This document discusses the process for constructing overhead transmission line foundations. It outlines several types of foundations depending on soil conditions, including normal dry soil, partially submerged soil, and fully submerged soil. The construction process involves 11 steps: surveying and pit marking, excavation, plain cement concrete, stub setting, steel reinforcement, concreting, curing, de-shuttering and template removal, grounding installation, backfilling and compacting, and leveling or removing excess soil. Additional details are provided for some of the key steps in the construction process.
Complete details of EHV Transmission Line. Consolidated this presentation from those experts who had contributed separately on slider share and other web pages.Thanks for their valuable inputs.
The major challenge in Indian power sector is operating upgrading of the transmission & distribution lines with efficient meteringApplication of smart grid devices for consistently condition monitoring of overhead lines &substation can decides the action of maintenance required and thus condition-based maintenance (CBM) technique can be implemented. To meet ever increase in demand, reduction of value of losses, utilization of huge renewable energy and absence of automation in power Transmission & Distribution, there is need of Preventive Maintenance (PM) & logy(RCM).
The financial growth of India also depends on availability of electricity. Indian power sector having characteristics as shortage of generation and high T & D losses up to 30% of total electricity generation with some parts of states of country up to 40%. When losses due to theft are added in the total then average losses increases up to 30%. The economical loss reaches at 1.5% of the national GDP which is increasing. To maintain stability of power system up gradation is essential. Transmission system is operated & regulated as per the Regulations & standards given by Central Electricity Regulatory Commission (CERC), Central Electricity Authority (CEA), State Electricity Regulatory Commissions (SERC). At present Maintenance technology is one of the topics of R & D for various countries.
Testing and Condition Monitoring of Substation EquipmentsSumeet Ratnawat
Testing and condition monitoring of substation equipments,Transformer specifications,Monitoring of Transformer,On-load Tap changer,Overhauling,Tan delta and capacitance,Thermal imaging,Sweep frequency response analysis,Oil analysis of Switchgear elements containing oil,tests on insulating oil,Breaker monitoring,Condition monitoring of CT,Condition monitoring of CVT,Surge Arresters,Condition monitoring of relays.
Design of a generating substation with the description of designing a transformer. Here we show some basic components of a substation. and we also show the parameters and calculation to design a transformer of a specific ratings.
Complete details of EHV Transmission Line. Consolidated this presentation from those experts who had contributed separately on slider share and other web pages.Thanks for their valuable inputs.
The major challenge in Indian power sector is operating upgrading of the transmission & distribution lines with efficient meteringApplication of smart grid devices for consistently condition monitoring of overhead lines &substation can decides the action of maintenance required and thus condition-based maintenance (CBM) technique can be implemented. To meet ever increase in demand, reduction of value of losses, utilization of huge renewable energy and absence of automation in power Transmission & Distribution, there is need of Preventive Maintenance (PM) & logy(RCM).
The financial growth of India also depends on availability of electricity. Indian power sector having characteristics as shortage of generation and high T & D losses up to 30% of total electricity generation with some parts of states of country up to 40%. When losses due to theft are added in the total then average losses increases up to 30%. The economical loss reaches at 1.5% of the national GDP which is increasing. To maintain stability of power system up gradation is essential. Transmission system is operated & regulated as per the Regulations & standards given by Central Electricity Regulatory Commission (CERC), Central Electricity Authority (CEA), State Electricity Regulatory Commissions (SERC). At present Maintenance technology is one of the topics of R & D for various countries.
Testing and Condition Monitoring of Substation EquipmentsSumeet Ratnawat
Testing and condition monitoring of substation equipments,Transformer specifications,Monitoring of Transformer,On-load Tap changer,Overhauling,Tan delta and capacitance,Thermal imaging,Sweep frequency response analysis,Oil analysis of Switchgear elements containing oil,tests on insulating oil,Breaker monitoring,Condition monitoring of CT,Condition monitoring of CVT,Surge Arresters,Condition monitoring of relays.
Design of a generating substation with the description of designing a transformer. Here we show some basic components of a substation. and we also show the parameters and calculation to design a transformer of a specific ratings.
Here are the details on 300MW Wind Power Project located in the Western Region of India presented by Gensol on the various phases of construction & execution; starting from :
1)Wind resource assessment,
2)Site feasibility studies,
3)Statuary & legal approvals required,
4)Civil & electrical works,
5)Quality & material inspection,
6)Post erection & monitoring etc.
(Click here to read more..)
Quality defects in TMT Bars, Possible causes and Potential Solutions.PrashantGoswami42
Maintaining high-quality standards in the production of TMT bars is crucial for ensuring structural integrity in construction. Addressing common defects through careful monitoring, standardized processes, and advanced technology can significantly improve the quality of TMT bars. Continuous training and adherence to quality control measures will also play a pivotal role in minimizing these defects.
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)MdTanvirMahtab2
This presentation is about the working procedure of Shahjalal Fertilizer Company Limited (SFCL). A Govt. owned Company of Bangladesh Chemical Industries Corporation under Ministry of Industries.
Forklift Classes Overview by Intella PartsIntella Parts
Discover the different forklift classes and their specific applications. Learn how to choose the right forklift for your needs to ensure safety, efficiency, and compliance in your operations.
For more technical information, visit our website https://intellaparts.com
Overview of the fundamental roles in Hydropower generation and the components involved in wider Electrical Engineering.
This paper presents the design and construction of hydroelectric dams from the hydrologist’s survey of the valley before construction, all aspects and involved disciplines, fluid dynamics, structural engineering, generation and mains frequency regulation to the very transmission of power through the network in the United Kingdom.
Author: Robbie Edward Sayers
Collaborators and co editors: Charlie Sims and Connor Healey.
(C) 2024 Robbie E. Sayers
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdfKamal Acharya
The College Bus Management system is completely developed by Visual Basic .NET Version. The application is connect with most secured database language MS SQL Server. The application is develop by using best combination of front-end and back-end languages. The application is totally design like flat user interface. This flat user interface is more attractive user interface in 2017. The application is gives more important to the system functionality. The application is to manage the student’s details, driver’s details, bus details, bus route details, bus fees details and more. The application has only one unit for admin. The admin can manage the entire application. The admin can login into the application by using username and password of the admin. The application is develop for big and small colleges. It is more user friendly for non-computer person. Even they can easily learn how to manage the application within hours. The application is more secure by the admin. The system will give an effective output for the VB.Net and SQL Server given as input to the system. The compiled java program given as input to the system, after scanning the program will generate different reports. The application generates the report for users. The admin can view and download the report of the data. The application deliver the excel format reports. Because, excel formatted reports is very easy to understand the income and expense of the college bus. This application is mainly develop for windows operating system users. In 2017, 73% of people enterprises are using windows operating system. So the application will easily install for all the windows operating system users. The application-developed size is very low. The application consumes very low space in disk. Therefore, the user can allocate very minimum local disk space for this application.
Vaccine management system project report documentation..pdfKamal Acharya
The Division of Vaccine and Immunization is facing increasing difficulty monitoring vaccines and other commodities distribution once they have been distributed from the national stores. With the introduction of new vaccines, more challenges have been anticipated with this additions posing serious threat to the already over strained vaccine supply chain system in Kenya.
About
Indigenized remote control interface card suitable for MAFI system CCR equipment. Compatible for IDM8000 CCR. Backplane mounted serial and TCP/Ethernet communication module for CCR remote access. IDM 8000 CCR remote control on serial and TCP protocol.
• Remote control: Parallel or serial interface.
• Compatible with MAFI CCR system.
• Compatible with IDM8000 CCR.
• Compatible with Backplane mount serial communication.
• Compatible with commercial and Defence aviation CCR system.
• Remote control system for accessing CCR and allied system over serial or TCP.
• Indigenized local Support/presence in India.
• Easy in configuration using DIP switches.
Technical Specifications
Indigenized remote control interface card suitable for MAFI system CCR equipment. Compatible for IDM8000 CCR. Backplane mounted serial and TCP/Ethernet communication module for CCR remote access. IDM 8000 CCR remote control on serial and TCP protocol.
Key Features
Indigenized remote control interface card suitable for MAFI system CCR equipment. Compatible for IDM8000 CCR. Backplane mounted serial and TCP/Ethernet communication module for CCR remote access. IDM 8000 CCR remote control on serial and TCP protocol.
• Remote control: Parallel or serial interface
• Compatible with MAFI CCR system
• Copatiable with IDM8000 CCR
• Compatible with Backplane mount serial communication.
• Compatible with commercial and Defence aviation CCR system.
• Remote control system for accessing CCR and allied system over serial or TCP.
• Indigenized local Support/presence in India.
Application
• Remote control: Parallel or serial interface.
• Compatible with MAFI CCR system.
• Compatible with IDM8000 CCR.
• Compatible with Backplane mount serial communication.
• Compatible with commercial and Defence aviation CCR system.
• Remote control system for accessing CCR and allied system over serial or TCP.
• Indigenized local Support/presence in India.
• Easy in configuration using DIP switches.
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxR&R Consult
CFD analysis is incredibly effective at solving mysteries and improving the performance of complex systems!
Here's a great example: At a large natural gas-fired power plant, where they use waste heat to generate steam and energy, they were puzzled that their boiler wasn't producing as much steam as expected.
R&R and Tetra Engineering Group Inc. were asked to solve the issue with reduced steam production.
An inspection had shown that a significant amount of hot flue gas was bypassing the boiler tubes, where the heat was supposed to be transferred.
R&R Consult conducted a CFD analysis, which revealed that 6.3% of the flue gas was bypassing the boiler tubes without transferring heat. The analysis also showed that the flue gas was instead being directed along the sides of the boiler and between the modules that were supposed to capture the heat. This was the cause of the reduced performance.
Based on our results, Tetra Engineering installed covering plates to reduce the bypass flow. This improved the boiler's performance and increased electricity production.
It is always satisfying when we can help solve complex challenges like this. Do your systems also need a check-up or optimization? Give us a call!
Work done in cooperation with James Malloy and David Moelling from Tetra Engineering.
More examples of our work https://www.r-r-consult.dk/en/cases-en/
Saudi Arabia stands as a titan in the global energy landscape, renowned for its abundant oil and gas resources. It's the largest exporter of petroleum and holds some of the world's most significant reserves. Let's delve into the top 10 oil and gas projects shaping Saudi Arabia's energy future in 2024.
2. TYPE OF FOUNDATION
NORMAL DRY
To be used for location in normal day cohesive or non-cohesive soils
PARTIALLY SUB-MERGED
To be used at locations where sub soil water table is met between 0.75
meter below the ground line.
FULLY SUB-MERGED
To be used at locations where sub-soil water table is met at less than
0.75 meter below the ground line.
Wet
To used for locations:
1. Where sub-soil water is met at 1.5 m or more below the ground line.
2. Which are in surface water for long periods with water penetration not
exceeding one meter below the ground
3. In black cotton soil
OVERHEAD TRANSMISSION LINE CONSTRUCTION 2
3. CONSTRUCTION PROCESS
1. SURVEYING AND PIT MARKING
2. EXCAVATION
3. PCC (Plain Cement Concrete)
4. STUB SETTING
5. STEEL REINFORCEMENT
6. CONCRETING
7. CURING
8. DE-SHUTTERING & TEMPLATE REMOVAL
9. GROUNDING INSTALLATION
10. BACKFILLING and COMPACTING.
11. LEVELING or REMOVAL OF EXCESS SOIL
12. GABION WALLS
OVERHEAD TRANSMISSION LINE CONSTRUCTION 3
4. SURVEYING AND PIT MARKING
Insert of Bench Marks (BM) with GPS;
Peg marking of tower locations;
Peg marking for each leg of tower;
Marking the pit with tape or lime
Submission of surveying and documentation
Add a Footer 4
5. EXCAVATION
5
Excavation will be done in accordance with classification of soil.
If the excavation is expected to encounter water through
groundwater, leaking pipes, storm water, or other sources, a
dewatering system will be provided.
Excavation according surveying and work drawings;
Footing excavation;
Topographic control of dimensions and quotas;
Excavation protection or Placement of protective barriers;
Submission and documentation of excavation works
Leveling or removal of excavation soils
6. PCC (PLAIN CEMENT CONCRETE)
Leveling of surface of foundation after excavation;
Laying of Plain Cement Concrete;
Submission of surveying and documentation
Add a Footer 6
7. STUB SETTINGS
7
Erection of template or les according drawings;
Placement of concrete tiles for stubs supports
Stub fixation according dimensions ;
Topographic control of dimensions and quotas;
Tightening of tower body/legs or templates;
Submission and documentation of stub settings
8. STEEL REINFORCEMENT
Add a Footer 8
Preparation of steel reinforcement in warehouse;
Control of dimensions and quality;
Installation of steel reinforcement in foundation ;
Final checking according approved drawings;
Submission of documentation
9. CONCRETING
9
Control of documentation of stub settings and steel reinforcement ;
Erection of formwork;
Approval of concrete formula;
Preparation and placement of concrete;
Testing of Fresh Concrete and Compressive Strength;
Topographic control of dimensions and quotas in topo of stubs;
Submission and documentation of concrete process
10. CURING
The test specimens will be left in the mold for at least 16
hours, but no longer than 3days, protected against shock,
vibration, and dehydration at a temperature of (20 ± 5) ºC
(or (25 ± 5) ºC in hot climates.
After removal from the mold, the test specimens will be
cured immediately before testing, in water at a temperature
of (20 ± 2) ºC, or in a chamber at (20 ± 2) ºC and relative
humidity ≥ 95%.
TEMPLATE REMOVAL
Template Dismantling procedure will start only when the
engineer decides so and always before the removal of the
shuttering. This procedure must be seen as the inverse of the
erection method.
Add a Footer 10
11. GROUNDING INSTALLATION
• The cutting of grounding materials as the approved drawing
shows.
• Positioning and fixation of the grounding material on their
final position.
• Start of backfilling procedures.
• When the backfilling has finished the electrical resistance will
be measured and recorded.
BACKFILLING and COMPACTING
Backfill shall be placed in layers
The materials shall be compacted
periodically perform backfill soil density tests
All backfill of the tower foundation shall be protected
Add a Footer 11
13. GABION WALLS
Ease of handling and transportation
Speed of construction
Flexibility (Gabions tolerate movement)
Permeability to water (Good drainage)
Add a Footer 13