SlideShare a Scribd company logo
PIPE JACKING
1
Internet Document
Pipe Jacking – Ritchie-Wiki.
Available online at http://www.ritchiewiki.com/wiki/index.php/Pipe_Jacking, checked on 2/4/2017.
Internet Document
Pipe Jacking Association Homepage.
Available online at http://pipejacking.org/, checked on 2/8/2017.
Internet Document
Welcome to Civil and Environmental Engineering at the University of Waterloo.
Available online at https://uwaterloo.ca/civil-environmental-engineering/, checked on 2/8/2017.
Internet Document
Ongoing & Upcoming Trenchless Projects in India
(2016). Available online at http://www.indstt.com/trenchless_projects.html, updated on 12/17/2016, checked on 2/8/2017.
Reference:
CONTENTS
•Introduction
• Brief History
• Methodology
• Application
• Standards
• Equipment/Component
• Classification
• Alternative methods
• Pros & Cons
2
INTRODUCTION
• Pipe Jacking is the oldest method of trenchless technology.
• Pipes are pushed through the ground behind the shield
using powerful jacks.
• Simultaneously excavation takes place within the shield.
• This process is continued until the pipeline is completed.
• The method provides a flexible, structural, watertight,
finished pipeline as the tunnel is excavated.
• Thrust wall is provided for the reaction of the jacks.
3
Contd.
4
Figure 1: Pipe jacking process (a) Jacks are pushing pipe
(b) Installation of pipeline under a runway.
(a) (b)
Source: www.pipejacking.org Source: www.pipejacking.org
CONTENTS
• Introduction
• Brief History
• Methodology
• Application
• Standards
• Equipment/Component
• Classification
• Alternative methods
• Pros & Cons
5
BRIEF HISTORY
• First mentioned in 1910, USA by Richardson & Mayo.
• In 60s, used in UK and APJA(American Pipe Jacking
Association) is formed.
• In 70s, process is industrialized in Japan.
• In 80s, developed in Europe.
(i) 1800mm dia trenchless pipe is laid for 460m in London,1982.
(ii) 560m in water bearing sand and gravel, Byles, 1983.
• Komatsu introduced first fully automated machine in
1975 – IRONMOLE
• Today pipe jacking is remotely operated.
6
INDIAN HISTORY
• First project is of 3.5km in 1998, Mumbai.
• In Cuttack 10km is constructed for sewer using
trenchless method.
• Other projects of less than 8km is completed in Goa,
Hyderabad, Kolkata, Delhi, Assam etc.
• A total of around 100km is build so far using trenchless
methods so far.
Ongoing projects-
• 55km of interceptor sewer along 3 major drains for
reduction of pollution in Yamuna river at New Delhi.
7
CONTENTS
• Introduction
• Brief History
• Methodology
• Application
• Standards
• Equipment/Component
• Classification
• Alternative methods
• Pros & Cons
8
METHODOLOGY
9
PLANNING
PROCEDURE
SPECIFIC FEATURE
PROCESS BASED ON SOIL
PIPE JACKING FORCE
FAILURE
SOLUTION
PLANING
• Understand the site history and potential obstructions.
• Look at old aerial photos.
• Conduct a geotechnical program.
• Locate all existing utilities.
• Minimize costs.
• Develop the best cross section.
• Use the right materials.
10
PROCEDURE
• The thrust pit and the reception pit are excavated at the
required places.
• Then the thrust wall is set up in the thrust pit according
to the requirement.
• In case of mechanized excavations, a very large pit is
required.
• But in case of manual excavation, a small pit is enough.
• Thrust ring is provided to ensure the even distribution of
stress along the circumference of the pipe.
11
Contd.
• The number of jacks vary upon the frictional resistance
of the soil, strength of pipes etc.,
• The size of the reception pit is to be big enough to
receive the jacking shield.
• To maintain the accuracy of alignment a steerable shield
is used during the pipe jacking.
• In case of small and short distance excavations, ordinary
survey method is sufficient.
• But in case of long excavations, remote sensing and
other techniques can be used.
12
Contd.
13
Figure 2a: Pipe Jacking Arrangement
Source: http://www-civ.eng.cam.ac.uk
Contd.
14
Figure 2b: Labelled arrangement of pipe jacking
Source: www.google.com
SPECIFIC FEATURES
• Simple cyclic procedure.
• Utilizes thrust from hydraulic jacks to force the pipe forward
• Person have to enter in pipe for excavation.
• Excavation can be manual or by machine.
• Excavation takes place in front of an articulated shield.
> Designed for worker safety.
> Shield guided with individually controlled hydraulic jacks.
• Practically limited to dia. greater than or equal to 1075mm.
• Pipe installation process occurs from entrance and exit
shaft.
15
16
Figure 3: Manual and Machine Excavation
Source: www.civil.uwaterloo.ca
Source: www.civil.uwaterloo.ca
Source: www.civil.uwaterloo.ca
Source: www.civil.uwaterloo.ca
PROCESS BASED ON SOIL
Unstable soil
• Face excavated simultaneously with the jacking operation.
• Minimize over excavation and the risk of face collapse.
• After pipe jacked into place hydraulic rams are retracted
and another pipe length is installed.
Stable soil
• Face excavation may precede the jacking operation.
• All spoils removed through the inside of the pipe to the
jacking pit.
17
PIPE JACKING FORCE
• Force on jacked pipe includes:
> Pipe dead weight.
> Penetration resistance or face pressure.
> Soil-pipe friction.
• Other forces like:
> Curvature forces.
> Soil dead load.
> Railway or highway live load.
• Jacking force must not exceed allowable pipe
compressive strength .
18
19
Figure 4: Face Resistance
Source: www.youtube.com
20
Figure 5: Skin friction and face resistance
Source: www.youtube.com
21
Figure 6: Total force is greater than permissible limit
Source: www.youtube.com
22
Figure 7: Force distribution with intermediate jack
Intermediate jack
Source: www.youtube.com
FAILURE
• Pipe generally fails from the corner first.
• Maximum force is acting at the edges due to:
> Uneven distribution of jacking force from one pipe to another.
> Unavoidable curvature.
> Elastic forces from pressure transfer rings at joints.
23
Figure 8: Failure of pipe
Source: www.youtube.comSource: www.youtube.com
24
Figure 9: Failure of pipe
Source: www.youtube.com
POSSIBLE SOLUTION
Solution
Open cut/dig and replace Trenchless
25
Tunnel &
Replace
Jacking Pipe
Tunnel Liner
Plate
Slip-lining
Jacking Pipe
Plastic liner
Lining-Rehab
Cured in
place
Shotcrete
CONTENTS
• Introduction
• Brief History
• Methodology
• Application
• Standards
• Equipment/Component
• Classification
• Alternative methods
• Pros & Cons
26
APPLICATION
• Larger Diameter Pipe (1050 mm and up).
• Lengths can range from 3 to over 200m.
• Sewers, and drainage construction.
• Gas and water mains.
• Oil pipelines.
• Industrial pipelines.
• Telecommunication.
• Pedestrian subways (access tunnels).
27
CONTENTS
• Introduction
• Brief History
• Methodology
• Application
• Standards
• Equipment/Component
• Classification
• Alternative methods
• Pros & Cons
28
STANDARDS
29
• BS 6164: 2011 – Code of practice for health and safety in
tunnelling in the construction industry.
• BS EN 16191 – Tunnelling machinery safety requirements
Table 1: Standards for pipe jacking
Source: www.pipejacking.org
CONTENTS
• Introduction
• Brief History
• Methodology
• Application
• Standards
• Equipment/Component
• Classification
• Alternative methods
• Pros & Cons
30
EQUIPMENT/COMPONENT
• Jacking Pit.
• Jack.
• Pipe.
• Thrust Ring.
• Thrust wall.
• Lubricant.
• Intermediate Jack.
• Cutting-head.
• Pressure Transfer Ring etc.
31
JACKING PIT
32
• Jacking pit size is function of Length of pipe segments,
Pipe diameter, Shield dimensions, Thrust wall design,
Jack size, Pressure rings and Guide rail systems.
• Pit should be shored using Timber or steel piling.
• Placement of concrete slab on the floor is recommended.
(a) (b)
Figure 10: Typical Jacking Pit(a) and (b)
Source: www.civil.uwaterloo.ca Source: www.civil.uwaterloo.ca
JACK AND PIPE
• Number and capacity of jack is a
function of pipe size, length, skin
friction, intermediate jacks etc.
It is suggested to provide even
number of jacks.
• Pipe should be light weighted,
smooth and strong enough to
withstand all the forces.
33
Figure 11a: Jack
Figure 11b: RCP Pipe
Source: www.civil.uwaterloo.ca
Source: www.civil.uwaterloo.ca
THRUST RING AND THRUST WALL
• Thrust ring distributes force
from jack head to pipe edges
equally.
A spacer is optional.
• Thrust wall is provided behind
the jack to transfer back thrust
of jack to earth and preventing
jack to sink.
34
Figure 12a: Thrust Ring
Figure 12b: Thrust Wall
Source: www.google.com
Source: www.google.com
LUBRICANT AND INTERMEDIATE JACK
• Lubrication is provided at
outer edges of pipe using
lubricant injection ports at
proper interval.
• Intermediate jack is provided
in between the entry and exit
shaft. Number of intermediate
jack depend on pipe length
and jack capacity.
IJ must match pipe diameter.
35
Figure 13a: Lubricant injection port
Figure 13b: Intermediate Jack
Source: www.civil.uwaterloo.ca
Source: www.civil.uwaterloo.ca
CUTTING-HEAD AND
PRESSURE TRANSFER RING
• Cutting-head or cutter is located at
the front of pipe line. It cuts down
the soil ahead using mechanical
motion into smaller fragments.
• Pressure transfer ring is used in
between of two pipe at joints, it
distribute the pressure to
succeeding pipe equally. It is made
either of cork or synthetic material.
36
Figure 14b: Pressure Transfer Ring
Figure 14a: Cutter-head
Source: www.youtube.com
Source: www.google.com
CONTENTS
• Introduction
• Brief History
• Methodology
• Application
• Standards
• Equipment/Component
• Classification
• Alternative methods
• Pros & Cons
37
CLASSIFICATION
38
PipeJackingcanbeclassified
onthebasisof:
Pipe Material
Cutter-head
Excavation
Technique
39
(a) Reinforced Concrete (b) Vitrified Clay (c) Ductile Iron
(d) Fibreglass (e) Steel (f) Composite
Figure 15: Classification on basis of pipe material(a)-(f)
Source: www.civil.uwaterloo.caSource: www.civil.uwaterloo.ca
Source: www.google.comSource: www.google.comSource: www.hobas.com
Source: www.google.com
40
(d) Backacters
(a) Open Face Cutter Booms
(e) Pressurized Slurry
(b) Tunnel Boring Machine (c) Earth Pressure Balance
Figure 16: Classification on basis of Cutter-head(a)-(e)
Source: http://rightofway.transportation.org Source: http://rightofway.transportation.org Source: http://rightofway.transportation.org
Source: http://rightofway.transportation.org Source: http://rightofway.transportation.org
41
(a) Manual Excavation (b) Machine Excavation
(c) Conveyer belt Excavation (d) Slurry Excavation
Figure 17: Classification on basis of excavation technique(a)-(d)
Source: www.civil.uwaterloo.caSource: www.civil.uwaterloo.ca
Source: www.google.comSource: www.google.com
CONTENTS
• Introduction
• Brief History
• Methodology
• Application
• Standards
• Equipment/Component
• Classification
• Alternative methods
• Pros & Cons
0
42
ALTERNATIVE METHODS
Trenchless
Piping
Non-steering
Methods
Steering
Methods
43
• Moling/Piercing
• Pipe Ramming
• Auger Boring
• Pipe Jacking
• Micro-tunneling
• Horizontal
directional drilling
Generic Size and Length
• Method Size(inch) Length(ft)
Moling 2” - 12” 150’
Ramming 8” - 72” 300’
Auger Bore 8” - 60” 250’
Pilot Tube 6” - 42” 300’
Pipe Jacking >42” 1,000’
Micro-tunneling 12” - 42” 1,500’
HDD 2” - 48” 6,500’
Tunneling >60” Any length
Table 2: Compatibility of different methods 41
Source: www.pipejacking.org
45
(a) Auger Boring (b) Pilot Tube (c) Horizontal Direction Drilling
(d) Micro-tunneling (e) Pipe Ramming
Figure 18: Alternative methods(a)-(e)
Source: http://rightofway.transportation.org Source: http://rightofway.transportation.org Source: http://rightofway.transportation.org
Source: http://rightofway.transportation.org Source: http://rightofway.transportation.org
CONTENTS
• Introduction
• Brief History
• Methodology
• Application
• Standards
• Equipment/Component
• Classification
• Alternative methods
• Pros & Cons
46
ADVANTAGE
• It avoids the excavation of trenches.
• Quick set-up, timely finish of projects.
• Good quality control and good grade of pipe used.
• Can be remotely operated.
• Versatile in various ground conditions.
• Cost efficient for large length pipe.
• Small surface settlements.
• Reduces disruption to existing services.
• Environment friendly.
• Less spoil.
47
DISADVANTAGE
• Costly for small lengths.
• Skilled personal is required.
• Dewatering of tunnel path is usually required.
• Not feasible for nature of soil changes drastically.
• Hard rock/Bed rock or very big boulders should not be
present in the path line.
48
CLOSING THOUGHTS
• Methods still evolving.
• Many hybrid methods emerging.
• Will never replace traditional open-cut methods;
however, they complement each other.
New idea
• To identify potential obstructions we can install a
GPR(Ground Penetrating Radar) at cutting head.
49

More Related Content

What's hot

Dewatering techniques
Dewatering techniquesDewatering techniques
Dewatering techniques
jamali husain
 
Pile load test
Pile load testPile load test
Pile load test
Naman Kantesaria
 
Coffer dam and its type
Coffer dam and its typeCoffer dam and its type
Coffer dam and its type
Gaurang Kakadiya
 
Vacuum dewatering
Vacuum dewateringVacuum dewatering
Vacuum dewatering
Aglaia Connect
 
PPT ON TRENCHLESS TECHNOLOGY
PPT ON TRENCHLESS TECHNOLOGY PPT ON TRENCHLESS TECHNOLOGY
PPT ON TRENCHLESS TECHNOLOGY
MD AMANULLAH
 
Rigid pavement
Rigid pavementRigid pavement
Rigid pavement
pjainrahul
 
Design of t beam bridge using wsm(2)
Design of t beam bridge using wsm(2)Design of t beam bridge using wsm(2)
Design of t beam bridge using wsm(2)Ankit Singh
 
Bridge Engineering
Bridge EngineeringBridge Engineering
Bridge Engineering
KHUSHBU SHAH
 
Load carrying capacity of piles
Load carrying capacity of pilesLoad carrying capacity of piles
Load carrying capacity of piles
Latif Hyder Wadho
 
Design and construction of well foundations
Design and construction of well foundationsDesign and construction of well foundations
Design and construction of well foundations
Dar Hilal
 
Reinforced soil
Reinforced soilReinforced soil
Reinforced soil
Mohit Goyal
 
Tunnelling methods
Tunnelling methodsTunnelling methods
Tunnelling methods
Durgesh Kumar Yadav
 
PHC pile Installation methods
PHC  pile Installation methodsPHC  pile Installation methods
PHC pile Installation methods
Halim Rahman
 
Well foundation ppt
Well foundation pptWell foundation ppt
Well foundation ppt
Alauddin aziz khan
 
Construction sequence for metro Project (Elevated and Underground) and Time c...
Construction sequence for metro Project (Elevated and Underground) and Time c...Construction sequence for metro Project (Elevated and Underground) and Time c...
Construction sequence for metro Project (Elevated and Underground) and Time c...
Akhilesh Shukla
 
Study of Prefabricated Vertical Drains
Study of Prefabricated Vertical DrainsStudy of Prefabricated Vertical Drains
Study of Prefabricated Vertical Drains
NatarajaSaiCharan1
 
Erection of steel Structure
Erection of steel StructureErection of steel Structure
Erection of steel Structure
Gaurang Kakadiya
 
Box Pushing Technique
Box Pushing TechniqueBox Pushing Technique
Box Pushing Technique
Seminar Links
 
Unit 1 sheet pile-converted
Unit 1   sheet pile-convertedUnit 1   sheet pile-converted
Unit 1 sheet pile-converted
Nigitha rajan
 
Well foundation
Well foundationWell foundation

What's hot (20)

Dewatering techniques
Dewatering techniquesDewatering techniques
Dewatering techniques
 
Pile load test
Pile load testPile load test
Pile load test
 
Coffer dam and its type
Coffer dam and its typeCoffer dam and its type
Coffer dam and its type
 
Vacuum dewatering
Vacuum dewateringVacuum dewatering
Vacuum dewatering
 
PPT ON TRENCHLESS TECHNOLOGY
PPT ON TRENCHLESS TECHNOLOGY PPT ON TRENCHLESS TECHNOLOGY
PPT ON TRENCHLESS TECHNOLOGY
 
Rigid pavement
Rigid pavementRigid pavement
Rigid pavement
 
Design of t beam bridge using wsm(2)
Design of t beam bridge using wsm(2)Design of t beam bridge using wsm(2)
Design of t beam bridge using wsm(2)
 
Bridge Engineering
Bridge EngineeringBridge Engineering
Bridge Engineering
 
Load carrying capacity of piles
Load carrying capacity of pilesLoad carrying capacity of piles
Load carrying capacity of piles
 
Design and construction of well foundations
Design and construction of well foundationsDesign and construction of well foundations
Design and construction of well foundations
 
Reinforced soil
Reinforced soilReinforced soil
Reinforced soil
 
Tunnelling methods
Tunnelling methodsTunnelling methods
Tunnelling methods
 
PHC pile Installation methods
PHC  pile Installation methodsPHC  pile Installation methods
PHC pile Installation methods
 
Well foundation ppt
Well foundation pptWell foundation ppt
Well foundation ppt
 
Construction sequence for metro Project (Elevated and Underground) and Time c...
Construction sequence for metro Project (Elevated and Underground) and Time c...Construction sequence for metro Project (Elevated and Underground) and Time c...
Construction sequence for metro Project (Elevated and Underground) and Time c...
 
Study of Prefabricated Vertical Drains
Study of Prefabricated Vertical DrainsStudy of Prefabricated Vertical Drains
Study of Prefabricated Vertical Drains
 
Erection of steel Structure
Erection of steel StructureErection of steel Structure
Erection of steel Structure
 
Box Pushing Technique
Box Pushing TechniqueBox Pushing Technique
Box Pushing Technique
 
Unit 1 sheet pile-converted
Unit 1   sheet pile-convertedUnit 1   sheet pile-converted
Unit 1 sheet pile-converted
 
Well foundation
Well foundationWell foundation
Well foundation
 

Viewers also liked

Irnss
IrnssIrnss
Trenchless technolgy
Trenchless technolgyTrenchless technolgy
Trenchless technolgy
Bhalchandra Tankkar
 
Trenchless technology
Trenchless technologyTrenchless technology
Trenchless technologykumarrajagp
 
Diaphragm Wall Presentation By Gagan
Diaphragm Wall Presentation By GaganDiaphragm Wall Presentation By Gagan
Diaphragm Wall Presentation By Gagan
HERITAGE INFRASPACE INDIA PRIVATE LIMITED
 
TRENCHLESS TECHNOLOGY
TRENCHLESS TECHNOLOGYTRENCHLESS TECHNOLOGY
TRENCHLESS TECHNOLOGY
Yatiraj Battul
 
Trenchless technology
Trenchless technologyTrenchless technology
Trenchless technology
MTarunkumarreddy
 
grouting and guniting
grouting and gunitinggrouting and guniting
grouting and gunitingVipul Kerni
 
Microtunneling presentation 2014
Microtunneling presentation 2014Microtunneling presentation 2014
Microtunneling presentation 2014Jamal A'Bed
 
reliability analysis in adjustment computation
reliability analysis in adjustment computationreliability analysis in adjustment computation
reliability analysis in adjustment computation
Himanshu Gupta
 
Interlocking pavement
Interlocking pavementInterlocking pavement
Interlocking pavement
Himanshu Gupta
 
TBRR Workshop, University of Washington
TBRR Workshop, University of WashingtonTBRR Workshop, University of Washington
TBRR Workshop, University of WashingtonAngelshoot
 
NAVIC (Navigation with Indian Constellation)
NAVIC (Navigation with Indian Constellation)NAVIC (Navigation with Indian Constellation)
NAVIC (Navigation with Indian Constellation)
Mohan Kanni
 
Working of digital camera
Working of digital cameraWorking of digital camera
Working of digital camera
Himanshu Gupta
 
Irnss ppt.
Irnss ppt.Irnss ppt.
Irnss ppt.
Rakesh Singh
 
IRNSS ISRO
IRNSS ISROIRNSS ISRO
IRNSS ISRO
Saad Abbasi
 
Indian satellite based navigation system description and implementation status
Indian satellite based navigation system description and implementation statusIndian satellite based navigation system description and implementation status
Indian satellite based navigation system description and implementation status
huangxj73
 
IRNSS by Anish Raj Goyal
IRNSS by Anish Raj GoyalIRNSS by Anish Raj Goyal
IRNSS by Anish Raj Goyal
Anish Raj Goyal
 
Navic
NavicNavic
Indian Regional Navigational Satellite System (IRNSS)
Indian Regional Navigational Satellite System (IRNSS)Indian Regional Navigational Satellite System (IRNSS)
Indian Regional Navigational Satellite System (IRNSS)
Yelendher Reddy
 
Silver Lake Reservoir Complex Storage Replacement; Construction Phase I Photo...
Silver Lake Reservoir Complex Storage Replacement; Construction Phase I Photo...Silver Lake Reservoir Complex Storage Replacement; Construction Phase I Photo...
Silver Lake Reservoir Complex Storage Replacement; Construction Phase I Photo...
Tina Howell, MBA LEED AP
 

Viewers also liked (20)

Irnss
IrnssIrnss
Irnss
 
Trenchless technolgy
Trenchless technolgyTrenchless technolgy
Trenchless technolgy
 
Trenchless technology
Trenchless technologyTrenchless technology
Trenchless technology
 
Diaphragm Wall Presentation By Gagan
Diaphragm Wall Presentation By GaganDiaphragm Wall Presentation By Gagan
Diaphragm Wall Presentation By Gagan
 
TRENCHLESS TECHNOLOGY
TRENCHLESS TECHNOLOGYTRENCHLESS TECHNOLOGY
TRENCHLESS TECHNOLOGY
 
Trenchless technology
Trenchless technologyTrenchless technology
Trenchless technology
 
grouting and guniting
grouting and gunitinggrouting and guniting
grouting and guniting
 
Microtunneling presentation 2014
Microtunneling presentation 2014Microtunneling presentation 2014
Microtunneling presentation 2014
 
reliability analysis in adjustment computation
reliability analysis in adjustment computationreliability analysis in adjustment computation
reliability analysis in adjustment computation
 
Interlocking pavement
Interlocking pavementInterlocking pavement
Interlocking pavement
 
TBRR Workshop, University of Washington
TBRR Workshop, University of WashingtonTBRR Workshop, University of Washington
TBRR Workshop, University of Washington
 
NAVIC (Navigation with Indian Constellation)
NAVIC (Navigation with Indian Constellation)NAVIC (Navigation with Indian Constellation)
NAVIC (Navigation with Indian Constellation)
 
Working of digital camera
Working of digital cameraWorking of digital camera
Working of digital camera
 
Irnss ppt.
Irnss ppt.Irnss ppt.
Irnss ppt.
 
IRNSS ISRO
IRNSS ISROIRNSS ISRO
IRNSS ISRO
 
Indian satellite based navigation system description and implementation status
Indian satellite based navigation system description and implementation statusIndian satellite based navigation system description and implementation status
Indian satellite based navigation system description and implementation status
 
IRNSS by Anish Raj Goyal
IRNSS by Anish Raj GoyalIRNSS by Anish Raj Goyal
IRNSS by Anish Raj Goyal
 
Navic
NavicNavic
Navic
 
Indian Regional Navigational Satellite System (IRNSS)
Indian Regional Navigational Satellite System (IRNSS)Indian Regional Navigational Satellite System (IRNSS)
Indian Regional Navigational Satellite System (IRNSS)
 
Silver Lake Reservoir Complex Storage Replacement; Construction Phase I Photo...
Silver Lake Reservoir Complex Storage Replacement; Construction Phase I Photo...Silver Lake Reservoir Complex Storage Replacement; Construction Phase I Photo...
Silver Lake Reservoir Complex Storage Replacement; Construction Phase I Photo...
 

Similar to Pipe Jacking

Trenchless technology
Trenchless technologyTrenchless technology
Trenchless technology
Aglaia Connect
 
trenchlesstechnologybymdamanullah-150920165545-lva1-app6892 (3).pdf
trenchlesstechnologybymdamanullah-150920165545-lva1-app6892 (3).pdftrenchlesstechnologybymdamanullah-150920165545-lva1-app6892 (3).pdf
trenchlesstechnologybymdamanullah-150920165545-lva1-app6892 (3).pdf
pawankumar491710
 
TRENCHLESS-TECHNOLOGY.pdf
TRENCHLESS-TECHNOLOGY.pdfTRENCHLESS-TECHNOLOGY.pdf
TRENCHLESS-TECHNOLOGY.pdf
KARTHIKGOUD64
 
Trenchless Technology for Laying Underground pipes.
Trenchless Technology for  Laying Underground pipes.Trenchless Technology for  Laying Underground pipes.
Trenchless Technology for Laying Underground pipes.
Himanshu Rao
 
UMAID IQBAL SEMINAR.pptx
UMAID IQBAL SEMINAR.pptxUMAID IQBAL SEMINAR.pptx
UMAID IQBAL SEMINAR.pptx
Praveendubey82
 
Trenchless Technology a Review
Trenchless Technology a Review Trenchless Technology a Review
Trenchless Technology a Review
AkshathaBhandary
 
Shotcrete technology
Shotcrete technologyShotcrete technology
Shotcrete technology
Raghavendra Raghu
 
Blue mountains cascade dam- Horizontal direction drill
Blue mountains cascade dam- Horizontal direction drillBlue mountains cascade dam- Horizontal direction drill
Blue mountains cascade dam- Horizontal direction drill
DeanGarratt
 
presentation on shotcrete technology
presentation on shotcrete technologypresentation on shotcrete technology
presentation on shotcrete technology
Abhishek Paul
 
transtech.pptx
transtech.pptxtranstech.pptx
transtech.pptx
pawankumar491710
 
A brief overview of drilling and blasting process for tunnel excavation used ...
A brief overview of drilling and blasting process for tunnel excavation used ...A brief overview of drilling and blasting process for tunnel excavation used ...
A brief overview of drilling and blasting process for tunnel excavation used ...
kimilsungLimbu
 
Dcl hdd presentation 9 2-2014
Dcl hdd presentation 9 2-2014Dcl hdd presentation 9 2-2014
Dcl hdd presentation 9 2-2014
Mohammed wahab
 
trenchless technology
trenchless technologytrenchless technology
trenchless technologyHemish Patel
 
Trenchless technology
Trenchless technologyTrenchless technology
Trenchless technology
dinesh sharma
 
Stripping of liners from pipes using hdd technology (2007)
Stripping of liners from pipes using hdd technology (2007)Stripping of liners from pipes using hdd technology (2007)
Stripping of liners from pipes using hdd technology (2007)
Western Pipeway
 
SDP Presentation.pptx
SDP Presentation.pptxSDP Presentation.pptx
SDP Presentation.pptx
SubhransuPatra3
 
Trenchless Technologies for New Pipe Installations
Trenchless Technologies for New Pipe InstallationsTrenchless Technologies for New Pipe Installations
Trenchless Technologies for New Pipe Installations
Loay Ghazaleh MBA, BSc Civil Eng.
 
A Complete Guide on Directional Boring
A Complete Guide on Directional BoringA Complete Guide on Directional Boring
A Complete Guide on Directional Boring
We-Bore-It
 
Trench less Technology
Trench less Technology Trench less Technology
Trench less Technology
Abhimanyu Saraswat
 

Similar to Pipe Jacking (20)

Trenchless technology
Trenchless technologyTrenchless technology
Trenchless technology
 
trenchlesstechnologybymdamanullah-150920165545-lva1-app6892 (3).pdf
trenchlesstechnologybymdamanullah-150920165545-lva1-app6892 (3).pdftrenchlesstechnologybymdamanullah-150920165545-lva1-app6892 (3).pdf
trenchlesstechnologybymdamanullah-150920165545-lva1-app6892 (3).pdf
 
TRENCHLESS-TECHNOLOGY.pdf
TRENCHLESS-TECHNOLOGY.pdfTRENCHLESS-TECHNOLOGY.pdf
TRENCHLESS-TECHNOLOGY.pdf
 
Trenchless Technology for Laying Underground pipes.
Trenchless Technology for  Laying Underground pipes.Trenchless Technology for  Laying Underground pipes.
Trenchless Technology for Laying Underground pipes.
 
UMAID IQBAL SEMINAR.pptx
UMAID IQBAL SEMINAR.pptxUMAID IQBAL SEMINAR.pptx
UMAID IQBAL SEMINAR.pptx
 
Trenchless Technology a Review
Trenchless Technology a Review Trenchless Technology a Review
Trenchless Technology a Review
 
Shotcrete technology
Shotcrete technologyShotcrete technology
Shotcrete technology
 
Blue mountains cascade dam- Horizontal direction drill
Blue mountains cascade dam- Horizontal direction drillBlue mountains cascade dam- Horizontal direction drill
Blue mountains cascade dam- Horizontal direction drill
 
presentation on shotcrete technology
presentation on shotcrete technologypresentation on shotcrete technology
presentation on shotcrete technology
 
transtech.pptx
transtech.pptxtranstech.pptx
transtech.pptx
 
A brief overview of drilling and blasting process for tunnel excavation used ...
A brief overview of drilling and blasting process for tunnel excavation used ...A brief overview of drilling and blasting process for tunnel excavation used ...
A brief overview of drilling and blasting process for tunnel excavation used ...
 
Dcl hdd presentation 9 2-2014
Dcl hdd presentation 9 2-2014Dcl hdd presentation 9 2-2014
Dcl hdd presentation 9 2-2014
 
trenchless technology
trenchless technologytrenchless technology
trenchless technology
 
Trenchless technology
Trenchless technologyTrenchless technology
Trenchless technology
 
Stripping of liners from pipes using hdd technology (2007)
Stripping of liners from pipes using hdd technology (2007)Stripping of liners from pipes using hdd technology (2007)
Stripping of liners from pipes using hdd technology (2007)
 
SDP Presentation.pptx
SDP Presentation.pptxSDP Presentation.pptx
SDP Presentation.pptx
 
Trenchless Technologies for New Pipe Installations
Trenchless Technologies for New Pipe InstallationsTrenchless Technologies for New Pipe Installations
Trenchless Technologies for New Pipe Installations
 
Final Project Presentation
Final Project PresentationFinal Project Presentation
Final Project Presentation
 
A Complete Guide on Directional Boring
A Complete Guide on Directional BoringA Complete Guide on Directional Boring
A Complete Guide on Directional Boring
 
Trench less Technology
Trench less Technology Trench less Technology
Trench less Technology
 

Recently uploaded

Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345
beazzy04
 
Cambridge International AS A Level Biology Coursebook - EBook (MaryFosbery J...
Cambridge International AS  A Level Biology Coursebook - EBook (MaryFosbery J...Cambridge International AS  A Level Biology Coursebook - EBook (MaryFosbery J...
Cambridge International AS A Level Biology Coursebook - EBook (MaryFosbery J...
AzmatAli747758
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
siemaillard
 
Unit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdfUnit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdf
Thiyagu K
 
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCECLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
BhavyaRajput3
 
GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...
GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...
GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...
Nguyen Thanh Tu Collection
 
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptxStudents, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
EduSkills OECD
 
PART A. Introduction to Costumer Service
PART A. Introduction to Costumer ServicePART A. Introduction to Costumer Service
PART A. Introduction to Costumer Service
PedroFerreira53928
 
The Art Pastor's Guide to Sabbath | Steve Thomason
The Art Pastor's Guide to Sabbath | Steve ThomasonThe Art Pastor's Guide to Sabbath | Steve Thomason
The Art Pastor's Guide to Sabbath | Steve Thomason
Steve Thomason
 
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXXPhrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
MIRIAMSALINAS13
 
Palestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptxPalestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptx
RaedMohamed3
 
How to Create Map Views in the Odoo 17 ERP
How to Create Map Views in the Odoo 17 ERPHow to Create Map Views in the Odoo 17 ERP
How to Create Map Views in the Odoo 17 ERP
Celine George
 
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
EugeneSaldivar
 
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
MysoreMuleSoftMeetup
 
1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx
JosvitaDsouza2
 
Supporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptxSupporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptx
Jisc
 
Thesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.pptThesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.ppt
EverAndrsGuerraGuerr
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
siemaillard
 
Basic phrases for greeting and assisting costumers
Basic phrases for greeting and assisting costumersBasic phrases for greeting and assisting costumers
Basic phrases for greeting and assisting costumers
PedroFerreira53928
 
Digital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and ResearchDigital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and Research
Vikramjit Singh
 

Recently uploaded (20)

Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345
 
Cambridge International AS A Level Biology Coursebook - EBook (MaryFosbery J...
Cambridge International AS  A Level Biology Coursebook - EBook (MaryFosbery J...Cambridge International AS  A Level Biology Coursebook - EBook (MaryFosbery J...
Cambridge International AS A Level Biology Coursebook - EBook (MaryFosbery J...
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
 
Unit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdfUnit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdf
 
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCECLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
 
GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...
GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...
GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...
 
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptxStudents, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
 
PART A. Introduction to Costumer Service
PART A. Introduction to Costumer ServicePART A. Introduction to Costumer Service
PART A. Introduction to Costumer Service
 
The Art Pastor's Guide to Sabbath | Steve Thomason
The Art Pastor's Guide to Sabbath | Steve ThomasonThe Art Pastor's Guide to Sabbath | Steve Thomason
The Art Pastor's Guide to Sabbath | Steve Thomason
 
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXXPhrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
 
Palestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptxPalestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptx
 
How to Create Map Views in the Odoo 17 ERP
How to Create Map Views in the Odoo 17 ERPHow to Create Map Views in the Odoo 17 ERP
How to Create Map Views in the Odoo 17 ERP
 
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
 
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
 
1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx
 
Supporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptxSupporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptx
 
Thesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.pptThesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.ppt
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
 
Basic phrases for greeting and assisting costumers
Basic phrases for greeting and assisting costumersBasic phrases for greeting and assisting costumers
Basic phrases for greeting and assisting costumers
 
Digital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and ResearchDigital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and Research
 

Pipe Jacking

  • 1. PIPE JACKING 1 Internet Document Pipe Jacking – Ritchie-Wiki. Available online at http://www.ritchiewiki.com/wiki/index.php/Pipe_Jacking, checked on 2/4/2017. Internet Document Pipe Jacking Association Homepage. Available online at http://pipejacking.org/, checked on 2/8/2017. Internet Document Welcome to Civil and Environmental Engineering at the University of Waterloo. Available online at https://uwaterloo.ca/civil-environmental-engineering/, checked on 2/8/2017. Internet Document Ongoing & Upcoming Trenchless Projects in India (2016). Available online at http://www.indstt.com/trenchless_projects.html, updated on 12/17/2016, checked on 2/8/2017. Reference:
  • 2. CONTENTS •Introduction • Brief History • Methodology • Application • Standards • Equipment/Component • Classification • Alternative methods • Pros & Cons 2
  • 3. INTRODUCTION • Pipe Jacking is the oldest method of trenchless technology. • Pipes are pushed through the ground behind the shield using powerful jacks. • Simultaneously excavation takes place within the shield. • This process is continued until the pipeline is completed. • The method provides a flexible, structural, watertight, finished pipeline as the tunnel is excavated. • Thrust wall is provided for the reaction of the jacks. 3
  • 4. Contd. 4 Figure 1: Pipe jacking process (a) Jacks are pushing pipe (b) Installation of pipeline under a runway. (a) (b) Source: www.pipejacking.org Source: www.pipejacking.org
  • 5. CONTENTS • Introduction • Brief History • Methodology • Application • Standards • Equipment/Component • Classification • Alternative methods • Pros & Cons 5
  • 6. BRIEF HISTORY • First mentioned in 1910, USA by Richardson & Mayo. • In 60s, used in UK and APJA(American Pipe Jacking Association) is formed. • In 70s, process is industrialized in Japan. • In 80s, developed in Europe. (i) 1800mm dia trenchless pipe is laid for 460m in London,1982. (ii) 560m in water bearing sand and gravel, Byles, 1983. • Komatsu introduced first fully automated machine in 1975 – IRONMOLE • Today pipe jacking is remotely operated. 6
  • 7. INDIAN HISTORY • First project is of 3.5km in 1998, Mumbai. • In Cuttack 10km is constructed for sewer using trenchless method. • Other projects of less than 8km is completed in Goa, Hyderabad, Kolkata, Delhi, Assam etc. • A total of around 100km is build so far using trenchless methods so far. Ongoing projects- • 55km of interceptor sewer along 3 major drains for reduction of pollution in Yamuna river at New Delhi. 7
  • 8. CONTENTS • Introduction • Brief History • Methodology • Application • Standards • Equipment/Component • Classification • Alternative methods • Pros & Cons 8
  • 9. METHODOLOGY 9 PLANNING PROCEDURE SPECIFIC FEATURE PROCESS BASED ON SOIL PIPE JACKING FORCE FAILURE SOLUTION
  • 10. PLANING • Understand the site history and potential obstructions. • Look at old aerial photos. • Conduct a geotechnical program. • Locate all existing utilities. • Minimize costs. • Develop the best cross section. • Use the right materials. 10
  • 11. PROCEDURE • The thrust pit and the reception pit are excavated at the required places. • Then the thrust wall is set up in the thrust pit according to the requirement. • In case of mechanized excavations, a very large pit is required. • But in case of manual excavation, a small pit is enough. • Thrust ring is provided to ensure the even distribution of stress along the circumference of the pipe. 11
  • 12. Contd. • The number of jacks vary upon the frictional resistance of the soil, strength of pipes etc., • The size of the reception pit is to be big enough to receive the jacking shield. • To maintain the accuracy of alignment a steerable shield is used during the pipe jacking. • In case of small and short distance excavations, ordinary survey method is sufficient. • But in case of long excavations, remote sensing and other techniques can be used. 12
  • 13. Contd. 13 Figure 2a: Pipe Jacking Arrangement Source: http://www-civ.eng.cam.ac.uk
  • 14. Contd. 14 Figure 2b: Labelled arrangement of pipe jacking Source: www.google.com
  • 15. SPECIFIC FEATURES • Simple cyclic procedure. • Utilizes thrust from hydraulic jacks to force the pipe forward • Person have to enter in pipe for excavation. • Excavation can be manual or by machine. • Excavation takes place in front of an articulated shield. > Designed for worker safety. > Shield guided with individually controlled hydraulic jacks. • Practically limited to dia. greater than or equal to 1075mm. • Pipe installation process occurs from entrance and exit shaft. 15
  • 16. 16 Figure 3: Manual and Machine Excavation Source: www.civil.uwaterloo.ca Source: www.civil.uwaterloo.ca Source: www.civil.uwaterloo.ca Source: www.civil.uwaterloo.ca
  • 17. PROCESS BASED ON SOIL Unstable soil • Face excavated simultaneously with the jacking operation. • Minimize over excavation and the risk of face collapse. • After pipe jacked into place hydraulic rams are retracted and another pipe length is installed. Stable soil • Face excavation may precede the jacking operation. • All spoils removed through the inside of the pipe to the jacking pit. 17
  • 18. PIPE JACKING FORCE • Force on jacked pipe includes: > Pipe dead weight. > Penetration resistance or face pressure. > Soil-pipe friction. • Other forces like: > Curvature forces. > Soil dead load. > Railway or highway live load. • Jacking force must not exceed allowable pipe compressive strength . 18
  • 19. 19 Figure 4: Face Resistance Source: www.youtube.com
  • 20. 20 Figure 5: Skin friction and face resistance Source: www.youtube.com
  • 21. 21 Figure 6: Total force is greater than permissible limit Source: www.youtube.com
  • 22. 22 Figure 7: Force distribution with intermediate jack Intermediate jack Source: www.youtube.com
  • 23. FAILURE • Pipe generally fails from the corner first. • Maximum force is acting at the edges due to: > Uneven distribution of jacking force from one pipe to another. > Unavoidable curvature. > Elastic forces from pressure transfer rings at joints. 23 Figure 8: Failure of pipe Source: www.youtube.comSource: www.youtube.com
  • 24. 24 Figure 9: Failure of pipe Source: www.youtube.com
  • 25. POSSIBLE SOLUTION Solution Open cut/dig and replace Trenchless 25 Tunnel & Replace Jacking Pipe Tunnel Liner Plate Slip-lining Jacking Pipe Plastic liner Lining-Rehab Cured in place Shotcrete
  • 26. CONTENTS • Introduction • Brief History • Methodology • Application • Standards • Equipment/Component • Classification • Alternative methods • Pros & Cons 26
  • 27. APPLICATION • Larger Diameter Pipe (1050 mm and up). • Lengths can range from 3 to over 200m. • Sewers, and drainage construction. • Gas and water mains. • Oil pipelines. • Industrial pipelines. • Telecommunication. • Pedestrian subways (access tunnels). 27
  • 28. CONTENTS • Introduction • Brief History • Methodology • Application • Standards • Equipment/Component • Classification • Alternative methods • Pros & Cons 28
  • 29. STANDARDS 29 • BS 6164: 2011 – Code of practice for health and safety in tunnelling in the construction industry. • BS EN 16191 – Tunnelling machinery safety requirements Table 1: Standards for pipe jacking Source: www.pipejacking.org
  • 30. CONTENTS • Introduction • Brief History • Methodology • Application • Standards • Equipment/Component • Classification • Alternative methods • Pros & Cons 30
  • 31. EQUIPMENT/COMPONENT • Jacking Pit. • Jack. • Pipe. • Thrust Ring. • Thrust wall. • Lubricant. • Intermediate Jack. • Cutting-head. • Pressure Transfer Ring etc. 31
  • 32. JACKING PIT 32 • Jacking pit size is function of Length of pipe segments, Pipe diameter, Shield dimensions, Thrust wall design, Jack size, Pressure rings and Guide rail systems. • Pit should be shored using Timber or steel piling. • Placement of concrete slab on the floor is recommended. (a) (b) Figure 10: Typical Jacking Pit(a) and (b) Source: www.civil.uwaterloo.ca Source: www.civil.uwaterloo.ca
  • 33. JACK AND PIPE • Number and capacity of jack is a function of pipe size, length, skin friction, intermediate jacks etc. It is suggested to provide even number of jacks. • Pipe should be light weighted, smooth and strong enough to withstand all the forces. 33 Figure 11a: Jack Figure 11b: RCP Pipe Source: www.civil.uwaterloo.ca Source: www.civil.uwaterloo.ca
  • 34. THRUST RING AND THRUST WALL • Thrust ring distributes force from jack head to pipe edges equally. A spacer is optional. • Thrust wall is provided behind the jack to transfer back thrust of jack to earth and preventing jack to sink. 34 Figure 12a: Thrust Ring Figure 12b: Thrust Wall Source: www.google.com Source: www.google.com
  • 35. LUBRICANT AND INTERMEDIATE JACK • Lubrication is provided at outer edges of pipe using lubricant injection ports at proper interval. • Intermediate jack is provided in between the entry and exit shaft. Number of intermediate jack depend on pipe length and jack capacity. IJ must match pipe diameter. 35 Figure 13a: Lubricant injection port Figure 13b: Intermediate Jack Source: www.civil.uwaterloo.ca Source: www.civil.uwaterloo.ca
  • 36. CUTTING-HEAD AND PRESSURE TRANSFER RING • Cutting-head or cutter is located at the front of pipe line. It cuts down the soil ahead using mechanical motion into smaller fragments. • Pressure transfer ring is used in between of two pipe at joints, it distribute the pressure to succeeding pipe equally. It is made either of cork or synthetic material. 36 Figure 14b: Pressure Transfer Ring Figure 14a: Cutter-head Source: www.youtube.com Source: www.google.com
  • 37. CONTENTS • Introduction • Brief History • Methodology • Application • Standards • Equipment/Component • Classification • Alternative methods • Pros & Cons 37
  • 39. 39 (a) Reinforced Concrete (b) Vitrified Clay (c) Ductile Iron (d) Fibreglass (e) Steel (f) Composite Figure 15: Classification on basis of pipe material(a)-(f) Source: www.civil.uwaterloo.caSource: www.civil.uwaterloo.ca Source: www.google.comSource: www.google.comSource: www.hobas.com Source: www.google.com
  • 40. 40 (d) Backacters (a) Open Face Cutter Booms (e) Pressurized Slurry (b) Tunnel Boring Machine (c) Earth Pressure Balance Figure 16: Classification on basis of Cutter-head(a)-(e) Source: http://rightofway.transportation.org Source: http://rightofway.transportation.org Source: http://rightofway.transportation.org Source: http://rightofway.transportation.org Source: http://rightofway.transportation.org
  • 41. 41 (a) Manual Excavation (b) Machine Excavation (c) Conveyer belt Excavation (d) Slurry Excavation Figure 17: Classification on basis of excavation technique(a)-(d) Source: www.civil.uwaterloo.caSource: www.civil.uwaterloo.ca Source: www.google.comSource: www.google.com
  • 42. CONTENTS • Introduction • Brief History • Methodology • Application • Standards • Equipment/Component • Classification • Alternative methods • Pros & Cons 0 42
  • 43. ALTERNATIVE METHODS Trenchless Piping Non-steering Methods Steering Methods 43 • Moling/Piercing • Pipe Ramming • Auger Boring • Pipe Jacking • Micro-tunneling • Horizontal directional drilling
  • 44. Generic Size and Length • Method Size(inch) Length(ft) Moling 2” - 12” 150’ Ramming 8” - 72” 300’ Auger Bore 8” - 60” 250’ Pilot Tube 6” - 42” 300’ Pipe Jacking >42” 1,000’ Micro-tunneling 12” - 42” 1,500’ HDD 2” - 48” 6,500’ Tunneling >60” Any length Table 2: Compatibility of different methods 41 Source: www.pipejacking.org
  • 45. 45 (a) Auger Boring (b) Pilot Tube (c) Horizontal Direction Drilling (d) Micro-tunneling (e) Pipe Ramming Figure 18: Alternative methods(a)-(e) Source: http://rightofway.transportation.org Source: http://rightofway.transportation.org Source: http://rightofway.transportation.org Source: http://rightofway.transportation.org Source: http://rightofway.transportation.org
  • 46. CONTENTS • Introduction • Brief History • Methodology • Application • Standards • Equipment/Component • Classification • Alternative methods • Pros & Cons 46
  • 47. ADVANTAGE • It avoids the excavation of trenches. • Quick set-up, timely finish of projects. • Good quality control and good grade of pipe used. • Can be remotely operated. • Versatile in various ground conditions. • Cost efficient for large length pipe. • Small surface settlements. • Reduces disruption to existing services. • Environment friendly. • Less spoil. 47
  • 48. DISADVANTAGE • Costly for small lengths. • Skilled personal is required. • Dewatering of tunnel path is usually required. • Not feasible for nature of soil changes drastically. • Hard rock/Bed rock or very big boulders should not be present in the path line. 48
  • 49. CLOSING THOUGHTS • Methods still evolving. • Many hybrid methods emerging. • Will never replace traditional open-cut methods; however, they complement each other. New idea • To identify potential obstructions we can install a GPR(Ground Penetrating Radar) at cutting head. 49