REHABILITATION & IMPROVEMENTS TO
COLOMBO – KANDY ROAD SECTION FROM
KADAWATHA TO NITTAMBUWA
8/12/2016 ACCESS ENGINEERING PLC
BOMBUWALA B.G.A.
EN 14 5011 80
Access Engineering Ltd.
• VISION
– To be the foremost Sri Lankan business enterprise in value
engineering
• MISSION
– To meet the challenges in the development of multi sector
civil engineering projects, providing innovative solutions
whilst developing long term progressive relationships with
all our stakeholders
8/12/2016 ACCESS ENGINEERING PLC
http://www.accessengsl.com
PROJECT DETAILS
Project: Rehabilitation and Improvement of A001 Colombo -
Kandy Road Section from Kadawatha – Nittambuwa.
Contractor: Access Engineering PLC
Consultancy: Road Development Authority
Project Value: Rs. 7.7 Billion
Project Duration: 18 months
Project Length: 23 km
Progress at the time of training: 25 months (7 km)
Current Progress: 34 months (9.5 km)
The rehabilitation includes improvements of road, pavements and
bridges.
8/12/2016 ACCESS ENGINEERING PLC
TRAINING SCHEDULE
TASK NAME DURATION (weeks)
Earthworks 3
Structures 3
 Drainages  1
 Culverts  2
Precast yard 0.5
Laboratory (QA/QC) 2
Finishes 0.5
Quantity Surveying 1.5
Bridge work & Piling 2
Total 12.5
8/12/2016 ACCESS ENGINEERING PLC
Earthworks
8/12/2016 ACCESS ENGINEERING PLC
Cross Section of Roadway
8/12/2016 ACCESS ENGINEERING PLC
7.4 m 7.4 m
MAIN FEATURES OF THE REVISED
PROPOSAL
8/12/2016 ACCESS ENGINEERING PLC
ITEM DESCRIPTION
Carriageway Four lane, 14.8m wide(2*7.4m)
Shoulders
Hard shoulder 0.6m(2*0.3m)
Soft shoulder 2.4m(2*1.2m)
Composition of Carriageway
Overlay sections
40mm thick Asphalt Wearing Course
Surfacing, 80mm(average) thick Asphalt
Binder Course(includes regulator for profile
correction)
Widening sections
40mm thick Asphalt wearing course and
80mm(average) thick Asphalt Binder Course
with a
325mm thick dense graded base course and a
350mm thick soil sub-base and capping layer
and sub grade as per requirement(Binder
thickness varies from section to section).
Detailed Cross Section of Roadway
8/12/2016 ACCESS ENGINEERING PLC
EARTH WORKS – ROCK FILLING &
EMBANKMENT FILLING
 An embankment consists of 4 parts which are:
• Rubble layer
• ABC layer
• Geo-textile membrane
• Soil layer
 First the area was prepared by removing existing soil and then Rubble layer was
laid up to 700mm height and then ABC was laid up to 100mm. After putting
membrane, the layers were compacted using 10-tonne compactor.
8/12/2016 ACCESS ENGINEERING PLC
EARTH WORKS – ROCK FILLING &
EMBANKMENT FILLING
 After compacting, soil layers were laid and compacted one by one up to
1250mm(250 *5 layers).
8/12/2016 ACCESS ENGINEERING PLC
EARTH WORKS – SUB-BASE AND
BASE
 Then sub-base bottom layer is filled up to about 200mm and sub-base top layer is
filled up to 150mm(total 350mm) heights.
8/12/2016 ACCESS ENGINEERING PLC
EARTH WORKS – SUB-BASE AND
BASE
• After that, Aggregate based course(ABC) first layer with 180mm thickness and
quarry dust were laid and compacted using Grader.
8/12/2016 ACCESS ENGINEERING PLC
Dense Graded Aggregate Base
Coarse(ABC)
• Provides uniform and stable foundation for the layers placed on top.
• Firmly bonded with the asphalt binder and wearing courses.
• Procedure for ABC top laying,
– First we had to install pegs in each chainage with additional 300mm space from new
EOP and from the end of the design offset of the new road.
– Design level + 45mm was marked in the pegs by using level machine.
– After that we had to provide 2 roller passes using roller.
– Again we have to check the levels in each chainage and we have to install pegs from the
offsets of EOP, 6m from the center and 8.3m from the center.
– Levels were given to the peg as design level + 14 mm and scratch ABC using grader.
– After that 2 roller passes was provided.
– Again we had to check the levels and we had to cut or fill ABC where necessary.
– At last we gave 4 roller passes and checked the levels.
8/12/2016 ACCESS ENGINEERING PLC
Dense Graded Aggregate Base
Coarse(ABC)
8/12/2016 ACCESS ENGINEERING PLC
Unloading
Spreading using
Motor Grader
Providing roller
passes
Doing correction to
necessary places
Giving Levels
EARTH WORKS - SHOULDER
• Constructing a soft shoulder.
• Soil was compacted above the sub base for the shoulder for a 1.2m width. The
total height of the layer was 325mm.
• At first, a 250mm layer was put and compacted by the 5-tonne compacter with 6
passes to a 200mm layer. Then a 150mm second layer was put and compacted to a
125mm layer. The cutting edge was 8.35m from center of the new road.
8/12/2016 ACCESS ENGINEERING PLC
Backfilling by
hand
Backfilling by
Bob-cat
Compacting
using 5-tonne
Structures
8/12/2016 ACCESS ENGINEERING PLC
MAIN FEATURES OF THE REVISED
PROPOSAL
8/12/2016 ACCESS ENGINEERING PLC
CULVERTS AND DRAINAGES -
DRAINAGES
 Constructing a line drainage in a highway and its importance.
 Site was cleaned and setting-out was carried by tape measurements to locate line
drainage path.
 Excavation levels were marked using Dumpy leveler.
 50mm screed concrete was poured and on top of it.
 Base and walls of type 1 drain was constructed using GR.25 concrete.
 Cured previous concrete.
 Light weight cover slabs were placed.
 Hume pipes were placed between drain and culvert.
8/12/2016 ACCESS ENGINEERING PLC
CULVERTS AND DRAINAGES -
DRAINAGES
Excavating
Formworking &
concreting
Cover slab
placing
8/12/2016 ACCESS ENGINEERING PLC
CULVERTS AND DRAINAGES -
CULVERTS
 Constructing a Box culvert in a highway and its importance.
 Existing road was cleaned and setting-out was carried by Total station & tape
measurements to locate Box culvert path.
 Excavation levels were marked using Dumpy leveler.
 Procedure:
• Excavating and demolishing of existing culvert if there is any.
• 75mm thick screed concrete (C15 (20)) pouring.
• Formworking, reinforcing and concreting base (Grade 30 (20) - Ready mixed).
• Formworking and reinforcing for wall plus lower hunch.
• Formworking for slab/deck plus upper hunch.
• Cleaning and De-watering.
• Concreting wall, slab/deck plus hunches. (Grade 30 (20) - Ready mixed).
8/12/2016 ACCESS ENGINEERING PLC
CULVERTS AND DRAINAGES -
CULVERTS
Excavating & demolishing Screed pouring
Formworking, reinforcing
& concreting of base
8/12/2016 ACCESS ENGINEERING PLC
CULVERTS AND DRAINAGES -
CULVERTS
Formworking &
reinforcing of walls + slab
Concreting of walls + slab Levels checking
8/12/2016 ACCESS ENGINEERING PLC
LABORATORY WORK
 Lab tests were done under following categories:
• Asphalt
Extraction test
Marshall test
Core cutting test
Asphalt stability and flow test
• Soil
Sand cone test
Procter compaction test
CBR test
DCP test
Atterburg Limit test
• ABC
AIV test
LAAV test
Sieve analysis test
8/12/2016 ACCESS ENGINEERING PLC
LABORATORY WORK
• Tests done to check the soil conditions and soil properties,
8/12/2016 ACCESS ENGINEERING PLC
TEST NAME APPARATUS TEST METHOD
Atterburg
Limit tests
Liquid Limit Liquid Limit apparatus AASTHO-T-89 , T-90
Plastic Limit - AASTHO-T-89 , T-90
Sieve analysis test
Sieves (mm)
Shoulder:
20, 5, 2.36, 0.600, 0.075,
pan.
Sub base:
20, 5, 1.18, 0.300, 0.075
pan.
BS 1377 - Part 2
Modified proctor compaction
test
Mold , Hammer , Oven
BS 1377 Test 13 / AASHTO T-
180
4-day soaked CBR at 95% MDD
(Modified)
Mold, Hammer, Gauge,
CBR test machine
AASHTO T-193
LABORATORY WORK
• Apparatuses
8/12/2016 ACCESS ENGINEERING PLC
COMPRESIVE TESTING
MACHINE
CBR TEST MACHINE
AUTOMATIVE MARSHALL
COMPACTOR
LABORATORY WORK
• Apparatuses
8/12/2016 ACCESS ENGINEERING PLC
CENTRIFUGAL ASPHALT
EXTRACTION APPARATUS
SPECIFIC GRAVITY FRAME
MOTORISED MARSHALL TEST
MACHINE
LABORATORY WORK
• Apparatuses
8/12/2016 ACCESS ENGINEERING PLC
LOS ANGELES MACHINE
LIQUID LIMIT TEST
APPARATUS
QUANTITY SURVEY WORK
 Conditions of Contract, Specifications, Bidding documents, Price fluctuations and
so on. As works I had done: taking quantities from drawings, calculating price
fluctuations, checking drawing levels on CS and LS drawings.
 Some of the documents I referred were:
8/12/2016 ACCESS ENGINEERING PLC
QUANTITY SURVEY WORK
 Codes of practices, standards and material references:
• Sri Lankan standards
• British standards
• AASHTO Publications (2002 Edition)
• ASTM Publications
• FIDIC Documents
• HMSO Publications
• ICTAD Publications
• TRL Publications
• DIN
8/12/2016 ACCESS ENGINEERING PLC
BRIDGES
 Constructing a pile using percussion boring method.
 Coffer dam was constructed. Jumbo bags, filled with soil were placed around the
embankment in order to stop collapsing. To reduce the block of the flow, we place
Hume pipes under the embankment at the beginning.
 Procedure:
• Locating bridge pile center using Total station.
• Excavating for temporary cover.
• Placing temporary cover and checking level and position at top.
• Setting pile Tripod.
• Placing rectangular case.
• Placing chisel/cutter.
• Combining a rod with the chisel and start boring till meeting bedrock.
• Do socketing for 1m.
• Flushing-out hole with Bentonite.
• Inserting Reinforcement mesh.
• Concreting pile.
8/12/2016 ACCESS ENGINEERING PLC
BRIDGES
Jumbo bags
filling with soil
Placing around
embankment
Setting out by
TS
8/12/2016 ACCESS ENGINEERING PLC
PILING
Placing tem. cover
& level checking
Setting out Tripod Soil boring
8/12/2016 ACCESS ENGINEERING PLC
PILING
Taking samples Flushing out
Putting
reinforcement mesh
& concreting
8/12/2016 ACCESS ENGINEERING PLC
Health and Safety
• Access Engineering PLC, operating in infrastructure
development field, shall provide and maintain high standard
of health & safety for all its employees and general public who
may be affected by the operation
• Creating awareness by training, sharing information &
supervision and maintaining preparedness to meet health &
safety emergencies to ensure a safe and healthy working
environment at all offices and sites.
8/12/2016 ACCESS ENGINEERING PLC
Environmental Policy
• Access Engineering PLC recognizes that in carrying out its activities it has a responsibility to
customers, employees and the general public to minimize environmental impacts. The
environmental policy of Access Engineering is to:
• Ensure compliance with all applicable legal and other requirements, which relate to its
environmental aspects.
• Promote environmental awareness and commitment to the policy amongst all employees
and Stake Holders through training, and communications to encourage suppliers and
subcontractors to apply sound environmental principles.
• Avoid the wastage of materials, water and energy by paying careful attention to their use.
• Prevent pollution and minimize environmental disturbance from our activities.
• Apply continual improvement by reviewing the environmental aspects related to our
activities by setting appropriate targets and objectives for improving performance.
8/12/2016 ACCESS ENGINEERING PLC
8/12/2016 ACCESS ENGINEERING PLC

Access Engineering PLC - Training Presentation

  • 1.
    REHABILITATION & IMPROVEMENTSTO COLOMBO – KANDY ROAD SECTION FROM KADAWATHA TO NITTAMBUWA 8/12/2016 ACCESS ENGINEERING PLC BOMBUWALA B.G.A. EN 14 5011 80
  • 2.
    Access Engineering Ltd. •VISION – To be the foremost Sri Lankan business enterprise in value engineering • MISSION – To meet the challenges in the development of multi sector civil engineering projects, providing innovative solutions whilst developing long term progressive relationships with all our stakeholders 8/12/2016 ACCESS ENGINEERING PLC http://www.accessengsl.com
  • 3.
    PROJECT DETAILS Project: Rehabilitationand Improvement of A001 Colombo - Kandy Road Section from Kadawatha – Nittambuwa. Contractor: Access Engineering PLC Consultancy: Road Development Authority Project Value: Rs. 7.7 Billion Project Duration: 18 months Project Length: 23 km Progress at the time of training: 25 months (7 km) Current Progress: 34 months (9.5 km) The rehabilitation includes improvements of road, pavements and bridges. 8/12/2016 ACCESS ENGINEERING PLC
  • 4.
    TRAINING SCHEDULE TASK NAMEDURATION (weeks) Earthworks 3 Structures 3  Drainages  1  Culverts  2 Precast yard 0.5 Laboratory (QA/QC) 2 Finishes 0.5 Quantity Surveying 1.5 Bridge work & Piling 2 Total 12.5 8/12/2016 ACCESS ENGINEERING PLC
  • 5.
  • 6.
    Cross Section ofRoadway 8/12/2016 ACCESS ENGINEERING PLC 7.4 m 7.4 m
  • 7.
    MAIN FEATURES OFTHE REVISED PROPOSAL 8/12/2016 ACCESS ENGINEERING PLC ITEM DESCRIPTION Carriageway Four lane, 14.8m wide(2*7.4m) Shoulders Hard shoulder 0.6m(2*0.3m) Soft shoulder 2.4m(2*1.2m) Composition of Carriageway Overlay sections 40mm thick Asphalt Wearing Course Surfacing, 80mm(average) thick Asphalt Binder Course(includes regulator for profile correction) Widening sections 40mm thick Asphalt wearing course and 80mm(average) thick Asphalt Binder Course with a 325mm thick dense graded base course and a 350mm thick soil sub-base and capping layer and sub grade as per requirement(Binder thickness varies from section to section).
  • 8.
    Detailed Cross Sectionof Roadway 8/12/2016 ACCESS ENGINEERING PLC
  • 9.
    EARTH WORKS –ROCK FILLING & EMBANKMENT FILLING  An embankment consists of 4 parts which are: • Rubble layer • ABC layer • Geo-textile membrane • Soil layer  First the area was prepared by removing existing soil and then Rubble layer was laid up to 700mm height and then ABC was laid up to 100mm. After putting membrane, the layers were compacted using 10-tonne compactor. 8/12/2016 ACCESS ENGINEERING PLC
  • 10.
    EARTH WORKS –ROCK FILLING & EMBANKMENT FILLING  After compacting, soil layers were laid and compacted one by one up to 1250mm(250 *5 layers). 8/12/2016 ACCESS ENGINEERING PLC
  • 11.
    EARTH WORKS –SUB-BASE AND BASE  Then sub-base bottom layer is filled up to about 200mm and sub-base top layer is filled up to 150mm(total 350mm) heights. 8/12/2016 ACCESS ENGINEERING PLC
  • 12.
    EARTH WORKS –SUB-BASE AND BASE • After that, Aggregate based course(ABC) first layer with 180mm thickness and quarry dust were laid and compacted using Grader. 8/12/2016 ACCESS ENGINEERING PLC
  • 13.
    Dense Graded AggregateBase Coarse(ABC) • Provides uniform and stable foundation for the layers placed on top. • Firmly bonded with the asphalt binder and wearing courses. • Procedure for ABC top laying, – First we had to install pegs in each chainage with additional 300mm space from new EOP and from the end of the design offset of the new road. – Design level + 45mm was marked in the pegs by using level machine. – After that we had to provide 2 roller passes using roller. – Again we have to check the levels in each chainage and we have to install pegs from the offsets of EOP, 6m from the center and 8.3m from the center. – Levels were given to the peg as design level + 14 mm and scratch ABC using grader. – After that 2 roller passes was provided. – Again we had to check the levels and we had to cut or fill ABC where necessary. – At last we gave 4 roller passes and checked the levels. 8/12/2016 ACCESS ENGINEERING PLC
  • 14.
    Dense Graded AggregateBase Coarse(ABC) 8/12/2016 ACCESS ENGINEERING PLC Unloading Spreading using Motor Grader Providing roller passes Doing correction to necessary places Giving Levels
  • 15.
    EARTH WORKS -SHOULDER • Constructing a soft shoulder. • Soil was compacted above the sub base for the shoulder for a 1.2m width. The total height of the layer was 325mm. • At first, a 250mm layer was put and compacted by the 5-tonne compacter with 6 passes to a 200mm layer. Then a 150mm second layer was put and compacted to a 125mm layer. The cutting edge was 8.35m from center of the new road. 8/12/2016 ACCESS ENGINEERING PLC Backfilling by hand Backfilling by Bob-cat Compacting using 5-tonne
  • 16.
  • 17.
    MAIN FEATURES OFTHE REVISED PROPOSAL 8/12/2016 ACCESS ENGINEERING PLC
  • 18.
    CULVERTS AND DRAINAGES- DRAINAGES  Constructing a line drainage in a highway and its importance.  Site was cleaned and setting-out was carried by tape measurements to locate line drainage path.  Excavation levels were marked using Dumpy leveler.  50mm screed concrete was poured and on top of it.  Base and walls of type 1 drain was constructed using GR.25 concrete.  Cured previous concrete.  Light weight cover slabs were placed.  Hume pipes were placed between drain and culvert. 8/12/2016 ACCESS ENGINEERING PLC
  • 19.
    CULVERTS AND DRAINAGES- DRAINAGES Excavating Formworking & concreting Cover slab placing 8/12/2016 ACCESS ENGINEERING PLC
  • 20.
    CULVERTS AND DRAINAGES- CULVERTS  Constructing a Box culvert in a highway and its importance.  Existing road was cleaned and setting-out was carried by Total station & tape measurements to locate Box culvert path.  Excavation levels were marked using Dumpy leveler.  Procedure: • Excavating and demolishing of existing culvert if there is any. • 75mm thick screed concrete (C15 (20)) pouring. • Formworking, reinforcing and concreting base (Grade 30 (20) - Ready mixed). • Formworking and reinforcing for wall plus lower hunch. • Formworking for slab/deck plus upper hunch. • Cleaning and De-watering. • Concreting wall, slab/deck plus hunches. (Grade 30 (20) - Ready mixed). 8/12/2016 ACCESS ENGINEERING PLC
  • 21.
    CULVERTS AND DRAINAGES- CULVERTS Excavating & demolishing Screed pouring Formworking, reinforcing & concreting of base 8/12/2016 ACCESS ENGINEERING PLC
  • 22.
    CULVERTS AND DRAINAGES- CULVERTS Formworking & reinforcing of walls + slab Concreting of walls + slab Levels checking 8/12/2016 ACCESS ENGINEERING PLC
  • 23.
    LABORATORY WORK  Labtests were done under following categories: • Asphalt Extraction test Marshall test Core cutting test Asphalt stability and flow test • Soil Sand cone test Procter compaction test CBR test DCP test Atterburg Limit test • ABC AIV test LAAV test Sieve analysis test 8/12/2016 ACCESS ENGINEERING PLC
  • 24.
    LABORATORY WORK • Testsdone to check the soil conditions and soil properties, 8/12/2016 ACCESS ENGINEERING PLC TEST NAME APPARATUS TEST METHOD Atterburg Limit tests Liquid Limit Liquid Limit apparatus AASTHO-T-89 , T-90 Plastic Limit - AASTHO-T-89 , T-90 Sieve analysis test Sieves (mm) Shoulder: 20, 5, 2.36, 0.600, 0.075, pan. Sub base: 20, 5, 1.18, 0.300, 0.075 pan. BS 1377 - Part 2 Modified proctor compaction test Mold , Hammer , Oven BS 1377 Test 13 / AASHTO T- 180 4-day soaked CBR at 95% MDD (Modified) Mold, Hammer, Gauge, CBR test machine AASHTO T-193
  • 25.
    LABORATORY WORK • Apparatuses 8/12/2016ACCESS ENGINEERING PLC COMPRESIVE TESTING MACHINE CBR TEST MACHINE AUTOMATIVE MARSHALL COMPACTOR
  • 26.
    LABORATORY WORK • Apparatuses 8/12/2016ACCESS ENGINEERING PLC CENTRIFUGAL ASPHALT EXTRACTION APPARATUS SPECIFIC GRAVITY FRAME MOTORISED MARSHALL TEST MACHINE
  • 27.
    LABORATORY WORK • Apparatuses 8/12/2016ACCESS ENGINEERING PLC LOS ANGELES MACHINE LIQUID LIMIT TEST APPARATUS
  • 28.
    QUANTITY SURVEY WORK Conditions of Contract, Specifications, Bidding documents, Price fluctuations and so on. As works I had done: taking quantities from drawings, calculating price fluctuations, checking drawing levels on CS and LS drawings.  Some of the documents I referred were: 8/12/2016 ACCESS ENGINEERING PLC
  • 29.
    QUANTITY SURVEY WORK Codes of practices, standards and material references: • Sri Lankan standards • British standards • AASHTO Publications (2002 Edition) • ASTM Publications • FIDIC Documents • HMSO Publications • ICTAD Publications • TRL Publications • DIN 8/12/2016 ACCESS ENGINEERING PLC
  • 30.
    BRIDGES  Constructing apile using percussion boring method.  Coffer dam was constructed. Jumbo bags, filled with soil were placed around the embankment in order to stop collapsing. To reduce the block of the flow, we place Hume pipes under the embankment at the beginning.  Procedure: • Locating bridge pile center using Total station. • Excavating for temporary cover. • Placing temporary cover and checking level and position at top. • Setting pile Tripod. • Placing rectangular case. • Placing chisel/cutter. • Combining a rod with the chisel and start boring till meeting bedrock. • Do socketing for 1m. • Flushing-out hole with Bentonite. • Inserting Reinforcement mesh. • Concreting pile. 8/12/2016 ACCESS ENGINEERING PLC
  • 31.
    BRIDGES Jumbo bags filling withsoil Placing around embankment Setting out by TS 8/12/2016 ACCESS ENGINEERING PLC
  • 32.
    PILING Placing tem. cover &level checking Setting out Tripod Soil boring 8/12/2016 ACCESS ENGINEERING PLC
  • 33.
    PILING Taking samples Flushingout Putting reinforcement mesh & concreting 8/12/2016 ACCESS ENGINEERING PLC
  • 34.
    Health and Safety •Access Engineering PLC, operating in infrastructure development field, shall provide and maintain high standard of health & safety for all its employees and general public who may be affected by the operation • Creating awareness by training, sharing information & supervision and maintaining preparedness to meet health & safety emergencies to ensure a safe and healthy working environment at all offices and sites. 8/12/2016 ACCESS ENGINEERING PLC
  • 35.
    Environmental Policy • AccessEngineering PLC recognizes that in carrying out its activities it has a responsibility to customers, employees and the general public to minimize environmental impacts. The environmental policy of Access Engineering is to: • Ensure compliance with all applicable legal and other requirements, which relate to its environmental aspects. • Promote environmental awareness and commitment to the policy amongst all employees and Stake Holders through training, and communications to encourage suppliers and subcontractors to apply sound environmental principles. • Avoid the wastage of materials, water and energy by paying careful attention to their use. • Prevent pollution and minimize environmental disturbance from our activities. • Apply continual improvement by reviewing the environmental aspects related to our activities by setting appropriate targets and objectives for improving performance. 8/12/2016 ACCESS ENGINEERING PLC
  • 36.