DECISION MAKING AND
PROBLEM SOLVING
PROJECT REPORT BY:
DIVYA RAJASRI TADI #13
YAN XINGZHOU #18
CONTENTS
INTRODUCTION
PROJECT: GLOBAL OIL CREDIT CARD OPERATION
OUR PROBLEM STATEMENT
THE NETWORK DIAGRAM
USE OF DUMMY ACTIVITIES
FINDING THE CRITICAL PATH
CRASHING THE COST
SUMMARY
REFERENCES
INTRODUCTION
The task of managing major projects is an ancient and honorable art.
Around 2600 B.C., the Egyptians claimed that 400,000 men worked
for 20 years to build the Great Pyramid for King Khufu. Modern
projects ranging from building a suburban shopping center to putting
a man on the moon are amazingly large, complex, and costly.
Completing such projects on time and within the budget is a
herculean task. In particular, the complicated problems of scheduling
massive projects are often structured by the interdependence of
activities. While dealing with projects involving thousands of
dependency relations, managers seek various effective methods of
analysis.
The PERT (project evaluation and review technique) commonly used
in conjunction with the critical path method (CPM), is one such
statistical tool used in project management. PERT is a method to
analyze the involved tasks in completing a given project, especially
the time needed to complete each task, and to identify the minimum
time needed to complete the total project. It was developed primarily
to simplify the planning and scheduling of large and complex projects
for the U.S. Navy Special Projects Office in 1957 to support the U.S.
Navy's Polaris nuclear submarine project. It was able to incorporate
uncertainty by making it possible to schedule a project while not
knowing precisely the details and durations of all the activities. It is
more of an event-oriented technique rather than start- and
completion-oriented, and is used more in projects where time is the
major factor rather than cost. It is applied to very large-scale, one-
time, complex, non-routine infrastructure and Research and
Development projects. An example of this was for the 1968 Winter
Olympics in Grenoble which applied PERT from 1965 until the
opening of the 1968 Games.
PROJECT: THE GLOBAL OIL CREDIT CARD
OPERATION
A crucial project for Rebecca Goldstein and Global Oil is, moving
their credit card operations from the home office in Dallas to Des
Moines, Iowa. Global Oil board of directors have set a deadline of 22
weeks to accomplish this project.
This project involves the following tasks –
 Real estate selecting one of three available office sites
 Personnel determining
 how many employees move from Dallas
 how many new employees will be hired
 who will train the newly hired employees
 Systems group must implement the operating procedures
 Treasurer’s office must organize the financial arrangements
 Architects have to design the interior space and oversee
needed structural improvements
Each of the sites that Global is considering is an existing building with
the appropriate amount of open space. However, office partitions,
computer facilities, furnishings, and so on, must all be provided. A
second complicating factor is that there is an interdependence of
activities. In other words, some parts of the project cannot be started
until other parts are completed like Global cannot construct the
interior of an office before it has been designed. Neither can it hire
new employees until it has determined its personnel requirements.
OUR PROBLEM STATEMENT
As the managers in the Operations Analysis Group, we are in charge
of planning the move, seeing that everything comes off according to
plan, and making sure that the deadline is met.
We know that PERT and CPM are specifically designed for projects
of this sort. We begin with the first step in the process that is to define
the activities in the project and to establish the proper precedence
relationships. This is an important first step since errors or omissions
at this stage can lead to a disastrously inaccurate schedule.
Table 14.1 shows the first activity list that we have prepared for the
move (the columns labeled “Time” and “Resources” are indications of
things to come). Each activity is placed on a separate line, and its
immediate predecessors are recorded on the same line. The
immediate predecessors of an activity are those activities that must
be completed prior to the start of the activity in question. For
example, in Table 14.1 we see that Global cannot start activity C,
determine personnel requirements, until activity B, create the
organizational and financial plan, is completed. Similarly, activity G,
hire new employees, cannot begin until activity F, select the Global
personnel that will move from Texas to Iowa, is completed. This
activity, F, in turn, cannot start until activity C, determine personnel
requirements, is completed.
THE NETWORK DIAGRAM
Defining in the PERT network diagram:
Branch – the arrow representing each activity
Node – the circle indicating the beginning and end of each activity
Event - represents the completion of activities that lead into a node
Referring to the activity list in Table 14.1, we see that “select office
site” is termed activity A. When this activity is completed, the event
“office site selected” occurs. Constructing the Network Diagram
Figure 14.2 shows a network diagram for activities A through C. We
emphasize at the outset that the numbers assigned to the nodes are
arbitrary.
They are simply used to identify events and do not imply anything
about precedence relationships. Indeed, we shall renumber the node
that terminates activity C several times as we develop the network
diagram for this project, but correct precedence relationships will
always be preserved. In the network diagram each activity must start
at the node in which its immediate predecessors ended. For example,
in Figure 14.2, activity C starts at node 3 because its immediate
predecessor, activity B, ended there. We see, that complications
arise as we attempt to add activity D to the network diagram. Both A
and C are immediate predecessors to D, and since we want to show
any activity such as D only once in our diagram, nodes 2 and 4 in
Figure 14.2 must be combined, and D should start from this new
node. This is shown in Figure 14.3. Node 3 now represents the event
that both activities A and C have been completed. Note that activity
E, which has only D as an immediate predecessor, can be added with
no difficulty. However, as we attempt to add activity F, a new problem
arises. Since F has C as an immediate predecessor, it would
emanate from node 3 (of Figure 14.3).
We see, however, that this would imply that F also has A as an
immediate predecessor, which is incorrect.
USE OF DUMMY ACTIVITIES
This diagramming dilemma is solved by introducing a dummy activity,
which is represented by a dashed line in the network diagram in
Figure 14.4.
This dummy activity is fictitious in the sense that it requires no time or
resources. It merely provides a pedagogical device that enables us to
draw a network representation that correctly maintains the
appropriate precedence relationships. Thus, Figure 14.4 indicates
that activity D can begin only after both activities A and C have been
completed. Similarly, activity F can occur only after activity C is
completed.
Figure 14.5 shows the network diagram for the first activity list as
presented in Figure 14.5.
A dummy activity can be used to cure this condition. Figure 14.6
illustrates the procedure. Since the dummy activity requires no time,
the correct time and precedent relationships are maintained.
This new representation has been introduced into Figure 14.7. Many
software packages do not require that these dummy activities be
input. Thus, for our purposes, they serve mainly the pedagogical goal
of correctly portraying the precedence relations (i.e., as used in
Figure 14.4).
We note that activities G and H both start at node 6 and terminate at
node 7. This does not present a problem in portraying the appropriate
precedence relationships, since only activity J starts at node 7. This
might, however, create a problem for certain software packages used
to solve PERT and CPM problems. In some of these programs, each
activity is identified by the number of its starting and ending node. If
such a program is to be used, the representation of G and H in Figure
14.5 would lead the computer to regard them as the same activity.
This would be incorrect, since in fact activities G and H are not the
same.
FINDING THE CRITICAL PATH
The Critical Path Method (CPM) is one of several related techniques
for doing project planning. CPM is for projects that are made up of a
number of individual "activities." If some of the activities require other
activities to finish before they can start, then the project becomes a
complex web of activities. Now, as mentioned earlier we have a 10
steps activity list.
A. Selecting Office Site
B. Creating Organizational and Financial Plan
C. Determining Personnel Requirements
D. Designing Facility
E. Constructing Interior
F. Selecting Personnel to Move
G. Hiring New Employees
H. Moving Records, Key Personnel, etc.
I. Making Financial Arrangements
J. Training New Personnel
After listing all these steps above, we need to collect data to estimate
the expected activity time. As what we have learned from the class,
we know there are three different types of estimate from different
perspectives.
Optimistic time (a): is the minimum time, which requires
everything has to go perfectly to achieve this time.
Most probable time (m): is the most likely time, where everything
is under normal circumstances.
Pessimistic time (b): is the maximum time, which follows where
something can go wrong.
By understanding these different perspectives of estimate we have
come with a table shown below.
Based on the original development of the PERT approach (during the
late 1950s), the procedure for estimating the expected value of the
activity times was motivated by the assumption that the activity time
was random variable with a particular probability distribution.
The figure shows the Construct Interior time use the probability
distribution, which gives us these formula above the chart.
The next step is to draw the Network Diagram to show the
relationships and the project process. And it is also the same time to
use CPM find critical path, which is the route cost most of your time in
this project. To complete the Network Diagram, we need to use some
dummy path the cure the incorrect relationship between activities and
crate a smooth path through the whole process.
Then we will find several path through 1 (the start) to 9 (the end).
1. A,D,E,J: and the total time will cost it = 3+4+8+3 = 18
2. B,C,D,E,J: and the total time will cost it = 5+3+4+8+3 = 23, which is
the CP.
3. B,C,F,H,J: and the total time will cost it = 5+3+2+2+3 = 15
4. B,C,F,G,J: and the total time will cost it = 5+3+2+4+3 = 17
5. B,I: and the total time will cost it = 5+5 =10
By finding the critical path, we will know is we let this project go, it will
spend more time as the board directors required. In the case, we need
to do the crash to this project.
CRASHING THE COST
Because the company usually does not share this information with
the public, so we created the chart below to demonstrate the
process of crashing the cost.
The critical path is B,C,D,E,J under this crash situation, the total
time will be: 3+1+2+5+1=11, which is almost half of what the board
directors want. The total cost of crushing will be
2*150+2*250+2*2500+3*10000+2*2500 =
300+500+5000+30000+5000 = $40800. As the CP is already
crashed, we need to crash the other paths to 11 to meet the final
goal along with the CP.
This figure above is the new Network Diagram which shows the normal
time and also the crash time.
On analyzing all the other paths again, we found that:
1. A,D,E,J = 3+2+5+1= 11 which does not need any change as it meets
the CP after the crash.
2. B,C,F,H,J = 3+1+2+2+1= 9 also does not need any crash.
3. B,C,F,G,J = 3+1+2+4+1= 11 same result as first path.
4. B,I = 3+5 =8 which was always less and does not need to crash.
So to the final decision is that we just need to crash the CP to get what
we want for this project, and the cost will be $40800.
As we all know, CPM and PERT try to reduce the time and cost of a
project. From the chart above, we find the original cost is $148400, and
the normal cost is $97700. However, we do not need to spend all of the
$148400 to finish the project within 11 weeks. The cost for 11 weeks will
be $40800+$97700= $138500. And this saves about $9900.
SUMMARY
Using the PERT and CMP give us an opportunity to eliminate extra cost
on unnecessary activity, which does not affect the total project time, to
not only save the cost, but also reduce the time for the project.
We started with a strategic analysis, as we aimed to keep the cost as
minimum as possible. Our responsibility was to move the credit card
operations from Dallas office to Iowa office for Global Oil within 22
weeks and $148400.
Implementing all the skills and techniques learnt in this class, we came
to a conclusion that PERT and CPM work best for this type of a project.
We started by making an activity list and then build network diagrams
and finally crashed the time as well as the cost required to implement
this project. We have been successful in determining how this project
can be completed within 11 weeks of time and with an expenditure of
$138500 only.
Thus, we have achieved our goal and made this project a success.
REFERENCES
 https://www.google.com/search?q=decision+making&espv=2&biw=15
36&bih=758&source=lnms&tbm=isch&sa=X&ei=PAY4VYTAG8TIsQSW
5IFg&ved=0CAYQ_AUoAQ
 http://smallbusiness.chron.com/cpm-pert-weaknesses-strengths-
1082.html
 http://en.wikipedia.org/wiki/Program_evaluation_and_review_techni
que
 http://www.interventions.org/pertcpm.html
 https://www.youtube.com/watch?v=LdRZN5o08Em
 http://www.mindtools.com/critpath.html
 http://www.slideshare.net/dubey1992/pert-cpm-project-
management
 https://www.boundless.com/management/textbooks/boundless-
management-textbook/control-8/financial-and-project-management-
tools-of-control-64/cpm-and-pert-charts-324-4024/
 http://civilengineersforum.com/pert-cpm/

More Related Content

What's hot

Project Management Report
Project Management ReportProject Management Report
Project Management ReportSANKET SENAPATI
 
Effect of construction delays on project time overrun
Effect of construction delays on project time overrunEffect of construction delays on project time overrun
Effect of construction delays on project time overruneSAT Journals
 
06 project time management
06  project time management06  project time management
06 project time managementAla Ibrahim
 
Project Scope Management -
Project Scope Management - Project Scope Management -
Project Scope Management - dyaksa hanindito
 
A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost managementImran Jamil
 
Work breakdown structure in project management ppt by kiran j
Work breakdown structure in project management ppt by kiran jWork breakdown structure in project management ppt by kiran j
Work breakdown structure in project management ppt by kiran jIIT delhi
 
Project Management Framework
Project Management FrameworkProject Management Framework
Project Management FrameworkRahul Sudame
 
Assignment 1 - Microsoft Project
Assignment 1 - Microsoft ProjectAssignment 1 - Microsoft Project
Assignment 1 - Microsoft ProjectKai Yun Pang
 
Project Management Case Study .EC Harris International Ltd. (Al Wahda Mast...
Project Management Case Study .EC Harris International Ltd.   (Al Wahda Mast...Project Management Case Study .EC Harris International Ltd.   (Al Wahda Mast...
Project Management Case Study .EC Harris International Ltd. (Al Wahda Mast...Malik Liaqat Ali
 
5 phases of project management
5 phases of project management5 phases of project management
5 phases of project managementJared C. Powell
 
Resource Scheduling
Resource SchedulingResource Scheduling
Resource SchedulingNicola2903
 
7. implementation (1) time management
7. implementation (1)   time management 7. implementation (1)   time management
7. implementation (1) time management Dania Abdel-aziz
 
The Network Diagram and Critical Path
The Network Diagram and Critical PathThe Network Diagram and Critical Path
The Network Diagram and Critical Pathdmdk12
 

What's hot (20)

Project Management Report
Project Management ReportProject Management Report
Project Management Report
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
 
Project Management
Project Management Project Management
Project Management
 
Effect of construction delays on project time overrun
Effect of construction delays on project time overrunEffect of construction delays on project time overrun
Effect of construction delays on project time overrun
 
06 project time management
06  project time management06  project time management
06 project time management
 
Project Scope Management -
Project Scope Management - Project Scope Management -
Project Scope Management -
 
A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost management
 
Project Scope Management
Project Scope ManagementProject Scope Management
Project Scope Management
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project Management
 
Work breakdown structure in project management ppt by kiran j
Work breakdown structure in project management ppt by kiran jWork breakdown structure in project management ppt by kiran j
Work breakdown structure in project management ppt by kiran j
 
Project Management Framework
Project Management FrameworkProject Management Framework
Project Management Framework
 
project management
project managementproject management
project management
 
Project Planning and Development
Project Planning and DevelopmentProject Planning and Development
Project Planning and Development
 
Assignment 1 - Microsoft Project
Assignment 1 - Microsoft ProjectAssignment 1 - Microsoft Project
Assignment 1 - Microsoft Project
 
Project Management Case Study .EC Harris International Ltd. (Al Wahda Mast...
Project Management Case Study .EC Harris International Ltd.   (Al Wahda Mast...Project Management Case Study .EC Harris International Ltd.   (Al Wahda Mast...
Project Management Case Study .EC Harris International Ltd. (Al Wahda Mast...
 
5 phases of project management
5 phases of project management5 phases of project management
5 phases of project management
 
Resource Scheduling
Resource SchedulingResource Scheduling
Resource Scheduling
 
7. implementation (1) time management
7. implementation (1)   time management 7. implementation (1)   time management
7. implementation (1) time management
 
The Network Diagram and Critical Path
The Network Diagram and Critical PathThe Network Diagram and Critical Path
The Network Diagram and Critical Path
 
Project planning and project work plan
Project planning and project work planProject planning and project work plan
Project planning and project work plan
 

Similar to FINAL REPORT

Network analysis cpm module3 ppt
Network analysis cpm module3 pptNetwork analysis cpm module3 ppt
Network analysis cpm module3 pptahsanrabbani
 
(PROGRAM EVALUATION AND REVIE TECHNIQUE)
(PROGRAM EVALUATION AND REVIE TECHNIQUE)(PROGRAM EVALUATION AND REVIE TECHNIQUE)
(PROGRAM EVALUATION AND REVIE TECHNIQUE)hannahpepino1
 
Unit.6. network analysis with cpm and pert
Unit.6. network analysis with cpm and pertUnit.6. network analysis with cpm and pert
Unit.6. network analysis with cpm and pertDagnaygebawGoshme
 
Network Problem CPM & PERT
Network Problem CPM &  PERTNetwork Problem CPM &  PERT
Network Problem CPM & PERTPulchowk Campus
 
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.pptTinotendaChivese
 
Appliedresearchmethodologylecture1 111207045430-phpapp01
Appliedresearchmethodologylecture1 111207045430-phpapp01Appliedresearchmethodologylecture1 111207045430-phpapp01
Appliedresearchmethodologylecture1 111207045430-phpapp01Sonali Srivastava
 
Network problem cpm and pert BY MITESH KUMAR
Network problem cpm and pert BY MITESH KUMARNetwork problem cpm and pert BY MITESH KUMAR
Network problem cpm and pert BY MITESH KUMARMitesh Kumar
 
Production & Operation Management Chapter 34, 35[1]
Production & Operation Management Chapter 34, 35[1]Production & Operation Management Chapter 34, 35[1]
Production & Operation Management Chapter 34, 35[1]Hariharan Ponnusamy
 
Critical path method
Critical path methodCritical path method
Critical path methodDhruv Shah
 
4 b. Project management - network analysis
4 b. Project management - network analysis4 b. Project management - network analysis
4 b. Project management - network analysisDr.R. SELVAM
 
MGT 3302, Introduction to Project Management 1 Cou.docx
MGT 3302, Introduction to Project Management 1 Cou.docxMGT 3302, Introduction to Project Management 1 Cou.docx
MGT 3302, Introduction to Project Management 1 Cou.docxadkinspaige22
 

Similar to FINAL REPORT (20)

PERT-Overview1.pdf
PERT-Overview1.pdfPERT-Overview1.pdf
PERT-Overview1.pdf
 
Network analysis cpm module3 ppt
Network analysis cpm module3 pptNetwork analysis cpm module3 ppt
Network analysis cpm module3 ppt
 
(PROGRAM EVALUATION AND REVIE TECHNIQUE)
(PROGRAM EVALUATION AND REVIE TECHNIQUE)(PROGRAM EVALUATION AND REVIE TECHNIQUE)
(PROGRAM EVALUATION AND REVIE TECHNIQUE)
 
Unit.6. network analysis with cpm and pert
Unit.6. network analysis with cpm and pertUnit.6. network analysis with cpm and pert
Unit.6. network analysis with cpm and pert
 
Network Problem CPM & PERT
Network Problem CPM &  PERTNetwork Problem CPM &  PERT
Network Problem CPM & PERT
 
Pert cpm-22-3-21
Pert cpm-22-3-21Pert cpm-22-3-21
Pert cpm-22-3-21
 
Ii. pert cpm
Ii. pert cpmIi. pert cpm
Ii. pert cpm
 
PERT-CPM PPT.pptx
PERT-CPM PPT.pptxPERT-CPM PPT.pptx
PERT-CPM PPT.pptx
 
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
 
Ch08 pm2ndhalf
Ch08 pm2ndhalfCh08 pm2ndhalf
Ch08 pm2ndhalf
 
IGNOU PERT CPM
IGNOU PERT CPMIGNOU PERT CPM
IGNOU PERT CPM
 
Chapter 3.pptx
Chapter 3.pptxChapter 3.pptx
Chapter 3.pptx
 
Appliedresearchmethodologylecture1 111207045430-phpapp01
Appliedresearchmethodologylecture1 111207045430-phpapp01Appliedresearchmethodologylecture1 111207045430-phpapp01
Appliedresearchmethodologylecture1 111207045430-phpapp01
 
Network problem cpm and pert BY MITESH KUMAR
Network problem cpm and pert BY MITESH KUMARNetwork problem cpm and pert BY MITESH KUMAR
Network problem cpm and pert BY MITESH KUMAR
 
Ovi project
Ovi  projectOvi  project
Ovi project
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
Production & Operation Management Chapter 34, 35[1]
Production & Operation Management Chapter 34, 35[1]Production & Operation Management Chapter 34, 35[1]
Production & Operation Management Chapter 34, 35[1]
 
Critical path method
Critical path methodCritical path method
Critical path method
 
4 b. Project management - network analysis
4 b. Project management - network analysis4 b. Project management - network analysis
4 b. Project management - network analysis
 
MGT 3302, Introduction to Project Management 1 Cou.docx
MGT 3302, Introduction to Project Management 1 Cou.docxMGT 3302, Introduction to Project Management 1 Cou.docx
MGT 3302, Introduction to Project Management 1 Cou.docx
 

More from Divya Tadi

Effective commn
Effective commnEffective commn
Effective commnDivya Tadi
 
Effective commn
Effective commnEffective commn
Effective commnDivya Tadi
 
Economics Certificate
Economics CertificateEconomics Certificate
Economics CertificateDivya Tadi
 
Negotiation skills
Negotiation skillsNegotiation skills
Negotiation skillsDivya Tadi
 
Financial Accounting
Financial AccountingFinancial Accounting
Financial AccountingDivya Tadi
 
final team app
final team appfinal team app
final team appDivya Tadi
 
Healthcare domain PPT
Healthcare domain PPTHealthcare domain PPT
Healthcare domain PPTDivya Tadi
 
DW DIMENSN MODELNG
DW DIMENSN MODELNGDW DIMENSN MODELNG
DW DIMENSN MODELNGDivya Tadi
 
HOT TOPIC REPORT DIVYA
HOT TOPIC REPORT DIVYAHOT TOPIC REPORT DIVYA
HOT TOPIC REPORT DIVYADivya Tadi
 
MYREVIEWERS ASAD Project
MYREVIEWERS ASAD ProjectMYREVIEWERS ASAD Project
MYREVIEWERS ASAD ProjectDivya Tadi
 
ADBMS Project Pearl
ADBMS Project PearlADBMS Project Pearl
ADBMS Project PearlDivya Tadi
 

More from Divya Tadi (14)

CBAP
CBAPCBAP
CBAP
 
Effective commn
Effective commnEffective commn
Effective commn
 
Effective commn
Effective commnEffective commn
Effective commn
 
Economics Certificate
Economics CertificateEconomics Certificate
Economics Certificate
 
Negotiation skills
Negotiation skillsNegotiation skills
Negotiation skills
 
Financial Accounting
Financial AccountingFinancial Accounting
Financial Accounting
 
Data
DataData
Data
 
final team app
final team appfinal team app
final team app
 
Healthcare domain PPT
Healthcare domain PPTHealthcare domain PPT
Healthcare domain PPT
 
DW DIMENSN MODELNG
DW DIMENSN MODELNGDW DIMENSN MODELNG
DW DIMENSN MODELNG
 
DM PROJECT
DM PROJECTDM PROJECT
DM PROJECT
 
HOT TOPIC REPORT DIVYA
HOT TOPIC REPORT DIVYAHOT TOPIC REPORT DIVYA
HOT TOPIC REPORT DIVYA
 
MYREVIEWERS ASAD Project
MYREVIEWERS ASAD ProjectMYREVIEWERS ASAD Project
MYREVIEWERS ASAD Project
 
ADBMS Project Pearl
ADBMS Project PearlADBMS Project Pearl
ADBMS Project Pearl
 

FINAL REPORT

  • 1. DECISION MAKING AND PROBLEM SOLVING PROJECT REPORT BY: DIVYA RAJASRI TADI #13 YAN XINGZHOU #18
  • 2. CONTENTS INTRODUCTION PROJECT: GLOBAL OIL CREDIT CARD OPERATION OUR PROBLEM STATEMENT THE NETWORK DIAGRAM USE OF DUMMY ACTIVITIES FINDING THE CRITICAL PATH CRASHING THE COST SUMMARY REFERENCES
  • 3. INTRODUCTION The task of managing major projects is an ancient and honorable art. Around 2600 B.C., the Egyptians claimed that 400,000 men worked for 20 years to build the Great Pyramid for King Khufu. Modern projects ranging from building a suburban shopping center to putting a man on the moon are amazingly large, complex, and costly. Completing such projects on time and within the budget is a herculean task. In particular, the complicated problems of scheduling massive projects are often structured by the interdependence of activities. While dealing with projects involving thousands of dependency relations, managers seek various effective methods of analysis. The PERT (project evaluation and review technique) commonly used in conjunction with the critical path method (CPM), is one such statistical tool used in project management. PERT is a method to analyze the involved tasks in completing a given project, especially the time needed to complete each task, and to identify the minimum time needed to complete the total project. It was developed primarily to simplify the planning and scheduling of large and complex projects for the U.S. Navy Special Projects Office in 1957 to support the U.S. Navy's Polaris nuclear submarine project. It was able to incorporate uncertainty by making it possible to schedule a project while not
  • 4. knowing precisely the details and durations of all the activities. It is more of an event-oriented technique rather than start- and completion-oriented, and is used more in projects where time is the major factor rather than cost. It is applied to very large-scale, one- time, complex, non-routine infrastructure and Research and Development projects. An example of this was for the 1968 Winter Olympics in Grenoble which applied PERT from 1965 until the opening of the 1968 Games. PROJECT: THE GLOBAL OIL CREDIT CARD OPERATION A crucial project for Rebecca Goldstein and Global Oil is, moving their credit card operations from the home office in Dallas to Des Moines, Iowa. Global Oil board of directors have set a deadline of 22 weeks to accomplish this project. This project involves the following tasks –  Real estate selecting one of three available office sites  Personnel determining  how many employees move from Dallas  how many new employees will be hired  who will train the newly hired employees
  • 5.  Systems group must implement the operating procedures  Treasurer’s office must organize the financial arrangements  Architects have to design the interior space and oversee needed structural improvements Each of the sites that Global is considering is an existing building with the appropriate amount of open space. However, office partitions, computer facilities, furnishings, and so on, must all be provided. A second complicating factor is that there is an interdependence of activities. In other words, some parts of the project cannot be started until other parts are completed like Global cannot construct the interior of an office before it has been designed. Neither can it hire new employees until it has determined its personnel requirements. OUR PROBLEM STATEMENT As the managers in the Operations Analysis Group, we are in charge of planning the move, seeing that everything comes off according to plan, and making sure that the deadline is met. We know that PERT and CPM are specifically designed for projects of this sort. We begin with the first step in the process that is to define the activities in the project and to establish the proper precedence
  • 6. relationships. This is an important first step since errors or omissions at this stage can lead to a disastrously inaccurate schedule. Table 14.1 shows the first activity list that we have prepared for the move (the columns labeled “Time” and “Resources” are indications of things to come). Each activity is placed on a separate line, and its immediate predecessors are recorded on the same line. The immediate predecessors of an activity are those activities that must be completed prior to the start of the activity in question. For example, in Table 14.1 we see that Global cannot start activity C, determine personnel requirements, until activity B, create the organizational and financial plan, is completed. Similarly, activity G,
  • 7. hire new employees, cannot begin until activity F, select the Global personnel that will move from Texas to Iowa, is completed. This activity, F, in turn, cannot start until activity C, determine personnel requirements, is completed. THE NETWORK DIAGRAM Defining in the PERT network diagram: Branch – the arrow representing each activity Node – the circle indicating the beginning and end of each activity Event - represents the completion of activities that lead into a node Referring to the activity list in Table 14.1, we see that “select office site” is termed activity A. When this activity is completed, the event “office site selected” occurs. Constructing the Network Diagram Figure 14.2 shows a network diagram for activities A through C. We emphasize at the outset that the numbers assigned to the nodes are arbitrary.
  • 8. They are simply used to identify events and do not imply anything about precedence relationships. Indeed, we shall renumber the node that terminates activity C several times as we develop the network diagram for this project, but correct precedence relationships will always be preserved. In the network diagram each activity must start at the node in which its immediate predecessors ended. For example, in Figure 14.2, activity C starts at node 3 because its immediate predecessor, activity B, ended there. We see, that complications arise as we attempt to add activity D to the network diagram. Both A and C are immediate predecessors to D, and since we want to show any activity such as D only once in our diagram, nodes 2 and 4 in Figure 14.2 must be combined, and D should start from this new node. This is shown in Figure 14.3. Node 3 now represents the event that both activities A and C have been completed. Note that activity E, which has only D as an immediate predecessor, can be added with no difficulty. However, as we attempt to add activity F, a new problem arises. Since F has C as an immediate predecessor, it would emanate from node 3 (of Figure 14.3).
  • 9. We see, however, that this would imply that F also has A as an immediate predecessor, which is incorrect. USE OF DUMMY ACTIVITIES This diagramming dilemma is solved by introducing a dummy activity, which is represented by a dashed line in the network diagram in Figure 14.4. This dummy activity is fictitious in the sense that it requires no time or resources. It merely provides a pedagogical device that enables us to
  • 10. draw a network representation that correctly maintains the appropriate precedence relationships. Thus, Figure 14.4 indicates that activity D can begin only after both activities A and C have been completed. Similarly, activity F can occur only after activity C is completed. Figure 14.5 shows the network diagram for the first activity list as presented in Figure 14.5. A dummy activity can be used to cure this condition. Figure 14.6 illustrates the procedure. Since the dummy activity requires no time, the correct time and precedent relationships are maintained.
  • 11. This new representation has been introduced into Figure 14.7. Many software packages do not require that these dummy activities be input. Thus, for our purposes, they serve mainly the pedagogical goal of correctly portraying the precedence relations (i.e., as used in Figure 14.4). We note that activities G and H both start at node 6 and terminate at node 7. This does not present a problem in portraying the appropriate precedence relationships, since only activity J starts at node 7. This might, however, create a problem for certain software packages used to solve PERT and CPM problems. In some of these programs, each
  • 12. activity is identified by the number of its starting and ending node. If such a program is to be used, the representation of G and H in Figure 14.5 would lead the computer to regard them as the same activity. This would be incorrect, since in fact activities G and H are not the same. FINDING THE CRITICAL PATH The Critical Path Method (CPM) is one of several related techniques for doing project planning. CPM is for projects that are made up of a number of individual "activities." If some of the activities require other activities to finish before they can start, then the project becomes a complex web of activities. Now, as mentioned earlier we have a 10 steps activity list. A. Selecting Office Site B. Creating Organizational and Financial Plan C. Determining Personnel Requirements D. Designing Facility E. Constructing Interior F. Selecting Personnel to Move G. Hiring New Employees H. Moving Records, Key Personnel, etc. I. Making Financial Arrangements
  • 13. J. Training New Personnel After listing all these steps above, we need to collect data to estimate the expected activity time. As what we have learned from the class, we know there are three different types of estimate from different perspectives. Optimistic time (a): is the minimum time, which requires everything has to go perfectly to achieve this time. Most probable time (m): is the most likely time, where everything is under normal circumstances. Pessimistic time (b): is the maximum time, which follows where something can go wrong. By understanding these different perspectives of estimate we have come with a table shown below.
  • 14. Based on the original development of the PERT approach (during the late 1950s), the procedure for estimating the expected value of the activity times was motivated by the assumption that the activity time was random variable with a particular probability distribution. The figure shows the Construct Interior time use the probability distribution, which gives us these formula above the chart. The next step is to draw the Network Diagram to show the relationships and the project process. And it is also the same time to use CPM find critical path, which is the route cost most of your time in this project. To complete the Network Diagram, we need to use some dummy path the cure the incorrect relationship between activities and crate a smooth path through the whole process.
  • 15. Then we will find several path through 1 (the start) to 9 (the end). 1. A,D,E,J: and the total time will cost it = 3+4+8+3 = 18 2. B,C,D,E,J: and the total time will cost it = 5+3+4+8+3 = 23, which is the CP. 3. B,C,F,H,J: and the total time will cost it = 5+3+2+2+3 = 15 4. B,C,F,G,J: and the total time will cost it = 5+3+2+4+3 = 17 5. B,I: and the total time will cost it = 5+5 =10 By finding the critical path, we will know is we let this project go, it will spend more time as the board directors required. In the case, we need to do the crash to this project.
  • 16. CRASHING THE COST Because the company usually does not share this information with the public, so we created the chart below to demonstrate the process of crashing the cost. The critical path is B,C,D,E,J under this crash situation, the total time will be: 3+1+2+5+1=11, which is almost half of what the board directors want. The total cost of crushing will be 2*150+2*250+2*2500+3*10000+2*2500 = 300+500+5000+30000+5000 = $40800. As the CP is already crashed, we need to crash the other paths to 11 to meet the final goal along with the CP.
  • 17. This figure above is the new Network Diagram which shows the normal time and also the crash time. On analyzing all the other paths again, we found that: 1. A,D,E,J = 3+2+5+1= 11 which does not need any change as it meets the CP after the crash. 2. B,C,F,H,J = 3+1+2+2+1= 9 also does not need any crash. 3. B,C,F,G,J = 3+1+2+4+1= 11 same result as first path. 4. B,I = 3+5 =8 which was always less and does not need to crash. So to the final decision is that we just need to crash the CP to get what we want for this project, and the cost will be $40800. As we all know, CPM and PERT try to reduce the time and cost of a project. From the chart above, we find the original cost is $148400, and the normal cost is $97700. However, we do not need to spend all of the
  • 18. $148400 to finish the project within 11 weeks. The cost for 11 weeks will be $40800+$97700= $138500. And this saves about $9900. SUMMARY Using the PERT and CMP give us an opportunity to eliminate extra cost on unnecessary activity, which does not affect the total project time, to not only save the cost, but also reduce the time for the project. We started with a strategic analysis, as we aimed to keep the cost as minimum as possible. Our responsibility was to move the credit card operations from Dallas office to Iowa office for Global Oil within 22 weeks and $148400. Implementing all the skills and techniques learnt in this class, we came to a conclusion that PERT and CPM work best for this type of a project. We started by making an activity list and then build network diagrams and finally crashed the time as well as the cost required to implement this project. We have been successful in determining how this project can be completed within 11 weeks of time and with an expenditure of $138500 only. Thus, we have achieved our goal and made this project a success.
  • 19. REFERENCES  https://www.google.com/search?q=decision+making&espv=2&biw=15 36&bih=758&source=lnms&tbm=isch&sa=X&ei=PAY4VYTAG8TIsQSW 5IFg&ved=0CAYQ_AUoAQ  http://smallbusiness.chron.com/cpm-pert-weaknesses-strengths- 1082.html  http://en.wikipedia.org/wiki/Program_evaluation_and_review_techni que  http://www.interventions.org/pertcpm.html  https://www.youtube.com/watch?v=LdRZN5o08Em  http://www.mindtools.com/critpath.html  http://www.slideshare.net/dubey1992/pert-cpm-project- management  https://www.boundless.com/management/textbooks/boundless- management-textbook/control-8/financial-and-project-management- tools-of-control-64/cpm-and-pert-charts-324-4024/  http://civilengineersforum.com/pert-cpm/