SlideShare a Scribd company logo
1 of 52
MONOLITHIC
DOME
S.PADMASHRE
IIIrd YEAR
C SECTION
INTRODUCTION
Monolithic Dome is thin wall reinforced
concrete shell structure.
The structure provides safe shelter for the
people area with hurricanes,fires,bomb
blasts and earthquakes.
Building consist of : an outer airtight
form,polyuretane foam, reinforced concrete.
2
This technique is an effective
alternative to conventional methods.
A curve rotated about a central axis to
form a surface, creates a DOME.
A Monolithic dome is a structure cast in
a one piece form.
3
4
MONOLITHIC DOME
5
HISTORY
The igloo may be the earliest form of
monolithic dome. While it is constructed
of blocks of compressed snow, these
blocks melts and re-freeze to form a
strong, homogeneous structure.
The strength is due to the natural
strength of the arch and insulation is
due to the minimal surface area of the
spherical section.
6
Turtle Reams was built by first creating
mould of dirt in the desired shape of
the shell, an ellipsoidal section 73m
long,49m wide and 12m high.
The mould was then covered in a grid of
rebar, to provide strength and a layer
of concrete 100mm thick.
7
After the concrete was cured, the dirt
was excavated through the doorways,
leaving the roof standing in its place.
The floor was then poured to finish the
structure.
8
MATERIALS USED
FOOTING :
A monolithic dome starts as a concrete
ring foundation, reinforced with steel
rebars.
For smaller domes, an integrated floor
and ring foundation may be used.
Vertical steel bars embedded in the ring
beam foundation are later attached to the
steel reinforcing of the dome itself.
9
AIRFORM KITS :
The kit consisted of a 1220cm(40ft)
diameter form along with reinforced
steel anchors.
It is ordered in the shape of half
sphere with no custom windows or door
augmentations.
10
POLYURETHANE FOAM :
Sprayed on polyurethane foam
insulation was of type using a part
process in which Diaphenylmethane-
4,4-diisocynate was mixed with blended
polyolresin.
11
REINFORCING STEEL :
Steel in the foundation and slab was
16mm and grade 40 rebar.
Dome shell 13mm and 9.5mm grade 60
rebar was used.
12
CONCRETE :
Foundation and slab a standard sack
concrete foundation mix was used.
Concrete used in the dome shell was 9
sack per cubic yard mix. This was made
up of 385kg Portland Cemnt,992kg
sand,178kg(1cm) gravel,0.7kg plastic
fibres and 118ml of air entraining agent
in additional to that of water.
13
EXTERIOR :
Exterior coatings are an essential
aspect in the longevity to the Dome
Exterior.
Coatings serve as a UV shield to protect
the Airform and foam insulation as well
as achieve a desired appearance.
14
CONSTRUCTION OF DOME
Monolithic dome is a rounded building
structure typically made of concrete
and rigid steel rods.
It consist of an outer airtight form,
polyurethane foam insulation and
reinforced concrete.
15
The building process of monolithic domes
entailed :
Lay down the foundation of the dome ,
usually made of reinforced concrete.
An air form or fabric is inflated over the
foundation .
Polyurethane foam is then added to the
inside of the form in two layers of
(7.6cm)thick. 16
Special clips are affixed to the foam
interior, and rebar is installed.
Finally concrete is poured over the air
form, rebar, and foam supporters and
dome like shape emerges.
17
18
STEPS OF
CONSTRUCTION
STEP ONE : Ring Beam Foundation
Monolithic Dome starts as a concrete
ring foundation.
Continuous reinforcing bars are
embedded in the ring beam foundation.
The ring creates a solid base to
construct the dome.
19
Concrete ring foundation
20
STEP TWO : Inflate Air form
Made of tough, weather -impermeable
material.
The air form is inflated with dual
inflator fans.
It determines the final shape of the
dome.
21
STEP THREE : Polyurethane foam
Foam is applied in the interior to stiffen
the air form, and provide a secure surface to
which reinforcement bar is affixed.
It get hardens and creates a superior
insulation layer.
22
STEP FOUR : Steel Reinforcing
Steel reinforcing rebar is attached to
the foam using a specially engineered
layout of hoop and vertical steel bar.
Small domes need small diameter bars
with wide spacing.
Large domes require
larger bars with closer
spacing
23
STEP FIVE : Shotcrete
It is a special spray mix of concrete, applied
to the interior surface of the dome.
The steel rebar is embedded in the concrete
and when about 7cm
of shotcrete is
applied.
24
Concrete was applied by shotcrete
process over a period of four days. Each
day from(1.25cm to 3.8cm)of concrete
is applied.
Blowers were left on for 8 hours and
then shut off.
The airlock was then closed for 30days
to allow curing on the concrete.
25
To provide a smooth finished surface, a
layer of cement based plaster was alter
hand applied and finished.
This was primed with water based
acrylic latex and finished with acrylic
latex enamel.
26
PROFILE AND SHAPES
The profile of a dome determines the
size of its surface area or dome shell,
and the amount of surface area affects
the construction cost.
The surface area of hemisphere dome
is twice that of its floor area i.e.,
2*pi*radius*radius.
Most of the monolithic dome have an
oblate ellipse profile.
27
SHAPES
DOME
VARIATIONS/CONFIGURATIONS
a) Low profile spherical segment :
Most efficient shape.
Used for large domes.
28
b) Hemisphere :
Surface area is double the floor area.
Useful for high-volume storage buildings
and smaller structures ,such as homes.
29
c) High profile spherical segment :
Most volume for the least floor area.
Used for e water tanks, storage
buildings, homes etc.
30
d) Oblate ellipsoid :
Very efficient for single structures.
Wall have maximum vertical slope vs.
structure size
31
e) Prolate ellipsoid (Long axis
horizontal):
Elliptical base creates a very unique
space
f) Prolate ellipsoid (Long axis vertical)
:
It is very tall.
Useful for bulk storage and buried
building.
32
Horizontal
Vertical
Prolate ellipsoid 33
g) Torus :
Not as space -efficient as dome.
These are homes with a centre
courtyard or garden.
34
DOME PROFILES
Lower the profile the less expense.
Windows and doors on the second floor
can be augmented.
If the land is a premium, go up with
integrated stem wall.
35
Caterpillar combination Dome
profiles
36
MULTI-DOME
COMBINATION
The caterpillar is great design .
60 feet wide , 300-500 feet long.
Easy to build and allow for linear
functions.
37
DOME OPENINGS
If dome is not huge, then all kinds of
openings are possible.
Stresses are higher in domes having
diameter larger than 100 feet.
Build the openings for the uses.
38
STRESSES ACTING ON
DOMES
Generally, a spherical dome may be
imagining consisting of a number of
horizontal rings placed one over the
other.
The diameters of the successive rings
increase in the downward direction and
the equilibrium is maintained
independently of the rings above it.
39
The circle of each ring is called latitude
while the circle drawn through two
diametrically opposite points on a
horizontal diameter and the crown is
known as a meridian circle.
The entire meridian circles coverage at
the crown of the spherical dome.
40
Two types of stresses acting on the
domes are :
Meridian thrust (T) along the direction
of meridian
Hoop stress along latitudes
41
ADVANTAGES
Advantages of a monolithic dome fall into
three general categories :
a)Economy in construction :
Cost of a dome is less .
Streamlined construction process and
use of only four ingredients contribute
to the domes economy.
Require less maintenance.
42
b)Security :
Ability to survive tornadoes, hurricanes
and earthquakes.
Provides fire protection.
They are very good for circulation of air
and heat so they are also for very cold
climates.
43
c)Aesthetics and comfort :
Any structure appears bare and
unattractive when its first built and
unenhanced. But just as enhancement
can soften and beautify straight lines
and corners.
44
d)Rapid construction :
Most are prefabricated.
The prefab elements are relatively small
and light weight.
This makes easy to transport them to
the site.
45
DISADVANTAGES
Disadvantages of monolithic dome :
a)Engineering :
Only specially trained construction
crews. Using the modern techniques.
Wasted space in narrow corners.
Lack of seams.
46
b)Social :
Different appearance of the domes
decreases the appeal for their use as
private residences and the strange
appearance and design may run afoul of
neighbourhood building covenants.
Depending on the situation a large
variety of variations available from the
standard circular shape can avoid some
of these problems. 47
Building permits may be difficult to
obtain if local officials are not familiar
with the monolithic dome.
Resale of a monolithic dome home may
be difficult because of its
unconventional appearance.
48
CONCLUSION
Monolithic Dome building technique is an
effective alternative to conventional
methods.
Monolithic domes are disaster
-resistant, energy efficient and cost
effective.
Safest buildings that can be built and
can be designed for many uses.
Monolithic domes are designated as
tornado shelters. 49
REFERENCES
https://en.wikipedia.org/wiki/Monolithic
_dome
www.monolithic.org/round2it/technical-
journal-think-round
South D.B et.al 1990, “Economics and
the thin shell dome” , Concrete
International Reprint.
Nanette South M.S, engr. Str. & Mech ,
et.al “Finite Element Modelling of
Monolithic Dome structures”. 50
51
52

More Related Content

What's hot (20)

CONSTRUCTION OF DOMES
CONSTRUCTION OF DOMESCONSTRUCTION OF DOMES
CONSTRUCTION OF DOMES
 
Specifications of buildings
Specifications of buildingsSpecifications of buildings
Specifications of buildings
 
Low cost building components
Low cost building componentsLow cost building components
Low cost building components
 
High rise building construction
High rise building constructionHigh rise building construction
High rise building construction
 
Self compacting concrete (scc)
Self compacting concrete (scc)Self compacting concrete (scc)
Self compacting concrete (scc)
 
Basement construction report
Basement construction reportBasement construction report
Basement construction report
 
RCC Elements column, beam.
RCC Elements  column, beam.RCC Elements  column, beam.
RCC Elements column, beam.
 
Session 2 water proofing
Session 2 water proofingSession 2 water proofing
Session 2 water proofing
 
Retaining wall
Retaining wallRetaining wall
Retaining wall
 
Seismic retrofitting techniques & rehabilitation
Seismic retrofitting techniques & rehabilitationSeismic retrofitting techniques & rehabilitation
Seismic retrofitting techniques & rehabilitation
 
Mivan shuttering
Mivan shutteringMivan shuttering
Mivan shuttering
 
Diagrids the language of the modern day builder
Diagrids the language of the modern day builderDiagrids the language of the modern day builder
Diagrids the language of the modern day builder
 
Strawbale construction
Strawbale constructionStrawbale construction
Strawbale construction
 
Curing of concrete
Curing of concreteCuring of concrete
Curing of concrete
 
R.C.C. STAIRS
R.C.C. STAIRSR.C.C. STAIRS
R.C.C. STAIRS
 
Rcc jacketing
Rcc jacketingRcc jacketing
Rcc jacketing
 
Precast concrete construction
Precast concrete constructionPrecast concrete construction
Precast concrete construction
 
Pile foundation
Pile foundationPile foundation
Pile foundation
 
Prestressed construction
Prestressed constructionPrestressed construction
Prestressed construction
 
High rise building
High rise buildingHigh rise building
High rise building
 

Similar to Monolithic dome ppt

O2 Arena Booklet
O2 Arena BookletO2 Arena Booklet
O2 Arena Bookleteileen_0692
 
Precast Concrete Structure: Architectural examples
Precast Concrete Structure: Architectural examplesPrecast Concrete Structure: Architectural examples
Precast Concrete Structure: Architectural examplesSayedaAmrin
 
Advanced Concrete Technic Erbil Polytechnic University
Advanced Concrete Technic Erbil Polytechnic UniversityAdvanced Concrete Technic Erbil Polytechnic University
Advanced Concrete Technic Erbil Polytechnic UniversityBahzad5
 
Spherical or geodesic dome
Spherical or geodesic domeSpherical or geodesic dome
Spherical or geodesic domePalakGarg52
 
Ct3 presentation slides
Ct3 presentation slides Ct3 presentation slides
Ct3 presentation slides lohwenjun
 
Domes Basics and It's Future from it's origin
Domes Basics and It's Future from it's originDomes Basics and It's Future from it's origin
Domes Basics and It's Future from it's originabhinavmj
 
KISHORE SEMINAR (2).pptx
KISHORE SEMINAR (2).pptxKISHORE SEMINAR (2).pptx
KISHORE SEMINAR (2).pptxBHARISH16
 
FERROCRETE - MATERIAL AND CONSTRUCTION METHODS
FERROCRETE - MATERIAL AND CONSTRUCTION METHODSFERROCRETE - MATERIAL AND CONSTRUCTION METHODS
FERROCRETE - MATERIAL AND CONSTRUCTION METHODSjagrutib22
 
A technical seminar bubble deck slab.pptx
A technical seminar bubble deck slab.pptxA technical seminar bubble deck slab.pptx
A technical seminar bubble deck slab.pptxhkhemanth564
 
A technical seminar bubble deck slab.pptx
A technical seminar bubble deck slab.pptxA technical seminar bubble deck slab.pptx
A technical seminar bubble deck slab.pptxhkhemanth564
 

Similar to Monolithic dome ppt (20)

O2 booklet
O2 bookletO2 booklet
O2 booklet
 
O2 Arena Booklet
O2 Arena BookletO2 Arena Booklet
O2 Arena Booklet
 
O2 booklet
O2 bookletO2 booklet
O2 booklet
 
advanced construction
advanced constructionadvanced construction
advanced construction
 
Finishingworks.pptx
Finishingworks.pptxFinishingworks.pptx
Finishingworks.pptx
 
burj khalifa
burj khalifaburj khalifa
burj khalifa
 
Surface active systems
Surface active systems Surface active systems
Surface active systems
 
Precast Concrete Structure: Architectural examples
Precast Concrete Structure: Architectural examplesPrecast Concrete Structure: Architectural examples
Precast Concrete Structure: Architectural examples
 
Advanced Concrete Technic Erbil Polytechnic University
Advanced Concrete Technic Erbil Polytechnic UniversityAdvanced Concrete Technic Erbil Polytechnic University
Advanced Concrete Technic Erbil Polytechnic University
 
Special Concrete - Concrete Technology
Special Concrete - Concrete TechnologySpecial Concrete - Concrete Technology
Special Concrete - Concrete Technology
 
Spherical or geodesic dome
Spherical or geodesic domeSpherical or geodesic dome
Spherical or geodesic dome
 
material ppt
material pptmaterial ppt
material ppt
 
Ct3 presentation slides
Ct3 presentation slides Ct3 presentation slides
Ct3 presentation slides
 
Latest ct3
Latest ct3Latest ct3
Latest ct3
 
Domes Basics and It's Future from it's origin
Domes Basics and It's Future from it's originDomes Basics and It's Future from it's origin
Domes Basics and It's Future from it's origin
 
KISHORE SEMINAR (2).pptx
KISHORE SEMINAR (2).pptxKISHORE SEMINAR (2).pptx
KISHORE SEMINAR (2).pptx
 
Concrete block
Concrete blockConcrete block
Concrete block
 
FERROCRETE - MATERIAL AND CONSTRUCTION METHODS
FERROCRETE - MATERIAL AND CONSTRUCTION METHODSFERROCRETE - MATERIAL AND CONSTRUCTION METHODS
FERROCRETE - MATERIAL AND CONSTRUCTION METHODS
 
A technical seminar bubble deck slab.pptx
A technical seminar bubble deck slab.pptxA technical seminar bubble deck slab.pptx
A technical seminar bubble deck slab.pptx
 
A technical seminar bubble deck slab.pptx
A technical seminar bubble deck slab.pptxA technical seminar bubble deck slab.pptx
A technical seminar bubble deck slab.pptx
 

Recently uploaded

Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAbhinavSharma374939
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 

Recently uploaded (20)

Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog Converter
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 

Monolithic dome ppt

  • 2. INTRODUCTION Monolithic Dome is thin wall reinforced concrete shell structure. The structure provides safe shelter for the people area with hurricanes,fires,bomb blasts and earthquakes. Building consist of : an outer airtight form,polyuretane foam, reinforced concrete. 2
  • 3. This technique is an effective alternative to conventional methods. A curve rotated about a central axis to form a surface, creates a DOME. A Monolithic dome is a structure cast in a one piece form. 3
  • 4. 4
  • 6. HISTORY The igloo may be the earliest form of monolithic dome. While it is constructed of blocks of compressed snow, these blocks melts and re-freeze to form a strong, homogeneous structure. The strength is due to the natural strength of the arch and insulation is due to the minimal surface area of the spherical section. 6
  • 7. Turtle Reams was built by first creating mould of dirt in the desired shape of the shell, an ellipsoidal section 73m long,49m wide and 12m high. The mould was then covered in a grid of rebar, to provide strength and a layer of concrete 100mm thick. 7
  • 8. After the concrete was cured, the dirt was excavated through the doorways, leaving the roof standing in its place. The floor was then poured to finish the structure. 8
  • 9. MATERIALS USED FOOTING : A monolithic dome starts as a concrete ring foundation, reinforced with steel rebars. For smaller domes, an integrated floor and ring foundation may be used. Vertical steel bars embedded in the ring beam foundation are later attached to the steel reinforcing of the dome itself. 9
  • 10. AIRFORM KITS : The kit consisted of a 1220cm(40ft) diameter form along with reinforced steel anchors. It is ordered in the shape of half sphere with no custom windows or door augmentations. 10
  • 11. POLYURETHANE FOAM : Sprayed on polyurethane foam insulation was of type using a part process in which Diaphenylmethane- 4,4-diisocynate was mixed with blended polyolresin. 11
  • 12. REINFORCING STEEL : Steel in the foundation and slab was 16mm and grade 40 rebar. Dome shell 13mm and 9.5mm grade 60 rebar was used. 12
  • 13. CONCRETE : Foundation and slab a standard sack concrete foundation mix was used. Concrete used in the dome shell was 9 sack per cubic yard mix. This was made up of 385kg Portland Cemnt,992kg sand,178kg(1cm) gravel,0.7kg plastic fibres and 118ml of air entraining agent in additional to that of water. 13
  • 14. EXTERIOR : Exterior coatings are an essential aspect in the longevity to the Dome Exterior. Coatings serve as a UV shield to protect the Airform and foam insulation as well as achieve a desired appearance. 14
  • 15. CONSTRUCTION OF DOME Monolithic dome is a rounded building structure typically made of concrete and rigid steel rods. It consist of an outer airtight form, polyurethane foam insulation and reinforced concrete. 15
  • 16. The building process of monolithic domes entailed : Lay down the foundation of the dome , usually made of reinforced concrete. An air form or fabric is inflated over the foundation . Polyurethane foam is then added to the inside of the form in two layers of (7.6cm)thick. 16
  • 17. Special clips are affixed to the foam interior, and rebar is installed. Finally concrete is poured over the air form, rebar, and foam supporters and dome like shape emerges. 17
  • 18. 18
  • 19. STEPS OF CONSTRUCTION STEP ONE : Ring Beam Foundation Monolithic Dome starts as a concrete ring foundation. Continuous reinforcing bars are embedded in the ring beam foundation. The ring creates a solid base to construct the dome. 19
  • 21. STEP TWO : Inflate Air form Made of tough, weather -impermeable material. The air form is inflated with dual inflator fans. It determines the final shape of the dome. 21
  • 22. STEP THREE : Polyurethane foam Foam is applied in the interior to stiffen the air form, and provide a secure surface to which reinforcement bar is affixed. It get hardens and creates a superior insulation layer. 22
  • 23. STEP FOUR : Steel Reinforcing Steel reinforcing rebar is attached to the foam using a specially engineered layout of hoop and vertical steel bar. Small domes need small diameter bars with wide spacing. Large domes require larger bars with closer spacing 23
  • 24. STEP FIVE : Shotcrete It is a special spray mix of concrete, applied to the interior surface of the dome. The steel rebar is embedded in the concrete and when about 7cm of shotcrete is applied. 24
  • 25. Concrete was applied by shotcrete process over a period of four days. Each day from(1.25cm to 3.8cm)of concrete is applied. Blowers were left on for 8 hours and then shut off. The airlock was then closed for 30days to allow curing on the concrete. 25
  • 26. To provide a smooth finished surface, a layer of cement based plaster was alter hand applied and finished. This was primed with water based acrylic latex and finished with acrylic latex enamel. 26
  • 27. PROFILE AND SHAPES The profile of a dome determines the size of its surface area or dome shell, and the amount of surface area affects the construction cost. The surface area of hemisphere dome is twice that of its floor area i.e., 2*pi*radius*radius. Most of the monolithic dome have an oblate ellipse profile. 27
  • 28. SHAPES DOME VARIATIONS/CONFIGURATIONS a) Low profile spherical segment : Most efficient shape. Used for large domes. 28
  • 29. b) Hemisphere : Surface area is double the floor area. Useful for high-volume storage buildings and smaller structures ,such as homes. 29
  • 30. c) High profile spherical segment : Most volume for the least floor area. Used for e water tanks, storage buildings, homes etc. 30
  • 31. d) Oblate ellipsoid : Very efficient for single structures. Wall have maximum vertical slope vs. structure size 31
  • 32. e) Prolate ellipsoid (Long axis horizontal): Elliptical base creates a very unique space f) Prolate ellipsoid (Long axis vertical) : It is very tall. Useful for bulk storage and buried building. 32
  • 34. g) Torus : Not as space -efficient as dome. These are homes with a centre courtyard or garden. 34
  • 35. DOME PROFILES Lower the profile the less expense. Windows and doors on the second floor can be augmented. If the land is a premium, go up with integrated stem wall. 35
  • 37. MULTI-DOME COMBINATION The caterpillar is great design . 60 feet wide , 300-500 feet long. Easy to build and allow for linear functions. 37
  • 38. DOME OPENINGS If dome is not huge, then all kinds of openings are possible. Stresses are higher in domes having diameter larger than 100 feet. Build the openings for the uses. 38
  • 39. STRESSES ACTING ON DOMES Generally, a spherical dome may be imagining consisting of a number of horizontal rings placed one over the other. The diameters of the successive rings increase in the downward direction and the equilibrium is maintained independently of the rings above it. 39
  • 40. The circle of each ring is called latitude while the circle drawn through two diametrically opposite points on a horizontal diameter and the crown is known as a meridian circle. The entire meridian circles coverage at the crown of the spherical dome. 40
  • 41. Two types of stresses acting on the domes are : Meridian thrust (T) along the direction of meridian Hoop stress along latitudes 41
  • 42. ADVANTAGES Advantages of a monolithic dome fall into three general categories : a)Economy in construction : Cost of a dome is less . Streamlined construction process and use of only four ingredients contribute to the domes economy. Require less maintenance. 42
  • 43. b)Security : Ability to survive tornadoes, hurricanes and earthquakes. Provides fire protection. They are very good for circulation of air and heat so they are also for very cold climates. 43
  • 44. c)Aesthetics and comfort : Any structure appears bare and unattractive when its first built and unenhanced. But just as enhancement can soften and beautify straight lines and corners. 44
  • 45. d)Rapid construction : Most are prefabricated. The prefab elements are relatively small and light weight. This makes easy to transport them to the site. 45
  • 46. DISADVANTAGES Disadvantages of monolithic dome : a)Engineering : Only specially trained construction crews. Using the modern techniques. Wasted space in narrow corners. Lack of seams. 46
  • 47. b)Social : Different appearance of the domes decreases the appeal for their use as private residences and the strange appearance and design may run afoul of neighbourhood building covenants. Depending on the situation a large variety of variations available from the standard circular shape can avoid some of these problems. 47
  • 48. Building permits may be difficult to obtain if local officials are not familiar with the monolithic dome. Resale of a monolithic dome home may be difficult because of its unconventional appearance. 48
  • 49. CONCLUSION Monolithic Dome building technique is an effective alternative to conventional methods. Monolithic domes are disaster -resistant, energy efficient and cost effective. Safest buildings that can be built and can be designed for many uses. Monolithic domes are designated as tornado shelters. 49
  • 50. REFERENCES https://en.wikipedia.org/wiki/Monolithic _dome www.monolithic.org/round2it/technical- journal-think-round South D.B et.al 1990, “Economics and the thin shell dome” , Concrete International Reprint. Nanette South M.S, engr. Str. & Mech , et.al “Finite Element Modelling of Monolithic Dome structures”. 50
  • 51. 51
  • 52. 52