This document provides an overview of Bangladesh's infrastructure and plans for nuclear energy development. It discusses Bangladesh's current power situation and reliance on non-renewable energy sources. It outlines plans from the Power System Master Plan 2010 to obtain 2000 MW of power from the Rooppur Nuclear Power Plant by 2021 and another 2000 MW by 2030. It describes the site and progress on the Rooppur NPP, including engineering surveys, environmental impact assessments, and signing agreements with Russia. It also discusses the nuclear regulatory framework, human resource development, and communication and public awareness efforts regarding nuclear energy.
Acceleration the utilization of Renewable Energy Sampe Purba
Presented in Asean Clean Energy Week, November 2020
Despite the pandemic covid 19, Indonesia commits to promote the utilization of Renewable Energy in our Energy Mix
The document discusses India's plans to develop offshore wind energy projects. Key points include:
- India has over 7,600 km of coastline with good potential for offshore wind energy generation.
- A national offshore wind energy policy was notified in 2015 with the Ministry of New and Renewable Energy as the nodal ministry.
- National Institute of Wind Energy (NIWE) has been designated as the nodal agency responsible for facilitating offshore wind development.
- Resource assessment studies have found potential of up to 695.5 GW of offshore wind capacity.
- The first 1 GW offshore wind project is planned off the coast of Gujarat. Resource assessment studies including LiDAR measurements have been conducted at this site
Developing and Sustaining Hydro Integrated Renewable Energy Power System (Hyd...Sammy S. Aiau
The document discusses developing and sustaining integrated renewable energy power systems for rural areas in Papua New Guinea. It provides background on PNG's energy sector, which is dominated by electricity, oil, and gas. PNG Power Limited is responsible for generation and distribution but only 7% of the population has access to electricity. The presentation outlines PNG's renewable energy resources including hydro, solar, and wind. It also discusses a case study of the Wantun micro-hydro project and proposes micro-grid systems and various business models to power rural micro-grids, emphasizing private sector participation and subsidies.
Bangladesh is constructing its first nuclear power plant, the Rooppur Nuclear Power Plant, with Russian assistance. The 2.4 GW plant is expected to begin operations in 2023 and will supply much needed electricity to help Bangladesh achieve its development goals. However, some have raised safety and economic concerns due to Bangladesh's lack of nuclear experience and reliance on foreign expertise. The plant will help meet the country's growing energy demands but debates continue around the risks versus the benefits of nuclear power compared to renewable sources.
Renewable Energy status and road-map of Bangladesh and support of UNDP-GEFDr. Md. Taibur Rahman
The document discusses renewable energy status and roadmap in Bangladesh. It provides an overview of current renewable energy capacity, policies and targets. Bangladesh aims to generate 30% of power from renewable sources by 2041 according to its Delta Plan. Current renewable energy capacity is only 3% of total generation but serves 13% of the population. Several ongoing and planned initiatives are discussed, including solar parks, mini-grids, irrigation projects, and a roadmap to achieve 30% renewable energy by 2041 through various programs and by addressing challenges such as land acquisition and grid integration.
The document summarizes an environmental impact assessment study for a proposed 1320 MW thermal power plant project in Payra, Bangladesh. The key points are:
1. The project involves constructing two 660 MW power units fueled by coal to help meet Bangladesh's growing energy demands and reduce reliance on natural gas.
2. The plant would be located near Kazol River in Patuakhali district and have the potential for an additional 1320 MW unit in the future.
3. The study analyzed environmental impacts from constructing and operating the plant on air and water quality, land use, biodiversity, and socioeconomics as well as proposed mitigation measures.
Prospect of Developments of the Clean Energy in IndonesiaBadariahYosiyana
The document discusses Indonesia's plans and targets for increasing clean energy and reducing greenhouse gas emissions through 2050. Key points include:
- Targets of reducing emissions 29-41% by 2030 and achieving net zero by 2050 through expanding renewable energy, energy efficiency, and clean technologies.
- Plans to increase renewable energy in the energy mix from 11% in 2020 to 28% by 2035, and strategies to accelerate reductions in greenhouse gas emissions.
- Challenges around financing the large investments needed for energy transformation and developing supporting infrastructure and human resources.
Acceleration the utilization of Renewable Energy Sampe Purba
Presented in Asean Clean Energy Week, November 2020
Despite the pandemic covid 19, Indonesia commits to promote the utilization of Renewable Energy in our Energy Mix
The document discusses India's plans to develop offshore wind energy projects. Key points include:
- India has over 7,600 km of coastline with good potential for offshore wind energy generation.
- A national offshore wind energy policy was notified in 2015 with the Ministry of New and Renewable Energy as the nodal ministry.
- National Institute of Wind Energy (NIWE) has been designated as the nodal agency responsible for facilitating offshore wind development.
- Resource assessment studies have found potential of up to 695.5 GW of offshore wind capacity.
- The first 1 GW offshore wind project is planned off the coast of Gujarat. Resource assessment studies including LiDAR measurements have been conducted at this site
Developing and Sustaining Hydro Integrated Renewable Energy Power System (Hyd...Sammy S. Aiau
The document discusses developing and sustaining integrated renewable energy power systems for rural areas in Papua New Guinea. It provides background on PNG's energy sector, which is dominated by electricity, oil, and gas. PNG Power Limited is responsible for generation and distribution but only 7% of the population has access to electricity. The presentation outlines PNG's renewable energy resources including hydro, solar, and wind. It also discusses a case study of the Wantun micro-hydro project and proposes micro-grid systems and various business models to power rural micro-grids, emphasizing private sector participation and subsidies.
Bangladesh is constructing its first nuclear power plant, the Rooppur Nuclear Power Plant, with Russian assistance. The 2.4 GW plant is expected to begin operations in 2023 and will supply much needed electricity to help Bangladesh achieve its development goals. However, some have raised safety and economic concerns due to Bangladesh's lack of nuclear experience and reliance on foreign expertise. The plant will help meet the country's growing energy demands but debates continue around the risks versus the benefits of nuclear power compared to renewable sources.
Renewable Energy status and road-map of Bangladesh and support of UNDP-GEFDr. Md. Taibur Rahman
The document discusses renewable energy status and roadmap in Bangladesh. It provides an overview of current renewable energy capacity, policies and targets. Bangladesh aims to generate 30% of power from renewable sources by 2041 according to its Delta Plan. Current renewable energy capacity is only 3% of total generation but serves 13% of the population. Several ongoing and planned initiatives are discussed, including solar parks, mini-grids, irrigation projects, and a roadmap to achieve 30% renewable energy by 2041 through various programs and by addressing challenges such as land acquisition and grid integration.
The document summarizes an environmental impact assessment study for a proposed 1320 MW thermal power plant project in Payra, Bangladesh. The key points are:
1. The project involves constructing two 660 MW power units fueled by coal to help meet Bangladesh's growing energy demands and reduce reliance on natural gas.
2. The plant would be located near Kazol River in Patuakhali district and have the potential for an additional 1320 MW unit in the future.
3. The study analyzed environmental impacts from constructing and operating the plant on air and water quality, land use, biodiversity, and socioeconomics as well as proposed mitigation measures.
Prospect of Developments of the Clean Energy in IndonesiaBadariahYosiyana
The document discusses Indonesia's plans and targets for increasing clean energy and reducing greenhouse gas emissions through 2050. Key points include:
- Targets of reducing emissions 29-41% by 2030 and achieving net zero by 2050 through expanding renewable energy, energy efficiency, and clean technologies.
- Plans to increase renewable energy in the energy mix from 11% in 2020 to 28% by 2035, and strategies to accelerate reductions in greenhouse gas emissions.
- Challenges around financing the large investments needed for energy transformation and developing supporting infrastructure and human resources.
The document provides information about the proposed Rampal Power Plant project in Bangladesh. It will be a 1320 megawatt coal-fired power station located 14 km north of the Sundarbans mangrove forest. The power plant is a joint venture between India and Bangladesh and is expected to be the largest power plant in Bangladesh. The document discusses the project description and location, purpose of the environmental impact assessment study, methodology used, evaluation of alternative sites, environmental and social baseline conditions in the study area, and potential impacts of the project.
The document discusses Bangladesh's first nuclear power plant called the Rooppur Nuclear Power Plant (RNPP) which is under construction. It will be located in Ishwardi, Pabna district and will have 2 units capable of producing 2,400 MW of electricity total. The RNPP is expected to begin operations in 2023 and will provide a safe, reliable and affordable source of clean energy for Bangladesh to meet its growing electricity demands. It discusses the technical features and safety standards that are in place to ensure safe operations.
This document provides an overview of Pakistan's power sector, including key statistics and the major entities involved. It notes that Pakistan has a population of 188 million people and per capita income of $1387 in 2013-14. The main sources of electricity generation are gas, oil, and hydro. The major organizations in the power sector include the Ministry of Water and Power, NEPRA, WAPDA, NTDC, PPIB, AEDB, NPCC, and NESPAK, each with distinct roles in policymaking, regulation, generation, transmission, and project development. The document aims to introduce readers to Pakistan's power infrastructure and the national and provincial agencies that govern it.
The document discusses Ultra Mega Power Projects (UMPPs) in India. It outlines that UMPPs are large coal power projects of 4000+ MW capacity each that are developed on a build-own-operate basis. Nine projects have been identified so far, with contracts awarded for four located at pit heads near coal mines. The projects aim to address India's growing power needs and pace of capacity addition. Barriers to private sector participation previously included regulatory issues but reforms like the Electricity Act of 2003 have helped support UMPPs. The process for developing UMPPs involves setting up special purpose vehicles and shell companies to handle land acquisition, clearances and competitive bidding for developers.
The proposed Jaitapur Nuclear Power Project in Maharashtra would be the largest nuclear power plant in the world. It plans to construct 6 European pressurized reactors, each producing 1650 megawatts of power for a total of 9,900 megawatts. The project faces significant opposition due to environmental and safety concerns in the seismically active region. Critics argue the project threatens the unique ecosystem of the Western Ghats and Konkan coast, and that India's regulatory system is not strong enough to ensure nuclear safety.
UK Nuclear New Build Power Stations - Nationally Significant Infrastructure P...A Hagan
UK Nuclear New Build Power Stations - Nationally Significant Infrastructure Projects (NSIP) through the Infrastructure Planning Commission (IPC) Process - taking into account National Policy Statements (NPS)
This document provides an overview of ADB projects in Mongolia's energy sector. It summarizes several completed projects including the Ulaanbaatar Low Carbon Energy Supply Project, Energy Conservation and Emissions Reduction from Poor Household Project, and Demonstration Project for Improved Electricity Services to Rural Areas. It also discusses the Updating the Energy Sector Development Plan technical assistance. Challenges facing projects are described such as delays due to consultant performance, data issues, and ADB procedures. Recommendations are made to increase government involvement in consultant selection and to improve schedule planning.
UNFCCC The background, Achievements in implementation, key emerging issues, Recommendation.
Climate Change Department
11/12/2019 9:16:07 PM
Semambo Muhammad
The document outlines Vietnam's nuclear power development program. Vietnam plans to construct multiple nuclear power plants to meet growing energy demands. The first two plants will be in Ninh Thuan province and have a capacity of 2000MW each. Vietnam faces challenges in developing its nuclear infrastructure and regulatory framework. It will need international support to further develop human resources, safety standards, and other nuclear capabilities as it moves forward with its plans to introduce nuclear power.
Status of Hydropower in Nepal- Presented in CIA Training Session at Luang Pra...Er. Abhushan Neupane
Cumulative Impact Assessment (CIA), as a tool is a holistic approach to study,assess, monitor and manage the Valued Engineering Components (VECs), in a specific and defined manner. It is imperative to use in the entire basin approach for Hydropower development in Nepal.
More information about this approach can be made available by the Trainee (representatives from Nepal)
Jordan has excellent solar and wind resources and is making renewable energy a priority. The country aims to source 10% of its energy from renewable sources like solar and wind by 2020. Jordan has established policies and incentives to attract renewable energy investments, including setting ceiling prices for different technologies, net metering, and tax exemptions. Projects are being developed through various approaches such as direct proposals, competitive bidding, and EPC contracts. The first round of direct proposals resulted in several solar PV projects that are now under construction. Jordan is on the right path to significantly increase renewable energy in its energy mix.
This document summarizes Bhutan's energy sector, including its goals and initiatives to achieve universal energy access, energy efficiency, and increased use of renewable energy as part of its commitments under SE4ALL. It outlines Bhutan's institutional arrangements and existing energy policies, then discusses the country's progress toward each of the three SE4ALL goals. Challenges are presented, such as a lack of legal frameworks and institutional capacity for renewable energy and energy efficiency. Investment opportunities are mentioned, primarily in ongoing studies and hydropower projects planned for implementation under public-private partnerships.
The document discusses coal-based thermal power projects under the China-Pakistan Economic Corridor. It outlines the composition and scope of Research and Analysis Group II, which is tasked with identifying economic benefits and controversies related to the projects. Short term measures proposed to ensure timely completion include providing security, infrastructure development, streamlining regulations, and raising community awareness. Medium term strategies involve facilitating stakeholders, resolving intergovernmental differences, and strengthening environmental protection regimes. Long term goals encompass equitable distribution of resources and continued economic prosperity.
ENSURING AFFORDABLE FUEL SECURITY FOR NTPCSantosh Verma
This document discusses India's energy security and fuel scenario, with a focus on NTPC's fuel needs and challenges. It provides an overview of India's growing energy demand and dependence on fossil fuels like coal for power generation. Coal is the main fuel for over 50% of India's primary energy and 69% of power generation, but there are issues with domestic coal supply that affect NTPC's plants. The document analyzes challenges related to coal, oil and gas, nuclear, and renewable sources. It recommends solutions like increasing domestic coal production, diversifying NTPC's fuel mix through renewable and nuclear sources, and establishing an effective framework for fuel supply agreements.
This document provides an overview of the power sector in India. It discusses the key stages in the development of the power sector from before 1956 to the present day. Some of the key points covered include:
- The power sector has gone through different eras including nationalization (1956-1991), liberalization (1991-2003), and the current growth era (2003-present).
- Key policy initiatives and legislation like the Electricity Act 2003 and National Tariff Policy 2006 have promoted private sector participation and competition.
- India has a total installed capacity of 248,509 MW as of 2014, with thermal power making up the largest share at 69%. Renewable energy capacity is also being increased significantly.
The document discusses the potential for wind energy in Lebanon. It outlines Lebanon's national framework and policy commitments to increase renewable energy, including a target of 12% renewable energy by 2020. One of the initiatives in Lebanon's National Energy Efficiency Action Plan is to generate electricity from wind power, with a target of 400-500 megawatts of wind energy by 2020. The first phases include requests for private sector proposals for a 50-100 megawatt wind farm and expressions of interest for a public sector 1-10 megawatt wind farm.
The document provides information about the proposed Rampal Power Plant project in Bangladesh. It will be a 1320 megawatt coal-fired power station located 14 km north of the Sundarbans mangrove forest. The power plant is a joint venture between India and Bangladesh and is expected to be the largest power plant in Bangladesh. The document discusses the project description and location, purpose of the environmental impact assessment study, methodology used, evaluation of alternative sites, environmental and social baseline conditions in the study area, and potential impacts of the project.
The document discusses Bangladesh's first nuclear power plant called the Rooppur Nuclear Power Plant (RNPP) which is under construction. It will be located in Ishwardi, Pabna district and will have 2 units capable of producing 2,400 MW of electricity total. The RNPP is expected to begin operations in 2023 and will provide a safe, reliable and affordable source of clean energy for Bangladesh to meet its growing electricity demands. It discusses the technical features and safety standards that are in place to ensure safe operations.
This document provides an overview of Pakistan's power sector, including key statistics and the major entities involved. It notes that Pakistan has a population of 188 million people and per capita income of $1387 in 2013-14. The main sources of electricity generation are gas, oil, and hydro. The major organizations in the power sector include the Ministry of Water and Power, NEPRA, WAPDA, NTDC, PPIB, AEDB, NPCC, and NESPAK, each with distinct roles in policymaking, regulation, generation, transmission, and project development. The document aims to introduce readers to Pakistan's power infrastructure and the national and provincial agencies that govern it.
The document discusses Ultra Mega Power Projects (UMPPs) in India. It outlines that UMPPs are large coal power projects of 4000+ MW capacity each that are developed on a build-own-operate basis. Nine projects have been identified so far, with contracts awarded for four located at pit heads near coal mines. The projects aim to address India's growing power needs and pace of capacity addition. Barriers to private sector participation previously included regulatory issues but reforms like the Electricity Act of 2003 have helped support UMPPs. The process for developing UMPPs involves setting up special purpose vehicles and shell companies to handle land acquisition, clearances and competitive bidding for developers.
The proposed Jaitapur Nuclear Power Project in Maharashtra would be the largest nuclear power plant in the world. It plans to construct 6 European pressurized reactors, each producing 1650 megawatts of power for a total of 9,900 megawatts. The project faces significant opposition due to environmental and safety concerns in the seismically active region. Critics argue the project threatens the unique ecosystem of the Western Ghats and Konkan coast, and that India's regulatory system is not strong enough to ensure nuclear safety.
UK Nuclear New Build Power Stations - Nationally Significant Infrastructure P...A Hagan
UK Nuclear New Build Power Stations - Nationally Significant Infrastructure Projects (NSIP) through the Infrastructure Planning Commission (IPC) Process - taking into account National Policy Statements (NPS)
This document provides an overview of ADB projects in Mongolia's energy sector. It summarizes several completed projects including the Ulaanbaatar Low Carbon Energy Supply Project, Energy Conservation and Emissions Reduction from Poor Household Project, and Demonstration Project for Improved Electricity Services to Rural Areas. It also discusses the Updating the Energy Sector Development Plan technical assistance. Challenges facing projects are described such as delays due to consultant performance, data issues, and ADB procedures. Recommendations are made to increase government involvement in consultant selection and to improve schedule planning.
UNFCCC The background, Achievements in implementation, key emerging issues, Recommendation.
Climate Change Department
11/12/2019 9:16:07 PM
Semambo Muhammad
The document outlines Vietnam's nuclear power development program. Vietnam plans to construct multiple nuclear power plants to meet growing energy demands. The first two plants will be in Ninh Thuan province and have a capacity of 2000MW each. Vietnam faces challenges in developing its nuclear infrastructure and regulatory framework. It will need international support to further develop human resources, safety standards, and other nuclear capabilities as it moves forward with its plans to introduce nuclear power.
Status of Hydropower in Nepal- Presented in CIA Training Session at Luang Pra...Er. Abhushan Neupane
Cumulative Impact Assessment (CIA), as a tool is a holistic approach to study,assess, monitor and manage the Valued Engineering Components (VECs), in a specific and defined manner. It is imperative to use in the entire basin approach for Hydropower development in Nepal.
More information about this approach can be made available by the Trainee (representatives from Nepal)
Jordan has excellent solar and wind resources and is making renewable energy a priority. The country aims to source 10% of its energy from renewable sources like solar and wind by 2020. Jordan has established policies and incentives to attract renewable energy investments, including setting ceiling prices for different technologies, net metering, and tax exemptions. Projects are being developed through various approaches such as direct proposals, competitive bidding, and EPC contracts. The first round of direct proposals resulted in several solar PV projects that are now under construction. Jordan is on the right path to significantly increase renewable energy in its energy mix.
This document summarizes Bhutan's energy sector, including its goals and initiatives to achieve universal energy access, energy efficiency, and increased use of renewable energy as part of its commitments under SE4ALL. It outlines Bhutan's institutional arrangements and existing energy policies, then discusses the country's progress toward each of the three SE4ALL goals. Challenges are presented, such as a lack of legal frameworks and institutional capacity for renewable energy and energy efficiency. Investment opportunities are mentioned, primarily in ongoing studies and hydropower projects planned for implementation under public-private partnerships.
The document discusses coal-based thermal power projects under the China-Pakistan Economic Corridor. It outlines the composition and scope of Research and Analysis Group II, which is tasked with identifying economic benefits and controversies related to the projects. Short term measures proposed to ensure timely completion include providing security, infrastructure development, streamlining regulations, and raising community awareness. Medium term strategies involve facilitating stakeholders, resolving intergovernmental differences, and strengthening environmental protection regimes. Long term goals encompass equitable distribution of resources and continued economic prosperity.
ENSURING AFFORDABLE FUEL SECURITY FOR NTPCSantosh Verma
This document discusses India's energy security and fuel scenario, with a focus on NTPC's fuel needs and challenges. It provides an overview of India's growing energy demand and dependence on fossil fuels like coal for power generation. Coal is the main fuel for over 50% of India's primary energy and 69% of power generation, but there are issues with domestic coal supply that affect NTPC's plants. The document analyzes challenges related to coal, oil and gas, nuclear, and renewable sources. It recommends solutions like increasing domestic coal production, diversifying NTPC's fuel mix through renewable and nuclear sources, and establishing an effective framework for fuel supply agreements.
This document provides an overview of the power sector in India. It discusses the key stages in the development of the power sector from before 1956 to the present day. Some of the key points covered include:
- The power sector has gone through different eras including nationalization (1956-1991), liberalization (1991-2003), and the current growth era (2003-present).
- Key policy initiatives and legislation like the Electricity Act 2003 and National Tariff Policy 2006 have promoted private sector participation and competition.
- India has a total installed capacity of 248,509 MW as of 2014, with thermal power making up the largest share at 69%. Renewable energy capacity is also being increased significantly.
The document discusses the potential for wind energy in Lebanon. It outlines Lebanon's national framework and policy commitments to increase renewable energy, including a target of 12% renewable energy by 2020. One of the initiatives in Lebanon's National Energy Efficiency Action Plan is to generate electricity from wind power, with a target of 400-500 megawatts of wind energy by 2020. The first phases include requests for private sector proposals for a 50-100 megawatt wind farm and expressions of interest for a public sector 1-10 megawatt wind farm.
How to Setup Default Value for a Field in Odoo 17Celine George
In Odoo, we can set a default value for a field during the creation of a record for a model. We have many methods in odoo for setting a default value to the field.
A Free 200-Page eBook ~ Brain and Mind Exercise.pptxOH TEIK BIN
(A Free eBook comprising 3 Sets of Presentation of a selection of Puzzles, Brain Teasers and Thinking Problems to exercise both the mind and the Right and Left Brain. To help keep the mind and brain fit and healthy. Good for both the young and old alike.
Answers are given for all the puzzles and problems.)
With Metta,
Bro. Oh Teik Bin 🙏🤓🤔🥰
How to Download & Install Module From the Odoo App Store in Odoo 17Celine George
Custom modules offer the flexibility to extend Odoo's capabilities, address unique requirements, and optimize workflows to align seamlessly with your organization's processes. By leveraging custom modules, businesses can unlock greater efficiency, productivity, and innovation, empowering them to stay competitive in today's dynamic market landscape. In this tutorial, we'll guide you step by step on how to easily download and install modules from the Odoo App Store.
CapTechTalks Webinar Slides June 2024 Donovan Wright.pptxCapitolTechU
Slides from a Capitol Technology University webinar held June 20, 2024. The webinar featured Dr. Donovan Wright, presenting on the Department of Defense Digital Transformation.
Elevate Your Nonprofit's Online Presence_ A Guide to Effective SEO Strategies...TechSoup
Whether you're new to SEO or looking to refine your existing strategies, this webinar will provide you with actionable insights and practical tips to elevate your nonprofit's online presence.
Creative Restart 2024: Mike Martin - Finding a way around “no”Taste
Ideas that are good for business and good for the world that we live in, are what I’m passionate about.
Some ideas take a year to make, some take 8 years. I want to share two projects that best illustrate this and why it is never good to stop at “no”.
220711130100 udita Chakraborty Aims and objectives of national policy on inf...
Breakout_Infrastructure of nuclear power plant
1. INFRASTRUCTURE
IN
BANGLADESH
8th INPRO Dialogue Forum:
Toward Nuclear Energy System Sustainability: Economics, Resource Availability, and Institutional Arrangements
26-29 August 2014, IAEA, Vienna, Austria
Engr. Md. Monirul Islam
Chairman (Current Charge)
BANGLADESH ATOMIC ENERGY COMMISSION
2. Outline
• Introduction
• Bangladesh Overview
• Present Power Situation
• Current & Future plans for NP development
• RNPP overview
• Structure of NEPIO
• Public & Political Support
• Recent Progress
• General Communication Program
• Public Awareness Program
3. Introduction
Bangladesh has long since been using atomic energy and
related technology in different fields for the overall socio-
economic development of the country and their uses are
increasing gradually.
3
4. Bangladesh: Basic Facts
• Official Name : People’s Republic of Bangladesh
• Capital City : Dhaka
• Area : 147,570 sq. km
• Total Population : 150 million
• Population Density : 833/sq. km
• Literacy : 50%
• Main Contributors to GDP : Agriculture and Garments Industries
• Natural Resources : Natural Gas, Coal & Hard rock
Basic Information
5. Bangladesh: Overview
Fig.1:Political Map of Bangladesh with Neighboring Countries
China
Rooppur NPP site Country without Nuclear Power Reactor Country with Nuclear Power Reactor
7. Renewable Energy :
Renewable energy is environment-friendly. At present, the different
categories of renewable energy that are being used in limited ways in our
country are as follows:
• Hydro-electricity
• Solar power generation using solar rays
• Wind-mill power generation using wind power
• Production of bio-gas using waste
• Electricity produced by Biomass Gasification Method using wood, rice
husk, etc.
8. Non-Renewable Energy
The proven reserve of natural gas which is the principal source of non-
renewable energy of the country is gradually depleting. The supply of gas
as a primary source of energy will be dried out soon if immediate steps
are not taken for exploration of new gas fields and extraction . In the use
of commercial energy, the notable ones include the following:
• Natural gas
• Oil from minerals and other sources
• Coal and coal like substance
• Compressed natural gas (CNG)
• Natural Gas Liquid (NGL)
9. Power System Master Plan-2010 (PSMP – 2010) proposes long-term fuel-mix as follows [4000
MWe from NPP by 2030]:
By 2021, the share of nuclear will be 10% of 20,000 MW = 2000 MW (2X1000 MW) from the Rooppur NPP.
PSMP-2010 also proposes addition of another
2000 MW from Rooppur nuclear plant
9
Energy 2010 2021 (20,000 MW)
Gas 87.50% 30%
Oil 06.00% 03%
Coal 03.70% 53%
Hydro 02.70% 01%
Nuclear 0% 10%
Renewable 00.50% 03%
Current & Future Plans for NPP Deployment
This share is about 28%
now !!
10. Strategic Position of NPP
Source: Power System Master Plan
Nuclear Power Plant
Cross Border Import
Imported Coal Power Plant
Establishment of Roopur NPP will boost
power generation as well as industrialization
in the Western zone of Bangladesh.
Rooppur NPP Site Overview
11. Rooppur Nuclear Power
Plant (RNPP) Project
NEPIO has been formed.
A bill to install Nuclear Power Plant has been passed in the
National Parliament- ensuring the strong national
commitment.
.
River Padma
RNPP Site
12. Rooppur NPP Site Overview
Satellite picture of Site Area: GPS Position : 24.06502, 89.045391
1
Main channel
Flow direction of Ganges River
Hardinge Bridge
Lalon Shah Bridge
Left bank
channel
Proposed Power Plant
Site
Intake point
Outfall point
Highway & Railway
13. Structure of NEPIO - Bangladesh
13
13
Working Group
Secretary MOST
Technical Committee
BAEC
Coordination Committee
Nuclear Power and Energy
Division (NPED)
NEPIO
Minister MOST
National Committee
8 Working Sub-Groups
(Ministry)
Development of Human
Resources
Funding and
Financing
National Participation
Nuclear Fuel Cycle,
Waste Management and
Environ Monitoring
Legal and Regulatory
Aspects, International
Obligations
Heavy Equipment
Transportation Planning
Ownership, Project
execution and Project
Management
Grid System
Prime Minister
BAERA
7 Sub-Committees on
RNPP (BAEC)
Ownership,
Project
execution &
Management
Legal and
Regulatory
International
Obligations
Development of
Human
Resources
Grid System
Development
Funding and
Financing
Nuclear FC,
WM and
Environ
Monitoring
National
Participation &
Procurement
14. Nuclear Power Project Stakeholders
NPP Project
Financing
entities
Government Regulations
&Licensing
Financial
commitments
Treaty Commitments
& National Law
Government Used Fuel
mgmt.
Decommi
ssioning
NSSS
Supplier
Fuel
Supply EPC
Contractor
Owners
Human
Capital
Operator
Off taker
Public
Subcontractors
Labor
Equipment
&Material Suppliers
ECAs
Commercial
Banks
15. BAEC is a Government entity, which is responsible for
promoting peaceful uses of atomic energy in the country.
[
Total manpower of BAEC stands at more than 2000, which
includes about 500 professionals having wide experience in
various fields of nuclear science and technology.
About 100 of these personnel have good exposure on
various aspects of NP program.
Nuclear Power Infrastructure
16. Nuclear Road Map of Bangladesh
• 2013-2016
• Finalization of Site evaluation
• Engineering Survey
• Feasibility Evaluation for Rooppur Nuclear Power Project and design as well as
working documentation for the first priority construction & erection base.
• Preparation of EIA report
• Establishment of Independent Regulatory Body
• Signing of Essential Agreement / Contracts with the Vendor country
• EPCM-Turnkey Agreement with Vendor
• Achievement of IAEA Milestone
• By the end of 2021
• Construction, commissioning and test operation and acceptance of the plant
• 2021 Commercial Operation
16
17. 17
Activities to
implement first NPP,
the RNPP
Preparatory work for
RNPP construction;
negotiating and
Concluding contract (s)
Pre-Project activities to
make a knowledgeable
decision on NPP
Consideration to
include nuclear energy
and initiatives to
implement RNPP since
1960s
PHASE 0 PHASE 1 PHASE 2 PHASE 3
Maintenance
and
continuous
infrastructure
improvement
Infrastructure
development
programme
Pre-project RNPP
definition
RNPP Construction
Ops
Commissioning
Nuclear power is
considered as a possible
option
MILESTONE 0
Ready to include nuclear as
realistic national energy strategy
option
MILESTONE 1
Ready to make commitment to a
nuclear
MILESTONE 2
Ready to negotiate the contract.
MILESTONE 3
Ready to commission and operate
first NPP
Pre-policy
2008 2010 2014 2018-2021
RNPP Project Timeline (Sixth Five Year Planning of Bangladesh and PSMP 2010)
Preparation for RNPP
1960s
IAEA Milestone 2 “ready to invite bids” is termed as “ready to negotiate the contract”
IAEA Milestone Approach of Nuclear Power Programme
18. Operation / decommissioning
•Preparing for assuming
commitments & obligations
Commissioning
Nuclear power option included
within the
national energy strategy
10 – 15 years
PHASE 2 PHASE 3
PHASE 1
MILESTONE 1
Ready to make a knowledgeable commitment to
a nuclear programme
MILESTONE 2
Ready to negotiate the contractor the
first NPP
•MILESTONE 3
•Ready to commission and operate the
first NPP
negotiate contract
Pre project Project decision making Construction
Maintenance and continuous
infrastructure improvement
Preparatory study Feasibility Study
18
Preparation of Infrastructure
Commissioning and Operation
• Project Decision Making
• Site Evaluation
• Engineering Survey
• Environment Impact Analysis(EIA)
• Feasibility Study
• Negotiation of Contract
• Closure of EPCM Turnkey/ EPC contract
• Establishing competent Nuclear Regulatory Authority
• Public information and understanding
IAEA Milestone Approach of Nuclear Power Infrastructure of Bangladesh
19. Mongla Port
• The port provides facilities and services to the international shipping lines and
maintaining adequate water depth in the channel as well as making provision
for safe day and night shipping.
• Present government has given top priority for developing port facilities up to
international standard which is necessary for the implementation of RNPP.
Mongla Port is situated (Lat.
21026.9` N. long. 890 34.4 E)
in the Bay of Bengal.
20. COMMUNICATION: contd.
• The entire coast along the Bay of Bengal is 710
Kilometer long. There are two major ports in the
country. Chittagong Port , the oldest port, and
the Mongla Port in Khulna region serves the western
part of Bangladesh . There are now 11 operational
airports in Bangladesh . Of these, the airports at
Dhaka, Chittagong, and Sylhet serve international
routes.
21.
22.
23.
24.
25.
26. Political & Public Support for NPP
2000: Bangladesh Nuclear Energy Action Plan was approved by the
government.
2008: Implementation of Rooppur NPP had become an Election Pledge of
the present ruling party including all major political parties.
2013: Government has taken Rooppur NPP as one of the five fast-track
projects.
BAEC also conducted a limited survey on public acceptance/awareness
about nuclear power programme that clearly described the unique public
acceptance level of the project
27. Recent Progress
2009: An MOU between BAEC and the ROSATOM was signed for
cooperation in the “Peaceful Uses of Nuclear Energy” on 13 May.
2010: A National Committee on RNPP headed by the Prime
Minister was formed.
2010: “In order to overcome the increasing power crisis in the
country nuclear power plant shall be established immediately” -
Resolution was passed unanimously by the National Parliament in
November.
2010: Hon’ble DG of IAEA, Mr. Amano visited Bangladesh during
14–15 December and assured his kind support for implementation
of Rooppur NPP.
28. Recent Progress
2011: The Cabinet approved the Interagency agreement between the
Russian Regulatory Body and the Ministry of Science and Technology
on cooperation in the areas of Nuclear Safety Regulation on 31 October
,2011.
IAEA-INIR mission conducted during November 2011, which
concluded that Bangladesh Nuclear Power Program in general has
progressed into Phase 2, being in the stage of preparation to negotiate
agreement(s)/contract(s).
Cooperation Agreement between GoB and Russian Federation
concerning the construction of ‘Rooppur NPP’ was signed on 02 Nov,
2011.
29. Recent Progress
Bangladesh Atomic Energy Regulatory Authority (BAERA) Act was
enacted in the National Parliament on 31 May 2012.
An independent regulatory body has been established under the
provision of BAERA Act;
A MOU for the training of the staff of nuclear power sector was
signed on 4 June 2012
A MOU for the establishment of Information Centre of Nuclear
Energy in Bangladesh was signed on 4 June 2012.
Bilateral consultation meeting between Russian Federation and
GoB for determining potential NPP cost and defining the terms and
conditions of the borrowed loans/credit financing from the vendor
sources conducted in July,2012.
30. Recent Progress
Bilateral consultation on main terms and conditions of the draft
contract (Legal and technical) for carrying out engineering survey
and environmental studies of Rooppur NPP) was held in Dhaka,
1~7 September, 2012.
Loan agreement has been signed with Russian Federation for
financing of for 2× 1000 MW for the preparatory stage of works
(Ist phage) for the construction of RNPP on 15th January 2013.
The Hon’ble Prime Minister of the People’s Republic of Bangladesh
has inaugurated the Construction of Rooppur Nuclear Power Plant
(First Phase) on 2 October, 2013.
31. Ground Breaking Ceremony of the Construction of
Rooppur Nuclear Power Plant (First Phase)
The Hon’ble Prime Minister of the People’s Republic of Bangladesh has inaugurated the Construction of
Rooppur Nuclear Power Plant
(First Phase) on 2 October, 2013.
Construction of
Rooppur Nuclear Power Plant (First Phase)
Development of the Feasibility
Evaluation, Environmental Impact
Assessment for Rooppur NPP site
and the performance of the
necessary Engineering Survey and
Environmental Studies
Development of design
documentation and first-
priority working
documentation for
construction of Rooppur NPP
Performance of first-priority
construction and erection
works of preparatory stage
Completion of remaining
works for the Performance
of first-priority construction
and erection works of
preparatory stage
Contract-1
(Signed) Contract-4
(Under Negotiation)
Contract-3
(Signed)
Contract-2
(Signed)
32. General Communication Program
• Scientific Information Division:
Under BAEC, this division is working for dissemination of information regarding Nuclear applications
and Nuclear Power projects through
Publishing Booklets/ Brochures,
Press release for news media (local & International) etc.
Response to queries placed by phone/letter/email.
attending Science Fairs/Exhibition (focused on Students and Common People),
• TV Shows; Dialogue and Open discussion with News Media :
• Officials from BAEC, NPP key personnel enjoys attending TV/Radio Shows regarding Nuclear
Aspects.
• Seminar and Round Table discussion with Print & Electronic Media also held often.
33. Interaction with Media at Site and National Forum
Recent round table discussion among
BAEC officials and other national experts on
Nuclear Power Programme
34. Interaction with Media at Site and National Forum
International Seminar on Nuclear Power: A chance of successful economic and
socio-political development held on 29-30 May, 2013 at Dhaka.
35. Interaction with Media at Site and National Forum
Interaction between ROSATOM and students of the Nuclear Engineering
department of Dhaka University
38. General Communication Program
• Interaction with Universities, Research Institutes and Academia:
• Educational and Research Organizations are considered as Key Stakeholder of
Rooppur NPP.
• Representatives from these institution are part of Policy making and
implementation of the NPP.
• Discussion and Exchange of information/ opinion takes place in various events.
39. Public Awareness Program
• Reaching Students through TEXTbooks and Hands-on-Experience:
• Initiative for addition of Facts about Nuclear Power Plant has been
taken and expected to be included in upcoming revision
Secondary/Higher Secondary Textbooks
41. Public Information issues
Radiation Application.
Nuclear Safety & Environment protection.
Nuclear Power Program Development Plan.
Benefits of NPP project to local community.
Continuing on Media / Methodology
Nation wide TV / Radio / Newspaper.
Local cable TV / Radio / Newspaper.
Invite local people to visit “TINT Research Reactor” & radiation
utilization – food, agriculture, medical.
Invite local leaders to visit NPP & nearby community in China, Japan.
Future Plan of PI Activities
42. A Round Table Discussion on N-power plant discussion
organized by the Daily Star Newspaper 2009-05-10 A Meeting with local public and people's
representatives in August 2010
Dialogues with the public, the people's representatives at various levels and the
decision makers are being conducted and Round Table Discussion on NPP are
being organized different media and professional bodies these activities
establish the public acceptance level of the Project
BAEC also conducted a limited survey on public acceptance/awareness
about nuclear power programme that clearly described the unique public
acceptance level of the project 42