SlideShare a Scribd company logo
1 of 22
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Chapter 11 –
Project Risk Management
PMP
Trainer: Anand BobadePMBOK 6th Edition, 2019, All rights reserved.
Monitor Risk
SIXTH EDITION
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
11.6 Monitor Risk
Monitor Risk - Definition
Monitor Risk : ITTO
Risk Audits
Risk Re-assessment
Technical Performance Measurement
Review
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Project Risk Management Processes
Plan Risk management Identify Risk
Perform Qualitative
Risk Analysis
Perform Quantitative
Risk Analysis
Plan Risk Response Implement Risk Monitor Risk
P
MC
P P P
P E
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
tracking identified risks, monitoring residual risks, identifying new
risks & evaluating risk process effectiveness throughout the project.
It improves efficiency of risk approach & optimize risk
responses.
Tracking identified risks Monitoring residual risks
Identifying new risks.
Evaluating Risk process
effectiveness.
Monitor Risk
Monitor Risks -> Definition
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Perform Variance & Trend analysis using performance information.
This process is not about managing or responding to
risks. So, do nothing about the Risk.
Determine
If project assumptions are still valid.
If assessed risk has changed or can be
retired
If Risk management plan is followed.
Alignment of contingency reserves.
Choose alternative strategies
(workarounds).
Execute contingency or fallback
plan.
Update PMP, OPA (Lesson
learned).
Monitor Risks -> Introduction
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Monitor Risk -> ITTO
Data analysis
Audits
Meetings
Project Management
Plan
Project documents
Work Performance
Data
Work Performance
reports
Work Performance
Information
Change request
PMP updates
Project document updates
OPA updates
Inputs Tools & Techniques Outputs
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Project Management
Plan
Project documents
Work Performance
Data
Work Performance
reports
Monitor Risk -> Inputs
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Risk Management Plan
• Overall Risk Management approach.
• How to control the risk.
Work Performance data
• WPD from execution (Direct & Manage Project work)
impacted by Risks.
• E.g., Deliverable status, schedule progress and cost incurred.
Work Performance reports:
• Reports from Monitor & control Project work.
• Contains Variance analysis, Earn Value Data & Forecasted
data.
• Useful in controlling Risks related to Project Performance.
Monitor Risks->Inputs
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Project documents
Monitor Risk -> Inputs -> Project documents
Issue log
Lessons learned
register
Risk Register Risk Report
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Data analysis Risk Audits Meetings
Monitor Risks->T&T
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Data analysis
Technical Performance
Measurement
Reserve Analysis
Monitor Risks->T&T
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Technical Performance
Measurement
Compare technical accomplishments of project milestones to technical milestones as per the
project plan. (Trend analysis using run charts)
Requires defined objectives & Quantifiable technical performance measurements (E.g.,
Transaction time, storage capacity, no. of defects)
If deviations are identified, they are documented & Risk Management team could suggest
corrective actions.
Q1 Q2 Q3
Design
Build & test
Prototype
Prototype
Demo to Client
Monitor Risks->T&T->Technical Perf. Measurement
Project
Milestone
Technical
Milestone
Technical
Milestone
Found many
defects
Impact
11.6 I T&T O
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Reserve Analysis
Compares the amount of contingency reserves remaining to the amount of risk
remaining at any time in the project in order to determine if the remaining
reserve is adequate.
Actual used reserves
Planned Reserves
Monitor Risks->T&T-> Reserve Analysis
If risks do not occur, then the contingency reserves which were meant to pay for those risks
can go back into the “pool” of reserves
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Risk Audits
Risk audits Verify effectiveness of the risk management process.
Risk audit meetings be held separately from the risk review meetings.
Risk review meeting is held to review effectiveness of risk responses
The format for the risk audit will be defined in the risk management plan.
Monitor Risks->T&T -> Risk Audits
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Meetings
Risk review meeting is held to review effectiveness of risk responses and are
separate from Status meetings
Documenting the
effectiveness of risk
Reassessment of current
risks
Closing of risks that are
outdated
Issues that have arisen
as the result of risks that
have occurred
Identification of lessons
to be learned
Monitor Risks->T&T -> Meetings
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Work Performance
Information
Change request PMP updates
Monitor Risks->Outputs
Project document
updates
OPA updates
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Project document
updates
Monitor Risks->Outputs-> Project document updates
Assumption log Issue log
Lessons learned
register
Risk Register Risk Report
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Work Performance
Information
Provide mechanism to communicate & support project decision making.
Monitor Risks->Outputs-> WPI
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Change Requests
Implementing contingency plan or workarounds sometime results in CR.
Recommended Corrective actions:
• Contingency Plans.
• Workarounds.
Recommended preventive actions:
• Ensure future project performance is
aligned with PMP.
Monitor Risks->Outputs->CR
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
OPA Updates
Template for Risk Management plan & Risk Register.
Risk Breakdown structure.
Risk Categories.
Lesson Learned.
Monitor Risks->Outputs -> OPA
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Monitor Risk - Definition
Monitor Risk : ITTO
Risk Audits
Risk Re-assessment
Technical Performance Measurement
Monitor Risks -> Review
Chap 11.7 Monitor Risks

More Related Content

What's hot

Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk ManagementMarkos Mulat G
 
Episode 25 : Project Risk Management
Episode 25 :  Project Risk ManagementEpisode 25 :  Project Risk Management
Episode 25 : Project Risk ManagementSAJJAD KHUDHUR ABBAS
 
Project Risk Management - PMBOK6
Project Risk Management - PMBOK6Project Risk Management - PMBOK6
Project Risk Management - PMBOK6Agus Suhanto
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk ManagementOleksa Stelmakh
 
PMP Training - 11 project risk management
PMP Training - 11 project risk managementPMP Training - 11 project risk management
PMP Training - 11 project risk managementejlp12
 
11.3 Perform Qualitative Risk Analysis
11.3 Perform Qualitative Risk Analysis11.3 Perform Qualitative Risk Analysis
11.3 Perform Qualitative Risk AnalysisDavidMcLachlan1
 
PMI Project Management Principles
PMI Project Management PrinciplesPMI Project Management Principles
PMI Project Management Principlestltiede
 
Risk Analysis : PMP- Project Risk Management
Risk Analysis : PMP- Project Risk ManagementRisk Analysis : PMP- Project Risk Management
Risk Analysis : PMP- Project Risk ManagementSaket Bansal
 
Quantitative Project Risk Analysis
Quantitative Project Risk AnalysisQuantitative Project Risk Analysis
Quantitative Project Risk AnalysisIntaver Insititute
 
Risk management
Risk managementRisk management
Risk managementBabasab Patil
 
Risk Management module PowerPoint Presentation Slides
Risk Management module PowerPoint Presentation SlidesRisk Management module PowerPoint Presentation Slides
Risk Management module PowerPoint Presentation SlidesSlideTeam
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Managementcgautam
 
Risk Management Process And Procedures PowerPoint Presentation Slides
Risk Management Process And Procedures PowerPoint Presentation SlidesRisk Management Process And Procedures PowerPoint Presentation Slides
Risk Management Process And Procedures PowerPoint Presentation SlidesSlideTeam
 
Risk Management
Risk ManagementRisk Management
Risk Managementcgeorgeo
 
Mitigation Plan PowerPoint Presentation Slides
Mitigation Plan PowerPoint Presentation SlidesMitigation Plan PowerPoint Presentation Slides
Mitigation Plan PowerPoint Presentation SlidesSlideTeam
 
Project risk management
Project risk managementProject risk management
Project risk managementEr Swati Nagal
 
Risk management concepts and learning
Risk management   concepts and learningRisk management   concepts and learning
Risk management concepts and learningVanita Ahuja
 

What's hot (20)

Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
Episode 25 : Project Risk Management
Episode 25 :  Project Risk ManagementEpisode 25 :  Project Risk Management
Episode 25 : Project Risk Management
 
Project Risk Management - PMBOK6
Project Risk Management - PMBOK6Project Risk Management - PMBOK6
Project Risk Management - PMBOK6
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
PMP Training - 11 project risk management
PMP Training - 11 project risk managementPMP Training - 11 project risk management
PMP Training - 11 project risk management
 
11.3 Perform Qualitative Risk Analysis
11.3 Perform Qualitative Risk Analysis11.3 Perform Qualitative Risk Analysis
11.3 Perform Qualitative Risk Analysis
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
PMI Project Management Principles
PMI Project Management PrinciplesPMI Project Management Principles
PMI Project Management Principles
 
Risk Analysis : PMP- Project Risk Management
Risk Analysis : PMP- Project Risk ManagementRisk Analysis : PMP- Project Risk Management
Risk Analysis : PMP- Project Risk Management
 
Quantitative Project Risk Analysis
Quantitative Project Risk AnalysisQuantitative Project Risk Analysis
Quantitative Project Risk Analysis
 
Risk Management in Project Management
Risk Management in Project ManagementRisk Management in Project Management
Risk Management in Project Management
 
Risk management
Risk managementRisk management
Risk management
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
Risk Management module PowerPoint Presentation Slides
Risk Management module PowerPoint Presentation SlidesRisk Management module PowerPoint Presentation Slides
Risk Management module PowerPoint Presentation Slides
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
Risk Management Process And Procedures PowerPoint Presentation Slides
Risk Management Process And Procedures PowerPoint Presentation SlidesRisk Management Process And Procedures PowerPoint Presentation Slides
Risk Management Process And Procedures PowerPoint Presentation Slides
 
Risk Management
Risk ManagementRisk Management
Risk Management
 
Mitigation Plan PowerPoint Presentation Slides
Mitigation Plan PowerPoint Presentation SlidesMitigation Plan PowerPoint Presentation Slides
Mitigation Plan PowerPoint Presentation Slides
 
Project risk management
Project risk managementProject risk management
Project risk management
 
Risk management concepts and learning
Risk management   concepts and learningRisk management   concepts and learning
Risk management concepts and learning
 

Similar to Chap 11.7 Monitor Risks

Chap 11.2 Identify Risks
Chap 11.2 Identify RisksChap 11.2 Identify Risks
Chap 11.2 Identify RisksAnand Bobade
 
Chap 4.5 Monitor and Control Project Work
Chap 4.5 Monitor and Control Project WorkChap 4.5 Monitor and Control Project Work
Chap 4.5 Monitor and Control Project WorkAnand Bobade
 
Chap 4.3 Direct and Manage Project work
Chap 4.3 Direct and Manage Project workChap 4.3 Direct and Manage Project work
Chap 4.3 Direct and Manage Project workAnand Bobade
 
Chap 5.6 Control Scope
Chap 5.6 Control ScopeChap 5.6 Control Scope
Chap 5.6 Control ScopeAnand Bobade
 
Chap 8.1 Plan quality management
Chap 8.1 Plan quality managementChap 8.1 Plan quality management
Chap 8.1 Plan quality managementAnand Bobade
 
Chap 6.2 Define Activity
Chap 6.2 Define ActivityChap 6.2 Define Activity
Chap 6.2 Define ActivityAnand Bobade
 
Chap 5.1 Plan Scope Management
Chap 5.1 Plan Scope ManagementChap 5.1 Plan Scope Management
Chap 5.1 Plan Scope ManagementAnand Bobade
 
Chap 6.6 Control Schedule
Chap 6.6 Control ScheduleChap 6.6 Control Schedule
Chap 6.6 Control ScheduleAnand Bobade
 
Chap 5.2 Collect requirements
Chap 5.2 Collect requirementsChap 5.2 Collect requirements
Chap 5.2 Collect requirementsAnand Bobade
 
Chap 5.3 define scope
Chap 5.3 define scopeChap 5.3 define scope
Chap 5.3 define scopeAnand Bobade
 
Chap 8.2 Manage Quality
Chap 8.2 Manage QualityChap 8.2 Manage Quality
Chap 8.2 Manage QualityAnand Bobade
 
Chap 4.7 Project or Phase Close
Chap 4.7 Project or Phase CloseChap 4.7 Project or Phase Close
Chap 4.7 Project or Phase CloseAnand Bobade
 
Chap 10.2 Manage Communication
Chap 10.2  Manage CommunicationChap 10.2  Manage Communication
Chap 10.2 Manage CommunicationAnand Bobade
 
Chap 6.1 Plan Schedule Management
Chap 6.1 Plan Schedule ManagementChap 6.1 Plan Schedule Management
Chap 6.1 Plan Schedule ManagementAnand Bobade
 
Chap 4.6 Perform Integrated Change Control
Chap 4.6 Perform Integrated Change ControlChap 4.6 Perform Integrated Change Control
Chap 4.6 Perform Integrated Change ControlAnand Bobade
 
Chap 8.3 Control Quality
Chap 8.3  Control QualityChap 8.3  Control Quality
Chap 8.3 Control QualityAnand Bobade
 
Chap 12.1 Plan Procurement Management
Chap 12.1 Plan Procurement ManagementChap 12.1 Plan Procurement Management
Chap 12.1 Plan Procurement ManagementAnand Bobade
 
Chap 10.3 Monitor Communication
Chap 10.3 Monitor CommunicationChap 10.3 Monitor Communication
Chap 10.3 Monitor CommunicationAnand Bobade
 
Chap 7.1 Plan Cost Management
Chap 7.1  Plan Cost ManagementChap 7.1  Plan Cost Management
Chap 7.1 Plan Cost ManagementAnand Bobade
 
Chap 5.5 validate scope
Chap 5.5 validate scopeChap 5.5 validate scope
Chap 5.5 validate scopeAnand Bobade
 

Similar to Chap 11.7 Monitor Risks (20)

Chap 11.2 Identify Risks
Chap 11.2 Identify RisksChap 11.2 Identify Risks
Chap 11.2 Identify Risks
 
Chap 4.5 Monitor and Control Project Work
Chap 4.5 Monitor and Control Project WorkChap 4.5 Monitor and Control Project Work
Chap 4.5 Monitor and Control Project Work
 
Chap 4.3 Direct and Manage Project work
Chap 4.3 Direct and Manage Project workChap 4.3 Direct and Manage Project work
Chap 4.3 Direct and Manage Project work
 
Chap 5.6 Control Scope
Chap 5.6 Control ScopeChap 5.6 Control Scope
Chap 5.6 Control Scope
 
Chap 8.1 Plan quality management
Chap 8.1 Plan quality managementChap 8.1 Plan quality management
Chap 8.1 Plan quality management
 
Chap 6.2 Define Activity
Chap 6.2 Define ActivityChap 6.2 Define Activity
Chap 6.2 Define Activity
 
Chap 5.1 Plan Scope Management
Chap 5.1 Plan Scope ManagementChap 5.1 Plan Scope Management
Chap 5.1 Plan Scope Management
 
Chap 6.6 Control Schedule
Chap 6.6 Control ScheduleChap 6.6 Control Schedule
Chap 6.6 Control Schedule
 
Chap 5.2 Collect requirements
Chap 5.2 Collect requirementsChap 5.2 Collect requirements
Chap 5.2 Collect requirements
 
Chap 5.3 define scope
Chap 5.3 define scopeChap 5.3 define scope
Chap 5.3 define scope
 
Chap 8.2 Manage Quality
Chap 8.2 Manage QualityChap 8.2 Manage Quality
Chap 8.2 Manage Quality
 
Chap 4.7 Project or Phase Close
Chap 4.7 Project or Phase CloseChap 4.7 Project or Phase Close
Chap 4.7 Project or Phase Close
 
Chap 10.2 Manage Communication
Chap 10.2  Manage CommunicationChap 10.2  Manage Communication
Chap 10.2 Manage Communication
 
Chap 6.1 Plan Schedule Management
Chap 6.1 Plan Schedule ManagementChap 6.1 Plan Schedule Management
Chap 6.1 Plan Schedule Management
 
Chap 4.6 Perform Integrated Change Control
Chap 4.6 Perform Integrated Change ControlChap 4.6 Perform Integrated Change Control
Chap 4.6 Perform Integrated Change Control
 
Chap 8.3 Control Quality
Chap 8.3  Control QualityChap 8.3  Control Quality
Chap 8.3 Control Quality
 
Chap 12.1 Plan Procurement Management
Chap 12.1 Plan Procurement ManagementChap 12.1 Plan Procurement Management
Chap 12.1 Plan Procurement Management
 
Chap 10.3 Monitor Communication
Chap 10.3 Monitor CommunicationChap 10.3 Monitor Communication
Chap 10.3 Monitor Communication
 
Chap 7.1 Plan Cost Management
Chap 7.1  Plan Cost ManagementChap 7.1  Plan Cost Management
Chap 7.1 Plan Cost Management
 
Chap 5.5 validate scope
Chap 5.5 validate scopeChap 5.5 validate scope
Chap 5.5 validate scope
 

More from Anand Bobade

PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...Anand Bobade
 
Chap 12.3 Control Procurement
Chap 12.3 Control ProcurementChap 12.3 Control Procurement
Chap 12.3 Control ProcurementAnand Bobade
 
Chap 12.2 Conduct Procurement
Chap 12.2 Conduct ProcurementChap 12.2 Conduct Procurement
Chap 12.2 Conduct ProcurementAnand Bobade
 
Chap 12.0 Procurement Management overview
Chap 12.0   Procurement Management overviewChap 12.0   Procurement Management overview
Chap 12.0 Procurement Management overviewAnand Bobade
 
Chap 10.1 Plan Communication Management
Chap 10.1  Plan Communication ManagementChap 10.1  Plan Communication Management
Chap 10.1 Plan Communication ManagementAnand Bobade
 
Chap 9.6 Control Resources
Chap 9.6  Control ResourcesChap 9.6  Control Resources
Chap 9.6 Control ResourcesAnand Bobade
 
Chap 9.5 Manage Team
Chap 9.5  Manage TeamChap 9.5  Manage Team
Chap 9.5 Manage TeamAnand Bobade
 
Chap 9.4 Develop Team
Chap 9.4  Develop TeamChap 9.4  Develop Team
Chap 9.4 Develop TeamAnand Bobade
 
Chap 9.3 Acquire Resources
Chap 9.3   Acquire ResourcesChap 9.3   Acquire Resources
Chap 9.3 Acquire ResourcesAnand Bobade
 
Chap 9.2 Estimate Activity Resource
Chap 9.2   Estimate Activity ResourceChap 9.2   Estimate Activity Resource
Chap 9.2 Estimate Activity ResourceAnand Bobade
 
Chap 9.1 Pan Resource Management
Chap 9.1   Pan Resource ManagementChap 9.1   Pan Resource Management
Chap 9.1 Pan Resource ManagementAnand Bobade
 
Chap 9.0 Project Resource Management overview
Chap 9.0   Project Resource Management overviewChap 9.0   Project Resource Management overview
Chap 9.0 Project Resource Management overviewAnand Bobade
 
Chap 7.4 Control Cost
Chap 7.4   Control CostChap 7.4   Control Cost
Chap 7.4 Control CostAnand Bobade
 
Chap 7.2 Estimate Cost
Chap 7.2 Estimate CostChap 7.2 Estimate Cost
Chap 7.2 Estimate CostAnand Bobade
 
Chap 7.3 Determine budget
Chap 7.3   Determine budgetChap 7.3   Determine budget
Chap 7.3 Determine budgetAnand Bobade
 
Chap 7.0 Project Cost Management Overview
Chap 7.0 Project Cost Management OverviewChap 7.0 Project Cost Management Overview
Chap 7.0 Project Cost Management OverviewAnand Bobade
 
Chap 6.5 Define Schedule
Chap 6.5 Define ScheduleChap 6.5 Define Schedule
Chap 6.5 Define ScheduleAnand Bobade
 
Chap 6.4 Estimate Activity Duration
Chap 6.4 Estimate Activity DurationChap 6.4 Estimate Activity Duration
Chap 6.4 Estimate Activity DurationAnand Bobade
 
Chap 6.3 Sequence Activity
Chap 6.3 Sequence ActivityChap 6.3 Sequence Activity
Chap 6.3 Sequence ActivityAnand Bobade
 
Chap 6.0 Schedule Management Overview
Chap 6.0 Schedule Management OverviewChap 6.0 Schedule Management Overview
Chap 6.0 Schedule Management OverviewAnand Bobade
 

More from Anand Bobade (20)

PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
 
Chap 12.3 Control Procurement
Chap 12.3 Control ProcurementChap 12.3 Control Procurement
Chap 12.3 Control Procurement
 
Chap 12.2 Conduct Procurement
Chap 12.2 Conduct ProcurementChap 12.2 Conduct Procurement
Chap 12.2 Conduct Procurement
 
Chap 12.0 Procurement Management overview
Chap 12.0   Procurement Management overviewChap 12.0   Procurement Management overview
Chap 12.0 Procurement Management overview
 
Chap 10.1 Plan Communication Management
Chap 10.1  Plan Communication ManagementChap 10.1  Plan Communication Management
Chap 10.1 Plan Communication Management
 
Chap 9.6 Control Resources
Chap 9.6  Control ResourcesChap 9.6  Control Resources
Chap 9.6 Control Resources
 
Chap 9.5 Manage Team
Chap 9.5  Manage TeamChap 9.5  Manage Team
Chap 9.5 Manage Team
 
Chap 9.4 Develop Team
Chap 9.4  Develop TeamChap 9.4  Develop Team
Chap 9.4 Develop Team
 
Chap 9.3 Acquire Resources
Chap 9.3   Acquire ResourcesChap 9.3   Acquire Resources
Chap 9.3 Acquire Resources
 
Chap 9.2 Estimate Activity Resource
Chap 9.2   Estimate Activity ResourceChap 9.2   Estimate Activity Resource
Chap 9.2 Estimate Activity Resource
 
Chap 9.1 Pan Resource Management
Chap 9.1   Pan Resource ManagementChap 9.1   Pan Resource Management
Chap 9.1 Pan Resource Management
 
Chap 9.0 Project Resource Management overview
Chap 9.0   Project Resource Management overviewChap 9.0   Project Resource Management overview
Chap 9.0 Project Resource Management overview
 
Chap 7.4 Control Cost
Chap 7.4   Control CostChap 7.4   Control Cost
Chap 7.4 Control Cost
 
Chap 7.2 Estimate Cost
Chap 7.2 Estimate CostChap 7.2 Estimate Cost
Chap 7.2 Estimate Cost
 
Chap 7.3 Determine budget
Chap 7.3   Determine budgetChap 7.3   Determine budget
Chap 7.3 Determine budget
 
Chap 7.0 Project Cost Management Overview
Chap 7.0 Project Cost Management OverviewChap 7.0 Project Cost Management Overview
Chap 7.0 Project Cost Management Overview
 
Chap 6.5 Define Schedule
Chap 6.5 Define ScheduleChap 6.5 Define Schedule
Chap 6.5 Define Schedule
 
Chap 6.4 Estimate Activity Duration
Chap 6.4 Estimate Activity DurationChap 6.4 Estimate Activity Duration
Chap 6.4 Estimate Activity Duration
 
Chap 6.3 Sequence Activity
Chap 6.3 Sequence ActivityChap 6.3 Sequence Activity
Chap 6.3 Sequence Activity
 
Chap 6.0 Schedule Management Overview
Chap 6.0 Schedule Management OverviewChap 6.0 Schedule Management Overview
Chap 6.0 Schedule Management Overview
 

Recently uploaded

LPC User Requirements for Automated Storage System Presentation
LPC User Requirements for Automated Storage System PresentationLPC User Requirements for Automated Storage System Presentation
LPC User Requirements for Automated Storage System Presentationthomas851723
 
Fifteenth Finance Commission Presentation
Fifteenth Finance Commission PresentationFifteenth Finance Commission Presentation
Fifteenth Finance Commission Presentationmintusiprd
 
GENUINE Babe,Call Girls IN Badarpur Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Badarpur  Delhi | +91-8377087607GENUINE Babe,Call Girls IN Badarpur  Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Badarpur Delhi | +91-8377087607dollysharma2066
 
Introduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-EngineeringIntroduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-Engineeringthomas851723
 
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girladitipandeya
 
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, MumbaiPooja Nehwal
 
Day 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampDay 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampPLCLeadershipDevelop
 
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual serviceCALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual serviceanilsa9823
 
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Pooja Nehwal
 
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Nehwal
 
LPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business SectorLPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business Sectorthomas851723
 
Board Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch PresentationBoard Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch Presentationcraig524401
 
Training Methods and Training Objectives
Training Methods and Training ObjectivesTraining Methods and Training Objectives
Training Methods and Training Objectivesmintusiprd
 
LPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations ReviewLPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations Reviewthomas851723
 
Risk management in surgery (bailey and love).pptx
Risk management in surgery (bailey and love).pptxRisk management in surgery (bailey and love).pptx
Risk management in surgery (bailey and love).pptxSaujanya Jung Pandey
 
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With RoomVIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Roomdivyansh0kumar0
 
CEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biographyCEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biographyHafizMuhammadAbdulla5
 

Recently uploaded (20)

LPC User Requirements for Automated Storage System Presentation
LPC User Requirements for Automated Storage System PresentationLPC User Requirements for Automated Storage System Presentation
LPC User Requirements for Automated Storage System Presentation
 
Fifteenth Finance Commission Presentation
Fifteenth Finance Commission PresentationFifteenth Finance Commission Presentation
Fifteenth Finance Commission Presentation
 
sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Servicesauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
 
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance VVIP 🍎 SERVICE
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SERVICECall Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SERVICE
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance VVIP 🍎 SERVICE
 
GENUINE Babe,Call Girls IN Badarpur Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Badarpur  Delhi | +91-8377087607GENUINE Babe,Call Girls IN Badarpur  Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Badarpur Delhi | +91-8377087607
 
Introduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-EngineeringIntroduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-Engineering
 
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
 
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
 
Day 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampDay 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC Bootcamp
 
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual serviceCALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
 
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
 
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
 
LPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business SectorLPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business Sector
 
Board Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch PresentationBoard Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch Presentation
 
Training Methods and Training Objectives
Training Methods and Training ObjectivesTraining Methods and Training Objectives
Training Methods and Training Objectives
 
LPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations ReviewLPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations Review
 
Risk management in surgery (bailey and love).pptx
Risk management in surgery (bailey and love).pptxRisk management in surgery (bailey and love).pptx
Risk management in surgery (bailey and love).pptx
 
Rohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No AdvanceRohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
 
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With RoomVIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
 
CEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biographyCEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biography
 

Chap 11.7 Monitor Risks

  • 1. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Chapter 11 – Project Risk Management PMP Trainer: Anand BobadePMBOK 6th Edition, 2019, All rights reserved. Monitor Risk SIXTH EDITION
  • 2. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) 11.6 Monitor Risk Monitor Risk - Definition Monitor Risk : ITTO Risk Audits Risk Re-assessment Technical Performance Measurement Review
  • 3. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Project Risk Management Processes Plan Risk management Identify Risk Perform Qualitative Risk Analysis Perform Quantitative Risk Analysis Plan Risk Response Implement Risk Monitor Risk P MC P P P P E
  • 4. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) tracking identified risks, monitoring residual risks, identifying new risks & evaluating risk process effectiveness throughout the project. It improves efficiency of risk approach & optimize risk responses. Tracking identified risks Monitoring residual risks Identifying new risks. Evaluating Risk process effectiveness. Monitor Risk Monitor Risks -> Definition
  • 5. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Perform Variance & Trend analysis using performance information. This process is not about managing or responding to risks. So, do nothing about the Risk. Determine If project assumptions are still valid. If assessed risk has changed or can be retired If Risk management plan is followed. Alignment of contingency reserves. Choose alternative strategies (workarounds). Execute contingency or fallback plan. Update PMP, OPA (Lesson learned). Monitor Risks -> Introduction
  • 6. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Monitor Risk -> ITTO Data analysis Audits Meetings Project Management Plan Project documents Work Performance Data Work Performance reports Work Performance Information Change request PMP updates Project document updates OPA updates Inputs Tools & Techniques Outputs
  • 7. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Project Management Plan Project documents Work Performance Data Work Performance reports Monitor Risk -> Inputs
  • 8. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Risk Management Plan • Overall Risk Management approach. • How to control the risk. Work Performance data • WPD from execution (Direct & Manage Project work) impacted by Risks. • E.g., Deliverable status, schedule progress and cost incurred. Work Performance reports: • Reports from Monitor & control Project work. • Contains Variance analysis, Earn Value Data & Forecasted data. • Useful in controlling Risks related to Project Performance. Monitor Risks->Inputs
  • 9. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Project documents Monitor Risk -> Inputs -> Project documents Issue log Lessons learned register Risk Register Risk Report
  • 10. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Data analysis Risk Audits Meetings Monitor Risks->T&T
  • 11. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Data analysis Technical Performance Measurement Reserve Analysis Monitor Risks->T&T
  • 12. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Technical Performance Measurement Compare technical accomplishments of project milestones to technical milestones as per the project plan. (Trend analysis using run charts) Requires defined objectives & Quantifiable technical performance measurements (E.g., Transaction time, storage capacity, no. of defects) If deviations are identified, they are documented & Risk Management team could suggest corrective actions. Q1 Q2 Q3 Design Build & test Prototype Prototype Demo to Client Monitor Risks->T&T->Technical Perf. Measurement Project Milestone Technical Milestone Technical Milestone Found many defects Impact 11.6 I T&T O
  • 13. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Reserve Analysis Compares the amount of contingency reserves remaining to the amount of risk remaining at any time in the project in order to determine if the remaining reserve is adequate. Actual used reserves Planned Reserves Monitor Risks->T&T-> Reserve Analysis If risks do not occur, then the contingency reserves which were meant to pay for those risks can go back into the “pool” of reserves
  • 14. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Risk Audits Risk audits Verify effectiveness of the risk management process. Risk audit meetings be held separately from the risk review meetings. Risk review meeting is held to review effectiveness of risk responses The format for the risk audit will be defined in the risk management plan. Monitor Risks->T&T -> Risk Audits
  • 15. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Meetings Risk review meeting is held to review effectiveness of risk responses and are separate from Status meetings Documenting the effectiveness of risk Reassessment of current risks Closing of risks that are outdated Issues that have arisen as the result of risks that have occurred Identification of lessons to be learned Monitor Risks->T&T -> Meetings
  • 16. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Work Performance Information Change request PMP updates Monitor Risks->Outputs Project document updates OPA updates
  • 17. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Project document updates Monitor Risks->Outputs-> Project document updates Assumption log Issue log Lessons learned register Risk Register Risk Report
  • 18. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Work Performance Information Provide mechanism to communicate & support project decision making. Monitor Risks->Outputs-> WPI
  • 19. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Change Requests Implementing contingency plan or workarounds sometime results in CR. Recommended Corrective actions: • Contingency Plans. • Workarounds. Recommended preventive actions: • Ensure future project performance is aligned with PMP. Monitor Risks->Outputs->CR
  • 20. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) OPA Updates Template for Risk Management plan & Risk Register. Risk Breakdown structure. Risk Categories. Lesson Learned. Monitor Risks->Outputs -> OPA
  • 21. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Monitor Risk - Definition Monitor Risk : ITTO Risk Audits Risk Re-assessment Technical Performance Measurement Monitor Risks -> Review