Project Management Techniques ( CPM & PERT Techniques )
A revised PPT from other shared PPT available
Project management is a scientific way of planning, implementing, monitoring & controlling the various aspects of a project such as time, money, materials, manpower & other resources.
By,
Mr. AKARESH JOSE
Kerala Agricultural University
akareshjose@gmail.com
Critical Path Explained With 7 Q&As and a Free Excel TemplateSHAZEBALIKHAN1
The critical path method is the most used project management technique. Learn the CPM with 7 FAQs ranging from definition to method, process, tests. The attached excel sheet (hyperlinked in the article) explains the implementation of CPM in a project schedule.
Project Management Techniques ( CPM & PERT Techniques )
A revised PPT from other shared PPT available
Project management is a scientific way of planning, implementing, monitoring & controlling the various aspects of a project such as time, money, materials, manpower & other resources.
By,
Mr. AKARESH JOSE
Kerala Agricultural University
akareshjose@gmail.com
Critical Path Explained With 7 Q&As and a Free Excel TemplateSHAZEBALIKHAN1
The critical path method is the most used project management technique. Learn the CPM with 7 FAQs ranging from definition to method, process, tests. The attached excel sheet (hyperlinked in the article) explains the implementation of CPM in a project schedule.
project management-cpm and pert methods for managersNaganna Chetty
A project is a one shot, time limited, goal directed, major undertaking, requiring the commitment of varied skills & resources.
A project:
Has a unique purpose.
Is temporary.
Is developed using progressive elaboration.
Requires resources, often from various areas.
Should have a primary customer or sponsor.
The project sponsor usually provides the direction and funding for the project.
Involves uncertainty.
Project managers work with project sponsors, project teams, and other people involved in projects to meet project goals.
Program: “A group of related projects managed in a coordinated way to obtain benefits and control not available from managing them individually.”
Program managers oversee programs and often act as bosses for project managers.
Project management is “the application of knowledge, skills, tools and techniques to project activities to meet project requirements.”
project management-cpm and pert methods for managersNaganna Chetty
A project is a one shot, time limited, goal directed, major undertaking, requiring the commitment of varied skills & resources.
A project:
Has a unique purpose.
Is temporary.
Is developed using progressive elaboration.
Requires resources, often from various areas.
Should have a primary customer or sponsor.
The project sponsor usually provides the direction and funding for the project.
Involves uncertainty.
Project managers work with project sponsors, project teams, and other people involved in projects to meet project goals.
Program: “A group of related projects managed in a coordinated way to obtain benefits and control not available from managing them individually.”
Program managers oversee programs and often act as bosses for project managers.
Project management is “the application of knowledge, skills, tools and techniques to project activities to meet project requirements.”
The case study discusses the potential of drone delivery and the challenges that need to be addressed before it becomes widespread.
Key takeaways:
Drone delivery is in its early stages: Amazon's trial in the UK demonstrates the potential for faster deliveries, but it's still limited by regulations and technology.
Regulations are a major hurdle: Safety concerns around drone collisions with airplanes and people have led to restrictions on flight height and location.
Other challenges exist: Who will use drone delivery the most? Is it cost-effective compared to traditional delivery trucks?
Discussion questions:
Managerial challenges: Integrating drones requires planning for new infrastructure, training staff, and navigating regulations. There are also marketing and recruitment considerations specific to this technology.
External forces vary by country: Regulations, consumer acceptance, and infrastructure all differ between countries.
Demographics matter: Younger generations might be more receptive to drone delivery, while older populations might have concerns.
Stakeholders for Amazon: Customers, regulators, aviation authorities, and competitors are all stakeholders. Regulators likely hold the greatest influence as they determine the feasibility of drone delivery.
Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...CIOWomenMagazine
This person is none other than Oprah Winfrey, a highly influential figure whose impact extends beyond television. This article will delve into the remarkable life and lasting legacy of Oprah. Her story serves as a reminder of the importance of perseverance, compassion, and firm determination.
Artificial intelligence (AI) offers new opportunities to radically reinvent the way we do business. This study explores how CEOs and top decision makers around the world are responding to the transformative potential of AI.
Senior Project and Engineering Leader Jim Smith.pdfJim Smith
I am a Project and Engineering Leader with extensive experience as a Business Operations Leader, Technical Project Manager, Engineering Manager and Operations Experience for Domestic and International companies such as Electrolux, Carrier, and Deutz. I have developed new products using Stage Gate development/MS Project/JIRA, for the pro-duction of Medical Equipment, Large Commercial Refrigeration Systems, Appliances, HVAC, and Diesel engines.
My experience includes:
Managed customized engineered refrigeration system projects with high voltage power panels from quote to ship, coordinating actions between electrical engineering, mechanical design and application engineering, purchasing, production, test, quality assurance and field installation. Managed projects $25k to $1M per project; 4-8 per month. (Hussmann refrigeration)
Successfully developed the $15-20M yearly corporate capital strategy for manufacturing, with the Executive Team and key stakeholders. Created project scope and specifications, business case, ROI, managed project plans with key personnel for nine consumer product manufacturing and distribution sites; to support the company’s strategic sales plan.
Over 15 years of experience managing and developing cost improvement projects with key Stakeholders, site Manufacturing Engineers, Mechanical Engineers, Maintenance, and facility support personnel to optimize pro-duction operations, safety, EHS, and new product development. (BioLab, Deutz, Caire)
Experience working as a Technical Manager developing new products with chemical engineers and packaging engineers to enhance and reduce the cost of retail products. I have led the activities of multiple engineering groups with diverse backgrounds.
Great experience managing the product development of products which utilize complex electrical controls, high voltage power panels, product testing, and commissioning.
Created project scope, business case, ROI for multiple capital projects to support electrotechnical assembly and CPG goods. Identified project cost, risk, success criteria, and performed equipment qualifications. (Carrier, Electrolux, Biolab, Price, Hussmann)
Created detailed projects plans using MS Project, Gant charts in excel, and updated new product development in Jira for stakeholders and project team members including critical path.
Great knowledge of ISO9001, NFPA, OSHA regulations.
User level knowledge of MRP/SAP, MS Project, Powerpoint, Visio, Mastercontrol, JIRA, Power BI and Tableau.
I appreciate your consideration, and look forward to discussing this role with you, and how I can lead your company’s growth and profitability. I can be contacted via LinkedIn via phone or E Mail.
Jim Smith
678-993-7195
jimsmith30024@gmail.com
The Team Member and Guest Experience - Lead and Take Care of your restaurant team. They are the people closest to and delivering Hospitality to your paying Guests!
Make the call, and we can assist you.
408-784-7371
Foodservice Consulting + Design
2. What is Project Management
Project management can be defined as the
coordination of activities with the potential use of
many organizations, both internal and external to
the business, in order to conduct a large scale
project from beginning to end.
There are two management science techniques
that are used for project management:
Program and Evaluation Review Technique
(PERT)
Critical Path Method (CPM)
3. PERT/CPM
PERT
Program Evaluation and Review Technique
Developed by U.S. Navy for Polaris missile project
Developed to handle uncertain activity times
CPM
Critical Path Method
Developed by Du Pont & Remington Rand
Developed for industrial projects for which
activity times generally were known
Today’s project management software packages have
combined the best features of both approaches.
4. PERT/CPM
PERT and CPM have been used to
plan, schedule, and control a wide
variety of projects:
R&D of new products and processes
Construction of buildings and highways
Maintenance of large and complex
equipment
Design and installation of new systems
5. PERT/CPM
PERT/CPM is used to plan the
scheduling of individual activities that
make up a project.
Projects may have as many as
several thousand activities.
A complicating factor in carrying out
the activities is that some activities
depend on the completion of other
activities before they can be started.
6. PERT/CPM
Project managers rely on PERT/CPM to help
them answer questions such as:
How can the project be displayed graphically?
What is the total time to complete the
project?
What are the scheduled start and finish dates
for each specific activity?
Which activities are critical and must be
completed exactly as scheduled to keep the
project on schedule?
7. How long can non critical activities be
delayed before they cause an increase
in the project completion time?
What is the probability of completing
the project by the deadline?
What is the least amount of money
needed to expedite the project to
obtain the bonus?
How should costs be monitored to keep
the project within budget?
8. Scheduling Using PERT/CPM
A path through a project network is
a route that follows a set of arcs
from the start node to the finish
node.
The length of a path is defined as
the sum of the durations of the
activities of the path.
What are the paths and their
corresponding lengths ?
9. Difference between PERT & CPM
PERT
It is usually analytical
in concept & designed
as probabilistic
network
It is built up of event
oriented diagrams
Three time estimates
are possible for
activities linking up
two activities
CPM
It is basically
synthesising in
concept and termed as
deterministic network
It is built up of
activities oriented
diagrams
One time estimate is
possible
10. Difference between PERT & CPM
PERT
Times are not related
to cost
Used for R & D
Projects, product
development
CPM
Time are related to
costs
Used for repetitive
work
11. A
START
G
H
M
F
J
K L
N
Activity Code
A. Excavate
B. Foundation
C. Rough wall
D. Roof
E. Exterior plumbing
F. Interior plumbing
G. Exterior siding
H. Exterior painting
I. Electrical work
J. Wallboard
K. Flooring
L. Interior painting
M. Exterior fixtures
N. Interior fixtures
2
4
10
7
4
6
7
9
5
8
4 5
6
2
0
0
FINISH
D I
E
C
B
12. Different Terminologies
Event :
A Particular instant in time showing the
end or beginning of an activity.
It is a point of accomplishment or
decision
This does not consume resources
An activity is bound by two events
13. Numbering of events
Event Numbering :
Event numbers should in some
respect reflect their logical
sequencing
14. Rule for numbering events
D R Fulkerson’s rule for numbering :
An initial event is one which has arrows coming
out of it and none entering it. In any network
there will be one such event. Number it 1
Delete all the arrows emerging from event 1.
This will create at least one more “initial event”
Number these new initial events as 2,3,..
Delete all emerging arrows from these numbered
events which will create new initial events
Continue till the last event is obtained which has
no arrows emerging out of it
15. Additional rules for numbering
events
All events must be numbered
The same number cannot be used for
more than one event. This is
necessary for identifying each activity
Event can be numbered in any order
but usually forward numbering
system is more familiar
16. Different Terminologies
Activity :
An activity represents efforts applied over a
period of time which has a definite beginning
and end
Activities are graphically represented by arrows
with description and time estimates written
along the arrow
Direction of the arrow indicates the sequence in
which events occur
Activity is actual performance of a task
It consumes resources i.e. manpower, material,
money
Activity represents what is to be done between
the achievement of any two events
An activity cannot be started until its preceding
event has been achieved
17. Activity & Event Relationship
An event can only be achieved when
all activities leading to that event are
complete
An activity can only be started when
its preceding event is achieved.
The preceding event thus dictates the
earliest start time of an activity.
While the succeeding event fixes the
accomplishment of that activity
18. Different Terminologies
Restriction :
When one activity must be completed
before a second activity can begin, the
first activity is considered to be restraint
or restricting activity. A<B
Pre-requisite Activity :
Is one which immediately precedes the
one being considered. A is pre-requisite
for B,C & F
A
F
D
B
C
E
19. Different Terminologies
Post-Requisite activity :
Is one which immediately follows one under
consideration. B,C & F are post requite to A
Descendent Activity :
A descendent activity is any activity restricted
by the one under consideration
B,C,D,E F are descendent of A
Antecedent Activity :
Any activity which must precede the one under
consideration. A & B are antecedent of D
A
F
D
B
C
E
20. Different Terminologies
Dummy Activity :
An activity that does not consume any kind of
resources but merely depicts the technological
dependence.
Merge :
A merge exists when two or more activities
converge at a single event
Burst :
A burst exists when two or more activities have
a common beginning event
21. Rules for drawing network diagram
Rule 1 :Each activity is represented
by one and only one arrow in the
network
Rule 2 : No two activities can be
identified by the same end event
a
b
a
b
dummy
WRONG RIGHT
22. Rules for drawing network diagram
Rule 3 : In order to ensure the correct
precedence relationship in the arrow
diagram, following must be checked
when every activity is added
What activities must be completed before
this activity can start ?
What activity must follow this activity ?
What activity must occur simultaneously
with this activity ?
23. Further guidelines for network
diagrams
Activity arrows should be drawn from
left to right indicating progressive
approach towards the ultimate
objective or final event
Crossing of arrows should be avoided
Unnecessary use of dummy activities
should be avoided
24. Network Rules
The length of arrows bears no relationship to the time
which the activity takes
The arrow in a network identifies logical conditions of
dependencies. The geometry of the arrow has no
significance
The direction of the arrow indicates the direction of
work flow. Normal convention is from left to right
All networks are constructed logically on the principle
of dependency
No event can be reached in a project before the
activity preceding is completed
No set of activites can form a circular loop
25. More Terminology
Earliest start time of an activity (ES)
The time at which an activity will begin if there
are no delays in a project.
Earliest finish time of an activity (EF)
The time at which an activity will finish if there
are no delays in a project.
Latest start time of an activity (LS)
The latest possible time that an activity can
start without delaying the project.
26. More Terminology Cont.
Latest finish time of an activity (LF)
The latest possible time that an activity
can be completed without delaying the
project.
Forward pass
The process of moving through a
project from start to finish to determine
the earliest start and finish times for
the activities in the project.
27. More Terminology Cont.
Backward pass
The process of moving through a project from finish
to start to determine the latest start and finish times
for the activities in the project.
Slack for an activity
The amount of time that a particular activity can be
delayed without delaying the whole project.
It is calculated by taking the difference between the
latest finish time with the earliest finish time.
28. More Terminology Cont.
Earliest start time rule
The earliest start time for an activity is
equal to the largest of the earliest finish
times of its immediate predecessors.
Latest finish time rule
The latest finish time is equal to the
smallest of the latest start times of its
immediate successors.
29. Procedure for Obtaining
Earliest Times
Step 1: For the activity that starts the
project, assign an earliest start time of
zero, i.e., E1=0.
Step 2: Any activity can start immediately
when all the preceding activities are
completed
The earliest start time for node j is given by
Ej = Max [Ei + Dij]
Where I is the collection of nodes which precede
node j
30. Procedure for Obtaining
Earliest Times Cont.
Step 3 : Repeat step 2 for the next
eligible activity until the end node is
reached
31. Procedure for Obtaining Latest
Start Times
In forward pass computation, the
earliest time when a particular
activity can be completed is known.
It is seen that some activities are
not critical to the completion of the
project
Can their starting time be delayed ?
What can be the maximum delay ?
Such questions arises when scheduling
resources
32. Procedure for Obtaining Latest
Start Times
Step 1: Set Li = Ei or Ts where Ts is the
scheduled date of completion of the project
and Ei is the earliest terminal time
Step 2: Li = Min [Lj – Dij]
i.e. the latest time for activities is the
minimum of the latest time of all succeeding
activities reducing their activity time.
Step 3: Repeat step 2 until starting activity is
reached
33. A
START
G
H
M
F
J
FINISH
K L
N
D I
E
C
B
2
4
10
7
4
6
7
9
5
8
4 5
6
2
S = (0, 0)
F = (2, 2)
S = (2, 2)
F = (6, 6)
S = (16, 20)
F = (22, 26)
S = (16, 16)
F = (20, 20)
S = (16, 18)
F = (23, 25)
S = (20, 20)
F = (25, 25)
S = (22, 26)
F = (29, 33)
S = (6, 6)
F = (16, 16)
S = (0, 0)
F = (0, 0)
S = (25, 25)
F = (33, 33)
S = (33, 33)
F = (38, 38)
S = (38, 38)
F = (44, 44)
S = (33, 34)
F = (37, 38)
S = (29, 33)
F = (38, 42)
S = (38, 42)
F = (40, 44)
S = (44, 44)
F = (44, 44)
0
0
34. Ways of Finding the Critical
Path
Examine all the paths and find the
path with the maximum length.
Calculate the slack for an activity.
If the slack is zero, it is on the critical
path.
If the slack is positive, it is not on the
critical path.
36. Activity on Arc Network
A(3)
D(12)
B(8)
E(10)
C(7)
F(20)
1 5
4
3
2
The network will build up with
each mouse click, in the order
you would construct it on
paper.
38. Earliest Event Times
A(3)
D(12)
B(8)
E(10)
C(7)
F(20)
1 5
4
3
2
0
3
12
22
42
To find EETs, work
forwards through the
network from the start
node to the finish
node.
The EET for an
event occurs
when all activities
leading into that
event are
complete.
39. Latest Event Times
A(3)
D(12)
B(8)
E(10)
C(7)
F(20)
1 5
4
3
2
3
0
12
22
42 42
22
12
4
0
To find LETs, work
backwards through
the network from the
finish node to the start
node.
The LET for an
event is the latest
it can occur
without delaying
subsequent
events.
40. Critical Activities
A(3)
D(12)
B(8)
E(10)
C(7)
F(20)
1 5
4
3
2
3 4
0 0
12 12
22 22
42 42
Critical activities are activities that cannot
run late. For critical activities:
Latest finish — Earliest start = length of
activity
The green arrows mark the critical
activities, which form the critical path.
The critical path(s) must form a continuous
route from the start node to the finish
node.
41. Revisiting Cables By Us Using
Probabilistic Time Estimates
Activity Description
Optimistic
time
Most likely
time
Pessimistic
time
A Develop product specifications 2 4 6
B Design manufacturing process 3 7 10
C Source & purchase materials 2 3 5
D Source & purchase tooling & equipment 4 7 9
E Receive & install tooling & equipment 12 16 20
F Receive materials 2 5 8
G Pilot production run 2 2 2
H Evaluate product design 2 3 4
I Evaluate process performance 2 3 5
J Write documentation report 2 4 6
K Transition to manufacturing 2 2 2
42. Using Beta Probability
Distribution to Calculate
Expected Time Durations
A typical beta distribution is shown below, note
that it has definite end points
The expected time for finishing each activity is
a weighted average
6
c
pessimisti
likely
most
4
optimistic
time
Exp.
43. Calculating Expected Task
Times
Activity
Optimistic
time
Most likely
time
Pessimistic
time
Expected
time
A 2 4 6 4
B 3 7 10 6.83
C 2 3 5 3.17
D 4 7 9 6.83
E 12 16 20 16
F 2 5 8 5
G 2 2 2 2
H 2 3 4 3
I 2 3 5 3.17
J 2 4 6 4
K 2 2 2 2
6
4 c
pessimisti
likely
most
optimistic
time
Expected
45. Estimated Path Durations
through the Network
ABDEGIJK is the expected critical
path & the project has an expected
duration of 44.83 weeks
Activities on paths Expected duration
ABDEGHJK 44.66
ABDEGIJK 44.83
ACFGHJK 23.17
ACFGIJK 23.34
48. Estimating the Probability of
Completion Dates
Using probabilistic time estimates offers the advantage of
predicting the probability of project completion dates
We have already calculated the expected time for each
activity by making three time estimates
Now we need to calculate the variance for each activity
The variance of the beta probability distribution is:
where p=pessimistic activity time estimate
o=optimistic activity time estimate
2
2
6
o
p
σ
49. Project Activity Variance
Activity Optimistic Most Likely Pessimistic Variance
A 2 4 6 0.44
B 3 7 10 1.36
C 2 3 5 0.25
D 4 7 9 0.69
E 12 16 20 1.78
F 2 5 8 1.00
G 2 2 2 0.00
H 2 3 4 0.11
I 2 3 5 0.25
J 2 4 6 0.44
K 2 2 2 0.00
50. Variances of Each Path
through the Network
Path
Number
Activities on
Path
Path Variance
(weeks)
1 A,B,D,E,G,H,J,k 4.82
2 A,B,D,E,G,I,J,K 4.96
3 A,C,F,G,H,J,K 2.24
4 A,C,F,G,I,J,K 2.38
51. Calculating the Probability of
Completing the Project in Less Than
a Specified Time
When you know:
The expected completion time
Its variance
You can calculate the probability of completing the
project in “X” weeks with the following formula:
Where DT = the specified completion date
EFPath = the expected completion time of the path
2
P
σ
EF
D
time
standard
path
time
expected
path
time
specified
z
P
T
path
of
variance
σ 2
Path
52. Example: Calculating the probability
of finishing the project in 48 weeks
Use the z values in Appendix B to determine
probabilities
e.g. probability for path 1 is
Path
Number
Activities on Path Path Variance
(weeks)
z-value Probability of
Completion
1 A,B,D,E,G,H,J,k 4.82 1.5216 0.9357
2 A,B,D,E,G,I,J,K 4.96 1.4215 0.9222
3 A,C,F,G,H,J,K 2.24 16.5898 1.000
4 A,C,F,G,I,J,K 2.38 15.9847 1.000
1.52
4.82
weeks
44.66
weeks
48
z
53. Project Network
A project network can be constructed to
model the precedence of the activities.
The nodes of the network represent the
activities.
The arcs of the network reflect the
precedence relationships of the
activities.
A critical path for the network is a path
consisting of activities with zero slack.
54. Network Analysis
Phases of Network Analysis
Phase I : Planning
Collection of all information pertinent to project
different types of works involved are separated
into activities
Time estimates are determined for each
activity
Activity sequencing is established by noting
their inter relationship (which must precede,
which must succeed, which are concurrent)
55. Network Analysis
Phases of Network Analysis
Phase II : Scheduling
assigning estimated start & finish time to each
activity
cost, availability of work crew, materials & other
resources associated with each activities must be
considered.
Showing the float on some activities and determining
the critical activities.
Preparation of time chart and using it for manpower
leveling and resource allocation
Cost analysis based on the time chart
56. Network Analysis
Phases of Network Analysis
Phase III : Control
Cost control of project
updating and reporting
proposed changes
simplifies communication and improve
coordination
57. Advantages of network analysis
It limits possibility of over looking a
job
It shows inter relationship of all jobs
in the project
It helps in communicating the ideas
It contribute to disciplined thinking
It identifies those jobs which are
critical for project completion
58. Advantages of network analysis
It provides time schedule consisting much
more information than a usual bar chart
It provides methods of resource allocation
to meet limiting condition
It integrates all elements of a programme
to whatever detail is desired
It facilitates reporting & project
documentation
59. Project Network
A project network is a network
diagram that uses nodes and arcs to
represent the progression of the
activities is a project from start to
finish.
Three pieces of information needed:
Activity information
Precedence relationship
Time information
60. Project Network Cont.
Two types of project networks
Activity-on-Arc (AOA)
On this diagram, the activity is
represented on an arc, while a node is
used to separate an activity from its
immediate predecessors.
Activity-on-Node (AON)
On this diagram, the activity is
represented by the node, while the arc is
used to showed the precedence
relationship between the activities.