SlideShare a Scribd company logo
1 of 36
REHABILITATION & IMPROVEMENTS TO
COLOMBO – KANDY ROAD SECTION FROM
KADAWATHA TO NITTAMBUWA
8/12/2016 ACCESS ENGINEERING PLC
BOMBUWALA B.G.A.
EN 14 5011 80
Access Engineering Ltd.
• VISION
– To be the foremost Sri Lankan business enterprise in value
engineering
• MISSION
– To meet the challenges in the development of multi sector
civil engineering projects, providing innovative solutions
whilst developing long term progressive relationships with
all our stakeholders
8/12/2016 ACCESS ENGINEERING PLC
http://www.accessengsl.com
PROJECT DETAILS
Project: Rehabilitation and Improvement of A001 Colombo -
Kandy Road Section from Kadawatha – Nittambuwa.
Contractor: Access Engineering PLC
Consultancy: Road Development Authority
Project Value: Rs. 7.7 Billion
Project Duration: 18 months
Project Length: 23 km
Progress at the time of training: 25 months (7 km)
Current Progress: 34 months (9.5 km)
The rehabilitation includes improvements of road, pavements and
bridges.
8/12/2016 ACCESS ENGINEERING PLC
TRAINING SCHEDULE
TASK NAME DURATION (weeks)
Earthworks 3
Structures 3
 Drainages  1
 Culverts  2
Precast yard 0.5
Laboratory (QA/QC) 2
Finishes 0.5
Quantity Surveying 1.5
Bridge work & Piling 2
Total 12.5
8/12/2016 ACCESS ENGINEERING PLC
Earthworks
8/12/2016 ACCESS ENGINEERING PLC
Cross Section of Roadway
8/12/2016 ACCESS ENGINEERING PLC
7.4 m 7.4 m
MAIN FEATURES OF THE REVISED
PROPOSAL
8/12/2016 ACCESS ENGINEERING PLC
ITEM DESCRIPTION
Carriageway Four lane, 14.8m wide(2*7.4m)
Shoulders
Hard shoulder 0.6m(2*0.3m)
Soft shoulder 2.4m(2*1.2m)
Composition of Carriageway
Overlay sections
40mm thick Asphalt Wearing Course
Surfacing, 80mm(average) thick Asphalt
Binder Course(includes regulator for profile
correction)
Widening sections
40mm thick Asphalt wearing course and
80mm(average) thick Asphalt Binder Course
with a
325mm thick dense graded base course and a
350mm thick soil sub-base and capping layer
and sub grade as per requirement(Binder
thickness varies from section to section).
Detailed Cross Section of Roadway
8/12/2016 ACCESS ENGINEERING PLC
EARTH WORKS – ROCK FILLING &
EMBANKMENT FILLING
 An embankment consists of 4 parts which are:
• Rubble layer
• ABC layer
• Geo-textile membrane
• Soil layer
 First the area was prepared by removing existing soil and then Rubble layer was
laid up to 700mm height and then ABC was laid up to 100mm. After putting
membrane, the layers were compacted using 10-tonne compactor.
8/12/2016 ACCESS ENGINEERING PLC
EARTH WORKS – ROCK FILLING &
EMBANKMENT FILLING
 After compacting, soil layers were laid and compacted one by one up to
1250mm(250 *5 layers).
8/12/2016 ACCESS ENGINEERING PLC
EARTH WORKS – SUB-BASE AND
BASE
 Then sub-base bottom layer is filled up to about 200mm and sub-base top layer is
filled up to 150mm(total 350mm) heights.
8/12/2016 ACCESS ENGINEERING PLC
EARTH WORKS – SUB-BASE AND
BASE
• After that, Aggregate based course(ABC) first layer with 180mm thickness and
quarry dust were laid and compacted using Grader.
8/12/2016 ACCESS ENGINEERING PLC
Dense Graded Aggregate Base
Coarse(ABC)
• Provides uniform and stable foundation for the layers placed on top.
• Firmly bonded with the asphalt binder and wearing courses.
• Procedure for ABC top laying,
– First we had to install pegs in each chainage with additional 300mm space from new
EOP and from the end of the design offset of the new road.
– Design level + 45mm was marked in the pegs by using level machine.
– After that we had to provide 2 roller passes using roller.
– Again we have to check the levels in each chainage and we have to install pegs from the
offsets of EOP, 6m from the center and 8.3m from the center.
– Levels were given to the peg as design level + 14 mm and scratch ABC using grader.
– After that 2 roller passes was provided.
– Again we had to check the levels and we had to cut or fill ABC where necessary.
– At last we gave 4 roller passes and checked the levels.
8/12/2016 ACCESS ENGINEERING PLC
Dense Graded Aggregate Base
Coarse(ABC)
8/12/2016 ACCESS ENGINEERING PLC
Unloading
Spreading using
Motor Grader
Providing roller
passes
Doing correction to
necessary places
Giving Levels
EARTH WORKS - SHOULDER
• Constructing a soft shoulder.
• Soil was compacted above the sub base for the shoulder for a 1.2m width. The
total height of the layer was 325mm.
• At first, a 250mm layer was put and compacted by the 5-tonne compacter with 6
passes to a 200mm layer. Then a 150mm second layer was put and compacted to a
125mm layer. The cutting edge was 8.35m from center of the new road.
8/12/2016 ACCESS ENGINEERING PLC
Backfilling by
hand
Backfilling by
Bob-cat
Compacting
using 5-tonne
Structures
8/12/2016 ACCESS ENGINEERING PLC
MAIN FEATURES OF THE REVISED
PROPOSAL
8/12/2016 ACCESS ENGINEERING PLC
CULVERTS AND DRAINAGES -
DRAINAGES
 Constructing a line drainage in a highway and its importance.
 Site was cleaned and setting-out was carried by tape measurements to locate line
drainage path.
 Excavation levels were marked using Dumpy leveler.
 50mm screed concrete was poured and on top of it.
 Base and walls of type 1 drain was constructed using GR.25 concrete.
 Cured previous concrete.
 Light weight cover slabs were placed.
 Hume pipes were placed between drain and culvert.
8/12/2016 ACCESS ENGINEERING PLC
CULVERTS AND DRAINAGES -
DRAINAGES
Excavating
Formworking &
concreting
Cover slab
placing
8/12/2016 ACCESS ENGINEERING PLC
CULVERTS AND DRAINAGES -
CULVERTS
 Constructing a Box culvert in a highway and its importance.
 Existing road was cleaned and setting-out was carried by Total station & tape
measurements to locate Box culvert path.
 Excavation levels were marked using Dumpy leveler.
 Procedure:
• Excavating and demolishing of existing culvert if there is any.
• 75mm thick screed concrete (C15 (20)) pouring.
• Formworking, reinforcing and concreting base (Grade 30 (20) - Ready mixed).
• Formworking and reinforcing for wall plus lower hunch.
• Formworking for slab/deck plus upper hunch.
• Cleaning and De-watering.
• Concreting wall, slab/deck plus hunches. (Grade 30 (20) - Ready mixed).
8/12/2016 ACCESS ENGINEERING PLC
CULVERTS AND DRAINAGES -
CULVERTS
Excavating & demolishing Screed pouring
Formworking, reinforcing
& concreting of base
8/12/2016 ACCESS ENGINEERING PLC
CULVERTS AND DRAINAGES -
CULVERTS
Formworking &
reinforcing of walls + slab
Concreting of walls + slab Levels checking
8/12/2016 ACCESS ENGINEERING PLC
LABORATORY WORK
 Lab tests were done under following categories:
• Asphalt
Extraction test
Marshall test
Core cutting test
Asphalt stability and flow test
• Soil
Sand cone test
Procter compaction test
CBR test
DCP test
Atterburg Limit test
• ABC
AIV test
LAAV test
Sieve analysis test
8/12/2016 ACCESS ENGINEERING PLC
LABORATORY WORK
• Tests done to check the soil conditions and soil properties,
8/12/2016 ACCESS ENGINEERING PLC
TEST NAME APPARATUS TEST METHOD
Atterburg
Limit tests
Liquid Limit Liquid Limit apparatus AASTHO-T-89 , T-90
Plastic Limit - AASTHO-T-89 , T-90
Sieve analysis test
Sieves (mm)
Shoulder:
20, 5, 2.36, 0.600, 0.075,
pan.
Sub base:
20, 5, 1.18, 0.300, 0.075
pan.
BS 1377 - Part 2
Modified proctor compaction
test
Mold , Hammer , Oven
BS 1377 Test 13 / AASHTO T-
180
4-day soaked CBR at 95% MDD
(Modified)
Mold, Hammer, Gauge,
CBR test machine
AASHTO T-193
LABORATORY WORK
• Apparatuses
8/12/2016 ACCESS ENGINEERING PLC
COMPRESIVE TESTING
MACHINE
CBR TEST MACHINE
AUTOMATIVE MARSHALL
COMPACTOR
LABORATORY WORK
• Apparatuses
8/12/2016 ACCESS ENGINEERING PLC
CENTRIFUGAL ASPHALT
EXTRACTION APPARATUS
SPECIFIC GRAVITY FRAME
MOTORISED MARSHALL TEST
MACHINE
LABORATORY WORK
• Apparatuses
8/12/2016 ACCESS ENGINEERING PLC
LOS ANGELES MACHINE
LIQUID LIMIT TEST
APPARATUS
QUANTITY SURVEY WORK
 Conditions of Contract, Specifications, Bidding documents, Price fluctuations and
so on. As works I had done: taking quantities from drawings, calculating price
fluctuations, checking drawing levels on CS and LS drawings.
 Some of the documents I referred were:
8/12/2016 ACCESS ENGINEERING PLC
QUANTITY SURVEY WORK
 Codes of practices, standards and material references:
• Sri Lankan standards
• British standards
• AASHTO Publications (2002 Edition)
• ASTM Publications
• FIDIC Documents
• HMSO Publications
• ICTAD Publications
• TRL Publications
• DIN
8/12/2016 ACCESS ENGINEERING PLC
BRIDGES
 Constructing a pile using percussion boring method.
 Coffer dam was constructed. Jumbo bags, filled with soil were placed around the
embankment in order to stop collapsing. To reduce the block of the flow, we place
Hume pipes under the embankment at the beginning.
 Procedure:
• Locating bridge pile center using Total station.
• Excavating for temporary cover.
• Placing temporary cover and checking level and position at top.
• Setting pile Tripod.
• Placing rectangular case.
• Placing chisel/cutter.
• Combining a rod with the chisel and start boring till meeting bedrock.
• Do socketing for 1m.
• Flushing-out hole with Bentonite.
• Inserting Reinforcement mesh.
• Concreting pile.
8/12/2016 ACCESS ENGINEERING PLC
BRIDGES
Jumbo bags
filling with soil
Placing around
embankment
Setting out by
TS
8/12/2016 ACCESS ENGINEERING PLC
PILING
Placing tem. cover
& level checking
Setting out Tripod Soil boring
8/12/2016 ACCESS ENGINEERING PLC
PILING
Taking samples Flushing out
Putting
reinforcement mesh
& concreting
8/12/2016 ACCESS ENGINEERING PLC
Health and Safety
• Access Engineering PLC, operating in infrastructure
development field, shall provide and maintain high standard
of health & safety for all its employees and general public who
may be affected by the operation
• Creating awareness by training, sharing information &
supervision and maintaining preparedness to meet health &
safety emergencies to ensure a safe and healthy working
environment at all offices and sites.
8/12/2016 ACCESS ENGINEERING PLC
Environmental Policy
• Access Engineering PLC recognizes that in carrying out its activities it has a responsibility to
customers, employees and the general public to minimize environmental impacts. The
environmental policy of Access Engineering is to:
• Ensure compliance with all applicable legal and other requirements, which relate to its
environmental aspects.
• Promote environmental awareness and commitment to the policy amongst all employees
and Stake Holders through training, and communications to encourage suppliers and
subcontractors to apply sound environmental principles.
• Avoid the wastage of materials, water and energy by paying careful attention to their use.
• Prevent pollution and minimize environmental disturbance from our activities.
• Apply continual improvement by reviewing the environmental aspects related to our
activities by setting appropriate targets and objectives for improving performance.
8/12/2016 ACCESS ENGINEERING PLC
8/12/2016 ACCESS ENGINEERING PLC

More Related Content

What's hot

Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017Crosstown TO
 
Western Works Construction Liaison Committee Meeting - September 2017
Western Works Construction Liaison Committee Meeting - September 2017Western Works Construction Liaison Committee Meeting - September 2017
Western Works Construction Liaison Committee Meeting - September 2017Crosstown TO
 
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017Crosstown TO
 
Thrasher Commercial Group
Thrasher Commercial GroupThrasher Commercial Group
Thrasher Commercial GroupJill Reeves
 
Tw Rcc Dams Display
Tw Rcc Dams DisplayTw Rcc Dams Display
Tw Rcc Dams DisplayTed Warren
 
Mahakali Bridge Project Presentation (2077 chaitra 11)
Mahakali Bridge Project Presentation (2077 chaitra 11)Mahakali Bridge Project Presentation (2077 chaitra 11)
Mahakali Bridge Project Presentation (2077 chaitra 11)Rabindra Shrestha
 
Morocco Mall Post Tensioned Concrete Case Study
Morocco Mall Post Tensioned Concrete Case StudyMorocco Mall Post Tensioned Concrete Case Study
Morocco Mall Post Tensioned Concrete Case StudyCCL Concrete
 
Re development works at east kidwai nagar, New Delhi
Re development works at east kidwai nagar, New DelhiRe development works at east kidwai nagar, New Delhi
Re development works at east kidwai nagar, New DelhiJaspreet singh
 
Silo at narrow space
Silo at narrow spaceSilo at narrow space
Silo at narrow spacechandra manik
 
Low Density Cellular Concrete
Low Density Cellular ConcreteLow Density Cellular Concrete
Low Density Cellular ConcreteJill Reeves
 
Creation of low cost Housing
Creation of low cost HousingCreation of low cost Housing
Creation of low cost HousingNilanjana Pal
 
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017Crosstown TO
 
Project Execution Plan for High Rise Building
Project Execution Plan for High Rise BuildingProject Execution Plan for High Rise Building
Project Execution Plan for High Rise BuildingDavid H Moloney
 
Caledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 finalCaledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 finalCrosstown TO
 
Roller - Compacted Concrete (RCC)
Roller - Compacted Concrete (RCC)Roller - Compacted Concrete (RCC)
Roller - Compacted Concrete (RCC)SSudhaVelan
 
Community Information Meeting of parkette design plan at Fairbank Station
Community Information Meeting of parkette design plan at Fairbank StationCommunity Information Meeting of parkette design plan at Fairbank Station
Community Information Meeting of parkette design plan at Fairbank StationCrosstown TO
 
Leaside - Laird Construction Liaison Committee Meeting - June 2017
Leaside - Laird Construction Liaison Committee Meeting - June 2017Leaside - Laird Construction Liaison Committee Meeting - June 2017
Leaside - Laird Construction Liaison Committee Meeting - June 2017Crosstown TO
 
vilas nikam - concrete technilogy A power point presentation on rmc
vilas nikam - concrete technilogy A power point presentation on rmcvilas nikam - concrete technilogy A power point presentation on rmc
vilas nikam - concrete technilogy A power point presentation on rmcNIKAMVN
 
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017Crosstown TO
 
Sustainable road maintenance strategies
Sustainable road maintenance strategiesSustainable road maintenance strategies
Sustainable road maintenance strategiesDragos Andrei
 

What's hot (20)

Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
 
Western Works Construction Liaison Committee Meeting - September 2017
Western Works Construction Liaison Committee Meeting - September 2017Western Works Construction Liaison Committee Meeting - September 2017
Western Works Construction Liaison Committee Meeting - September 2017
 
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017
 
Thrasher Commercial Group
Thrasher Commercial GroupThrasher Commercial Group
Thrasher Commercial Group
 
Tw Rcc Dams Display
Tw Rcc Dams DisplayTw Rcc Dams Display
Tw Rcc Dams Display
 
Mahakali Bridge Project Presentation (2077 chaitra 11)
Mahakali Bridge Project Presentation (2077 chaitra 11)Mahakali Bridge Project Presentation (2077 chaitra 11)
Mahakali Bridge Project Presentation (2077 chaitra 11)
 
Morocco Mall Post Tensioned Concrete Case Study
Morocco Mall Post Tensioned Concrete Case StudyMorocco Mall Post Tensioned Concrete Case Study
Morocco Mall Post Tensioned Concrete Case Study
 
Re development works at east kidwai nagar, New Delhi
Re development works at east kidwai nagar, New DelhiRe development works at east kidwai nagar, New Delhi
Re development works at east kidwai nagar, New Delhi
 
Silo at narrow space
Silo at narrow spaceSilo at narrow space
Silo at narrow space
 
Low Density Cellular Concrete
Low Density Cellular ConcreteLow Density Cellular Concrete
Low Density Cellular Concrete
 
Creation of low cost Housing
Creation of low cost HousingCreation of low cost Housing
Creation of low cost Housing
 
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017
 
Project Execution Plan for High Rise Building
Project Execution Plan for High Rise BuildingProject Execution Plan for High Rise Building
Project Execution Plan for High Rise Building
 
Caledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 finalCaledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 final
 
Roller - Compacted Concrete (RCC)
Roller - Compacted Concrete (RCC)Roller - Compacted Concrete (RCC)
Roller - Compacted Concrete (RCC)
 
Community Information Meeting of parkette design plan at Fairbank Station
Community Information Meeting of parkette design plan at Fairbank StationCommunity Information Meeting of parkette design plan at Fairbank Station
Community Information Meeting of parkette design plan at Fairbank Station
 
Leaside - Laird Construction Liaison Committee Meeting - June 2017
Leaside - Laird Construction Liaison Committee Meeting - June 2017Leaside - Laird Construction Liaison Committee Meeting - June 2017
Leaside - Laird Construction Liaison Committee Meeting - June 2017
 
vilas nikam - concrete technilogy A power point presentation on rmc
vilas nikam - concrete technilogy A power point presentation on rmcvilas nikam - concrete technilogy A power point presentation on rmc
vilas nikam - concrete technilogy A power point presentation on rmc
 
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017
 
Sustainable road maintenance strategies
Sustainable road maintenance strategiesSustainable road maintenance strategies
Sustainable road maintenance strategies
 

Viewers also liked (9)

Roads & Pavements
Roads & PavementsRoads & Pavements
Roads & Pavements
 
Trenchless Installation of Drainage Culverts with Pipe Ramming Method
Trenchless Installation of Drainage Culverts with Pipe Ramming MethodTrenchless Installation of Drainage Culverts with Pipe Ramming Method
Trenchless Installation of Drainage Culverts with Pipe Ramming Method
 
Group 5 1
Group 5 1Group 5 1
Group 5 1
 
Road drainage
Road drainageRoad drainage
Road drainage
 
20100514 pipe arch presentation to iem may 2010
20100514 pipe arch presentation to iem   may 201020100514 pipe arch presentation to iem   may 2010
20100514 pipe arch presentation to iem may 2010
 
The construction method for surface drainage (housing)
The construction method for surface drainage (housing)The construction method for surface drainage (housing)
The construction method for surface drainage (housing)
 
Drainage
DrainageDrainage
Drainage
 
Drainage system
Drainage systemDrainage system
Drainage system
 
Drainage system
Drainage systemDrainage system
Drainage system
 

Similar to Access Engineering PLC - Training Presentation

UMAID IQBAL SEMINAR.pptx
UMAID IQBAL SEMINAR.pptxUMAID IQBAL SEMINAR.pptx
UMAID IQBAL SEMINAR.pptxPraveendubey82
 
Pt slab design philosophy with slides and pictures showing benefit
Pt slab design philosophy  with slides and pictures showing benefitPt slab design philosophy  with slides and pictures showing benefit
Pt slab design philosophy with slides and pictures showing benefitPerwez Ahmad
 
Developers Transflex Installation
Developers Transflex InstallationDevelopers Transflex Installation
Developers Transflex Installationguest470ea8
 
selfcompactingconcretescc-160316004923.pptx
selfcompactingconcretescc-160316004923.pptxselfcompactingconcretescc-160316004923.pptx
selfcompactingconcretescc-160316004923.pptxARUNKUMARC39
 
Precast Six lane flyover project
Precast Six lane flyover projectPrecast Six lane flyover project
Precast Six lane flyover projectKriShna Sharma
 
CIVIL CONSTRUCTION IN FATIMA FERTILIZER COMPANY LIMITED
CIVIL CONSTRUCTION INFATIMA FERTILIZER COMPANY LIMITEDCIVIL CONSTRUCTION INFATIMA FERTILIZER COMPANY LIMITED
CIVIL CONSTRUCTION IN FATIMA FERTILIZER COMPANY LIMITEDWater Birds (Ali)
 
INTERLOCKING CONCRETE BLOCKS PAVEMENTS
INTERLOCKING CONCRETE BLOCKS PAVEMENTSINTERLOCKING CONCRETE BLOCKS PAVEMENTS
INTERLOCKING CONCRETE BLOCKS PAVEMENTSDileep Gowda
 
autoclaved aerated concrete
autoclaved aerated concreteautoclaved aerated concrete
autoclaved aerated concreteSIVA Aruna
 
Self compacting concrete (scc)
Self compacting concrete (scc)Self compacting concrete (scc)
Self compacting concrete (scc)y Sahaja
 
A.ÖZGÜR MISIRLIOĞLU TANITIM
A.ÖZGÜR MISIRLIOĞLU TANITIMA.ÖZGÜR MISIRLIOĞLU TANITIM
A.ÖZGÜR MISIRLIOĞLU TANITIMAhmet Ozgur
 
Civil - Structural Works
Civil - Structural WorksCivil - Structural Works
Civil - Structural WorksBabu Arumugam
 
Evanston project briefing 4 22 13
Evanston project briefing 4 22 13Evanston project briefing 4 22 13
Evanston project briefing 4 22 13cityofevanston
 
Evanston project briefing 4 22 13
Evanston project briefing 4 22 13Evanston project briefing 4 22 13
Evanston project briefing 4 22 13cityofevanston
 
RoadstaB - Road Stabilization
RoadstaB - Road StabilizationRoadstaB - Road Stabilization
RoadstaB - Road StabilizationNikhil Sharma
 
self-compacting concrete
self-compacting concrete self-compacting concrete
self-compacting concrete Sreekutty S
 
Technical textiles in Central Public Works Department
Technical textiles in Central Public Works DepartmentTechnical textiles in Central Public Works Department
Technical textiles in Central Public Works DepartmentDr K M SONI
 

Similar to Access Engineering PLC - Training Presentation (20)

UMAID IQBAL SEMINAR.pptx
UMAID IQBAL SEMINAR.pptxUMAID IQBAL SEMINAR.pptx
UMAID IQBAL SEMINAR.pptx
 
Roadstab 2017
Roadstab 2017Roadstab 2017
Roadstab 2017
 
Pt slab design philosophy with slides and pictures showing benefit
Pt slab design philosophy  with slides and pictures showing benefitPt slab design philosophy  with slides and pictures showing benefit
Pt slab design philosophy with slides and pictures showing benefit
 
Developers Transflex Installation
Developers Transflex InstallationDevelopers Transflex Installation
Developers Transflex Installation
 
selfcompactingconcretescc-160316004923.pptx
selfcompactingconcretescc-160316004923.pptxselfcompactingconcretescc-160316004923.pptx
selfcompactingconcretescc-160316004923.pptx
 
Precast Six lane flyover project
Precast Six lane flyover projectPrecast Six lane flyover project
Precast Six lane flyover project
 
CIVIL CONSTRUCTION IN FATIMA FERTILIZER COMPANY LIMITED
CIVIL CONSTRUCTION INFATIMA FERTILIZER COMPANY LIMITEDCIVIL CONSTRUCTION INFATIMA FERTILIZER COMPANY LIMITED
CIVIL CONSTRUCTION IN FATIMA FERTILIZER COMPANY LIMITED
 
INTERLOCKING CONCRETE BLOCKS PAVEMENTS
INTERLOCKING CONCRETE BLOCKS PAVEMENTSINTERLOCKING CONCRETE BLOCKS PAVEMENTS
INTERLOCKING CONCRETE BLOCKS PAVEMENTS
 
autoclaved aerated concrete
autoclaved aerated concreteautoclaved aerated concrete
autoclaved aerated concrete
 
Presentation
PresentationPresentation
Presentation
 
SMHB
SMHBSMHB
SMHB
 
Self compacting concrete (scc)
Self compacting concrete (scc)Self compacting concrete (scc)
Self compacting concrete (scc)
 
PPT FINAL.pptx
PPT FINAL.pptxPPT FINAL.pptx
PPT FINAL.pptx
 
A.ÖZGÜR MISIRLIOĞLU TANITIM
A.ÖZGÜR MISIRLIOĞLU TANITIMA.ÖZGÜR MISIRLIOĞLU TANITIM
A.ÖZGÜR MISIRLIOĞLU TANITIM
 
Civil - Structural Works
Civil - Structural WorksCivil - Structural Works
Civil - Structural Works
 
Evanston project briefing 4 22 13
Evanston project briefing 4 22 13Evanston project briefing 4 22 13
Evanston project briefing 4 22 13
 
Evanston project briefing 4 22 13
Evanston project briefing 4 22 13Evanston project briefing 4 22 13
Evanston project briefing 4 22 13
 
RoadstaB - Road Stabilization
RoadstaB - Road StabilizationRoadstaB - Road Stabilization
RoadstaB - Road Stabilization
 
self-compacting concrete
self-compacting concrete self-compacting concrete
self-compacting concrete
 
Technical textiles in Central Public Works Department
Technical textiles in Central Public Works DepartmentTechnical textiles in Central Public Works Department
Technical textiles in Central Public Works Department
 

Access Engineering PLC - Training Presentation

  • 1. REHABILITATION & IMPROVEMENTS TO COLOMBO – KANDY ROAD SECTION FROM KADAWATHA TO NITTAMBUWA 8/12/2016 ACCESS ENGINEERING PLC BOMBUWALA B.G.A. EN 14 5011 80
  • 2. Access Engineering Ltd. • VISION – To be the foremost Sri Lankan business enterprise in value engineering • MISSION – To meet the challenges in the development of multi sector civil engineering projects, providing innovative solutions whilst developing long term progressive relationships with all our stakeholders 8/12/2016 ACCESS ENGINEERING PLC http://www.accessengsl.com
  • 3. PROJECT DETAILS Project: Rehabilitation and Improvement of A001 Colombo - Kandy Road Section from Kadawatha – Nittambuwa. Contractor: Access Engineering PLC Consultancy: Road Development Authority Project Value: Rs. 7.7 Billion Project Duration: 18 months Project Length: 23 km Progress at the time of training: 25 months (7 km) Current Progress: 34 months (9.5 km) The rehabilitation includes improvements of road, pavements and bridges. 8/12/2016 ACCESS ENGINEERING PLC
  • 4. TRAINING SCHEDULE TASK NAME DURATION (weeks) Earthworks 3 Structures 3  Drainages  1  Culverts  2 Precast yard 0.5 Laboratory (QA/QC) 2 Finishes 0.5 Quantity Surveying 1.5 Bridge work & Piling 2 Total 12.5 8/12/2016 ACCESS ENGINEERING PLC
  • 6. Cross Section of Roadway 8/12/2016 ACCESS ENGINEERING PLC 7.4 m 7.4 m
  • 7. MAIN FEATURES OF THE REVISED PROPOSAL 8/12/2016 ACCESS ENGINEERING PLC ITEM DESCRIPTION Carriageway Four lane, 14.8m wide(2*7.4m) Shoulders Hard shoulder 0.6m(2*0.3m) Soft shoulder 2.4m(2*1.2m) Composition of Carriageway Overlay sections 40mm thick Asphalt Wearing Course Surfacing, 80mm(average) thick Asphalt Binder Course(includes regulator for profile correction) Widening sections 40mm thick Asphalt wearing course and 80mm(average) thick Asphalt Binder Course with a 325mm thick dense graded base course and a 350mm thick soil sub-base and capping layer and sub grade as per requirement(Binder thickness varies from section to section).
  • 8. Detailed Cross Section of Roadway 8/12/2016 ACCESS ENGINEERING PLC
  • 9. EARTH WORKS – ROCK FILLING & EMBANKMENT FILLING  An embankment consists of 4 parts which are: • Rubble layer • ABC layer • Geo-textile membrane • Soil layer  First the area was prepared by removing existing soil and then Rubble layer was laid up to 700mm height and then ABC was laid up to 100mm. After putting membrane, the layers were compacted using 10-tonne compactor. 8/12/2016 ACCESS ENGINEERING PLC
  • 10. EARTH WORKS – ROCK FILLING & EMBANKMENT FILLING  After compacting, soil layers were laid and compacted one by one up to 1250mm(250 *5 layers). 8/12/2016 ACCESS ENGINEERING PLC
  • 11. EARTH WORKS – SUB-BASE AND BASE  Then sub-base bottom layer is filled up to about 200mm and sub-base top layer is filled up to 150mm(total 350mm) heights. 8/12/2016 ACCESS ENGINEERING PLC
  • 12. EARTH WORKS – SUB-BASE AND BASE • After that, Aggregate based course(ABC) first layer with 180mm thickness and quarry dust were laid and compacted using Grader. 8/12/2016 ACCESS ENGINEERING PLC
  • 13. Dense Graded Aggregate Base Coarse(ABC) • Provides uniform and stable foundation for the layers placed on top. • Firmly bonded with the asphalt binder and wearing courses. • Procedure for ABC top laying, – First we had to install pegs in each chainage with additional 300mm space from new EOP and from the end of the design offset of the new road. – Design level + 45mm was marked in the pegs by using level machine. – After that we had to provide 2 roller passes using roller. – Again we have to check the levels in each chainage and we have to install pegs from the offsets of EOP, 6m from the center and 8.3m from the center. – Levels were given to the peg as design level + 14 mm and scratch ABC using grader. – After that 2 roller passes was provided. – Again we had to check the levels and we had to cut or fill ABC where necessary. – At last we gave 4 roller passes and checked the levels. 8/12/2016 ACCESS ENGINEERING PLC
  • 14. Dense Graded Aggregate Base Coarse(ABC) 8/12/2016 ACCESS ENGINEERING PLC Unloading Spreading using Motor Grader Providing roller passes Doing correction to necessary places Giving Levels
  • 15. EARTH WORKS - SHOULDER • Constructing a soft shoulder. • Soil was compacted above the sub base for the shoulder for a 1.2m width. The total height of the layer was 325mm. • At first, a 250mm layer was put and compacted by the 5-tonne compacter with 6 passes to a 200mm layer. Then a 150mm second layer was put and compacted to a 125mm layer. The cutting edge was 8.35m from center of the new road. 8/12/2016 ACCESS ENGINEERING PLC Backfilling by hand Backfilling by Bob-cat Compacting using 5-tonne
  • 17. MAIN FEATURES OF THE REVISED PROPOSAL 8/12/2016 ACCESS ENGINEERING PLC
  • 18. CULVERTS AND DRAINAGES - DRAINAGES  Constructing a line drainage in a highway and its importance.  Site was cleaned and setting-out was carried by tape measurements to locate line drainage path.  Excavation levels were marked using Dumpy leveler.  50mm screed concrete was poured and on top of it.  Base and walls of type 1 drain was constructed using GR.25 concrete.  Cured previous concrete.  Light weight cover slabs were placed.  Hume pipes were placed between drain and culvert. 8/12/2016 ACCESS ENGINEERING PLC
  • 19. CULVERTS AND DRAINAGES - DRAINAGES Excavating Formworking & concreting Cover slab placing 8/12/2016 ACCESS ENGINEERING PLC
  • 20. CULVERTS AND DRAINAGES - CULVERTS  Constructing a Box culvert in a highway and its importance.  Existing road was cleaned and setting-out was carried by Total station & tape measurements to locate Box culvert path.  Excavation levels were marked using Dumpy leveler.  Procedure: • Excavating and demolishing of existing culvert if there is any. • 75mm thick screed concrete (C15 (20)) pouring. • Formworking, reinforcing and concreting base (Grade 30 (20) - Ready mixed). • Formworking and reinforcing for wall plus lower hunch. • Formworking for slab/deck plus upper hunch. • Cleaning and De-watering. • Concreting wall, slab/deck plus hunches. (Grade 30 (20) - Ready mixed). 8/12/2016 ACCESS ENGINEERING PLC
  • 21. CULVERTS AND DRAINAGES - CULVERTS Excavating & demolishing Screed pouring Formworking, reinforcing & concreting of base 8/12/2016 ACCESS ENGINEERING PLC
  • 22. CULVERTS AND DRAINAGES - CULVERTS Formworking & reinforcing of walls + slab Concreting of walls + slab Levels checking 8/12/2016 ACCESS ENGINEERING PLC
  • 23. LABORATORY WORK  Lab tests were done under following categories: • Asphalt Extraction test Marshall test Core cutting test Asphalt stability and flow test • Soil Sand cone test Procter compaction test CBR test DCP test Atterburg Limit test • ABC AIV test LAAV test Sieve analysis test 8/12/2016 ACCESS ENGINEERING PLC
  • 24. LABORATORY WORK • Tests done to check the soil conditions and soil properties, 8/12/2016 ACCESS ENGINEERING PLC TEST NAME APPARATUS TEST METHOD Atterburg Limit tests Liquid Limit Liquid Limit apparatus AASTHO-T-89 , T-90 Plastic Limit - AASTHO-T-89 , T-90 Sieve analysis test Sieves (mm) Shoulder: 20, 5, 2.36, 0.600, 0.075, pan. Sub base: 20, 5, 1.18, 0.300, 0.075 pan. BS 1377 - Part 2 Modified proctor compaction test Mold , Hammer , Oven BS 1377 Test 13 / AASHTO T- 180 4-day soaked CBR at 95% MDD (Modified) Mold, Hammer, Gauge, CBR test machine AASHTO T-193
  • 25. LABORATORY WORK • Apparatuses 8/12/2016 ACCESS ENGINEERING PLC COMPRESIVE TESTING MACHINE CBR TEST MACHINE AUTOMATIVE MARSHALL COMPACTOR
  • 26. LABORATORY WORK • Apparatuses 8/12/2016 ACCESS ENGINEERING PLC CENTRIFUGAL ASPHALT EXTRACTION APPARATUS SPECIFIC GRAVITY FRAME MOTORISED MARSHALL TEST MACHINE
  • 27. LABORATORY WORK • Apparatuses 8/12/2016 ACCESS ENGINEERING PLC LOS ANGELES MACHINE LIQUID LIMIT TEST APPARATUS
  • 28. QUANTITY SURVEY WORK  Conditions of Contract, Specifications, Bidding documents, Price fluctuations and so on. As works I had done: taking quantities from drawings, calculating price fluctuations, checking drawing levels on CS and LS drawings.  Some of the documents I referred were: 8/12/2016 ACCESS ENGINEERING PLC
  • 29. QUANTITY SURVEY WORK  Codes of practices, standards and material references: • Sri Lankan standards • British standards • AASHTO Publications (2002 Edition) • ASTM Publications • FIDIC Documents • HMSO Publications • ICTAD Publications • TRL Publications • DIN 8/12/2016 ACCESS ENGINEERING PLC
  • 30. BRIDGES  Constructing a pile using percussion boring method.  Coffer dam was constructed. Jumbo bags, filled with soil were placed around the embankment in order to stop collapsing. To reduce the block of the flow, we place Hume pipes under the embankment at the beginning.  Procedure: • Locating bridge pile center using Total station. • Excavating for temporary cover. • Placing temporary cover and checking level and position at top. • Setting pile Tripod. • Placing rectangular case. • Placing chisel/cutter. • Combining a rod with the chisel and start boring till meeting bedrock. • Do socketing for 1m. • Flushing-out hole with Bentonite. • Inserting Reinforcement mesh. • Concreting pile. 8/12/2016 ACCESS ENGINEERING PLC
  • 31. BRIDGES Jumbo bags filling with soil Placing around embankment Setting out by TS 8/12/2016 ACCESS ENGINEERING PLC
  • 32. PILING Placing tem. cover & level checking Setting out Tripod Soil boring 8/12/2016 ACCESS ENGINEERING PLC
  • 33. PILING Taking samples Flushing out Putting reinforcement mesh & concreting 8/12/2016 ACCESS ENGINEERING PLC
  • 34. Health and Safety • Access Engineering PLC, operating in infrastructure development field, shall provide and maintain high standard of health & safety for all its employees and general public who may be affected by the operation • Creating awareness by training, sharing information & supervision and maintaining preparedness to meet health & safety emergencies to ensure a safe and healthy working environment at all offices and sites. 8/12/2016 ACCESS ENGINEERING PLC
  • 35. Environmental Policy • Access Engineering PLC recognizes that in carrying out its activities it has a responsibility to customers, employees and the general public to minimize environmental impacts. The environmental policy of Access Engineering is to: • Ensure compliance with all applicable legal and other requirements, which relate to its environmental aspects. • Promote environmental awareness and commitment to the policy amongst all employees and Stake Holders through training, and communications to encourage suppliers and subcontractors to apply sound environmental principles. • Avoid the wastage of materials, water and energy by paying careful attention to their use. • Prevent pollution and minimize environmental disturbance from our activities. • Apply continual improvement by reviewing the environmental aspects related to our activities by setting appropriate targets and objectives for improving performance. 8/12/2016 ACCESS ENGINEERING PLC