SlideShare a Scribd company logo
Offshore wind energy Development in
India
1
Introduction
• At the recently concluded CoP26, Hon’ble Prime Minister’s introduced five nectar elements (Panchamrit)
towards contribution to climate action. One of the key element of Panchamrit is to achieve electric
cumulative installed capacity 500 GW from non-fossil based capacity by 2030.
• GOI has set a target of 30 GW of offshore wind installations by 2030
• Preliminary wind resource estimation based on Mesoscale model suggested potential of 70 GW of offshore
wind off the coast of Gujarat and Tamil Nadu in the demarcated area .
• The ‘Offshore Wind Policy’ outlining the basic framework was issued earlier in October, 2015.
• The Guidelines for Offshore Wind Power Studies and Surveys for carrying out offshore study/survey were
issued in September 2018.
• Now, A strategy/roadmap has been prepared to work towards achieving the set target which was discussed
with stakeholders under the chairmanship of Hon’ble minister.
2
Assuming 4.5MW /Sq. km of seabed area, 35-40 GW
of Installable potential is estimated in Gujarat
• 05 offshore zones (Zone A-B-D-E-F) identified off
Gujarat Coast.
• NIWE carried out studies/surveys for 370 sq. km sea
bed area in zone B:
(i) Wind Resource assessment (through LIDAR)
(Average wind speed – 7.5 m/s)
(ii) Geophysical and Geotechnical investigation
(iii) Rapid Environment Impact Assessment (EIA)
(iv) Oceanographic (Wave, Tide & current) study
(v) Marine Spatial Planning (MSP) under progress.
• This site will be considered for 1st phase of offshore
wind development.
Identified Offshore sites (Gujarat)
Assuming 4.5MW /Sq. km of
seabed area, 25-30 GW of
Installable potential is estimated
in Tamil Nadu
07 offshore zones (Zone A-G) identified off Tamil Nadu Coast.
Preliminary Assessment shows high annual average wind speeds in the range of 9 - 10.5 m/s.
Detailed offshore measurement study/survey not conducted.
MNRE intends to invite offshore wind developers for carrying out study/survey in these zones.
These zones may come up in 2nd phase of offshore development.
Indicative Auction Trajectory
Year Year wise Offshore Wind Bids
2022 1 GW
2023 2 GW
2024 3 GW
2026 4 GW
2027 5 GW
2028 5 GW
2029 5 GW
2030 5 GW
Total 30 GW
• In 1st phase, offshore bidding for 1 GW capacity off
Gujarat coast to be floated by SECI in year 2022.
• In 2nd phase, bidding for 2 GW capacity will be
floated in year 2023 for projects along Indian
coastline by SECI.
• The VGF based Competitive bidding will be
followed only for 1st and 2nd phase projects.
• For 3rd phase of projects, the support in the form of
evacuation infrastructure and fiscal incentives such
as waiver of transmission charges and Renewable
Energy Certificates (REC) multipliers will be
explored.
5
Scope of Project Development
• Evacuation of power from the offshore pooling
delivery point to the onshore
meeting/interconnection point by CTU/PGCIL. The
cost of evacuation will be socialised.
• ‘Lease Agreement’ for 30 years between MNRE or its
designated agency and successful bidders. Annual
floor lease fee @ Rs 1.0 lakhs/Sq.km/year for entire
allocated block shall be paid from the date of
allotment to till decommissioning of the project.
• Detailed Project Submission within 6 months of
Capacity Awarded.
• Four Years time period for project Development from
the date of signing of “Concessionaire agreement”.
Fig: Evacuation Infrastructure Network
6
Offshore Development Models (Model-1)
• Demarcated offshore sites where MNRE/NIWE has carried out
detailed studies/surveys.
• In 1st Phase identified Zone ‘B3’ (370 Sq.km) off the coast of
Gujarat.
• Under this Model, a two stage single bid process followed by
E-Reverse Auction (e-RA) based on the VGF amount will be
adopted for awarding capacity.
• This model can be further extended to other zones where
necessary studies & surveys have been carried out by NIWE.
Fig: Offshore Wind site Zone ‘B3’ off Gujarat Coast
7
Offshore Development Models (Model-2)
• This model is applicable for all sites along coastline (except sites covered under model-1)
• Developer may select any offshore site/sites and carry out study survey.
• Bidding Mechanism to be the same as followed under Model-1.
• Project Development can happen through either;
(i) Bidding
(ii) Sale of Power under Open Access regime ( Developer has to submit the DPR within 5 years from the date of
consent for study/survey issued by NIWE, which may be extended up to max 6 years on a case to case basis)
• Post expiry of the 6 year period, all clearances to the relevant developer shall be withdrawn and the developer shall
deposit the study/survey data they have collected with NIWE.
• In case of project development under open access, the developer may submit the proposal along with DPR to NIWE.
Developer shall directly approach the consumer for sale of power through open access.
8
9
Institutional Mechanism
Sl. No Activity Institution
1 Application submission for Letter of Consent
(study/survey)
NIWE
2 Power off-take SECI/State DISCOM/Bilateral Agreement
3 Grid connectivity Central Transmission Utility (CTU)
4 Lease agreement MNRE or its designated agency
5 Single window clearances for NoC’s NIWE will facilitate all the stage-I & stage-II clearances.
6 Grid connection permission CTU
7 Project implementation agreement Bidder and SECI or other implementing agencies
8 Project monitoring SECI/NIWE
Physical Studies conducted
Sl. No Name Institution Remarks
1 Offshore wind resource assessment
using LIDAR at Zone B, Gulf of
khambhat, Off Gujarat coast
NIWE, Chennai Data published 2 years (2017-2019)
2 Geo-Physical (370 Sq.km) &
Geotechnical investigation at Zone
B, Gulf of khambhat, Off Gujarat
coast
NIWE through NIOT, Chennai & NIO,
Goa and COWI (70sq.km)
Completed and awaiting clearance for
data porting
3 Rapid EIA for 365Sq.km at Zone B,
Gulf of khambhat, Off Gujarat coast
NIWE through NIO, Goa Completed along with stakeholder
consultation
4 Geotechnical investigation at Zone
A,B&C1, Gulf of Mannar, Off
TamilNadu coast
NIWE through M/s COMACOE Completed and awaiting clearance for
data porting
10
11
Reports Published through various TA Programmes
Sl. No Name Institution Remarks
1 Feasibility Report For Offshore Wind Power Development In
Gujarat.
FOWIND EU Supported project
2 Feasibility Report For Offshore Wind Power Development
InTamil Nadu.
FOWIND EU Supported project
3 Report On Supply Chain, Ports And Logistics. FOWIND EU Supported project
4 Grid Integration Study For Offshore Wind Firm
DevelopmentIn Gujarat And Tamil Nadu.
FOWIND EU Supported project
5 Metocean Study., MetoceanWeather Windows for
installation., and Metocean Data Requirements.
FOWPI EU Supported project
6 Procedures for Offshore Wind. FOWPI EU Supported project
7 FOWPI Wind Turbine Layout and AEP. FOWPI EU Supported project
8 New Technology Catalogue with offshore wind data DEA Denmark Collaboration
Present Status
The following studies are going on through various bilateral/multilateral cooperation
projects and in coordination with other departments/authorities;
• Port & Logistics
• Grid & Transmission
• Updated Supply Chain
• Marine Spatial Planning
 The concept note for a viable gap funding has been prepared for MoF.
 Offshore wind energy lease rules for regulating sea bed allocation is under preparation.
A offshore wind test cum research centre & Greening of Rameswaram has been planned
at Dhanuskodi for which preliminary activities along with DPR preparation is under
preparation.
The drafting of contractual documents required such as Lease agreement,
implementation agreement, concessionaire agreement, connectivity agreement etc. ,is
under preparation.
12
Offshore Wind Energy Test cum Research Facility
13
 To Establish India’s first offshore wind demonstration facility
 To create a research facility for carrying out following activities;
 Developing India specific offshore wind turbines
 Component development
 Grid synchronization
 Performance Assessment
 Optimization O&M
 To create a offshore wind test facility for;
 Testing of new offshore wind turbine developed by Turbine manufacturers
 Testing of any new components by component manufactures
 1st of its kind in Asia Pacific region – Shall act as Test ecntre serving the requirements of entire Asia
Pacific Region
 To provide RE power to the Rameshwaram city to make it India’s first Green City powered by 100% RE.
 To create a training facility for offshore wind sector
 Project shall consist of Installation of :
 2 X 8 MW Wind Turbine Generators
 1 MW AC Solar PV Ground Mounted Capacity
 Additional Two nos of universal wind turbine foundations to be provided for testing of
new turbines.
 The power generated from the proposed Wind project & Solar PV Project to be
supplied for making the Rameswaram city green.
 Revenue generated to be utilized for maintenance of the project & associated R & D
activities
 Necessary support to be provided by MNRE for establishing the facility.
14
Project Features
RAMESHWARAM ISLAND LOAD & OFFSHORE PLANT GENERATION
15
RAMESHWARAM ISLAND LOAD
 At present the load at Rameshwaram is
served through 16 MVA(2*8MVA) 33/11kV
sub-station connected to Mandapam
substation of main land.
 Total annual energy consumption of
Rameshwaram: 33.208 million units (data
collected for the period March 2021 to
Feb 2022)
PLF OF PROPOSED PLANT
 Annual Power Generation from the proposed hybrid power plant: 52.2 GWh/year
 Average PLF of offshore turbines expected to be around 35.3% considering existing class of European design wind
turbine of higher specific power. (49.47 GWh/year)
 1MW solar plant it is expected generation of 1.689 GWh/year
29-06-2022 MNRE | OFFSHORE WIND | April 2022
PROJECT LOCATION (DHANUSKODI)
16
• The Project Site is 25 Kms from Rameshwaram city
(birthplace of India's renowned scientist and former
President of India, A. P. J. Abdul Kalam).
• Rameshwaram is well connected by Road & Railway
• Test site situated on the shoreline and surrounded
by shallow seawater in three directions.
SITE FEATURES
17
Wind conditions 8.36 m/sec (at 102 m AGL), 6 % Turbulence
Intensity (at 15 m/sec)
Sufficient space for the test
site, including wind field, test
area
75 acres of land leased by the State
Government (Tamil Nadu)
Good infrastructure such as
roads, bridges, harbor, power
lines
Tuticorin Port – 200 Km distance (by Road).
Around 130 km by Sea route
Study on Strengthening of Roads, Bridges
for transportation of WT Components needs
to be carried out.
Closeness to promising
offshore sites, where access
to harbors is important
Access to skilled workforce Available (Nearest Cities: Madurai, Tuticorin
& Tirunelveli) – 200 km
Minimum interference in
nature and environment
No interference expected
Minimum impact on
neighbouring households
Rameshwaram is nearest Town and located
25 Km from the Site
WIND CONDITIONS AT DHANUSKODI
18
• 8.36 m/sec (at 102 m AGL)
• 6 % Turbulence Intensity (at
15 m/sec)
• Power Law Index – 0.0432
• Global titled irradiation is
2112 kwh/m^2.
RAMESHWARAM ISLAND LOAD & OFFSHORE PLANT GENERATION
19
RAMESHWARAM ISLAND LOAD
 At present the load at Rameshwaram is
served through 16 MVA(2*8MVA) 33/11kV
sub-station connected to Mandapam
substation of main land.
 Total annual energy consumption of
Rameshwaram: 33.208 million units (data
collected for the period March 2021 to
Feb 2022)
PLF OF PROPOSED PLANT
 Annual Power Generation from the proposed hybrid power plant: 52.2 GWh/year
 Average PLF of offshore turbines expected to be around 35.3% considering existing class of European design wind
turbine of higher specific power. (49.47 GWh/year)
 1MW solar plant it is expected generation of 1.689 GWh/year
Thank You
6/29/2022 MNRE | OFFSHORE | March 2022 20

More Related Content

What's hot

Wind Energy ppt
Wind Energy pptWind Energy ppt
Wind Energy ppt
tabi5
 
Future of solar Power Projects in India
Future of solar Power Projects in IndiaFuture of solar Power Projects in India
Future of solar Power Projects in India
Harish Sharma
 
Wind power in india
Wind power in indiaWind power in india
Wind power in india
VinodKumar Reddy A
 
Renewable energy potential for india
Renewable energy potential for indiaRenewable energy potential for india
Renewable energy potential for indiaRajkumar Viral
 
Wind energy
Wind energyWind energy
Wind energy
chaitanyanvvk
 
Feasibility of Solar Project with Open Access in Maharashtra
Feasibility of Solar Project with Open Access in Maharashtra Feasibility of Solar Project with Open Access in Maharashtra
Feasibility of Solar Project with Open Access in Maharashtra
Gensol Engineering Limited
 
Wind Energy Presentation 2003
Wind Energy Presentation 2003Wind Energy Presentation 2003
Wind Energy Presentation 2003guest9122ca
 
Presentation by MNRE on Solar Parks
Presentation by MNRE on Solar ParksPresentation by MNRE on Solar Parks
Presentation by MNRE on Solar Parks
Gensol Engineering Limited
 
Future of wind energy in india
Future of wind energy in indiaFuture of wind energy in india
Future of wind energy in india
Manoj Bhambu
 
HYPHEN: First gigawatt-scale green ammonia project in Namibia - Marco Raffine...
HYPHEN: First gigawatt-scale green ammonia project in Namibia - Marco Raffine...HYPHEN: First gigawatt-scale green ammonia project in Namibia - Marco Raffine...
HYPHEN: First gigawatt-scale green ammonia project in Namibia - Marco Raffine...
OECD Environment
 
Wind Energy Project Analysis
Wind Energy Project AnalysisWind Energy Project Analysis
Wind Energy Project AnalysisLeonardo ENERGY
 
OFFSHORE WIND ENERGY
OFFSHORE WIND ENERGYOFFSHORE WIND ENERGY
OFFSHORE WIND ENERGY
Madan Singh
 
Power point presentation on Nuclear Power in India
Power point presentation on Nuclear Power in IndiaPower point presentation on Nuclear Power in India
Power point presentation on Nuclear Power in India
MoniSarker
 
Offshore wind energy in India Overview
Offshore wind energy in India OverviewOffshore wind energy in India Overview
Offshore wind energy in India Overview
ShantanuBHG
 
Introduction to Wind Energy
Introduction to Wind EnergyIntroduction to Wind Energy
Introduction to Wind Energy
Mohammad Tawfik
 
Renewable Energy Sources
Renewable Energy SourcesRenewable Energy Sources
Renewable Energy Sources
Dr. Rjaendra Singh Thakur
 
Power sector in India
Power sector in IndiaPower sector in India
Power sector in India
Daya Kherwar
 
Wind Energy Power Point Presentation
Wind Energy Power Point PresentationWind Energy Power Point Presentation
Wind Energy Power Point Presentation
rclassic
 
Unit i solar radiation; its measurement
Unit  i solar radiation; its measurementUnit  i solar radiation; its measurement
Unit i solar radiation; its measurement
MadhuriPawar37
 
Renewable energy in India: Present Status and Policy
Renewable energy in India: Present Status and PolicyRenewable energy in India: Present Status and Policy
Renewable energy in India: Present Status and Policy
Malik Sameeullah
 

What's hot (20)

Wind Energy ppt
Wind Energy pptWind Energy ppt
Wind Energy ppt
 
Future of solar Power Projects in India
Future of solar Power Projects in IndiaFuture of solar Power Projects in India
Future of solar Power Projects in India
 
Wind power in india
Wind power in indiaWind power in india
Wind power in india
 
Renewable energy potential for india
Renewable energy potential for indiaRenewable energy potential for india
Renewable energy potential for india
 
Wind energy
Wind energyWind energy
Wind energy
 
Feasibility of Solar Project with Open Access in Maharashtra
Feasibility of Solar Project with Open Access in Maharashtra Feasibility of Solar Project with Open Access in Maharashtra
Feasibility of Solar Project with Open Access in Maharashtra
 
Wind Energy Presentation 2003
Wind Energy Presentation 2003Wind Energy Presentation 2003
Wind Energy Presentation 2003
 
Presentation by MNRE on Solar Parks
Presentation by MNRE on Solar ParksPresentation by MNRE on Solar Parks
Presentation by MNRE on Solar Parks
 
Future of wind energy in india
Future of wind energy in indiaFuture of wind energy in india
Future of wind energy in india
 
HYPHEN: First gigawatt-scale green ammonia project in Namibia - Marco Raffine...
HYPHEN: First gigawatt-scale green ammonia project in Namibia - Marco Raffine...HYPHEN: First gigawatt-scale green ammonia project in Namibia - Marco Raffine...
HYPHEN: First gigawatt-scale green ammonia project in Namibia - Marco Raffine...
 
Wind Energy Project Analysis
Wind Energy Project AnalysisWind Energy Project Analysis
Wind Energy Project Analysis
 
OFFSHORE WIND ENERGY
OFFSHORE WIND ENERGYOFFSHORE WIND ENERGY
OFFSHORE WIND ENERGY
 
Power point presentation on Nuclear Power in India
Power point presentation on Nuclear Power in IndiaPower point presentation on Nuclear Power in India
Power point presentation on Nuclear Power in India
 
Offshore wind energy in India Overview
Offshore wind energy in India OverviewOffshore wind energy in India Overview
Offshore wind energy in India Overview
 
Introduction to Wind Energy
Introduction to Wind EnergyIntroduction to Wind Energy
Introduction to Wind Energy
 
Renewable Energy Sources
Renewable Energy SourcesRenewable Energy Sources
Renewable Energy Sources
 
Power sector in India
Power sector in IndiaPower sector in India
Power sector in India
 
Wind Energy Power Point Presentation
Wind Energy Power Point PresentationWind Energy Power Point Presentation
Wind Energy Power Point Presentation
 
Unit i solar radiation; its measurement
Unit  i solar radiation; its measurementUnit  i solar radiation; its measurement
Unit i solar radiation; its measurement
 
Renewable energy in India: Present Status and Policy
Renewable energy in India: Present Status and PolicyRenewable energy in India: Present Status and Policy
Renewable energy in India: Present Status and Policy
 

Similar to Offshore wind energy Development in India, MNRE, Government of India

offshore.pptx
offshore.pptxoffshore.pptx
offshore.pptx
ssuser8f8879
 
offshore wind energy in India
offshore wind energy in India offshore wind energy in India
offshore wind energy in India
RitanshaKanwarNathaw
 
Boo wind power in egypt
Boo wind power in egyptBoo wind power in egypt
Boo wind power in egypt
RCREEE
 
Wind power in India
Wind power in India Wind power in India
Wind power in India
amananand003
 
Draft explanatory-memorandum solar-power-projects
Draft explanatory-memorandum solar-power-projectsDraft explanatory-memorandum solar-power-projects
Draft explanatory-memorandum solar-power-projectsSanman Rajput
 
Small Power Generation Plant
Small Power Generation PlantSmall Power Generation Plant
Small Power Generation Plant
Craig Abednego Malone
 
MARG-OPENACCESS-INVESTOR
MARG-OPENACCESS-INVESTORMARG-OPENACCESS-INVESTOR
MARG-OPENACCESS-INVESTORRanbir Ghosh
 
OSW ambitions in the Philippines and what it will take to build the first few...
OSW ambitions in the Philippines and what it will take to build the first few...OSW ambitions in the Philippines and what it will take to build the first few...
OSW ambitions in the Philippines and what it will take to build the first few...
OECD Environment
 
Renewable energy projects in jordan
Renewable energy projects in jordanRenewable energy projects in jordan
Renewable energy projects in jordan
RCREEE
 
Ultra mega power projects
Ultra mega power projectsUltra mega power projects
Ultra mega power projects
shivraj negi
 
Draft guidelines-of-2000 mw-vgf-scheme
Draft guidelines-of-2000 mw-vgf-schemeDraft guidelines-of-2000 mw-vgf-scheme
Draft guidelines-of-2000 mw-vgf-schemeSanman Rajput
 
Draft guidelines-of-2000 mw-vgf-scheme
Draft guidelines-of-2000 mw-vgf-schemeDraft guidelines-of-2000 mw-vgf-scheme
Draft guidelines-of-2000 mw-vgf-schemeSanman Rajput
 
RfS for 35 MW in Puducherry under NSM Ph-II, Batch-III
RfS for 35 MW in Puducherry under NSM Ph-II, Batch-IIIRfS for 35 MW in Puducherry under NSM Ph-II, Batch-III
RfS for 35 MW in Puducherry under NSM Ph-II, Batch-III
Harish Sharma
 
Overview of the energy sector in zambia case of renewable energy
Overview of the energy sector in zambia   case of renewable energyOverview of the energy sector in zambia   case of renewable energy
Overview of the energy sector in zambia case of renewable energy
Jerry Sakala
 
Overview of solar power generation in india
Overview of solar power generation in indiaOverview of solar power generation in india
Overview of solar power generation in india
Binit Das
 
Session 2 Dr Ziad Jibril Sabra, Jordan
Session 2 Dr Ziad Jibril Sabra, JordanSession 2 Dr Ziad Jibril Sabra, Jordan
Session 2 Dr Ziad Jibril Sabra, Jordan
OECDGlobalRelations
 
Breakout_Infrastructure of nuclear power plant
Breakout_Infrastructure of nuclear power plantBreakout_Infrastructure of nuclear power plant
Breakout_Infrastructure of nuclear power plant
hasansust20
 
Techno-Economic Feasibility Study to Install 30 MW Grid-connected Wind Farms ...
Techno-Economic Feasibility Study to Install 30 MW Grid-connected Wind Farms ...Techno-Economic Feasibility Study to Install 30 MW Grid-connected Wind Farms ...
Techno-Economic Feasibility Study to Install 30 MW Grid-connected Wind Farms ...
IRJET Journal
 
Jaitapur nuclear power plant ppt
Jaitapur nuclear power plant pptJaitapur nuclear power plant ppt
Jaitapur nuclear power plant pptNikita Bhinde
 

Similar to Offshore wind energy Development in India, MNRE, Government of India (20)

offshore.pptx
offshore.pptxoffshore.pptx
offshore.pptx
 
Wind sector brief
Wind sector briefWind sector brief
Wind sector brief
 
offshore wind energy in India
offshore wind energy in India offshore wind energy in India
offshore wind energy in India
 
Boo wind power in egypt
Boo wind power in egyptBoo wind power in egypt
Boo wind power in egypt
 
Wind power in India
Wind power in India Wind power in India
Wind power in India
 
Draft explanatory-memorandum solar-power-projects
Draft explanatory-memorandum solar-power-projectsDraft explanatory-memorandum solar-power-projects
Draft explanatory-memorandum solar-power-projects
 
Small Power Generation Plant
Small Power Generation PlantSmall Power Generation Plant
Small Power Generation Plant
 
MARG-OPENACCESS-INVESTOR
MARG-OPENACCESS-INVESTORMARG-OPENACCESS-INVESTOR
MARG-OPENACCESS-INVESTOR
 
OSW ambitions in the Philippines and what it will take to build the first few...
OSW ambitions in the Philippines and what it will take to build the first few...OSW ambitions in the Philippines and what it will take to build the first few...
OSW ambitions in the Philippines and what it will take to build the first few...
 
Renewable energy projects in jordan
Renewable energy projects in jordanRenewable energy projects in jordan
Renewable energy projects in jordan
 
Ultra mega power projects
Ultra mega power projectsUltra mega power projects
Ultra mega power projects
 
Draft guidelines-of-2000 mw-vgf-scheme
Draft guidelines-of-2000 mw-vgf-schemeDraft guidelines-of-2000 mw-vgf-scheme
Draft guidelines-of-2000 mw-vgf-scheme
 
Draft guidelines-of-2000 mw-vgf-scheme
Draft guidelines-of-2000 mw-vgf-schemeDraft guidelines-of-2000 mw-vgf-scheme
Draft guidelines-of-2000 mw-vgf-scheme
 
RfS for 35 MW in Puducherry under NSM Ph-II, Batch-III
RfS for 35 MW in Puducherry under NSM Ph-II, Batch-IIIRfS for 35 MW in Puducherry under NSM Ph-II, Batch-III
RfS for 35 MW in Puducherry under NSM Ph-II, Batch-III
 
Overview of the energy sector in zambia case of renewable energy
Overview of the energy sector in zambia   case of renewable energyOverview of the energy sector in zambia   case of renewable energy
Overview of the energy sector in zambia case of renewable energy
 
Overview of solar power generation in india
Overview of solar power generation in indiaOverview of solar power generation in india
Overview of solar power generation in india
 
Session 2 Dr Ziad Jibril Sabra, Jordan
Session 2 Dr Ziad Jibril Sabra, JordanSession 2 Dr Ziad Jibril Sabra, Jordan
Session 2 Dr Ziad Jibril Sabra, Jordan
 
Breakout_Infrastructure of nuclear power plant
Breakout_Infrastructure of nuclear power plantBreakout_Infrastructure of nuclear power plant
Breakout_Infrastructure of nuclear power plant
 
Techno-Economic Feasibility Study to Install 30 MW Grid-connected Wind Farms ...
Techno-Economic Feasibility Study to Install 30 MW Grid-connected Wind Farms ...Techno-Economic Feasibility Study to Install 30 MW Grid-connected Wind Farms ...
Techno-Economic Feasibility Study to Install 30 MW Grid-connected Wind Farms ...
 
Jaitapur nuclear power plant ppt
Jaitapur nuclear power plant pptJaitapur nuclear power plant ppt
Jaitapur nuclear power plant ppt
 

More from OECD Environment

OECD Green Talks LIVE | Diving deeper: the evolving landscape for assessing w...
OECD Green Talks LIVE | Diving deeper: the evolving landscape for assessing w...OECD Green Talks LIVE | Diving deeper: the evolving landscape for assessing w...
OECD Green Talks LIVE | Diving deeper: the evolving landscape for assessing w...
OECD Environment
 
Detlef Van Vuuren- Integrated modelling for interrelated crises.pdf
Detlef Van Vuuren- Integrated modelling for interrelated crises.pdfDetlef Van Vuuren- Integrated modelling for interrelated crises.pdf
Detlef Van Vuuren- Integrated modelling for interrelated crises.pdf
OECD Environment
 
Thomas Hertel- Integrated Policies for the Triple Planetary Crisis.pdf
Thomas Hertel- Integrated Policies for the Triple Planetary Crisis.pdfThomas Hertel- Integrated Policies for the Triple Planetary Crisis.pdf
Thomas Hertel- Integrated Policies for the Triple Planetary Crisis.pdf
OECD Environment
 
Jon Sampedro - Assessing synergies and trade offs for health and sustainable ...
Jon Sampedro - Assessing synergies and trade offs for health and sustainable ...Jon Sampedro - Assessing synergies and trade offs for health and sustainable ...
Jon Sampedro - Assessing synergies and trade offs for health and sustainable ...
OECD Environment
 
Astrid Bos - Identifying trade offs & searching for synergies.pdf
Astrid Bos - Identifying trade offs & searching for synergies.pdfAstrid Bos - Identifying trade offs & searching for synergies.pdf
Astrid Bos - Identifying trade offs & searching for synergies.pdf
OECD Environment
 
Ruth Delzeit - Modelling environmental and socio-economic impacts of cropland...
Ruth Delzeit - Modelling environmental and socio-economic impacts of cropland...Ruth Delzeit - Modelling environmental and socio-economic impacts of cropland...
Ruth Delzeit - Modelling environmental and socio-economic impacts of cropland...
OECD Environment
 
Wilfried Winiwarter - Implementing nitrogen pollution control pathways in the...
Wilfried Winiwarter - Implementing nitrogen pollution control pathways in the...Wilfried Winiwarter - Implementing nitrogen pollution control pathways in the...
Wilfried Winiwarter - Implementing nitrogen pollution control pathways in the...
OECD Environment
 
Laurent Drouet - Physical and Economic Risks of Climate Change.pdf
Laurent Drouet - Physical and Economic Risks of Climate Change.pdfLaurent Drouet - Physical and Economic Risks of Climate Change.pdf
Laurent Drouet - Physical and Economic Risks of Climate Change.pdf
OECD Environment
 
Shinichiro Fujimori - Biodiversity modeling in AIM (Asia pacific Integrated M...
Shinichiro Fujimori - Biodiversity modeling in AIM (Asia pacific Integrated M...Shinichiro Fujimori - Biodiversity modeling in AIM (Asia pacific Integrated M...
Shinichiro Fujimori - Biodiversity modeling in AIM (Asia pacific Integrated M...
OECD Environment
 
HyeJin Kim and Simon Smart - The biodiversity nexus across multiple drivers: ...
HyeJin Kim and Simon Smart - The biodiversity nexus across multiple drivers: ...HyeJin Kim and Simon Smart - The biodiversity nexus across multiple drivers: ...
HyeJin Kim and Simon Smart - The biodiversity nexus across multiple drivers: ...
OECD Environment
 
GREEN Action Task Force - Full Presentations.pdf
GREEN Action Task Force - Full Presentations.pdfGREEN Action Task Force - Full Presentations.pdf
GREEN Action Task Force - Full Presentations.pdf
OECD Environment
 
Case Study: Peptides-based Plant Protection Product (harpin proteins*) by Ros...
Case Study: Peptides-based Plant Protection Product (harpin proteins*) by Ros...Case Study: Peptides-based Plant Protection Product (harpin proteins*) by Ros...
Case Study: Peptides-based Plant Protection Product (harpin proteins*) by Ros...
OECD Environment
 
CLE Contribution on the Assessment of Innovative Biochemicals in the EU Statu...
CLE Contribution on the Assessment of Innovative Biochemicals in the EU Statu...CLE Contribution on the Assessment of Innovative Biochemicals in the EU Statu...
CLE Contribution on the Assessment of Innovative Biochemicals in the EU Statu...
OECD Environment
 
Additional Considerations for Pesticide Formulations Containing Microbial Pes...
Additional Considerations for Pesticide Formulations Containing Microbial Pes...Additional Considerations for Pesticide Formulations Containing Microbial Pes...
Additional Considerations for Pesticide Formulations Containing Microbial Pes...
OECD Environment
 
Role of genome sequencing (WGS) in microbial biopesticides safety assessment ...
Role of genome sequencing (WGS) in microbial biopesticides safety assessment ...Role of genome sequencing (WGS) in microbial biopesticides safety assessment ...
Role of genome sequencing (WGS) in microbial biopesticides safety assessment ...
OECD Environment
 
Considerations for Problem Formulation for Human Health Safety Assessments of...
Considerations for Problem Formulation for Human Health Safety Assessments of...Considerations for Problem Formulation for Human Health Safety Assessments of...
Considerations for Problem Formulation for Human Health Safety Assessments of...
OECD Environment
 
How to Identify and Quantify Mixtures What is Essential to Know for Risk Asse...
How to Identify and Quantify Mixtures What is Essential to Know for Risk Asse...How to Identify and Quantify Mixtures What is Essential to Know for Risk Asse...
How to Identify and Quantify Mixtures What is Essential to Know for Risk Asse...
OECD Environment
 
APVMA outcome-focussed approach to data requirements to support registration ...
APVMA outcome-focussed approach to data requirements to support registration ...APVMA outcome-focussed approach to data requirements to support registration ...
APVMA outcome-focussed approach to data requirements to support registration ...
OECD Environment
 
The U.S. Perspective on Problem Formulation for Biopesticides: Shannon BORGES
The U.S. Perspective on Problem Formulation for Biopesticides: Shannon BORGESThe U.S. Perspective on Problem Formulation for Biopesticides: Shannon BORGES
The U.S. Perspective on Problem Formulation for Biopesticides: Shannon BORGES
OECD Environment
 
Problem formulation for environmental risk assessment – Finnish case study: ...
Problem formulation for environmental risk assessment – Finnish case study:  ...Problem formulation for environmental risk assessment – Finnish case study:  ...
Problem formulation for environmental risk assessment – Finnish case study: ...
OECD Environment
 

More from OECD Environment (20)

OECD Green Talks LIVE | Diving deeper: the evolving landscape for assessing w...
OECD Green Talks LIVE | Diving deeper: the evolving landscape for assessing w...OECD Green Talks LIVE | Diving deeper: the evolving landscape for assessing w...
OECD Green Talks LIVE | Diving deeper: the evolving landscape for assessing w...
 
Detlef Van Vuuren- Integrated modelling for interrelated crises.pdf
Detlef Van Vuuren- Integrated modelling for interrelated crises.pdfDetlef Van Vuuren- Integrated modelling for interrelated crises.pdf
Detlef Van Vuuren- Integrated modelling for interrelated crises.pdf
 
Thomas Hertel- Integrated Policies for the Triple Planetary Crisis.pdf
Thomas Hertel- Integrated Policies for the Triple Planetary Crisis.pdfThomas Hertel- Integrated Policies for the Triple Planetary Crisis.pdf
Thomas Hertel- Integrated Policies for the Triple Planetary Crisis.pdf
 
Jon Sampedro - Assessing synergies and trade offs for health and sustainable ...
Jon Sampedro - Assessing synergies and trade offs for health and sustainable ...Jon Sampedro - Assessing synergies and trade offs for health and sustainable ...
Jon Sampedro - Assessing synergies and trade offs for health and sustainable ...
 
Astrid Bos - Identifying trade offs & searching for synergies.pdf
Astrid Bos - Identifying trade offs & searching for synergies.pdfAstrid Bos - Identifying trade offs & searching for synergies.pdf
Astrid Bos - Identifying trade offs & searching for synergies.pdf
 
Ruth Delzeit - Modelling environmental and socio-economic impacts of cropland...
Ruth Delzeit - Modelling environmental and socio-economic impacts of cropland...Ruth Delzeit - Modelling environmental and socio-economic impacts of cropland...
Ruth Delzeit - Modelling environmental and socio-economic impacts of cropland...
 
Wilfried Winiwarter - Implementing nitrogen pollution control pathways in the...
Wilfried Winiwarter - Implementing nitrogen pollution control pathways in the...Wilfried Winiwarter - Implementing nitrogen pollution control pathways in the...
Wilfried Winiwarter - Implementing nitrogen pollution control pathways in the...
 
Laurent Drouet - Physical and Economic Risks of Climate Change.pdf
Laurent Drouet - Physical and Economic Risks of Climate Change.pdfLaurent Drouet - Physical and Economic Risks of Climate Change.pdf
Laurent Drouet - Physical and Economic Risks of Climate Change.pdf
 
Shinichiro Fujimori - Biodiversity modeling in AIM (Asia pacific Integrated M...
Shinichiro Fujimori - Biodiversity modeling in AIM (Asia pacific Integrated M...Shinichiro Fujimori - Biodiversity modeling in AIM (Asia pacific Integrated M...
Shinichiro Fujimori - Biodiversity modeling in AIM (Asia pacific Integrated M...
 
HyeJin Kim and Simon Smart - The biodiversity nexus across multiple drivers: ...
HyeJin Kim and Simon Smart - The biodiversity nexus across multiple drivers: ...HyeJin Kim and Simon Smart - The biodiversity nexus across multiple drivers: ...
HyeJin Kim and Simon Smart - The biodiversity nexus across multiple drivers: ...
 
GREEN Action Task Force - Full Presentations.pdf
GREEN Action Task Force - Full Presentations.pdfGREEN Action Task Force - Full Presentations.pdf
GREEN Action Task Force - Full Presentations.pdf
 
Case Study: Peptides-based Plant Protection Product (harpin proteins*) by Ros...
Case Study: Peptides-based Plant Protection Product (harpin proteins*) by Ros...Case Study: Peptides-based Plant Protection Product (harpin proteins*) by Ros...
Case Study: Peptides-based Plant Protection Product (harpin proteins*) by Ros...
 
CLE Contribution on the Assessment of Innovative Biochemicals in the EU Statu...
CLE Contribution on the Assessment of Innovative Biochemicals in the EU Statu...CLE Contribution on the Assessment of Innovative Biochemicals in the EU Statu...
CLE Contribution on the Assessment of Innovative Biochemicals in the EU Statu...
 
Additional Considerations for Pesticide Formulations Containing Microbial Pes...
Additional Considerations for Pesticide Formulations Containing Microbial Pes...Additional Considerations for Pesticide Formulations Containing Microbial Pes...
Additional Considerations for Pesticide Formulations Containing Microbial Pes...
 
Role of genome sequencing (WGS) in microbial biopesticides safety assessment ...
Role of genome sequencing (WGS) in microbial biopesticides safety assessment ...Role of genome sequencing (WGS) in microbial biopesticides safety assessment ...
Role of genome sequencing (WGS) in microbial biopesticides safety assessment ...
 
Considerations for Problem Formulation for Human Health Safety Assessments of...
Considerations for Problem Formulation for Human Health Safety Assessments of...Considerations for Problem Formulation for Human Health Safety Assessments of...
Considerations for Problem Formulation for Human Health Safety Assessments of...
 
How to Identify and Quantify Mixtures What is Essential to Know for Risk Asse...
How to Identify and Quantify Mixtures What is Essential to Know for Risk Asse...How to Identify and Quantify Mixtures What is Essential to Know for Risk Asse...
How to Identify and Quantify Mixtures What is Essential to Know for Risk Asse...
 
APVMA outcome-focussed approach to data requirements to support registration ...
APVMA outcome-focussed approach to data requirements to support registration ...APVMA outcome-focussed approach to data requirements to support registration ...
APVMA outcome-focussed approach to data requirements to support registration ...
 
The U.S. Perspective on Problem Formulation for Biopesticides: Shannon BORGES
The U.S. Perspective on Problem Formulation for Biopesticides: Shannon BORGESThe U.S. Perspective on Problem Formulation for Biopesticides: Shannon BORGES
The U.S. Perspective on Problem Formulation for Biopesticides: Shannon BORGES
 
Problem formulation for environmental risk assessment – Finnish case study: ...
Problem formulation for environmental risk assessment – Finnish case study:  ...Problem formulation for environmental risk assessment – Finnish case study:  ...
Problem formulation for environmental risk assessment – Finnish case study: ...
 

Recently uploaded

Alert-driven Community-based Forest monitoring: A case of the Peruvian Amazon
Alert-driven Community-based Forest monitoring: A case of the Peruvian AmazonAlert-driven Community-based Forest monitoring: A case of the Peruvian Amazon
Alert-driven Community-based Forest monitoring: A case of the Peruvian Amazon
CIFOR-ICRAF
 
NRW Board Paper - DRAFT NRW Recreation Strategy
NRW Board Paper - DRAFT NRW Recreation StrategyNRW Board Paper - DRAFT NRW Recreation Strategy
NRW Board Paper - DRAFT NRW Recreation Strategy
Robin Grant
 
Natural farming @ Dr. Siddhartha S. Jena.pptx
Natural farming @ Dr. Siddhartha S. Jena.pptxNatural farming @ Dr. Siddhartha S. Jena.pptx
Natural farming @ Dr. Siddhartha S. Jena.pptx
sidjena70
 
Daan Park Hydrangea flower season I like it
Daan Park Hydrangea flower season I like itDaan Park Hydrangea flower season I like it
Daan Park Hydrangea flower season I like it
a0966109726
 
Micro RNA genes and their likely influence in rice (Oryza sativa L.) dynamic ...
Micro RNA genes and their likely influence in rice (Oryza sativa L.) dynamic ...Micro RNA genes and their likely influence in rice (Oryza sativa L.) dynamic ...
Micro RNA genes and their likely influence in rice (Oryza sativa L.) dynamic ...
Open Access Research Paper
 
growbilliontrees.com-Trees for Granddaughter (1).pdf
growbilliontrees.com-Trees for Granddaughter (1).pdfgrowbilliontrees.com-Trees for Granddaughter (1).pdf
growbilliontrees.com-Trees for Granddaughter (1).pdf
yadavakashagra
 
Environmental Science Book By Dr. Y.K. Singh
Environmental Science Book By Dr. Y.K. SinghEnvironmental Science Book By Dr. Y.K. Singh
Environmental Science Book By Dr. Y.K. Singh
AhmadKhan917612
 
Q&A with the Experts: The Food Service Playbook
Q&A with the Experts: The Food Service PlaybookQ&A with the Experts: The Food Service Playbook
Q&A with the Experts: The Food Service Playbook
World Resources Institute (WRI)
 
"Understanding the Carbon Cycle: Processes, Human Impacts, and Strategies for...
"Understanding the Carbon Cycle: Processes, Human Impacts, and Strategies for..."Understanding the Carbon Cycle: Processes, Human Impacts, and Strategies for...
"Understanding the Carbon Cycle: Processes, Human Impacts, and Strategies for...
MMariSelvam4
 
DRAFT NRW Recreation Strategy - People and Nature thriving together
DRAFT NRW Recreation Strategy - People and Nature thriving togetherDRAFT NRW Recreation Strategy - People and Nature thriving together
DRAFT NRW Recreation Strategy - People and Nature thriving together
Robin Grant
 
Characterization and the Kinetics of drying at the drying oven and with micro...
Characterization and the Kinetics of drying at the drying oven and with micro...Characterization and the Kinetics of drying at the drying oven and with micro...
Characterization and the Kinetics of drying at the drying oven and with micro...
Open Access Research Paper
 
UNDERSTANDING WHAT GREEN WASHING IS!.pdf
UNDERSTANDING WHAT GREEN WASHING IS!.pdfUNDERSTANDING WHAT GREEN WASHING IS!.pdf
UNDERSTANDING WHAT GREEN WASHING IS!.pdf
JulietMogola
 
Presentación Giulio Quaggiotto-Diálogo improbable .pptx.pdf
Presentación Giulio Quaggiotto-Diálogo improbable .pptx.pdfPresentación Giulio Quaggiotto-Diálogo improbable .pptx.pdf
Presentación Giulio Quaggiotto-Diálogo improbable .pptx.pdf
Innovation and Technology for Development Centre
 
AGRICULTURE Hydrophonic FERTILISER PPT.pptx
AGRICULTURE Hydrophonic FERTILISER PPT.pptxAGRICULTURE Hydrophonic FERTILISER PPT.pptx
AGRICULTURE Hydrophonic FERTILISER PPT.pptx
BanitaDsouza
 
Prevalence, biochemical and hematological study of diabetic patients
Prevalence, biochemical and hematological study of diabetic patientsPrevalence, biochemical and hematological study of diabetic patients
Prevalence, biochemical and hematological study of diabetic patients
Open Access Research Paper
 
IPCC Vice Chair Ladislaus Change Central Asia Climate Change Conference 27 Ma...
IPCC Vice Chair Ladislaus Change Central Asia Climate Change Conference 27 Ma...IPCC Vice Chair Ladislaus Change Central Asia Climate Change Conference 27 Ma...
IPCC Vice Chair Ladislaus Change Central Asia Climate Change Conference 27 Ma...
ipcc-media
 
Artificial Reefs by Kuddle Life Foundation - May 2024
Artificial Reefs by Kuddle Life Foundation - May 2024Artificial Reefs by Kuddle Life Foundation - May 2024
Artificial Reefs by Kuddle Life Foundation - May 2024
punit537210
 
Celebrating World-environment-day-2024.pdf
Celebrating  World-environment-day-2024.pdfCelebrating  World-environment-day-2024.pdf
Celebrating World-environment-day-2024.pdf
rohankumarsinghrore1
 
Sustainable farming practices in India .pptx
Sustainable farming  practices in India .pptxSustainable farming  practices in India .pptx
Sustainable farming practices in India .pptx
chaitaliambole
 
Bhopal Gas Leak Tragedy - A Night of death
Bhopal Gas Leak Tragedy - A Night of deathBhopal Gas Leak Tragedy - A Night of death
Bhopal Gas Leak Tragedy - A Night of death
upasana742003
 

Recently uploaded (20)

Alert-driven Community-based Forest monitoring: A case of the Peruvian Amazon
Alert-driven Community-based Forest monitoring: A case of the Peruvian AmazonAlert-driven Community-based Forest monitoring: A case of the Peruvian Amazon
Alert-driven Community-based Forest monitoring: A case of the Peruvian Amazon
 
NRW Board Paper - DRAFT NRW Recreation Strategy
NRW Board Paper - DRAFT NRW Recreation StrategyNRW Board Paper - DRAFT NRW Recreation Strategy
NRW Board Paper - DRAFT NRW Recreation Strategy
 
Natural farming @ Dr. Siddhartha S. Jena.pptx
Natural farming @ Dr. Siddhartha S. Jena.pptxNatural farming @ Dr. Siddhartha S. Jena.pptx
Natural farming @ Dr. Siddhartha S. Jena.pptx
 
Daan Park Hydrangea flower season I like it
Daan Park Hydrangea flower season I like itDaan Park Hydrangea flower season I like it
Daan Park Hydrangea flower season I like it
 
Micro RNA genes and their likely influence in rice (Oryza sativa L.) dynamic ...
Micro RNA genes and their likely influence in rice (Oryza sativa L.) dynamic ...Micro RNA genes and their likely influence in rice (Oryza sativa L.) dynamic ...
Micro RNA genes and their likely influence in rice (Oryza sativa L.) dynamic ...
 
growbilliontrees.com-Trees for Granddaughter (1).pdf
growbilliontrees.com-Trees for Granddaughter (1).pdfgrowbilliontrees.com-Trees for Granddaughter (1).pdf
growbilliontrees.com-Trees for Granddaughter (1).pdf
 
Environmental Science Book By Dr. Y.K. Singh
Environmental Science Book By Dr. Y.K. SinghEnvironmental Science Book By Dr. Y.K. Singh
Environmental Science Book By Dr. Y.K. Singh
 
Q&A with the Experts: The Food Service Playbook
Q&A with the Experts: The Food Service PlaybookQ&A with the Experts: The Food Service Playbook
Q&A with the Experts: The Food Service Playbook
 
"Understanding the Carbon Cycle: Processes, Human Impacts, and Strategies for...
"Understanding the Carbon Cycle: Processes, Human Impacts, and Strategies for..."Understanding the Carbon Cycle: Processes, Human Impacts, and Strategies for...
"Understanding the Carbon Cycle: Processes, Human Impacts, and Strategies for...
 
DRAFT NRW Recreation Strategy - People and Nature thriving together
DRAFT NRW Recreation Strategy - People and Nature thriving togetherDRAFT NRW Recreation Strategy - People and Nature thriving together
DRAFT NRW Recreation Strategy - People and Nature thriving together
 
Characterization and the Kinetics of drying at the drying oven and with micro...
Characterization and the Kinetics of drying at the drying oven and with micro...Characterization and the Kinetics of drying at the drying oven and with micro...
Characterization and the Kinetics of drying at the drying oven and with micro...
 
UNDERSTANDING WHAT GREEN WASHING IS!.pdf
UNDERSTANDING WHAT GREEN WASHING IS!.pdfUNDERSTANDING WHAT GREEN WASHING IS!.pdf
UNDERSTANDING WHAT GREEN WASHING IS!.pdf
 
Presentación Giulio Quaggiotto-Diálogo improbable .pptx.pdf
Presentación Giulio Quaggiotto-Diálogo improbable .pptx.pdfPresentación Giulio Quaggiotto-Diálogo improbable .pptx.pdf
Presentación Giulio Quaggiotto-Diálogo improbable .pptx.pdf
 
AGRICULTURE Hydrophonic FERTILISER PPT.pptx
AGRICULTURE Hydrophonic FERTILISER PPT.pptxAGRICULTURE Hydrophonic FERTILISER PPT.pptx
AGRICULTURE Hydrophonic FERTILISER PPT.pptx
 
Prevalence, biochemical and hematological study of diabetic patients
Prevalence, biochemical and hematological study of diabetic patientsPrevalence, biochemical and hematological study of diabetic patients
Prevalence, biochemical and hematological study of diabetic patients
 
IPCC Vice Chair Ladislaus Change Central Asia Climate Change Conference 27 Ma...
IPCC Vice Chair Ladislaus Change Central Asia Climate Change Conference 27 Ma...IPCC Vice Chair Ladislaus Change Central Asia Climate Change Conference 27 Ma...
IPCC Vice Chair Ladislaus Change Central Asia Climate Change Conference 27 Ma...
 
Artificial Reefs by Kuddle Life Foundation - May 2024
Artificial Reefs by Kuddle Life Foundation - May 2024Artificial Reefs by Kuddle Life Foundation - May 2024
Artificial Reefs by Kuddle Life Foundation - May 2024
 
Celebrating World-environment-day-2024.pdf
Celebrating  World-environment-day-2024.pdfCelebrating  World-environment-day-2024.pdf
Celebrating World-environment-day-2024.pdf
 
Sustainable farming practices in India .pptx
Sustainable farming  practices in India .pptxSustainable farming  practices in India .pptx
Sustainable farming practices in India .pptx
 
Bhopal Gas Leak Tragedy - A Night of death
Bhopal Gas Leak Tragedy - A Night of deathBhopal Gas Leak Tragedy - A Night of death
Bhopal Gas Leak Tragedy - A Night of death
 

Offshore wind energy Development in India, MNRE, Government of India

  • 1. Offshore wind energy Development in India 1
  • 2. Introduction • At the recently concluded CoP26, Hon’ble Prime Minister’s introduced five nectar elements (Panchamrit) towards contribution to climate action. One of the key element of Panchamrit is to achieve electric cumulative installed capacity 500 GW from non-fossil based capacity by 2030. • GOI has set a target of 30 GW of offshore wind installations by 2030 • Preliminary wind resource estimation based on Mesoscale model suggested potential of 70 GW of offshore wind off the coast of Gujarat and Tamil Nadu in the demarcated area . • The ‘Offshore Wind Policy’ outlining the basic framework was issued earlier in October, 2015. • The Guidelines for Offshore Wind Power Studies and Surveys for carrying out offshore study/survey were issued in September 2018. • Now, A strategy/roadmap has been prepared to work towards achieving the set target which was discussed with stakeholders under the chairmanship of Hon’ble minister. 2
  • 3. Assuming 4.5MW /Sq. km of seabed area, 35-40 GW of Installable potential is estimated in Gujarat • 05 offshore zones (Zone A-B-D-E-F) identified off Gujarat Coast. • NIWE carried out studies/surveys for 370 sq. km sea bed area in zone B: (i) Wind Resource assessment (through LIDAR) (Average wind speed – 7.5 m/s) (ii) Geophysical and Geotechnical investigation (iii) Rapid Environment Impact Assessment (EIA) (iv) Oceanographic (Wave, Tide & current) study (v) Marine Spatial Planning (MSP) under progress. • This site will be considered for 1st phase of offshore wind development. Identified Offshore sites (Gujarat)
  • 4. Assuming 4.5MW /Sq. km of seabed area, 25-30 GW of Installable potential is estimated in Tamil Nadu 07 offshore zones (Zone A-G) identified off Tamil Nadu Coast. Preliminary Assessment shows high annual average wind speeds in the range of 9 - 10.5 m/s. Detailed offshore measurement study/survey not conducted. MNRE intends to invite offshore wind developers for carrying out study/survey in these zones. These zones may come up in 2nd phase of offshore development.
  • 5. Indicative Auction Trajectory Year Year wise Offshore Wind Bids 2022 1 GW 2023 2 GW 2024 3 GW 2026 4 GW 2027 5 GW 2028 5 GW 2029 5 GW 2030 5 GW Total 30 GW • In 1st phase, offshore bidding for 1 GW capacity off Gujarat coast to be floated by SECI in year 2022. • In 2nd phase, bidding for 2 GW capacity will be floated in year 2023 for projects along Indian coastline by SECI. • The VGF based Competitive bidding will be followed only for 1st and 2nd phase projects. • For 3rd phase of projects, the support in the form of evacuation infrastructure and fiscal incentives such as waiver of transmission charges and Renewable Energy Certificates (REC) multipliers will be explored. 5
  • 6. Scope of Project Development • Evacuation of power from the offshore pooling delivery point to the onshore meeting/interconnection point by CTU/PGCIL. The cost of evacuation will be socialised. • ‘Lease Agreement’ for 30 years between MNRE or its designated agency and successful bidders. Annual floor lease fee @ Rs 1.0 lakhs/Sq.km/year for entire allocated block shall be paid from the date of allotment to till decommissioning of the project. • Detailed Project Submission within 6 months of Capacity Awarded. • Four Years time period for project Development from the date of signing of “Concessionaire agreement”. Fig: Evacuation Infrastructure Network 6
  • 7. Offshore Development Models (Model-1) • Demarcated offshore sites where MNRE/NIWE has carried out detailed studies/surveys. • In 1st Phase identified Zone ‘B3’ (370 Sq.km) off the coast of Gujarat. • Under this Model, a two stage single bid process followed by E-Reverse Auction (e-RA) based on the VGF amount will be adopted for awarding capacity. • This model can be further extended to other zones where necessary studies & surveys have been carried out by NIWE. Fig: Offshore Wind site Zone ‘B3’ off Gujarat Coast 7
  • 8. Offshore Development Models (Model-2) • This model is applicable for all sites along coastline (except sites covered under model-1) • Developer may select any offshore site/sites and carry out study survey. • Bidding Mechanism to be the same as followed under Model-1. • Project Development can happen through either; (i) Bidding (ii) Sale of Power under Open Access regime ( Developer has to submit the DPR within 5 years from the date of consent for study/survey issued by NIWE, which may be extended up to max 6 years on a case to case basis) • Post expiry of the 6 year period, all clearances to the relevant developer shall be withdrawn and the developer shall deposit the study/survey data they have collected with NIWE. • In case of project development under open access, the developer may submit the proposal along with DPR to NIWE. Developer shall directly approach the consumer for sale of power through open access. 8
  • 9. 9 Institutional Mechanism Sl. No Activity Institution 1 Application submission for Letter of Consent (study/survey) NIWE 2 Power off-take SECI/State DISCOM/Bilateral Agreement 3 Grid connectivity Central Transmission Utility (CTU) 4 Lease agreement MNRE or its designated agency 5 Single window clearances for NoC’s NIWE will facilitate all the stage-I & stage-II clearances. 6 Grid connection permission CTU 7 Project implementation agreement Bidder and SECI or other implementing agencies 8 Project monitoring SECI/NIWE
  • 10. Physical Studies conducted Sl. No Name Institution Remarks 1 Offshore wind resource assessment using LIDAR at Zone B, Gulf of khambhat, Off Gujarat coast NIWE, Chennai Data published 2 years (2017-2019) 2 Geo-Physical (370 Sq.km) & Geotechnical investigation at Zone B, Gulf of khambhat, Off Gujarat coast NIWE through NIOT, Chennai & NIO, Goa and COWI (70sq.km) Completed and awaiting clearance for data porting 3 Rapid EIA for 365Sq.km at Zone B, Gulf of khambhat, Off Gujarat coast NIWE through NIO, Goa Completed along with stakeholder consultation 4 Geotechnical investigation at Zone A,B&C1, Gulf of Mannar, Off TamilNadu coast NIWE through M/s COMACOE Completed and awaiting clearance for data porting 10
  • 11. 11 Reports Published through various TA Programmes Sl. No Name Institution Remarks 1 Feasibility Report For Offshore Wind Power Development In Gujarat. FOWIND EU Supported project 2 Feasibility Report For Offshore Wind Power Development InTamil Nadu. FOWIND EU Supported project 3 Report On Supply Chain, Ports And Logistics. FOWIND EU Supported project 4 Grid Integration Study For Offshore Wind Firm DevelopmentIn Gujarat And Tamil Nadu. FOWIND EU Supported project 5 Metocean Study., MetoceanWeather Windows for installation., and Metocean Data Requirements. FOWPI EU Supported project 6 Procedures for Offshore Wind. FOWPI EU Supported project 7 FOWPI Wind Turbine Layout and AEP. FOWPI EU Supported project 8 New Technology Catalogue with offshore wind data DEA Denmark Collaboration
  • 12. Present Status The following studies are going on through various bilateral/multilateral cooperation projects and in coordination with other departments/authorities; • Port & Logistics • Grid & Transmission • Updated Supply Chain • Marine Spatial Planning  The concept note for a viable gap funding has been prepared for MoF.  Offshore wind energy lease rules for regulating sea bed allocation is under preparation. A offshore wind test cum research centre & Greening of Rameswaram has been planned at Dhanuskodi for which preliminary activities along with DPR preparation is under preparation. The drafting of contractual documents required such as Lease agreement, implementation agreement, concessionaire agreement, connectivity agreement etc. ,is under preparation. 12
  • 13. Offshore Wind Energy Test cum Research Facility 13  To Establish India’s first offshore wind demonstration facility  To create a research facility for carrying out following activities;  Developing India specific offshore wind turbines  Component development  Grid synchronization  Performance Assessment  Optimization O&M  To create a offshore wind test facility for;  Testing of new offshore wind turbine developed by Turbine manufacturers  Testing of any new components by component manufactures  1st of its kind in Asia Pacific region – Shall act as Test ecntre serving the requirements of entire Asia Pacific Region  To provide RE power to the Rameshwaram city to make it India’s first Green City powered by 100% RE.  To create a training facility for offshore wind sector
  • 14.  Project shall consist of Installation of :  2 X 8 MW Wind Turbine Generators  1 MW AC Solar PV Ground Mounted Capacity  Additional Two nos of universal wind turbine foundations to be provided for testing of new turbines.  The power generated from the proposed Wind project & Solar PV Project to be supplied for making the Rameswaram city green.  Revenue generated to be utilized for maintenance of the project & associated R & D activities  Necessary support to be provided by MNRE for establishing the facility. 14 Project Features
  • 15. RAMESHWARAM ISLAND LOAD & OFFSHORE PLANT GENERATION 15 RAMESHWARAM ISLAND LOAD  At present the load at Rameshwaram is served through 16 MVA(2*8MVA) 33/11kV sub-station connected to Mandapam substation of main land.  Total annual energy consumption of Rameshwaram: 33.208 million units (data collected for the period March 2021 to Feb 2022) PLF OF PROPOSED PLANT  Annual Power Generation from the proposed hybrid power plant: 52.2 GWh/year  Average PLF of offshore turbines expected to be around 35.3% considering existing class of European design wind turbine of higher specific power. (49.47 GWh/year)  1MW solar plant it is expected generation of 1.689 GWh/year 29-06-2022 MNRE | OFFSHORE WIND | April 2022
  • 16. PROJECT LOCATION (DHANUSKODI) 16 • The Project Site is 25 Kms from Rameshwaram city (birthplace of India's renowned scientist and former President of India, A. P. J. Abdul Kalam). • Rameshwaram is well connected by Road & Railway • Test site situated on the shoreline and surrounded by shallow seawater in three directions.
  • 17. SITE FEATURES 17 Wind conditions 8.36 m/sec (at 102 m AGL), 6 % Turbulence Intensity (at 15 m/sec) Sufficient space for the test site, including wind field, test area 75 acres of land leased by the State Government (Tamil Nadu) Good infrastructure such as roads, bridges, harbor, power lines Tuticorin Port – 200 Km distance (by Road). Around 130 km by Sea route Study on Strengthening of Roads, Bridges for transportation of WT Components needs to be carried out. Closeness to promising offshore sites, where access to harbors is important Access to skilled workforce Available (Nearest Cities: Madurai, Tuticorin & Tirunelveli) – 200 km Minimum interference in nature and environment No interference expected Minimum impact on neighbouring households Rameshwaram is nearest Town and located 25 Km from the Site
  • 18. WIND CONDITIONS AT DHANUSKODI 18 • 8.36 m/sec (at 102 m AGL) • 6 % Turbulence Intensity (at 15 m/sec) • Power Law Index – 0.0432 • Global titled irradiation is 2112 kwh/m^2.
  • 19. RAMESHWARAM ISLAND LOAD & OFFSHORE PLANT GENERATION 19 RAMESHWARAM ISLAND LOAD  At present the load at Rameshwaram is served through 16 MVA(2*8MVA) 33/11kV sub-station connected to Mandapam substation of main land.  Total annual energy consumption of Rameshwaram: 33.208 million units (data collected for the period March 2021 to Feb 2022) PLF OF PROPOSED PLANT  Annual Power Generation from the proposed hybrid power plant: 52.2 GWh/year  Average PLF of offshore turbines expected to be around 35.3% considering existing class of European design wind turbine of higher specific power. (49.47 GWh/year)  1MW solar plant it is expected generation of 1.689 GWh/year
  • 20. Thank You 6/29/2022 MNRE | OFFSHORE | March 2022 20