SlideShare a Scribd company logo
1/7
Civilverse Admin 4 October 2020
MS Project Terminology- Top 20 Terms Everyone Must
Know
civilverse.org/ms-project-terminology
Microsoft Project is one of the most used project scheduling and planning tool. The
project schedule with the Gantt Chart is helpful in visualizing the timeline of the project.
The critical path can also be visualized through the same. This article covers the top 20
MS Project terminology.
One of the important features of Microsoft Project is to create resource loaded schedules.
The resources can be defined and then can be allotted to the activities. This helps in the
planning of the resources and their required duration.
The MS Project terminology covers the task, summary task, milestone, calendar in MSP,
recurring task, task dependencies, manually and auto-scheduled tasks, baseline schedule
and baseline cost etc.
Following are 20 must-know MS Project terminology. The understanding of these terms
will help to learn the MS Project effectively.
1. Task
The activity defined in the project schedule is called ‘task’ in MS Project.
2. Summary Task
2/7
Task, Summary Task and Milestone
The summary task is the one which summarises a task or a group of tasks. The duration of
the summary task depends on its sub-tasks. The start date of the summary task is the
earliest start of its sub-tasks and finish date is the last finish date of its sub-tasks. The
summary tasks indicate a higher level of WBS than its sub-tasks.
The summary tasks are highlighted by the bold text.
3. Milestone
A milestone indicates a task of zero duration. It is used as entry milestone, exit milestone,
completion of certain activity whose process of completion is not included in the task.
For example, the handover of the site to the contractor for starting the work can be
marked as entry milestone in the schedule. The mobilisation of equipment to a
construction site can be marked as a milestone and handover to the client after
construction as exit milestone.
4. Manually Scheduled Task
The manually-scheduled task gives the steering wheel to the user. The user defines the
duration, work and the start date of the activity. The manually scheduled task is denoted
with a blue pin.
The manually scheduled task is to be used when the duration, work or the start date are
not known and to be decided later.
5. Auto-Scheduled Task
Manually Scheduled and Auto-Scheduled Tasks
3/7
The auto-scheduled task itself schedules the start date on the project start date or the
current date as per the predefined settings. It also assumes the duration of the activity as 1
day which can be changed as per the requirement. It is denoted by a blue box with a grey
right arrow.
6. Predecessor and Successor
The predecessor and successor follow their usual meaning. For example, activity ‘A’ is
followed by activity ‘B’, then ‘A’ is called the predecessor to ‘B’ and ‘B’ is called the
successor to ‘A’.
7. Calendar
The calendar in MS Project defines the working and non-working days along with working
and non-working time for each day. The calendars are of two types- task calendar that
controls the task and the resource calendar that controls the resource. The MS Project
has three pre-defined calendars-
a. Standard (Project Calendar) with 8 hours working on working days and
Saturday and Sunday as non-working days
b. Night Shift Calendar with 12 am to 8 am working with Sunday off.
c. 24 Hour Calendar with 7 days for 24 hours working every day.
The new calendar can also be created with the desired working days and time along with
keeping provision for holidays, leave etc.
8. Duration
The duration of an activity is the time to complete the activity. The duration of an activity
can be suitably be defined in days, week or month. The task calendar controls the
duration in terms of excluding the non-working days.
4/7
9. Work
The MS Project calculates the finish date, and cost etc. by the work. The work is calculated
by duration and the working time. For example, an activity has 1-day duration and
Standard Project Calendar assigned to it, the MS Project considers the activity as 8 hours
of work.
10. Unit
In MS Project unit means the unit resource. The task can be assigned to a unit. The unit
can also be assigned 50% or 80% or in any desired percentage of its actual value to a task
depending on the work requirement.
The 50% assignment of a unit to a task means that the resource works half of its total
work.
11. WBS
WBS Code Definition Dialog Box
The Work Breakdown Structure (WBS) is the breakdown of a project into manageable and
deliverable parts. For More on WBS click here.
The MS Project assigns a WBS Code to every task. The WBS Code of a task can be
modified as per the organisation.
12. Project Start Date
The MS Project allows us to mention the project start date. This function is helpful in
aligning the auto-scheduled tasks to the project start date. Further, the whole project can
be postponed just by changing the project start date.
5/7
Project Start Date & Status Date
13. Status Date
The status date is used in the schedule update and monitoring. It is the date of a project
progress update. For example, a 10-day activity was to finish on 31 January, but you
update the progress as on 28 January, then 28 January is to be set as the status date.
The status date shouldn’t be confused as today date.
14. Recurring Tasks
Recurring Task
Recurring Task Dialog Box
st
th th
6/7
The recurring task is used for the activity that is repeated during the project life. For
example, review meetings held at the end of every month is a recurring task and it can be
defined just once under recurring task with the desired recurring time.
15. Task Dependencies
The tasks are interlinked with each other through task dependencies. The task
dependencies are of four types-
1. Start to Start (SS)– Two activities start together.
2. Start to Finish (SF)– First activity starts after the second activity finishes.
3. Finish to Finish (FF)– Two activities finish together.
4. Finish to Start (FS)– First activity finishes when first starts.
16. Lead and Lag Time
The lead and lag times are used in conjugation with the task dependencies. The lead time
is positive and the lag time is negative. For example, activity ‘B’ starts 1 day after activity
‘A’ then it can be said that activity ‘B’ has 1-day lead with Start to Start.
Similarly, if activity ‘B’ finishes one day before activity ‘A’ then, ‘A’ is linked to ‘B’ with
Finish to Finish with 1-day lag.
17. Respect Link
The respect link option is used for the manually scheduled tasks. The respect link function
enables the MS Project to reschedule the task as per task dependencies when the project is
being manually scheduled.
18. Resource
Resource Sheet
The resource in MS project can be defined as work, material or cost. The manpower is a
work resource, concrete used in the project is a material resource and the mobilisation
advance given to the contractor at the project start is the cost resource.
The amount of these resources can be accrued to the resource on the start of their usage
duration, end of the usage duration or prorated (distributed throughout the duration).
19. Baseline Schedule
7/7
Baseline Schedule
The project schedule agreed between the client and the contractor is called Baseline
Schedule. All the progress, delay, planned vs actual analysis, etc. are measured with
respect to the Baseline Schedule.
20. Baseline Cost
The cost of the project that is to be incurred as per the Baseline Schedule is called Baseline
Cost. The cost variation is measured against the Baseline Cost of the project.
Read the Part-2 of this article. Click MS Project Terminology-Top 20 Terms- Part 2.
Want to move ahead with MS Project? Click here for Changing Working days and Time in
MS Project.
For more on Project Schedules click here.
Liked the MS project terminology post? Or do you have a suggestion or a doubt? Let me
know in the comment below.
Happy Engineering!

More Related Content

What's hot

Microsoft Projects; a step by-step guide for beginner's
Microsoft Projects; a step by-step guide for beginner'sMicrosoft Projects; a step by-step guide for beginner's
Microsoft Projects; a step by-step guide for beginner'sAbhik Tushar Das
 
Primavera - Tutorial
Primavera - TutorialPrimavera - Tutorial
Primavera - TutorialRajeev Sharma
 
The Project Management Process - Week 1
The Project Management Process -  Week 1The Project Management Process -  Week 1
The Project Management Process - Week 1Craig Brown
 
Project Control- Overview Presentation Tafseer
Project Control- Overview Presentation   TafseerProject Control- Overview Presentation   Tafseer
Project Control- Overview Presentation TafseerKishan Solankimbaccepmp
 
Primavera P6 Tips and Tricks
Primavera P6 Tips and TricksPrimavera P6 Tips and Tricks
Primavera P6 Tips and Tricksp6academy
 
Introduction To Primavera (P6)
Introduction To Primavera (P6)Introduction To Primavera (P6)
Introduction To Primavera (P6)Sandip Kumar Verma
 
Project Management using MS Project 2010
Project Management using MS Project 2010Project Management using MS Project 2010
Project Management using MS Project 2010Abdul Ghaffar, PMP
 
Favorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIFavorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIChris Carson
 
Setting up a pmo
Setting up a pmoSetting up a pmo
Setting up a pmocrmackenzie
 
How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2Abdelhay Ghanem
 
08-Project-Control-ppt.ppt
08-Project-Control-ppt.ppt08-Project-Control-ppt.ppt
08-Project-Control-ppt.pptTecnicoItca
 
Project management chapter 2
Project management chapter 2Project management chapter 2
Project management chapter 2Dauda Jamada
 
Setting up a Project Management Office (PMO)
Setting up a Project Management Office (PMO)Setting up a Project Management Office (PMO)
Setting up a Project Management Office (PMO)Hussain Bandukwala
 

What's hot (20)

Primavera Training P6
Primavera Training P6Primavera Training P6
Primavera Training P6
 
Microsoft Projects; a step by-step guide for beginner's
Microsoft Projects; a step by-step guide for beginner'sMicrosoft Projects; a step by-step guide for beginner's
Microsoft Projects; a step by-step guide for beginner's
 
Primavera - Tutorial
Primavera - TutorialPrimavera - Tutorial
Primavera - Tutorial
 
The Project Management Process - Week 1
The Project Management Process -  Week 1The Project Management Process -  Week 1
The Project Management Process - Week 1
 
Project Control- Overview Presentation Tafseer
Project Control- Overview Presentation   TafseerProject Control- Overview Presentation   Tafseer
Project Control- Overview Presentation Tafseer
 
Primavera P6 Tips and Tricks
Primavera P6 Tips and TricksPrimavera P6 Tips and Tricks
Primavera P6 Tips and Tricks
 
Loading cost in primavera schedule using resources and expenses r01
Loading cost in primavera schedule using resources and expenses r01Loading cost in primavera schedule using resources and expenses r01
Loading cost in primavera schedule using resources and expenses r01
 
Schedule Updates
Schedule UpdatesSchedule Updates
Schedule Updates
 
Project Schedule Management
Project Schedule ManagementProject Schedule Management
Project Schedule Management
 
Planning fundamentals - Project Management
Planning fundamentals - Project ManagementPlanning fundamentals - Project Management
Planning fundamentals - Project Management
 
080613 Mega-Project Schedule Integration & Management RCF Method-1
080613 Mega-Project Schedule Integration & Management RCF Method-1 080613 Mega-Project Schedule Integration & Management RCF Method-1
080613 Mega-Project Schedule Integration & Management RCF Method-1
 
Introduction To Primavera (P6)
Introduction To Primavera (P6)Introduction To Primavera (P6)
Introduction To Primavera (P6)
 
Project Management using MS Project 2010
Project Management using MS Project 2010Project Management using MS Project 2010
Project Management using MS Project 2010
 
Favorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIFavorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEI
 
Setting up a pmo
Setting up a pmoSetting up a pmo
Setting up a pmo
 
PMO Frameworks
PMO FrameworksPMO Frameworks
PMO Frameworks
 
How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2
 
08-Project-Control-ppt.ppt
08-Project-Control-ppt.ppt08-Project-Control-ppt.ppt
08-Project-Control-ppt.ppt
 
Project management chapter 2
Project management chapter 2Project management chapter 2
Project management chapter 2
 
Setting up a Project Management Office (PMO)
Setting up a Project Management Office (PMO)Setting up a Project Management Office (PMO)
Setting up a Project Management Office (PMO)
 

Similar to MS Project Terminology -Top 20 terms everyone must know

Project 2007 full handout
Project 2007 full handoutProject 2007 full handout
Project 2007 full handoutZenawi Mehari
 
MGT 3302, Introduction to Project Management 1 Cou.docx
MGT 3302, Introduction to Project Management 1 Cou.docxMGT 3302, Introduction to Project Management 1 Cou.docx
MGT 3302, Introduction to Project Management 1 Cou.docxadkinspaige22
 
Building a-project-schedule
Building a-project-scheduleBuilding a-project-schedule
Building a-project-scheduleRaaz Karkee
 
Fundamentals of project planning and scheduling
Fundamentals of project planning and schedulingFundamentals of project planning and scheduling
Fundamentals of project planning and schedulingAtul Gaur PMP
 
Wbs & Project Scheduling
Wbs & Project SchedulingWbs & Project Scheduling
Wbs & Project Schedulingsslovepk
 
2007 MS Project Training Instructors Manual (sample)
2007 MS Project Training Instructors Manual (sample)2007 MS Project Training Instructors Manual (sample)
2007 MS Project Training Instructors Manual (sample)Bruce Gordon
 
Construction Project Schedule Template- Residential Building
Construction Project Schedule Template- Residential BuildingConstruction Project Schedule Template- Residential Building
Construction Project Schedule Template- Residential BuildingSHAZEBALIKHAN1
 
MBA 6941, Managing Project Teams 1 Course Learning Outco.docx
MBA 6941, Managing Project Teams 1 Course Learning Outco.docxMBA 6941, Managing Project Teams 1 Course Learning Outco.docx
MBA 6941, Managing Project Teams 1 Course Learning Outco.docxalfredacavx97
 
Free float and total float - PMP/CAPM from PMI
Free float and total float - PMP/CAPM from PMIFree float and total float - PMP/CAPM from PMI
Free float and total float - PMP/CAPM from PMIMudassir Iqbal
 
Advanced project management mod 3
Advanced project management mod 3Advanced project management mod 3
Advanced project management mod 3POOJA UDAYAN
 
Project Implementation.pdf
Project Implementation.pdfProject Implementation.pdf
Project Implementation.pdfssuserc0e4e0
 
Project control tools by Samuel obino mokaya
Project control tools by Samuel obino mokayaProject control tools by Samuel obino mokaya
Project control tools by Samuel obino mokayaDiscover JKUAT
 
Critical Path MethodIntroductionOnce you have the network diag.docx
Critical Path MethodIntroductionOnce you have the network diag.docxCritical Path MethodIntroductionOnce you have the network diag.docx
Critical Path MethodIntroductionOnce you have the network diag.docxannettsparrow
 
Summer Internship Report by waqar ahmed javed
Summer Internship Report by waqar ahmed javedSummer Internship Report by waqar ahmed javed
Summer Internship Report by waqar ahmed javedWaqar Ahmed
 
Project schedule- What, How, Tools & Techniques
Project schedule- What, How, Tools & TechniquesProject schedule- What, How, Tools & Techniques
Project schedule- What, How, Tools & TechniquesSHAZEBALIKHAN1
 
Planning and scheduling Techniques.ppt
Planning and scheduling  Techniques.pptPlanning and scheduling  Techniques.ppt
Planning and scheduling Techniques.pptDejeneTsegaye6
 

Similar to MS Project Terminology -Top 20 terms everyone must know (20)

Project 2007 full handout
Project 2007 full handoutProject 2007 full handout
Project 2007 full handout
 
MGT 3302, Introduction to Project Management 1 Cou.docx
MGT 3302, Introduction to Project Management 1 Cou.docxMGT 3302, Introduction to Project Management 1 Cou.docx
MGT 3302, Introduction to Project Management 1 Cou.docx
 
Building a-project-schedule
Building a-project-scheduleBuilding a-project-schedule
Building a-project-schedule
 
Pm chapter 5...
Pm chapter 5...Pm chapter 5...
Pm chapter 5...
 
Fundamentals of project planning and scheduling
Fundamentals of project planning and schedulingFundamentals of project planning and scheduling
Fundamentals of project planning and scheduling
 
Wbs & Project Scheduling
Wbs & Project SchedulingWbs & Project Scheduling
Wbs & Project Scheduling
 
2007 MS Project Training Instructors Manual (sample)
2007 MS Project Training Instructors Manual (sample)2007 MS Project Training Instructors Manual (sample)
2007 MS Project Training Instructors Manual (sample)
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
 
Construction Project Schedule Template- Residential Building
Construction Project Schedule Template- Residential BuildingConstruction Project Schedule Template- Residential Building
Construction Project Schedule Template- Residential Building
 
MS Project 2010 Training
MS Project 2010 TrainingMS Project 2010 Training
MS Project 2010 Training
 
MBA 6941, Managing Project Teams 1 Course Learning Outco.docx
MBA 6941, Managing Project Teams 1 Course Learning Outco.docxMBA 6941, Managing Project Teams 1 Course Learning Outco.docx
MBA 6941, Managing Project Teams 1 Course Learning Outco.docx
 
Free float and total float - PMP/CAPM from PMI
Free float and total float - PMP/CAPM from PMIFree float and total float - PMP/CAPM from PMI
Free float and total float - PMP/CAPM from PMI
 
Advanced project management mod 3
Advanced project management mod 3Advanced project management mod 3
Advanced project management mod 3
 
Project Implementation.pdf
Project Implementation.pdfProject Implementation.pdf
Project Implementation.pdf
 
Project control tools by Samuel obino mokaya
Project control tools by Samuel obino mokayaProject control tools by Samuel obino mokaya
Project control tools by Samuel obino mokaya
 
Critical Path MethodIntroductionOnce you have the network diag.docx
Critical Path MethodIntroductionOnce you have the network diag.docxCritical Path MethodIntroductionOnce you have the network diag.docx
Critical Path MethodIntroductionOnce you have the network diag.docx
 
Summer Internship Report by waqar ahmed javed
Summer Internship Report by waqar ahmed javedSummer Internship Report by waqar ahmed javed
Summer Internship Report by waqar ahmed javed
 
Project schedule- What, How, Tools & Techniques
Project schedule- What, How, Tools & TechniquesProject schedule- What, How, Tools & Techniques
Project schedule- What, How, Tools & Techniques
 
Planning and scheduling Techniques.ppt
Planning and scheduling  Techniques.pptPlanning and scheduling  Techniques.ppt
Planning and scheduling Techniques.ppt
 

More from SHAZEBALIKHAN1

Critical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel TemplateCritical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel TemplateSHAZEBALIKHAN1
 
5 Project Risk Identification Tools I Use & How You Can Use Them Too
5 Project Risk Identification Tools I Use & How You Can Use Them Too5 Project Risk Identification Tools I Use & How You Can Use Them Too
5 Project Risk Identification Tools I Use & How You Can Use Them TooSHAZEBALIKHAN1
 
Top 20 Standard Contract Clauses Every Manager Should Know
Top 20 Standard Contract Clauses Every Manager Should KnowTop 20 Standard Contract Clauses Every Manager Should Know
Top 20 Standard Contract Clauses Every Manager Should KnowSHAZEBALIKHAN1
 
Residential Building Preliminary Cost Estimate- Excel Template
Residential Building Preliminary Cost Estimate- Excel TemplateResidential Building Preliminary Cost Estimate- Excel Template
Residential Building Preliminary Cost Estimate- Excel TemplateSHAZEBALIKHAN1
 
3 Most Important In-situ Soil Tests for Construction Works
3 Most Important In-situ Soil Tests for Construction Works3 Most Important In-situ Soil Tests for Construction Works
3 Most Important In-situ Soil Tests for Construction WorksSHAZEBALIKHAN1
 
5 Must Know Types of Concrete Testing for Civil Engineers
5 Must Know Types of Concrete Testing for Civil Engineers5 Must Know Types of Concrete Testing for Civil Engineers
5 Must Know Types of Concrete Testing for Civil EngineersSHAZEBALIKHAN1
 
All About Construction Labour Planning- Excel Template
All About Construction Labour Planning- Excel TemplateAll About Construction Labour Planning- Excel Template
All About Construction Labour Planning- Excel TemplateSHAZEBALIKHAN1
 
10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation Steps10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation StepsSHAZEBALIKHAN1
 
Construction Material Estimate with MS Excel file
Construction Material Estimate with MS Excel fileConstruction Material Estimate with MS Excel file
Construction Material Estimate with MS Excel fileSHAZEBALIKHAN1
 
Managing the Construction Claims Effectively
Managing the Construction Claims EffectivelyManaging the Construction Claims Effectively
Managing the Construction Claims EffectivelySHAZEBALIKHAN1
 
Most Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management TermsMost Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management TermsSHAZEBALIKHAN1
 
Top 5 Concrete Quality Control Methods at Site
Top 5 Concrete Quality Control Methods at SiteTop 5 Concrete Quality Control Methods at Site
Top 5 Concrete Quality Control Methods at SiteSHAZEBALIKHAN1
 
My 5 Learnings of Waterfall Project Management
My 5 Learnings of Waterfall Project ManagementMy 5 Learnings of Waterfall Project Management
My 5 Learnings of Waterfall Project ManagementSHAZEBALIKHAN1
 
Construction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential BuildingConstruction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential BuildingSHAZEBALIKHAN1
 
5 Popular Types of Construction Contracts
5 Popular Types of Construction Contracts5 Popular Types of Construction Contracts
5 Popular Types of Construction ContractsSHAZEBALIKHAN1
 
Project Time Estimation 6 Powerful Tips & Tricks
Project Time Estimation 6 Powerful Tips & TricksProject Time Estimation 6 Powerful Tips & Tricks
Project Time Estimation 6 Powerful Tips & TricksSHAZEBALIKHAN1
 
Types of Building Foundations- Shallow and Deep
Types of Building Foundations- Shallow and DeepTypes of Building Foundations- Shallow and Deep
Types of Building Foundations- Shallow and DeepSHAZEBALIKHAN1
 
DCMA 14-Point Schedule Quality Check
DCMA 14-Point Schedule Quality CheckDCMA 14-Point Schedule Quality Check
DCMA 14-Point Schedule Quality CheckSHAZEBALIKHAN1
 
Basics of Contract Management
Basics of Contract ManagementBasics of Contract Management
Basics of Contract ManagementSHAZEBALIKHAN1
 
Bamboo Reinforced Concrete - Criteria & Performance
Bamboo Reinforced Concrete - Criteria & PerformanceBamboo Reinforced Concrete - Criteria & Performance
Bamboo Reinforced Concrete - Criteria & PerformanceSHAZEBALIKHAN1
 

More from SHAZEBALIKHAN1 (20)

Critical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel TemplateCritical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel Template
 
5 Project Risk Identification Tools I Use & How You Can Use Them Too
5 Project Risk Identification Tools I Use & How You Can Use Them Too5 Project Risk Identification Tools I Use & How You Can Use Them Too
5 Project Risk Identification Tools I Use & How You Can Use Them Too
 
Top 20 Standard Contract Clauses Every Manager Should Know
Top 20 Standard Contract Clauses Every Manager Should KnowTop 20 Standard Contract Clauses Every Manager Should Know
Top 20 Standard Contract Clauses Every Manager Should Know
 
Residential Building Preliminary Cost Estimate- Excel Template
Residential Building Preliminary Cost Estimate- Excel TemplateResidential Building Preliminary Cost Estimate- Excel Template
Residential Building Preliminary Cost Estimate- Excel Template
 
3 Most Important In-situ Soil Tests for Construction Works
3 Most Important In-situ Soil Tests for Construction Works3 Most Important In-situ Soil Tests for Construction Works
3 Most Important In-situ Soil Tests for Construction Works
 
5 Must Know Types of Concrete Testing for Civil Engineers
5 Must Know Types of Concrete Testing for Civil Engineers5 Must Know Types of Concrete Testing for Civil Engineers
5 Must Know Types of Concrete Testing for Civil Engineers
 
All About Construction Labour Planning- Excel Template
All About Construction Labour Planning- Excel TemplateAll About Construction Labour Planning- Excel Template
All About Construction Labour Planning- Excel Template
 
10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation Steps10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation Steps
 
Construction Material Estimate with MS Excel file
Construction Material Estimate with MS Excel fileConstruction Material Estimate with MS Excel file
Construction Material Estimate with MS Excel file
 
Managing the Construction Claims Effectively
Managing the Construction Claims EffectivelyManaging the Construction Claims Effectively
Managing the Construction Claims Effectively
 
Most Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management TermsMost Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management Terms
 
Top 5 Concrete Quality Control Methods at Site
Top 5 Concrete Quality Control Methods at SiteTop 5 Concrete Quality Control Methods at Site
Top 5 Concrete Quality Control Methods at Site
 
My 5 Learnings of Waterfall Project Management
My 5 Learnings of Waterfall Project ManagementMy 5 Learnings of Waterfall Project Management
My 5 Learnings of Waterfall Project Management
 
Construction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential BuildingConstruction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential Building
 
5 Popular Types of Construction Contracts
5 Popular Types of Construction Contracts5 Popular Types of Construction Contracts
5 Popular Types of Construction Contracts
 
Project Time Estimation 6 Powerful Tips & Tricks
Project Time Estimation 6 Powerful Tips & TricksProject Time Estimation 6 Powerful Tips & Tricks
Project Time Estimation 6 Powerful Tips & Tricks
 
Types of Building Foundations- Shallow and Deep
Types of Building Foundations- Shallow and DeepTypes of Building Foundations- Shallow and Deep
Types of Building Foundations- Shallow and Deep
 
DCMA 14-Point Schedule Quality Check
DCMA 14-Point Schedule Quality CheckDCMA 14-Point Schedule Quality Check
DCMA 14-Point Schedule Quality Check
 
Basics of Contract Management
Basics of Contract ManagementBasics of Contract Management
Basics of Contract Management
 
Bamboo Reinforced Concrete - Criteria & Performance
Bamboo Reinforced Concrete - Criteria & PerformanceBamboo Reinforced Concrete - Criteria & Performance
Bamboo Reinforced Concrete - Criteria & Performance
 

Recently uploaded

KIT-601 Lecture Notes-UNIT-4.pdf Frequent Itemsets and Clustering
KIT-601 Lecture Notes-UNIT-4.pdf Frequent Itemsets and ClusteringKIT-601 Lecture Notes-UNIT-4.pdf Frequent Itemsets and Clustering
KIT-601 Lecture Notes-UNIT-4.pdf Frequent Itemsets and ClusteringDr. Radhey Shyam
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxR&R Consult
 
2024 DevOps Pro Europe - Growing at the edge
2024 DevOps Pro Europe - Growing at the edge2024 DevOps Pro Europe - Growing at the edge
2024 DevOps Pro Europe - Growing at the edgePaco Orozco
 
KIT-601 Lecture Notes-UNIT-5.pdf Frame Works and Visualization
KIT-601 Lecture Notes-UNIT-5.pdf Frame Works and VisualizationKIT-601 Lecture Notes-UNIT-5.pdf Frame Works and Visualization
KIT-601 Lecture Notes-UNIT-5.pdf Frame Works and VisualizationDr. Radhey Shyam
 
Hall booking system project report .pdf
Hall booking system project report  .pdfHall booking system project report  .pdf
Hall booking system project report .pdfKamal Acharya
 
The Ultimate Guide to External Floating Roofs for Oil Storage Tanks.docx
The Ultimate Guide to External Floating Roofs for Oil Storage Tanks.docxThe Ultimate Guide to External Floating Roofs for Oil Storage Tanks.docx
The Ultimate Guide to External Floating Roofs for Oil Storage Tanks.docxCenterEnamel
 
Construction method of steel structure space frame .pptx
Construction method of steel structure space frame .pptxConstruction method of steel structure space frame .pptx
Construction method of steel structure space frame .pptxwendy cai
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdfAhmedHussein950959
 
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...Amil baba
 
Introduction to Machine Learning Unit-4 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-4 Notes for II-II Mechanical EngineeringIntroduction to Machine Learning Unit-4 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-4 Notes for II-II Mechanical EngineeringC Sai Kiran
 
Laundry management system project report.pdf
Laundry management system project report.pdfLaundry management system project report.pdf
Laundry management system project report.pdfKamal Acharya
 
Peek implant persentation - Copy (1).pdf
Peek implant persentation - Copy (1).pdfPeek implant persentation - Copy (1).pdf
Peek implant persentation - Copy (1).pdfAyahmorsy
 
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical EngineeringIntroduction to Machine Learning Unit-5 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical EngineeringC Sai Kiran
 
A case study of cinema management system project report..pdf
A case study of cinema management system project report..pdfA case study of cinema management system project report..pdf
A case study of cinema management system project report..pdfKamal Acharya
 
ENERGY STORAGE DEVICES INTRODUCTION UNIT-I
ENERGY STORAGE DEVICES  INTRODUCTION UNIT-IENERGY STORAGE DEVICES  INTRODUCTION UNIT-I
ENERGY STORAGE DEVICES INTRODUCTION UNIT-IVigneshvaranMech
 
fluid mechanics gate notes . gate all pyqs answer
fluid mechanics gate notes . gate all pyqs answerfluid mechanics gate notes . gate all pyqs answer
fluid mechanics gate notes . gate all pyqs answerapareshmondalnita
 
Top 13 Famous Civil Engineering Scientist
Top 13 Famous Civil Engineering ScientistTop 13 Famous Civil Engineering Scientist
Top 13 Famous Civil Engineering Scientistgettygaming1
 
Online resume builder management system project report.pdf
Online resume builder management system project report.pdfOnline resume builder management system project report.pdf
Online resume builder management system project report.pdfKamal Acharya
 
Explosives Industry manufacturing process.pdf
Explosives Industry manufacturing process.pdfExplosives Industry manufacturing process.pdf
Explosives Industry manufacturing process.pdf884710SadaqatAli
 
Digital Signal Processing Lecture notes n.pdf
Digital Signal Processing Lecture notes n.pdfDigital Signal Processing Lecture notes n.pdf
Digital Signal Processing Lecture notes n.pdfAbrahamGadissa
 

Recently uploaded (20)

KIT-601 Lecture Notes-UNIT-4.pdf Frequent Itemsets and Clustering
KIT-601 Lecture Notes-UNIT-4.pdf Frequent Itemsets and ClusteringKIT-601 Lecture Notes-UNIT-4.pdf Frequent Itemsets and Clustering
KIT-601 Lecture Notes-UNIT-4.pdf Frequent Itemsets and Clustering
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
2024 DevOps Pro Europe - Growing at the edge
2024 DevOps Pro Europe - Growing at the edge2024 DevOps Pro Europe - Growing at the edge
2024 DevOps Pro Europe - Growing at the edge
 
KIT-601 Lecture Notes-UNIT-5.pdf Frame Works and Visualization
KIT-601 Lecture Notes-UNIT-5.pdf Frame Works and VisualizationKIT-601 Lecture Notes-UNIT-5.pdf Frame Works and Visualization
KIT-601 Lecture Notes-UNIT-5.pdf Frame Works and Visualization
 
Hall booking system project report .pdf
Hall booking system project report  .pdfHall booking system project report  .pdf
Hall booking system project report .pdf
 
The Ultimate Guide to External Floating Roofs for Oil Storage Tanks.docx
The Ultimate Guide to External Floating Roofs for Oil Storage Tanks.docxThe Ultimate Guide to External Floating Roofs for Oil Storage Tanks.docx
The Ultimate Guide to External Floating Roofs for Oil Storage Tanks.docx
 
Construction method of steel structure space frame .pptx
Construction method of steel structure space frame .pptxConstruction method of steel structure space frame .pptx
Construction method of steel structure space frame .pptx
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
 
Introduction to Machine Learning Unit-4 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-4 Notes for II-II Mechanical EngineeringIntroduction to Machine Learning Unit-4 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-4 Notes for II-II Mechanical Engineering
 
Laundry management system project report.pdf
Laundry management system project report.pdfLaundry management system project report.pdf
Laundry management system project report.pdf
 
Peek implant persentation - Copy (1).pdf
Peek implant persentation - Copy (1).pdfPeek implant persentation - Copy (1).pdf
Peek implant persentation - Copy (1).pdf
 
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical EngineeringIntroduction to Machine Learning Unit-5 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical Engineering
 
A case study of cinema management system project report..pdf
A case study of cinema management system project report..pdfA case study of cinema management system project report..pdf
A case study of cinema management system project report..pdf
 
ENERGY STORAGE DEVICES INTRODUCTION UNIT-I
ENERGY STORAGE DEVICES  INTRODUCTION UNIT-IENERGY STORAGE DEVICES  INTRODUCTION UNIT-I
ENERGY STORAGE DEVICES INTRODUCTION UNIT-I
 
fluid mechanics gate notes . gate all pyqs answer
fluid mechanics gate notes . gate all pyqs answerfluid mechanics gate notes . gate all pyqs answer
fluid mechanics gate notes . gate all pyqs answer
 
Top 13 Famous Civil Engineering Scientist
Top 13 Famous Civil Engineering ScientistTop 13 Famous Civil Engineering Scientist
Top 13 Famous Civil Engineering Scientist
 
Online resume builder management system project report.pdf
Online resume builder management system project report.pdfOnline resume builder management system project report.pdf
Online resume builder management system project report.pdf
 
Explosives Industry manufacturing process.pdf
Explosives Industry manufacturing process.pdfExplosives Industry manufacturing process.pdf
Explosives Industry manufacturing process.pdf
 
Digital Signal Processing Lecture notes n.pdf
Digital Signal Processing Lecture notes n.pdfDigital Signal Processing Lecture notes n.pdf
Digital Signal Processing Lecture notes n.pdf
 

MS Project Terminology -Top 20 terms everyone must know

  • 1. 1/7 Civilverse Admin 4 October 2020 MS Project Terminology- Top 20 Terms Everyone Must Know civilverse.org/ms-project-terminology Microsoft Project is one of the most used project scheduling and planning tool. The project schedule with the Gantt Chart is helpful in visualizing the timeline of the project. The critical path can also be visualized through the same. This article covers the top 20 MS Project terminology. One of the important features of Microsoft Project is to create resource loaded schedules. The resources can be defined and then can be allotted to the activities. This helps in the planning of the resources and their required duration. The MS Project terminology covers the task, summary task, milestone, calendar in MSP, recurring task, task dependencies, manually and auto-scheduled tasks, baseline schedule and baseline cost etc. Following are 20 must-know MS Project terminology. The understanding of these terms will help to learn the MS Project effectively. 1. Task The activity defined in the project schedule is called ‘task’ in MS Project. 2. Summary Task
  • 2. 2/7 Task, Summary Task and Milestone The summary task is the one which summarises a task or a group of tasks. The duration of the summary task depends on its sub-tasks. The start date of the summary task is the earliest start of its sub-tasks and finish date is the last finish date of its sub-tasks. The summary tasks indicate a higher level of WBS than its sub-tasks. The summary tasks are highlighted by the bold text. 3. Milestone A milestone indicates a task of zero duration. It is used as entry milestone, exit milestone, completion of certain activity whose process of completion is not included in the task. For example, the handover of the site to the contractor for starting the work can be marked as entry milestone in the schedule. The mobilisation of equipment to a construction site can be marked as a milestone and handover to the client after construction as exit milestone. 4. Manually Scheduled Task The manually-scheduled task gives the steering wheel to the user. The user defines the duration, work and the start date of the activity. The manually scheduled task is denoted with a blue pin. The manually scheduled task is to be used when the duration, work or the start date are not known and to be decided later. 5. Auto-Scheduled Task Manually Scheduled and Auto-Scheduled Tasks
  • 3. 3/7 The auto-scheduled task itself schedules the start date on the project start date or the current date as per the predefined settings. It also assumes the duration of the activity as 1 day which can be changed as per the requirement. It is denoted by a blue box with a grey right arrow. 6. Predecessor and Successor The predecessor and successor follow their usual meaning. For example, activity ‘A’ is followed by activity ‘B’, then ‘A’ is called the predecessor to ‘B’ and ‘B’ is called the successor to ‘A’. 7. Calendar The calendar in MS Project defines the working and non-working days along with working and non-working time for each day. The calendars are of two types- task calendar that controls the task and the resource calendar that controls the resource. The MS Project has three pre-defined calendars- a. Standard (Project Calendar) with 8 hours working on working days and Saturday and Sunday as non-working days b. Night Shift Calendar with 12 am to 8 am working with Sunday off. c. 24 Hour Calendar with 7 days for 24 hours working every day. The new calendar can also be created with the desired working days and time along with keeping provision for holidays, leave etc. 8. Duration The duration of an activity is the time to complete the activity. The duration of an activity can be suitably be defined in days, week or month. The task calendar controls the duration in terms of excluding the non-working days.
  • 4. 4/7 9. Work The MS Project calculates the finish date, and cost etc. by the work. The work is calculated by duration and the working time. For example, an activity has 1-day duration and Standard Project Calendar assigned to it, the MS Project considers the activity as 8 hours of work. 10. Unit In MS Project unit means the unit resource. The task can be assigned to a unit. The unit can also be assigned 50% or 80% or in any desired percentage of its actual value to a task depending on the work requirement. The 50% assignment of a unit to a task means that the resource works half of its total work. 11. WBS WBS Code Definition Dialog Box The Work Breakdown Structure (WBS) is the breakdown of a project into manageable and deliverable parts. For More on WBS click here. The MS Project assigns a WBS Code to every task. The WBS Code of a task can be modified as per the organisation. 12. Project Start Date The MS Project allows us to mention the project start date. This function is helpful in aligning the auto-scheduled tasks to the project start date. Further, the whole project can be postponed just by changing the project start date.
  • 5. 5/7 Project Start Date & Status Date 13. Status Date The status date is used in the schedule update and monitoring. It is the date of a project progress update. For example, a 10-day activity was to finish on 31 January, but you update the progress as on 28 January, then 28 January is to be set as the status date. The status date shouldn’t be confused as today date. 14. Recurring Tasks Recurring Task Recurring Task Dialog Box st th th
  • 6. 6/7 The recurring task is used for the activity that is repeated during the project life. For example, review meetings held at the end of every month is a recurring task and it can be defined just once under recurring task with the desired recurring time. 15. Task Dependencies The tasks are interlinked with each other through task dependencies. The task dependencies are of four types- 1. Start to Start (SS)– Two activities start together. 2. Start to Finish (SF)– First activity starts after the second activity finishes. 3. Finish to Finish (FF)– Two activities finish together. 4. Finish to Start (FS)– First activity finishes when first starts. 16. Lead and Lag Time The lead and lag times are used in conjugation with the task dependencies. The lead time is positive and the lag time is negative. For example, activity ‘B’ starts 1 day after activity ‘A’ then it can be said that activity ‘B’ has 1-day lead with Start to Start. Similarly, if activity ‘B’ finishes one day before activity ‘A’ then, ‘A’ is linked to ‘B’ with Finish to Finish with 1-day lag. 17. Respect Link The respect link option is used for the manually scheduled tasks. The respect link function enables the MS Project to reschedule the task as per task dependencies when the project is being manually scheduled. 18. Resource Resource Sheet The resource in MS project can be defined as work, material or cost. The manpower is a work resource, concrete used in the project is a material resource and the mobilisation advance given to the contractor at the project start is the cost resource. The amount of these resources can be accrued to the resource on the start of their usage duration, end of the usage duration or prorated (distributed throughout the duration). 19. Baseline Schedule
  • 7. 7/7 Baseline Schedule The project schedule agreed between the client and the contractor is called Baseline Schedule. All the progress, delay, planned vs actual analysis, etc. are measured with respect to the Baseline Schedule. 20. Baseline Cost The cost of the project that is to be incurred as per the Baseline Schedule is called Baseline Cost. The cost variation is measured against the Baseline Cost of the project. Read the Part-2 of this article. Click MS Project Terminology-Top 20 Terms- Part 2. Want to move ahead with MS Project? Click here for Changing Working days and Time in MS Project. For more on Project Schedules click here. Liked the MS project terminology post? Or do you have a suggestion or a doubt? Let me know in the comment below. Happy Engineering!