OPEN PIT MINING 
KHALEEQ AHMED 
1 1PWMIN0644 
7TH SEMESTER 
MINING ENGINEERING 
12/14/2014 
1
Contents: 
Introduction 
Sequence of Development 
Cycle of Operation 
Auxiliary Operations 
Conditions 
Advantages 
Disadvantages 
References 
12/14/2014 
2
Introduction 
12/14/2014 
3 
In open pit mining : 
 Any overburden is stripped and transported to a disposal area to 
uncover the mineral deposit 
 Both stripping and mining are from one or a sequence of 
benches 
 Open-pit mines are used when deposits are found near the 
surface 
 Open pit mining is large scale method in term of production 
rate 
 Responsible for 60% of all surface outputs
Introduction(cont.) 
12/14/2014 
4
Sequence of Development 
12/14/2014 
5 
Major steps in the development are: 
 Land clearance 
 Location of surface plant 
 Location of waste dump 
 Equipment selection 
 Haul Road 
 Establishment of first bench
Sequence of Development (cont.) 
12/14/2014 
6
Cycle of Operation 
12/14/2014 
7 
The nature of overburden or waste and the ore to be mine 
determines the cycle of operation 
The stripping and mining cycle of operation consist of the 
following: 
 Drilling 
 Blasting 
 Excavation 
 Haulage
Cycle of Operation (cont.) 
12/14/2014 
8 
Drilling 
 Auger for weak rock 
 Roller bit for average rock 
 Percussion for very hard rock
Cycle of Operation(cont.) 
12/14/2014 
9 
Blasting 
 ANFO or slurry for soil or weak rock 
 WABOX or Dynamite for hard rock
Cycle of Operation(cont.) 
12/14/2014 
10 
Excavation 
 Power shovel 
 Front-end loader 
 Dozer 
 Scrapers(soil) 
 Dragline 
 Bucket wheel(soil)
Cycle of Operation(cont.) 
12/14/2014 
11 
Scraper 
Front-end Loader 
Drag line Power Shovel
Cycle of Operation(cont.) 
12/14/2014 
12 
Haulage 
 Truck 
 Belt 
 Conveyor 
 Rail
Cycle of Operation(cont.) 
12/14/2014 
13
Auxiliary Operations 
12/14/2014 
14 
Health and Safety 
Environmental Control 
Ground Control 
Power Supply 
Water Disposal 
Material Supply 
Maintenance 
Rehabilitation
Conditions 
12/14/2014 
15 
Ore Strength: Any 
Rock Strength: Any 
Deposit Shape: any but preferably tabular 
Deposit Dip: any but preferably low 
Deposit Size: Large, Thick 
Ore Grade: can be very low 
Ore Uniformity: uniform, variable 
Depth: Shallow to intermediate
Advantages 
12/14/2014 
16 
High Productivity 
Lowest Cost 
High Production Rate 
Early Production 
Low labor requirement 
Good recovery 
Good health and safety
Disadvantages 
12/14/2014 
17 
High Capital investment 
Surface damaged 
Require large Deposit 
Weather detrimental 
Slope stability 
Waste Disposal

Open pit mining

  • 1.
    OPEN PIT MINING KHALEEQ AHMED 1 1PWMIN0644 7TH SEMESTER MINING ENGINEERING 12/14/2014 1
  • 2.
    Contents: Introduction Sequenceof Development Cycle of Operation Auxiliary Operations Conditions Advantages Disadvantages References 12/14/2014 2
  • 3.
    Introduction 12/14/2014 3 In open pit mining :  Any overburden is stripped and transported to a disposal area to uncover the mineral deposit  Both stripping and mining are from one or a sequence of benches  Open-pit mines are used when deposits are found near the surface  Open pit mining is large scale method in term of production rate  Responsible for 60% of all surface outputs
  • 4.
  • 5.
    Sequence of Development 12/14/2014 5 Major steps in the development are:  Land clearance  Location of surface plant  Location of waste dump  Equipment selection  Haul Road  Establishment of first bench
  • 6.
    Sequence of Development(cont.) 12/14/2014 6
  • 7.
    Cycle of Operation 12/14/2014 7 The nature of overburden or waste and the ore to be mine determines the cycle of operation The stripping and mining cycle of operation consist of the following:  Drilling  Blasting  Excavation  Haulage
  • 8.
    Cycle of Operation(cont.) 12/14/2014 8 Drilling  Auger for weak rock  Roller bit for average rock  Percussion for very hard rock
  • 9.
    Cycle of Operation(cont.) 12/14/2014 9 Blasting  ANFO or slurry for soil or weak rock  WABOX or Dynamite for hard rock
  • 10.
    Cycle of Operation(cont.) 12/14/2014 10 Excavation  Power shovel  Front-end loader  Dozer  Scrapers(soil)  Dragline  Bucket wheel(soil)
  • 11.
    Cycle of Operation(cont.) 12/14/2014 11 Scraper Front-end Loader Drag line Power Shovel
  • 12.
    Cycle of Operation(cont.) 12/14/2014 12 Haulage  Truck  Belt  Conveyor  Rail
  • 13.
  • 14.
    Auxiliary Operations 12/14/2014 14 Health and Safety Environmental Control Ground Control Power Supply Water Disposal Material Supply Maintenance Rehabilitation
  • 15.
    Conditions 12/14/2014 15 Ore Strength: Any Rock Strength: Any Deposit Shape: any but preferably tabular Deposit Dip: any but preferably low Deposit Size: Large, Thick Ore Grade: can be very low Ore Uniformity: uniform, variable Depth: Shallow to intermediate
  • 16.
    Advantages 12/14/2014 16 High Productivity Lowest Cost High Production Rate Early Production Low labor requirement Good recovery Good health and safety
  • 17.
    Disadvantages 12/14/2014 17 High Capital investment Surface damaged Require large Deposit Weather detrimental Slope stability Waste Disposal