SlideShare a Scribd company logo
Project Charter
www.optimumfx.com
Intent
• To provide a framework with which a project team can
detail with great clarity the project to be undertaken and
then ultimately evaluate their results.
Why create a project charter?
• Provides the team with a template to clearly define the project
and understand their roles within it.
• Generates buy in from the team as the objectives are mutually
agreed
• Ensures project objectives are targeted and realistic (SMART)
• Will serve as a good reference document to retain clarity
throughout longer timescale projects and during project
evaluation updates
• To identify any constraints that may effect the project outcome
such as volume, resourcing, skills gaps, specific tools
• Team can define/agree key dates for status updates and who
will be involved
Project charter framework
Project title: Date: 01/01/2015
Prepared by: Version: 1.0
Evaluation (actual results vs goal): Evaluation score:
A line control score of 92% was achieved within
7 months. Remaining 8% not achievable due to
Line OEE increase measured as 5.2% largely
achieved through cascade restart from packer to
labeller and labeller to filler. Accumulation was also
maximised through sensor adjustment.
How well did I perform in this project?
Score: 9 (Scale of 0-10)
Score: 9 (Scale of 0-10)
older equipment functionality.
How well did the team perform?
Initial review to be held in week 4
Update email issued by 4:00pm every Friday
New product trials week 10
Key: Team leader (days)
Automation engineer/Line STO
Support: Line control consultant
Machine OEM engineers
5 levels of control methodology
Siemens PLC programming skills
Any actions requiring capital investment will be
reviewed with ops manager for sign off.
Team will present initial audit results and
improvement actions within 2 weeks of project
start.
Weekly progress updates will be issued via email.
required technical skills available.
Any line downtime that is required will be factored
into the production plan and provided.
Volume available to test the impact of changes.
No reasonable capital expenditure will be denied,
however the focus should be on extracting the
most from the hardware and software
functionality that currently exists.
A line control team will be formed with all the
not being present
Line control team members will be expected on
average to devote 70-80% of their time to this
project within the first month and 30-50%
thereafter.
Volume for certain bottle sizes and or pack types
Re-audit completed and improvement results
Increase in line utilisation not achieved
Line reliability and wear reduction opportunities
not identified
Zero reduction in machine MTBF through line
control.
Project Charter
Background to the project/current state:
(Include KPI's & Potential cost savings "SMART")
90%+ line control score within 6 months
5% increase to line OEE
Increased equipment reliability and wear reduction
Minimised impact of energy saving functionality
on critical machine restart following a stoppage.
Implementing the 5 levels of control on PET Line 1
John Smith
Desired outcome and expected results:
(Include KPI's)
A year ago Line 1 was upgraded with a new filler,
bottle conveyors, labeller and packer.
Although the updated equipment met its
acceptance trial targets it is believed that
increased line utilisation and equipment reliability
can be achieved through line control
Key dates in the project/outline plan: Key project personnel/support required:
Criteria of success: Consequences of failure:
Assumptions: Constraints:
Guidelines/ground rules: Tools to be applied:
implementation.
Line OEE is currently at 65%.
identified.
Audit documents completed including reaction
timings, for all pack types and bottle sizes.
Improvement opportunities identified/prioritised
and all achievable improvement work complete.
A Project without a charter!
Setting the scene:
As a manager you decide to trigger an improvement project on your site. In
your head you have a clear idea of what you are looking to achieve and you
assign a team of people to it. You verbally outline your requirements at a kick
off meeting and define a target date but no charter is created.
Possible results:
• Over the coming weeks the team loose clarity on what the project objectives
are and fail to meet them
• Team buy in is limited and the purpose/benefits of the project are not clearly
understood
• Specific skills are required that are not present within the project team and
this constrains the project whilst additional resource is made available
• Due to a lack of clearly defined ground rules some of the team loose focus
and begin to prioritise other responsibilities, resulting in the project slipping
further behind schedule.
Result - Project targets not met!

More Related Content

What's hot

PROJECT CHARTER
PROJECT CHARTERPROJECT CHARTER
PROJECT CHARTER
Muneeb HaXan
 
06. Project Management Process Groups
06. Project Management Process Groups06. Project Management Process Groups
06. Project Management Process Groups
BhuWan Khadka
 
Project Management Concepts (from PMBOK 5th Ed)
Project Management Concepts (from PMBOK 5th Ed)Project Management Concepts (from PMBOK 5th Ed)
Project Management Concepts (from PMBOK 5th Ed)
Jeremy Jay Lim
 
Project Closure Checklist
Project Closure ChecklistProject Closure Checklist
Project Closure Checklist
Anand Subramaniam
 
Project Governance Framework PowerPoint Presentation Slides
Project Governance Framework PowerPoint Presentation SlidesProject Governance Framework PowerPoint Presentation Slides
Project Governance Framework PowerPoint Presentation Slides
SlideTeam
 
Project Management and Process
Project Management and ProcessProject Management and Process
Project Management and Process
Muhammad Rehman
 
05. Project And Organizational Structure
05. Project And Organizational Structure05. Project And Organizational Structure
05. Project And Organizational Structure
BhuWan Khadka
 
Project planning and project work plan
Project planning and project work planProject planning and project work plan
Project planning and project work plan
Ferdinand Importado, CPA, MBA
 
Project Scope Management
Project Scope ManagementProject Scope Management
Project Scope Management
Andersson Lujan Ojeda
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project Management
Slav Karaslavov
 
Project Closure Process Steps PowerPoint Presentation Slides
Project Closure Process Steps PowerPoint Presentation Slides Project Closure Process Steps PowerPoint Presentation Slides
Project Closure Process Steps PowerPoint Presentation Slides
SlideTeam
 
PMP Lecture 1: Introduction to Project Management
PMP Lecture 1: Introduction to Project ManagementPMP Lecture 1: Introduction to Project Management
PMP Lecture 1: Introduction to Project Management
Mohamed Loey
 
Company project kick off
Company project kick off Company project kick off
Company project kick off
Michael James Cyrus
 
Software Project Management: Project Planning
Software Project Management: Project PlanningSoftware Project Management: Project Planning
Software Project Management: Project Planning
Minhas Kamal
 
Basics of project management
Basics of project managementBasics of project management
Basics of project management
debmithu
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
Ajeesh Mk
 
Software Project Management: Project Charter
Software Project Management: Project CharterSoftware Project Management: Project Charter
Software Project Management: Project Charter
Minhas Kamal
 
Triple constraint
Triple constraintTriple constraint
Triple constraint
sonali talkar
 
Program management scope management
Program management   scope managementProgram management   scope management
Program management scope management
Julen Mohanty
 

What's hot (20)

PROJECT CHARTER
PROJECT CHARTERPROJECT CHARTER
PROJECT CHARTER
 
06. Project Management Process Groups
06. Project Management Process Groups06. Project Management Process Groups
06. Project Management Process Groups
 
Project Management Concepts (from PMBOK 5th Ed)
Project Management Concepts (from PMBOK 5th Ed)Project Management Concepts (from PMBOK 5th Ed)
Project Management Concepts (from PMBOK 5th Ed)
 
Project Closure Checklist
Project Closure ChecklistProject Closure Checklist
Project Closure Checklist
 
Project Governance Framework PowerPoint Presentation Slides
Project Governance Framework PowerPoint Presentation SlidesProject Governance Framework PowerPoint Presentation Slides
Project Governance Framework PowerPoint Presentation Slides
 
Project Management and Process
Project Management and ProcessProject Management and Process
Project Management and Process
 
05. Project And Organizational Structure
05. Project And Organizational Structure05. Project And Organizational Structure
05. Project And Organizational Structure
 
Project planning and project work plan
Project planning and project work planProject planning and project work plan
Project planning and project work plan
 
Project Scope Management
Project Scope ManagementProject Scope Management
Project Scope Management
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project Management
 
Project Closure Process Steps PowerPoint Presentation Slides
Project Closure Process Steps PowerPoint Presentation Slides Project Closure Process Steps PowerPoint Presentation Slides
Project Closure Process Steps PowerPoint Presentation Slides
 
PMP Lecture 1: Introduction to Project Management
PMP Lecture 1: Introduction to Project ManagementPMP Lecture 1: Introduction to Project Management
PMP Lecture 1: Introduction to Project Management
 
Company project kick off
Company project kick off Company project kick off
Company project kick off
 
Software Project Management: Project Planning
Software Project Management: Project PlanningSoftware Project Management: Project Planning
Software Project Management: Project Planning
 
Basics of project management
Basics of project managementBasics of project management
Basics of project management
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
 
Project closeout-report
Project closeout-reportProject closeout-report
Project closeout-report
 
Software Project Management: Project Charter
Software Project Management: Project CharterSoftware Project Management: Project Charter
Software Project Management: Project Charter
 
Triple constraint
Triple constraintTriple constraint
Triple constraint
 
Program management scope management
Program management   scope managementProgram management   scope management
Program management scope management
 

Viewers also liked

Project Charter Guide
Project Charter GuideProject Charter Guide
Project Charter Guide
Casual Project Management
 
Social Media Project Charter Template
Social Media Project Charter TemplateSocial Media Project Charter Template
Social Media Project Charter Template
Demand Metric
 
Project charter sample
Project charter sampleProject charter sample
Project charter sample
Gregory Weiss
 
Project Charter Template
Project Charter TemplateProject Charter Template
Project Charter Template
dmdk12
 
Project scope and requirements management
Project scope and requirements managementProject scope and requirements management
Project scope and requirements management
tictactoe123
 
Mobile Marketing Project Charter
Mobile Marketing Project CharterMobile Marketing Project Charter
Mobile Marketing Project Charter
Demand Metric
 
EDLD 5388 Project Charter
EDLD 5388 Project CharterEDLD 5388 Project Charter
EDLD 5388 Project CharterLisa Costello
 
Warwick Gap Project Charter
Warwick Gap Project CharterWarwick Gap Project Charter
Warwick Gap Project CharterPetros Leandros
 
Project Charter - Weddle
Project Charter - WeddleProject Charter - Weddle
Project Charter - WeddleJoanne Weddle
 
09 project charter
09 project charter09 project charter
09 project charterAinul Yaqin
 
Project Charter
Project CharterProject Charter
Project Charter
As Faizin
 
Final Paper #4.Doc Project Management
Final Paper #4.Doc Project ManagementFinal Paper #4.Doc Project Management
Final Paper #4.Doc Project Management
joshg30
 
Scrum - A Short Tour
Scrum - A Short TourScrum - A Short Tour
Scrum - A Short Tour
Vineet Patni
 
Project charter digitalisasi dokumen
Project charter digitalisasi dokumen Project charter digitalisasi dokumen
Project charter digitalisasi dokumen smk negeri 42 jakarta
 
Network Guardians Project Charter Final Ver.
Network Guardians Project Charter Final Ver.Network Guardians Project Charter Final Ver.
Network Guardians Project Charter Final Ver.Joseph C. Douglas
 
Presentation project management
Presentation project managementPresentation project management
Presentation project managementFlobz Caloy
 
Project Management - A few things I learned about it
Project Management - A few things I learned about itProject Management - A few things I learned about it
Project Management - A few things I learned about it
Paolo Barone
 

Viewers also liked (20)

Project Charter Guide
Project Charter GuideProject Charter Guide
Project Charter Guide
 
Social Media Project Charter Template
Social Media Project Charter TemplateSocial Media Project Charter Template
Social Media Project Charter Template
 
Project Charter
Project CharterProject Charter
Project Charter
 
Project charter sample
Project charter sampleProject charter sample
Project charter sample
 
Project Charter Template
Project Charter TemplateProject Charter Template
Project Charter Template
 
Project scope and requirements management
Project scope and requirements managementProject scope and requirements management
Project scope and requirements management
 
Mobile Marketing Project Charter
Mobile Marketing Project CharterMobile Marketing Project Charter
Mobile Marketing Project Charter
 
EDLD 5388 Project Charter
EDLD 5388 Project CharterEDLD 5388 Project Charter
EDLD 5388 Project Charter
 
Warwick Gap Project Charter
Warwick Gap Project CharterWarwick Gap Project Charter
Warwick Gap Project Charter
 
Project Charter - Weddle
Project Charter - WeddleProject Charter - Weddle
Project Charter - Weddle
 
Project Charter
Project CharterProject Charter
Project Charter
 
09 project charter
09 project charter09 project charter
09 project charter
 
Project Charter
Project CharterProject Charter
Project Charter
 
Aula 8 - Gerenciamento da Comunicação
Aula 8 - Gerenciamento da ComunicaçãoAula 8 - Gerenciamento da Comunicação
Aula 8 - Gerenciamento da Comunicação
 
Final Paper #4.Doc Project Management
Final Paper #4.Doc Project ManagementFinal Paper #4.Doc Project Management
Final Paper #4.Doc Project Management
 
Scrum - A Short Tour
Scrum - A Short TourScrum - A Short Tour
Scrum - A Short Tour
 
Project charter digitalisasi dokumen
Project charter digitalisasi dokumen Project charter digitalisasi dokumen
Project charter digitalisasi dokumen
 
Network Guardians Project Charter Final Ver.
Network Guardians Project Charter Final Ver.Network Guardians Project Charter Final Ver.
Network Guardians Project Charter Final Ver.
 
Presentation project management
Presentation project managementPresentation project management
Presentation project management
 
Project Management - A few things I learned about it
Project Management - A few things I learned about itProject Management - A few things I learned about it
Project Management - A few things I learned about it
 

Similar to Project charter

Microsoft Dynamics AX Implementation Stabilization Case Studies
Microsoft Dynamics AX Implementation Stabilization Case StudiesMicrosoft Dynamics AX Implementation Stabilization Case Studies
Microsoft Dynamics AX Implementation Stabilization Case Studies
meritweb
 
3&4. project scope management at project.ppt
3&4. project scope management at project.ppt3&4. project scope management at project.ppt
3&4. project scope management at project.ppt
GoharSaeed6
 
Is your project not going well this will help you get it back on track
Is your project not going well this will help you get it back on trackIs your project not going well this will help you get it back on track
Is your project not going well this will help you get it back on track
Project Management Solutions
 
Project control and process instrumentation
Project control and process instrumentationProject control and process instrumentation
Project control and process instrumentation
Kuppusamy P
 
Presentation by meghna jadhav
Presentation by meghna jadhavPresentation by meghna jadhav
Presentation by meghna jadhavPMI_IREP_TP
 
Project Management ORION Systems
Project Management ORION SystemsProject Management ORION Systems
Project Management ORION Systemsreeza fazily
 
Project-Charter_Rubab Tanveer_PTC_AKF_PDF
Project-Charter_Rubab Tanveer_PTC_AKF_PDFProject-Charter_Rubab Tanveer_PTC_AKF_PDF
Project-Charter_Rubab Tanveer_PTC_AKF_PDFRubab Tanveer
 
Do it, sf state project lifecycle management (plm) v1.19 091012
Do it, sf state project lifecycle management (plm) v1.19 091012Do it, sf state project lifecycle management (plm) v1.19 091012
Do it, sf state project lifecycle management (plm) v1.19 091012
satish526
 
Plan_QualityManagement
Plan_QualityManagementPlan_QualityManagement
Plan_QualityManagementFahad Saleem
 
Hello Class- This is a very rough draft of the assignment. I have
Hello Class- This is a very rough draft of the assignment. I have Hello Class- This is a very rough draft of the assignment. I have
Hello Class- This is a very rough draft of the assignment. I have
SusanaFurman449
 
Development methodologies
Development methodologiesDevelopment methodologies
Development methodologies
missstevenson01
 
Program challenges - TPM Problem Solver
Program challenges - TPM Problem SolverProgram challenges - TPM Problem Solver
Program challenges - TPM Problem Solver
Sachidananda Panda (SPC5, SP, CSM)
 
MandC.pdf
MandC.pdfMandC.pdf
MandC.pdf
sadsfcdvdfssd
 
Dev ops I Best Practices I NuggetHub
Dev ops I Best Practices I NuggetHubDev ops I Best Practices I NuggetHub
Dev ops I Best Practices I NuggetHub
RichardNowack
 
Developing Standards for Enterprise Schedule Quality
Developing Standards for Enterprise Schedule QualityDeveloping Standards for Enterprise Schedule Quality
Developing Standards for Enterprise Schedule Quality
Acumen
 
Project Management Framework
Project Management FrameworkProject Management Framework
Project Management Framework
Rahul Sudame
 

Similar to Project charter (20)

Microsoft Dynamics AX Implementation Stabilization Case Studies
Microsoft Dynamics AX Implementation Stabilization Case StudiesMicrosoft Dynamics AX Implementation Stabilization Case Studies
Microsoft Dynamics AX Implementation Stabilization Case Studies
 
3&4. project scope management at project.ppt
3&4. project scope management at project.ppt3&4. project scope management at project.ppt
3&4. project scope management at project.ppt
 
Is your project not going well this will help you get it back on track
Is your project not going well this will help you get it back on trackIs your project not going well this will help you get it back on track
Is your project not going well this will help you get it back on track
 
Project control and process instrumentation
Project control and process instrumentationProject control and process instrumentation
Project control and process instrumentation
 
build-for-speed-brochure
build-for-speed-brochurebuild-for-speed-brochure
build-for-speed-brochure
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
 
Presentation by meghna jadhav
Presentation by meghna jadhavPresentation by meghna jadhav
Presentation by meghna jadhav
 
Project Management ORION Systems
Project Management ORION SystemsProject Management ORION Systems
Project Management ORION Systems
 
PAC Fast Track Implementation Program
PAC Fast Track Implementation ProgramPAC Fast Track Implementation Program
PAC Fast Track Implementation Program
 
Project-Charter_Rubab Tanveer_PTC_AKF_PDF
Project-Charter_Rubab Tanveer_PTC_AKF_PDFProject-Charter_Rubab Tanveer_PTC_AKF_PDF
Project-Charter_Rubab Tanveer_PTC_AKF_PDF
 
Do it, sf state project lifecycle management (plm) v1.19 091012
Do it, sf state project lifecycle management (plm) v1.19 091012Do it, sf state project lifecycle management (plm) v1.19 091012
Do it, sf state project lifecycle management (plm) v1.19 091012
 
Plan_QualityManagement
Plan_QualityManagementPlan_QualityManagement
Plan_QualityManagement
 
Hello Class- This is a very rough draft of the assignment. I have
Hello Class- This is a very rough draft of the assignment. I have Hello Class- This is a very rough draft of the assignment. I have
Hello Class- This is a very rough draft of the assignment. I have
 
Development methodologies
Development methodologiesDevelopment methodologies
Development methodologies
 
Pm audit and assessment approach final
Pm audit and assessment approach   finalPm audit and assessment approach   final
Pm audit and assessment approach final
 
Program challenges - TPM Problem Solver
Program challenges - TPM Problem SolverProgram challenges - TPM Problem Solver
Program challenges - TPM Problem Solver
 
MandC.pdf
MandC.pdfMandC.pdf
MandC.pdf
 
Dev ops I Best Practices I NuggetHub
Dev ops I Best Practices I NuggetHubDev ops I Best Practices I NuggetHub
Dev ops I Best Practices I NuggetHub
 
Developing Standards for Enterprise Schedule Quality
Developing Standards for Enterprise Schedule QualityDeveloping Standards for Enterprise Schedule Quality
Developing Standards for Enterprise Schedule Quality
 
Project Management Framework
Project Management FrameworkProject Management Framework
Project Management Framework
 

More from LineView Academy (was OFX Academy)

SIC (Short Interval Control) Methodology
SIC (Short Interval Control) MethodologySIC (Short Interval Control) Methodology
SIC (Short Interval Control) Methodology
LineView Academy (was OFX Academy)
 
Giving and receiving feedback - the methodology
Giving and receiving feedback - the methodologyGiving and receiving feedback - the methodology
Giving and receiving feedback - the methodology
LineView Academy (was OFX Academy)
 
Line Crew Optimisation Methodology
Line Crew Optimisation MethodologyLine Crew Optimisation Methodology
Line Crew Optimisation Methodology
LineView Academy (was OFX Academy)
 
RACI Methodology
RACI MethodologyRACI Methodology
Actionable information 3
Actionable information 3Actionable information 3
Actionable information 3
LineView Academy (was OFX Academy)
 
Actionable information 2
Actionable information 2Actionable information 2
Actionable information 2
LineView Academy (was OFX Academy)
 
Actionable information 1
Actionable information 1Actionable information 1
Actionable information 1
LineView Academy (was OFX Academy)
 
SERVE model
SERVE modelSERVE model
Paradigm thinking
Paradigm thinkingParadigm thinking
Neurological levels
Neurological levelsNeurological levels
Helicopter leadership
Helicopter leadershipHelicopter leadership
Helicopter leadership
LineView Academy (was OFX Academy)
 
Evolving consciousness
Evolving consciousnessEvolving consciousness
Evolving consciousness
LineView Academy (was OFX Academy)
 
AADACM - Changing habits
AADACM - Changing habitsAADACM - Changing habits
AADACM - Changing habits
LineView Academy (was OFX Academy)
 
Creating a high five team
Creating a high five teamCreating a high five team
Creating a high five team
LineView Academy (was OFX Academy)
 
Performance management
Performance managementPerformance management
Performance management
LineView Academy (was OFX Academy)
 
Developing a sustainable CI culture
Developing a sustainable CI cultureDeveloping a sustainable CI culture
Developing a sustainable CI culture
LineView Academy (was OFX Academy)
 
Meeting auditing skills
Meeting auditing skillsMeeting auditing skills
Meeting auditing skills
LineView Academy (was OFX Academy)
 
Auditing meetings
Auditing meetingsAuditing meetings

More from LineView Academy (was OFX Academy) (20)

SIC (Short Interval Control) Methodology
SIC (Short Interval Control) MethodologySIC (Short Interval Control) Methodology
SIC (Short Interval Control) Methodology
 
Giving and receiving feedback - the methodology
Giving and receiving feedback - the methodologyGiving and receiving feedback - the methodology
Giving and receiving feedback - the methodology
 
Line Crew Optimisation Methodology
Line Crew Optimisation MethodologyLine Crew Optimisation Methodology
Line Crew Optimisation Methodology
 
RACI Methodology
RACI MethodologyRACI Methodology
RACI Methodology
 
Actionable information 3
Actionable information 3Actionable information 3
Actionable information 3
 
Actionable information 2
Actionable information 2Actionable information 2
Actionable information 2
 
Actionable information 1
Actionable information 1Actionable information 1
Actionable information 1
 
SERVE model
SERVE modelSERVE model
SERVE model
 
Paradigm thinking
Paradigm thinkingParadigm thinking
Paradigm thinking
 
Neurological levels
Neurological levelsNeurological levels
Neurological levels
 
Living in the present
Living in the presentLiving in the present
Living in the present
 
Helicopter leadership
Helicopter leadershipHelicopter leadership
Helicopter leadership
 
Evolving consciousness
Evolving consciousnessEvolving consciousness
Evolving consciousness
 
AADACM - Changing habits
AADACM - Changing habitsAADACM - Changing habits
AADACM - Changing habits
 
Creating a high five team
Creating a high five teamCreating a high five team
Creating a high five team
 
Situaltional leadership
Situaltional leadershipSitualtional leadership
Situaltional leadership
 
Performance management
Performance managementPerformance management
Performance management
 
Developing a sustainable CI culture
Developing a sustainable CI cultureDeveloping a sustainable CI culture
Developing a sustainable CI culture
 
Meeting auditing skills
Meeting auditing skillsMeeting auditing skills
Meeting auditing skills
 
Auditing meetings
Auditing meetingsAuditing meetings
Auditing meetings
 

Recently uploaded

TCS AI for Business Study – Key Findings
TCS AI for Business Study – Key FindingsTCS AI for Business Study – Key Findings
TCS AI for Business Study – Key Findings
Tata Consultancy Services
 
W.H.Bender Quote 65 - The Team Member and Guest Experience
W.H.Bender Quote 65 - The Team Member and Guest ExperienceW.H.Bender Quote 65 - The Team Member and Guest Experience
W.H.Bender Quote 65 - The Team Member and Guest Experience
William (Bill) H. Bender, FCSI
 
Modern Database Management 12th Global Edition by Hoffer solution manual.docx
Modern Database Management 12th Global Edition by Hoffer solution manual.docxModern Database Management 12th Global Edition by Hoffer solution manual.docx
Modern Database Management 12th Global Edition by Hoffer solution manual.docx
ssuserf63bd7
 
Founder-Game Director Workshop (Session 1)
Founder-Game Director  Workshop (Session 1)Founder-Game Director  Workshop (Session 1)
Founder-Game Director Workshop (Session 1)
Amir H. Fassihi
 
Training- integrated management system (iso)
Training- integrated management system (iso)Training- integrated management system (iso)
Training- integrated management system (iso)
akaash13
 
Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...
Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...
Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...
CIOWomenMagazine
 
SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....
SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....
SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....
juniourjohnstone
 
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
gcljeuzdu
 
Leadership Ethics and Change, Purpose to Impact Plan
Leadership Ethics and Change, Purpose to Impact PlanLeadership Ethics and Change, Purpose to Impact Plan
Leadership Ethics and Change, Purpose to Impact Plan
Muhammad Adil Jamil
 

Recently uploaded (9)

TCS AI for Business Study – Key Findings
TCS AI for Business Study – Key FindingsTCS AI for Business Study – Key Findings
TCS AI for Business Study – Key Findings
 
W.H.Bender Quote 65 - The Team Member and Guest Experience
W.H.Bender Quote 65 - The Team Member and Guest ExperienceW.H.Bender Quote 65 - The Team Member and Guest Experience
W.H.Bender Quote 65 - The Team Member and Guest Experience
 
Modern Database Management 12th Global Edition by Hoffer solution manual.docx
Modern Database Management 12th Global Edition by Hoffer solution manual.docxModern Database Management 12th Global Edition by Hoffer solution manual.docx
Modern Database Management 12th Global Edition by Hoffer solution manual.docx
 
Founder-Game Director Workshop (Session 1)
Founder-Game Director  Workshop (Session 1)Founder-Game Director  Workshop (Session 1)
Founder-Game Director Workshop (Session 1)
 
Training- integrated management system (iso)
Training- integrated management system (iso)Training- integrated management system (iso)
Training- integrated management system (iso)
 
Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...
Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...
Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...
 
SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....
SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....
SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....
 
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
 
Leadership Ethics and Change, Purpose to Impact Plan
Leadership Ethics and Change, Purpose to Impact PlanLeadership Ethics and Change, Purpose to Impact Plan
Leadership Ethics and Change, Purpose to Impact Plan
 

Project charter

  • 2. Intent • To provide a framework with which a project team can detail with great clarity the project to be undertaken and then ultimately evaluate their results.
  • 3. Why create a project charter? • Provides the team with a template to clearly define the project and understand their roles within it. • Generates buy in from the team as the objectives are mutually agreed • Ensures project objectives are targeted and realistic (SMART) • Will serve as a good reference document to retain clarity throughout longer timescale projects and during project evaluation updates • To identify any constraints that may effect the project outcome such as volume, resourcing, skills gaps, specific tools • Team can define/agree key dates for status updates and who will be involved
  • 4. Project charter framework Project title: Date: 01/01/2015 Prepared by: Version: 1.0 Evaluation (actual results vs goal): Evaluation score: A line control score of 92% was achieved within 7 months. Remaining 8% not achievable due to Line OEE increase measured as 5.2% largely achieved through cascade restart from packer to labeller and labeller to filler. Accumulation was also maximised through sensor adjustment. How well did I perform in this project? Score: 9 (Scale of 0-10) Score: 9 (Scale of 0-10) older equipment functionality. How well did the team perform? Initial review to be held in week 4 Update email issued by 4:00pm every Friday New product trials week 10 Key: Team leader (days) Automation engineer/Line STO Support: Line control consultant Machine OEM engineers 5 levels of control methodology Siemens PLC programming skills Any actions requiring capital investment will be reviewed with ops manager for sign off. Team will present initial audit results and improvement actions within 2 weeks of project start. Weekly progress updates will be issued via email. required technical skills available. Any line downtime that is required will be factored into the production plan and provided. Volume available to test the impact of changes. No reasonable capital expenditure will be denied, however the focus should be on extracting the most from the hardware and software functionality that currently exists. A line control team will be formed with all the not being present Line control team members will be expected on average to devote 70-80% of their time to this project within the first month and 30-50% thereafter. Volume for certain bottle sizes and or pack types Re-audit completed and improvement results Increase in line utilisation not achieved Line reliability and wear reduction opportunities not identified Zero reduction in machine MTBF through line control. Project Charter Background to the project/current state: (Include KPI's & Potential cost savings "SMART") 90%+ line control score within 6 months 5% increase to line OEE Increased equipment reliability and wear reduction Minimised impact of energy saving functionality on critical machine restart following a stoppage. Implementing the 5 levels of control on PET Line 1 John Smith Desired outcome and expected results: (Include KPI's) A year ago Line 1 was upgraded with a new filler, bottle conveyors, labeller and packer. Although the updated equipment met its acceptance trial targets it is believed that increased line utilisation and equipment reliability can be achieved through line control Key dates in the project/outline plan: Key project personnel/support required: Criteria of success: Consequences of failure: Assumptions: Constraints: Guidelines/ground rules: Tools to be applied: implementation. Line OEE is currently at 65%. identified. Audit documents completed including reaction timings, for all pack types and bottle sizes. Improvement opportunities identified/prioritised and all achievable improvement work complete.
  • 5. A Project without a charter! Setting the scene: As a manager you decide to trigger an improvement project on your site. In your head you have a clear idea of what you are looking to achieve and you assign a team of people to it. You verbally outline your requirements at a kick off meeting and define a target date but no charter is created. Possible results: • Over the coming weeks the team loose clarity on what the project objectives are and fail to meet them • Team buy in is limited and the purpose/benefits of the project are not clearly understood • Specific skills are required that are not present within the project team and this constrains the project whilst additional resource is made available • Due to a lack of clearly defined ground rules some of the team loose focus and begin to prioritise other responsibilities, resulting in the project slipping further behind schedule. Result - Project targets not met!