SlideShare a Scribd company logo
1 of 13
HOPE ENTERPRISE UNIVERSITY COLLAGE
DEPARTMENT OF ARCHITECTURE
“Foundation”
By: 1.Arsema Bekele
2.Amen Mikael
3.Alazar Hagos
4.Biruk Yared
5.Bisrateab Fekadu
6.Esmael Abdu
7.Simon Asene
8.Tsinat Chelot
9. Mahilet Getahun
Date: March 28-2024G.C
OUTLINE
O1. Introduction
02. Design and Construction
03. The structural system
04. Foundation
05. Construction Materials
06. Conclusion
01. INTRODUCTION
Key Details of the Project
● Construction period: 2009 – 2012
● Height: 309.6 m (1,016 ft)
● Floor count: 95
● Floor area: 110,000 m2 (1,200,000 sq ft)
● Architect: Renzo Piano
● Developer: Sellar Property Group
● Main contractor: Mace
● Main designer: WSP
● Owner: State of Qatar (95%), Sellar Property Group (5%)
● Contract cost: £435 million
02. Design and Construction
● Delivering Europe's tallest tower in record time pushed
structural engineers and contractors to rethink the
fundamental principles of construction and employ new
ways to build faster and taller than had previously been done
in the UK.
● To overcome the challenges of safely constructing a
skyscraper in central London, adjacent to a major
transportation hub, the team achieved a number of firsts,
including the first top-down core, the UK's largest concrete
pour, the first use of jump-lift construction, the world's first
inclined hoist, and the first crane supported on a slipform.
03. The structural system
MAIN STRUCTURE
● The structural system of the tower is a combination of
different systems. It consists of concrete cores, composite
floors, and steel structural members.
● The Shard Tower has about 54,000 cubic metric tons of
concrete and the steel system has a weight of about 11,000
tons.
● The core of the tower was made by slip forming. The core
was constructed at a rate of at least 3 meters per day.
● The steel columns are aligned with the slope of the Shard
Tower.
● The size, weight, and spacing of the columns get smaller
the higher they go up in floors..
04. Foundation
● Movement monitoring, vibration, ground water
and reuse of old piles were taken into account in
designing foundation.
● Top-Down construction methodology was used in
construction.
● Plunged columns used to supported core and Top-
down slabs.
● The slab underneath the core has 3m thickness
with four layers of reinforcement in each direction
to provide stiffness.
Cont..
● Top-down construction is a time-saving technique in which
construction occurs from the ground level downwards. At the
location, 500 mm x 500 mm steel columns were "plunged" from the
ground level through empty pile bores into freshly poured concrete.
● The slab was then cast directly on grade. After gaining strength, the
slab was capable of propping the perimeter embedded walls and
could be supported by the plunge columns, allowing excavation
below the slab to proceed. This allowed the construction of the
superstructure and basement to proceed simultaneously.
● This technique made it possible to construct the first 23 storeys of
the 72-story concrete core as well as a large portion of the
surrounding tower before the basement had been completely
excavated. This was needed because of the difficulty of
constructing a skyscraper in a densely populated location near to a
major transportation hub, and it helped to shorten the lengthy
construction schedule by four months.
CONT…
THE LOWDOWN ON TOP-DOWN
Step one
The secant pile wall is installed around the perimeter along with the
plunge piles and columns.
Step two
The ground floor slab of the building is cast and excavation begins
down to level two of the basement
Step three
The floor slab at basement level two is cast and the slip farm for care
construction erected to "jump start" the core. As the core goes up
excavation below basement level two continues.
Step four
As the core construction continues, the raft foundation is cast at
basement level three (the lower red level in the picture) before the
concrete walls between the base of the core and the raft are installed
Step 1
Step 2
Step 3
Step 4
Cont…
● The foundation and basement levels, up to level 39 serve as offices and lower retail.
● The engineers decided to use a steel frame with deep beams to enable further spacing within the
columns.
● A majority of the steel used within the building exists within the lower office levels of the building
(ground-39). The sections contains 15,000 pieces of structural steel and weighs 12,000 tons.
● This steel structure is made using 20 inch deep I beans that acquire standard holes for system pass
through. On top of the beams is a lightweight concrete slab measuring 5 inches thick.
● They were designed to span up to 50 feet (from perimeter to core) for spatial adaptability in offices.
● The joints that connected the cladding and the floor plates utilized compact plate girders. The
utilization of these girders was specified for low depths on the facade.
● This was a desire by the architect to take advantage of the sun penetration. Additionally, the floor
that sits on these open beams are raised on cambers
Cont…
05. Construction Materials
● The distinctive tapered form consists of the following structures:
First 40 floors: Composite steel frame.
Up to the 60th floor: Post-tension concrete frame.
Up to the 72nd floor: Conventional reinforced concrete frame.
Spire to 87th floor: Pre-fabricated steel.
● The use of concrete and steel improved the structure's efficiency.
Post-tensioned concrete was better suited for the smaller spans
higher up the building, saving 550 millimetres per level. In
addition, ceiling space for services was improved by the use of
uniform-depth steel beams acting in combination with concrete
floor slabs. The structure contains 11,000 panes of glass and has a
total surface area of 56,000 square metres (600,000 sq. ft).
06. Conclusion
● Due to the soft and compressible nature of the London Clay beneath the site, deep foundation techniques were
employed to provide adequate support for the skyscraper. The foundation system utilized a combination of
concrete piles and raft foundations.
● Concrete piles were driven deep into the ground to reach stable strata below the soft clay. These piles serve as
load-bearing elements, transferring the weight of the building to deeper, more stable layers of soil or rock. The
depth and diameter of the piles were carefully calculated to ensure sufficient support for the immense weight of
the structure.
● In addition to the piles, a massive reinforced concrete raft foundation was constructed atop the piles. The raft
foundation, also known as a mat foundation, spreads the weight of the building over a large area, reducing the
pressure on the underlying soil. This helps prevent settlement and ensures the stability of the structure.
● Designing the foundation system for The Shard posed several engineering challenges. The presence of the River
Thames nearby required special consideration for potential scouring and erosion of the riverbed. Additionally,
the sheer height of the building and its complex architectural design necessitated innovative structural solutions
to ensure stability and resistance to wind loads and seismic activity.
● After completion, the foundation system of The Shard is continuously monitored for any signs of settlement or
structural movement. Advanced monitoring techniques, including sensors embedded within the foundation
elements, help engineers detect and address any issues promptly. Regular maintenance and inspection ensure the
long-term integrity and safety of the building.
● Overall, the foundation system of The Shard is a testament to the ingenuity and expertise of the engineers and
architects involved in its design and construction. By employing advanced techniques and meticulous planning,
they created a solid foundation that supports one of the most iconic skyscrapers in the world.
CREDITS: This presentation template was created by Slidesgo, and includes
icons by Flaticon, and infographics & images by Freepik
Thanks!
Do you have any questions?

More Related Content

Similar to foundation and structural system of the shard building

MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVEMODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVEDr K M SONI
 
High Rise Structures case study - The Gherkin & Shanghai financial center.
High Rise Structures  case study - The Gherkin & Shanghai financial center.High Rise Structures  case study - The Gherkin & Shanghai financial center.
High Rise Structures case study - The Gherkin & Shanghai financial center.Shabarinath R
 
Slip formwork for chimney
Slip formwork for chimneySlip formwork for chimney
Slip formwork for chimneyAxay Sharma
 
London Aquatics Center – Zaha Hadid Architects
 London Aquatics Center – Zaha Hadid Architects London Aquatics Center – Zaha Hadid Architects
London Aquatics Center – Zaha Hadid ArchitectsDhanveersinh Chavda
 
the kajima cut and take down method
the kajima cut and take down methodthe kajima cut and take down method
the kajima cut and take down methodDarshan Parakhiya
 
national building code
national building codenational building code
national building codeRuhiya Garg
 
Construction Technology Essay Sample Harvard
Construction Technology Essay Sample HarvardConstruction Technology Essay Sample Harvard
Construction Technology Essay Sample HarvardWriters Per Hour
 
HIGH RISE BUILDINGS.pptx
HIGH RISE BUILDINGS.pptxHIGH RISE BUILDINGS.pptx
HIGH RISE BUILDINGS.pptxgoreshsaini2
 
high rise seismic resistant buildings
 high rise seismic resistant buildings high rise seismic resistant buildings
high rise seismic resistant buildingsAr.Farooqh A
 
Aldar Headquarters Dubai
Aldar Headquarters DubaiAldar Headquarters Dubai
Aldar Headquarters DubaiNeha Rampuria
 
Milstein hall by oma.pptx
Milstein hall by oma.pptxMilstein hall by oma.pptx
Milstein hall by oma.pptxBett34
 

Similar to foundation and structural system of the shard building (20)

MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVEMODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
 
High Rise Structures case study - The Gherkin & Shanghai financial center.
High Rise Structures  case study - The Gherkin & Shanghai financial center.High Rise Structures  case study - The Gherkin & Shanghai financial center.
High Rise Structures case study - The Gherkin & Shanghai financial center.
 
Type of high rise building
Type of high rise buildingType of high rise building
Type of high rise building
 
Slip formwork for chimney
Slip formwork for chimneySlip formwork for chimney
Slip formwork for chimney
 
London Aquatics Center – Zaha Hadid Architects
 London Aquatics Center – Zaha Hadid Architects London Aquatics Center – Zaha Hadid Architects
London Aquatics Center – Zaha Hadid Architects
 
burj khalifa
burj khalifaburj khalifa
burj khalifa
 
5th batch.pptx
5th batch.pptx5th batch.pptx
5th batch.pptx
 
the kajima cut and take down method
the kajima cut and take down methodthe kajima cut and take down method
the kajima cut and take down method
 
national building code
national building codenational building code
national building code
 
Construction Technology Essay Sample Harvard
Construction Technology Essay Sample HarvardConstruction Technology Essay Sample Harvard
Construction Technology Essay Sample Harvard
 
KINGDOM TOWER JEDDAH TOWER
KINGDOM TOWER JEDDAH TOWERKINGDOM TOWER JEDDAH TOWER
KINGDOM TOWER JEDDAH TOWER
 
HIGH RISE BUILDINGS.pptx
HIGH RISE BUILDINGS.pptxHIGH RISE BUILDINGS.pptx
HIGH RISE BUILDINGS.pptx
 
Capital gate abu dhabi
Capital gate abu dhabiCapital gate abu dhabi
Capital gate abu dhabi
 
advanced construction
advanced constructionadvanced construction
advanced construction
 
high rise seismic resistant buildings
 high rise seismic resistant buildings high rise seismic resistant buildings
high rise seismic resistant buildings
 
Aldar Headquarters Dubai
Aldar Headquarters DubaiAldar Headquarters Dubai
Aldar Headquarters Dubai
 
Car park 02
Car park 02Car park 02
Car park 02
 
simplex infrastructure
simplex infrastructure simplex infrastructure
simplex infrastructure
 
Mod. 1.pptx
Mod. 1.pptxMod. 1.pptx
Mod. 1.pptx
 
Milstein hall by oma.pptx
Milstein hall by oma.pptxMilstein hall by oma.pptx
Milstein hall by oma.pptx
 

Recently uploaded

Generative AI on Enterprise Cloud with NiFi and Milvus
Generative AI on Enterprise Cloud with NiFi and MilvusGenerative AI on Enterprise Cloud with NiFi and Milvus
Generative AI on Enterprise Cloud with NiFi and MilvusTimothy Spann
 
VIP High Class Call Girls Jamshedpur Anushka 8250192130 Independent Escort Se...
VIP High Class Call Girls Jamshedpur Anushka 8250192130 Independent Escort Se...VIP High Class Call Girls Jamshedpur Anushka 8250192130 Independent Escort Se...
VIP High Class Call Girls Jamshedpur Anushka 8250192130 Independent Escort Se...Suhani Kapoor
 
VidaXL dropshipping via API with DroFx.pptx
VidaXL dropshipping via API with DroFx.pptxVidaXL dropshipping via API with DroFx.pptx
VidaXL dropshipping via API with DroFx.pptxolyaivanovalion
 
Schema on read is obsolete. Welcome metaprogramming..pdf
Schema on read is obsolete. Welcome metaprogramming..pdfSchema on read is obsolete. Welcome metaprogramming..pdf
Schema on read is obsolete. Welcome metaprogramming..pdfLars Albertsson
 
VIP Call Girls Service Miyapur Hyderabad Call +91-8250192130
VIP Call Girls Service Miyapur Hyderabad Call +91-8250192130VIP Call Girls Service Miyapur Hyderabad Call +91-8250192130
VIP Call Girls Service Miyapur Hyderabad Call +91-8250192130Suhani Kapoor
 
VIP High Profile Call Girls Amravati Aarushi 8250192130 Independent Escort Se...
VIP High Profile Call Girls Amravati Aarushi 8250192130 Independent Escort Se...VIP High Profile Call Girls Amravati Aarushi 8250192130 Independent Escort Se...
VIP High Profile Call Girls Amravati Aarushi 8250192130 Independent Escort Se...Suhani Kapoor
 
Delhi Call Girls Punjabi Bagh 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Call
Delhi Call Girls Punjabi Bagh 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip CallDelhi Call Girls Punjabi Bagh 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Call
Delhi Call Girls Punjabi Bagh 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Callshivangimorya083
 
FESE Capital Markets Fact Sheet 2024 Q1.pdf
FESE Capital Markets Fact Sheet 2024 Q1.pdfFESE Capital Markets Fact Sheet 2024 Q1.pdf
FESE Capital Markets Fact Sheet 2024 Q1.pdfMarinCaroMartnezBerg
 
Ravak dropshipping via API with DroFx.pptx
Ravak dropshipping via API with DroFx.pptxRavak dropshipping via API with DroFx.pptx
Ravak dropshipping via API with DroFx.pptxolyaivanovalion
 
Log Analysis using OSSEC sasoasasasas.pptx
Log Analysis using OSSEC sasoasasasas.pptxLog Analysis using OSSEC sasoasasasas.pptx
Log Analysis using OSSEC sasoasasasas.pptxJohnnyPlasten
 
Invezz.com - Grow your wealth with trading signals
Invezz.com - Grow your wealth with trading signalsInvezz.com - Grow your wealth with trading signals
Invezz.com - Grow your wealth with trading signalsInvezz1
 
100-Concepts-of-AI by Anupama Kate .pptx
100-Concepts-of-AI by Anupama Kate .pptx100-Concepts-of-AI by Anupama Kate .pptx
100-Concepts-of-AI by Anupama Kate .pptxAnupama Kate
 
BPAC WITH UFSBI GENERAL PRESENTATION 18_05_2017-1.pptx
BPAC WITH UFSBI GENERAL PRESENTATION 18_05_2017-1.pptxBPAC WITH UFSBI GENERAL PRESENTATION 18_05_2017-1.pptx
BPAC WITH UFSBI GENERAL PRESENTATION 18_05_2017-1.pptxMohammedJunaid861692
 
Call Girls in Sarai Kale Khan Delhi 💯 Call Us 🔝9205541914 🔝( Delhi) Escorts S...
Call Girls in Sarai Kale Khan Delhi 💯 Call Us 🔝9205541914 🔝( Delhi) Escorts S...Call Girls in Sarai Kale Khan Delhi 💯 Call Us 🔝9205541914 🔝( Delhi) Escorts S...
Call Girls in Sarai Kale Khan Delhi 💯 Call Us 🔝9205541914 🔝( Delhi) Escorts S...Delhi Call girls
 
Industrialised data - the key to AI success.pdf
Industrialised data - the key to AI success.pdfIndustrialised data - the key to AI success.pdf
Industrialised data - the key to AI success.pdfLars Albertsson
 
Smarteg dropshipping via API with DroFx.pptx
Smarteg dropshipping via API with DroFx.pptxSmarteg dropshipping via API with DroFx.pptx
Smarteg dropshipping via API with DroFx.pptxolyaivanovalion
 
Brighton SEO | April 2024 | Data Storytelling
Brighton SEO | April 2024 | Data StorytellingBrighton SEO | April 2024 | Data Storytelling
Brighton SEO | April 2024 | Data StorytellingNeil Barnes
 
Al Barsha Escorts $#$ O565212860 $#$ Escort Service In Al Barsha
Al Barsha Escorts $#$ O565212860 $#$ Escort Service In Al BarshaAl Barsha Escorts $#$ O565212860 $#$ Escort Service In Al Barsha
Al Barsha Escorts $#$ O565212860 $#$ Escort Service In Al BarshaAroojKhan71
 

Recently uploaded (20)

Generative AI on Enterprise Cloud with NiFi and Milvus
Generative AI on Enterprise Cloud with NiFi and MilvusGenerative AI on Enterprise Cloud with NiFi and Milvus
Generative AI on Enterprise Cloud with NiFi and Milvus
 
VIP High Class Call Girls Jamshedpur Anushka 8250192130 Independent Escort Se...
VIP High Class Call Girls Jamshedpur Anushka 8250192130 Independent Escort Se...VIP High Class Call Girls Jamshedpur Anushka 8250192130 Independent Escort Se...
VIP High Class Call Girls Jamshedpur Anushka 8250192130 Independent Escort Se...
 
VidaXL dropshipping via API with DroFx.pptx
VidaXL dropshipping via API with DroFx.pptxVidaXL dropshipping via API with DroFx.pptx
VidaXL dropshipping via API with DroFx.pptx
 
VIP Call Girls Service Charbagh { Lucknow Call Girls Service 9548273370 } Boo...
VIP Call Girls Service Charbagh { Lucknow Call Girls Service 9548273370 } Boo...VIP Call Girls Service Charbagh { Lucknow Call Girls Service 9548273370 } Boo...
VIP Call Girls Service Charbagh { Lucknow Call Girls Service 9548273370 } Boo...
 
Schema on read is obsolete. Welcome metaprogramming..pdf
Schema on read is obsolete. Welcome metaprogramming..pdfSchema on read is obsolete. Welcome metaprogramming..pdf
Schema on read is obsolete. Welcome metaprogramming..pdf
 
VIP Call Girls Service Miyapur Hyderabad Call +91-8250192130
VIP Call Girls Service Miyapur Hyderabad Call +91-8250192130VIP Call Girls Service Miyapur Hyderabad Call +91-8250192130
VIP Call Girls Service Miyapur Hyderabad Call +91-8250192130
 
VIP High Profile Call Girls Amravati Aarushi 8250192130 Independent Escort Se...
VIP High Profile Call Girls Amravati Aarushi 8250192130 Independent Escort Se...VIP High Profile Call Girls Amravati Aarushi 8250192130 Independent Escort Se...
VIP High Profile Call Girls Amravati Aarushi 8250192130 Independent Escort Se...
 
Delhi Call Girls Punjabi Bagh 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Call
Delhi Call Girls Punjabi Bagh 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip CallDelhi Call Girls Punjabi Bagh 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Call
Delhi Call Girls Punjabi Bagh 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Call
 
Delhi 99530 vip 56974 Genuine Escort Service Call Girls in Kishangarh
Delhi 99530 vip 56974 Genuine Escort Service Call Girls in  KishangarhDelhi 99530 vip 56974 Genuine Escort Service Call Girls in  Kishangarh
Delhi 99530 vip 56974 Genuine Escort Service Call Girls in Kishangarh
 
FESE Capital Markets Fact Sheet 2024 Q1.pdf
FESE Capital Markets Fact Sheet 2024 Q1.pdfFESE Capital Markets Fact Sheet 2024 Q1.pdf
FESE Capital Markets Fact Sheet 2024 Q1.pdf
 
Ravak dropshipping via API with DroFx.pptx
Ravak dropshipping via API with DroFx.pptxRavak dropshipping via API with DroFx.pptx
Ravak dropshipping via API with DroFx.pptx
 
Log Analysis using OSSEC sasoasasasas.pptx
Log Analysis using OSSEC sasoasasasas.pptxLog Analysis using OSSEC sasoasasasas.pptx
Log Analysis using OSSEC sasoasasasas.pptx
 
Invezz.com - Grow your wealth with trading signals
Invezz.com - Grow your wealth with trading signalsInvezz.com - Grow your wealth with trading signals
Invezz.com - Grow your wealth with trading signals
 
100-Concepts-of-AI by Anupama Kate .pptx
100-Concepts-of-AI by Anupama Kate .pptx100-Concepts-of-AI by Anupama Kate .pptx
100-Concepts-of-AI by Anupama Kate .pptx
 
BPAC WITH UFSBI GENERAL PRESENTATION 18_05_2017-1.pptx
BPAC WITH UFSBI GENERAL PRESENTATION 18_05_2017-1.pptxBPAC WITH UFSBI GENERAL PRESENTATION 18_05_2017-1.pptx
BPAC WITH UFSBI GENERAL PRESENTATION 18_05_2017-1.pptx
 
Call Girls in Sarai Kale Khan Delhi 💯 Call Us 🔝9205541914 🔝( Delhi) Escorts S...
Call Girls in Sarai Kale Khan Delhi 💯 Call Us 🔝9205541914 🔝( Delhi) Escorts S...Call Girls in Sarai Kale Khan Delhi 💯 Call Us 🔝9205541914 🔝( Delhi) Escorts S...
Call Girls in Sarai Kale Khan Delhi 💯 Call Us 🔝9205541914 🔝( Delhi) Escorts S...
 
Industrialised data - the key to AI success.pdf
Industrialised data - the key to AI success.pdfIndustrialised data - the key to AI success.pdf
Industrialised data - the key to AI success.pdf
 
Smarteg dropshipping via API with DroFx.pptx
Smarteg dropshipping via API with DroFx.pptxSmarteg dropshipping via API with DroFx.pptx
Smarteg dropshipping via API with DroFx.pptx
 
Brighton SEO | April 2024 | Data Storytelling
Brighton SEO | April 2024 | Data StorytellingBrighton SEO | April 2024 | Data Storytelling
Brighton SEO | April 2024 | Data Storytelling
 
Al Barsha Escorts $#$ O565212860 $#$ Escort Service In Al Barsha
Al Barsha Escorts $#$ O565212860 $#$ Escort Service In Al BarshaAl Barsha Escorts $#$ O565212860 $#$ Escort Service In Al Barsha
Al Barsha Escorts $#$ O565212860 $#$ Escort Service In Al Barsha
 

foundation and structural system of the shard building

  • 1. HOPE ENTERPRISE UNIVERSITY COLLAGE DEPARTMENT OF ARCHITECTURE “Foundation” By: 1.Arsema Bekele 2.Amen Mikael 3.Alazar Hagos 4.Biruk Yared 5.Bisrateab Fekadu 6.Esmael Abdu 7.Simon Asene 8.Tsinat Chelot 9. Mahilet Getahun Date: March 28-2024G.C
  • 2. OUTLINE O1. Introduction 02. Design and Construction 03. The structural system 04. Foundation 05. Construction Materials 06. Conclusion
  • 3. 01. INTRODUCTION Key Details of the Project ● Construction period: 2009 – 2012 ● Height: 309.6 m (1,016 ft) ● Floor count: 95 ● Floor area: 110,000 m2 (1,200,000 sq ft) ● Architect: Renzo Piano ● Developer: Sellar Property Group ● Main contractor: Mace ● Main designer: WSP ● Owner: State of Qatar (95%), Sellar Property Group (5%) ● Contract cost: £435 million
  • 4. 02. Design and Construction ● Delivering Europe's tallest tower in record time pushed structural engineers and contractors to rethink the fundamental principles of construction and employ new ways to build faster and taller than had previously been done in the UK. ● To overcome the challenges of safely constructing a skyscraper in central London, adjacent to a major transportation hub, the team achieved a number of firsts, including the first top-down core, the UK's largest concrete pour, the first use of jump-lift construction, the world's first inclined hoist, and the first crane supported on a slipform.
  • 5. 03. The structural system MAIN STRUCTURE ● The structural system of the tower is a combination of different systems. It consists of concrete cores, composite floors, and steel structural members. ● The Shard Tower has about 54,000 cubic metric tons of concrete and the steel system has a weight of about 11,000 tons. ● The core of the tower was made by slip forming. The core was constructed at a rate of at least 3 meters per day. ● The steel columns are aligned with the slope of the Shard Tower. ● The size, weight, and spacing of the columns get smaller the higher they go up in floors..
  • 6. 04. Foundation ● Movement monitoring, vibration, ground water and reuse of old piles were taken into account in designing foundation. ● Top-Down construction methodology was used in construction. ● Plunged columns used to supported core and Top- down slabs. ● The slab underneath the core has 3m thickness with four layers of reinforcement in each direction to provide stiffness.
  • 7. Cont.. ● Top-down construction is a time-saving technique in which construction occurs from the ground level downwards. At the location, 500 mm x 500 mm steel columns were "plunged" from the ground level through empty pile bores into freshly poured concrete. ● The slab was then cast directly on grade. After gaining strength, the slab was capable of propping the perimeter embedded walls and could be supported by the plunge columns, allowing excavation below the slab to proceed. This allowed the construction of the superstructure and basement to proceed simultaneously. ● This technique made it possible to construct the first 23 storeys of the 72-story concrete core as well as a large portion of the surrounding tower before the basement had been completely excavated. This was needed because of the difficulty of constructing a skyscraper in a densely populated location near to a major transportation hub, and it helped to shorten the lengthy construction schedule by four months.
  • 8. CONT… THE LOWDOWN ON TOP-DOWN Step one The secant pile wall is installed around the perimeter along with the plunge piles and columns. Step two The ground floor slab of the building is cast and excavation begins down to level two of the basement Step three The floor slab at basement level two is cast and the slip farm for care construction erected to "jump start" the core. As the core goes up excavation below basement level two continues. Step four As the core construction continues, the raft foundation is cast at basement level three (the lower red level in the picture) before the concrete walls between the base of the core and the raft are installed Step 1 Step 2 Step 3 Step 4
  • 9. Cont… ● The foundation and basement levels, up to level 39 serve as offices and lower retail. ● The engineers decided to use a steel frame with deep beams to enable further spacing within the columns. ● A majority of the steel used within the building exists within the lower office levels of the building (ground-39). The sections contains 15,000 pieces of structural steel and weighs 12,000 tons. ● This steel structure is made using 20 inch deep I beans that acquire standard holes for system pass through. On top of the beams is a lightweight concrete slab measuring 5 inches thick. ● They were designed to span up to 50 feet (from perimeter to core) for spatial adaptability in offices. ● The joints that connected the cladding and the floor plates utilized compact plate girders. The utilization of these girders was specified for low depths on the facade. ● This was a desire by the architect to take advantage of the sun penetration. Additionally, the floor that sits on these open beams are raised on cambers
  • 11. 05. Construction Materials ● The distinctive tapered form consists of the following structures: First 40 floors: Composite steel frame. Up to the 60th floor: Post-tension concrete frame. Up to the 72nd floor: Conventional reinforced concrete frame. Spire to 87th floor: Pre-fabricated steel. ● The use of concrete and steel improved the structure's efficiency. Post-tensioned concrete was better suited for the smaller spans higher up the building, saving 550 millimetres per level. In addition, ceiling space for services was improved by the use of uniform-depth steel beams acting in combination with concrete floor slabs. The structure contains 11,000 panes of glass and has a total surface area of 56,000 square metres (600,000 sq. ft).
  • 12. 06. Conclusion ● Due to the soft and compressible nature of the London Clay beneath the site, deep foundation techniques were employed to provide adequate support for the skyscraper. The foundation system utilized a combination of concrete piles and raft foundations. ● Concrete piles were driven deep into the ground to reach stable strata below the soft clay. These piles serve as load-bearing elements, transferring the weight of the building to deeper, more stable layers of soil or rock. The depth and diameter of the piles were carefully calculated to ensure sufficient support for the immense weight of the structure. ● In addition to the piles, a massive reinforced concrete raft foundation was constructed atop the piles. The raft foundation, also known as a mat foundation, spreads the weight of the building over a large area, reducing the pressure on the underlying soil. This helps prevent settlement and ensures the stability of the structure. ● Designing the foundation system for The Shard posed several engineering challenges. The presence of the River Thames nearby required special consideration for potential scouring and erosion of the riverbed. Additionally, the sheer height of the building and its complex architectural design necessitated innovative structural solutions to ensure stability and resistance to wind loads and seismic activity. ● After completion, the foundation system of The Shard is continuously monitored for any signs of settlement or structural movement. Advanced monitoring techniques, including sensors embedded within the foundation elements, help engineers detect and address any issues promptly. Regular maintenance and inspection ensure the long-term integrity and safety of the building. ● Overall, the foundation system of The Shard is a testament to the ingenuity and expertise of the engineers and architects involved in its design and construction. By employing advanced techniques and meticulous planning, they created a solid foundation that supports one of the most iconic skyscrapers in the world.
  • 13. CREDITS: This presentation template was created by Slidesgo, and includes icons by Flaticon, and infographics & images by Freepik Thanks! Do you have any questions?