Chapters 13 & 14 Chapter 13 Q1. You are the project manager of the GUY Project for your organization. This project has recently been chartered and you’re starting the process of stakeholder identification. In this process, you’re working with your project team, some of the known stakeholders, and your project sponsor. Which one of the following inputs will you NOT need for the stakeholder identification process? B. The communications management plan is not an input to the stakeholder identification process. Q2. Beth is the project manager for a large health care project. She is working with the project sponsor to define the steps she’ll use to perform stakeholder analysis. Which of the following correctly defines the steps for stakeholder analysis? C. Of all the choices presented, C is the best answer. Stakeholder identification starts with the project manager identifying and documenting the stakeholders’ contact information, knowledge, expectations of the project, and their level of influence over project decisions. Then, the project manager must prioritize and classify stakeholders based on their power, influence, expectations, and concerns for the project. Finally, Beth should plan for managing the stakeholders based on possible negative or positive scenarios in the project that may affect the stakeholders. Q3. You are the project manager for your organization. Management has asked you to create a stakeholder classification model to show the amount of authority stakeholders have over project decisions in relation to how much their political capital and position in the company could affect the project. What type of stakeholder classification model should you create? A. Management is asking you to create a power/influence grid. Evaluating the amount of power and influence a stakeholder has over the project will determine where the stakeholder is placed on the grid. Stakeholders with high power and high influence are top priority. Stakeholders with little power and influence are still considered, but they have less priority than other stakeholders in the project. Q4. Henry has been tasked to create a salience model for his project. This model defines three characteristics for project stakeholders. Which one of the following is NOT one of the three characteristics of the stakeholders mapped in the salience model? D. A salience model plots out a person’s power, urgency, and legitimacy in the project. It does not include their influence. Q5. You are the project manager of a large technology project for your company. This project will span the United States and parts of Europe. There are key stakeholders in all countries represented. As part of your stakeholder analysis you’d like to create a document that captures all of the stakeholders’ contact information, assessment information, and classification in the project. What type of document are you creating? C. You are creating a stakeholder register. The stakeholder register is the on ...