impact AssessmentEnvironmental Impact Assessment
Environmental Impact Assessment
 
Eia sem 40_02
Eia sem 40_02Eia sem 40_02
Eia sem 40_02
 
Environmental impact assessment
Environmental impact assessmentEnvironmental impact assessment
Environmental impact assessment
 
manunath1-copy-170405123133 (1).pdf
manunath1-copy-170405123133 (1).pdfmanunath1-copy-170405123133 (1).pdf
manunath1-copy-170405123133 (1).pdf
 
IEE and screening in EIA
IEE and screening in EIAIEE and screening in EIA
IEE and screening in EIA
 
environmental impact assessment
environmental impact assessment environmental impact assessment
environmental impact assessment
 
Beige and Brown Aesthetic Group Project Presentation_20230920_011228_0000.pdf
Beige and Brown Aesthetic Group Project Presentation_20230920_011228_0000.pdfBeige and Brown Aesthetic Group Project Presentation_20230920_011228_0000.pdf
Beige and Brown Aesthetic Group Project Presentation_20230920_011228_0000.pdf
 
environmentalimpactassessmenteia-210826024951.pdf
environmentalimpactassessmenteia-210826024951.pdfenvironmentalimpactassessmenteia-210826024951.pdf
environmentalimpactassessmenteia-210826024951.pdf
 
Environmental impact assessment (eia)
Environmental impact assessment (eia)Environmental impact assessment (eia)
Environmental impact assessment (eia)
 

More from thanga2

ACCOUSTICS COMMUNICATION OF NOCTURNAL BIRDS IN SACON CAMPUS.pptx
ACCOUSTICS COMMUNICATION OF NOCTURNAL BIRDS IN SACON CAMPUS.pptxACCOUSTICS COMMUNICATION OF NOCTURNAL BIRDS IN SACON CAMPUS.pptx
ACCOUSTICS COMMUNICATION OF NOCTURNAL BIRDS IN SACON CAMPUS.pptx
thanga2
 
trial.ppt
trial.ppttrial.ppt
trial.ppt
thanga2
 
Impact prediction_class 4.pptx
Impact prediction_class 4.pptxImpact prediction_class 4.pptx
Impact prediction_class 4.pptx
thanga2
 
Procedure for EIA.pptx
Procedure for EIA.pptxProcedure for EIA.pptx
Procedure for EIA.pptx
thanga2
 
THERMAL POLLUTION & POWER PLANTS AND THEIR CONTROL.pptx
THERMAL POLLUTION & POWER PLANTS AND THEIR CONTROL.pptxTHERMAL POLLUTION & POWER PLANTS AND THEIR CONTROL.pptx
THERMAL POLLUTION & POWER PLANTS AND THEIR CONTROL.pptx
thanga2
 
Public Liability Insurance Act 1991.pptx
Public Liability Insurance Act 1991.pptxPublic Liability Insurance Act 1991.pptx
Public Liability Insurance Act 1991.pptx
thanga2
 
water cess act.pptx
water cess act.pptxwater cess act.pptx
water cess act.pptx
thanga2
 
Water Act _class 7.pptx
Water  Act _class 7.pptxWater  Act _class 7.pptx
Water Act _class 7.pptx
thanga2
 
REMOTE SENSING ppt.pptx
REMOTE SENSING ppt.pptxREMOTE SENSING ppt.pptx
REMOTE SENSING ppt.pptx
thanga2
 
Environmental Applications of GIS.pptx
Environmental Applications of GIS.pptxEnvironmental Applications of GIS.pptx
Environmental Applications of GIS.pptx
thanga2
 
VISUAL AND DIGITAL IMAGE PROCESSING.pptx
VISUAL AND DIGITAL IMAGE PROCESSING.pptxVISUAL AND DIGITAL IMAGE PROCESSING.pptx
VISUAL AND DIGITAL IMAGE PROCESSING.pptx
thanga2
 
SENSORS AND SCANNERS.pptx
SENSORS AND SCANNERS.pptxSENSORS AND SCANNERS.pptx
SENSORS AND SCANNERS.pptx
thanga2
 

More from thanga2 (12)

ACCOUSTICS COMMUNICATION OF NOCTURNAL BIRDS IN SACON CAMPUS.pptx
ACCOUSTICS COMMUNICATION OF NOCTURNAL BIRDS IN SACON CAMPUS.pptxACCOUSTICS COMMUNICATION OF NOCTURNAL BIRDS IN SACON CAMPUS.pptx
ACCOUSTICS COMMUNICATION OF NOCTURNAL BIRDS IN SACON CAMPUS.pptx
 
trial.ppt
trial.ppttrial.ppt
trial.ppt
 
Impact prediction_class 4.pptx
Impact prediction_class 4.pptxImpact prediction_class 4.pptx
Impact prediction_class 4.pptx
 
Procedure for EIA.pptx
Procedure for EIA.pptxProcedure for EIA.pptx
Procedure for EIA.pptx
 
THERMAL POLLUTION & POWER PLANTS AND THEIR CONTROL.pptx
THERMAL POLLUTION & POWER PLANTS AND THEIR CONTROL.pptxTHERMAL POLLUTION & POWER PLANTS AND THEIR CONTROL.pptx
THERMAL POLLUTION & POWER PLANTS AND THEIR CONTROL.pptx
 
Public Liability Insurance Act 1991.pptx
Public Liability Insurance Act 1991.pptxPublic Liability Insurance Act 1991.pptx
Public Liability Insurance Act 1991.pptx
 
water cess act.pptx
water cess act.pptxwater cess act.pptx
water cess act.pptx
 
Water Act _class 7.pptx
Water  Act _class 7.pptxWater  Act _class 7.pptx
Water Act _class 7.pptx
 
REMOTE SENSING ppt.pptx
REMOTE SENSING ppt.pptxREMOTE SENSING ppt.pptx
REMOTE SENSING ppt.pptx
 
Environmental Applications of GIS.pptx
Environmental Applications of GIS.pptxEnvironmental Applications of GIS.pptx
Environmental Applications of GIS.pptx
 
VISUAL AND DIGITAL IMAGE PROCESSING.pptx
VISUAL AND DIGITAL IMAGE PROCESSING.pptxVISUAL AND DIGITAL IMAGE PROCESSING.pptx
VISUAL AND DIGITAL IMAGE PROCESSING.pptx
 
SENSORS AND SCANNERS.pptx
SENSORS AND SCANNERS.pptxSENSORS AND SCANNERS.pptx
SENSORS AND SCANNERS.pptx
 

Recently uploaded

Summary of the Climate and Energy Policy of Australia
Summary of the Climate and Energy Policy of AustraliaSummary of the Climate and Energy Policy of Australia
Summary of the Climate and Energy Policy of Australia
yasmindemoraes1
 
Bhopal Gas Leak Tragedy - A Night of death
Bhopal Gas Leak Tragedy - A Night of deathBhopal Gas Leak Tragedy - A Night of death
Bhopal Gas Leak Tragedy - A Night of death
upasana742003
 
Artificial Reefs by Kuddle Life Foundation - May 2024
Artificial Reefs by Kuddle Life Foundation - May 2024Artificial Reefs by Kuddle Life Foundation - May 2024
Artificial Reefs by Kuddle Life Foundation - May 2024
punit537210
 
UNDERSTANDING WHAT GREEN WASHING IS!.pdf
UNDERSTANDING WHAT GREEN WASHING IS!.pdfUNDERSTANDING WHAT GREEN WASHING IS!.pdf
UNDERSTANDING WHAT GREEN WASHING IS!.pdf
JulietMogola
 
Environmental Science Book By Dr. Y.K. Singh
Environmental Science Book By Dr. Y.K. SinghEnvironmental Science Book By Dr. Y.K. Singh
Environmental Science Book By Dr. Y.K. Singh
AhmadKhan917612
 
Natural farming @ Dr. Siddhartha S. Jena.pptx
Natural farming @ Dr. Siddhartha S. Jena.pptxNatural farming @ Dr. Siddhartha S. Jena.pptx
Natural farming @ Dr. Siddhartha S. Jena.pptx
sidjena70
 
NRW Board Paper - DRAFT NRW Recreation Strategy
NRW Board Paper - DRAFT NRW Recreation StrategyNRW Board Paper - DRAFT NRW Recreation Strategy
NRW Board Paper - DRAFT NRW Recreation Strategy
Robin Grant
 
ppt on beauty of the nature by Palak.pptx
ppt on  beauty of the nature by Palak.pptxppt on  beauty of the nature by Palak.pptx
ppt on beauty of the nature by Palak.pptx
RaniJaiswal16
 
Willie Nelson Net Worth: A Journey Through Music, Movies, and Business Ventures
Willie Nelson Net Worth: A Journey Through Music, Movies, and Business VenturesWillie Nelson Net Worth: A Journey Through Music, Movies, and Business Ventures
Willie Nelson Net Worth: A Journey Through Music, Movies, and Business Ventures
greendigital
 
Celebrating World-environment-day-2024.pdf
Celebrating  World-environment-day-2024.pdfCelebrating  World-environment-day-2024.pdf
Celebrating World-environment-day-2024.pdf
rohankumarsinghrore1
 
AGRICULTURE Hydrophonic FERTILISER PPT.pptx
AGRICULTURE Hydrophonic FERTILISER PPT.pptxAGRICULTURE Hydrophonic FERTILISER PPT.pptx
AGRICULTURE Hydrophonic FERTILISER PPT.pptx
BanitaDsouza
 
"Understanding the Carbon Cycle: Processes, Human Impacts, and Strategies for...
"Understanding the Carbon Cycle: Processes, Human Impacts, and Strategies for..."Understanding the Carbon Cycle: Processes, Human Impacts, and Strategies for...
"Understanding the Carbon Cycle: Processes, Human Impacts, and Strategies for...
MMariSelvam4
 
Characterization and the Kinetics of drying at the drying oven and with micro...
Characterization and the Kinetics of drying at the drying oven and with micro...Characterization and the Kinetics of drying at the drying oven and with micro...
Characterization and the Kinetics of drying at the drying oven and with micro...
Open Access Research Paper
 
Micro RNA genes and their likely influence in rice (Oryza sativa L.) dynamic ...
Micro RNA genes and their likely influence in rice (Oryza sativa L.) dynamic ...Micro RNA genes and their likely influence in rice (Oryza sativa L.) dynamic ...
Micro RNA genes and their likely influence in rice (Oryza sativa L.) dynamic ...
Open Access Research Paper
 
Presentación Giulio Quaggiotto-Diálogo improbable .pptx.pdf
Presentación Giulio Quaggiotto-Diálogo improbable .pptx.pdfPresentación Giulio Quaggiotto-Diálogo improbable .pptx.pdf
Presentación Giulio Quaggiotto-Diálogo improbable .pptx.pdf
Innovation and Technology for Development Centre
 
Q&A with the Experts: The Food Service Playbook
Q&A with the Experts: The Food Service PlaybookQ&A with the Experts: The Food Service Playbook
Q&A with the Experts: The Food Service Playbook
World Resources Institute (WRI)
 
International+e-Commerce+Platform-www.cfye-commerce.shop
International+e-Commerce+Platform-www.cfye-commerce.shopInternational+e-Commerce+Platform-www.cfye-commerce.shop
International+e-Commerce+Platform-www.cfye-commerce.shop
laozhuseo02
 
Daan Park Hydrangea flower season I like it
Daan Park Hydrangea flower season I like itDaan Park Hydrangea flower season I like it
Daan Park Hydrangea flower season I like it
a0966109726
 
Alert-driven Community-based Forest monitoring: A case of the Peruvian Amazon
Alert-driven Community-based Forest monitoring: A case of the Peruvian AmazonAlert-driven Community-based Forest monitoring: A case of the Peruvian Amazon
Alert-driven Community-based Forest monitoring: A case of the Peruvian Amazon
CIFOR-ICRAF
 
IPCC Vice Chair Ladislaus Change Central Asia Climate Change Conference 27 Ma...
IPCC Vice Chair Ladislaus Change Central Asia Climate Change Conference 27 Ma...IPCC Vice Chair Ladislaus Change Central Asia Climate Change Conference 27 Ma...
IPCC Vice Chair Ladislaus Change Central Asia Climate Change Conference 27 Ma...
ipcc-media
 

Recently uploaded (20)

Summary of the Climate and Energy Policy of Australia
Summary of the Climate and Energy Policy of AustraliaSummary of the Climate and Energy Policy of Australia
Summary of the Climate and Energy Policy of Australia
 
Bhopal Gas Leak Tragedy - A Night of death
Bhopal Gas Leak Tragedy - A Night of deathBhopal Gas Leak Tragedy - A Night of death
Bhopal Gas Leak Tragedy - A Night of death
 
Artificial Reefs by Kuddle Life Foundation - May 2024
Artificial Reefs by Kuddle Life Foundation - May 2024Artificial Reefs by Kuddle Life Foundation - May 2024
Artificial Reefs by Kuddle Life Foundation - May 2024
 
UNDERSTANDING WHAT GREEN WASHING IS!.pdf
UNDERSTANDING WHAT GREEN WASHING IS!.pdfUNDERSTANDING WHAT GREEN WASHING IS!.pdf
UNDERSTANDING WHAT GREEN WASHING IS!.pdf
 
Environmental Science Book By Dr. Y.K. Singh
Environmental Science Book By Dr. Y.K. SinghEnvironmental Science Book By Dr. Y.K. Singh
Environmental Science Book By Dr. Y.K. Singh
 
Natural farming @ Dr. Siddhartha S. Jena.pptx
Natural farming @ Dr. Siddhartha S. Jena.pptxNatural farming @ Dr. Siddhartha S. Jena.pptx
Natural farming @ Dr. Siddhartha S. Jena.pptx
 
NRW Board Paper - DRAFT NRW Recreation Strategy
NRW Board Paper - DRAFT NRW Recreation StrategyNRW Board Paper - DRAFT NRW Recreation Strategy
NRW Board Paper - DRAFT NRW Recreation Strategy
 
ppt on beauty of the nature by Palak.pptx
ppt on  beauty of the nature by Palak.pptxppt on  beauty of the nature by Palak.pptx
ppt on beauty of the nature by Palak.pptx
 
Willie Nelson Net Worth: A Journey Through Music, Movies, and Business Ventures
Willie Nelson Net Worth: A Journey Through Music, Movies, and Business VenturesWillie Nelson Net Worth: A Journey Through Music, Movies, and Business Ventures
Willie Nelson Net Worth: A Journey Through Music, Movies, and Business Ventures
 
Celebrating World-environment-day-2024.pdf
Celebrating  World-environment-day-2024.pdfCelebrating  World-environment-day-2024.pdf
Celebrating World-environment-day-2024.pdf
 
AGRICULTURE Hydrophonic FERTILISER PPT.pptx
AGRICULTURE Hydrophonic FERTILISER PPT.pptxAGRICULTURE Hydrophonic FERTILISER PPT.pptx
AGRICULTURE Hydrophonic FERTILISER PPT.pptx
 
"Understanding the Carbon Cycle: Processes, Human Impacts, and Strategies for...
"Understanding the Carbon Cycle: Processes, Human Impacts, and Strategies for..."Understanding the Carbon Cycle: Processes, Human Impacts, and Strategies for...
"Understanding the Carbon Cycle: Processes, Human Impacts, and Strategies for...
 
Characterization and the Kinetics of drying at the drying oven and with micro...
Characterization and the Kinetics of drying at the drying oven and with micro...Characterization and the Kinetics of drying at the drying oven and with micro...
Characterization and the Kinetics of drying at the drying oven and with micro...
 
Micro RNA genes and their likely influence in rice (Oryza sativa L.) dynamic ...
Micro RNA genes and their likely influence in rice (Oryza sativa L.) dynamic ...Micro RNA genes and their likely influence in rice (Oryza sativa L.) dynamic ...
Micro RNA genes and their likely influence in rice (Oryza sativa L.) dynamic ...
 
Presentación Giulio Quaggiotto-Diálogo improbable .pptx.pdf
Presentación Giulio Quaggiotto-Diálogo improbable .pptx.pdfPresentación Giulio Quaggiotto-Diálogo improbable .pptx.pdf
Presentación Giulio Quaggiotto-Diálogo improbable .pptx.pdf
 
Q&A with the Experts: The Food Service Playbook
Q&A with the Experts: The Food Service PlaybookQ&A with the Experts: The Food Service Playbook
Q&A with the Experts: The Food Service Playbook
 
International+e-Commerce+Platform-www.cfye-commerce.shop
International+e-Commerce+Platform-www.cfye-commerce.shopInternational+e-Commerce+Platform-www.cfye-commerce.shop
International+e-Commerce+Platform-www.cfye-commerce.shop
 
Daan Park Hydrangea flower season I like it
Daan Park Hydrangea flower season I like itDaan Park Hydrangea flower season I like it
Daan Park Hydrangea flower season I like it
 
Alert-driven Community-based Forest monitoring: A case of the Peruvian Amazon
Alert-driven Community-based Forest monitoring: A case of the Peruvian AmazonAlert-driven Community-based Forest monitoring: A case of the Peruvian Amazon
Alert-driven Community-based Forest monitoring: A case of the Peruvian Amazon
 
IPCC Vice Chair Ladislaus Change Central Asia Climate Change Conference 27 Ma...
IPCC Vice Chair Ladislaus Change Central Asia Climate Change Conference 27 Ma...IPCC Vice Chair Ladislaus Change Central Asia Climate Change Conference 27 Ma...
IPCC Vice Chair Ladislaus Change Central Asia Climate Change Conference 27 Ma...
 

Procedure for EIA.pptx

  • 2. STEPS IN EIA • Screening • Scoping • Baseline study • Impact prediction • Impact assessment • Mitigation • Producing the environmental impact statement
  • 3. • Public hearing • Decision making • Monitoring and implementation of environmental management plan • Assessment of Alternatives, Delineation of Mitigation Measures and Environmental Impact Assessment Report • Risk assessment
  • 4. Screening • The EIA process begins from the very start of a project. • Once a developer has identified a need and assessed all the possible alternatives of project design and sites to select a preferred alternative, two important questions must be asked: • 'What will be the effects of this development on the environment? • Are those effects significant?' • If the answer to the second question is 'yes', an EIA may be required. Answering this question is a process known as screening and can be an essential first step into a formal EIA.
  • 5. • The EIA process is, it must be stressed, iterative. • This is demonstrated at this early stage of screening where the requirement for a formal EIA and its associated cost implications can lead the developer to reassess the project design with a view to reducing the significant impacts to a level where an EIA is not legally required (Nielsen et al 2005).
  • 6. Scoping • Where it is decided that a formal EIA is required, the next stage is to define the issues that need to be addressed, that is, those impacts that have a significant effect on the environment. • This is known as scoping and is essential for focusing the available resources on the relevant issues.
  • 7. Baseline study • Following on from scoping, it is essential to collect all relevant information on the current status of the environment. • This study is referred to as a baseline study as it provides a baseline against which change due to a development can be measured.
  • 8. Impact prediction • Once the baseline study information is available, the important task of impact prediction can begin. • Impact prediction involves forecasting the likely changes in the environment that will occur as a result of the development.
  • 9. Impact assessment • The next phase involves the assessment of the identified impacts - impact assessment. • This requires interpretation of the importance or significance of the impacts to provide a conclusion, which can ultimately be used by decision-makers in determining the fate of the project application.
  • 10. Mitigation • Frequently, the assessment of impacts will reveal damaging effects upon the environment. • These may be alleviated by mitigation measures. • Mitigation involves taking measures to reduce or remove environmental impacts and it can be seen that the iterative nature of the EIA process is well demonstrated here.
  • 11. • For example, successful design of mitigation measures could possibly result in the removal of all significant impacts • Hence a new screening exercise would reveal that there might have been no need to carry out a formal EIA had the mitigation measures been included from the start.
  • 12. The important aspects of EIA are • risk assessment, • environmental management and • post product monitoring.
  • 13. EIA is to • serve as a primary environmental tool with clear provisions. • apply consistently to all proposals with potential environmental impacts. • use scientific practice and suggest strategies for mitigation. • address all possible factors such as short term, long term, small scale and large scale effects. • consider sustainable aspects such as capacity for assimilation, carrying capacity, biodiversity protection. • lay down a flexible approach for public involvement. • have in built mechanism of follow up and feedback. • include mechanisms for monitoring, auditing and evaluation.
  • 14. Environmental Components Of EIA The EIA process looks into the following components of the environment. Air environment • Quality of ambient air present and predicted. • Meteorological data: Wind speed, direction, humidity etc. • Quantity of emission likely from project. • Impact of the emission on the area. • Pollution control desires/air quality standards
  • 15. Noise • Levels of noise present and predicted • Strategies for reducing noise pollution.
  • 16. Water environment • Existing ground and surface water resources, their quality and quantity within the zone. • Impact of proposed project on water resources
  • 17. Biological environment • Flora and fauna in impact zone. • Potential damage (likely) due to project, due to effluents, emissions and landscaping. • Biological stress (prediction).
  • 18. Land environment • Study of soil characteristics, land use, and drainage pattern, and the likely adverse impact of the project. • Impact on historical monuments and heritage site.
  • 19. Steps in Preparation of EIA report • Collection of baseline data from primary and secondary sources; • Prediction of impacts based on past experience and mathematical modelling; • Evolution of impacts versus evaluation of net cost benefit; • Preparation of environmental management plans to reduce the impacts to the minimum; • Quantitative estimation of financial cost of monitoring plan and the mitigation measures
  • 20. Environment Management Plan • Delineation of mitigation measures including prevention and control for each environmental component and rehabilitation and resettlement plan.
  • 21. Environmental Appraisal • An Appraisal Committee constituted by the Ministry of Environment and Forests will first scrutinized a project based on the data presented by the project authorities. • If necessary, the MoEF may also hold consultations with the investors and experts on specific issues as and when necessary. • After considering all the facets of a projects, environmental clearance is accorded subject to implementation of the stipulated environmental safeguards.
  • 22. • In case of projects where the project proponents have submitted complete information, a decision is taken within 90 days. • The six regional offices of the Ministry functioning at Shillong  Bhubaneshwar  Chandigarh  Bangalore  Lucknow and Bhopal undertake monitoring of cleared projects.
  • 23. EIA of Coasts • Coastal Zone Management Plans (CZMPs) are prepared by coastal states or Union Territories as per rules set by CRZ notification 1991. • CZMPs are prepared based on identification and categorization of coastal areas for different activities and then submitted to the MoEF for approval. • The ministry then forms a task force for examining their plans.
  • 24. Single window clearance • Environmental clearance + Forestry clearance. • When a project requires both environmental clearance as well as approval under the Forest (Conservation) Act, 1980, proposals for both are required to be given simultaneously to the concerned divisions of the Ministry. • The processing is done simultaneously for clearance or rejection. • If the project does not involve diversion of forestland, the case is processed only for environmental clearance.
  • 25. The Main Participants Of EIA EIA applies to public and private sections. The six main players are: • Those who propose the project • The environmental consultant who prepare EIA on behalf of project proponent. • Pollution Control Board (State or National). • Public has the right to express their opinion. • The Impact Assessment Agency. • Regional centre of the Ministry of Environment and Forest.
  • 26. Benefits of EIA • EIA links environment with development for environmentally safe and sustainable development. • EIA provides a cost effective method to eliminate or minimize the adverse impact of developmental projects. • EIA enables the decision makers to analyse the effect of developmental activities on the environment well before the developmental project is implemented. • EIA encourages the adaptation of mitigation strategies in the developmental plan. • EIA makes sure that the developmental plan is environmentally sound and within limits of the capacity of assimilation and regeneration of the ecosystem.
  • 27. Shortcomings of Environmental Impact Assessment Applicability • There are several projects with significant environmental impacts that are exempted from the notification either because they are not listed in schedule I, or their investments are less than what is provided for in the notification.
  • 28. Composition of expert committees and standards • It is being found that the team formed for conducting EIA studies is lacking the expertise in various fields such as environmentalists, wild life experts, Anthropologists and Social Scientists (to study the social impact of the project).
  • 29. Public hearing • Public comments are not considered at the early stage, which often leads to conflict at the later stage of project clearance. • A number of projects with significant environmental and social impacts have been excluded from the mandatory public hearing process. • The documents which the public are entitled to are seldom available on time. • The data collectors do not pay respect to the indigenous knowledge of local people
  • 30. Quality of EIA • One of the biggest concerns with the environmental clearance process is related to the quality of EIA report that are being carried out. • The reports are generally incomplete and provided with false data. • Many EIA reports are based on single season data. • The EIA document in itself is so bulky and technical, which makes it very difficult to decipher so as to aid in the decision making process.
  • 31. Lack of Credibility • It is the responsibility of the project proponent to commission the preparation of the EIA for its project. • The EIA is actually funded by an agency or individual whose primary interest is to procure clearance for the project proposed. • There is little chance that the final assessment presented is un biased, even if the consultant may provide an unbiased assessment that is critical of the proposed project.
  • 32. • There are so many cases of fraudulent EIA studies where erroneous data has been used, same facts used for two totally different places etc. • There is no accreditation of EIA consultants, therefore any such consultant with a track record of fraudulent cases cannot be held liable for discrepancies. • It is hard to imagine any consultant after being paid lakh of rupees, preparing a report for the project proponents, indicating that the project is not viable.
  • 33. Case Study • The MoEF constituted the Western Ghats Experts Ecology Panel (WGEEP) in 2010 under the Chairmanship of Prof. Madhav Gadgil. • The Panel submitted its report in 2011 but it was not made public immediately due to its stringent assessment of the condition of Western Ghats. • The report suggested many radical changes that needs to be brought to conserve Western Ghats. • The recommendation if implemented would adversely affect mining mafia, sand mafia and local encroachers.
  • 34. • Under pressure from various stakeholders, MoEF set up the High Level Working Group (HLWG) under the Chairmanship of Dr. K. Kasturirangan to study recommendations of WGEEP. • The HLWG had diluted many recommendations of WGEEP to satisfy the interests of various mafia.