SlideShare a Scribd company logo
1 of 15
Time Management
Chapter 6
Time Management
Chapter 6
“… includes the processes required to manage the timely completion of the project.”
Process Process Group Key Deliverables
6.1 Plan Schedule Management Planning Schedule Management Plan
6.2 Define Activities Planning Activities List
6.3 Sequence Activities Planning Schedule Network Diagrams
6.4 Estimate Activity Resources Planning Activity Resource Requirements
6.5 Estimate Activity Durations Planning Activity Resource Durations
6.6 Develop Schedule Planning Schedule Baseline
6.7 Control Schedule Monitoring & Controlling Change Requests
Time Management
Chapter 6
Plan Schedule Management
Process 1
Key Points
 “The process of policies, procedures & documentation for planning, developing, managing, executing & controlling
the project schedule.. throughout the project.”
 Defines units of measurements: Hrs/Days/Wks and Levels of Accuracy: +/- 10%
 Reporting formats: Status meetings ex. Weekly on Thursdays
Time Management
Chapter 6
Define Activities
Process 2
Key Points
 “The process of identifying & documenting the specific actions to be performed to produce the project deliverables.”
 Work packages are broken down (decomposed) into activities at a level small enough to estimate, schedule, execute,
monitor & control
 Rolling Wave Planning: used in large (Progressively Elaborated) projects, plan as you go, as milestones get closer
 Activity List: list of every activity required to complete project
 Activity Attributes: description of every activity with its’ Predecessor, Successor & Constraints
Time Management
Chapter 6
Sequence Activities
Process 3
Key Points
 “… is the process of identifying & documenting relationships among project activities.”
 Network diagramming how the logical sequence of activities & milestones will be performed to obtain the greatest
efficiency given all constraints
 Justifies time estimates, shows the workflow & interdependencies, identifies areas to compress schedule
Time Management
Chapter 6
Sequence Activities
Process 3 Key Points
 Precedence Diagramming (PDM) / Activity on Node (AON): Must common to show activities & their dependencies
 Types of Dependencies: Mandatory, Discretionary, External & Internal
 Identify: Predecessor & Successor activities, # of paths
 Finish-to-Start (FS): most commonly used relationship / SF dependency is rarely used
 Lead Time: gives the successor activity time to start before the predecessor finishes
 Lag Time: purposefully delays time between predecessor & successor activities
Time Management
Chapter 6
Time Management
Chapter 6
Estimate Activity Resources
Process 4
Key Points
 “Estimates type & quantities of material, human resources, equipment or supplies required to perform each activity”
 Every activity has to have a resource assigned to it: Person, Equipment, Material
 Bottom-up estimating: estimate each activity, work package, control account rolled into overall project estimate
 Activity resource requirements: details which resources are assigned to each activity
 Closely coordinated with Estimate Costs in Cost Management
Time Management
Chapter 6
Estimate Activity Durations
Process 5
Key Points
 “Estimating the # of work periods needed to complete individual activities with estimated resources.”
 Provides the amount of time each activity will take to complete… is a major input to Develop Schedule process
 Resource Calendar: shows the availability, capabilities, skills of HR & quantity & availability of equipment
 Estimating Tools: Analogous (ave. similar projects), Parametric (historical), Three Point
Time Management
Chapter 6
Estimate Activity Durations
Process 5
Key Points
 Duration Estimating Tools:
 Analogous: (ave. of past similar projects)
 Three Point: Simple Average (P+O+M)/3 , Weighted Average (P+4M+O)/6
 Group Decision: Most used as involving Team Members gets their Buy-In
 Reserve Analysis:
 Management Reserves – funds set aside for Unknown scheduling risks
 Contingency Reserves – funds set aside for Known project risks
Time Management
Chapter 6
Develop Schedule
Process 6
Key Points
 “… activity sequences, durations, resource requirements & schedule constraints are analyzed to generate a schedule
of planned start, finish & milestone dates.”
 Project Schedule is approved, realistic, iterative & serves as the baseline to track progress
 Team members confirm their assigned activities do not conflict with resource calendars or other projects
Time Management
Chapter 6
Develop Schedule
Process 6
Key Points
Tools - Critical Path Method:
 Is a string of activities that make up the longest path of durations for the project to be completed
 every single activity on the CP must finish on time for the project to finish on time
 A delay on the CP will delay the entire project
 Float/Slack – amount of time an activity can SLIP before it delays the project – Equals Zero on CP
 Total Float, Free Float, Project Float
 ES & EF – how much freedom PM can move Activity Start Dates wo/ causing problems
 LS & LF – How much “play” PM has in the schedule
 Schedule Compression – when a timeframe is unrealistic, compress the schedule wo/ changing the scope
 Fast Tracking or Crashing
 Resource Optimization – adjusting use of resources: Resource Leveling, Smoothing
 Critical Chain Method – assigning each activity to occur as late as possible
Time Management
Chapter 6
Control Schedule
Process 7
Key Points
 “Monitor status of project activities to update progress & manage changes to the schedule baseline.”
 PM stays in Control of the project by continuingly measuring the Schedule against the Plan
 Reviewing Work Performance Data & Schedule Performance
 Change Requests: are submitted to take corrective & preventative actions to minimize risks
Time Management
Chapter 6
CAPM Exam Prep
Quiz 2
• Review of Scope, Time & Cost Management
• Identify each of the Processes by their Process Group
• Identify the Processes & key ITTOs
• Review 5 Process Groups, 10 Knowledge Areas & 47 Processes

More Related Content

What's hot

Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-seminiMaya
 
Project Schedule Management - Estimate Activity Durations - PMP Workgroup
Project Schedule Management - Estimate Activity Durations - PMP WorkgroupProject Schedule Management - Estimate Activity Durations - PMP Workgroup
Project Schedule Management - Estimate Activity Durations - PMP WorkgroupTùng Trần Thanh
 
Project Management1
Project Management1Project Management1
Project Management1ibsslideshow
 
Resource Scheduling
Resource SchedulingResource Scheduling
Resource SchedulingNicola2903
 
Software engineering 11 project scheduling
Software engineering 11 project schedulingSoftware engineering 11 project scheduling
Software engineering 11 project schedulingVaibhav Khanna
 
Network diagrams
Network diagramsNetwork diagrams
Network diagramsLii Van
 
Project Scheduling
Project Scheduling Project Scheduling
Project Scheduling Reema
 
Project Management focused on Scheduling of a Project
Project Management focused on Scheduling of a ProjectProject Management focused on Scheduling of a Project
Project Management focused on Scheduling of a ProjectMeryem Yıldız
 
Literature Review in Project Scheduling Techniques
Literature Review in Project Scheduling TechniquesLiterature Review in Project Scheduling Techniques
Literature Review in Project Scheduling TechniquesObi-Ugbo Alex
 
SPM Activity Planning Introduction
SPM Activity Planning IntroductionSPM Activity Planning Introduction
SPM Activity Planning IntroductionKanchana Devi
 

What's hot (18)

Project time management
Project time managementProject time management
Project time management
 
Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-
 
Chapt7 slides
Chapt7 slidesChapt7 slides
Chapt7 slides
 
Project Schedule Management - Estimate Activity Durations - PMP Workgroup
Project Schedule Management - Estimate Activity Durations - PMP WorkgroupProject Schedule Management - Estimate Activity Durations - PMP Workgroup
Project Schedule Management - Estimate Activity Durations - PMP Workgroup
 
Project Management1
Project Management1Project Management1
Project Management1
 
Resource Scheduling
Resource SchedulingResource Scheduling
Resource Scheduling
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
 
Software engineering 11 project scheduling
Software engineering 11 project schedulingSoftware engineering 11 project scheduling
Software engineering 11 project scheduling
 
6.3 Sequence Activities
6.3 Sequence Activities6.3 Sequence Activities
6.3 Sequence Activities
 
Resource management
Resource managementResource management
Resource management
 
Network diagrams
Network diagramsNetwork diagrams
Network diagrams
 
Project Scheduling
Project Scheduling Project Scheduling
Project Scheduling
 
3. project time management
3. project time management3. project time management
3. project time management
 
Project Management focused on Scheduling of a Project
Project Management focused on Scheduling of a ProjectProject Management focused on Scheduling of a Project
Project Management focused on Scheduling of a Project
 
Ash Samadi - Project Management
Ash Samadi - Project ManagementAsh Samadi - Project Management
Ash Samadi - Project Management
 
HM 418 2e hcpm05 (1)
HM 418 2e hcpm05 (1)HM 418 2e hcpm05 (1)
HM 418 2e hcpm05 (1)
 
Literature Review in Project Scheduling Techniques
Literature Review in Project Scheduling TechniquesLiterature Review in Project Scheduling Techniques
Literature Review in Project Scheduling Techniques
 
SPM Activity Planning Introduction
SPM Activity Planning IntroductionSPM Activity Planning Introduction
SPM Activity Planning Introduction
 

Similar to Time Management Processes and Key Points

TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5Hisham Ali,PMP
 
06 projecttimemanagement
06 projecttimemanagement06 projecttimemanagement
06 projecttimemanagementDhamo daran
 
Topic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdfTopic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdfHuyNguyen657394
 
Project Management: Project Schedule Management Knowledge Area
Project Management: Project Schedule Management Knowledge AreaProject Management: Project Schedule Management Knowledge Area
Project Management: Project Schedule Management Knowledge AreaJoshua Render
 
Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Agus Suhanto
 
Project Management Notes 3
Project Management Notes 3Project Management Notes 3
Project Management Notes 3Golam Bitonsir
 
Day 3-3 - Final Revision (Time)
Day 3-3 - Final Revision (Time)Day 3-3 - Final Revision (Time)
Day 3-3 - Final Revision (Time)Jeffrey Cheah
 
A brief on project time management
A brief on project time managementA brief on project time management
A brief on project time managementImran Jamil
 
Day 3 Schedule -walaa (3).pptx
Day 3 Schedule -walaa (3).pptxDay 3 Schedule -walaa (3).pptx
Day 3 Schedule -walaa (3).pptxMohanadRabea1
 
Best Project Scheduling Techniques.
Best Project Scheduling Techniques.Best Project Scheduling Techniques.
Best Project Scheduling Techniques.NIILM University
 
Pmbok 5th planning process group part two
Pmbok 5th planning process group part twoPmbok 5th planning process group part two
Pmbok 5th planning process group part twoHossam Maghrabi
 
Project Scheduling
Project SchedulingProject Scheduling
Project SchedulingReema
 
ABCs Of Project Time Management Planning Slides
ABCs Of Project Time Management Planning SlidesABCs Of Project Time Management Planning Slides
ABCs Of Project Time Management Planning SlidesYousef Abugosh, PMP, MA
 
Schedule Development
Schedule DevelopmentSchedule Development
Schedule DevelopmentChris Carson
 

Similar to Time Management Processes and Key Points (20)

TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5
 
06 projecttimemanagement
06 projecttimemanagement06 projecttimemanagement
06 projecttimemanagement
 
Time management
Time managementTime management
Time management
 
5. PMP Training - Time management
5. PMP Training - Time management5. PMP Training - Time management
5. PMP Training - Time management
 
06 project time management m
06 project time management m06 project time management m
06 project time management m
 
Topic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdfTopic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdf
 
Time Masterclass
Time MasterclassTime Masterclass
Time Masterclass
 
Project Management: Project Schedule Management Knowledge Area
Project Management: Project Schedule Management Knowledge AreaProject Management: Project Schedule Management Knowledge Area
Project Management: Project Schedule Management Knowledge Area
 
Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6
 
Project Management Notes 3
Project Management Notes 3Project Management Notes 3
Project Management Notes 3
 
Day 3-3 - Final Revision (Time)
Day 3-3 - Final Revision (Time)Day 3-3 - Final Revision (Time)
Day 3-3 - Final Revision (Time)
 
A brief on project time management
A brief on project time managementA brief on project time management
A brief on project time management
 
Day 3 Schedule -walaa (3).pptx
Day 3 Schedule -walaa (3).pptxDay 3 Schedule -walaa (3).pptx
Day 3 Schedule -walaa (3).pptx
 
4) PTM & PCM .pptx
4) PTM & PCM .pptx4) PTM & PCM .pptx
4) PTM & PCM .pptx
 
Best Project Scheduling Techniques.
Best Project Scheduling Techniques.Best Project Scheduling Techniques.
Best Project Scheduling Techniques.
 
Pmbok 5th planning process group part two
Pmbok 5th planning process group part twoPmbok 5th planning process group part two
Pmbok 5th planning process group part two
 
6 time PMBOK
6 time PMBOK6 time PMBOK
6 time PMBOK
 
Project Scheduling
Project SchedulingProject Scheduling
Project Scheduling
 
ABCs Of Project Time Management Planning Slides
ABCs Of Project Time Management Planning SlidesABCs Of Project Time Management Planning Slides
ABCs Of Project Time Management Planning Slides
 
Schedule Development
Schedule DevelopmentSchedule Development
Schedule Development
 

More from Muzette Charles, PMP

PMP Muzette Charles_Sp19_Week6_Ethics Review
PMP Muzette Charles_Sp19_Week6_Ethics ReviewPMP Muzette Charles_Sp19_Week6_Ethics Review
PMP Muzette Charles_Sp19_Week6_Ethics ReviewMuzette Charles, PMP
 
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_Stakeholder
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_StakeholderPMP Muzette Charles_Sp2019_Chapter12_13 Procurement_Stakeholder
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_StakeholderMuzette Charles, PMP
 
PMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
PMP Muzette Charles_Sp2019_Week5_Chapter11_RiskPMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
PMP Muzette Charles_Sp2019_Week5_Chapter11_RiskMuzette Charles, PMP
 
PMP Muzette Charles_Spring2019_Week4_Chapter9_10
PMP Muzette Charles_Spring2019_Week4_Chapter9_10PMP Muzette Charles_Spring2019_Week4_Chapter9_10
PMP Muzette Charles_Spring2019_Week4_Chapter9_10Muzette Charles, PMP
 
PMP Muzette Charles_Spring2019_Week4_Chapter8
PMP Muzette Charles_Spring2019_Week4_Chapter8PMP Muzette Charles_Spring2019_Week4_Chapter8
PMP Muzette Charles_Spring2019_Week4_Chapter8Muzette Charles, PMP
 
PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7Muzette Charles, PMP
 
PMP Muzette Charles_Sp2019_Week2_Chapter4_5
PMP Muzette Charles_Sp2019_Week2_Chapter4_5PMP Muzette Charles_Sp2019_Week2_Chapter4_5
PMP Muzette Charles_Sp2019_Week2_Chapter4_5Muzette Charles, PMP
 
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3PMP Muzette Charles_Sp2019_Week1_chapter1_2_3
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3Muzette Charles, PMP
 
CAPM Muzette Charles Ethics_Review
CAPM Muzette Charles Ethics_ReviewCAPM Muzette Charles Ethics_Review
CAPM Muzette Charles Ethics_ReviewMuzette Charles, PMP
 
CAPM Muzette Charles Week5 Chapter9-10
CAPM Muzette Charles Week5 Chapter9-10CAPM Muzette Charles Week5 Chapter9-10
CAPM Muzette Charles Week5 Chapter9-10Muzette Charles, PMP
 
CAPM Muzette Charles_Week4_Chapter7-8
CAPM Muzette Charles_Week4_Chapter7-8CAPM Muzette Charles_Week4_Chapter7-8
CAPM Muzette Charles_Week4_Chapter7-8Muzette Charles, PMP
 
CAPM Muzette Charles_Week1_Chapter1-2
CAPM Muzette Charles_Week1_Chapter1-2CAPM Muzette Charles_Week1_Chapter1-2
CAPM Muzette Charles_Week1_Chapter1-2Muzette Charles, PMP
 

More from Muzette Charles, PMP (20)

PMP Muzette Charles_Sp19_Week6_Ethics Review
PMP Muzette Charles_Sp19_Week6_Ethics ReviewPMP Muzette Charles_Sp19_Week6_Ethics Review
PMP Muzette Charles_Sp19_Week6_Ethics Review
 
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_Stakeholder
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_StakeholderPMP Muzette Charles_Sp2019_Chapter12_13 Procurement_Stakeholder
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_Stakeholder
 
PMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
PMP Muzette Charles_Sp2019_Week5_Chapter11_RiskPMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
PMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
 
PMP Muzette Charles_Spring2019_Week4_Chapter9_10
PMP Muzette Charles_Spring2019_Week4_Chapter9_10PMP Muzette Charles_Spring2019_Week4_Chapter9_10
PMP Muzette Charles_Spring2019_Week4_Chapter9_10
 
PMP Muzette Charles_Spring2019_Week4_Chapter8
PMP Muzette Charles_Spring2019_Week4_Chapter8PMP Muzette Charles_Spring2019_Week4_Chapter8
PMP Muzette Charles_Spring2019_Week4_Chapter8
 
PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7
 
PMP Muzette Charles_Sp2019_Week2_Chapter4_5
PMP Muzette Charles_Sp2019_Week2_Chapter4_5PMP Muzette Charles_Sp2019_Week2_Chapter4_5
PMP Muzette Charles_Sp2019_Week2_Chapter4_5
 
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3PMP Muzette Charles_Sp2019_Week1_chapter1_2_3
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3
 
CAPM Muzette Charles Ethics_Review
CAPM Muzette Charles Ethics_ReviewCAPM Muzette Charles Ethics_Review
CAPM Muzette Charles Ethics_Review
 
CAPM Muzette Charles Chapter11-13
CAPM Muzette Charles Chapter11-13CAPM Muzette Charles Chapter11-13
CAPM Muzette Charles Chapter11-13
 
CAPM Muzette Charles Week5 Chapter9-10
CAPM Muzette Charles Week5 Chapter9-10CAPM Muzette Charles Week5 Chapter9-10
CAPM Muzette Charles Week5 Chapter9-10
 
CAPM Muzette Charles_Week4_Chapter7-8
CAPM Muzette Charles_Week4_Chapter7-8CAPM Muzette Charles_Week4_Chapter7-8
CAPM Muzette Charles_Week4_Chapter7-8
 
CAPM Muzette Charles Chapter3-4
CAPM Muzette Charles Chapter3-4CAPM Muzette Charles Chapter3-4
CAPM Muzette Charles Chapter3-4
 
CAPM Muzette Charles_Week1_Chapter1-2
CAPM Muzette Charles_Week1_Chapter1-2CAPM Muzette Charles_Week1_Chapter1-2
CAPM Muzette Charles_Week1_Chapter1-2
 
CAPM Week 6 Final Review
CAPM Week 6 Final ReviewCAPM Week 6 Final Review
CAPM Week 6 Final Review
 
CAPM Week 5 Chapter 13
CAPM Week 5 Chapter 13CAPM Week 5 Chapter 13
CAPM Week 5 Chapter 13
 
CAPM Week 5 Chapter 12
CAPM Week 5 Chapter 12CAPM Week 5 Chapter 12
CAPM Week 5 Chapter 12
 
CAPM Week 4 Chapter 11
CAPM Week 4 Chapter 11CAPM Week 4 Chapter 11
CAPM Week 4 Chapter 11
 
CAPM Week 4 Chapter 10
CAPM Week 4 Chapter 10CAPM Week 4 Chapter 10
CAPM Week 4 Chapter 10
 
CAPM Week 3 Chapter 9
CAPM Week 3 Chapter 9CAPM Week 3 Chapter 9
CAPM Week 3 Chapter 9
 

Recently uploaded

POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxSayali Powar
 
भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,Virag Sontakke
 
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfEnzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfSumit Tiwari
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Educationpboyjonauth
 
Roles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceRoles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceSamikshaHamane
 
Biting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdfBiting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdfadityarao40181
 
Final demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxFinal demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxAvyJaneVismanos
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsanshu789521
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxthorishapillay1
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Celine George
 
MARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized GroupMARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized GroupJonathanParaisoCruz
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxRaymartEstabillo3
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
Hierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of managementHierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of managementmkooblal
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Meghan Sutherland In Media Res Media Component
Meghan Sutherland In Media Res Media ComponentMeghan Sutherland In Media Res Media Component
Meghan Sutherland In Media Res Media ComponentInMediaRes1
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxOH TEIK BIN
 

Recently uploaded (20)

POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
 
भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,
 
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfEnzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Education
 
Roles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceRoles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in Pharmacovigilance
 
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
 
Biting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdfBiting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdf
 
Final demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxFinal demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptx
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha elections
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptx
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
 
MARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized GroupMARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized Group
 
OS-operating systems- ch04 (Threads) ...
OS-operating systems- ch04 (Threads) ...OS-operating systems- ch04 (Threads) ...
OS-operating systems- ch04 (Threads) ...
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
Hierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of managementHierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of management
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 
Meghan Sutherland In Media Res Media Component
Meghan Sutherland In Media Res Media ComponentMeghan Sutherland In Media Res Media Component
Meghan Sutherland In Media Res Media Component
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptx
 
9953330565 Low Rate Call Girls In Rohini Delhi NCR
9953330565 Low Rate Call Girls In Rohini  Delhi NCR9953330565 Low Rate Call Girls In Rohini  Delhi NCR
9953330565 Low Rate Call Girls In Rohini Delhi NCR
 

Time Management Processes and Key Points

  • 2. Time Management Chapter 6 “… includes the processes required to manage the timely completion of the project.” Process Process Group Key Deliverables 6.1 Plan Schedule Management Planning Schedule Management Plan 6.2 Define Activities Planning Activities List 6.3 Sequence Activities Planning Schedule Network Diagrams 6.4 Estimate Activity Resources Planning Activity Resource Requirements 6.5 Estimate Activity Durations Planning Activity Resource Durations 6.6 Develop Schedule Planning Schedule Baseline 6.7 Control Schedule Monitoring & Controlling Change Requests
  • 3. Time Management Chapter 6 Plan Schedule Management Process 1 Key Points  “The process of policies, procedures & documentation for planning, developing, managing, executing & controlling the project schedule.. throughout the project.”  Defines units of measurements: Hrs/Days/Wks and Levels of Accuracy: +/- 10%  Reporting formats: Status meetings ex. Weekly on Thursdays
  • 4. Time Management Chapter 6 Define Activities Process 2 Key Points  “The process of identifying & documenting the specific actions to be performed to produce the project deliverables.”  Work packages are broken down (decomposed) into activities at a level small enough to estimate, schedule, execute, monitor & control  Rolling Wave Planning: used in large (Progressively Elaborated) projects, plan as you go, as milestones get closer  Activity List: list of every activity required to complete project  Activity Attributes: description of every activity with its’ Predecessor, Successor & Constraints
  • 5. Time Management Chapter 6 Sequence Activities Process 3 Key Points  “… is the process of identifying & documenting relationships among project activities.”  Network diagramming how the logical sequence of activities & milestones will be performed to obtain the greatest efficiency given all constraints  Justifies time estimates, shows the workflow & interdependencies, identifies areas to compress schedule
  • 6. Time Management Chapter 6 Sequence Activities Process 3 Key Points  Precedence Diagramming (PDM) / Activity on Node (AON): Must common to show activities & their dependencies  Types of Dependencies: Mandatory, Discretionary, External & Internal  Identify: Predecessor & Successor activities, # of paths  Finish-to-Start (FS): most commonly used relationship / SF dependency is rarely used  Lead Time: gives the successor activity time to start before the predecessor finishes  Lag Time: purposefully delays time between predecessor & successor activities
  • 8. Time Management Chapter 6 Estimate Activity Resources Process 4 Key Points  “Estimates type & quantities of material, human resources, equipment or supplies required to perform each activity”  Every activity has to have a resource assigned to it: Person, Equipment, Material  Bottom-up estimating: estimate each activity, work package, control account rolled into overall project estimate  Activity resource requirements: details which resources are assigned to each activity  Closely coordinated with Estimate Costs in Cost Management
  • 9. Time Management Chapter 6 Estimate Activity Durations Process 5 Key Points  “Estimating the # of work periods needed to complete individual activities with estimated resources.”  Provides the amount of time each activity will take to complete… is a major input to Develop Schedule process  Resource Calendar: shows the availability, capabilities, skills of HR & quantity & availability of equipment  Estimating Tools: Analogous (ave. similar projects), Parametric (historical), Three Point
  • 10. Time Management Chapter 6 Estimate Activity Durations Process 5 Key Points  Duration Estimating Tools:  Analogous: (ave. of past similar projects)  Three Point: Simple Average (P+O+M)/3 , Weighted Average (P+4M+O)/6  Group Decision: Most used as involving Team Members gets their Buy-In  Reserve Analysis:  Management Reserves – funds set aside for Unknown scheduling risks  Contingency Reserves – funds set aside for Known project risks
  • 11. Time Management Chapter 6 Develop Schedule Process 6 Key Points  “… activity sequences, durations, resource requirements & schedule constraints are analyzed to generate a schedule of planned start, finish & milestone dates.”  Project Schedule is approved, realistic, iterative & serves as the baseline to track progress  Team members confirm their assigned activities do not conflict with resource calendars or other projects
  • 12. Time Management Chapter 6 Develop Schedule Process 6 Key Points Tools - Critical Path Method:  Is a string of activities that make up the longest path of durations for the project to be completed  every single activity on the CP must finish on time for the project to finish on time  A delay on the CP will delay the entire project  Float/Slack – amount of time an activity can SLIP before it delays the project – Equals Zero on CP  Total Float, Free Float, Project Float  ES & EF – how much freedom PM can move Activity Start Dates wo/ causing problems  LS & LF – How much “play” PM has in the schedule  Schedule Compression – when a timeframe is unrealistic, compress the schedule wo/ changing the scope  Fast Tracking or Crashing  Resource Optimization – adjusting use of resources: Resource Leveling, Smoothing  Critical Chain Method – assigning each activity to occur as late as possible
  • 13. Time Management Chapter 6 Control Schedule Process 7 Key Points  “Monitor status of project activities to update progress & manage changes to the schedule baseline.”  PM stays in Control of the project by continuingly measuring the Schedule against the Plan  Reviewing Work Performance Data & Schedule Performance  Change Requests: are submitted to take corrective & preventative actions to minimize risks
  • 15. CAPM Exam Prep Quiz 2 • Review of Scope, Time & Cost Management • Identify each of the Processes by their Process Group • Identify the Processes & key ITTOs • Review 5 Process Groups, 10 Knowledge Areas & 47 Processes