SlideShare a Scribd company logo
Network Scheduling with Limited Resources
Introduction  ,[object Object],[object Object],[object Object],[object Object],[object Object]
Schedule  Graph  , Unlimited  Resources Labor available Project completion time  18 10 12 6 6 1
Let assume following constraint 10 labor available on any one day  Schedule  Graph , Resource  Limit  Of  10  Men  Cont.. 10 10 10 10 6 6 1
Complexity Of Project Scheduling With Limited Resource ,[object Object],[object Object],[object Object]
Heuristic Programs  ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
Heuristic method for Resource Leveling of Project Schedule ,[object Object],[object Object],[object Object],[object Object]
Early start schedule  graph Manpower loading chart  Maximum slack 7 days so postpone activity 9  Peak requirement 24 Number  over  activity indicates the activity number as well  as  resource.
Schedule  Graph  Manpower loading  chart . Peak requirement reduce to 15  Cont..
Schedule  Graph  Manpower  Loading Chart  Activity 8 is delay by full slack of 2 days Peak requirement occur at days 1, 2  Cont..
Schedule  Graph  Manpower  Loading Chart. Best result obtain by delaying activity 3 by 2 days  Smoothen  histogram Cont..
Smoothing   Peak Resource Requirement
Heuristic Method for Resource Allocation in Project Scheduling ,[object Object],[object Object],[object Object],[object Object]
Day 1  - only one job 7 is available to start in this period and there  are  sufficient  men  to  schedule it. Schedule job 7 , 3 men remain available Only 10 men are available for the project on any day. Resource Day
Day 2-  Job 1,3,4,5 can be started on day 2 , but there are not enough men to schedule them Then second heuristic is applied for scheduling  the jobs with least slack first Schedule job 3( slack=0); 7 men remain Schedule job 4( slack=0); 3 men remain Schedule job 1( slack=3); 2 men remain Job 5 must be delayed , as there are just [2=10-(4+3+1)] men unassigned Postponed the job 5 ( slack =4) Cont..
Day 3-  continue job 3(slack =0); 7 men remain continue job 4(slack =0); 3men remain continue job 1(slack =3); 2men remain Postpone  job 5 (slack =3) Cont..
Day 4 Continue job 4 (slack =0); 6 men remain  Continue job 1 (slack =3); 5 men remain  Job 6  has no slack and hence  is critical , but only 5 men are  still unassigned  Then 3 rd   heuristic is  applied – job 1 could be postponed without  delaying  the project  Reschedule  job 1 ; 6 men remain  Schedule job 6 (slack =0); 0 men remain  Postpone Job 5 (slack =2) Cont..
Cont.. Day Manpower/ resource requirement
Day 5 Continue job 6 (slack=0); 4 men remain  Schedule Job 2 (slack =0); 2 men remain Schedule Job 1 ( slack = 0); 1 men remain  Postpone  job 5 (slack =1) Day 6  Continue Job 6 (slack =0); 4 Men remain . Continue Job 2 (slack =0); 2 Men remain . Continue Job 1 (slack =0); 1 Men remain . Postpone  job 5 (slack =0) Now job 5 is critical but no active job can be postponed without delaying project Cont..
Cont.. Day Manpower
Day 7  Continue Job 1 (slack =1); 9 Men remain  Schedule Job 5 ( slack =0); 4 Men remain  Postpone job 9 ( slack =1) Day 8 Continue Job 5 (slack =0); 5 men remain  Postpone job 9 (slack =0);  No noncritical job can be rescheduled Postpone  Job 8 (Slack =2) Day Manpower
Day 9–  Schedule job 9 ( slack =0); 1 man remain .  Postpone job 8 (slack =2) Day 10 –  Schedule job 10 ( slack =0);  no man remain. Postpone  Job 8 (slack =1) Day 11 – Continue  job 10 (slack =0); no men remain . Postpone Job 8 (slack =0)
Day 12— Continue job 10 (slack =1); no men remain  Postpone Job 8( slack =0) Day 13— Schedule  job 8 ( slack =0); 2 men remain Day 14 –  Continue job 8 ( slack = 0); 2 men remain  Cont.. Manpower Day Final schedule limited resource 1 2 3 4 5 6 7 8 9 10 11 12 13 14 7 7 7 10 9 9 6 6 9 10 10 10 8 8
Other Heuristic Approaches ,[object Object],[object Object],[object Object],[object Object]
[object Object],[object Object],[object Object],Cont..
[object Object],[object Object],[object Object],[object Object],Cont..
Conceptual Problem of Critical Path Analysis When Resource Are Limited
Early start schedule Late Start schedule  Cont.. Day Resource Day Resource 1 2 3 4 5 18 10 10 8 7 1 2 3 4 5 4 4 5 18 22
If resources are limited up to 10 men then optimal early start schedule  and Late start schedule is as follows Early start schedule Day Resource 1 2 3 4 5 6 10  10 10 9 7 7
Late Start schedule  Day Resource 1 2 3 4 5 6 10 10 8 10 7 8
[object Object],[object Object],[object Object],[object Object],[object Object]
Conclusion ,[object Object],[object Object],[object Object],[object Object]
[object Object],[object Object],[object Object],Cont..
[object Object],[object Object],[object Object],[object Object],Cont..
Integer Programming Formulation – Project scheduling with limited Resource ,[object Object],[object Object],[object Object],[object Object],[object Object]
[object Object],[object Object],where k is some number such  that
[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
2 .  Job will be performed : 3. Capacity of shop will not be exceeded  4.No job will be started before its predecessors  are completed  d = 1,……,z  AND  j= 1,….,n  except  beginning job
5 .  No jobs will be split  :
 
 
 

More Related Content

What's hot

Project management - CPM & PERT
Project management   - CPM & PERTProject management   - CPM & PERT
Project management - CPM & PERT
Dr. Varaprasada Rao Manda
 
Session 8 4th edition PMP
Session 8 4th edition PMPSession 8 4th edition PMP
Session 8 4th edition PMP
محمد عصمت عبد الرازق
 
Resource management
Resource managementResource management
Planning and scheduling
Planning and schedulingPlanning and scheduling
Planning and scheduling
Abhishek Kumar
 
ABCs Of Project Time Management Planning Slides
ABCs Of Project Time Management Planning SlidesABCs Of Project Time Management Planning Slides
ABCs Of Project Time Management Planning Slides
Yousef Abugosh, PMP, MA
 
Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )
Akaresh Jose Kaviyil JY
 
Project management cpm-pert
Project management   cpm-pertProject management   cpm-pert
Project management cpm-pert
Dr. Varaprasada Rao Manda
 
EpM
EpMEpM
FINAL REPORT
FINAL REPORTFINAL REPORT
FINAL REPORT
Divya Tadi
 
Syam critical path cpa
Syam critical path cpaSyam critical path cpa
Syam critical path cpa
syamputra
 
PERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLSPERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLS
Zulfiquer Ahmed Amin
 
Unit v mha project evaluation review technique (pert)
Unit  v  mha project evaluation review technique (pert)Unit  v  mha project evaluation review technique (pert)
Unit v mha project evaluation review technique (pert)
anjalatchi
 
Baseline Compliance Analysis
Baseline Compliance AnalysisBaseline Compliance Analysis
Baseline Compliance Analysis
Acumen
 
CAPM Week 2 Chapter 6
CAPM Week 2 Chapter 6CAPM Week 2 Chapter 6
CAPM Week 2 Chapter 6
Muzette Charles, PMP
 
PMBOK Planning Process Group
PMBOK Planning Process GroupPMBOK Planning Process Group
PMBOK Planning Process Group
Curtis Tsang
 
6.3 sequence activities
6.3 sequence activities6.3 sequence activities
6.3 sequence activities
PMVISION Training
 
PertGanttchart
PertGanttchartPertGanttchart
PertGanttchart
learnt
 
Project Management focused on Scheduling of a Project
Project Management focused on Scheduling of a ProjectProject Management focused on Scheduling of a Project
Project Management focused on Scheduling of a Project
Meryem Yıldız
 
How Does MS Project Works 6- Task Controlling Factors
How Does MS Project Works 6- Task Controlling FactorsHow Does MS Project Works 6- Task Controlling Factors
How Does MS Project Works 6- Task Controlling Factors
SHAZEBALIKHAN1
 
Project Scheduling
Project SchedulingProject Scheduling
Project Scheduling
Baker Khader Abdallah, PMP
 

What's hot (20)

Project management - CPM & PERT
Project management   - CPM & PERTProject management   - CPM & PERT
Project management - CPM & PERT
 
Session 8 4th edition PMP
Session 8 4th edition PMPSession 8 4th edition PMP
Session 8 4th edition PMP
 
Resource management
Resource managementResource management
Resource management
 
Planning and scheduling
Planning and schedulingPlanning and scheduling
Planning and scheduling
 
ABCs Of Project Time Management Planning Slides
ABCs Of Project Time Management Planning SlidesABCs Of Project Time Management Planning Slides
ABCs Of Project Time Management Planning Slides
 
Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )
 
Project management cpm-pert
Project management   cpm-pertProject management   cpm-pert
Project management cpm-pert
 
EpM
EpMEpM
EpM
 
FINAL REPORT
FINAL REPORTFINAL REPORT
FINAL REPORT
 
Syam critical path cpa
Syam critical path cpaSyam critical path cpa
Syam critical path cpa
 
PERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLSPERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLS
 
Unit v mha project evaluation review technique (pert)
Unit  v  mha project evaluation review technique (pert)Unit  v  mha project evaluation review technique (pert)
Unit v mha project evaluation review technique (pert)
 
Baseline Compliance Analysis
Baseline Compliance AnalysisBaseline Compliance Analysis
Baseline Compliance Analysis
 
CAPM Week 2 Chapter 6
CAPM Week 2 Chapter 6CAPM Week 2 Chapter 6
CAPM Week 2 Chapter 6
 
PMBOK Planning Process Group
PMBOK Planning Process GroupPMBOK Planning Process Group
PMBOK Planning Process Group
 
6.3 sequence activities
6.3 sequence activities6.3 sequence activities
6.3 sequence activities
 
PertGanttchart
PertGanttchartPertGanttchart
PertGanttchart
 
Project Management focused on Scheduling of a Project
Project Management focused on Scheduling of a ProjectProject Management focused on Scheduling of a Project
Project Management focused on Scheduling of a Project
 
How Does MS Project Works 6- Task Controlling Factors
How Does MS Project Works 6- Task Controlling FactorsHow Does MS Project Works 6- Task Controlling Factors
How Does MS Project Works 6- Task Controlling Factors
 
Project Scheduling
Project SchedulingProject Scheduling
Project Scheduling
 

Viewers also liked

Bar chart
Bar chartBar chart
Network scheduling
Network schedulingNetwork scheduling
Network scheduling
Ravi Shekhar
 
Pert
PertPert
Pert
corvinno
 
Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)
Abhishek Pachisia
 
Jollibee food corporation
Jollibee food corporationJollibee food corporation
Jollibee food corporation
Rohit Sharma
 
P E R T
P E R TP E R T
P E R T
Vikas Verma
 

Viewers also liked (6)

Bar chart
Bar chartBar chart
Bar chart
 
Network scheduling
Network schedulingNetwork scheduling
Network scheduling
 
Pert
PertPert
Pert
 
Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)
 
Jollibee food corporation
Jollibee food corporationJollibee food corporation
Jollibee food corporation
 
P E R T
P E R TP E R T
P E R T
 

Similar to Network scheduling with limited_resources- revised1

Resource Planning
Resource PlanningResource Planning
Resource Planning
Wajahat Ali
 
Lukas.joe
Lukas.joeLukas.joe
Lukas.joe
NASAPMC
 
Lukas.joe
Lukas.joeLukas.joe
Lukas.joe
NASAPMC
 
Resource-Allocation.ppt
Resource-Allocation.pptResource-Allocation.ppt
Resource-Allocation.ppt
TecnicoItca
 
PMGT 510Principles of Project ManagementGroup Assign.docx
PMGT 510Principles of Project ManagementGroup Assign.docxPMGT 510Principles of Project ManagementGroup Assign.docx
PMGT 510Principles of Project ManagementGroup Assign.docx
stilliegeorgiana
 
Critical Path MethodIntroductionOnce you have the network diag.docx
Critical Path MethodIntroductionOnce you have the network diag.docxCritical Path MethodIntroductionOnce you have the network diag.docx
Critical Path MethodIntroductionOnce you have the network diag.docx
annettsparrow
 
Program_Evaluation_and_Review_Technique.pptx
Program_Evaluation_and_Review_Technique.pptxProgram_Evaluation_and_Review_Technique.pptx
Program_Evaluation_and_Review_Technique.pptx
mamtabisht10
 
How to change working days and time in MS Project?
How to change working days and time in MS Project?How to change working days and time in MS Project?
How to change working days and time in MS Project?
SHAZEBALIKHAN1
 
Understanding Microsoft Project 'Calendars' ‘Working Time’, etc
Understanding Microsoft Project 'Calendars' ‘Working Time’, etcUnderstanding Microsoft Project 'Calendars' ‘Working Time’, etc
Understanding Microsoft Project 'Calendars' ‘Working Time’, etc
Khalid Noor Mohammed
 
Approaches to real time scheduling
Approaches to real time schedulingApproaches to real time scheduling
Approaches to real time scheduling
Kamal Acharya
 
06 projecttimemanagement
06 projecttimemanagement06 projecttimemanagement
06 projecttimemanagement
Dhamo daran
 
Resource Scheduling
Resource Scheduling  Resource Scheduling
Resource Scheduling
Nicola2903
 
Pert Cpm Nis
Pert   Cpm NisPert   Cpm Nis
Pert Cpm Nis
Naveed Salman
 
Om chapter 14
Om chapter 14Om chapter 14
Om chapter 14
sameeksha jain
 
Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-
seminiMaya
 
Primavera presentation
Primavera presentationPrimavera presentation
Primavera presentation
Nithin Dev
 
Seminar on pert
Seminar on pertSeminar on pert
Seminar on pert
Santosh Kumari
 
Ms Project 2007(Basic)
Ms Project 2007(Basic)Ms Project 2007(Basic)
Ms Project 2007(Basic)
Dinesh Singh
 
Module :-5 project scheduling and resource levelling
Module :-5 project scheduling and resource levellingModule :-5 project scheduling and resource levelling
Module :-5 project scheduling and resource levelling
Shree Swami atmanand saraswati inst. of technology, surat
 
MS Project - Lesson #4 - Working With CalendarsObjectives - MS.docx
MS Project - Lesson #4 - Working With CalendarsObjectives - MS.docxMS Project - Lesson #4 - Working With CalendarsObjectives - MS.docx
MS Project - Lesson #4 - Working With CalendarsObjectives - MS.docx
rosemarybdodson23141
 

Similar to Network scheduling with limited_resources- revised1 (20)

Resource Planning
Resource PlanningResource Planning
Resource Planning
 
Lukas.joe
Lukas.joeLukas.joe
Lukas.joe
 
Lukas.joe
Lukas.joeLukas.joe
Lukas.joe
 
Resource-Allocation.ppt
Resource-Allocation.pptResource-Allocation.ppt
Resource-Allocation.ppt
 
PMGT 510Principles of Project ManagementGroup Assign.docx
PMGT 510Principles of Project ManagementGroup Assign.docxPMGT 510Principles of Project ManagementGroup Assign.docx
PMGT 510Principles of Project ManagementGroup Assign.docx
 
Critical Path MethodIntroductionOnce you have the network diag.docx
Critical Path MethodIntroductionOnce you have the network diag.docxCritical Path MethodIntroductionOnce you have the network diag.docx
Critical Path MethodIntroductionOnce you have the network diag.docx
 
Program_Evaluation_and_Review_Technique.pptx
Program_Evaluation_and_Review_Technique.pptxProgram_Evaluation_and_Review_Technique.pptx
Program_Evaluation_and_Review_Technique.pptx
 
How to change working days and time in MS Project?
How to change working days and time in MS Project?How to change working days and time in MS Project?
How to change working days and time in MS Project?
 
Understanding Microsoft Project 'Calendars' ‘Working Time’, etc
Understanding Microsoft Project 'Calendars' ‘Working Time’, etcUnderstanding Microsoft Project 'Calendars' ‘Working Time’, etc
Understanding Microsoft Project 'Calendars' ‘Working Time’, etc
 
Approaches to real time scheduling
Approaches to real time schedulingApproaches to real time scheduling
Approaches to real time scheduling
 
06 projecttimemanagement
06 projecttimemanagement06 projecttimemanagement
06 projecttimemanagement
 
Resource Scheduling
Resource Scheduling  Resource Scheduling
Resource Scheduling
 
Pert Cpm Nis
Pert   Cpm NisPert   Cpm Nis
Pert Cpm Nis
 
Om chapter 14
Om chapter 14Om chapter 14
Om chapter 14
 
Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-
 
Primavera presentation
Primavera presentationPrimavera presentation
Primavera presentation
 
Seminar on pert
Seminar on pertSeminar on pert
Seminar on pert
 
Ms Project 2007(Basic)
Ms Project 2007(Basic)Ms Project 2007(Basic)
Ms Project 2007(Basic)
 
Module :-5 project scheduling and resource levelling
Module :-5 project scheduling and resource levellingModule :-5 project scheduling and resource levelling
Module :-5 project scheduling and resource levelling
 
MS Project - Lesson #4 - Working With CalendarsObjectives - MS.docx
MS Project - Lesson #4 - Working With CalendarsObjectives - MS.docxMS Project - Lesson #4 - Working With CalendarsObjectives - MS.docx
MS Project - Lesson #4 - Working With CalendarsObjectives - MS.docx
 

Recently uploaded

ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
PECB
 
คำศัพท์ คำพื้นฐานการอ่าน ภาษาอังกฤษ ระดับชั้น ม.1
คำศัพท์ คำพื้นฐานการอ่าน ภาษาอังกฤษ ระดับชั้น ม.1คำศัพท์ คำพื้นฐานการอ่าน ภาษาอังกฤษ ระดับชั้น ม.1
คำศัพท์ คำพื้นฐานการอ่าน ภาษาอังกฤษ ระดับชั้น ม.1
สมใจ จันสุกสี
 
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdfবাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
eBook.com.bd (প্রয়োজনীয় বাংলা বই)
 
Digital Artefact 1 - Tiny Home Environmental Design
Digital Artefact 1 - Tiny Home Environmental DesignDigital Artefact 1 - Tiny Home Environmental Design
Digital Artefact 1 - Tiny Home Environmental Design
amberjdewit93
 
PCOS corelations and management through Ayurveda.
PCOS corelations and management through Ayurveda.PCOS corelations and management through Ayurveda.
PCOS corelations and management through Ayurveda.
Dr. Shivangi Singh Parihar
 
What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...
What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...
What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...
GeorgeMilliken2
 
NEWSPAPERS - QUESTION 1 - REVISION POWERPOINT.pptx
NEWSPAPERS - QUESTION 1 - REVISION POWERPOINT.pptxNEWSPAPERS - QUESTION 1 - REVISION POWERPOINT.pptx
NEWSPAPERS - QUESTION 1 - REVISION POWERPOINT.pptx
iammrhaywood
 
RHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem students
RHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem studentsRHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem students
RHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem students
Himanshu Rai
 
How to Setup Warehouse & Location in Odoo 17 Inventory
How to Setup Warehouse & Location in Odoo 17 InventoryHow to Setup Warehouse & Location in Odoo 17 Inventory
How to Setup Warehouse & Location in Odoo 17 Inventory
Celine George
 
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdfANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
Priyankaranawat4
 
Cognitive Development Adolescence Psychology
Cognitive Development Adolescence PsychologyCognitive Development Adolescence Psychology
Cognitive Development Adolescence Psychology
paigestewart1632
 
UGC NET Exam Paper 1- Unit 1:Teaching Aptitude
UGC NET Exam Paper 1- Unit 1:Teaching AptitudeUGC NET Exam Paper 1- Unit 1:Teaching Aptitude
UGC NET Exam Paper 1- Unit 1:Teaching Aptitude
S. Raj Kumar
 
C1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptx
C1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptxC1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptx
C1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptx
mulvey2
 
Advanced Java[Extra Concepts, Not Difficult].docx
Advanced Java[Extra Concepts, Not Difficult].docxAdvanced Java[Extra Concepts, Not Difficult].docx
Advanced Java[Extra Concepts, Not Difficult].docx
adhitya5119
 
A Independência da América Espanhola LAPBOOK.pdf
A Independência da América Espanhola LAPBOOK.pdfA Independência da América Espanhola LAPBOOK.pdf
A Independência da América Espanhola LAPBOOK.pdf
Jean Carlos Nunes Paixão
 
Pollock and Snow "DEIA in the Scholarly Landscape, Session One: Setting Expec...
Pollock and Snow "DEIA in the Scholarly Landscape, Session One: Setting Expec...Pollock and Snow "DEIA in the Scholarly Landscape, Session One: Setting Expec...
Pollock and Snow "DEIA in the Scholarly Landscape, Session One: Setting Expec...
National Information Standards Organization (NISO)
 
Film vocab for eal 3 students: Australia the movie
Film vocab for eal 3 students: Australia the movieFilm vocab for eal 3 students: Australia the movie
Film vocab for eal 3 students: Australia the movie
Nicholas Montgomery
 
How to Make a Field Mandatory in Odoo 17
How to Make a Field Mandatory in Odoo 17How to Make a Field Mandatory in Odoo 17
How to Make a Field Mandatory in Odoo 17
Celine George
 
PIMS Job Advertisement 2024.pdf Islamabad
PIMS Job Advertisement 2024.pdf IslamabadPIMS Job Advertisement 2024.pdf Islamabad
PIMS Job Advertisement 2024.pdf Islamabad
AyyanKhan40
 
Reimagining Your Library Space: How to Increase the Vibes in Your Library No ...
Reimagining Your Library Space: How to Increase the Vibes in Your Library No ...Reimagining Your Library Space: How to Increase the Vibes in Your Library No ...
Reimagining Your Library Space: How to Increase the Vibes in Your Library No ...
Diana Rendina
 

Recently uploaded (20)

ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
 
คำศัพท์ คำพื้นฐานการอ่าน ภาษาอังกฤษ ระดับชั้น ม.1
คำศัพท์ คำพื้นฐานการอ่าน ภาษาอังกฤษ ระดับชั้น ม.1คำศัพท์ คำพื้นฐานการอ่าน ภาษาอังกฤษ ระดับชั้น ม.1
คำศัพท์ คำพื้นฐานการอ่าน ภาษาอังกฤษ ระดับชั้น ม.1
 
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdfবাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
 
Digital Artefact 1 - Tiny Home Environmental Design
Digital Artefact 1 - Tiny Home Environmental DesignDigital Artefact 1 - Tiny Home Environmental Design
Digital Artefact 1 - Tiny Home Environmental Design
 
PCOS corelations and management through Ayurveda.
PCOS corelations and management through Ayurveda.PCOS corelations and management through Ayurveda.
PCOS corelations and management through Ayurveda.
 
What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...
What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...
What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...
 
NEWSPAPERS - QUESTION 1 - REVISION POWERPOINT.pptx
NEWSPAPERS - QUESTION 1 - REVISION POWERPOINT.pptxNEWSPAPERS - QUESTION 1 - REVISION POWERPOINT.pptx
NEWSPAPERS - QUESTION 1 - REVISION POWERPOINT.pptx
 
RHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem students
RHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem studentsRHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem students
RHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem students
 
How to Setup Warehouse & Location in Odoo 17 Inventory
How to Setup Warehouse & Location in Odoo 17 InventoryHow to Setup Warehouse & Location in Odoo 17 Inventory
How to Setup Warehouse & Location in Odoo 17 Inventory
 
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdfANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
 
Cognitive Development Adolescence Psychology
Cognitive Development Adolescence PsychologyCognitive Development Adolescence Psychology
Cognitive Development Adolescence Psychology
 
UGC NET Exam Paper 1- Unit 1:Teaching Aptitude
UGC NET Exam Paper 1- Unit 1:Teaching AptitudeUGC NET Exam Paper 1- Unit 1:Teaching Aptitude
UGC NET Exam Paper 1- Unit 1:Teaching Aptitude
 
C1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptx
C1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptxC1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptx
C1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptx
 
Advanced Java[Extra Concepts, Not Difficult].docx
Advanced Java[Extra Concepts, Not Difficult].docxAdvanced Java[Extra Concepts, Not Difficult].docx
Advanced Java[Extra Concepts, Not Difficult].docx
 
A Independência da América Espanhola LAPBOOK.pdf
A Independência da América Espanhola LAPBOOK.pdfA Independência da América Espanhola LAPBOOK.pdf
A Independência da América Espanhola LAPBOOK.pdf
 
Pollock and Snow "DEIA in the Scholarly Landscape, Session One: Setting Expec...
Pollock and Snow "DEIA in the Scholarly Landscape, Session One: Setting Expec...Pollock and Snow "DEIA in the Scholarly Landscape, Session One: Setting Expec...
Pollock and Snow "DEIA in the Scholarly Landscape, Session One: Setting Expec...
 
Film vocab for eal 3 students: Australia the movie
Film vocab for eal 3 students: Australia the movieFilm vocab for eal 3 students: Australia the movie
Film vocab for eal 3 students: Australia the movie
 
How to Make a Field Mandatory in Odoo 17
How to Make a Field Mandatory in Odoo 17How to Make a Field Mandatory in Odoo 17
How to Make a Field Mandatory in Odoo 17
 
PIMS Job Advertisement 2024.pdf Islamabad
PIMS Job Advertisement 2024.pdf IslamabadPIMS Job Advertisement 2024.pdf Islamabad
PIMS Job Advertisement 2024.pdf Islamabad
 
Reimagining Your Library Space: How to Increase the Vibes in Your Library No ...
Reimagining Your Library Space: How to Increase the Vibes in Your Library No ...Reimagining Your Library Space: How to Increase the Vibes in Your Library No ...
Reimagining Your Library Space: How to Increase the Vibes in Your Library No ...
 

Network scheduling with limited_resources- revised1

  • 1. Network Scheduling with Limited Resources
  • 2.
  • 3. Schedule Graph , Unlimited Resources Labor available Project completion time 18 10 12 6 6 1
  • 4. Let assume following constraint 10 labor available on any one day Schedule Graph , Resource Limit Of 10 Men Cont.. 10 10 10 10 6 6 1
  • 5.
  • 6.
  • 7.
  • 8. Early start schedule graph Manpower loading chart Maximum slack 7 days so postpone activity 9 Peak requirement 24 Number over activity indicates the activity number as well as resource.
  • 9. Schedule Graph Manpower loading chart . Peak requirement reduce to 15 Cont..
  • 10. Schedule Graph Manpower Loading Chart Activity 8 is delay by full slack of 2 days Peak requirement occur at days 1, 2 Cont..
  • 11. Schedule Graph Manpower Loading Chart. Best result obtain by delaying activity 3 by 2 days Smoothen histogram Cont..
  • 12. Smoothing Peak Resource Requirement
  • 13.
  • 14. Day 1 - only one job 7 is available to start in this period and there are sufficient men to schedule it. Schedule job 7 , 3 men remain available Only 10 men are available for the project on any day. Resource Day
  • 15. Day 2- Job 1,3,4,5 can be started on day 2 , but there are not enough men to schedule them Then second heuristic is applied for scheduling the jobs with least slack first Schedule job 3( slack=0); 7 men remain Schedule job 4( slack=0); 3 men remain Schedule job 1( slack=3); 2 men remain Job 5 must be delayed , as there are just [2=10-(4+3+1)] men unassigned Postponed the job 5 ( slack =4) Cont..
  • 16. Day 3- continue job 3(slack =0); 7 men remain continue job 4(slack =0); 3men remain continue job 1(slack =3); 2men remain Postpone job 5 (slack =3) Cont..
  • 17. Day 4 Continue job 4 (slack =0); 6 men remain Continue job 1 (slack =3); 5 men remain Job 6 has no slack and hence is critical , but only 5 men are still unassigned Then 3 rd heuristic is applied – job 1 could be postponed without delaying the project Reschedule job 1 ; 6 men remain Schedule job 6 (slack =0); 0 men remain Postpone Job 5 (slack =2) Cont..
  • 18. Cont.. Day Manpower/ resource requirement
  • 19. Day 5 Continue job 6 (slack=0); 4 men remain Schedule Job 2 (slack =0); 2 men remain Schedule Job 1 ( slack = 0); 1 men remain Postpone job 5 (slack =1) Day 6 Continue Job 6 (slack =0); 4 Men remain . Continue Job 2 (slack =0); 2 Men remain . Continue Job 1 (slack =0); 1 Men remain . Postpone job 5 (slack =0) Now job 5 is critical but no active job can be postponed without delaying project Cont..
  • 21. Day 7 Continue Job 1 (slack =1); 9 Men remain Schedule Job 5 ( slack =0); 4 Men remain Postpone job 9 ( slack =1) Day 8 Continue Job 5 (slack =0); 5 men remain Postpone job 9 (slack =0); No noncritical job can be rescheduled Postpone Job 8 (Slack =2) Day Manpower
  • 22. Day 9– Schedule job 9 ( slack =0); 1 man remain . Postpone job 8 (slack =2) Day 10 – Schedule job 10 ( slack =0); no man remain. Postpone Job 8 (slack =1) Day 11 – Continue job 10 (slack =0); no men remain . Postpone Job 8 (slack =0)
  • 23. Day 12— Continue job 10 (slack =1); no men remain Postpone Job 8( slack =0) Day 13— Schedule job 8 ( slack =0); 2 men remain Day 14 – Continue job 8 ( slack = 0); 2 men remain Cont.. Manpower Day Final schedule limited resource 1 2 3 4 5 6 7 8 9 10 11 12 13 14 7 7 7 10 9 9 6 6 9 10 10 10 8 8
  • 24.
  • 25.
  • 26.
  • 27. Conceptual Problem of Critical Path Analysis When Resource Are Limited
  • 28. Early start schedule Late Start schedule Cont.. Day Resource Day Resource 1 2 3 4 5 18 10 10 8 7 1 2 3 4 5 4 4 5 18 22
  • 29. If resources are limited up to 10 men then optimal early start schedule and Late start schedule is as follows Early start schedule Day Resource 1 2 3 4 5 6 10 10 10 9 7 7
  • 30. Late Start schedule Day Resource 1 2 3 4 5 6 10 10 8 10 7 8
  • 31.
  • 32.
  • 33.
  • 34.
  • 35.
  • 36.
  • 37.
  • 38. 2 . Job will be performed : 3. Capacity of shop will not be exceeded 4.No job will be started before its predecessors are completed d = 1,……,z AND j= 1,….,n except beginning job
  • 39. 5 . No jobs will be split :
  • 40.  
  • 41.  
  • 42.