Mosul Dam Crisis: The most dangerous dam in the worldphamill
“….in terms of internal erosion potential of the foundation, Mosul Dam is the most dangerous dam in the world… If a small problem [at] Mosul Dam occurs, failure is likely.”
U.S. Army Corps of Engineers, September 2006
Presentaion - Nadhir Al-Ansari
Professor - Department of Civil, Environmental and Natural Resources Engineering
Lulea University of Technology
Key Facts
The Mosul Dam provides critical irrigation, flood control, and hydropower to NW Iraq
Leaks were discovered within months of operation
U.S. Army study concludes that the dam is at a “high risk” of failure
Projected loss of life from dam failure 500,000 (U.S. Embassy est. 1.47 million)
Only permanent solution is to construct a second dam at estimated cost of $2 billion
this slide shows different types of dams, their sizes and short information of dams.following dams are explained in this slide which are given below masonry dam, concrete dam, arch dam,earthen dam. this slide also shows types of material required for dam, strength, hight
Some general information about golden gate bridge, San Francisco, America. Longest suspension bridge of his time and most visited bridge till now and marvel of CONSTRUCTION. Many movies also include this bridge because of because of its beauty. What a achievement!!!!
Mosul Dam Crisis: The most dangerous dam in the worldphamill
“….in terms of internal erosion potential of the foundation, Mosul Dam is the most dangerous dam in the world… If a small problem [at] Mosul Dam occurs, failure is likely.”
U.S. Army Corps of Engineers, September 2006
Presentaion - Nadhir Al-Ansari
Professor - Department of Civil, Environmental and Natural Resources Engineering
Lulea University of Technology
Key Facts
The Mosul Dam provides critical irrigation, flood control, and hydropower to NW Iraq
Leaks were discovered within months of operation
U.S. Army study concludes that the dam is at a “high risk” of failure
Projected loss of life from dam failure 500,000 (U.S. Embassy est. 1.47 million)
Only permanent solution is to construct a second dam at estimated cost of $2 billion
this slide shows different types of dams, their sizes and short information of dams.following dams are explained in this slide which are given below masonry dam, concrete dam, arch dam,earthen dam. this slide also shows types of material required for dam, strength, hight
Some general information about golden gate bridge, San Francisco, America. Longest suspension bridge of his time and most visited bridge till now and marvel of CONSTRUCTION. Many movies also include this bridge because of because of its beauty. What a achievement!!!!
Detailed Slope Stability Analysis and Assessment of the Original Carsington E...Dr.Costas Sachpazis
A 1225 m long, 35 m high zone earth filled embankment was being constructed from 1981 to 1984 from a British Regional Water Authority to regulate flows in the River Derwent in England. The Carsington Dam was planned to be one of the largest earth filled dams in Britain. Its reservoir capacity was 35 million m3 and the watertight element was Rolled Clay Core with an upstream extension of boot shaped and shoulders of compacted mudstone with horizontal drainage layers of crushed limestone about 4 metres apart and a cut-off grout curtain (Davey and Eccles, 1983).
The downstream slope was 1:2.5 and the upstream slope 1:3. Fill placing began in May 1982 and took three summers, with winter shutdowns. In August 1983 a small berm was placed at the upstream toe to compensate for a faster rate of construction. Earth filling restarted in April 1984 and was one metre below the final crest level on 4 June 1984 when the upstream slope slipped (Skempton, 1985). Observations of pore pressure and settlement were made during construction at four sections and horizontal displacements were observed from August 1983. The Carsington Dam was almost completed on 1984.
However, at the beginning of June 1984, a 400-m length of the upstream shoulder of the embankment dam slipped some 11 m and failed. At the time of the failure, embankment construction was virtually complete with the dam approaching its maximum height of 35 m. Horizontal drainage blankets were incorporated in both the upstream and the downstream shale fill shoulders. Piezometers had been installed and pore pressures were being monitored in the foundation, in the clay core, and in the shoulder fill. The failure surface passed through the boot shaped rolled clay core and a relatively thin layer of surface clay in the foundation of the dam. Investigation of the events at Carsington has made important contributions to the fundamental understanding of the behaviour of large earthworks of this type (Vaughan et al., 1989; Dounias et al., 1996).
The objective of this research is to evaluate a detailed slope stability assessment of the Carsington Earth Embankment Dam in the UK used to retain mine tailings.
By using and applying advanced geotechnical engineering analysis tools and modelling techniques the Carsington Earth Embankment Dam, which is considered a particular geotechnical structure, is analysed.
In the current detailed slope stability analyses the total and effective stress state soil properties / parameters were used, and the most critical slip circle centre according to Fellenius - Jumikis method was initially determined. Subsequently, the Carsington Earth Embankment Dam and its foundation was analysed and examined against failure by slope instability. Considerations of loading conditions which may result to instability for all likely combinations of reservoir and tailwater levels, seepage conditions, both after and during construction were made, and hence three construction and / or loading condit
Detailed Slope Stability Analysis and Assessment of the Original Carsington E...Dr.Costas Sachpazis
A 1225 m long, 35 m high zone earth filled embankment was being constructed from 1981 to 1984 from a British Regional Water Authority to regulate flows in the River Derwent in England. The Carsington Dam was planned to be one of the largest earth filled dams in Britain. Its reservoir capacity was 35 million m3 and the watertight element was Rolled Clay Core with an upstream extension of boot shaped and shoulders of compacted mudstone with horizontal drainage layers of crushed limestone about 4 metres apart and a cut-off grout curtain (Davey and Eccles, 1983).
The downstream slope was 1:2.5 and the upstream slope 1:3. Fill placing began in May 1982 and took three summers, with winter shutdowns. In August 1983 a small berm was placed at the upstream toe to compensate for a faster rate of construction. Earth filling restarted in April 1984 and was one metre below the final crest level on 4 June 1984 when the upstream slope slipped (Skempton, 1985). Observations of pore pressure and settlement were made during construction at four sections and horizontal displacements were observed from August 1983. The Carsington Dam was almost completed on 1984.
However, at the beginning of June 1984, a 400-m length of the upstream shoulder of the embankment dam slipped some 11 m and failed. At the time of the failure, embankment construction was virtually complete with the dam approaching its maximum height of 35 m. Horizontal drainage blankets were incorporated in both the upstream and the downstream shale fill shoulders. Piezometers had been installed and pore pressures were being monitored in the foundation, in the clay core, and in the shoulder fill. The failure surface passed through the boot shaped rolled clay core and a relatively thin layer of surface clay in the foundation of the dam. Investigation of the events at Carsington has made important contributions to the fundamental understanding of the behaviour of large earthworks of this type (Vaughan et al., 1989; Dounias et al., 1996).
The objective of this research is to evaluate a detailed slope stability assessment of the Carsington Earth Embankment Dam in the UK used to retain mine tailings.
By using and applying advanced geotechnical engineering analysis tools and modelling techniques the Carsington Earth Embankment Dam, which is considered a particular geotechnical structure, is analysed.
In the current detailed slope stability analyses the total and effective stress state soil properties / parameters were used, and the most critical slip circle centre according to Fellenius - Jumikis method was initially determined. Subsequently, the Carsington Earth Embankment Dam and its foundation was analysed and examined against failure by slope instability. Considerations of loading conditions which may result to instability for all likely combinations of reservoir and tailwater levels, seepage conditions, both after and during construction were made, and hence three construction and / or loading condit
A submerged floating tunnel, also known as submerged floating tube bridge, suspended tunnel, or Archimedes bridge, is a proposed design for a tunnel that floats in water, supported by its buoyancy. The tube would be placed underwater, deep enough to avoid water traffic and weather, but not so deep that high water pressure needs to be dealt with—usually 20–50 m is sufficient. Cables either anchored to the Earth or to pontoons at the surface would prevent it from floating to the surface or ...
interesting civil engineering topics
civil engineering topics for presentation
seminar topics pdf
best seminar topics for civil engineering
civil seminar topics ppt
civil engineering seminar topics 2019
seminar topics for mechanical engineers
mechanical engineering seminar topics 2018
Immersed tube tunnel is an alternative to bridges and bored tunnels for the crossing of harbors/rivers. Different strategies were considered for the construction of the immersed tunnels in India from different projects around the world during the project.
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)MdTanvirMahtab2
This presentation is about the working procedure of Shahjalal Fertilizer Company Limited (SFCL). A Govt. owned Company of Bangladesh Chemical Industries Corporation under Ministry of Industries.
Welcome to WIPAC Monthly the magazine brought to you by the LinkedIn Group Water Industry Process Automation & Control.
In this month's edition, along with this month's industry news to celebrate the 13 years since the group was created we have articles including
A case study of the used of Advanced Process Control at the Wastewater Treatment works at Lleida in Spain
A look back on an article on smart wastewater networks in order to see how the industry has measured up in the interim around the adoption of Digital Transformation in the Water Industry.
Final project report on grocery store management system..pdfKamal Acharya
In today’s fast-changing business environment, it’s extremely important to be able to respond to client needs in the most effective and timely manner. If your customers wish to see your business online and have instant access to your products or services.
Online Grocery Store is an e-commerce website, which retails various grocery products. This project allows viewing various products available enables registered users to purchase desired products instantly using Paytm, UPI payment processor (Instant Pay) and also can place order by using Cash on Delivery (Pay Later) option. This project provides an easy access to Administrators and Managers to view orders placed using Pay Later and Instant Pay options.
In order to develop an e-commerce website, a number of Technologies must be studied and understood. These include multi-tiered architecture, server and client-side scripting techniques, implementation technologies, programming language (such as PHP, HTML, CSS, JavaScript) and MySQL relational databases. This is a project with the objective to develop a basic website where a consumer is provided with a shopping cart website and also to know about the technologies used to develop such a website.
This document will discuss each of the underlying technologies to create and implement an e- commerce website.
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Dr.Costas Sachpazis
Terzaghi's soil bearing capacity theory, developed by Karl Terzaghi, is a fundamental principle in geotechnical engineering used to determine the bearing capacity of shallow foundations. This theory provides a method to calculate the ultimate bearing capacity of soil, which is the maximum load per unit area that the soil can support without undergoing shear failure. The Calculation HTML Code included.
Explore the innovative world of trenchless pipe repair with our comprehensive guide, "The Benefits and Techniques of Trenchless Pipe Repair." This document delves into the modern methods of repairing underground pipes without the need for extensive excavation, highlighting the numerous advantages and the latest techniques used in the industry.
Learn about the cost savings, reduced environmental impact, and minimal disruption associated with trenchless technology. Discover detailed explanations of popular techniques such as pipe bursting, cured-in-place pipe (CIPP) lining, and directional drilling. Understand how these methods can be applied to various types of infrastructure, from residential plumbing to large-scale municipal systems.
Ideal for homeowners, contractors, engineers, and anyone interested in modern plumbing solutions, this guide provides valuable insights into why trenchless pipe repair is becoming the preferred choice for pipe rehabilitation. Stay informed about the latest advancements and best practices in the field.
About
Indigenized remote control interface card suitable for MAFI system CCR equipment. Compatible for IDM8000 CCR. Backplane mounted serial and TCP/Ethernet communication module for CCR remote access. IDM 8000 CCR remote control on serial and TCP protocol.
• Remote control: Parallel or serial interface.
• Compatible with MAFI CCR system.
• Compatible with IDM8000 CCR.
• Compatible with Backplane mount serial communication.
• Compatible with commercial and Defence aviation CCR system.
• Remote control system for accessing CCR and allied system over serial or TCP.
• Indigenized local Support/presence in India.
• Easy in configuration using DIP switches.
Technical Specifications
Indigenized remote control interface card suitable for MAFI system CCR equipment. Compatible for IDM8000 CCR. Backplane mounted serial and TCP/Ethernet communication module for CCR remote access. IDM 8000 CCR remote control on serial and TCP protocol.
Key Features
Indigenized remote control interface card suitable for MAFI system CCR equipment. Compatible for IDM8000 CCR. Backplane mounted serial and TCP/Ethernet communication module for CCR remote access. IDM 8000 CCR remote control on serial and TCP protocol.
• Remote control: Parallel or serial interface
• Compatible with MAFI CCR system
• Copatiable with IDM8000 CCR
• Compatible with Backplane mount serial communication.
• Compatible with commercial and Defence aviation CCR system.
• Remote control system for accessing CCR and allied system over serial or TCP.
• Indigenized local Support/presence in India.
Application
• Remote control: Parallel or serial interface.
• Compatible with MAFI CCR system.
• Compatible with IDM8000 CCR.
• Compatible with Backplane mount serial communication.
• Compatible with commercial and Defence aviation CCR system.
• Remote control system for accessing CCR and allied system over serial or TCP.
• Indigenized local Support/presence in India.
• Easy in configuration using DIP switches.
1. BUSAN GEOJE FIXED LINK
• Subject : BDD
• Guided by : Shweta Mahajan Mam
• Name : Prajwal Deshmukh
2. INTRODUCTION :-
• The Busan –Geoje Fixed Link project is highly ambitious and
challenging infrastructure scheme to cut down journey time between
korea’s south coast city of Busan and the island of Geoje. With the help
of this project they manage to develop Geoje as tourist spot and save US
$300million by solving traffic related issues with the help ofthis
project. The link consist mainly three parts which are :
8.2 km long link, which includes immersed Tunnel of 48m depth
Athree-pylon cable-stayed bridge
Approach bridges with cable-stayed and road and rock tunnels on
islands
3. BRIDGE COMPONENTS
Total length : 8.2km
Lot 1 bridge :1.65 km (1.03 mi)
Between Geoje and Jeoislands, a 1.65 km (1.03 mi) bridge
includes a three-pylon cable-stay bridge. This bridge has two
mainspans of 230 meters (750 ft) with side spans of 106 meters
(348 ft). The pylons are 102 meters (335 ft) tall and there is 36
meters (118 ft) of clearance underneath the bridge.
Lot 2 bridge :1.87 km (1.16 mi)
between Jungjukand Jeoislands includes acable-stayed
bridge with a 475 m(1,558 ft) main span and 220 m(720 ft) side
spans. This bridge provides 52 meters (171 ft) of navigational
clearance and has two 156 m(512 ft) diamond-shapedpylons.
Lot 3 Immersed tube tunnel : 3.2km
The total length of the immersed tunnel is 4 km with two 170
metre long cut and cover sections at both ends.
5. Bridge :-
• There are five pylons in total for the two cable stayedbridges
which were built in deep sea conditions.
• Caisson foundations have been used for the piers and pylonsas
they eliminate the need for water excluding temporary works.
• The caissons are 33m high precast concrete cellular structures.
• The caisson foundations were fabricated at a casting yard onthe
mainland.
• The heaviest weighs 9,600t but the natural buoyancy of the open-
celled structures was utilised when they were taken out to sea.By
floating them, the weight could be shared between the water and
the crane so a smaller 3,000tfloating crane could beused.
6. DESIGNCONDITIONS:-
Hydraulicpressure :-
• The deepest foundation point of the tunnel is 47m below meansea
level.
• The water pressure imposes a significant load on the tunnel
elements, in particular in the transverse direction.
• Anumber of other effects add to the water pressure on the tunnel.
The total characteristic pressure can reach an equivalent of 58m
water pressure for certain conditions.
• An increase in the mean sea level of 0.4mhas been included due to
the global warming.
Wavesandcurrent:-
• Most waves at the project area are generated by winds including tropical
storms and typhoons. Waves generated by distant storms can also reach the
tunnel alignment from southerly directions:
• Anumber of typhoon pass through the project area every year.
7. • The deep water wave height generated by typhoon and swell wavescan
reach 9.2m for a 10,000 year returnperiod.
• Result from the numerical wave modelling show that the significant
wave height is about 0.4mand 0.8mat the most exposed location along
the tunnel alignment.
• Tidal range varies between 0.8mand 1.6m.
• The maximum near surface current spring tide is about0.8m/sec,
reducing with depth to 0.6m/sec at near bottom.
Earthquake :-
• The Busan metropolitan area is classified as a seismic zone-I based on
the result of seismic hazard analysis as specified in the KoreanStandard
Specification of Highway Bridges.
• Therefore, in this area the corresponding seismic zone coefficient fora
500 year return period is as---
Seismic Zone I
Zone Coefficient 0.11
8. • The risk coefficients representing the ratio of effective peak groundare—
Acceleration coefficient (A) =Seismic ZoneCoefficient × RiskCoefficient
Shipimpact :-
• The Southern coastline of Korea has a large volume of sea going
traffic including containerships, gas and oil tankers.
• Militarily it is an important and strategic area.
• Overall design of the Busan-Geoje Fixed Link Project considered
loadings from impact and sinking of a 50,000ton vessel sailing to a
neighbouring port.
Return Period(year) 500 1000
Risk Coefficient 1 1.4
9. CONSTRUCTION:-
Soilimprovement/ foundation :-
• Marine clay is forming the sea bed except in the near shoreareas
where bed rock outcrops.
• The thickness of the marine clay along most of the tunnel
alignment exceeds 20m.
• The major part of marine clay was “very soft to soft” and of“very
high plasticity” to “extremely high plasticity”.
• Tomake the foundation more robust, soil improvement with
cement deep mixing (CDM)and sand compaction piles (SCP) was
chosen.
10. CEMENT DEEP MIXING
(CDM)
• Where the tunnel is placed in a trench ( E3to E14) the clay was
strengthened with walls formed by contiguous columns ofmixed
cement and clay.
• The CDMcolumns were constructed using the wet mixing method,
where cement slurry is mixed with theclay.
• The mixing shafts were first drilled with the rotating blades intothe
soil to the desired depth. The cement slurry is injected in the
withdrawal stage, where the vertical speed of the machine and the
flow rate of the cement slurry were keptconstant.
• Four 1 mdiameter columns with overlaps of 10 cm form a 1.9 m
square column pattern. Toform continuous walls, these square
columns were placed with 10 cm overlaps in rows. The CDMwalls
reach depths of up to 60 mbelow sea level.
13. Joints
• Inconsideration of the large water depths, the
immersion and segment joints were both
required to have a double water barrier.
• The immersion joint was designed as the
conventional primary Omega seal and
secondary Ginagasket configuration.
14. CONSTRUCTION OF BRIDGE The 29 superstructure spans for the approach bridges are up to90 m long,
weigh up to 2,427 tonnes, composite with a 300-mm-thick concrete deck slab.
After prefabrication at Obi Bay,the spans were skidded to the waterside for
transport to the site.
The geology of the site generally comprises marine deposits (sandy andclayey
layers) overlying residual soil (formed by decomposing and weathering of the
bedrock in places) and bedrock. The nature of the bedrock was variable and
consists of Cretaceous mudstones, tuff, sandstones and granite.
The foundations for the Lot 1 bridge piers were cellular caissons founded on
weak or hard rock, located in up to approximately 30m of water.
Viaduct and anchor pier shafts were precast concrete, and the three 103-m-
high pylons are cast in situ with the legs providing a signature gentle curvein
transverse elevation. The lower pylon legs taper inward toward the caisson
foundations, reducing the plan area of the foundations.
15. PROJECT
COST
Total cost -1.8 billion
Govt. subsidy- 0.45 billion
By consortium-1.35 billion
lead contractor- Daewoo Engg.& Construction company
• Project has been designed for service life of 100 years.