Work Performance
Data
Work Performance
Information
Work Performance
Report
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
Definitions
Work Performance Data:
• The raw observations & measurements identified
during activities performed to carry out the project
work.
Work Performance Information:
• The performance data collected from various
controlling processes, analyzed in context &
integrated based on relationships across areas.
Work Performance Report:
• The physical or electronic representation of WPI
compiled in project documents, intended to generate
decision or raise issues, actions or awareness
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
What is Work Performance Data (WPD)?
Work
Performance
Data
The raw observations & measurements identified
during activities performed to carry out the
project work.
It is the raw data of the project’s status.
e.g. actual cost, actual duration etc.
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
How WPD is generated?
Work
Performance
Data
The compliance of requirements, non-conformities.
The number of change requests received, accepted
or rejected.
How many activities have been started, finished, &
status of current activities etc.
Cost parameter of project. E.g., work completed,
money spent to date, etc.
Testing & performance measurements. E.g.,
characteristics of product, quality metrics, number
of defects, rejection rate, etc.
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
How WPD is generated?
Work
Performance
Data
Distribution of communications reports, feedback
on report, etc.
Risk status, new identified risks, effectiveness of
risk response plan, contingency or management
reserve utilization, risk impact on schedule, cost,
and scope.
Procurement related activities. E.g., quality
standards met by seller, seller’s performance, etc.
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
How WPD is generated?
Work
Performance
Data
Executing PG ->
Direct and Manage
Project work
Work Performance
Data
Validate Scope Control Scope Control
Schedule
Control Cost Control Quality
Control
Communicatio
n
Control Risks Control
Stakeholder
Eng.
Control
Procurements
Monitoring &
Controlling PG
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
Project team status meeting
WPD -> Example
No of activities started,
finished
Work completed,
money spent.
Number of defects found,
the rejection rate
Risk status; new risks,
effectiveness of risk
response plan
Control Schedule –
identify delay
Control Cost – Analyses
cost of completed work
vs money spent
Control Quality – analyse
data & control quality
Control Risks – analyse
risk data & re-
asses/control risks
Monitoring & Controlling PG
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
12.3 Control Procurement ->Input->WPDWhat is Work Performance Information (WPI)?
Work
Performance
Information
The performance data collected from various controlling
processes, analyzed in context and integrated based on
relationships across areas
PM analyze the work performance data. Compare
planned performance with actual performance
E.g, Planned vs actual cost, planned vs actual duration
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
12.3 Control Procurement ->Input->WPDHow WPI is generated?
Work
Performance
Information
Review project’s progress; e.g. status of
deliverables, whether deliverable is accepted, how
project scope is performing against scope baseline.
Compare planned schedule with actual schedule.
You will see the planned duration for an activity,
and the time taken by the activity to be completed,
etc
PM will compare planned cost with actual cost of
this activity; i.e. planned cost versus actual cost
spent. You will also review other parameters such
as cost variance, cost performance, etc
PM will analyze planned versus actual technical
performance, such as how many defects, tolerance
& threshold was allowed, and how much it actually
is, how much rework is required, etc
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
12.3 Control Procurement ->Input->WPDHow WPI is generated?
Work
Performance
Information
Find the status and progress information of the
project & check if it is communicated or not.
Compare how risks have occurred, efficiency of risk
response plan, how much contingency money has
been spent, and what is remaining reserve, etc.
Review the seller’s performance against agreed
terms.
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
Monitoring & Controlling PG-> Control Process
12.3 Control Procurement ->Input->WPDHow WPI is generated?
Work
Performance
Information
Validate Scope Control Scope Control
Schedule
Control Cost Control Quality
Control
Communication
Control Risks Control
Stakeholder Eng.
Control
Procurements
Monitoring & Controlling
PG-> Monitor & Control
Project work
Work Performance
Information
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
Relation between WPD & WPI
• Executing PG ->Direct
& Manage process
• Generates WPD
• Monitor & Control PG -
> All Control process
• Generate WPI
•Monitoring & Controlling
PG-> Monitor & Control
Project work
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
WPI -> Example
Control Schedule – identify
delay & try controlling it
Control Cost – Analyses cost of
completed work against money
spent
Control Quality – analyse data
& control quality
Control Risks – analyse risk
data & re-asses/control risks
Compare, Assess, Document,
Forecast & Communicate
 SV, SPI
 CV, CPI
 Quality issues, corrective actions
 New risks, closed risk
User below T&T to initiate CR &
distribute reports:
 Expert Judgment
 Analytical Techniques
 PMIS &Meetings
Monitoring & Controlling PG ->
Control Processes
Monitoring & Controlling PG ->
Monitor & Control Project work
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
12.3 Control Procurement ->Input->WPDWhat is Work Performance Reports (WPR)?
Work
Performance
Reports
The physical or electronic representation of work performance
information compiled in project documents, intended to generate
decision or raise issues, actions or awareness
Are output of the Monitor & Control Project Work process, and
input to various managing and controlling processes.
Helps stakeholders with current status of the project and its
performance against the planned baselines.
If project is not progressing as planned, stakeholder may decide to
take any corrective action. E.g., extra funds or resources, or time
extension etc.
It can be given to stakeholders in a format desired by them and as
decided in the communication management plan.
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
12.3 Control Procurement ->Input->WPDHow WPR is generated?
Work
Performance
Reports
Manage Project
Team
Manage
Communication
Perform
Integrated
Change Control
Control Risks Control
Procurement
Monitoring & Controlling PG->
Monitor & Control Project work
Monitoring & Controlling PGExecuting PG
Work Performance
Reports
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
12.3 Control Procurement ->Input->WPDFormat of WPR
Work
Performance
Reports
Performance Reports may be any combination of these
formats:
Burndown
Chart
S-Curve Bar Charts
Histograms Tables Run Charts.
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
12.3 Control Procurement ->Input->WPDContent of WPR
Work
Performance
Reports
The content of the Performance Reports includes:
Percentage of the work completed
Balance work to be completed
Cost incurred
Balance of funds available
Balance of time available
Major risks that have occurred, or passed without occurring
Major remaining identified risks
Results of variance analysis: e.g. schedule variance and cost variance
Performance indexes: e.g. SPI , CPI
Forecasted fund required to complete the remaining work
Forecasted time required to complete the remaining work
Summary of major approved change requests.
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
WPR -> Example
Execute PG -> Manage
Communication:
Share Performance report to all
stakeholders through manage
communication process.
M & C PG -> Perform Integrated
Change Control:
Huge variance or major finding in
performance reports will warrant CR.
CCB
Monitoring & Controlling PG ->
Monitor & Control Project work
Stakeholders
Compare, Assess,
Document,
Forecast & Communicate
 SV, SPI
 CV, CPI
 Quality issues, corrective
actions
 New risks, closed risk
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
ReviewReview
Work performance data is a collection of raw information of the project’s status.
On the other hand, work performance information is a comparison of various
performances, like cost and schedule, etc.
Work performance data and work performance information are the basis for the
Performance Reports.
The Performance Reports are the reports given to project stakeholders to make them
aware of the current status and the forecasted progress of the project.
The Performance Reports show stakeholders how the project is going.
The forecast analysis of what they should expect if the project is allowed to keep
going in the same way, or what additional funds or resources may be required to
complete the project
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
ReviewSample Questions
1. Anand is working on CRM project for Dubai
Customs, even though you are using agile methods,
you realize you are preparing an extensive amount of
data and information. You regularly share data with
your project team. Your last team meeting focused on
the number of change requests and also the start and
finish dates of activities in your schedule. They are
examples of—
• A. Key performance indicators
• B. Work performance reports
• C. Work performance data
• D. Work performance information
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
ReviewSample Questions
2. The purpose of work performance data
in control communications is to present
results of comparative analysis to the—
• A. Performance measurement baseline
• B. Communications management plan
• C. Stakeholder management plan
• D. Deliverable status
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
ReviewSample Questions
3. Work performance information
includes all the following EXCEPT—
• A. Started deliverables
• B. Costs authorized and incurred
• C. Progress of deliverables
• D. Completed deliverables
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
ReviewSample Questions
4. Work performance information is an output
of which process?
• A. Manage risks
• B. Manage communications
• C. Control communications
• D. Report performance
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
ReviewSample Questions
5. Assume you want to optimize the work
performance reports you will use to manage
communications. You should do so by—
• A. Determining the most appropriate choice of
communications media
• B. Setting different communications techniques for
different stakeholder groups
• B. Ensuring the information is consistent with regulations
and standards
• D. Ensuring comprehensiveness, accuracy, and availability
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
ReviewSample Questions - Answers
1. c. Work performance data
• Work performance data are the raw observations and
measurements identified during activities performed to carry out
the work of the project. Other examples are the reported
percent of work physically completed, quality and technical
performance measures, number of defects, actual costs, and
actual durations. [Executing]
2. a. Performance measurement baseline
• Wok performance data are an input in control communications.
These data organize and summarize information gathered and
present the results of comparative analysis to the performance
measurement baseline. [Monitoring and Controlling]
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
ReviewSample Questions - Answers
3. b. Costs authorized and incurred
• Work performance information is an output of validate scope.
It emphasizes deliverables—whether or not they have started,
their progress, and ones that have finished or have been
accepted. [Monitoring and Controlling]
4. c. Control communications
• Work performance information, an output of control
communications, organizes and summaries performance data
such as status and progress information on the project at the
level required by stakeholders. This information next is
communicated to the appropriate stakeholders. [Monitoring
and Controlling]
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
ReviewSample Questions - Answers
5. d. Ensuring comprehensiveness,
accuracy, and availability
• Work performance reports are an input to manage
communications. They are a collection of project
performance and status information used to facilitate
discussion and create communications. They should
be comprehensive, accurate, and available in a timely
way. [Executing]
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
Additional Free Resources
Visit Slide Share website & you will find other Knowledge area presentation… Please share!!

PMP Key Exam Concepts WPD, WPI & WPR

  • 1.
    By: Anand Bobade;PMP, SCEA, MCP, CIW (nmbobade@gmail.com) PMP: Key Exam Concepts Series Crystal Clear understanding of key PMP concepts are essential to pass the PMP exam. These slide will help you to: • Visually learn key concepts • Get deep understand with real world examples • Sample Questions Work Performance Data Work Performance Information Work Performance Report
  • 2.
    By: Anand Bobade;PMP, SCEA, MCP, CIW (nmbobade@gmail.com) Definitions Work Performance Data: • The raw observations & measurements identified during activities performed to carry out the project work. Work Performance Information: • The performance data collected from various controlling processes, analyzed in context & integrated based on relationships across areas. Work Performance Report: • The physical or electronic representation of WPI compiled in project documents, intended to generate decision or raise issues, actions or awareness
  • 3.
    By: Anand Bobade;PMP, SCEA, MCP, CIW (nmbobade@gmail.com) What is Work Performance Data (WPD)? Work Performance Data The raw observations & measurements identified during activities performed to carry out the project work. It is the raw data of the project’s status. e.g. actual cost, actual duration etc.
  • 4.
    By: Anand Bobade;PMP, SCEA, MCP, CIW (nmbobade@gmail.com) How WPD is generated? Work Performance Data The compliance of requirements, non-conformities. The number of change requests received, accepted or rejected. How many activities have been started, finished, & status of current activities etc. Cost parameter of project. E.g., work completed, money spent to date, etc. Testing & performance measurements. E.g., characteristics of product, quality metrics, number of defects, rejection rate, etc.
  • 5.
    By: Anand Bobade;PMP, SCEA, MCP, CIW (nmbobade@gmail.com) How WPD is generated? Work Performance Data Distribution of communications reports, feedback on report, etc. Risk status, new identified risks, effectiveness of risk response plan, contingency or management reserve utilization, risk impact on schedule, cost, and scope. Procurement related activities. E.g., quality standards met by seller, seller’s performance, etc.
  • 6.
    By: Anand Bobade;PMP, SCEA, MCP, CIW (nmbobade@gmail.com) How WPD is generated? Work Performance Data Executing PG -> Direct and Manage Project work Work Performance Data Validate Scope Control Scope Control Schedule Control Cost Control Quality Control Communicatio n Control Risks Control Stakeholder Eng. Control Procurements Monitoring & Controlling PG
  • 7.
    By: Anand Bobade;PMP, SCEA, MCP, CIW (nmbobade@gmail.com) Project team status meeting WPD -> Example No of activities started, finished Work completed, money spent. Number of defects found, the rejection rate Risk status; new risks, effectiveness of risk response plan Control Schedule – identify delay Control Cost – Analyses cost of completed work vs money spent Control Quality – analyse data & control quality Control Risks – analyse risk data & re- asses/control risks Monitoring & Controlling PG
  • 8.
    By: Anand Bobade;PMP, SCEA, MCP, CIW (nmbobade@gmail.com) 12.3 Control Procurement ->Input->WPDWhat is Work Performance Information (WPI)? Work Performance Information The performance data collected from various controlling processes, analyzed in context and integrated based on relationships across areas PM analyze the work performance data. Compare planned performance with actual performance E.g, Planned vs actual cost, planned vs actual duration
  • 9.
    By: Anand Bobade;PMP, SCEA, MCP, CIW (nmbobade@gmail.com) 12.3 Control Procurement ->Input->WPDHow WPI is generated? Work Performance Information Review project’s progress; e.g. status of deliverables, whether deliverable is accepted, how project scope is performing against scope baseline. Compare planned schedule with actual schedule. You will see the planned duration for an activity, and the time taken by the activity to be completed, etc PM will compare planned cost with actual cost of this activity; i.e. planned cost versus actual cost spent. You will also review other parameters such as cost variance, cost performance, etc PM will analyze planned versus actual technical performance, such as how many defects, tolerance & threshold was allowed, and how much it actually is, how much rework is required, etc
  • 10.
    By: Anand Bobade;PMP, SCEA, MCP, CIW (nmbobade@gmail.com) 12.3 Control Procurement ->Input->WPDHow WPI is generated? Work Performance Information Find the status and progress information of the project & check if it is communicated or not. Compare how risks have occurred, efficiency of risk response plan, how much contingency money has been spent, and what is remaining reserve, etc. Review the seller’s performance against agreed terms.
  • 11.
    By: Anand Bobade;PMP, SCEA, MCP, CIW (nmbobade@gmail.com) Monitoring & Controlling PG-> Control Process 12.3 Control Procurement ->Input->WPDHow WPI is generated? Work Performance Information Validate Scope Control Scope Control Schedule Control Cost Control Quality Control Communication Control Risks Control Stakeholder Eng. Control Procurements Monitoring & Controlling PG-> Monitor & Control Project work Work Performance Information
  • 12.
    By: Anand Bobade;PMP, SCEA, MCP, CIW (nmbobade@gmail.com) Relation between WPD & WPI • Executing PG ->Direct & Manage process • Generates WPD • Monitor & Control PG - > All Control process • Generate WPI •Monitoring & Controlling PG-> Monitor & Control Project work
  • 13.
    By: Anand Bobade;PMP, SCEA, MCP, CIW (nmbobade@gmail.com) WPI -> Example Control Schedule – identify delay & try controlling it Control Cost – Analyses cost of completed work against money spent Control Quality – analyse data & control quality Control Risks – analyse risk data & re-asses/control risks Compare, Assess, Document, Forecast & Communicate  SV, SPI  CV, CPI  Quality issues, corrective actions  New risks, closed risk User below T&T to initiate CR & distribute reports:  Expert Judgment  Analytical Techniques  PMIS &Meetings Monitoring & Controlling PG -> Control Processes Monitoring & Controlling PG -> Monitor & Control Project work
  • 14.
    By: Anand Bobade;PMP, SCEA, MCP, CIW (nmbobade@gmail.com) 12.3 Control Procurement ->Input->WPDWhat is Work Performance Reports (WPR)? Work Performance Reports The physical or electronic representation of work performance information compiled in project documents, intended to generate decision or raise issues, actions or awareness Are output of the Monitor & Control Project Work process, and input to various managing and controlling processes. Helps stakeholders with current status of the project and its performance against the planned baselines. If project is not progressing as planned, stakeholder may decide to take any corrective action. E.g., extra funds or resources, or time extension etc. It can be given to stakeholders in a format desired by them and as decided in the communication management plan.
  • 15.
    By: Anand Bobade;PMP, SCEA, MCP, CIW (nmbobade@gmail.com) 12.3 Control Procurement ->Input->WPDHow WPR is generated? Work Performance Reports Manage Project Team Manage Communication Perform Integrated Change Control Control Risks Control Procurement Monitoring & Controlling PG-> Monitor & Control Project work Monitoring & Controlling PGExecuting PG Work Performance Reports
  • 16.
    By: Anand Bobade;PMP, SCEA, MCP, CIW (nmbobade@gmail.com) 12.3 Control Procurement ->Input->WPDFormat of WPR Work Performance Reports Performance Reports may be any combination of these formats: Burndown Chart S-Curve Bar Charts Histograms Tables Run Charts.
  • 17.
    By: Anand Bobade;PMP, SCEA, MCP, CIW (nmbobade@gmail.com) 12.3 Control Procurement ->Input->WPDContent of WPR Work Performance Reports The content of the Performance Reports includes: Percentage of the work completed Balance work to be completed Cost incurred Balance of funds available Balance of time available Major risks that have occurred, or passed without occurring Major remaining identified risks Results of variance analysis: e.g. schedule variance and cost variance Performance indexes: e.g. SPI , CPI Forecasted fund required to complete the remaining work Forecasted time required to complete the remaining work Summary of major approved change requests.
  • 18.
    By: Anand Bobade;PMP, SCEA, MCP, CIW (nmbobade@gmail.com) WPR -> Example Execute PG -> Manage Communication: Share Performance report to all stakeholders through manage communication process. M & C PG -> Perform Integrated Change Control: Huge variance or major finding in performance reports will warrant CR. CCB Monitoring & Controlling PG -> Monitor & Control Project work Stakeholders Compare, Assess, Document, Forecast & Communicate  SV, SPI  CV, CPI  Quality issues, corrective actions  New risks, closed risk
  • 19.
    By: Anand Bobade;PMP, SCEA, MCP, CIW (nmbobade@gmail.com) ReviewReview Work performance data is a collection of raw information of the project’s status. On the other hand, work performance information is a comparison of various performances, like cost and schedule, etc. Work performance data and work performance information are the basis for the Performance Reports. The Performance Reports are the reports given to project stakeholders to make them aware of the current status and the forecasted progress of the project. The Performance Reports show stakeholders how the project is going. The forecast analysis of what they should expect if the project is allowed to keep going in the same way, or what additional funds or resources may be required to complete the project
  • 20.
    By: Anand Bobade;PMP, SCEA, MCP, CIW (nmbobade@gmail.com) ReviewSample Questions 1. Anand is working on CRM project for Dubai Customs, even though you are using agile methods, you realize you are preparing an extensive amount of data and information. You regularly share data with your project team. Your last team meeting focused on the number of change requests and also the start and finish dates of activities in your schedule. They are examples of— • A. Key performance indicators • B. Work performance reports • C. Work performance data • D. Work performance information
  • 21.
    By: Anand Bobade;PMP, SCEA, MCP, CIW (nmbobade@gmail.com) ReviewSample Questions 2. The purpose of work performance data in control communications is to present results of comparative analysis to the— • A. Performance measurement baseline • B. Communications management plan • C. Stakeholder management plan • D. Deliverable status
  • 22.
    By: Anand Bobade;PMP, SCEA, MCP, CIW (nmbobade@gmail.com) ReviewSample Questions 3. Work performance information includes all the following EXCEPT— • A. Started deliverables • B. Costs authorized and incurred • C. Progress of deliverables • D. Completed deliverables
  • 23.
    By: Anand Bobade;PMP, SCEA, MCP, CIW (nmbobade@gmail.com) ReviewSample Questions 4. Work performance information is an output of which process? • A. Manage risks • B. Manage communications • C. Control communications • D. Report performance
  • 24.
    By: Anand Bobade;PMP, SCEA, MCP, CIW (nmbobade@gmail.com) ReviewSample Questions 5. Assume you want to optimize the work performance reports you will use to manage communications. You should do so by— • A. Determining the most appropriate choice of communications media • B. Setting different communications techniques for different stakeholder groups • B. Ensuring the information is consistent with regulations and standards • D. Ensuring comprehensiveness, accuracy, and availability
  • 25.
    By: Anand Bobade;PMP, SCEA, MCP, CIW (nmbobade@gmail.com) ReviewSample Questions - Answers 1. c. Work performance data • Work performance data are the raw observations and measurements identified during activities performed to carry out the work of the project. Other examples are the reported percent of work physically completed, quality and technical performance measures, number of defects, actual costs, and actual durations. [Executing] 2. a. Performance measurement baseline • Wok performance data are an input in control communications. These data organize and summarize information gathered and present the results of comparative analysis to the performance measurement baseline. [Monitoring and Controlling]
  • 26.
    By: Anand Bobade;PMP, SCEA, MCP, CIW (nmbobade@gmail.com) ReviewSample Questions - Answers 3. b. Costs authorized and incurred • Work performance information is an output of validate scope. It emphasizes deliverables—whether or not they have started, their progress, and ones that have finished or have been accepted. [Monitoring and Controlling] 4. c. Control communications • Work performance information, an output of control communications, organizes and summaries performance data such as status and progress information on the project at the level required by stakeholders. This information next is communicated to the appropriate stakeholders. [Monitoring and Controlling]
  • 27.
    By: Anand Bobade;PMP, SCEA, MCP, CIW (nmbobade@gmail.com) ReviewSample Questions - Answers 5. d. Ensuring comprehensiveness, accuracy, and availability • Work performance reports are an input to manage communications. They are a collection of project performance and status information used to facilitate discussion and create communications. They should be comprehensive, accurate, and available in a timely way. [Executing]
  • 28.
    By: Anand Bobade;PMP, SCEA, MCP, CIW (nmbobade@gmail.com) Additional Free Resources Visit Slide Share website & you will find other Knowledge area presentation… Please share!!