Chapter 7 –
Project Cost Management
PMP
Trainer: Anand BobadePMBOK 6th Edition, 2019, All rights reserved.
Plan Cost
management
SIXTH EDITION
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
Overview
Process definition
Process - ITTO
What are Analytical Techniques?
Cost Management plan
Life cycle costing
Review
7.1 Plan Cost Management
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
How PM will plan and execute the Cost management activities
Cost planning is very critical Starts early in the project
Involves Estimating,
Budgeting & controlling
Report cost (Cash flow) to
concern stakeholders
Plan Cost Management
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
Establishes Policies, procedures & documentation for planning,
managing, expending & controlling project costs.
It provides guidance and direction on how the project
costs will be managed throughout the project.
Establishing
Planning Managing
Expending Controlling
Plan Cost Management -> Definition
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
Plan Cost Management-> ITTO
Expert Judgment
Data analysis
Meetings
Project Management
Plan
Project Charter
Enterprise
environmental factors
Organizational process
assets
Cost Management
plan
Inputs Tools & Techniques Outputs
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
PMP Project Charter EEF OPA
Plan Cost Management-> Inputs
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
PMP
• Scope statement and WBS detail.Scope baseline
• When the project costs will be
incurred.
Schedule
baseline
• Risks (Risk reserves)
• Communications (for reporting).
Other details
Plan Cost Management->Inputs->PMP
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
Project Charter
Provides the summary budget
Approval requirements that will influence the management of
the project costs.
Measurable objectives
& success criteria's
High level risks
Summary milestone
schedule
Summary budget Stakeholder list
Project approval
requirements
Plan Cost Management->Inputs->Project charter
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
Enterprise Env.
Factors
Market conditions, Currency exchange rates.
Published commercial information (resource cost)
Project management information system.
Organizational culture and structure.
Plan Cost Management->Inputs->EEF
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
Organization
Process Assets
Existing cost policies, procedures, and guidelines
(e.g., invoicing process)
Financial controls procedures.
Historical information and lessons learned (e.g.,
past cost escalation issues)
Financial databases (E.g., internal resource rates)
Plan Cost Management->Inputs->OPA
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
Expert Judgment Data Analysis Meetings
Plan Cost Management -> Tools & Techniques
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
Expert
Judgment
They provides valuable insight on costing methods.
Apply experience & information from prior similar
projects.
Examine & compare different approaches (Cost of
Quality, Cost benefit analysis etc).
Provide input for financial analytical techniques
(ROI, IRR etc)
Plan Cost Management ->T&T->Expert Judgment
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
Data analysis
Analyse ways to finance resources:
Make Buy Rent Lease
Financial Techniques used for analysis:
Payback period
Return on
Investment(ROI)
Internal Rate of
Return (IRR)
Net Present Value
(NPV)
Planning may involve choosing strategic options to fund
Self-funding Funding with equity Funding with debt
Plan Cost Management ->T&T->Analytical Techniques
PM may not be involved in financial decisions.
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
Meetings
Meetings will be used to discuss how to estimate & manage cost.
Project
Manager
Sponsor
Key team
members
Financial
experts
Key
Stakeholders
Plan Cost Management ->T&T->Meetings
Any one with cost planning, estimation, budgeting related responsibilities
should attend then meetings.
Discuss & analyse
ways to finance
resources
Discuss & agree
on funding
options
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
Cost Management
Plan
Plan Cost Management-> Output->Cost Managment Plan
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
Cost Management
Plan
Guidelines to establish Cost baseline.
Cost change control procedures.
Details about all three processes.
Funding decisions.
Guidelines for dealing with fluctuating cost.
Roles & responsibilities for cost related activities.
Units of Measure Level of Precision Level of Accuracy
Organizational
procedure links
Control Thresholds
Rules for Perfor.
Measurement
Reporting Formats Additional Details
How the project costs will be planned, structured, and controlled.
Plan Cost Management-> Output->Cost Managment Plan
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
Units of Measure:
• Resources : Staff hours, days or lump sum cost
• Road construction project: Kilometer or Miles.
Level of Precision:
• Degree to which cost estimate will be
rounded. E.g. 99.85 => 100
Level of Accuracy:
•Initial-Rough order of magnitude(–25% to 75%)
•later - Definite estimate –5 to +10%.
Organizational procedure links:
•Control Account - Code linked to accounting system.
•WBS provide framework for cost management & helps
maintain consistency in estimations.
Plan Cost Management->Output->Cost Management Plan
Cost Management
Plan
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
Control Thresholds:
• Agreed amount of variation to be allowed.
• 1% Schedule variance to schedule baseline.
Rules for Performance Measurement:
•Define points in WBS -> Measure Control Accounts
performance.
•Established EVM techniques (Weighted milestones,
fixed formula, % complete)
•Specify tracking methodologies (Calculating EAC)
•Used in Performance based contracts.
Reporting Formats:
• Agreed reporting format to share cost reports,
Cash-flow’s etc.
Plan Cost Management->Output->Cost Management Plan
Cost Management
Plan
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
Process Description:
• Each of the three cost management Processes
are documented.
Additional Details:
• How the project will be funded.
• Strategic funding choices.
• Procedure to manage currency fluctuation.
Plan Cost Management->Output->Cost Management Plan
Cost Management
Plan
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
Plan Cost Management->Output->Cost Management Plan
Cost Management
Plan
Life Cycle Costing:
• Broader view of Project Cost Management
• Consider effect of cost decisions on using,
maintaining & supporting the product, service
or result of the project.
• Life cycle costing together with value
engineering can improve decision making
• Used to reduce cost and execution time.
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
Cost planning is very critical
Starts early in the project
Involves estimating, budgeting, and controlling
costs
T&T-> Expert, Data analysis & meeting
Funding (Self-funding, Funding with equity,
Funding with debt)
Analyse ways to finance resources (Make or Buy,
Rent or Lease)
Plan Cost Management -> Review
Chap 7.1  Plan Cost Management

More Related Content

What's hot

Chap 9.1 Pan Resource Management
Chap 9.1   Pan Resource ManagementChap 9.1   Pan Resource Management
Chap 9.1 Pan Resource ManagementAnand Bobade
 
Chap 8.2 Manage Quality
Chap 8.2 Manage QualityChap 8.2 Manage Quality
Chap 8.2 Manage QualityAnand Bobade
 
Chap 6.0 Schedule Management Overview
Chap 6.0 Schedule Management OverviewChap 6.0 Schedule Management Overview
Chap 6.0 Schedule Management OverviewAnand Bobade
 
PMP Chap 5 - Project Scope Management - Part1
PMP Chap 5 - Project Scope Management - Part1PMP Chap 5 - Project Scope Management - Part1
PMP Chap 5 - Project Scope Management - Part1Anand Bobade
 
PMP Chap 5 - Project Scope Management - Part 2
PMP Chap 5 - Project Scope Management - Part 2PMP Chap 5 - Project Scope Management - Part 2
PMP Chap 5 - Project Scope Management - Part 2Anand Bobade
 
PMP Chap 4 - Project Integration Management - Part1
PMP Chap 4 - Project Integration Management - Part1PMP Chap 4 - Project Integration Management - Part1
PMP Chap 4 - Project Integration Management - Part1Anand Bobade
 
PMP Chap 10 - Project Communication Management Details
PMP  Chap 10 - Project Communication Management DetailsPMP  Chap 10 - Project Communication Management Details
PMP Chap 10 - Project Communication Management DetailsAnand Bobade
 
Chap 9.2 Estimate Activity Resource
Chap 9.2   Estimate Activity ResourceChap 9.2   Estimate Activity Resource
Chap 9.2 Estimate Activity ResourceAnand Bobade
 
PMP Chap 2- Org. Influence and Project Life Cycle
PMP Chap 2- Org. Influence and Project Life CyclePMP Chap 2- Org. Influence and Project Life Cycle
PMP Chap 2- Org. Influence and Project Life CycleAnand Bobade
 
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...Anand Bobade
 
Chap 12.2 Conduct Procurement
Chap 12.2 Conduct ProcurementChap 12.2 Conduct Procurement
Chap 12.2 Conduct ProcurementAnand Bobade
 
Chap 8.3 Control Quality
Chap 8.3  Control QualityChap 8.3  Control Quality
Chap 8.3 Control QualityAnand Bobade
 
PMP Chap 6 - Project Time management - Part2
PMP Chap 6 - Project Time management - Part2PMP Chap 6 - Project Time management - Part2
PMP Chap 6 - Project Time management - Part2Anand Bobade
 
PMP 47 process definitions
PMP 47 process definitionsPMP 47 process definitions
PMP 47 process definitionsAnand Bobade
 
Pmp chap 11 - project risk management - Part 2
Pmp   chap 11 - project risk management - Part 2Pmp   chap 11 - project risk management - Part 2
Pmp chap 11 - project risk management - Part 2Anand Bobade
 
Chap 5.3 define scope
Chap 5.3 define scopeChap 5.3 define scope
Chap 5.3 define scopeAnand Bobade
 
Chap 9.6 Control Resources
Chap 9.6  Control ResourcesChap 9.6  Control Resources
Chap 9.6 Control ResourcesAnand Bobade
 
Chap 9.5 Manage Team
Chap 9.5  Manage TeamChap 9.5  Manage Team
Chap 9.5 Manage TeamAnand Bobade
 
PMP Chap4-Project Integration Management Details: Part-2
PMP Chap4-Project Integration Management Details: Part-2PMP Chap4-Project Integration Management Details: Part-2
PMP Chap4-Project Integration Management Details: Part-2Anand Bobade
 
Chap 11.2 Identify Risks
Chap 11.2 Identify RisksChap 11.2 Identify Risks
Chap 11.2 Identify RisksAnand Bobade
 

What's hot (20)

Chap 9.1 Pan Resource Management
Chap 9.1   Pan Resource ManagementChap 9.1   Pan Resource Management
Chap 9.1 Pan Resource Management
 
Chap 8.2 Manage Quality
Chap 8.2 Manage QualityChap 8.2 Manage Quality
Chap 8.2 Manage Quality
 
Chap 6.0 Schedule Management Overview
Chap 6.0 Schedule Management OverviewChap 6.0 Schedule Management Overview
Chap 6.0 Schedule Management Overview
 
PMP Chap 5 - Project Scope Management - Part1
PMP Chap 5 - Project Scope Management - Part1PMP Chap 5 - Project Scope Management - Part1
PMP Chap 5 - Project Scope Management - Part1
 
PMP Chap 5 - Project Scope Management - Part 2
PMP Chap 5 - Project Scope Management - Part 2PMP Chap 5 - Project Scope Management - Part 2
PMP Chap 5 - Project Scope Management - Part 2
 
PMP Chap 4 - Project Integration Management - Part1
PMP Chap 4 - Project Integration Management - Part1PMP Chap 4 - Project Integration Management - Part1
PMP Chap 4 - Project Integration Management - Part1
 
PMP Chap 10 - Project Communication Management Details
PMP  Chap 10 - Project Communication Management DetailsPMP  Chap 10 - Project Communication Management Details
PMP Chap 10 - Project Communication Management Details
 
Chap 9.2 Estimate Activity Resource
Chap 9.2   Estimate Activity ResourceChap 9.2   Estimate Activity Resource
Chap 9.2 Estimate Activity Resource
 
PMP Chap 2- Org. Influence and Project Life Cycle
PMP Chap 2- Org. Influence and Project Life CyclePMP Chap 2- Org. Influence and Project Life Cycle
PMP Chap 2- Org. Influence and Project Life Cycle
 
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
 
Chap 12.2 Conduct Procurement
Chap 12.2 Conduct ProcurementChap 12.2 Conduct Procurement
Chap 12.2 Conduct Procurement
 
Chap 8.3 Control Quality
Chap 8.3  Control QualityChap 8.3  Control Quality
Chap 8.3 Control Quality
 
PMP Chap 6 - Project Time management - Part2
PMP Chap 6 - Project Time management - Part2PMP Chap 6 - Project Time management - Part2
PMP Chap 6 - Project Time management - Part2
 
PMP 47 process definitions
PMP 47 process definitionsPMP 47 process definitions
PMP 47 process definitions
 
Pmp chap 11 - project risk management - Part 2
Pmp   chap 11 - project risk management - Part 2Pmp   chap 11 - project risk management - Part 2
Pmp chap 11 - project risk management - Part 2
 
Chap 5.3 define scope
Chap 5.3 define scopeChap 5.3 define scope
Chap 5.3 define scope
 
Chap 9.6 Control Resources
Chap 9.6  Control ResourcesChap 9.6  Control Resources
Chap 9.6 Control Resources
 
Chap 9.5 Manage Team
Chap 9.5  Manage TeamChap 9.5  Manage Team
Chap 9.5 Manage Team
 
PMP Chap4-Project Integration Management Details: Part-2
PMP Chap4-Project Integration Management Details: Part-2PMP Chap4-Project Integration Management Details: Part-2
PMP Chap4-Project Integration Management Details: Part-2
 
Chap 11.2 Identify Risks
Chap 11.2 Identify RisksChap 11.2 Identify Risks
Chap 11.2 Identify Risks
 

Similar to Chap 7.1 Plan Cost Management

PMP Chap 7 - Project Cost Management - Part 1
PMP Chap 7 - Project Cost Management - Part 1PMP Chap 7 - Project Cost Management - Part 1
PMP Chap 7 - Project Cost Management - Part 1Anand Bobade
 
Chap 4.5 Monitor and Control Project Work
Chap 4.5 Monitor and Control Project WorkChap 4.5 Monitor and Control Project Work
Chap 4.5 Monitor and Control Project WorkAnand Bobade
 
Chap 4.6 Perform Integrated Change Control
Chap 4.6 Perform Integrated Change ControlChap 4.6 Perform Integrated Change Control
Chap 4.6 Perform Integrated Change ControlAnand Bobade
 
Chap 5.1 Plan Scope Management
Chap 5.1 Plan Scope ManagementChap 5.1 Plan Scope Management
Chap 5.1 Plan Scope ManagementAnand Bobade
 
Chap 6.1 Plan Schedule Management
Chap 6.1 Plan Schedule ManagementChap 6.1 Plan Schedule Management
Chap 6.1 Plan Schedule ManagementAnand Bobade
 
Chap 5.6 Control Scope
Chap 5.6 Control ScopeChap 5.6 Control Scope
Chap 5.6 Control ScopeAnand Bobade
 
Chap 5.2 Collect requirements
Chap 5.2 Collect requirementsChap 5.2 Collect requirements
Chap 5.2 Collect requirementsAnand Bobade
 
Chap 6.2 Define Activity
Chap 6.2 Define ActivityChap 6.2 Define Activity
Chap 6.2 Define ActivityAnand Bobade
 
Chap 4.7 Project or Phase Close
Chap 4.7 Project or Phase CloseChap 4.7 Project or Phase Close
Chap 4.7 Project or Phase CloseAnand Bobade
 
PMP Chap 3 - Project Management Processes
PMP Chap 3 - Project Management ProcessesPMP Chap 3 - Project Management Processes
PMP Chap 3 - Project Management ProcessesAnand Bobade
 
Chap 6.6 Control Schedule
Chap 6.6 Control ScheduleChap 6.6 Control Schedule
Chap 6.6 Control ScheduleAnand Bobade
 
Chap 11.7 Monitor Risks
Chap 11.7 Monitor RisksChap 11.7 Monitor Risks
Chap 11.7 Monitor RisksAnand Bobade
 
Chap 4.3 Direct and Manage Project work
Chap 4.3 Direct and Manage Project workChap 4.3 Direct and Manage Project work
Chap 4.3 Direct and Manage Project workAnand Bobade
 
5 financial new
5 financial new5 financial new
5 financial newRahul Gupta
 
Chap 4.1- Develop Project Charter
Chap 4.1- Develop Project CharterChap 4.1- Develop Project Charter
Chap 4.1- Develop Project CharterAnand Bobade
 
Project Management - Getting the basics right
Project Management - Getting the basics right Project Management - Getting the basics right
Project Management - Getting the basics right Simon Misiewicz
 
Project Control- Overview Presentation Tafseer
Project Control- Overview Presentation   TafseerProject Control- Overview Presentation   Tafseer
Project Control- Overview Presentation TafseerKishan Solankimbaccepmp
 
Chap 12.1 Plan Procurement Management
Chap 12.1 Plan Procurement ManagementChap 12.1 Plan Procurement Management
Chap 12.1 Plan Procurement ManagementAnand Bobade
 
4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt
4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt
4. PAE AcFn621Ch-4a Project Alaysis and Selection.pptProfDrAnbalaganChinn
 
CostManagementSlides.pdf
CostManagementSlides.pdfCostManagementSlides.pdf
CostManagementSlides.pdfAmrishTyagi8
 

Similar to Chap 7.1 Plan Cost Management (20)

PMP Chap 7 - Project Cost Management - Part 1
PMP Chap 7 - Project Cost Management - Part 1PMP Chap 7 - Project Cost Management - Part 1
PMP Chap 7 - Project Cost Management - Part 1
 
Chap 4.5 Monitor and Control Project Work
Chap 4.5 Monitor and Control Project WorkChap 4.5 Monitor and Control Project Work
Chap 4.5 Monitor and Control Project Work
 
Chap 4.6 Perform Integrated Change Control
Chap 4.6 Perform Integrated Change ControlChap 4.6 Perform Integrated Change Control
Chap 4.6 Perform Integrated Change Control
 
Chap 5.1 Plan Scope Management
Chap 5.1 Plan Scope ManagementChap 5.1 Plan Scope Management
Chap 5.1 Plan Scope Management
 
Chap 6.1 Plan Schedule Management
Chap 6.1 Plan Schedule ManagementChap 6.1 Plan Schedule Management
Chap 6.1 Plan Schedule Management
 
Chap 5.6 Control Scope
Chap 5.6 Control ScopeChap 5.6 Control Scope
Chap 5.6 Control Scope
 
Chap 5.2 Collect requirements
Chap 5.2 Collect requirementsChap 5.2 Collect requirements
Chap 5.2 Collect requirements
 
Chap 6.2 Define Activity
Chap 6.2 Define ActivityChap 6.2 Define Activity
Chap 6.2 Define Activity
 
Chap 4.7 Project or Phase Close
Chap 4.7 Project or Phase CloseChap 4.7 Project or Phase Close
Chap 4.7 Project or Phase Close
 
PMP Chap 3 - Project Management Processes
PMP Chap 3 - Project Management ProcessesPMP Chap 3 - Project Management Processes
PMP Chap 3 - Project Management Processes
 
Chap 6.6 Control Schedule
Chap 6.6 Control ScheduleChap 6.6 Control Schedule
Chap 6.6 Control Schedule
 
Chap 11.7 Monitor Risks
Chap 11.7 Monitor RisksChap 11.7 Monitor Risks
Chap 11.7 Monitor Risks
 
Chap 4.3 Direct and Manage Project work
Chap 4.3 Direct and Manage Project workChap 4.3 Direct and Manage Project work
Chap 4.3 Direct and Manage Project work
 
5 financial new
5 financial new5 financial new
5 financial new
 
Chap 4.1- Develop Project Charter
Chap 4.1- Develop Project CharterChap 4.1- Develop Project Charter
Chap 4.1- Develop Project Charter
 
Project Management - Getting the basics right
Project Management - Getting the basics right Project Management - Getting the basics right
Project Management - Getting the basics right
 
Project Control- Overview Presentation Tafseer
Project Control- Overview Presentation   TafseerProject Control- Overview Presentation   Tafseer
Project Control- Overview Presentation Tafseer
 
Chap 12.1 Plan Procurement Management
Chap 12.1 Plan Procurement ManagementChap 12.1 Plan Procurement Management
Chap 12.1 Plan Procurement Management
 
4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt
4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt
4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt
 
CostManagementSlides.pdf
CostManagementSlides.pdfCostManagementSlides.pdf
CostManagementSlides.pdf
 

More from Anand Bobade

Chap 12.3 Control Procurement
Chap 12.3 Control ProcurementChap 12.3 Control Procurement
Chap 12.3 Control ProcurementAnand Bobade
 
Chap 12.0 Procurement Management overview
Chap 12.0   Procurement Management overviewChap 12.0   Procurement Management overview
Chap 12.0 Procurement Management overviewAnand Bobade
 
Chap 10.3 Monitor Communication
Chap 10.3 Monitor CommunicationChap 10.3 Monitor Communication
Chap 10.3 Monitor CommunicationAnand Bobade
 
Chap 10.2 Manage Communication
Chap 10.2  Manage CommunicationChap 10.2  Manage Communication
Chap 10.2 Manage CommunicationAnand Bobade
 
Chap 10.1 Plan Communication Management
Chap 10.1  Plan Communication ManagementChap 10.1  Plan Communication Management
Chap 10.1 Plan Communication ManagementAnand Bobade
 
Chap 9.3 Acquire Resources
Chap 9.3   Acquire ResourcesChap 9.3   Acquire Resources
Chap 9.3 Acquire ResourcesAnand Bobade
 
Chap 9.0 Project Resource Management overview
Chap 9.0   Project Resource Management overviewChap 9.0   Project Resource Management overview
Chap 9.0 Project Resource Management overviewAnand Bobade
 
Chap 6.5 Define Schedule
Chap 6.5 Define ScheduleChap 6.5 Define Schedule
Chap 6.5 Define ScheduleAnand Bobade
 
Chap 6.4 Estimate Activity Duration
Chap 6.4 Estimate Activity DurationChap 6.4 Estimate Activity Duration
Chap 6.4 Estimate Activity DurationAnand Bobade
 
Chap 6.3 Sequence Activity
Chap 6.3 Sequence ActivityChap 6.3 Sequence Activity
Chap 6.3 Sequence ActivityAnand Bobade
 
Chap 5.5 validate scope
Chap 5.5 validate scopeChap 5.5 validate scope
Chap 5.5 validate scopeAnand Bobade
 

More from Anand Bobade (11)

Chap 12.3 Control Procurement
Chap 12.3 Control ProcurementChap 12.3 Control Procurement
Chap 12.3 Control Procurement
 
Chap 12.0 Procurement Management overview
Chap 12.0   Procurement Management overviewChap 12.0   Procurement Management overview
Chap 12.0 Procurement Management overview
 
Chap 10.3 Monitor Communication
Chap 10.3 Monitor CommunicationChap 10.3 Monitor Communication
Chap 10.3 Monitor Communication
 
Chap 10.2 Manage Communication
Chap 10.2  Manage CommunicationChap 10.2  Manage Communication
Chap 10.2 Manage Communication
 
Chap 10.1 Plan Communication Management
Chap 10.1  Plan Communication ManagementChap 10.1  Plan Communication Management
Chap 10.1 Plan Communication Management
 
Chap 9.3 Acquire Resources
Chap 9.3   Acquire ResourcesChap 9.3   Acquire Resources
Chap 9.3 Acquire Resources
 
Chap 9.0 Project Resource Management overview
Chap 9.0   Project Resource Management overviewChap 9.0   Project Resource Management overview
Chap 9.0 Project Resource Management overview
 
Chap 6.5 Define Schedule
Chap 6.5 Define ScheduleChap 6.5 Define Schedule
Chap 6.5 Define Schedule
 
Chap 6.4 Estimate Activity Duration
Chap 6.4 Estimate Activity DurationChap 6.4 Estimate Activity Duration
Chap 6.4 Estimate Activity Duration
 
Chap 6.3 Sequence Activity
Chap 6.3 Sequence ActivityChap 6.3 Sequence Activity
Chap 6.3 Sequence Activity
 
Chap 5.5 validate scope
Chap 5.5 validate scopeChap 5.5 validate scope
Chap 5.5 validate scope
 

Recently uploaded

Siliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime Siliguri
Siliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime SiliguriSiliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime Siliguri
Siliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime Siligurimeghakumariji156
 
How Software Developers Destroy Business Value.pptx
How Software Developers Destroy Business Value.pptxHow Software Developers Destroy Business Value.pptx
How Software Developers Destroy Business Value.pptxAaron Stannard
 
W.H.Bender Quote 62 - Always strive to be a Hospitality Service professional
W.H.Bender Quote 62 - Always strive to be a Hospitality Service professionalW.H.Bender Quote 62 - Always strive to be a Hospitality Service professional
W.H.Bender Quote 62 - Always strive to be a Hospitality Service professionalWilliam (Bill) H. Bender, FCSI
 
internship thesis pakistan aeronautical complex kamra
internship thesis pakistan aeronautical complex kamrainternship thesis pakistan aeronautical complex kamra
internship thesis pakistan aeronautical complex kamraAllTops
 
Spring-2024-Priesthoods of Augustus Yale Historical Review
Spring-2024-Priesthoods of Augustus Yale Historical ReviewSpring-2024-Priesthoods of Augustus Yale Historical Review
Spring-2024-Priesthoods of Augustus Yale Historical Reviewyalehistoricalreview
 
Internal Reconstruction Corporate accounting by bhumika Garg
Internal Reconstruction Corporate accounting by bhumika GargInternal Reconstruction Corporate accounting by bhumika Garg
Internal Reconstruction Corporate accounting by bhumika Garganuragrcsec2023
 
Gautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Gautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot ModelGautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Gautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot ModelNitya salvi
 
The Psychology Of Motivation - Richard Brown
The Psychology Of Motivation - Richard BrownThe Psychology Of Motivation - Richard Brown
The Psychology Of Motivation - Richard BrownSandaliGurusinghe2
 
Marketing Management 16th edition by Philip Kotler test bank.docx
Marketing Management 16th edition by Philip Kotler test bank.docxMarketing Management 16th edition by Philip Kotler test bank.docx
Marketing Management 16th edition by Philip Kotler test bank.docxssuserf63bd7
 
Persuasive and Communication is the art of negotiation.
Persuasive and Communication is the art of negotiation.Persuasive and Communication is the art of negotiation.
Persuasive and Communication is the art of negotiation.aruny7087
 
Information Technology Project Management, Revised 7th edition test bank.docx
Information Technology Project Management, Revised 7th edition test bank.docxInformation Technology Project Management, Revised 7th edition test bank.docx
Information Technology Project Management, Revised 7th edition test bank.docxssuserf63bd7
 
Group work -meaning and definitions- Characteristics and Importance
Group work -meaning and definitions- Characteristics and ImportanceGroup work -meaning and definitions- Characteristics and Importance
Group work -meaning and definitions- Characteristics and Importanceajay0134
 
thesis-and-viva-voce preparation for research scholars
thesis-and-viva-voce preparation for research scholarsthesis-and-viva-voce preparation for research scholars
thesis-and-viva-voce preparation for research scholarsPAmudhaKumar
 
digital Human resource management presentation.pdf
digital Human resource management presentation.pdfdigital Human resource management presentation.pdf
digital Human resource management presentation.pdfArtiSrivastava23
 
Mount abu Escort💋 Kajal Rate 4500/- Cash Payment 24/7
Mount abu Escort💋 Kajal Rate 4500/- Cash Payment 24/7Mount abu Escort💋 Kajal Rate 4500/- Cash Payment 24/7
Mount abu Escort💋 Kajal Rate 4500/- Cash Payment 24/7ickkoo5
 

Recently uploaded (15)

Siliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime Siliguri
Siliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime SiliguriSiliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime Siliguri
Siliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime Siliguri
 
How Software Developers Destroy Business Value.pptx
How Software Developers Destroy Business Value.pptxHow Software Developers Destroy Business Value.pptx
How Software Developers Destroy Business Value.pptx
 
W.H.Bender Quote 62 - Always strive to be a Hospitality Service professional
W.H.Bender Quote 62 - Always strive to be a Hospitality Service professionalW.H.Bender Quote 62 - Always strive to be a Hospitality Service professional
W.H.Bender Quote 62 - Always strive to be a Hospitality Service professional
 
internship thesis pakistan aeronautical complex kamra
internship thesis pakistan aeronautical complex kamrainternship thesis pakistan aeronautical complex kamra
internship thesis pakistan aeronautical complex kamra
 
Spring-2024-Priesthoods of Augustus Yale Historical Review
Spring-2024-Priesthoods of Augustus Yale Historical ReviewSpring-2024-Priesthoods of Augustus Yale Historical Review
Spring-2024-Priesthoods of Augustus Yale Historical Review
 
Internal Reconstruction Corporate accounting by bhumika Garg
Internal Reconstruction Corporate accounting by bhumika GargInternal Reconstruction Corporate accounting by bhumika Garg
Internal Reconstruction Corporate accounting by bhumika Garg
 
Gautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Gautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot ModelGautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Gautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot Model
 
The Psychology Of Motivation - Richard Brown
The Psychology Of Motivation - Richard BrownThe Psychology Of Motivation - Richard Brown
The Psychology Of Motivation - Richard Brown
 
Marketing Management 16th edition by Philip Kotler test bank.docx
Marketing Management 16th edition by Philip Kotler test bank.docxMarketing Management 16th edition by Philip Kotler test bank.docx
Marketing Management 16th edition by Philip Kotler test bank.docx
 
Persuasive and Communication is the art of negotiation.
Persuasive and Communication is the art of negotiation.Persuasive and Communication is the art of negotiation.
Persuasive and Communication is the art of negotiation.
 
Information Technology Project Management, Revised 7th edition test bank.docx
Information Technology Project Management, Revised 7th edition test bank.docxInformation Technology Project Management, Revised 7th edition test bank.docx
Information Technology Project Management, Revised 7th edition test bank.docx
 
Group work -meaning and definitions- Characteristics and Importance
Group work -meaning and definitions- Characteristics and ImportanceGroup work -meaning and definitions- Characteristics and Importance
Group work -meaning and definitions- Characteristics and Importance
 
thesis-and-viva-voce preparation for research scholars
thesis-and-viva-voce preparation for research scholarsthesis-and-viva-voce preparation for research scholars
thesis-and-viva-voce preparation for research scholars
 
digital Human resource management presentation.pdf
digital Human resource management presentation.pdfdigital Human resource management presentation.pdf
digital Human resource management presentation.pdf
 
Mount abu Escort💋 Kajal Rate 4500/- Cash Payment 24/7
Mount abu Escort💋 Kajal Rate 4500/- Cash Payment 24/7Mount abu Escort💋 Kajal Rate 4500/- Cash Payment 24/7
Mount abu Escort💋 Kajal Rate 4500/- Cash Payment 24/7
 

Chap 7.1 Plan Cost Management

  • 1. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . Chapter 7 – Project Cost Management PMP Trainer: Anand BobadePMBOK 6th Edition, 2019, All rights reserved. Plan Cost management SIXTH EDITION
  • 2. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . Overview Process definition Process - ITTO What are Analytical Techniques? Cost Management plan Life cycle costing Review 7.1 Plan Cost Management
  • 3. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . How PM will plan and execute the Cost management activities Cost planning is very critical Starts early in the project Involves Estimating, Budgeting & controlling Report cost (Cash flow) to concern stakeholders Plan Cost Management
  • 4. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . Establishes Policies, procedures & documentation for planning, managing, expending & controlling project costs. It provides guidance and direction on how the project costs will be managed throughout the project. Establishing Planning Managing Expending Controlling Plan Cost Management -> Definition
  • 5. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . Plan Cost Management-> ITTO Expert Judgment Data analysis Meetings Project Management Plan Project Charter Enterprise environmental factors Organizational process assets Cost Management plan Inputs Tools & Techniques Outputs
  • 6. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . PMP Project Charter EEF OPA Plan Cost Management-> Inputs
  • 7. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . PMP • Scope statement and WBS detail.Scope baseline • When the project costs will be incurred. Schedule baseline • Risks (Risk reserves) • Communications (for reporting). Other details Plan Cost Management->Inputs->PMP
  • 8. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . Project Charter Provides the summary budget Approval requirements that will influence the management of the project costs. Measurable objectives & success criteria's High level risks Summary milestone schedule Summary budget Stakeholder list Project approval requirements Plan Cost Management->Inputs->Project charter
  • 9. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . Enterprise Env. Factors Market conditions, Currency exchange rates. Published commercial information (resource cost) Project management information system. Organizational culture and structure. Plan Cost Management->Inputs->EEF
  • 10. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . Organization Process Assets Existing cost policies, procedures, and guidelines (e.g., invoicing process) Financial controls procedures. Historical information and lessons learned (e.g., past cost escalation issues) Financial databases (E.g., internal resource rates) Plan Cost Management->Inputs->OPA
  • 11. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . Expert Judgment Data Analysis Meetings Plan Cost Management -> Tools & Techniques
  • 12. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . Expert Judgment They provides valuable insight on costing methods. Apply experience & information from prior similar projects. Examine & compare different approaches (Cost of Quality, Cost benefit analysis etc). Provide input for financial analytical techniques (ROI, IRR etc) Plan Cost Management ->T&T->Expert Judgment
  • 13. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . Data analysis Analyse ways to finance resources: Make Buy Rent Lease Financial Techniques used for analysis: Payback period Return on Investment(ROI) Internal Rate of Return (IRR) Net Present Value (NPV) Planning may involve choosing strategic options to fund Self-funding Funding with equity Funding with debt Plan Cost Management ->T&T->Analytical Techniques PM may not be involved in financial decisions.
  • 14. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . Meetings Meetings will be used to discuss how to estimate & manage cost. Project Manager Sponsor Key team members Financial experts Key Stakeholders Plan Cost Management ->T&T->Meetings Any one with cost planning, estimation, budgeting related responsibilities should attend then meetings. Discuss & analyse ways to finance resources Discuss & agree on funding options
  • 15. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . Cost Management Plan Plan Cost Management-> Output->Cost Managment Plan
  • 16. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . Cost Management Plan Guidelines to establish Cost baseline. Cost change control procedures. Details about all three processes. Funding decisions. Guidelines for dealing with fluctuating cost. Roles & responsibilities for cost related activities. Units of Measure Level of Precision Level of Accuracy Organizational procedure links Control Thresholds Rules for Perfor. Measurement Reporting Formats Additional Details How the project costs will be planned, structured, and controlled. Plan Cost Management-> Output->Cost Managment Plan
  • 17. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . Units of Measure: • Resources : Staff hours, days or lump sum cost • Road construction project: Kilometer or Miles. Level of Precision: • Degree to which cost estimate will be rounded. E.g. 99.85 => 100 Level of Accuracy: •Initial-Rough order of magnitude(–25% to 75%) •later - Definite estimate –5 to +10%. Organizational procedure links: •Control Account - Code linked to accounting system. •WBS provide framework for cost management & helps maintain consistency in estimations. Plan Cost Management->Output->Cost Management Plan Cost Management Plan
  • 18. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . Control Thresholds: • Agreed amount of variation to be allowed. • 1% Schedule variance to schedule baseline. Rules for Performance Measurement: •Define points in WBS -> Measure Control Accounts performance. •Established EVM techniques (Weighted milestones, fixed formula, % complete) •Specify tracking methodologies (Calculating EAC) •Used in Performance based contracts. Reporting Formats: • Agreed reporting format to share cost reports, Cash-flow’s etc. Plan Cost Management->Output->Cost Management Plan Cost Management Plan
  • 19. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . Process Description: • Each of the three cost management Processes are documented. Additional Details: • How the project will be funded. • Strategic funding choices. • Procedure to manage currency fluctuation. Plan Cost Management->Output->Cost Management Plan Cost Management Plan
  • 20. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . Plan Cost Management->Output->Cost Management Plan Cost Management Plan Life Cycle Costing: • Broader view of Project Cost Management • Consider effect of cost decisions on using, maintaining & supporting the product, service or result of the project. • Life cycle costing together with value engineering can improve decision making • Used to reduce cost and execution time.
  • 21. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . Cost planning is very critical Starts early in the project Involves estimating, budgeting, and controlling costs T&T-> Expert, Data analysis & meeting Funding (Self-funding, Funding with equity, Funding with debt) Analyse ways to finance resources (Make or Buy, Rent or Lease) Plan Cost Management -> Review