SlideShare a Scribd company logo
“BURJ AL ARAB”
THE TOWER OF ARABS
PRESENTED BY
P.V.MANEKAR
TECHNICAL DETAILS
 Concrete on the island: 33,000 sq m
 Concrete in the superstructure: 36,000 sq m
 Total tonnage of steel: 9000 tones
 Gross area of building: 120,000 sq m
 Glass: 43,446 sq m
 Marbles: 24,000 sq m
 202 duplex suites
 Ranges from 170 sq m to 780 sq m
 Floor count: 18
 Elevator count 16
CONSTRUCTION
 Construction was began in 1994 and completed in october1999.
 Chief architect: Tom Wright
 Chief structural engineer: Anthony McCarter
 Contractor: Al Habtoor Engineering, Fletcher construction, Murray
& Roberts
 Steel contractor: Eversendai Engineering
 Owner: Sheikh Mohammed bin Rashid al Maktoom
 Construction cost: $650 million
ARTIFICIAL ISLAND
 It took three years to reclaim the land from the sea, and less
than three years to construct the building.
 As there is only sand to hold the building up the column rely
on friction.
 Distance of shore to the outer point of island: 450m
 Size of island: 150m per side
 Sea depth: 7.5m
 No. of piles: 230
 Size of piles: 1.5m
 Length of piles: 45m
 Temporary tube piles driven into sea bed
 Temporary sheet piles and tie rods driven into sea bed to support
boundary rocks (see figure 1)
 Permanent boundary rock bunds deposited either side of sheet
piles
 Hydraulic fill layers deposited between bunds to displace sea
water and form island (see figure 2 with fill layers partially
complete)
 Permanent concrete armour units placed around island to
protect it from the waves
 2m diameter 43m deep piles driven through island and sea bed
below to stabilize structure (see figure 3)
 Island interior excavated and temporary sheet pile coffer dam
inserted
 2m thick concrete plug slab laid at base of island
 Reinforced concrete retaining wall built
 Basement floors created (see figure 4)
CONCRETE ARMOUR UNITS
ATRIUM WALL
 Constructed from 2 skins of Teflon
coated fiber glass separated by air
gap of 500mm.
 The largest Teflon coated fiber
fabric wall is used to cover the
atrium.
 This is first time such technology
has been used vertically.
 It resembles a huge sail.
 The tallest 182m atrium in the
world.
EXOSKELETON LEG ERECTION
 Made of two build up H section 1.8 x 4.5m deep plate girders.
 Creates a gentle curve concurrence with building edge
developing the shape of a sail.
 Alignment was carried out using total station located at three
different fixed locations.
BRACE FRAME
 ‘X’ Shape rear bracings are cross
bracings of fabricated box sections.
 Boxes are 2.2m x 1.4m and made
from 25mm to 40 mm thick plates.
 They tie two cores of the building to
give stability to the structure.
 The length of one brace was around
60m in one direction.
TRUSSES
 Hugh tubular triangular truss.
 Vary from 76m to 90m and
weight 160 to 180 tons.
 There are six trusses to resists
lateral loads and reduce
moment & deflection.
 Connects with 300mm diameter pin to the core wall and rear leg.
 To solve the problem of expansion and contraction which can
change 5cm in a day, special steering linkage rod was designed.
TRUSSES
HORIZONTALS
 Weight is 200 tons connects the core wall to exoskeleton rear leg.
 Assembled in one piece in assembly yard near the site.
 Erected by strand jacking method similar to diagonals
HELIPAD STRUCTURE
 This structure is at 212m level front side of building, weights about
330 tons.
 Two props of 1m diameter circular steel pipes forming an inverted
V shape.
 Tapered at 30º to the vertical and tied back to center core by 40m
long spine truss weighing 120 tons.
SKY RESTAURENT STRUCTURE
 Most complex and potentially dangerous structure.
 It is located 200m above the persian gulf.
 It is built on 30m long 8 box girder cantilevers from the main core
wall radiates as support and are not visible.
 Floor size of 70mx25m.
 Entire structure is enclosed in aluminuim and glass.
MAST
 This is 104 meter long.
 Oval shape of 2.5m x 5m and gradually
decreases to 2.5 x 2m at top.
 Segments has inside arrangements
of permanent ladders and interval
platforms to facilitate access.
 Manholes at periodic intervals through
which workers have access.
WIND EFFECTS
 Vibration may cause due to vortex shedding.
 11 invisible hanging weight called the tune mass dampers at
vulnerable points inside the exoskeleton.
 The shape of burj Al Arab lowers wind forces more effectively
because of the streamlined V and curved fabric atrium wall.
WIND EFFECTS
SEISMIC IMPACT
 Dubai is not in earthquake resisting zone.
 However, burj al arab is design to resist
earthquake of MM VII intensity.
 Tune mass dampers also helps to resist the
effect of earthquake.
 Seismic zone factor of 0.20g is considered
for the detailed design phase.
CONCLUSION
 Burj Al Arab, is currently recognized as one of spectacular
structure in the history of structural engineering.
 Problems like high concentration of chloride in the air and
extreme temperature, wind effect and potential seismic events
have to be taken into account in the detailed design phase.
 The Burj Al Arab hotel project, which is uniquely complex yet
rewarding, marks the advancement in structural engineering
technology.
THANK YOU !

More Related Content

What's hot

Burj khalifa-mode of construction
Burj khalifa-mode of constructionBurj khalifa-mode of construction
Burj khalifa-mode of constructionJoji Mathew
 
Burj Al Arab, Tower Of The Arabs
Burj Al Arab, Tower Of The ArabsBurj Al Arab, Tower Of The Arabs
Burj Al Arab, Tower Of The ArabsLaura Domínguez
 
Dubai burj al-arab hotel2 copy
Dubai burj al-arab hotel2 copyDubai burj al-arab hotel2 copy
Dubai burj al-arab hotel2 copyChyi Ong
 
High-rise structural systems
High-rise structural systemsHigh-rise structural systems
High-rise structural systemsAkshay Revekar
 
Petronas tower - Malaysia (Theory of Structures)
Petronas tower - Malaysia  (Theory of Structures)Petronas tower - Malaysia  (Theory of Structures)
Petronas tower - Malaysia (Theory of Structures)RADHIKASARDA8
 
Petronas twin tower
Petronas twin towerPetronas twin tower
Petronas twin towerSomya Gupta
 
Bundled Tube Structural System
 Bundled Tube Structural System Bundled Tube Structural System
Bundled Tube Structural SystemUmer Farooq
 
Burj al arab hotel case study
Burj al arab hotel case study Burj al arab hotel case study
Burj al arab hotel case study Anas Khan
 
Burj Khalifa - Design & construction technologies
Burj Khalifa - Design & construction technologiesBurj Khalifa - Design & construction technologies
Burj Khalifa - Design & construction technologiesAkshey Sharma
 

What's hot (20)

Burj Al Arab
Burj Al ArabBurj Al Arab
Burj Al Arab
 
Burj al arab-uae
Burj al arab-uaeBurj al arab-uae
Burj al arab-uae
 
Capital gate abu dhabi
Capital gate abu dhabiCapital gate abu dhabi
Capital gate abu dhabi
 
Burj khalifa Dubai
Burj khalifa DubaiBurj khalifa Dubai
Burj khalifa Dubai
 
Burj khalifa-mode of construction
Burj khalifa-mode of constructionBurj khalifa-mode of construction
Burj khalifa-mode of construction
 
Burj Al Arab, Tower Of The Arabs
Burj Al Arab, Tower Of The ArabsBurj Al Arab, Tower Of The Arabs
Burj Al Arab, Tower Of The Arabs
 
Dubai burj al-arab hotel2 copy
Dubai burj al-arab hotel2 copyDubai burj al-arab hotel2 copy
Dubai burj al-arab hotel2 copy
 
Burj khalifa
Burj khalifaBurj khalifa
Burj khalifa
 
Burj Khalifa
Burj KhalifaBurj Khalifa
Burj Khalifa
 
Pm burj case
Pm burj casePm burj case
Pm burj case
 
Burj al-arab
Burj al-arabBurj al-arab
Burj al-arab
 
High-rise structural systems
High-rise structural systemsHigh-rise structural systems
High-rise structural systems
 
Petronas tower - Malaysia (Theory of Structures)
Petronas tower - Malaysia  (Theory of Structures)Petronas tower - Malaysia  (Theory of Structures)
Petronas tower - Malaysia (Theory of Structures)
 
Petronas twin tower
Petronas twin towerPetronas twin tower
Petronas twin tower
 
Bundled Tube Structural System
 Bundled Tube Structural System Bundled Tube Structural System
Bundled Tube Structural System
 
Burj-al-arab
Burj-al-arabBurj-al-arab
Burj-al-arab
 
Empire state building
Empire state buildingEmpire state building
Empire state building
 
Burj al arab hotel case study
Burj al arab hotel case study Burj al arab hotel case study
Burj al arab hotel case study
 
Burj Khalifa - Design & construction technologies
Burj Khalifa - Design & construction technologiesBurj Khalifa - Design & construction technologies
Burj Khalifa - Design & construction technologies
 
Burj khalifa
Burj khalifaBurj khalifa
Burj khalifa
 

Similar to PPT ON BURJ AL ARAB

Burj al arab (Cofferdam&Rigging)
Burj al arab (Cofferdam&Rigging)Burj al arab (Cofferdam&Rigging)
Burj al arab (Cofferdam&Rigging)Sunny Mahajan
 
Busan geoje fixed link
Busan   geoje fixed linkBusan   geoje fixed link
Busan geoje fixed linkVicky Matwan
 
BURJ AL ARAB Presentation on Structural System
BURJ AL ARAB Presentation on Structural SystemBURJ AL ARAB Presentation on Structural System
BURJ AL ARAB Presentation on Structural SystemABDURRAB ANSARI
 
CAPITAL GATE, ABU DHABI
CAPITAL GATE, ABU DHABICAPITAL GATE, ABU DHABI
CAPITAL GATE, ABU DHABISelf employed
 
ANSHU PPT NARDEY SIR.pptx
ANSHU PPT NARDEY SIR.pptxANSHU PPT NARDEY SIR.pptx
ANSHU PPT NARDEY SIR.pptxAnshuBarmase
 
BHUSAN GEOJE FIXED LINK presentation
BHUSAN GEOJE FIXED LINK presentationBHUSAN GEOJE FIXED LINK presentation
BHUSAN GEOJE FIXED LINK presentationAmir Amdani
 
Burj al-arab
Burj al-arabBurj al-arab
Burj al-arabmilyas143
 
foundation and structural system of the shard building
foundation and structural system  of the shard buildingfoundation and structural system  of the shard building
foundation and structural system of the shard buildingBirukYared3
 
Glass fibre reinforced gypsum panels
Glass fibre reinforced gypsum panelsGlass fibre reinforced gypsum panels
Glass fibre reinforced gypsum panelsRavi Shankar
 
Soldier Bored and Diaphragm
Soldier Bored and DiaphragmSoldier Bored and Diaphragm
Soldier Bored and DiaphragmYingHongKang
 
Integrating Geothermal Loops into the Diaphragm walls of the Knightsbridge Pa...
Integrating Geothermal Loops into the Diaphragm walls of the Knightsbridge Pa...Integrating Geothermal Loops into the Diaphragm walls of the Knightsbridge Pa...
Integrating Geothermal Loops into the Diaphragm walls of the Knightsbridge Pa...Tonyamis
 
Aldar Headquarters Dubai
Aldar Headquarters DubaiAldar Headquarters Dubai
Aldar Headquarters DubaiNeha Rampuria
 

Similar to PPT ON BURJ AL ARAB (20)

Burj al arab (Cofferdam&Rigging)
Burj al arab (Cofferdam&Rigging)Burj al arab (Cofferdam&Rigging)
Burj al arab (Cofferdam&Rigging)
 
BurjAlArab.pdf
BurjAlArab.pdfBurjAlArab.pdf
BurjAlArab.pdf
 
Busan geoje fixed link
Busan   geoje fixed linkBusan   geoje fixed link
Busan geoje fixed link
 
BURJ AL ARAB Presentation on Structural System
BURJ AL ARAB Presentation on Structural SystemBURJ AL ARAB Presentation on Structural System
BURJ AL ARAB Presentation on Structural System
 
Al dar hq
Al dar hqAl dar hq
Al dar hq
 
CAPITAL GATE, ABU DHABI
CAPITAL GATE, ABU DHABICAPITAL GATE, ABU DHABI
CAPITAL GATE, ABU DHABI
 
burj khalifa
burj khalifaburj khalifa
burj khalifa
 
ANSHU PPT NARDEY SIR.pptx
ANSHU PPT NARDEY SIR.pptxANSHU PPT NARDEY SIR.pptx
ANSHU PPT NARDEY SIR.pptx
 
BHUSAN GEOJE FIXED LINK presentation
BHUSAN GEOJE FIXED LINK presentationBHUSAN GEOJE FIXED LINK presentation
BHUSAN GEOJE FIXED LINK presentation
 
Burj al-arab
Burj al-arabBurj al-arab
Burj al-arab
 
foundation and structural system of the shard building
foundation and structural system  of the shard buildingfoundation and structural system  of the shard building
foundation and structural system of the shard building
 
Diaphragm wall construction
Diaphragm wall constructionDiaphragm wall construction
Diaphragm wall construction
 
Glass fibre reinforced gypsum panels
Glass fibre reinforced gypsum panelsGlass fibre reinforced gypsum panels
Glass fibre reinforced gypsum panels
 
Busan Geoje
Busan GeojeBusan Geoje
Busan Geoje
 
Soldier Bored and Diaphragm
Soldier Bored and DiaphragmSoldier Bored and Diaphragm
Soldier Bored and Diaphragm
 
Project Taipei 101
Project Taipei 101Project Taipei 101
Project Taipei 101
 
Integrating Geothermal Loops into the Diaphragm walls of the Knightsbridge Pa...
Integrating Geothermal Loops into the Diaphragm walls of the Knightsbridge Pa...Integrating Geothermal Loops into the Diaphragm walls of the Knightsbridge Pa...
Integrating Geothermal Loops into the Diaphragm walls of the Knightsbridge Pa...
 
KINGDOM TOWER JEDDAH TOWER
KINGDOM TOWER JEDDAH TOWERKINGDOM TOWER JEDDAH TOWER
KINGDOM TOWER JEDDAH TOWER
 
Aldar Headquarters Dubai
Aldar Headquarters DubaiAldar Headquarters Dubai
Aldar Headquarters Dubai
 
Monolithic dome ppt
Monolithic dome pptMonolithic dome ppt
Monolithic dome ppt
 

Recently uploaded

Digital Signal Processing Lecture notes n.pdf
Digital Signal Processing Lecture notes n.pdfDigital Signal Processing Lecture notes n.pdf
Digital Signal Processing Lecture notes n.pdfAbrahamGadissa
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwoodseandesed
 
Furniture showroom management system project.pdf
Furniture showroom management system project.pdfFurniture showroom management system project.pdf
Furniture showroom management system project.pdfKamal Acharya
 
Arduino based vehicle speed tracker project
Arduino based vehicle speed tracker projectArduino based vehicle speed tracker project
Arduino based vehicle speed tracker projectRased Khan
 
Toll tax management system project report..pdf
Toll tax management system project report..pdfToll tax management system project report..pdf
Toll tax management system project report..pdfKamal Acharya
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.PrashantGoswami42
 
A CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdf
A CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdfA CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdf
A CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdfKamal Acharya
 
IT-601 Lecture Notes-UNIT-2.pdf Data Analysis
IT-601 Lecture Notes-UNIT-2.pdf Data AnalysisIT-601 Lecture Notes-UNIT-2.pdf Data Analysis
IT-601 Lecture Notes-UNIT-2.pdf Data AnalysisDr. Radhey Shyam
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdfKamal Acharya
 
Laundry management system project report.pdf
Laundry management system project report.pdfLaundry management system project report.pdf
Laundry management system project report.pdfKamal Acharya
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industriesMuhammadTufail242431
 
KIT-601 Lecture Notes-UNIT-3.pdf Mining Data Stream
KIT-601 Lecture Notes-UNIT-3.pdf Mining Data StreamKIT-601 Lecture Notes-UNIT-3.pdf Mining Data Stream
KIT-601 Lecture Notes-UNIT-3.pdf Mining Data StreamDr. Radhey Shyam
 
RESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdf
RESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdfRESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdf
RESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdfKamal Acharya
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxR&R Consult
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacksgerogepatton
 
Hall booking system project report .pdf
Hall booking system project report  .pdfHall booking system project report  .pdf
Hall booking system project report .pdfKamal Acharya
 
KIT-601 Lecture Notes-UNIT-4.pdf Frequent Itemsets and Clustering
KIT-601 Lecture Notes-UNIT-4.pdf Frequent Itemsets and ClusteringKIT-601 Lecture Notes-UNIT-4.pdf Frequent Itemsets and Clustering
KIT-601 Lecture Notes-UNIT-4.pdf Frequent Itemsets and ClusteringDr. Radhey Shyam
 
İTÜ CAD and Reverse Engineering Workshop
İTÜ CAD and Reverse Engineering WorkshopİTÜ CAD and Reverse Engineering Workshop
İTÜ CAD and Reverse Engineering WorkshopEmre Günaydın
 
RS Khurmi Machine Design Clutch and Brake Exercise Numerical Solutions
RS Khurmi Machine Design Clutch and Brake Exercise Numerical SolutionsRS Khurmi Machine Design Clutch and Brake Exercise Numerical Solutions
RS Khurmi Machine Design Clutch and Brake Exercise Numerical SolutionsAtif Razi
 

Recently uploaded (20)

Digital Signal Processing Lecture notes n.pdf
Digital Signal Processing Lecture notes n.pdfDigital Signal Processing Lecture notes n.pdf
Digital Signal Processing Lecture notes n.pdf
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
Furniture showroom management system project.pdf
Furniture showroom management system project.pdfFurniture showroom management system project.pdf
Furniture showroom management system project.pdf
 
Arduino based vehicle speed tracker project
Arduino based vehicle speed tracker projectArduino based vehicle speed tracker project
Arduino based vehicle speed tracker project
 
Toll tax management system project report..pdf
Toll tax management system project report..pdfToll tax management system project report..pdf
Toll tax management system project report..pdf
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
 
A CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdf
A CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdfA CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdf
A CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdf
 
IT-601 Lecture Notes-UNIT-2.pdf Data Analysis
IT-601 Lecture Notes-UNIT-2.pdf Data AnalysisIT-601 Lecture Notes-UNIT-2.pdf Data Analysis
IT-601 Lecture Notes-UNIT-2.pdf Data Analysis
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
 
Laundry management system project report.pdf
Laundry management system project report.pdfLaundry management system project report.pdf
Laundry management system project report.pdf
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
 
KIT-601 Lecture Notes-UNIT-3.pdf Mining Data Stream
KIT-601 Lecture Notes-UNIT-3.pdf Mining Data StreamKIT-601 Lecture Notes-UNIT-3.pdf Mining Data Stream
KIT-601 Lecture Notes-UNIT-3.pdf Mining Data Stream
 
RESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdf
RESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdfRESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdf
RESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdf
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
Hall booking system project report .pdf
Hall booking system project report  .pdfHall booking system project report  .pdf
Hall booking system project report .pdf
 
KIT-601 Lecture Notes-UNIT-4.pdf Frequent Itemsets and Clustering
KIT-601 Lecture Notes-UNIT-4.pdf Frequent Itemsets and ClusteringKIT-601 Lecture Notes-UNIT-4.pdf Frequent Itemsets and Clustering
KIT-601 Lecture Notes-UNIT-4.pdf Frequent Itemsets and Clustering
 
İTÜ CAD and Reverse Engineering Workshop
İTÜ CAD and Reverse Engineering WorkshopİTÜ CAD and Reverse Engineering Workshop
İTÜ CAD and Reverse Engineering Workshop
 
RS Khurmi Machine Design Clutch and Brake Exercise Numerical Solutions
RS Khurmi Machine Design Clutch and Brake Exercise Numerical SolutionsRS Khurmi Machine Design Clutch and Brake Exercise Numerical Solutions
RS Khurmi Machine Design Clutch and Brake Exercise Numerical Solutions
 

PPT ON BURJ AL ARAB

  • 1. “BURJ AL ARAB” THE TOWER OF ARABS PRESENTED BY P.V.MANEKAR
  • 2. TECHNICAL DETAILS  Concrete on the island: 33,000 sq m  Concrete in the superstructure: 36,000 sq m  Total tonnage of steel: 9000 tones  Gross area of building: 120,000 sq m  Glass: 43,446 sq m  Marbles: 24,000 sq m  202 duplex suites  Ranges from 170 sq m to 780 sq m  Floor count: 18  Elevator count 16
  • 3. CONSTRUCTION  Construction was began in 1994 and completed in october1999.  Chief architect: Tom Wright  Chief structural engineer: Anthony McCarter  Contractor: Al Habtoor Engineering, Fletcher construction, Murray & Roberts  Steel contractor: Eversendai Engineering  Owner: Sheikh Mohammed bin Rashid al Maktoom  Construction cost: $650 million
  • 4. ARTIFICIAL ISLAND  It took three years to reclaim the land from the sea, and less than three years to construct the building.  As there is only sand to hold the building up the column rely on friction.  Distance of shore to the outer point of island: 450m  Size of island: 150m per side  Sea depth: 7.5m  No. of piles: 230  Size of piles: 1.5m  Length of piles: 45m
  • 5.  Temporary tube piles driven into sea bed  Temporary sheet piles and tie rods driven into sea bed to support boundary rocks (see figure 1)  Permanent boundary rock bunds deposited either side of sheet piles  Hydraulic fill layers deposited between bunds to displace sea water and form island (see figure 2 with fill layers partially complete)
  • 6.  Permanent concrete armour units placed around island to protect it from the waves  2m diameter 43m deep piles driven through island and sea bed below to stabilize structure (see figure 3)  Island interior excavated and temporary sheet pile coffer dam inserted  2m thick concrete plug slab laid at base of island  Reinforced concrete retaining wall built  Basement floors created (see figure 4)
  • 8. ATRIUM WALL  Constructed from 2 skins of Teflon coated fiber glass separated by air gap of 500mm.  The largest Teflon coated fiber fabric wall is used to cover the atrium.  This is first time such technology has been used vertically.  It resembles a huge sail.  The tallest 182m atrium in the world.
  • 9. EXOSKELETON LEG ERECTION  Made of two build up H section 1.8 x 4.5m deep plate girders.  Creates a gentle curve concurrence with building edge developing the shape of a sail.  Alignment was carried out using total station located at three different fixed locations.
  • 10. BRACE FRAME  ‘X’ Shape rear bracings are cross bracings of fabricated box sections.  Boxes are 2.2m x 1.4m and made from 25mm to 40 mm thick plates.  They tie two cores of the building to give stability to the structure.  The length of one brace was around 60m in one direction.
  • 11. TRUSSES  Hugh tubular triangular truss.  Vary from 76m to 90m and weight 160 to 180 tons.  There are six trusses to resists lateral loads and reduce moment & deflection.
  • 12.  Connects with 300mm diameter pin to the core wall and rear leg.  To solve the problem of expansion and contraction which can change 5cm in a day, special steering linkage rod was designed. TRUSSES
  • 13. HORIZONTALS  Weight is 200 tons connects the core wall to exoskeleton rear leg.  Assembled in one piece in assembly yard near the site.  Erected by strand jacking method similar to diagonals
  • 15.  This structure is at 212m level front side of building, weights about 330 tons.  Two props of 1m diameter circular steel pipes forming an inverted V shape.  Tapered at 30º to the vertical and tied back to center core by 40m long spine truss weighing 120 tons.
  • 17.  Most complex and potentially dangerous structure.  It is located 200m above the persian gulf.  It is built on 30m long 8 box girder cantilevers from the main core wall radiates as support and are not visible.  Floor size of 70mx25m.  Entire structure is enclosed in aluminuim and glass.
  • 18. MAST  This is 104 meter long.  Oval shape of 2.5m x 5m and gradually decreases to 2.5 x 2m at top.  Segments has inside arrangements of permanent ladders and interval platforms to facilitate access.  Manholes at periodic intervals through which workers have access.
  • 19. WIND EFFECTS  Vibration may cause due to vortex shedding.  11 invisible hanging weight called the tune mass dampers at vulnerable points inside the exoskeleton.  The shape of burj Al Arab lowers wind forces more effectively because of the streamlined V and curved fabric atrium wall.
  • 21. SEISMIC IMPACT  Dubai is not in earthquake resisting zone.  However, burj al arab is design to resist earthquake of MM VII intensity.  Tune mass dampers also helps to resist the effect of earthquake.  Seismic zone factor of 0.20g is considered for the detailed design phase.
  • 22. CONCLUSION  Burj Al Arab, is currently recognized as one of spectacular structure in the history of structural engineering.  Problems like high concentration of chloride in the air and extreme temperature, wind effect and potential seismic events have to be taken into account in the detailed design phase.  The Burj Al Arab hotel project, which is uniquely complex yet rewarding, marks the advancement in structural engineering technology.