Question bank on Stakeholder Management PMBOK-5
1. Project stakeholder management includes all of the following except
a. Identify the people, groups, or organizations that could impact or be
impacted by the project.
b. Analyze stakeholder expectations and their impact on the project.
c. Develop appropriate management strategy for effectively engaging
stakeholders in project decisions and execution.
d. Develop strategies to avoid the incorporation of changes suggested by
the stakeholders.
2. Project stakeholder management focuses on
a. Continuous communication with the stakeholders to understand their
needs and expectations.
b. Addressing issues as they occur.
c. Managing conflicting interests.
d. Fostering appropriate stakeholder engagement in project decisions
and activities.
e. All of the above.
3. What should be the key project objective?
a. Completion of project within schedule and time.
b. Avoid scope changes in the project.
c. Stakeholder satisfaction
d. Completion of project within cost.
4. The process of identifying the people ,groups, or organizations that could
impact or be impacted by a decision ,activity, or outcome of the project
and analyzing and documenting relevant information regarding their
interests,involvement,interdependencies, influence and potential impact
on the project is
a. Control Stakeholder Management
b. Manage stakeholder Engagement
c. Identify stakeholders
d. Stakeholder Analysis.
5. The process of development of appropriate management strategies to
effectively engage stakeholders throughout the project lifecycle, based on
analysis of their needs, interests and potential impact on project success.
a. Control stakeholder Management
b. Manage stakeholder engagement
c. Plan stakeholder management
d. Control stakeholder engagement.
6. The process of communicating and working with stakeholders to meet
their needs and expectations, address issues as they occur, and foster
appropriate stakeholders engagement in project activities throughout
the project lifecycle is called
a. Control stakeholder engagement
b. Manage stakeholder engagement
c. Plan stakeholder management
d. Control stakeholder Engagement.
7. The process of monitoring overall project stakeholder relationships and
adjusting strategies and plans for engaging stakeholders is called
a. Control stakeholder engagement
b. Manage stakeholder engagement
c. Plan stakeholder management
d. Control stakeholder engagement.
8. Which of the following is not input to the Identify stakeholders process
a. Project charter
b. Project documents
c. Procurement documents
d. Organizational process assets
e. Enterprise environmental factors.
9. Which of the following is not a tool & technique for the Identify
stakeholder’s process?
a. Stakeholders analysis
b. Expert judgment
c. Meetings
d. Analytical techniques.
10. Stakeholder register is an input to all of the following except
a. Collect requirements.
b. Plan quality management.
c. Plan communication management & Control Communications.
d. Plan risk management & identify risks.
11. Project charter provides information about
a. Internal & external parties related with the project
b. Parties affected by the result or the execution of the project
c. Groups or departments participating in the project
d. Other people or organizations affected by the project
e. All of the above.
12. All of the following are EEF except
a. Organizational Culture and structure
b. Govt. or industry standards
c. Global regional or local trends
d. Stakeholders register from other projects.
13. All of the following are OPA except
a. Stakeholders register templates
b. Lessons learnt from previous projects
c. Stakeholders register from previous projects
d. Organizational culture and structure.
14. Which of the following are not classification model for stakeholder analysis
a. Power /interest grid model.
b. Power/influence grid model.
c. Influence /Impact grid model.
d. Influence/Interest grid model.
15. Salience Model of classification of the stakeholders focuses on
a. Classifying the stakeholders based on their level of authority and level
of concern regarding the project outcomes.
b. Classifying the stakeholders based on their active involvement and
the level of authority.
c. Classifying the stakeholders on the basis of their active involvement
in the project and their ability to effect changes to the project
planning and execution.
d. Classifying the stakeholders based on their power, urgency, and
legitimacy.
16. If a stakeholder has High power and high interest in the project then
a. Monitor them
b. Keep them informed
c. Keep them satisfied
d. Manage closely
17. If a stakeholder has high interest in the project and low power then
a. Monitor them.
b. Keep them informed.
c. Keep them satisfied.
d. Manage them closely.
18.If a stakeholder has high power and low interest in the project then
a. Monitor them
b. Keep them informed
c. Manage them closely
d. Keep them satisfied.
19. The stakeholders register contains all details related to the identified
stakeholders except
a. Identification information-Name, Organization, position, location, role
in the project, contact information.
b. Assessment information-Major requirements, main expectations,
potential influence in the phase in the lifecycle with the most interest.
c. Stakeholder classification-Internal/external,
supporter/neutral/resister.
d. Stakeholder management plan.
Note-The key benefit of plan stakeholder management is that it gives clear
actionable plan to interact with project stakeholders.
20. All of the following are the inputs to the Plan stakeholders management
process except
a. Project management plan
b. Stakeholders register
c. EEF
d. OPA
e. Project documents
21. All of the following are the tools and techniques of Plan stakeholder
management except
a. Expert judgment
b. Meetings
c. Stakeholder analysis
d. Analytical techniques
22. Which of the following is the output of the plan stakeholder
management process
a. OPA updates
b. EEF updates
c. Project document updates
d. Project management plan updates.
23. As input to the plan stakeholder management project management plan
provides all of the following except
a. Life cycle selected for the project and the processes that will be
applied to each phase.
b. Description of how work will be executed to achieve project objectives
c. Description of how human resources requirements will be met how
roles and responsibilities reporting relationships and staffing
management plan will be addressed and structured in the project.
d. How stakeholder register will be updated.
e. How change management plan will be implemented.
f. Need and techniques for communications among stakeholders.
24. Expert judgment can be obtained though
a. One to one meetings
b. Interviews
c. Focus groups
d. Surveys
e. All of the above
25. The stakeholder management plan provides the following information
a. Desired and current engagement levels of the key stakeholders
b. Scope and impact of changes to stakeholders
c. Identified interrelationships and potential overlap between
stakeholders.
d. Stakeholder’s communication requirements for the current project
phase.
e. All of the above.
26. The stakeholder management plan provides the following information
a. Information’s to be distributed to stakeholders
b. Reason for the distribution of a particular information
c. Time frame and the frequency for the information to be distributed.
d. Method for updating and refining the stakeholder management plan
e. All of the above.
27. The stakeholder management plan is an input to which of the following
process
a. Collect requirements
b. Control Stakeholder engagement
c. Plan procurement management
d. Plan risk management
28.All of the following are inputs to the manage stakeholder engagement
process except
a. SH engagement plan
b. Communications management plan
c. Change request
d. Organizational process assets.
29.Which of the following is not T&T for the manage SH engagement process
a. Communication skills
b. Interpersonal skills
c. Management skills
d. Communication methods
30. Which of the following is not an output of the manage stakeholder
engagement
a. Stakeholder management plan updates
b. OPA updates
c. Project documents updates
d. Project management plan updates.
31Issue log is an input to all of the following process except
a. Control stakeholder engagement
b. Manage project team
c. Control communications
d. Develop project management plan.
32 Stakeholder management plan provides the following
a. Guidance on how the various stake holders will be involved in the
project.
b. It provides the methods and technologies used in the stakeholder
communication.
c. Used to determine the level of interactions of various stakeholders.
d. It helps define the strategy for identifying and managing stakeholders
throughout the project lifecycle.
e. All of the above.
33. The communication management plan provides
a. Stakeholder’s communication requirements.
b. Information to be communicated including the language, format, and
content and level of detail.
c. Reason for distribution of information.
d. Person and groups who will receive information
e. Escalation process
f. All the above.
34. All of the following are Organizational process assets except
a. Organizational communication requirements.
b. Issue management procedures.
c. Change control procedures.
d. Historical information about previous projects.
e. All of the above.
35. The OPA updates includes
a. Stakeholders notifications
b. Project reports
c. Project presentations
d. Project records
e. Feedback from stakeholders & Lessons learnt.
f. All of the above
36. The primary observations and measurements identified during
activities being performed to carry out the project work is called
a. Reported %of work completed.
b. Work performance data.
c. Work performance information.
d. Work performance Index.
37. Project documents which are used as input to the control stakeholder
management process are
a. Project schedule
b. Stakeholder register
c. Issues log
d. Change log
e. Project communications
f. All of the above.
38. All of the following are examples of work performance information
except
a. Status of deliverables
b. Implementation status of change requests
c. Forecasted estimates to compete
d. Number of change requests.
Note- The recommended corrective actions include changes that bring the
expected future performance in line with the project management plan.
The recommended preventive actions can reduce the probability of future
negative project performance.
39. OPA updates includes updates on stakeholder notifications, project
reports, project presentation, Feedback from stakeholders, lessons learnt
documentation.
Answers
Q.No Answers Q.No Answers Q.No Answers Q.No Answers
1 D 11 E 21 C 31 D
2 E 12 D 22 C 32 E
3 C 13 D 23 A 33 F
4 C 14 D 24 E 34 E
5 C 15 D 25 E 35 F
6 B 16 D 26 E 36 B
7 A 17 B 27 A 37 F
8 B 18 D 28 C 38 D
9 D 19 D 29 A
10 C 20 E 30 A
Stakeholder management qb
Stakeholder management qb

More Related Content

What's hot

10 pmp communication management exam
10 pmp communication  management exam10 pmp communication  management exam
10 pmp communication management exam
Jamil Faraj , PMP
 
Pmp2
Pmp2Pmp2
Solved question paper of Assistant computer operator of PSC conducted on 2018
Solved question paper of Assistant computer operator of PSC conducted on 2018Solved question paper of Assistant computer operator of PSC conducted on 2018
Solved question paper of Assistant computer operator of PSC conducted on 2018
Suresh Khanal
 
Pmi sp questions with answers
Pmi sp questions with answersPmi sp questions with answers
Pmi sp questions with answers
Mohamed Saeed
 
Logic of Formulas - how to answer EVM questions without Math
Logic of Formulas - how to answer EVM questions without MathLogic of Formulas - how to answer EVM questions without Math
Logic of Formulas - how to answer EVM questions without Math
Martin Bailey
 
03 pmp project management processes exam
03 pmp project management processes exam03 pmp project management processes exam
03 pmp project management processes exam
Jamil Faraj , PMP
 
11 pmp risk management exam
11 pmp risk management exam11 pmp risk management exam
11 pmp risk management exam
Jamil Faraj , PMP
 
08 pmp quality management exam
08 pmp quality management exam08 pmp quality management exam
08 pmp quality management exam
Jamil Faraj , PMP
 
Project Management Plan
Project Management PlanProject Management Plan
Project Management Plan
Kyle Hammon
 

What's hot (9)

10 pmp communication management exam
10 pmp communication  management exam10 pmp communication  management exam
10 pmp communication management exam
 
Pmp2
Pmp2Pmp2
Pmp2
 
Solved question paper of Assistant computer operator of PSC conducted on 2018
Solved question paper of Assistant computer operator of PSC conducted on 2018Solved question paper of Assistant computer operator of PSC conducted on 2018
Solved question paper of Assistant computer operator of PSC conducted on 2018
 
Pmi sp questions with answers
Pmi sp questions with answersPmi sp questions with answers
Pmi sp questions with answers
 
Logic of Formulas - how to answer EVM questions without Math
Logic of Formulas - how to answer EVM questions without MathLogic of Formulas - how to answer EVM questions without Math
Logic of Formulas - how to answer EVM questions without Math
 
03 pmp project management processes exam
03 pmp project management processes exam03 pmp project management processes exam
03 pmp project management processes exam
 
11 pmp risk management exam
11 pmp risk management exam11 pmp risk management exam
11 pmp risk management exam
 
08 pmp quality management exam
08 pmp quality management exam08 pmp quality management exam
08 pmp quality management exam
 
Project Management Plan
Project Management PlanProject Management Plan
Project Management Plan
 

Similar to Stakeholder management qb

Pmp stakeholder chapter 13
Pmp stakeholder chapter 13Pmp stakeholder chapter 13
Pmp stakeholder chapter 13
Ahmed Elshaboury,PMP,LEED GA
 
Itpm question bank
Itpm   question bankItpm   question bank
Itpm question bank
Hussain111321
 
Project ManagementECE 326 Exam 2Description Exam 2 question.docx
Project ManagementECE 326 Exam 2Description Exam 2 question.docxProject ManagementECE 326 Exam 2Description Exam 2 question.docx
Project ManagementECE 326 Exam 2Description Exam 2 question.docx
wkyra78
 
Liberty university busi 313 quiz 1 complete solutions correct answers key
Liberty university busi 313 quiz 1 complete solutions correct answers keyLiberty university busi 313 quiz 1 complete solutions correct answers key
Liberty university busi 313 quiz 1 complete solutions correct answers key
Harry White
 
Pmp Questions Complete
Pmp Questions CompletePmp Questions Complete
Pmp Questions Complete
KareemBullard1
 
PMP Certification Training Course Part-64
PMP Certification Training Course Part-64PMP Certification Training Course Part-64
PMP Certification Training Course Part-64
Skillogic Solutions
 
Free CAPM Exam Sample Question
Free CAPM Exam Sample QuestionFree CAPM Exam Sample Question
Free CAPM Exam Sample Question
OSP International LLC
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
OSP International LLC
 
CAPM Sample Q and A
CAPM Sample Q and ACAPM Sample Q and A
CAPM Sample Q and A
OSP International LLC
 
SERVICES DELIVERY
SERVICES DELIVERYSERVICES DELIVERY
SERVICES DELIVERY
NAHDA Organization
 
10. Stakeholder Management
10. Stakeholder Management10. Stakeholder Management
10. Stakeholder Management
Sanjay Rajpoot
 
Project charter template
Project charter templateProject charter template
Project charter template
Harshal Majithia
 
is not one of the stages of a project life cycle 6. Which of the fol.pdf
is not one of the stages of a project life cycle 6. Which of the fol.pdfis not one of the stages of a project life cycle 6. Which of the fol.pdf
is not one of the stages of a project life cycle 6. Which of the fol.pdf
aristogifts99
 
MANAGEMENT-OF-COMMUNITY-IMMERSION.pptx
MANAGEMENT-OF-COMMUNITY-IMMERSION.pptxMANAGEMENT-OF-COMMUNITY-IMMERSION.pptx
MANAGEMENT-OF-COMMUNITY-IMMERSION.pptx
EJINAABEGAILJASMINEA
 
Project evaluation and implementation notes and questions
Project evaluation and implementation   notes and questionsProject evaluation and implementation   notes and questions
Project evaluation and implementation notes and questions
Anirban Chakraborty
 
(Enter your answers on the enclosed answer sheet)1. A humanis an e.docx
(Enter your answers on the enclosed answer sheet)1. A humanis an e.docx(Enter your answers on the enclosed answer sheet)1. A humanis an e.docx
(Enter your answers on the enclosed answer sheet)1. A humanis an e.docx
tienmixon
 
scope-statement-sample.doc
scope-statement-sample.docscope-statement-sample.doc
scope-statement-sample.doc
AhsanRahman13
 
Communications Management Plan Templatewww.ProjectManagementDo.docx
Communications Management Plan Templatewww.ProjectManagementDo.docxCommunications Management Plan Templatewww.ProjectManagementDo.docx
Communications Management Plan Templatewww.ProjectManagementDo.docx
clarebernice
 
BSBPMG522 Undertake project work1HousekeepingE.docx
BSBPMG522 Undertake project work1HousekeepingE.docxBSBPMG522 Undertake project work1HousekeepingE.docx
BSBPMG522 Undertake project work1HousekeepingE.docx
curwenmichaela
 
BSBPMG522 Undertake project work1Housekeeping.docx
BSBPMG522 Undertake project work1Housekeeping.docxBSBPMG522 Undertake project work1Housekeeping.docx
BSBPMG522 Undertake project work1Housekeeping.docx
jasoninnes20
 

Similar to Stakeholder management qb (20)

Pmp stakeholder chapter 13
Pmp stakeholder chapter 13Pmp stakeholder chapter 13
Pmp stakeholder chapter 13
 
Itpm question bank
Itpm   question bankItpm   question bank
Itpm question bank
 
Project ManagementECE 326 Exam 2Description Exam 2 question.docx
Project ManagementECE 326 Exam 2Description Exam 2 question.docxProject ManagementECE 326 Exam 2Description Exam 2 question.docx
Project ManagementECE 326 Exam 2Description Exam 2 question.docx
 
Liberty university busi 313 quiz 1 complete solutions correct answers key
Liberty university busi 313 quiz 1 complete solutions correct answers keyLiberty university busi 313 quiz 1 complete solutions correct answers key
Liberty university busi 313 quiz 1 complete solutions correct answers key
 
Pmp Questions Complete
Pmp Questions CompletePmp Questions Complete
Pmp Questions Complete
 
PMP Certification Training Course Part-64
PMP Certification Training Course Part-64PMP Certification Training Course Part-64
PMP Certification Training Course Part-64
 
Free CAPM Exam Sample Question
Free CAPM Exam Sample QuestionFree CAPM Exam Sample Question
Free CAPM Exam Sample Question
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
 
CAPM Sample Q and A
CAPM Sample Q and ACAPM Sample Q and A
CAPM Sample Q and A
 
SERVICES DELIVERY
SERVICES DELIVERYSERVICES DELIVERY
SERVICES DELIVERY
 
10. Stakeholder Management
10. Stakeholder Management10. Stakeholder Management
10. Stakeholder Management
 
Project charter template
Project charter templateProject charter template
Project charter template
 
is not one of the stages of a project life cycle 6. Which of the fol.pdf
is not one of the stages of a project life cycle 6. Which of the fol.pdfis not one of the stages of a project life cycle 6. Which of the fol.pdf
is not one of the stages of a project life cycle 6. Which of the fol.pdf
 
MANAGEMENT-OF-COMMUNITY-IMMERSION.pptx
MANAGEMENT-OF-COMMUNITY-IMMERSION.pptxMANAGEMENT-OF-COMMUNITY-IMMERSION.pptx
MANAGEMENT-OF-COMMUNITY-IMMERSION.pptx
 
Project evaluation and implementation notes and questions
Project evaluation and implementation   notes and questionsProject evaluation and implementation   notes and questions
Project evaluation and implementation notes and questions
 
(Enter your answers on the enclosed answer sheet)1. A humanis an e.docx
(Enter your answers on the enclosed answer sheet)1. A humanis an e.docx(Enter your answers on the enclosed answer sheet)1. A humanis an e.docx
(Enter your answers on the enclosed answer sheet)1. A humanis an e.docx
 
scope-statement-sample.doc
scope-statement-sample.docscope-statement-sample.doc
scope-statement-sample.doc
 
Communications Management Plan Templatewww.ProjectManagementDo.docx
Communications Management Plan Templatewww.ProjectManagementDo.docxCommunications Management Plan Templatewww.ProjectManagementDo.docx
Communications Management Plan Templatewww.ProjectManagementDo.docx
 
BSBPMG522 Undertake project work1HousekeepingE.docx
BSBPMG522 Undertake project work1HousekeepingE.docxBSBPMG522 Undertake project work1HousekeepingE.docx
BSBPMG522 Undertake project work1HousekeepingE.docx
 
BSBPMG522 Undertake project work1Housekeeping.docx
BSBPMG522 Undertake project work1Housekeeping.docxBSBPMG522 Undertake project work1Housekeeping.docx
BSBPMG522 Undertake project work1Housekeeping.docx
 

Recently uploaded

在线制作加拿大萨省大学毕业证文凭证书实拍图原版一模一样
在线制作加拿大萨省大学毕业证文凭证书实拍图原版一模一样在线制作加拿大萨省大学毕业证文凭证书实拍图原版一模一样
在线制作加拿大萨省大学毕业证文凭证书实拍图原版一模一样
2zjra9bn
 
0624.speakingengagementsandteaching-01.pdf
0624.speakingengagementsandteaching-01.pdf0624.speakingengagementsandteaching-01.pdf
0624.speakingengagementsandteaching-01.pdf
Thomas GIRARD BDes
 
5 Common Mistakes to Avoid During the Job Application Process.pdf
5 Common Mistakes to Avoid During the Job Application Process.pdf5 Common Mistakes to Avoid During the Job Application Process.pdf
5 Common Mistakes to Avoid During the Job Application Process.pdf
Alliance Jobs
 
RECOGNITION AWARD 13 - TO ALESSANDRO MARTINS.pdf
RECOGNITION AWARD 13 - TO ALESSANDRO MARTINS.pdfRECOGNITION AWARD 13 - TO ALESSANDRO MARTINS.pdf
RECOGNITION AWARD 13 - TO ALESSANDRO MARTINS.pdf
AlessandroMartins454470
 
Jill Pizzola's Tenure as Senior Talent Acquisition Partner at THOMSON REUTERS...
Jill Pizzola's Tenure as Senior Talent Acquisition Partner at THOMSON REUTERS...Jill Pizzola's Tenure as Senior Talent Acquisition Partner at THOMSON REUTERS...
Jill Pizzola's Tenure as Senior Talent Acquisition Partner at THOMSON REUTERS...
dsnow9802
 
Introducing Gopay Mobile App For Environment.pptx
Introducing Gopay Mobile App For Environment.pptxIntroducing Gopay Mobile App For Environment.pptx
Introducing Gopay Mobile App For Environment.pptx
FauzanHarits1
 
lab.123456789123456789123456789123456789
lab.123456789123456789123456789123456789lab.123456789123456789123456789123456789
lab.123456789123456789123456789123456789
Ghh
 
Job Finding Apps Everything You Need to Know in 2024
Job Finding Apps Everything You Need to Know in 2024Job Finding Apps Everything You Need to Know in 2024
Job Finding Apps Everything You Need to Know in 2024
SnapJob
 
一比一原版(UBC毕业证)不列颠哥伦比亚大学毕业证如何办理
一比一原版(UBC毕业证)不列颠哥伦比亚大学毕业证如何办理一比一原版(UBC毕业证)不列颠哥伦比亚大学毕业证如何办理
一比一原版(UBC毕业证)不列颠哥伦比亚大学毕业证如何办理
pxyhy
 
Leadership Ambassador club Adventist module
Leadership Ambassador club Adventist moduleLeadership Ambassador club Adventist module
Leadership Ambassador club Adventist module
kakomaeric00
 
一比一原版布拉德福德大学毕业证(bradford毕业证)如何办理
一比一原版布拉德福德大学毕业证(bradford毕业证)如何办理一比一原版布拉德福德大学毕业证(bradford毕业证)如何办理
一比一原版布拉德福德大学毕业证(bradford毕业证)如何办理
taqyea
 
labb123456789123456789123456789123456789
labb123456789123456789123456789123456789labb123456789123456789123456789123456789
labb123456789123456789123456789123456789
Ghh
 
一比一原版(SFU毕业证)西蒙弗雷泽大学毕业证如何办理
一比一原版(SFU毕业证)西蒙弗雷泽大学毕业证如何办理一比一原版(SFU毕业证)西蒙弗雷泽大学毕业证如何办理
一比一原版(SFU毕业证)西蒙弗雷泽大学毕业证如何办理
pxyhy
 
Status of Women in Pakistan.pptxStatus of Women in Pakistan.pptx
Status of Women in Pakistan.pptxStatus of Women in Pakistan.pptxStatus of Women in Pakistan.pptxStatus of Women in Pakistan.pptx
Status of Women in Pakistan.pptxStatus of Women in Pakistan.pptx
MuhammadWaqasBaloch1
 
一比一原版(QU毕业证)皇后大学毕业证如何办理
一比一原版(QU毕业证)皇后大学毕业证如何办理一比一原版(QU毕业证)皇后大学毕业证如何办理
一比一原版(QU毕业证)皇后大学毕业证如何办理
yuhofha
 
原版制作(RMIT毕业证书)墨尔本皇家理工大学毕业证在读证明一模一样
原版制作(RMIT毕业证书)墨尔本皇家理工大学毕业证在读证明一模一样原版制作(RMIT毕业证书)墨尔本皇家理工大学毕业证在读证明一模一样
原版制作(RMIT毕业证书)墨尔本皇家理工大学毕业证在读证明一模一样
atwvhyhm
 
A Guide to a Winning Interview June 2024
A Guide to a Winning Interview June 2024A Guide to a Winning Interview June 2024
A Guide to a Winning Interview June 2024
Bruce Bennett
 
thyroid case presentation.pptx Kamala's Lakshaman palatial
thyroid case presentation.pptx Kamala's Lakshaman palatialthyroid case presentation.pptx Kamala's Lakshaman palatial
thyroid case presentation.pptx Kamala's Lakshaman palatial
Aditya Raghav
 
一比一原版(TMU毕业证)多伦多都会大学毕业证如何办理
一比一原版(TMU毕业证)多伦多都会大学毕业证如何办理一比一原版(TMU毕业证)多伦多都会大学毕业证如何办理
一比一原版(TMU毕业证)多伦多都会大学毕业证如何办理
yuhofha
 
一比一原版(YU毕业证)约克大学毕业证如何办理
一比一原版(YU毕业证)约克大学毕业证如何办理一比一原版(YU毕业证)约克大学毕业证如何办理
一比一原版(YU毕业证)约克大学毕业证如何办理
yuhofha
 

Recently uploaded (20)

在线制作加拿大萨省大学毕业证文凭证书实拍图原版一模一样
在线制作加拿大萨省大学毕业证文凭证书实拍图原版一模一样在线制作加拿大萨省大学毕业证文凭证书实拍图原版一模一样
在线制作加拿大萨省大学毕业证文凭证书实拍图原版一模一样
 
0624.speakingengagementsandteaching-01.pdf
0624.speakingengagementsandteaching-01.pdf0624.speakingengagementsandteaching-01.pdf
0624.speakingengagementsandteaching-01.pdf
 
5 Common Mistakes to Avoid During the Job Application Process.pdf
5 Common Mistakes to Avoid During the Job Application Process.pdf5 Common Mistakes to Avoid During the Job Application Process.pdf
5 Common Mistakes to Avoid During the Job Application Process.pdf
 
RECOGNITION AWARD 13 - TO ALESSANDRO MARTINS.pdf
RECOGNITION AWARD 13 - TO ALESSANDRO MARTINS.pdfRECOGNITION AWARD 13 - TO ALESSANDRO MARTINS.pdf
RECOGNITION AWARD 13 - TO ALESSANDRO MARTINS.pdf
 
Jill Pizzola's Tenure as Senior Talent Acquisition Partner at THOMSON REUTERS...
Jill Pizzola's Tenure as Senior Talent Acquisition Partner at THOMSON REUTERS...Jill Pizzola's Tenure as Senior Talent Acquisition Partner at THOMSON REUTERS...
Jill Pizzola's Tenure as Senior Talent Acquisition Partner at THOMSON REUTERS...
 
Introducing Gopay Mobile App For Environment.pptx
Introducing Gopay Mobile App For Environment.pptxIntroducing Gopay Mobile App For Environment.pptx
Introducing Gopay Mobile App For Environment.pptx
 
lab.123456789123456789123456789123456789
lab.123456789123456789123456789123456789lab.123456789123456789123456789123456789
lab.123456789123456789123456789123456789
 
Job Finding Apps Everything You Need to Know in 2024
Job Finding Apps Everything You Need to Know in 2024Job Finding Apps Everything You Need to Know in 2024
Job Finding Apps Everything You Need to Know in 2024
 
一比一原版(UBC毕业证)不列颠哥伦比亚大学毕业证如何办理
一比一原版(UBC毕业证)不列颠哥伦比亚大学毕业证如何办理一比一原版(UBC毕业证)不列颠哥伦比亚大学毕业证如何办理
一比一原版(UBC毕业证)不列颠哥伦比亚大学毕业证如何办理
 
Leadership Ambassador club Adventist module
Leadership Ambassador club Adventist moduleLeadership Ambassador club Adventist module
Leadership Ambassador club Adventist module
 
一比一原版布拉德福德大学毕业证(bradford毕业证)如何办理
一比一原版布拉德福德大学毕业证(bradford毕业证)如何办理一比一原版布拉德福德大学毕业证(bradford毕业证)如何办理
一比一原版布拉德福德大学毕业证(bradford毕业证)如何办理
 
labb123456789123456789123456789123456789
labb123456789123456789123456789123456789labb123456789123456789123456789123456789
labb123456789123456789123456789123456789
 
一比一原版(SFU毕业证)西蒙弗雷泽大学毕业证如何办理
一比一原版(SFU毕业证)西蒙弗雷泽大学毕业证如何办理一比一原版(SFU毕业证)西蒙弗雷泽大学毕业证如何办理
一比一原版(SFU毕业证)西蒙弗雷泽大学毕业证如何办理
 
Status of Women in Pakistan.pptxStatus of Women in Pakistan.pptx
Status of Women in Pakistan.pptxStatus of Women in Pakistan.pptxStatus of Women in Pakistan.pptxStatus of Women in Pakistan.pptx
Status of Women in Pakistan.pptxStatus of Women in Pakistan.pptx
 
一比一原版(QU毕业证)皇后大学毕业证如何办理
一比一原版(QU毕业证)皇后大学毕业证如何办理一比一原版(QU毕业证)皇后大学毕业证如何办理
一比一原版(QU毕业证)皇后大学毕业证如何办理
 
原版制作(RMIT毕业证书)墨尔本皇家理工大学毕业证在读证明一模一样
原版制作(RMIT毕业证书)墨尔本皇家理工大学毕业证在读证明一模一样原版制作(RMIT毕业证书)墨尔本皇家理工大学毕业证在读证明一模一样
原版制作(RMIT毕业证书)墨尔本皇家理工大学毕业证在读证明一模一样
 
A Guide to a Winning Interview June 2024
A Guide to a Winning Interview June 2024A Guide to a Winning Interview June 2024
A Guide to a Winning Interview June 2024
 
thyroid case presentation.pptx Kamala's Lakshaman palatial
thyroid case presentation.pptx Kamala's Lakshaman palatialthyroid case presentation.pptx Kamala's Lakshaman palatial
thyroid case presentation.pptx Kamala's Lakshaman palatial
 
一比一原版(TMU毕业证)多伦多都会大学毕业证如何办理
一比一原版(TMU毕业证)多伦多都会大学毕业证如何办理一比一原版(TMU毕业证)多伦多都会大学毕业证如何办理
一比一原版(TMU毕业证)多伦多都会大学毕业证如何办理
 
一比一原版(YU毕业证)约克大学毕业证如何办理
一比一原版(YU毕业证)约克大学毕业证如何办理一比一原版(YU毕业证)约克大学毕业证如何办理
一比一原版(YU毕业证)约克大学毕业证如何办理
 

Stakeholder management qb

  • 1. Question bank on Stakeholder Management PMBOK-5 1. Project stakeholder management includes all of the following except a. Identify the people, groups, or organizations that could impact or be impacted by the project. b. Analyze stakeholder expectations and their impact on the project. c. Develop appropriate management strategy for effectively engaging stakeholders in project decisions and execution. d. Develop strategies to avoid the incorporation of changes suggested by the stakeholders. 2. Project stakeholder management focuses on a. Continuous communication with the stakeholders to understand their needs and expectations. b. Addressing issues as they occur. c. Managing conflicting interests. d. Fostering appropriate stakeholder engagement in project decisions and activities. e. All of the above. 3. What should be the key project objective? a. Completion of project within schedule and time. b. Avoid scope changes in the project. c. Stakeholder satisfaction d. Completion of project within cost. 4. The process of identifying the people ,groups, or organizations that could impact or be impacted by a decision ,activity, or outcome of the project and analyzing and documenting relevant information regarding their interests,involvement,interdependencies, influence and potential impact on the project is a. Control Stakeholder Management
  • 2. b. Manage stakeholder Engagement c. Identify stakeholders d. Stakeholder Analysis. 5. The process of development of appropriate management strategies to effectively engage stakeholders throughout the project lifecycle, based on analysis of their needs, interests and potential impact on project success. a. Control stakeholder Management b. Manage stakeholder engagement c. Plan stakeholder management d. Control stakeholder engagement. 6. The process of communicating and working with stakeholders to meet their needs and expectations, address issues as they occur, and foster appropriate stakeholders engagement in project activities throughout the project lifecycle is called a. Control stakeholder engagement b. Manage stakeholder engagement c. Plan stakeholder management d. Control stakeholder Engagement. 7. The process of monitoring overall project stakeholder relationships and adjusting strategies and plans for engaging stakeholders is called a. Control stakeholder engagement b. Manage stakeholder engagement c. Plan stakeholder management d. Control stakeholder engagement. 8. Which of the following is not input to the Identify stakeholders process a. Project charter b. Project documents c. Procurement documents d. Organizational process assets e. Enterprise environmental factors.
  • 3. 9. Which of the following is not a tool & technique for the Identify stakeholder’s process? a. Stakeholders analysis b. Expert judgment c. Meetings d. Analytical techniques. 10. Stakeholder register is an input to all of the following except a. Collect requirements. b. Plan quality management. c. Plan communication management & Control Communications. d. Plan risk management & identify risks. 11. Project charter provides information about a. Internal & external parties related with the project b. Parties affected by the result or the execution of the project c. Groups or departments participating in the project d. Other people or organizations affected by the project e. All of the above. 12. All of the following are EEF except a. Organizational Culture and structure b. Govt. or industry standards c. Global regional or local trends d. Stakeholders register from other projects. 13. All of the following are OPA except a. Stakeholders register templates b. Lessons learnt from previous projects c. Stakeholders register from previous projects d. Organizational culture and structure.
  • 4. 14. Which of the following are not classification model for stakeholder analysis a. Power /interest grid model. b. Power/influence grid model. c. Influence /Impact grid model. d. Influence/Interest grid model. 15. Salience Model of classification of the stakeholders focuses on a. Classifying the stakeholders based on their level of authority and level of concern regarding the project outcomes. b. Classifying the stakeholders based on their active involvement and the level of authority. c. Classifying the stakeholders on the basis of their active involvement in the project and their ability to effect changes to the project planning and execution. d. Classifying the stakeholders based on their power, urgency, and legitimacy. 16. If a stakeholder has High power and high interest in the project then a. Monitor them b. Keep them informed c. Keep them satisfied d. Manage closely 17. If a stakeholder has high interest in the project and low power then a. Monitor them. b. Keep them informed. c. Keep them satisfied. d. Manage them closely. 18.If a stakeholder has high power and low interest in the project then a. Monitor them b. Keep them informed c. Manage them closely d. Keep them satisfied.
  • 5. 19. The stakeholders register contains all details related to the identified stakeholders except a. Identification information-Name, Organization, position, location, role in the project, contact information. b. Assessment information-Major requirements, main expectations, potential influence in the phase in the lifecycle with the most interest. c. Stakeholder classification-Internal/external, supporter/neutral/resister. d. Stakeholder management plan. Note-The key benefit of plan stakeholder management is that it gives clear actionable plan to interact with project stakeholders. 20. All of the following are the inputs to the Plan stakeholders management process except a. Project management plan b. Stakeholders register c. EEF d. OPA e. Project documents 21. All of the following are the tools and techniques of Plan stakeholder management except a. Expert judgment b. Meetings c. Stakeholder analysis d. Analytical techniques 22. Which of the following is the output of the plan stakeholder management process a. OPA updates b. EEF updates c. Project document updates d. Project management plan updates.
  • 6. 23. As input to the plan stakeholder management project management plan provides all of the following except a. Life cycle selected for the project and the processes that will be applied to each phase. b. Description of how work will be executed to achieve project objectives c. Description of how human resources requirements will be met how roles and responsibilities reporting relationships and staffing management plan will be addressed and structured in the project. d. How stakeholder register will be updated. e. How change management plan will be implemented. f. Need and techniques for communications among stakeholders. 24. Expert judgment can be obtained though a. One to one meetings b. Interviews c. Focus groups d. Surveys e. All of the above 25. The stakeholder management plan provides the following information a. Desired and current engagement levels of the key stakeholders b. Scope and impact of changes to stakeholders c. Identified interrelationships and potential overlap between stakeholders. d. Stakeholder’s communication requirements for the current project phase. e. All of the above. 26. The stakeholder management plan provides the following information a. Information’s to be distributed to stakeholders b. Reason for the distribution of a particular information c. Time frame and the frequency for the information to be distributed. d. Method for updating and refining the stakeholder management plan e. All of the above.
  • 7. 27. The stakeholder management plan is an input to which of the following process a. Collect requirements b. Control Stakeholder engagement c. Plan procurement management d. Plan risk management 28.All of the following are inputs to the manage stakeholder engagement process except a. SH engagement plan b. Communications management plan c. Change request d. Organizational process assets. 29.Which of the following is not T&T for the manage SH engagement process a. Communication skills b. Interpersonal skills c. Management skills d. Communication methods 30. Which of the following is not an output of the manage stakeholder engagement a. Stakeholder management plan updates b. OPA updates c. Project documents updates d. Project management plan updates. 31Issue log is an input to all of the following process except a. Control stakeholder engagement b. Manage project team c. Control communications d. Develop project management plan. 32 Stakeholder management plan provides the following a. Guidance on how the various stake holders will be involved in the project.
  • 8. b. It provides the methods and technologies used in the stakeholder communication. c. Used to determine the level of interactions of various stakeholders. d. It helps define the strategy for identifying and managing stakeholders throughout the project lifecycle. e. All of the above. 33. The communication management plan provides a. Stakeholder’s communication requirements. b. Information to be communicated including the language, format, and content and level of detail. c. Reason for distribution of information. d. Person and groups who will receive information e. Escalation process f. All the above. 34. All of the following are Organizational process assets except a. Organizational communication requirements. b. Issue management procedures. c. Change control procedures. d. Historical information about previous projects. e. All of the above. 35. The OPA updates includes a. Stakeholders notifications b. Project reports c. Project presentations d. Project records e. Feedback from stakeholders & Lessons learnt.
  • 9. f. All of the above 36. The primary observations and measurements identified during activities being performed to carry out the project work is called a. Reported %of work completed. b. Work performance data. c. Work performance information. d. Work performance Index. 37. Project documents which are used as input to the control stakeholder management process are a. Project schedule b. Stakeholder register c. Issues log d. Change log e. Project communications f. All of the above. 38. All of the following are examples of work performance information except a. Status of deliverables b. Implementation status of change requests c. Forecasted estimates to compete d. Number of change requests. Note- The recommended corrective actions include changes that bring the expected future performance in line with the project management plan. The recommended preventive actions can reduce the probability of future negative project performance.
  • 10. 39. OPA updates includes updates on stakeholder notifications, project reports, project presentation, Feedback from stakeholders, lessons learnt documentation. Answers Q.No Answers Q.No Answers Q.No Answers Q.No Answers 1 D 11 E 21 C 31 D 2 E 12 D 22 C 32 E 3 C 13 D 23 A 33 F 4 C 14 D 24 E 34 E 5 C 15 D 25 E 35 F 6 B 16 D 26 E 36 B 7 A 17 B 27 A 37 F 8 B 18 D 28 C 38 D 9 D 19 D 29 A 10 C 20 E 30 A