SlideShare a Scribd company logo
1
Project Stakeholder Management
Chapter 13
2
 13.1 Identify Stakeholder
 13.2 Plan Stakeholder Management
 13.3 Manage Stakeholder Engagement
 13.4 Control Stakeholder Engagement
KEY TERMS
3
• 13.1 Identify Stakeholders (Initiating) identifying the people,
groups, or organizations that could impact or be impacted by
a decision, activity, or outcome of the project.
• 13.2 Plan Stakeholder Management (Planning) developing
appropriate management strategies to effectively engage
stakeholders throughout the project life cycle.
• 13.3 Manage Stakeholder Engagement (Executing)
communicating and working with stakeholders to meet their
needs/expectations.
• 13.4 Control Stakeholder Engagement (Monitoring & Control)
monitoring overall project stakeholder relationships
And adjusting strategies and plans for engaging
stakeholders.
4
13.1 Identify Stakeholders
5
13.1 Identify Stakeholders
• Identifying the people, groups, or organizations
that could impact or be impacted by a decision,
activity, or outcome of the project.
6
7
13.1 Identify Stakeholders Inputs
1. Project Charter .
2. Procurement Documents
3. EEF
4. OPA
8
13.1 Identify Stakeholders T & T
1. Stakeholder Analysis: gathering & analyzing
information to determine stakeholder in 3 steps:
 Identify all potential stakeholders & relevant
information (roles, departments, interests,
knowledge levels, expectations & influence
levels).
 Identify potential impact or support each
stakeholder could generate (power-interest)
 Assess how key stakeholders are likely to react or
respond to various situations.
9
Stakeholder Analysis
classification models used for stakeholders analysis
• Power/interest grid
based on:
level of authority (power)
level or concern (interest)
• Power/influence grid
based on
level of authority (power)
active involvement (influence)
• Influence/impact grid
based on
active involvement (influence)
ability to effect changes (impact)
10
• Salience model based on
power (ability to impose their will),
urgency (need for immediate attention)
legitimacy (their involvement is appropriate).
Power Urgency
Legitimacy
1
2
3
4
5
6
7
11
13.1 Identify Stakeholders T & T
2. Expert Judgment: groups or individuals specialized in
certain areas such:
 Senior management
 Subject matter experts
 Industry groups and consultants
 Professional and technical associations
 Project managers with experience in similar
projects
 Identified stakeholders.
3. Meetings
12
13.1 Identify Stakeholders Outputs
Stakeholder
Register
• Identification Information: name,
organizational position, location, role
in project, … etc.
• Assessment Information: major
requirements , expectation, potential
influence in project … etc.
• Stakeholder Classification:
Internal/External, supporter, neutral,
resistor, … etc.
13
14
13.2 Plan Stakeholders
Management
15
13.2 Plan Stakeholders Management
• Developing appropriate management strategies to
effectively engage stakeholders throughout the
project life cycle.
16
17
Analytical Techniques, engagement levels:
The engagement level of the stakeholders
Unaware Unaware of project and potential impacts.
Resistant
Aware of project and potential impacts and
resistant to change.
Neutral
Aware of project yet neither supportive nor
resistant.
Supportive
Aware of project & impacts and supportive to
change.
Leading
Aware of project & impacts and actively engaged
in ensuring the project is a success.
18
C : Current engagement
D : Desired engagement
• Stakeholders Engagement Assessment Matrix
• Through this analytical process, gaps between the current
and desired engagement levels can be identified.
• Actions and communications required to close these gaps
can be identified by the project team using expert judgment.
19
13.2 Plan Stakeholder Management Inputs
1. Project Management Plan .
2. Stakeholder Register
3. EEF
4. OPA
13.2 Plan Stakeholder Management Outputs
1. Stakeholder Management Plan
2. Project Documents Updates
20
13.3 Manage Stakeholders
Engagement
21
13.3 Manage Stakeholders Engagement
• Communicating and working with stakeholders
to meet their needs/expectations.
• The key benefit is to allow the project manager to
increase support and minimize resistance from
stakeholders.
22
23
13.3 Manage Stakeholder Engagement Inputs
1. Stakeholder Management Plan.
2. Communication Management Plan
3. Change Log
4. OPA
13.3 Manage Stakeholder Engagement Outputs
1. Issue Log.
2. Change Requests
3. Project Management Plan Updates
4. Project Document Updates
5. OPA Updates
24
13.3 Manage Stakeholder Engagement T &T
1. Communications Methods
Interactive communication . Push & Pull communication
2. Interpersonal Skills
 Building trust
 Resolving conflict
 Active listening
 Overcoming resistance to change
3. Management Skills
 Influence people to support project
 Negotiate agreements
 Modify organizational behavior
25
13.4 Control Stakeholders
Engagement
26
13.3 Control Stakeholders Engagement
• monitoring overall project stakeholder relationships And
adjusting strategies and plans for engaging stakeholders.
• The key benefit is to maintain or increase the efficiency
and effectiveness of stakeholder
engagement activities.
27
28
13.4 Control Stakeholder Engagement Inputs
1. Project Management Plan
2. Issue Log
3. Work Performance Data
4. Project Documents
• Project schedule,
• Stakeholder register
• Issue log
• Change log
• Project communications.
29
13.4 Control Stakeholder Engagement Outputs
1. Work Performance Information
2. Change Requests
3. Project Management Plan Updates
4. Project Document Updates
5. OPA Updates
30
Questions
l. When do stakeholders have the MOST influence on a
project?
A. At the beginning of the project
B. In the middle of the project
C. At the end of the project
D. Throughout the project
31
Questions
l. When do stakeholders have the MOST influence on a
project?
A. At the beginning of the project
B. In the middle of the project
C. At the end of the project
D. Throughout the project
Answer : A
32
Questions
2. Stakeholders can be identified in which project
management process groups?
A. Initiating, planning, executing, and monitoring and
controlling.
B. Initiating and planning.
C. Planning and monitoring and controlling.
D. Monitoring and controlling and closing.
33
Questions
2. Stakeholders can be identified in which project
management process groups?
A. Initiating, planning, executing, and monitoring and
controlling.
B. Initiating and planning.
C. Planning and monitoring and controlling.
D. Monitoring and controlling and closing.
Answer : A .
The early you identify stakeholder. The less conflicts you get.
34
Questions
3. A particular stakeholder has a reputation for requesting many
changes on projects. What is the BEST approach a project
manager can take at the beginning of the project to manage this
situation?
A. Say "No" to the stakeholder a few times to dissuade him from
submitting more changes.
B. Get the stakeholder involved in the project as early as possible.
C. Talk to the stakeholder's boss to find ways of directing the stakeholder's
activities to another project.
D. Ask that the stakeholder not be included in the stakeholder listing.
35
Questions
3. A particular stakeholder has a reputation for requesting many
changes on projects. What is the BEST approach a project
manager can take at the beginning of the project to manage this
situation?
A. Say "No" to the stakeholder a few times to dissuade him from
submitting more changes.
B. Get the stakeholder involved in the project as early as possible.
C. Talk to the stakeholder's boss to find ways of directing the stakeholder's
activities to another project.
D. Ask that the stakeholder not be included in the stakeholder listing.
Answer : B
36
Questions
4. A project manager wants to more extensively involve the
stakeholders on the project. Which of the following would be
the BEST way to accomplish this?
A. Have the stakeholders periodically review the list of project
requirements.
B. Invite the stakeholders to attend project status meetings.
C. Send status reports to the stakeholders.
D. Update the stakeholders on the status of all project
changes.
37
Questions
4. A project manager wants to more extensively involve the
stakeholders on the project. Which of the following would be
the BEST way to accomplish this?
A. Have the stakeholders periodically review the list of project
requirements.
B. Invite the stakeholders to attend project status meetings.
C. Send status reports to the stakeholders.
D. Update the stakeholders on the status of all project
changes.
Answer : A
38
Questions
5. A stakeholders engagement assessment matrix can be
used to identify:
A. Communication gaps.
B. Additional stakeholders.
C. Key relationships between stakeholders.
D. Skill levels of stakeholders.
39
Questions
5. A stakeholders engagement assessment matrix can be
used to identify:
A. Communication gaps.
B. Additional stakeholders.
C. Key relationships between stakeholders.
D. Skill levels of stakeholders.
Answer : A
40
Questions
6. The role of each stakeholder is determined by:
A. The stakeholder and the sponsor.
B. The project manager and the sponsor.
C. The team and the project manager.
D. The project manager and the stakeholder.
41
Questions
6. The role of each stakeholder is determined by:
A. The stakeholder and the sponsor.
B. The project manager and the sponsor.
C. The team and the project manager.
D. The project manager and the stakeholder.
Answer : D
stakeholders have input into what they will be contributing to the project.
42
Questions
7. The project manager is trying to recall a stakeholder's
preferred communication method. Where can she find that
information?
A. RACI chart
B. Stakeholders engagement assessment matrix
C. Stakeholder management plan
D. Human resource management plan
43
Questions
7. The project manager is trying to recall a stakeholder's
preferred communication method. Where can she find that
information?
A. RACI chart
B. Stakeholders engagement assessment matrix
C. Stakeholder management plan
D. Human resource management plan
Answer : C
44
Questions
8. The degree to which a particular stakeholder may be able
to positively or negatively affect a project is his or her:
A. Level of engagement.
B. Level of interest.
C. Level of commitment.
D. Level of influence.
45
Questions
8. The degree to which a particular stakeholder may be able
to positively or negatively affect a project is his or her:
A. Level of engagement.
B. Level of interest.
C. Level of commitment.
D. Level of influence.
Answer : D
46
Questions
9. The stakeholder register is an input to which of the
following processes?
A. Plan Risk Management and Collect Requirements
B. Perform Integrated Change Control and Plan
Communications Management
C. Plan Quality Management and Perform Quality Assurance
D. Identify Risks and Develop Project Charter
47
Questions
9. The stakeholder register is an input to which of the
following processes?
A. Plan Risk Management and Collect Requirements
B. Perform Integrated Change Control and Plan
Communications Management
C. Plan Quality Management and Perform Quality Assurance
D. Identify Risks and Develop Project Charter
Answer : A
the stakeholder register is an input to :
Collect Requirements / Plan Quality Management / Plan Communications
Management / Plan Risk / Management / and Identify Risks.
48
Questions
10. The key objective of stakeholder management is:
A. Communication.
B. Coordination.
C. Satisfaction.
D. Relationships.
49
Questions
10. The key objective of stakeholder management is:
A. Communication.
B. Coordination.
C. Satisfaction.
D. Relationships.
Answer : C

More Related Content

What's hot

Project communication management
Project communication  managementProject communication  management
Project communication management
youness jabbar
 
Project Management
Project ManagementProject Management
Project Management
ajithsrc
 
Project Stakeholder Management - PMBOK6
Project Stakeholder Management - PMBOK6Project Stakeholder Management - PMBOK6
Project Stakeholder Management - PMBOK6
Agus Suhanto
 
11. Project Communication Management
11. Project Communication Management11. Project Communication Management
11. Project Communication Management
BhuWan Khadka
 
PMP Lecture 4: Project Integration Management
PMP Lecture 4: Project Integration ManagementPMP Lecture 4: Project Integration Management
PMP Lecture 4: Project Integration Management
Mohamed Loey
 
5 phases of project management
5 phases of project management5 phases of project management
5 phases of project management
Jared C. Powell
 
Integrated Project Management
Integrated Project ManagementIntegrated Project Management
Integrated Project Management
Inam Khosa
 
Project Time Management - PMBOK 5th Edition
Project  Time Management - PMBOK 5th EditionProject  Time Management - PMBOK 5th Edition
Project Time Management - PMBOK 5th Edition
pankajsh10
 
PMP_Project Communication Management
PMP_Project Communication ManagementPMP_Project Communication Management
PMP_Project Communication Management
Hisham Haridy MBA, PMP®, RMP®, SP®
 
Pmp4
Pmp4Pmp4
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project Management
Kris Kimmerle
 
Project integration management
Project integration managementProject integration management
Project integration management
Prabudh Dhingra
 
Project charter
Project charterProject charter
Project Management
Project ManagementProject Management
Project Management
Mark Roman
 
13.2 Plan Stakeholder Engagement
13.2 Plan Stakeholder Engagement13.2 Plan Stakeholder Engagement
13.2 Plan Stakeholder Engagement
DavidMcLachlan1
 
Chap 5 Estimating Project Times
Chap 5 Estimating Project TimesChap 5 Estimating Project Times
Chap 5 Estimating Project Times
project management
 
The Project Management Process - Week 6 Leadership
The Project Management Process - Week 6   LeadershipThe Project Management Process - Week 6   Leadership
The Project Management Process - Week 6 Leadership
Craig Brown
 
Pmp quality chapter 8
Pmp quality chapter 8Pmp quality chapter 8
Pmp quality chapter 8
Ahmed Elshaboury,PMP,LEED GA
 
Project communication management
Project communication managementProject communication management
Project communication management
Dikshant Ghimire
 
01 pmp introduct to project management exam
01 pmp introduct to project management exam01 pmp introduct to project management exam
01 pmp introduct to project management exam
Jamil Faraj , PMP
 

What's hot (20)

Project communication management
Project communication  managementProject communication  management
Project communication management
 
Project Management
Project ManagementProject Management
Project Management
 
Project Stakeholder Management - PMBOK6
Project Stakeholder Management - PMBOK6Project Stakeholder Management - PMBOK6
Project Stakeholder Management - PMBOK6
 
11. Project Communication Management
11. Project Communication Management11. Project Communication Management
11. Project Communication Management
 
PMP Lecture 4: Project Integration Management
PMP Lecture 4: Project Integration ManagementPMP Lecture 4: Project Integration Management
PMP Lecture 4: Project Integration Management
 
5 phases of project management
5 phases of project management5 phases of project management
5 phases of project management
 
Integrated Project Management
Integrated Project ManagementIntegrated Project Management
Integrated Project Management
 
Project Time Management - PMBOK 5th Edition
Project  Time Management - PMBOK 5th EditionProject  Time Management - PMBOK 5th Edition
Project Time Management - PMBOK 5th Edition
 
PMP_Project Communication Management
PMP_Project Communication ManagementPMP_Project Communication Management
PMP_Project Communication Management
 
Pmp4
Pmp4Pmp4
Pmp4
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project Management
 
Project integration management
Project integration managementProject integration management
Project integration management
 
Project charter
Project charterProject charter
Project charter
 
Project Management
Project ManagementProject Management
Project Management
 
13.2 Plan Stakeholder Engagement
13.2 Plan Stakeholder Engagement13.2 Plan Stakeholder Engagement
13.2 Plan Stakeholder Engagement
 
Chap 5 Estimating Project Times
Chap 5 Estimating Project TimesChap 5 Estimating Project Times
Chap 5 Estimating Project Times
 
The Project Management Process - Week 6 Leadership
The Project Management Process - Week 6   LeadershipThe Project Management Process - Week 6   Leadership
The Project Management Process - Week 6 Leadership
 
Pmp quality chapter 8
Pmp quality chapter 8Pmp quality chapter 8
Pmp quality chapter 8
 
Project communication management
Project communication managementProject communication management
Project communication management
 
01 pmp introduct to project management exam
01 pmp introduct to project management exam01 pmp introduct to project management exam
01 pmp introduct to project management exam
 

Similar to Pmp stakeholder chapter 13

10. Stakeholder Management
10. Stakeholder Management10. Stakeholder Management
10. Stakeholder Management
Sanjay Rajpoot
 
Stakeholder Management Knowledge Area
Stakeholder Management Knowledge AreaStakeholder Management Knowledge Area
Stakeholder Management Knowledge Area
Joshua Render
 
Stakeholder Managment - Presentation.pptx
Stakeholder Managment - Presentation.pptxStakeholder Managment - Presentation.pptx
Stakeholder Managment - Presentation.pptx
UmairZaman13
 
Chapter 13
Chapter 13Chapter 13
Trends in stakeholder management shruti prashant
Trends in stakeholder management shruti prashantTrends in stakeholder management shruti prashant
Trends in stakeholder management shruti prashantGuneet Singh
 
10. PMP Project Stakeholder Management.ppt
10. PMP Project Stakeholder Management.ppt10. PMP Project Stakeholder Management.ppt
10. PMP Project Stakeholder Management.ppt
ItcHcm1
 
Stakeholder analysis-toolkit-v3
Stakeholder analysis-toolkit-v3Stakeholder analysis-toolkit-v3
Stakeholder analysis-toolkit-v3
andre rahman
 
Stakeholder management In Construction Industry
Stakeholder management In  Construction IndustryStakeholder management In  Construction Industry
Stakeholder management In Construction Industry
Girish Singh
 
Project stakeholder management by Nelson Mandela Anyomi
Project stakeholder management by Nelson Mandela AnyomiProject stakeholder management by Nelson Mandela Anyomi
Project stakeholder management by Nelson Mandela Anyomi
Nelson Mandela Anyomi
 
PMP Certification Training Course Part-64
PMP Certification Training Course Part-64PMP Certification Training Course Part-64
PMP Certification Training Course Part-64
Skillogic Solutions
 
15_Ch13.pptx
15_Ch13.pptx15_Ch13.pptx
15_Ch13.pptx
suhas80
 
CAPM Week 5 Chapter 13
CAPM Week 5 Chapter 13CAPM Week 5 Chapter 13
CAPM Week 5 Chapter 13
Muzette Charles, PMP
 
Create Your End User Adoption Strategy
Create Your End User Adoption StrategyCreate Your End User Adoption Strategy
Create Your End User Adoption Strategy
Erica Toelle
 
13.3 Manage Stakeholder Engagement
13.3 Manage Stakeholder Engagement13.3 Manage Stakeholder Engagement
13.3 Manage Stakeholder Engagement
DavidMcLachlan1
 
Chapters 13 & 14Chapter 13Q1. You are the project manager of.docx
Chapters 13 & 14Chapter 13Q1. You are the project manager of.docxChapters 13 & 14Chapter 13Q1. You are the project manager of.docx
Chapters 13 & 14Chapter 13Q1. You are the project manager of.docx
christinemaritza
 
Project initiation topic 2.8_stakeholder management
Project initiation topic 2.8_stakeholder managementProject initiation topic 2.8_stakeholder management
Project initiation topic 2.8_stakeholder management
RudreshSamant
 
Project stakeholder Management PMBOK Sixth
Project stakeholder Management PMBOK SixthProject stakeholder Management PMBOK Sixth
Project stakeholder Management PMBOK Sixth
Dr. Pankaj Sharma PgMP,PMP,PMI-ACP, LSSMBB
 
Understanding ngo dynamics
Understanding ngo dynamicsUnderstanding ngo dynamics
Understanding ngo dynamics
Jamiu Akangbe
 
Project Stakeholder Management [read-only] [compatibility mode]
Project Stakeholder Management [read-only] [compatibility mode]Project Stakeholder Management [read-only] [compatibility mode]
Project Stakeholder Management [read-only] [compatibility mode]
Astute Trainers and Consultants
 

Similar to Pmp stakeholder chapter 13 (20)

10. Stakeholder Management
10. Stakeholder Management10. Stakeholder Management
10. Stakeholder Management
 
Stakeholder management qb
Stakeholder management qbStakeholder management qb
Stakeholder management qb
 
Stakeholder Management Knowledge Area
Stakeholder Management Knowledge AreaStakeholder Management Knowledge Area
Stakeholder Management Knowledge Area
 
Stakeholder Managment - Presentation.pptx
Stakeholder Managment - Presentation.pptxStakeholder Managment - Presentation.pptx
Stakeholder Managment - Presentation.pptx
 
Chapter 13
Chapter 13Chapter 13
Chapter 13
 
Trends in stakeholder management shruti prashant
Trends in stakeholder management shruti prashantTrends in stakeholder management shruti prashant
Trends in stakeholder management shruti prashant
 
10. PMP Project Stakeholder Management.ppt
10. PMP Project Stakeholder Management.ppt10. PMP Project Stakeholder Management.ppt
10. PMP Project Stakeholder Management.ppt
 
Stakeholder analysis-toolkit-v3
Stakeholder analysis-toolkit-v3Stakeholder analysis-toolkit-v3
Stakeholder analysis-toolkit-v3
 
Stakeholder management In Construction Industry
Stakeholder management In  Construction IndustryStakeholder management In  Construction Industry
Stakeholder management In Construction Industry
 
Project stakeholder management by Nelson Mandela Anyomi
Project stakeholder management by Nelson Mandela AnyomiProject stakeholder management by Nelson Mandela Anyomi
Project stakeholder management by Nelson Mandela Anyomi
 
PMP Certification Training Course Part-64
PMP Certification Training Course Part-64PMP Certification Training Course Part-64
PMP Certification Training Course Part-64
 
15_Ch13.pptx
15_Ch13.pptx15_Ch13.pptx
15_Ch13.pptx
 
CAPM Week 5 Chapter 13
CAPM Week 5 Chapter 13CAPM Week 5 Chapter 13
CAPM Week 5 Chapter 13
 
Create Your End User Adoption Strategy
Create Your End User Adoption StrategyCreate Your End User Adoption Strategy
Create Your End User Adoption Strategy
 
13.3 Manage Stakeholder Engagement
13.3 Manage Stakeholder Engagement13.3 Manage Stakeholder Engagement
13.3 Manage Stakeholder Engagement
 
Chapters 13 & 14Chapter 13Q1. You are the project manager of.docx
Chapters 13 & 14Chapter 13Q1. You are the project manager of.docxChapters 13 & 14Chapter 13Q1. You are the project manager of.docx
Chapters 13 & 14Chapter 13Q1. You are the project manager of.docx
 
Project initiation topic 2.8_stakeholder management
Project initiation topic 2.8_stakeholder managementProject initiation topic 2.8_stakeholder management
Project initiation topic 2.8_stakeholder management
 
Project stakeholder Management PMBOK Sixth
Project stakeholder Management PMBOK SixthProject stakeholder Management PMBOK Sixth
Project stakeholder Management PMBOK Sixth
 
Understanding ngo dynamics
Understanding ngo dynamicsUnderstanding ngo dynamics
Understanding ngo dynamics
 
Project Stakeholder Management [read-only] [compatibility mode]
Project Stakeholder Management [read-only] [compatibility mode]Project Stakeholder Management [read-only] [compatibility mode]
Project Stakeholder Management [read-only] [compatibility mode]
 

More from Ahmed Elshaboury,PMP,LEED GA

Pmp procurement chapter 12
Pmp procurement chapter 12Pmp procurement chapter 12
Pmp procurement chapter 12
Ahmed Elshaboury,PMP,LEED GA
 
Pmp risk chapter 11
Pmp risk chapter 11Pmp risk chapter 11
Pmp risk chapter 11
Ahmed Elshaboury,PMP,LEED GA
 
Pmp hr chapter 9
Pmp hr chapter 9Pmp hr chapter 9
Pmp cost chapter 7
Pmp cost chapter 7Pmp cost chapter 7
Pmp cost chapter 7
Ahmed Elshaboury,PMP,LEED GA
 
Pmp time chapter 6
Pmp time chapter 6Pmp time chapter 6
Pmp time chapter 6
Ahmed Elshaboury,PMP,LEED GA
 
Pmp scope chapter 5
Pmp scope chapter 5Pmp scope chapter 5
Pmp scope chapter 5
Ahmed Elshaboury,PMP,LEED GA
 
Pmp integration chapter 4
Pmp integration chapter 4Pmp integration chapter 4
Pmp integration chapter 4
Ahmed Elshaboury,PMP,LEED GA
 
PMP / Framework 1 2-3
PMP / Framework 1 2-3PMP / Framework 1 2-3
PMP / Framework 1 2-3
Ahmed Elshaboury,PMP,LEED GA
 

More from Ahmed Elshaboury,PMP,LEED GA (8)

Pmp procurement chapter 12
Pmp procurement chapter 12Pmp procurement chapter 12
Pmp procurement chapter 12
 
Pmp risk chapter 11
Pmp risk chapter 11Pmp risk chapter 11
Pmp risk chapter 11
 
Pmp hr chapter 9
Pmp hr chapter 9Pmp hr chapter 9
Pmp hr chapter 9
 
Pmp cost chapter 7
Pmp cost chapter 7Pmp cost chapter 7
Pmp cost chapter 7
 
Pmp time chapter 6
Pmp time chapter 6Pmp time chapter 6
Pmp time chapter 6
 
Pmp scope chapter 5
Pmp scope chapter 5Pmp scope chapter 5
Pmp scope chapter 5
 
Pmp integration chapter 4
Pmp integration chapter 4Pmp integration chapter 4
Pmp integration chapter 4
 
PMP / Framework 1 2-3
PMP / Framework 1 2-3PMP / Framework 1 2-3
PMP / Framework 1 2-3
 

Recently uploaded

原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样
原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样
原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样
tdt5v4b
 
Case Analysis - The Sky is the Limit | Principles of Management
Case Analysis - The Sky is the Limit | Principles of ManagementCase Analysis - The Sky is the Limit | Principles of Management
Case Analysis - The Sky is the Limit | Principles of Management
A. F. M. Rubayat-Ul Jannat
 
Comparing Stability and Sustainability in Agile Systems
Comparing Stability and Sustainability in Agile SystemsComparing Stability and Sustainability in Agile Systems
Comparing Stability and Sustainability in Agile Systems
Rob Healy
 
Integrity in leadership builds trust by ensuring consistency between words an...
Integrity in leadership builds trust by ensuring consistency between words an...Integrity in leadership builds trust by ensuring consistency between words an...
Integrity in leadership builds trust by ensuring consistency between words an...
Ram V Chary
 
12 steps to transform your organization into the agile org you deserve
12 steps to transform your organization into the agile org you deserve12 steps to transform your organization into the agile org you deserve
12 steps to transform your organization into the agile org you deserve
Pierre E. NEIS
 
Leadership Ethics and Change, Purpose to Impact Plan
Leadership Ethics and Change, Purpose to Impact PlanLeadership Ethics and Change, Purpose to Impact Plan
Leadership Ethics and Change, Purpose to Impact Plan
Muhammad Adil Jamil
 
Senior Project and Engineering Leader Jim Smith.pdf
Senior Project and Engineering Leader Jim Smith.pdfSenior Project and Engineering Leader Jim Smith.pdf
Senior Project and Engineering Leader Jim Smith.pdf
Jim Smith
 
W.H.Bender Quote 66 - ServPoints Sequence of Service™ should be Identified fo...
W.H.Bender Quote 66 - ServPoints Sequence of Service™ should be Identified fo...W.H.Bender Quote 66 - ServPoints Sequence of Service™ should be Identified fo...
W.H.Bender Quote 66 - ServPoints Sequence of Service™ should be Identified fo...
William (Bill) H. Bender, FCSI
 
The Management Guide: From Projects to Portfolio
The Management Guide: From Projects to PortfolioThe Management Guide: From Projects to Portfolio
The Management Guide: From Projects to Portfolio
Ahmed AbdelMoneim
 
Strategic Org Design with Org Topologies™
Strategic Org Design with Org Topologies™Strategic Org Design with Org Topologies™
Strategic Org Design with Org Topologies™
Alexey Krivitsky
 
在线办理(UVic毕业证书)维多利亚大学毕业证录取通知书一模一样
在线办理(UVic毕业证书)维多利亚大学毕业证录取通知书一模一样在线办理(UVic毕业证书)维多利亚大学毕业证录取通知书一模一样
在线办理(UVic毕业证书)维多利亚大学毕业证录取通知书一模一样
tdt5v4b
 
Enriching engagement with ethical review processes
Enriching engagement with ethical review processesEnriching engagement with ethical review processes
Enriching engagement with ethical review processes
strikingabalance
 
20240608 QFM019 Engineering Leadership Reading List May 2024
20240608 QFM019 Engineering Leadership Reading List May 202420240608 QFM019 Engineering Leadership Reading List May 2024
20240608 QFM019 Engineering Leadership Reading List May 2024
Matthew Sinclair
 
在线办理(Murdoch毕业证书)莫道克大学毕业证电子版成绩单一模一样
在线办理(Murdoch毕业证书)莫道克大学毕业证电子版成绩单一模一样在线办理(Murdoch毕业证书)莫道克大学毕业证电子版成绩单一模一样
在线办理(Murdoch毕业证书)莫道克大学毕业证电子版成绩单一模一样
tdt5v4b
 
Employment Practices Regulation and Multinational Corporations
Employment PracticesRegulation and Multinational CorporationsEmployment PracticesRegulation and Multinational Corporations
Employment Practices Regulation and Multinational Corporations
RoopaTemkar
 
原版制作(CDU毕业证书)查尔斯达尔文大学毕业证PDF成绩单一模一样
原版制作(CDU毕业证书)查尔斯达尔文大学毕业证PDF成绩单一模一样原版制作(CDU毕业证书)查尔斯达尔文大学毕业证PDF成绩单一模一样
原版制作(CDU毕业证书)查尔斯达尔文大学毕业证PDF成绩单一模一样
tdt5v4b
 
Risk-Management-presentation for cooperatives
Risk-Management-presentation for cooperativesRisk-Management-presentation for cooperatives
Risk-Management-presentation for cooperatives
bernanbumatay1
 
CV Ensio Suopanki1.pdf ENGLISH Russian Finnish German
CV Ensio Suopanki1.pdf ENGLISH Russian Finnish GermanCV Ensio Suopanki1.pdf ENGLISH Russian Finnish German
CV Ensio Suopanki1.pdf ENGLISH Russian Finnish German
EUS+ Management & Consulting Excellence
 
Addiction to Winning Across Diverse Populations.pdf
Addiction to Winning Across Diverse Populations.pdfAddiction to Winning Across Diverse Populations.pdf
Addiction to Winning Across Diverse Populations.pdf
Bill641377
 
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
gcljeuzdu
 

Recently uploaded (20)

原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样
原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样
原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样
 
Case Analysis - The Sky is the Limit | Principles of Management
Case Analysis - The Sky is the Limit | Principles of ManagementCase Analysis - The Sky is the Limit | Principles of Management
Case Analysis - The Sky is the Limit | Principles of Management
 
Comparing Stability and Sustainability in Agile Systems
Comparing Stability and Sustainability in Agile SystemsComparing Stability and Sustainability in Agile Systems
Comparing Stability and Sustainability in Agile Systems
 
Integrity in leadership builds trust by ensuring consistency between words an...
Integrity in leadership builds trust by ensuring consistency between words an...Integrity in leadership builds trust by ensuring consistency between words an...
Integrity in leadership builds trust by ensuring consistency between words an...
 
12 steps to transform your organization into the agile org you deserve
12 steps to transform your organization into the agile org you deserve12 steps to transform your organization into the agile org you deserve
12 steps to transform your organization into the agile org you deserve
 
Leadership Ethics and Change, Purpose to Impact Plan
Leadership Ethics and Change, Purpose to Impact PlanLeadership Ethics and Change, Purpose to Impact Plan
Leadership Ethics and Change, Purpose to Impact Plan
 
Senior Project and Engineering Leader Jim Smith.pdf
Senior Project and Engineering Leader Jim Smith.pdfSenior Project and Engineering Leader Jim Smith.pdf
Senior Project and Engineering Leader Jim Smith.pdf
 
W.H.Bender Quote 66 - ServPoints Sequence of Service™ should be Identified fo...
W.H.Bender Quote 66 - ServPoints Sequence of Service™ should be Identified fo...W.H.Bender Quote 66 - ServPoints Sequence of Service™ should be Identified fo...
W.H.Bender Quote 66 - ServPoints Sequence of Service™ should be Identified fo...
 
The Management Guide: From Projects to Portfolio
The Management Guide: From Projects to PortfolioThe Management Guide: From Projects to Portfolio
The Management Guide: From Projects to Portfolio
 
Strategic Org Design with Org Topologies™
Strategic Org Design with Org Topologies™Strategic Org Design with Org Topologies™
Strategic Org Design with Org Topologies™
 
在线办理(UVic毕业证书)维多利亚大学毕业证录取通知书一模一样
在线办理(UVic毕业证书)维多利亚大学毕业证录取通知书一模一样在线办理(UVic毕业证书)维多利亚大学毕业证录取通知书一模一样
在线办理(UVic毕业证书)维多利亚大学毕业证录取通知书一模一样
 
Enriching engagement with ethical review processes
Enriching engagement with ethical review processesEnriching engagement with ethical review processes
Enriching engagement with ethical review processes
 
20240608 QFM019 Engineering Leadership Reading List May 2024
20240608 QFM019 Engineering Leadership Reading List May 202420240608 QFM019 Engineering Leadership Reading List May 2024
20240608 QFM019 Engineering Leadership Reading List May 2024
 
在线办理(Murdoch毕业证书)莫道克大学毕业证电子版成绩单一模一样
在线办理(Murdoch毕业证书)莫道克大学毕业证电子版成绩单一模一样在线办理(Murdoch毕业证书)莫道克大学毕业证电子版成绩单一模一样
在线办理(Murdoch毕业证书)莫道克大学毕业证电子版成绩单一模一样
 
Employment Practices Regulation and Multinational Corporations
Employment PracticesRegulation and Multinational CorporationsEmployment PracticesRegulation and Multinational Corporations
Employment Practices Regulation and Multinational Corporations
 
原版制作(CDU毕业证书)查尔斯达尔文大学毕业证PDF成绩单一模一样
原版制作(CDU毕业证书)查尔斯达尔文大学毕业证PDF成绩单一模一样原版制作(CDU毕业证书)查尔斯达尔文大学毕业证PDF成绩单一模一样
原版制作(CDU毕业证书)查尔斯达尔文大学毕业证PDF成绩单一模一样
 
Risk-Management-presentation for cooperatives
Risk-Management-presentation for cooperativesRisk-Management-presentation for cooperatives
Risk-Management-presentation for cooperatives
 
CV Ensio Suopanki1.pdf ENGLISH Russian Finnish German
CV Ensio Suopanki1.pdf ENGLISH Russian Finnish GermanCV Ensio Suopanki1.pdf ENGLISH Russian Finnish German
CV Ensio Suopanki1.pdf ENGLISH Russian Finnish German
 
Addiction to Winning Across Diverse Populations.pdf
Addiction to Winning Across Diverse Populations.pdfAddiction to Winning Across Diverse Populations.pdf
Addiction to Winning Across Diverse Populations.pdf
 
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
 

Pmp stakeholder chapter 13

  • 2. 2  13.1 Identify Stakeholder  13.2 Plan Stakeholder Management  13.3 Manage Stakeholder Engagement  13.4 Control Stakeholder Engagement KEY TERMS
  • 3. 3 • 13.1 Identify Stakeholders (Initiating) identifying the people, groups, or organizations that could impact or be impacted by a decision, activity, or outcome of the project. • 13.2 Plan Stakeholder Management (Planning) developing appropriate management strategies to effectively engage stakeholders throughout the project life cycle. • 13.3 Manage Stakeholder Engagement (Executing) communicating and working with stakeholders to meet their needs/expectations. • 13.4 Control Stakeholder Engagement (Monitoring & Control) monitoring overall project stakeholder relationships And adjusting strategies and plans for engaging stakeholders.
  • 5. 5 13.1 Identify Stakeholders • Identifying the people, groups, or organizations that could impact or be impacted by a decision, activity, or outcome of the project.
  • 6. 6
  • 7. 7 13.1 Identify Stakeholders Inputs 1. Project Charter . 2. Procurement Documents 3. EEF 4. OPA
  • 8. 8 13.1 Identify Stakeholders T & T 1. Stakeholder Analysis: gathering & analyzing information to determine stakeholder in 3 steps:  Identify all potential stakeholders & relevant information (roles, departments, interests, knowledge levels, expectations & influence levels).  Identify potential impact or support each stakeholder could generate (power-interest)  Assess how key stakeholders are likely to react or respond to various situations.
  • 9. 9 Stakeholder Analysis classification models used for stakeholders analysis • Power/interest grid based on: level of authority (power) level or concern (interest) • Power/influence grid based on level of authority (power) active involvement (influence) • Influence/impact grid based on active involvement (influence) ability to effect changes (impact)
  • 10. 10 • Salience model based on power (ability to impose their will), urgency (need for immediate attention) legitimacy (their involvement is appropriate). Power Urgency Legitimacy 1 2 3 4 5 6 7
  • 11. 11 13.1 Identify Stakeholders T & T 2. Expert Judgment: groups or individuals specialized in certain areas such:  Senior management  Subject matter experts  Industry groups and consultants  Professional and technical associations  Project managers with experience in similar projects  Identified stakeholders. 3. Meetings
  • 12. 12 13.1 Identify Stakeholders Outputs Stakeholder Register • Identification Information: name, organizational position, location, role in project, … etc. • Assessment Information: major requirements , expectation, potential influence in project … etc. • Stakeholder Classification: Internal/External, supporter, neutral, resistor, … etc.
  • 13. 13
  • 15. 15 13.2 Plan Stakeholders Management • Developing appropriate management strategies to effectively engage stakeholders throughout the project life cycle.
  • 16. 16
  • 17. 17 Analytical Techniques, engagement levels: The engagement level of the stakeholders Unaware Unaware of project and potential impacts. Resistant Aware of project and potential impacts and resistant to change. Neutral Aware of project yet neither supportive nor resistant. Supportive Aware of project & impacts and supportive to change. Leading Aware of project & impacts and actively engaged in ensuring the project is a success.
  • 18. 18 C : Current engagement D : Desired engagement • Stakeholders Engagement Assessment Matrix • Through this analytical process, gaps between the current and desired engagement levels can be identified. • Actions and communications required to close these gaps can be identified by the project team using expert judgment.
  • 19. 19 13.2 Plan Stakeholder Management Inputs 1. Project Management Plan . 2. Stakeholder Register 3. EEF 4. OPA 13.2 Plan Stakeholder Management Outputs 1. Stakeholder Management Plan 2. Project Documents Updates
  • 21. 21 13.3 Manage Stakeholders Engagement • Communicating and working with stakeholders to meet their needs/expectations. • The key benefit is to allow the project manager to increase support and minimize resistance from stakeholders.
  • 22. 22
  • 23. 23 13.3 Manage Stakeholder Engagement Inputs 1. Stakeholder Management Plan. 2. Communication Management Plan 3. Change Log 4. OPA 13.3 Manage Stakeholder Engagement Outputs 1. Issue Log. 2. Change Requests 3. Project Management Plan Updates 4. Project Document Updates 5. OPA Updates
  • 24. 24 13.3 Manage Stakeholder Engagement T &T 1. Communications Methods Interactive communication . Push & Pull communication 2. Interpersonal Skills  Building trust  Resolving conflict  Active listening  Overcoming resistance to change 3. Management Skills  Influence people to support project  Negotiate agreements  Modify organizational behavior
  • 26. 26 13.3 Control Stakeholders Engagement • monitoring overall project stakeholder relationships And adjusting strategies and plans for engaging stakeholders. • The key benefit is to maintain or increase the efficiency and effectiveness of stakeholder engagement activities.
  • 27. 27
  • 28. 28 13.4 Control Stakeholder Engagement Inputs 1. Project Management Plan 2. Issue Log 3. Work Performance Data 4. Project Documents • Project schedule, • Stakeholder register • Issue log • Change log • Project communications.
  • 29. 29 13.4 Control Stakeholder Engagement Outputs 1. Work Performance Information 2. Change Requests 3. Project Management Plan Updates 4. Project Document Updates 5. OPA Updates
  • 30. 30 Questions l. When do stakeholders have the MOST influence on a project? A. At the beginning of the project B. In the middle of the project C. At the end of the project D. Throughout the project
  • 31. 31 Questions l. When do stakeholders have the MOST influence on a project? A. At the beginning of the project B. In the middle of the project C. At the end of the project D. Throughout the project Answer : A
  • 32. 32 Questions 2. Stakeholders can be identified in which project management process groups? A. Initiating, planning, executing, and monitoring and controlling. B. Initiating and planning. C. Planning and monitoring and controlling. D. Monitoring and controlling and closing.
  • 33. 33 Questions 2. Stakeholders can be identified in which project management process groups? A. Initiating, planning, executing, and monitoring and controlling. B. Initiating and planning. C. Planning and monitoring and controlling. D. Monitoring and controlling and closing. Answer : A . The early you identify stakeholder. The less conflicts you get.
  • 34. 34 Questions 3. A particular stakeholder has a reputation for requesting many changes on projects. What is the BEST approach a project manager can take at the beginning of the project to manage this situation? A. Say "No" to the stakeholder a few times to dissuade him from submitting more changes. B. Get the stakeholder involved in the project as early as possible. C. Talk to the stakeholder's boss to find ways of directing the stakeholder's activities to another project. D. Ask that the stakeholder not be included in the stakeholder listing.
  • 35. 35 Questions 3. A particular stakeholder has a reputation for requesting many changes on projects. What is the BEST approach a project manager can take at the beginning of the project to manage this situation? A. Say "No" to the stakeholder a few times to dissuade him from submitting more changes. B. Get the stakeholder involved in the project as early as possible. C. Talk to the stakeholder's boss to find ways of directing the stakeholder's activities to another project. D. Ask that the stakeholder not be included in the stakeholder listing. Answer : B
  • 36. 36 Questions 4. A project manager wants to more extensively involve the stakeholders on the project. Which of the following would be the BEST way to accomplish this? A. Have the stakeholders periodically review the list of project requirements. B. Invite the stakeholders to attend project status meetings. C. Send status reports to the stakeholders. D. Update the stakeholders on the status of all project changes.
  • 37. 37 Questions 4. A project manager wants to more extensively involve the stakeholders on the project. Which of the following would be the BEST way to accomplish this? A. Have the stakeholders periodically review the list of project requirements. B. Invite the stakeholders to attend project status meetings. C. Send status reports to the stakeholders. D. Update the stakeholders on the status of all project changes. Answer : A
  • 38. 38 Questions 5. A stakeholders engagement assessment matrix can be used to identify: A. Communication gaps. B. Additional stakeholders. C. Key relationships between stakeholders. D. Skill levels of stakeholders.
  • 39. 39 Questions 5. A stakeholders engagement assessment matrix can be used to identify: A. Communication gaps. B. Additional stakeholders. C. Key relationships between stakeholders. D. Skill levels of stakeholders. Answer : A
  • 40. 40 Questions 6. The role of each stakeholder is determined by: A. The stakeholder and the sponsor. B. The project manager and the sponsor. C. The team and the project manager. D. The project manager and the stakeholder.
  • 41. 41 Questions 6. The role of each stakeholder is determined by: A. The stakeholder and the sponsor. B. The project manager and the sponsor. C. The team and the project manager. D. The project manager and the stakeholder. Answer : D stakeholders have input into what they will be contributing to the project.
  • 42. 42 Questions 7. The project manager is trying to recall a stakeholder's preferred communication method. Where can she find that information? A. RACI chart B. Stakeholders engagement assessment matrix C. Stakeholder management plan D. Human resource management plan
  • 43. 43 Questions 7. The project manager is trying to recall a stakeholder's preferred communication method. Where can she find that information? A. RACI chart B. Stakeholders engagement assessment matrix C. Stakeholder management plan D. Human resource management plan Answer : C
  • 44. 44 Questions 8. The degree to which a particular stakeholder may be able to positively or negatively affect a project is his or her: A. Level of engagement. B. Level of interest. C. Level of commitment. D. Level of influence.
  • 45. 45 Questions 8. The degree to which a particular stakeholder may be able to positively or negatively affect a project is his or her: A. Level of engagement. B. Level of interest. C. Level of commitment. D. Level of influence. Answer : D
  • 46. 46 Questions 9. The stakeholder register is an input to which of the following processes? A. Plan Risk Management and Collect Requirements B. Perform Integrated Change Control and Plan Communications Management C. Plan Quality Management and Perform Quality Assurance D. Identify Risks and Develop Project Charter
  • 47. 47 Questions 9. The stakeholder register is an input to which of the following processes? A. Plan Risk Management and Collect Requirements B. Perform Integrated Change Control and Plan Communications Management C. Plan Quality Management and Perform Quality Assurance D. Identify Risks and Develop Project Charter Answer : A the stakeholder register is an input to : Collect Requirements / Plan Quality Management / Plan Communications Management / Plan Risk / Management / and Identify Risks.
  • 48. 48 Questions 10. The key objective of stakeholder management is: A. Communication. B. Coordination. C. Satisfaction. D. Relationships.
  • 49. 49 Questions 10. The key objective of stakeholder management is: A. Communication. B. Coordination. C. Satisfaction. D. Relationships. Answer : C