1. TRENCHLESS TECHNOLOGY
Prepared By:
PATEL HEMISHKUMAR ANILBHAI
ENROLLMENT NO: 130080714008
FIRST SEMESTER
BIRLA
VISHVAKARMA
MAHAVIDHYALAYA
GUJARAT
TECHNOLOGICAL
UNIVERSITY
M.E. [ CONSTRUCTION
ENGINEERING &
MANAGEMENT ]CONSTRUCTION TECHNIQUES
(711402)
Guide By:
PROF. JAYESHKUMAR R. PITRODA
ASSISTANT PROFESSOR & RESEARCH
SCHOLAR
CIVIL ENGINEERING DEPARTMENT
B.V.M ENGINEERING COLLEGE
2. CONTENTS
2
Introduction
History
WHY Trenchless ?
Trenchless methods
New installation
Rehabilitation and Renovation
Techniques of Trenchless Technology
Conclusion
Reference
Acknowledgement
3. Introduction
A family of methods, materials, and equipment capable
of being used for the installation of new or replacement
or rehabilitation of existing underground infrastructure
with minimal disruption to surface traffic, business, and
other activities.
3
4. History
Trenchless technology has been around for many decades
Auger or Jack and Bore in use for 40-50 years
Impact moles were populars for street crossings and to go
under rock gardens
Horizontal Directional Drilling (HDD) started to gain
popularity in late 80`s
Address at 1991 ‘ NO DIG’
4
6. Why TRENCHLESS ?
Minimal disturbance to traffic
Year around construction
Improved safety
Reduced landscape damage
Minimal disturbance to local business
Improved construction productivity
Can access otherwise inaccessible areas
6
8. New installation
Methods for the installation of a new pipeline or duct,
including dealing with service connections are :
8
Augur boring
Impact moling
Micro tunneling
Horizontal Directional
Drilling
9. AUGUR BORING
To excavate the soil, which
is transported by augur
flights operating in a
casing the drive pit.
Range 100 to 1000 mm
diameter
9
10. IMPACT MOLING
Impact moling is a technique in which a percussive mole
(soil displacement hammer) is launched from an
excavation to displace the soil and form a bore.
This method is restricted to relatively small diameter lines
in compressible soil conditions.
10
11. MICROTUNNELING
The micro tunneling boring machine is remote controlled, a
laser guided system is employed, a jacking system is used
to thrust, and continuous pressure is provided to the face
of the excavation to balance groundwater and earth
pressures.
11
12. HORIZONTAL DIRECTIONAL
DRILLING (HDD)
Used for installing pressure pipes under major
obstacles such as airport runways, rivers, railway
tracks and roads.
12
14. PIPE BURSTING
In this method an existing
pipe can be replaced with
a pipeline of the same or
larger dimension without
opening up the ground.
It used where the load on
the system is more than
the existing pipe can
handle and replacement
is required.
14
15. PIPE EATING
Pipe eating is an online micro tunneled replacement
technique.
The existing defective pipeline is crushed and removed
through the new pipeline
15
16. RELINING THE EXISTING PIPES
In this method man hole required at the both ends of pipe.
16
Cured-in-
place lining
Spray liningSlip lining
Close-fit
lining
18. Techniques of Trenchless Technology
i. Augur boring
ii. Moling
iii. Ramming
iv. Directional drilling
18
19. AUGUR BORING
Auger boring is a
technique for forming a
horizontal bore hole
through the ground, from a
drive shaft to a reception
shaft, by means of a
rotating cutting head. The
cutting head is attached to
the leading end of an
auger string. Spoil is
transported back to the
drive shaft by the rotation
of helical-wound auger
flights within the steel
19
20. Advantages
A
U
G
U
R
B
O
R
I
N
G
The major advantage is that the casing is
installed at the same time as the borehole
excavation takes place.
This method can be used wide variety of soil
types.
20
21. Disadvantages
A
U
G
U
R
B
O
R
I
N
G
This method requires different size cutting
heads and augur sizes or each casing diameter,
which increases the investment in equipment.
The investment in bore, pit construction, and
the initial setup is also required.
In case of soils containing large boulders, this
method cannot be used advantageously.
21
22. MOLING
Instead pits are excavated at intervals for the mole to be
placed. The mole is then entered into the earth on the
horizontal face at the bottom of the pit. Destination pits of
similar proportions are also dug.
The mole displaces the soil creating a bore for the new
services to then be pulled through.
22
23. Advantages
M
O
L
I
N
G
It is a rapid, economic, and effective method of
installing small diameter lines.
Any type of utility line can be installed using this
method.
The stability of the soil around the borehole is
increased due to compaction.
The investment in equipment is minimum.
23
24. Disadvantages
M
O
L
I
N
G
Compaction method are limited in their length
by reliability because basic systems are
unintelligent, unguided tools that tend to bury
themselves, surface in the middle road or
damage exiting utility lines.
24
25. RAMMING
Ramming creates very little displacement in the
surrounding ground.
The pipe is rammed through the soil by using a device
attached to the end of wide to drive the pipe through the
soil.
This method is economical for small dia pipelines.
25
26. DIRECTIONAL DRILLING (DD)
Directional Drilling makes the impossible possible.
Generally, it is preferred for long line drilling.
26
27. Advantages
D
D
The major advantage is the speed of installation
combined with the minimum environmental and
social impact.
Long and complicated crossings can be
accomplished with a great degree of accuracy.
Sufficient depth can be accomplished to avoid
other utilities.
Limitation of access and reception pits is
another advantage.
27
28. Disadvantages
D
D
Special equipment and very high degree of
operation skill is required.
As the cost of equipment and the operation are
high, bore length should be sufficient in order
for it to be economical.
Mainly steel pipe is being installed by this
method.
28
29. CONCLUSION
Cost effective
Low labor requirements
Little site restoration required
Environmental friendly
Reduce environment Construction hazards
Reduce noise and air quality impacts
Reduce traffic congestion
Trenchless technology is the new way forward.
29
31. ACKNOWLEGEMENT
31
DR. F. S. Umrigar, Principal, B.V.M. Engineering college,
Prof. J. J. Bhavsar, Associate Prof., PG co-ordinator, cvil
engineering department, B.V.M. Engineering college Vallabh
Vidhyanagar, Gujrat, India for their motivation and
infrastructural support to carry out the research work.
Prof. Jayeshkumar R. Pitroda assitant prof. And research
scholar civil engineering department, B.V.M. Engineering
college Vallabh Vidhyanagar.