SlideShare a Scribd company logo
1 of 15
Download to read offline
P D Y 3 1 0
2-1
SURFACE MINING
METHODS
REFERENCE:
BULLIVANT, DA. Current Surface Mining Techniques.
Journal for the Transportation of Materials in Bulk: Bulk
Solids Handling, vol 7, n6, December 1987, pp827-833.
2.1 Ore reserves Suitable for Surface Mining
Ore reserves suitable for surface mining can be classified initially as;
Relatively horizontal stratified reserves with a thin or thick
covering of overburden
Stratified vein-type deposits with an inclination steeper than the
natural angle of repose of the material so that waste cannot be
tipped inside the pit
Massive deposits, deep and very large laterally such that
dumping of the waste within the pit is not possible.
Of all the variations of surface mining methods available, the three most
common methods only will be described here, namely;
Strip mining
Terrace mining
Open-pit mining
Figure 2.1 refers to the classification of these methods
Chapter
2
P D Y 3 1 0
2-2
Figure 2.1 Classification of mining methods
Note how the general classification system works, from stratified (or
layered) types of deposits, through the type of layering, the thickness of
overburden and finally the means by which overburden is handled;
specifically, in-pit or ex-pit systems.
A further consideration is the type of material (waste or ore) handling
systems that can be used in each type of mining operation, namely
cyclic (discontinuous) or continuous systems. Refer to Bullivant’s
reference for a description and analysis of the two systems and how
they could be applied (and under what circumstances) for each type of
mining method considered here.
P D Y 3 1 0
2-3
2.2 Strip Mining
Strip mining is ideally applied where the surface of the ground and the
ore body itself are relatively horizontal and not too deep under the
surface, and a wide area is available to be mined in a series of strips.
Typical examples of this type of mining are the larger tonnage coal
mining operations in Mpumulanga.
Favourable conditions are:
Relatively thin overburden (0-50m maximum other wise stripping
ration and cost of stripping becomes too high)
Regular and constant surface topography and coal layers (not
more than 20º variation from horizontal on the coal seam –
topography can vary more since pre-stripping can be used to
level it – but this is expensive to apply)
Extensive area of reserves (to give adequate life of mine (LOM)
and to cover all capital loan repayments – typically more than 20
years life at 4-14mt per annum production)
Walking draglines are for many years the most popular machine for this
type of mining due to their flexibility, utility and availability, but more
importantly, their low operating costs for waste mining (R/t or R/BCM).
The dragline is a typical combined cyclic excavator and material carrier
since it both excavates material and dumps it without the use of trucks
or conveyor belts. The dragline sits above the waste or overburden
block, usually 50m or so wide, on the highwall side and excavates the
material in front of itself, to dump it on the low-wall or spoil side of the
strip to uncover the coal seam below it.
For maximum productivity, a long strip is required (over 2km in length) to
reduce excessive “dead-heading” time. Longer pits increase the risks of
time dependant slope failure in both the highwall and the (waste) low-
wall and take up large surface areas that can cause rehabilitation and
transport problems. If mixing of coal is important (to meet sales
specifications) then long stripping lengths are also problematic in terms
of the active mining fronts available for mixing the coal. Where highwall
or low-wall stability is problematic, it becomes necessary to monitor the
stability of the pit extensively. Where the floor dips in the direction of the
highwall it is often necessary to improve the stability of the waste dump
through the use of a variety of additional mining method variations,
namely:
Selective placing of the waste (soft, slippery material for example
clay and shale) on top and not in the bottom of the waste dumps.
P D Y 3 1 0
2-4
Stripping or the blasting of the floor surface of the pit to give a
better friction surface (especially if floor is a low-friction material –
carbonaceous shale, etc.).
Excavation of clay materials (typical shales) from the floor to
expose material with more frictional resistance. That will
normally require a bench extension working method together with
the additional specialised handling of clay material (which will
result in increased waste handlings costs and therefore reduced
profitability).
Large scale floor slopes (ie. Coal seam inclinations) of more than 8 –
20º have in many cases lead to failures of waste dumps (usually
coinciding with heavy rains, poor drainage and clay material in the
bottom of the waste dump) and therefore modified terrace or even open-
pit mining methods have to be applied – although these methods are
often not financially viable with a low unit-cost high volume product such
as coal. Note that small scale changes in floor (or coal seam) elevation
or inclination are not as problematic from a geotechnical point of view,
but nevertheless create extremely difficult working conditions when
dragline mining is used (refer to Chapter 10 for details).
Nowadays, several large strip mines operate in areas that were
previously mined by underground methods, for example New Vaal
Colliery. In such cases it is difficult to anticipate the stability of the
overburden and geotechnical surveys are required especially where
underground rooms are required to be blasted (by collapsing the pillars
between) prior to using a dragline on these areas. Irrespective of the
precise geology of the coal seam, the general approach remains similar
to conventional strip mining and Figure 2.2 and 2.3 show the
terminology used and typical method of strip mining.
P D Y 3 1 0
2-5
Figure 2.2 Strip mining terminology
P D Y 3 1 0
2-6
Figure 2.3 Strip mining with dragline (on overburden) and rope
shovel (below, loading coal)
2.3 Terrace Mining
Where the overburden is too thick (or the floor of the pit (ie. The ore
inclination) is too steeply dipping) to allow waste dumping directly over
the pit (as is the case with a dragline and strip mining), it is necessary to
use intermediate cyclic or continuous transport (eg. trucks or conveyors)
to transport the overburden to where it can be tipped back into the
previously mined void.
It is a multi-benched sideways-moving method, the whole mine moves
over the ore reserve from one end to the other, but not necessarily in a
single bench. The number of benches used is usually a function of the
excavation depth and type of machinery used (typically between 10-15m
bench height and 1-32 benches in the terrace).
Examples of this type of mining are the German lignite mines (where
bucket-wheel excavators are used to excavate the overburden – a
typical example of a continuous excavating system) and, to a lesser
extent, some coal mines in the UK. In these cases, trucks and shovels
are used to work 10 benches simultaneously to expose the coal seams
underneath. The uppermost layer of overburden is normally mined
using hydraulic excavators and trucks, or (when soft material exists),
P D Y 3 1 0
2-7
using a bucket wheel excavator, conveyor belt and stacker. These
methods are more expensive to use than a dragline, but the dragline is
itself not suited to this type of mining due to the limited dump radius of
the machine and the much larger width of a terrace mine compared to a
strip mine. It is possible however to use a dragline in combination with a
“long” terrace as illustrated in Figure 2.4, but only in the lower or bottom
benches where the dig and dump point are within the working radius of
the dragline.
Figure 2.4 Combined terrace (pre-stripping of soft overburden) and
strip mining (stripping deeper hard overburden) methods and associated
equipment.
In South Africa, Grootegeluk Colliery is a typical example of terrace type
of mining. Currently, 11 benches are mined, 6 of overburden waste and
5 of coal. A dragline cannot be used due to the depth of the coal and
width of the pit, but later on in the life of the mine, the mined-out terraces
will be back-filled with waste (ie. The mining method will change from
modified terrace to conventional terrace – see Figure 2.1). On a smaller
scale Mooiplaas Dolomite is also a terrace mining operation (in this
case, ore is transported out of the mine using an in-pit crusher and
conveyor and waste is tipped directly as envisaged in a terrace mining
operation). Mine Figure 2.5 illustrates a typical 3 bench waste (OB1-3)
and 3 coal seam terrace operation with mining moving from R to L in the
diagram.
Where steeply dipping orebodies are encountered, the modified method
is most often applied as shown in Figure 2.6 in a more typical 3 waste
bench terrace operation with steeply dipping orebody. In this case, the
pit dimensions are limited by seam exposure (pit length) and available
working area (for mining and dumping faces) (pit width).
P D Y 3 1 0
2-8
Figure 2.5 Typical terrace mining operation
Figure 2.6 Terrace mining method with around the pit conveyor and
hydraulic excavator and haul trucks
P D Y 3 1 0
2-9
2.4 Open-pit Mining
This is the traditional cone-shaped excavation (although it can be any
shape, depending on the size and shape of the orebody) that is used
when the ore body is typically pipe-shaped, vein-type, steeply dipping
stratified or irregular. Although it is most often associated with metallic
orebodies, eg. Palabora copper, Mamatwan and Sishen iron-ore, it can
be used for any deposit that suits the geometry – most typically diamond
pipes – Venetia, Koffiefontein and Finsch.
The excavation is normally by rope- or hydraulic shovels with trucks
carrying both ore and waste. Drill and blast is most often used, which
makes the process cyclic. Waste is dumped outside the mined-out area
since no room is available within the pit. Waste is placed as close to the
edge of the pit as possible, to minimise transport costs. Figure 2.7
illustrates the terminology used in the pit design and Figure 2.8 the
mining method.
Figure 2.7 Typical open-pit bench terminology
Benches are normally excavated from 2-15m in height in stacks of 3 to
4, in between which is a crest on which the haul road is placed. When
the number of benches in the stack increases, the road gradient
increases too. Benches in the stack have a steep face angle whilst the
stack and overall slope angles are flatter, thereby helping to prevent
slope failures. From an analysis of overall slope geometry, it is clear
that as steep a slope as possible should be mined, to reduce the overall
stripping ratio. However, this rule is limited by the maximum gradient of
the haul road – typically 8-10% which requires frequent wider crests,
and the need to have flatter slope angles in places to provide slope
P D Y 3 1 0
2-10
stability. Note that each pit slope can have a different angle according to
the requirements of the design – with or without haul road, geology, etc.
Figure 2.8 Open-pit mining sequence (for pipe-like orebody)
P D Y 3 1 0
2-11
Mineral and especially waste transport costs comprise the greatest
amount of an open-pit mine’s working costs. To reduce this cost aspect
– especially when the pit gets deeper, the following options are possible;
In-pit crushers together with a conveyor belt, instead of truck
transport. (a continuous transport system (conveyor belt) is
usually much cheaper in terms of R/t hauled) and can be
installed at a steeper angle thereby saving stripping costs by
virtue of reduced stripping ratio.
Trolley-assist on the main haul road. (electrical power supply to
trucks) – faster trucks, steeper roads or cheaper R/t costs
Computerised truck dispatch – more efficient use of trucks
Steeper bench slope angles (in other words, a reduced stripping
ratio) where stability allows them – especially at the bottom of the
pit when LOM approaches end.
As a result of the high cost of rock transport – up to 50% of an open-pit’s
total operating costs, many large pits consider continuous transport
systems. The OPEC induced rise in the price of oil in the 1970’s and
more recently in 2000/1 has forced mines to rethink strategies for
reducing fuel consumption. Continuous transport systems (and the
associated in-pit crusher if drill and blast is used) begin to out-perform
truck based systems – since they are run on electricity, not diesel fuel.
Whilst electricity can still be cheaply provided from local coal power
stations (South Africa’s electricity is one of the cheapest in the world),
considerable ore and waste transport cost savings can also be realised.
These savings become all the more important as the depth of the pit
increases, since the cost of transport increases exponentially with
increasing vertical transport distance.
As a result of their application flexibility, truck and shovel systems are
always popular and widely applied in mining, but in terms of energy-
efficiency, trucks use only 40% of the energy input to move the load, the
remaining 60% is used to move the tare mass of the truck itself.
Conveyors use 80% of the energy input to move the load. Although oil
prices are now at a more realistic level, energy costs of trucks are still
50% higher than that of conveyors in some parts of the world. In South
Africa, with it’s low local production and small strategic reserve, together
with the R/$ exchange rate, the trade-off between the two systems must
be regularly re-evaluated. Chapter 9 contains more details concerning
the design and use of continuous haulage systems.
P D Y 3 1 0
2-12
⌦EXAMPLE QUESTIONS
1 In surface mining, two excavation systems, namely cyclic and
continuous, are defined;
1.1 Why are the two systems differentiated?
1.1.1 Illustrate the components of each system in terms
of ground preparation, excavation, transport and
dumping.
1.1.2 Under certain circumstances, components of both
systems can be combined. What circumstances may
lead to such combined systems being used?
2 Two surface mines are considering the use of a conveyor in
conjunction with their current fleet of trucks and shovels. The
mines are;
(i) a strip mine operation in which coal is transported
out of the strip from a depth of 37m to a coal plant on
surface, at a rate of 1,2mt per month.
(ii) an open-pit operation in which coal and waste are
transported from a depth of 300m to either a waste dump
or a processing plant on surface, at a rate of 1,22mt per
month (ore) at a stripping ratio of 3:1.
Give advice to the mines concerning the practicality and utility of
using a conveyor to either replace or supplement the existing
systems.
Give advice to the mines as to what extra additional equipment
they may need if they were to combine existing and new
conveyor systems.
3 Explain the terms;
a. Loose cubic meters (LCM)
b. Bank cubic meters (BCM)
with reference to overburden handling.
c. Bench, stack and overall slope angles and the
factor governing the choice of slope angle in each case.
P D Y 3 1 0
2-13
d. Overall (s)- and immediate (variable) stripping
ratio (S’), with reference to the open pit mining method.
3.1 Illustrate a surface mining classification method that
differentiates between strip- and terrace mining methods. Refer
in your answer to a stratified ore body that lies relatively
horizontal and include the other factors that would allow either
method to be identified for a particular set of conditions.
3.2 With the help of diagrams, illustrate and discuss the
differences between the two methods mentioned in 3.1 above,
in terms of the mining process (especially overburden handling)
and the typical dimensions of each type of mining. It is NOT
necessary to discuss equipment choices.
4 Illustrate with a suitable diagram, how waste overburden and
orebody geometry dictates the choice of mining method. You
should consider four surface mining methods in your answer
and show which methods may be combined and under what
circumstances.
5 Explain the following terms with the aid of sketches, as they
apply to an open-pit operation;
(a) Overall slope angle
(b) Bench stack slope angle
5.1 Why is the individual bench slope angle steeper than the
stack slope angle, which is steeper than the overall pit slope
angle?
5.2 Discuss the concept of stripping ratio and how haul road
gradient, bench, stack and overall slope angles effect it.
6 What are the primary classifications of orebodies that are
suitable for surface mining and on what basis would you decide
if such an orebody can actually be mined?
7 What is meant by “break-even stripping ratio” and what factors
would you consider when you need to determine its value?
7.1 Illustrate with suitable cross-section sketches showing
ore and waste components, how overall stripping ration can be;
a. constant
P D Y 3 1 0
2-14
b. Increasing
c. Decreasing
over the life of an open-pit mine.
8 Describe, using suitable annotated sketches, the difference
between terrace and modified terrace methods of surface
mining. Give a typical example of a mine in South Africa that
has used both methods and explain how the methods follow
each other.
9 Describe briefly how the operational life of a mine (LOM) can
influence the choice of transport equipment. Refer in your
answer to a new open-pit mine and a deep open-pit mine that is
near the end of it’s production lifetime.
⌦STUDENT ASSIGNMENT
Compile your own notes from Bullivant’s reference paper, with particular
reference to;
The mining-method classification system
Transport systems flow diagram (continuous and cyclic
excavation and transport systems), component, combination and
the degree to which they may be successfully applied and used
in each type of mining method discussed.
P M Y 1 2 0
1

More Related Content

What's hot

Pwc basics-of-mining-2-som-mining-methods
Pwc basics-of-mining-2-som-mining-methodsPwc basics-of-mining-2-som-mining-methods
Pwc basics-of-mining-2-som-mining-methodsAzzuhry Smallville
 
Lecture 2 basic surface mining practise-2
Lecture 2  basic surface mining practise-2Lecture 2  basic surface mining practise-2
Lecture 2 basic surface mining practise-2IDHAMUKI
 
Core Concepts Mining Cycle
Core Concepts Mining CycleCore Concepts Mining Cycle
Core Concepts Mining CycleMining Matters
 
Basics of openpit mining
Basics of openpit miningBasics of openpit mining
Basics of openpit miningSATYANARAYANA I
 
Mine planning process A Madowe SAIMM paper
Mine planning process A Madowe SAIMM paperMine planning process A Madowe SAIMM paper
Mine planning process A Madowe SAIMM paperAlfred Madowe
 
Underground mining method
Underground mining methodUnderground mining method
Underground mining methodSafdar Ali
 
Underground mining system
Underground mining systemUnderground mining system
Underground mining systemSrimontorumpa
 
Mining Methods
Mining MethodsMining Methods
Mining MethodsVR M
 
Support Systems In Cut And Fill Method Of Stoping
Support Systems In Cut And Fill Method Of StopingSupport Systems In Cut And Fill Method Of Stoping
Support Systems In Cut And Fill Method Of Stopingem_vishal
 
Underground mining methods
Underground mining methodsUnderground mining methods
Underground mining methodsTayyab Anwar
 

What's hot (20)

Open pit mining
Open pit miningOpen pit mining
Open pit mining
 
Pwc basics-of-mining-2-som-mining-methods
Pwc basics-of-mining-2-som-mining-methodsPwc basics-of-mining-2-som-mining-methods
Pwc basics-of-mining-2-som-mining-methods
 
Lecture 2 basic surface mining practise-2
Lecture 2  basic surface mining practise-2Lecture 2  basic surface mining practise-2
Lecture 2 basic surface mining practise-2
 
Topic 5: Mining Methods-Part I-Surface mining
Topic 5: Mining Methods-Part I-Surface mining Topic 5: Mining Methods-Part I-Surface mining
Topic 5: Mining Methods-Part I-Surface mining
 
Core Concepts Mining Cycle
Core Concepts Mining CycleCore Concepts Mining Cycle
Core Concepts Mining Cycle
 
Basics of openpit mining
Basics of openpit miningBasics of openpit mining
Basics of openpit mining
 
Room and Pillar Mining Method
Room and Pillar Mining MethodRoom and Pillar Mining Method
Room and Pillar Mining Method
 
Cut and Fill mining
Cut and Fill miningCut and Fill mining
Cut and Fill mining
 
Topic 2: Mining
Topic 2: MiningTopic 2: Mining
Topic 2: Mining
 
Mine planning process A Madowe SAIMM paper
Mine planning process A Madowe SAIMM paperMine planning process A Madowe SAIMM paper
Mine planning process A Madowe SAIMM paper
 
Open pit mining
Open pit miningOpen pit mining
Open pit mining
 
coal mining
coal miningcoal mining
coal mining
 
Underground mining method
Underground mining methodUnderground mining method
Underground mining method
 
Underground mining system
Underground mining systemUnderground mining system
Underground mining system
 
Topic 7-mining methods-part iii -surface mining- placer mining
Topic 7-mining methods-part iii -surface mining- placer miningTopic 7-mining methods-part iii -surface mining- placer mining
Topic 7-mining methods-part iii -surface mining- placer mining
 
Surface mining
Surface miningSurface mining
Surface mining
 
Mining Methods
Mining MethodsMining Methods
Mining Methods
 
Support Systems In Cut And Fill Method Of Stoping
Support Systems In Cut And Fill Method Of StopingSupport Systems In Cut And Fill Method Of Stoping
Support Systems In Cut And Fill Method Of Stoping
 
Openpitmining
OpenpitminingOpenpitmining
Openpitmining
 
Underground mining methods
Underground mining methodsUnderground mining methods
Underground mining methods
 

Similar to Ch2 before

Coal mining methods
Coal mining methodsCoal mining methods
Coal mining methodsPramoda Raj
 
Coal mining methods Seminar Presentation
Coal mining methods Seminar Presentation Coal mining methods Seminar Presentation
Coal mining methods Seminar Presentation Chandan Pradhan
 
BLOCK CAVING ATRI.ppt
BLOCK CAVING ATRI.pptBLOCK CAVING ATRI.ppt
BLOCK CAVING ATRI.pptAnshul Yadav
 
Underground Coal Mining Study
Underground Coal Mining StudyUnderground Coal Mining Study
Underground Coal Mining StudyOnur Tuncay
 
Thin seam mining
Thin seam miningThin seam mining
Thin seam miningSafdar Ali
 
Valgma an evaluation_of_technological_overburden_thickness_limit
Valgma an evaluation_of_technological_overburden_thickness_limitValgma an evaluation_of_technological_overburden_thickness_limit
Valgma an evaluation_of_technological_overburden_thickness_limitIngo Valgma
 
Criteria for selection of Board and pillar for multiple seams
Criteria for selection of Board and pillar for multiple seamsCriteria for selection of Board and pillar for multiple seams
Criteria for selection of Board and pillar for multiple seamsAsim kumar Satapathy
 
2 1 excavation_basementconstruction
2 1 excavation_basementconstruction2 1 excavation_basementconstruction
2 1 excavation_basementconstructionvietcgxd
 
Performance review of TBM
Performance review of TBMPerformance review of TBM
Performance review of TBMindranjanGhosh
 
Coal Lectures Series Mining Technology Presentation
Coal Lectures Series   Mining Technology PresentationCoal Lectures Series   Mining Technology Presentation
Coal Lectures Series Mining Technology PresentationThames Global Consultants
 
report for tunnelling by tunnel boring machine
report for tunnelling by tunnel boring machinereport for tunnelling by tunnel boring machine
report for tunnelling by tunnel boring machineVISHAL KUMAR SINGH
 

Similar to Ch2 before (20)

PDF document lecture 3.pdf
PDF document lecture 3.pdfPDF document lecture 3.pdf
PDF document lecture 3.pdf
 
Cut & fill mining method
Cut & fill mining methodCut & fill mining method
Cut & fill mining method
 
Coal mining methods
Coal mining methodsCoal mining methods
Coal mining methods
 
Coal mining methods Seminar Presentation
Coal mining methods Seminar Presentation Coal mining methods Seminar Presentation
Coal mining methods Seminar Presentation
 
Continuous miner
Continuous minerContinuous miner
Continuous miner
 
BLOCK CAVING ATRI.ppt
BLOCK CAVING ATRI.pptBLOCK CAVING ATRI.ppt
BLOCK CAVING ATRI.ppt
 
Caving Underground Mining Methods (longwall, Sublevel caving, & Block caving)
Caving Underground Mining Methods (longwall, Sublevel caving, &  Block caving)Caving Underground Mining Methods (longwall, Sublevel caving, &  Block caving)
Caving Underground Mining Methods (longwall, Sublevel caving, & Block caving)
 
Underground Coal Mining Study
Underground Coal Mining StudyUnderground Coal Mining Study
Underground Coal Mining Study
 
Thin seam mining
Thin seam miningThin seam mining
Thin seam mining
 
Valgma an evaluation_of_technological_overburden_thickness_limit
Valgma an evaluation_of_technological_overburden_thickness_limitValgma an evaluation_of_technological_overburden_thickness_limit
Valgma an evaluation_of_technological_overburden_thickness_limit
 
Criteria for selection of Board and pillar for multiple seams
Criteria for selection of Board and pillar for multiple seamsCriteria for selection of Board and pillar for multiple seams
Criteria for selection of Board and pillar for multiple seams
 
Underground Mining System Question Pattern and Answer
Underground Mining System Question Pattern and AnswerUnderground Mining System Question Pattern and Answer
Underground Mining System Question Pattern and Answer
 
Cut and Fill Stoping
Cut and Fill StopingCut and Fill Stoping
Cut and Fill Stoping
 
2 1 excavation_basementconstruction
2 1 excavation_basementconstruction2 1 excavation_basementconstruction
2 1 excavation_basementconstruction
 
Performance review of TBM
Performance review of TBMPerformance review of TBM
Performance review of TBM
 
Power shovel
Power shovelPower shovel
Power shovel
 
ISEE Journal
ISEE JournalISEE Journal
ISEE Journal
 
Coal Lectures Series Mining Technology
Coal Lectures Series   Mining TechnologyCoal Lectures Series   Mining Technology
Coal Lectures Series Mining Technology
 
Coal Lectures Series Mining Technology Presentation
Coal Lectures Series   Mining Technology PresentationCoal Lectures Series   Mining Technology Presentation
Coal Lectures Series Mining Technology Presentation
 
report for tunnelling by tunnel boring machine
report for tunnelling by tunnel boring machinereport for tunnelling by tunnel boring machine
report for tunnelling by tunnel boring machine
 

Recently uploaded

Effects of rheological properties on mixing
Effects of rheological properties on mixingEffects of rheological properties on mixing
Effects of rheological properties on mixingviprabot1
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
DATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage exampleDATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage examplePragyanshuParadkar1
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 

Recently uploaded (20)

Effects of rheological properties on mixing
Effects of rheological properties on mixingEffects of rheological properties on mixing
Effects of rheological properties on mixing
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
DATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage exampleDATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage example
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 

Ch2 before

  • 1. P D Y 3 1 0 2-1 SURFACE MINING METHODS REFERENCE: BULLIVANT, DA. Current Surface Mining Techniques. Journal for the Transportation of Materials in Bulk: Bulk Solids Handling, vol 7, n6, December 1987, pp827-833. 2.1 Ore reserves Suitable for Surface Mining Ore reserves suitable for surface mining can be classified initially as; Relatively horizontal stratified reserves with a thin or thick covering of overburden Stratified vein-type deposits with an inclination steeper than the natural angle of repose of the material so that waste cannot be tipped inside the pit Massive deposits, deep and very large laterally such that dumping of the waste within the pit is not possible. Of all the variations of surface mining methods available, the three most common methods only will be described here, namely; Strip mining Terrace mining Open-pit mining Figure 2.1 refers to the classification of these methods Chapter 2
  • 2. P D Y 3 1 0 2-2 Figure 2.1 Classification of mining methods Note how the general classification system works, from stratified (or layered) types of deposits, through the type of layering, the thickness of overburden and finally the means by which overburden is handled; specifically, in-pit or ex-pit systems. A further consideration is the type of material (waste or ore) handling systems that can be used in each type of mining operation, namely cyclic (discontinuous) or continuous systems. Refer to Bullivant’s reference for a description and analysis of the two systems and how they could be applied (and under what circumstances) for each type of mining method considered here.
  • 3. P D Y 3 1 0 2-3 2.2 Strip Mining Strip mining is ideally applied where the surface of the ground and the ore body itself are relatively horizontal and not too deep under the surface, and a wide area is available to be mined in a series of strips. Typical examples of this type of mining are the larger tonnage coal mining operations in Mpumulanga. Favourable conditions are: Relatively thin overburden (0-50m maximum other wise stripping ration and cost of stripping becomes too high) Regular and constant surface topography and coal layers (not more than 20º variation from horizontal on the coal seam – topography can vary more since pre-stripping can be used to level it – but this is expensive to apply) Extensive area of reserves (to give adequate life of mine (LOM) and to cover all capital loan repayments – typically more than 20 years life at 4-14mt per annum production) Walking draglines are for many years the most popular machine for this type of mining due to their flexibility, utility and availability, but more importantly, their low operating costs for waste mining (R/t or R/BCM). The dragline is a typical combined cyclic excavator and material carrier since it both excavates material and dumps it without the use of trucks or conveyor belts. The dragline sits above the waste or overburden block, usually 50m or so wide, on the highwall side and excavates the material in front of itself, to dump it on the low-wall or spoil side of the strip to uncover the coal seam below it. For maximum productivity, a long strip is required (over 2km in length) to reduce excessive “dead-heading” time. Longer pits increase the risks of time dependant slope failure in both the highwall and the (waste) low- wall and take up large surface areas that can cause rehabilitation and transport problems. If mixing of coal is important (to meet sales specifications) then long stripping lengths are also problematic in terms of the active mining fronts available for mixing the coal. Where highwall or low-wall stability is problematic, it becomes necessary to monitor the stability of the pit extensively. Where the floor dips in the direction of the highwall it is often necessary to improve the stability of the waste dump through the use of a variety of additional mining method variations, namely: Selective placing of the waste (soft, slippery material for example clay and shale) on top and not in the bottom of the waste dumps.
  • 4. P D Y 3 1 0 2-4 Stripping or the blasting of the floor surface of the pit to give a better friction surface (especially if floor is a low-friction material – carbonaceous shale, etc.). Excavation of clay materials (typical shales) from the floor to expose material with more frictional resistance. That will normally require a bench extension working method together with the additional specialised handling of clay material (which will result in increased waste handlings costs and therefore reduced profitability). Large scale floor slopes (ie. Coal seam inclinations) of more than 8 – 20º have in many cases lead to failures of waste dumps (usually coinciding with heavy rains, poor drainage and clay material in the bottom of the waste dump) and therefore modified terrace or even open- pit mining methods have to be applied – although these methods are often not financially viable with a low unit-cost high volume product such as coal. Note that small scale changes in floor (or coal seam) elevation or inclination are not as problematic from a geotechnical point of view, but nevertheless create extremely difficult working conditions when dragline mining is used (refer to Chapter 10 for details). Nowadays, several large strip mines operate in areas that were previously mined by underground methods, for example New Vaal Colliery. In such cases it is difficult to anticipate the stability of the overburden and geotechnical surveys are required especially where underground rooms are required to be blasted (by collapsing the pillars between) prior to using a dragline on these areas. Irrespective of the precise geology of the coal seam, the general approach remains similar to conventional strip mining and Figure 2.2 and 2.3 show the terminology used and typical method of strip mining.
  • 5. P D Y 3 1 0 2-5 Figure 2.2 Strip mining terminology
  • 6. P D Y 3 1 0 2-6 Figure 2.3 Strip mining with dragline (on overburden) and rope shovel (below, loading coal) 2.3 Terrace Mining Where the overburden is too thick (or the floor of the pit (ie. The ore inclination) is too steeply dipping) to allow waste dumping directly over the pit (as is the case with a dragline and strip mining), it is necessary to use intermediate cyclic or continuous transport (eg. trucks or conveyors) to transport the overburden to where it can be tipped back into the previously mined void. It is a multi-benched sideways-moving method, the whole mine moves over the ore reserve from one end to the other, but not necessarily in a single bench. The number of benches used is usually a function of the excavation depth and type of machinery used (typically between 10-15m bench height and 1-32 benches in the terrace). Examples of this type of mining are the German lignite mines (where bucket-wheel excavators are used to excavate the overburden – a typical example of a continuous excavating system) and, to a lesser extent, some coal mines in the UK. In these cases, trucks and shovels are used to work 10 benches simultaneously to expose the coal seams underneath. The uppermost layer of overburden is normally mined using hydraulic excavators and trucks, or (when soft material exists),
  • 7. P D Y 3 1 0 2-7 using a bucket wheel excavator, conveyor belt and stacker. These methods are more expensive to use than a dragline, but the dragline is itself not suited to this type of mining due to the limited dump radius of the machine and the much larger width of a terrace mine compared to a strip mine. It is possible however to use a dragline in combination with a “long” terrace as illustrated in Figure 2.4, but only in the lower or bottom benches where the dig and dump point are within the working radius of the dragline. Figure 2.4 Combined terrace (pre-stripping of soft overburden) and strip mining (stripping deeper hard overburden) methods and associated equipment. In South Africa, Grootegeluk Colliery is a typical example of terrace type of mining. Currently, 11 benches are mined, 6 of overburden waste and 5 of coal. A dragline cannot be used due to the depth of the coal and width of the pit, but later on in the life of the mine, the mined-out terraces will be back-filled with waste (ie. The mining method will change from modified terrace to conventional terrace – see Figure 2.1). On a smaller scale Mooiplaas Dolomite is also a terrace mining operation (in this case, ore is transported out of the mine using an in-pit crusher and conveyor and waste is tipped directly as envisaged in a terrace mining operation). Mine Figure 2.5 illustrates a typical 3 bench waste (OB1-3) and 3 coal seam terrace operation with mining moving from R to L in the diagram. Where steeply dipping orebodies are encountered, the modified method is most often applied as shown in Figure 2.6 in a more typical 3 waste bench terrace operation with steeply dipping orebody. In this case, the pit dimensions are limited by seam exposure (pit length) and available working area (for mining and dumping faces) (pit width).
  • 8. P D Y 3 1 0 2-8 Figure 2.5 Typical terrace mining operation Figure 2.6 Terrace mining method with around the pit conveyor and hydraulic excavator and haul trucks
  • 9. P D Y 3 1 0 2-9 2.4 Open-pit Mining This is the traditional cone-shaped excavation (although it can be any shape, depending on the size and shape of the orebody) that is used when the ore body is typically pipe-shaped, vein-type, steeply dipping stratified or irregular. Although it is most often associated with metallic orebodies, eg. Palabora copper, Mamatwan and Sishen iron-ore, it can be used for any deposit that suits the geometry – most typically diamond pipes – Venetia, Koffiefontein and Finsch. The excavation is normally by rope- or hydraulic shovels with trucks carrying both ore and waste. Drill and blast is most often used, which makes the process cyclic. Waste is dumped outside the mined-out area since no room is available within the pit. Waste is placed as close to the edge of the pit as possible, to minimise transport costs. Figure 2.7 illustrates the terminology used in the pit design and Figure 2.8 the mining method. Figure 2.7 Typical open-pit bench terminology Benches are normally excavated from 2-15m in height in stacks of 3 to 4, in between which is a crest on which the haul road is placed. When the number of benches in the stack increases, the road gradient increases too. Benches in the stack have a steep face angle whilst the stack and overall slope angles are flatter, thereby helping to prevent slope failures. From an analysis of overall slope geometry, it is clear that as steep a slope as possible should be mined, to reduce the overall stripping ratio. However, this rule is limited by the maximum gradient of the haul road – typically 8-10% which requires frequent wider crests, and the need to have flatter slope angles in places to provide slope
  • 10. P D Y 3 1 0 2-10 stability. Note that each pit slope can have a different angle according to the requirements of the design – with or without haul road, geology, etc. Figure 2.8 Open-pit mining sequence (for pipe-like orebody)
  • 11. P D Y 3 1 0 2-11 Mineral and especially waste transport costs comprise the greatest amount of an open-pit mine’s working costs. To reduce this cost aspect – especially when the pit gets deeper, the following options are possible; In-pit crushers together with a conveyor belt, instead of truck transport. (a continuous transport system (conveyor belt) is usually much cheaper in terms of R/t hauled) and can be installed at a steeper angle thereby saving stripping costs by virtue of reduced stripping ratio. Trolley-assist on the main haul road. (electrical power supply to trucks) – faster trucks, steeper roads or cheaper R/t costs Computerised truck dispatch – more efficient use of trucks Steeper bench slope angles (in other words, a reduced stripping ratio) where stability allows them – especially at the bottom of the pit when LOM approaches end. As a result of the high cost of rock transport – up to 50% of an open-pit’s total operating costs, many large pits consider continuous transport systems. The OPEC induced rise in the price of oil in the 1970’s and more recently in 2000/1 has forced mines to rethink strategies for reducing fuel consumption. Continuous transport systems (and the associated in-pit crusher if drill and blast is used) begin to out-perform truck based systems – since they are run on electricity, not diesel fuel. Whilst electricity can still be cheaply provided from local coal power stations (South Africa’s electricity is one of the cheapest in the world), considerable ore and waste transport cost savings can also be realised. These savings become all the more important as the depth of the pit increases, since the cost of transport increases exponentially with increasing vertical transport distance. As a result of their application flexibility, truck and shovel systems are always popular and widely applied in mining, but in terms of energy- efficiency, trucks use only 40% of the energy input to move the load, the remaining 60% is used to move the tare mass of the truck itself. Conveyors use 80% of the energy input to move the load. Although oil prices are now at a more realistic level, energy costs of trucks are still 50% higher than that of conveyors in some parts of the world. In South Africa, with it’s low local production and small strategic reserve, together with the R/$ exchange rate, the trade-off between the two systems must be regularly re-evaluated. Chapter 9 contains more details concerning the design and use of continuous haulage systems.
  • 12. P D Y 3 1 0 2-12 ⌦EXAMPLE QUESTIONS 1 In surface mining, two excavation systems, namely cyclic and continuous, are defined; 1.1 Why are the two systems differentiated? 1.1.1 Illustrate the components of each system in terms of ground preparation, excavation, transport and dumping. 1.1.2 Under certain circumstances, components of both systems can be combined. What circumstances may lead to such combined systems being used? 2 Two surface mines are considering the use of a conveyor in conjunction with their current fleet of trucks and shovels. The mines are; (i) a strip mine operation in which coal is transported out of the strip from a depth of 37m to a coal plant on surface, at a rate of 1,2mt per month. (ii) an open-pit operation in which coal and waste are transported from a depth of 300m to either a waste dump or a processing plant on surface, at a rate of 1,22mt per month (ore) at a stripping ratio of 3:1. Give advice to the mines concerning the practicality and utility of using a conveyor to either replace or supplement the existing systems. Give advice to the mines as to what extra additional equipment they may need if they were to combine existing and new conveyor systems. 3 Explain the terms; a. Loose cubic meters (LCM) b. Bank cubic meters (BCM) with reference to overburden handling. c. Bench, stack and overall slope angles and the factor governing the choice of slope angle in each case.
  • 13. P D Y 3 1 0 2-13 d. Overall (s)- and immediate (variable) stripping ratio (S’), with reference to the open pit mining method. 3.1 Illustrate a surface mining classification method that differentiates between strip- and terrace mining methods. Refer in your answer to a stratified ore body that lies relatively horizontal and include the other factors that would allow either method to be identified for a particular set of conditions. 3.2 With the help of diagrams, illustrate and discuss the differences between the two methods mentioned in 3.1 above, in terms of the mining process (especially overburden handling) and the typical dimensions of each type of mining. It is NOT necessary to discuss equipment choices. 4 Illustrate with a suitable diagram, how waste overburden and orebody geometry dictates the choice of mining method. You should consider four surface mining methods in your answer and show which methods may be combined and under what circumstances. 5 Explain the following terms with the aid of sketches, as they apply to an open-pit operation; (a) Overall slope angle (b) Bench stack slope angle 5.1 Why is the individual bench slope angle steeper than the stack slope angle, which is steeper than the overall pit slope angle? 5.2 Discuss the concept of stripping ratio and how haul road gradient, bench, stack and overall slope angles effect it. 6 What are the primary classifications of orebodies that are suitable for surface mining and on what basis would you decide if such an orebody can actually be mined? 7 What is meant by “break-even stripping ratio” and what factors would you consider when you need to determine its value? 7.1 Illustrate with suitable cross-section sketches showing ore and waste components, how overall stripping ration can be; a. constant
  • 14. P D Y 3 1 0 2-14 b. Increasing c. Decreasing over the life of an open-pit mine. 8 Describe, using suitable annotated sketches, the difference between terrace and modified terrace methods of surface mining. Give a typical example of a mine in South Africa that has used both methods and explain how the methods follow each other. 9 Describe briefly how the operational life of a mine (LOM) can influence the choice of transport equipment. Refer in your answer to a new open-pit mine and a deep open-pit mine that is near the end of it’s production lifetime. ⌦STUDENT ASSIGNMENT Compile your own notes from Bullivant’s reference paper, with particular reference to; The mining-method classification system Transport systems flow diagram (continuous and cyclic excavation and transport systems), component, combination and the degree to which they may be successfully applied and used in each type of mining method discussed.
  • 15. P M Y 1 2 0 1