A RCC bridge is a monolithic structure that is poured in place. Forms are placed, the reinforcing steel is placed into the forms and a concrete mix is poured into the forms. The rebar extends beyond the form to allow connection to the next section to be poured. In a PSC structure the elements are precast either in a yard or onsite. They are cast with longitudinal holes to allow the prestressing strands to be extended between them. These strands use their tension to pull the units together and to act as reinforcement by prestreeing the entirety of the structure to make it stronger.
Pile foundation is important for construction of foundation where bearing capacity of soil is poor. Pile foundation is use for distribution of uneven load of superstructure.There are so many type of pile are use for construction. Here i present some of pile with suitable condition for construction and methods for construction.
Thank you.
Larsen and Toubro (Lucknow Metro Project) Summer Internship PresentationShuBham RaNa
Hello Friends Myself SHUBHAM RANA . I am pursuing B.Tech in Civil Engineering from IIT ROORKEE. This is the glimpse of my work and basic aspects which I learned while doing my Internship in Larsen and Toubro Heavy Civil Infra IC. Thank You :)
A RCC bridge is a monolithic structure that is poured in place. Forms are placed, the reinforcing steel is placed into the forms and a concrete mix is poured into the forms. The rebar extends beyond the form to allow connection to the next section to be poured. In a PSC structure the elements are precast either in a yard or onsite. They are cast with longitudinal holes to allow the prestressing strands to be extended between them. These strands use their tension to pull the units together and to act as reinforcement by prestreeing the entirety of the structure to make it stronger.
Pile foundation is important for construction of foundation where bearing capacity of soil is poor. Pile foundation is use for distribution of uneven load of superstructure.There are so many type of pile are use for construction. Here i present some of pile with suitable condition for construction and methods for construction.
Thank you.
Larsen and Toubro (Lucknow Metro Project) Summer Internship PresentationShuBham RaNa
Hello Friends Myself SHUBHAM RANA . I am pursuing B.Tech in Civil Engineering from IIT ROORKEE. This is the glimpse of my work and basic aspects which I learned while doing my Internship in Larsen and Toubro Heavy Civil Infra IC. Thank You :)
Uses of special kind of technologies for implementation of special kind of st...Rajesh Prasad
The said technical paper was presented by Rajesh Prasad in IC TRAM 2018 (International Conference- Technological Advancement in Railways and Metro Projects at Manekshaw Centre New Delhi on 04.10.2018
There was a Bridge 2018 Conference on Innovative Technologies of Bridges organised by IIBE at Lucknow. During the conference held on 25.05.18 this paper was presented by Rajesh Prasad, ED Metro RVNL.
There was a Bridge 2018 Conference on Innovative Technologies of Bridges organised by IIBE at Lucknow. During the conference held on 25.05.18 this paper was presented by Rajesh Prasad, ED Metro RVNL.
Presentation about Under-construction Mahakali Bridge Project in 3 days Training Program on Construction and Quality Control of PSC Bridges चैत्र ११,१२,१३ ,२०७७ organized by
Federal Road Supervision and Monitoring Office, Surkhet
Presentation on Flyover at Aziz Cross on GT Road GujranwalaRubnawaz Bhatti
Presentation on Flyover at Aziz Cross on GT Road Gujranwala. First project in the history of Pakistan where flyovers are constructed on different heights
Final project report on grocery store management system..pdfKamal Acharya
In today’s fast-changing business environment, it’s extremely important to be able to respond to client needs in the most effective and timely manner. If your customers wish to see your business online and have instant access to your products or services.
Online Grocery Store is an e-commerce website, which retails various grocery products. This project allows viewing various products available enables registered users to purchase desired products instantly using Paytm, UPI payment processor (Instant Pay) and also can place order by using Cash on Delivery (Pay Later) option. This project provides an easy access to Administrators and Managers to view orders placed using Pay Later and Instant Pay options.
In order to develop an e-commerce website, a number of Technologies must be studied and understood. These include multi-tiered architecture, server and client-side scripting techniques, implementation technologies, programming language (such as PHP, HTML, CSS, JavaScript) and MySQL relational databases. This is a project with the objective to develop a basic website where a consumer is provided with a shopping cart website and also to know about the technologies used to develop such a website.
This document will discuss each of the underlying technologies to create and implement an e- commerce website.
Hierarchical Digital Twin of a Naval Power SystemKerry Sado
A hierarchical digital twin of a Naval DC power system has been developed and experimentally verified. Similar to other state-of-the-art digital twins, this technology creates a digital replica of the physical system executed in real-time or faster, which can modify hardware controls. However, its advantage stems from distributing computational efforts by utilizing a hierarchical structure composed of lower-level digital twin blocks and a higher-level system digital twin. Each digital twin block is associated with a physical subsystem of the hardware and communicates with a singular system digital twin, which creates a system-level response. By extracting information from each level of the hierarchy, power system controls of the hardware were reconfigured autonomously. This hierarchical digital twin development offers several advantages over other digital twins, particularly in the field of naval power systems. The hierarchical structure allows for greater computational efficiency and scalability while the ability to autonomously reconfigure hardware controls offers increased flexibility and responsiveness. The hierarchical decomposition and models utilized were well aligned with the physical twin, as indicated by the maximum deviations between the developed digital twin hierarchy and the hardware.
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERSveerababupersonal22
It consists of cw radar and fmcw radar ,range measurement,if amplifier and fmcw altimeterThe CW radar operates using continuous wave transmission, while the FMCW radar employs frequency-modulated continuous wave technology. Range measurement is a crucial aspect of radar systems, providing information about the distance to a target. The IF amplifier plays a key role in signal processing, amplifying intermediate frequency signals for further analysis. The FMCW altimeter utilizes frequency-modulated continuous wave technology to accurately measure altitude above a reference point.
Immunizing Image Classifiers Against Localized Adversary Attacksgerogepatton
This paper addresses the vulnerability of deep learning models, particularly convolutional neural networks
(CNN)s, to adversarial attacks and presents a proactive training technique designed to counter them. We
introduce a novel volumization algorithm, which transforms 2D images into 3D volumetric representations.
When combined with 3D convolution and deep curriculum learning optimization (CLO), itsignificantly improves
the immunity of models against localized universal attacks by up to 40%. We evaluate our proposed approach
using contemporary CNN architectures and the modified Canadian Institute for Advanced Research (CIFAR-10
and CIFAR-100) and ImageNet Large Scale Visual Recognition Challenge (ILSVRC12) datasets, showcasing
accuracy improvements over previous techniques. The results indicate that the combination of the volumetric
input and curriculum learning holds significant promise for mitigating adversarial attacks without necessitating
adversary training.
Using recycled concrete aggregates (RCA) for pavements is crucial to achieving sustainability. Implementing RCA for new pavement can minimize carbon footprint, conserve natural resources, reduce harmful emissions, and lower life cycle costs. Compared to natural aggregate (NA), RCA pavement has fewer comprehensive studies and sustainability assessments.
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...Amil Baba Dawood bangali
Contact with Dawood Bhai Just call on +92322-6382012 and we'll help you. We'll solve all your problems within 12 to 24 hours and with 101% guarantee and with astrology systematic. If you want to take any personal or professional advice then also you can call us on +92322-6382012 , ONLINE LOVE PROBLEM & Other all types of Daily Life Problem's.Then CALL or WHATSAPP us on +92322-6382012 and Get all these problems solutions here by Amil Baba DAWOOD BANGALI
#vashikaranspecialist #astrologer #palmistry #amliyaat #taweez #manpasandshadi #horoscope #spiritual #lovelife #lovespell #marriagespell#aamilbabainpakistan #amilbabainkarachi #powerfullblackmagicspell #kalajadumantarspecialist #realamilbaba #AmilbabainPakistan #astrologerincanada #astrologerindubai #lovespellsmaster #kalajaduspecialist #lovespellsthatwork #aamilbabainlahore#blackmagicformarriage #aamilbaba #kalajadu #kalailam #taweez #wazifaexpert #jadumantar #vashikaranspecialist #astrologer #palmistry #amliyaat #taweez #manpasandshadi #horoscope #spiritual #lovelife #lovespell #marriagespell#aamilbabainpakistan #amilbabainkarachi #powerfullblackmagicspell #kalajadumantarspecialist #realamilbaba #AmilbabainPakistan #astrologerincanada #astrologerindubai #lovespellsmaster #kalajaduspecialist #lovespellsthatwork #aamilbabainlahore #blackmagicforlove #blackmagicformarriage #aamilbaba #kalajadu #kalailam #taweez #wazifaexpert #jadumantar #vashikaranspecialist #astrologer #palmistry #amliyaat #taweez #manpasandshadi #horoscope #spiritual #lovelife #lovespell #marriagespell#aamilbabainpakistan #amilbabainkarachi #powerfullblackmagicspell #kalajadumantarspecialist #realamilbaba #AmilbabainPakistan #astrologerincanada #astrologerindubai #lovespellsmaster #kalajaduspecialist #lovespellsthatwork #aamilbabainlahore #Amilbabainuk #amilbabainspain #amilbabaindubai #Amilbabainnorway #amilbabainkrachi #amilbabainlahore #amilbabaingujranwalan #amilbabainislamabad
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)MdTanvirMahtab2
This presentation is about the working procedure of Shahjalal Fertilizer Company Limited (SFCL). A Govt. owned Company of Bangladesh Chemical Industries Corporation under Ministry of Industries.
Saudi Arabia stands as a titan in the global energy landscape, renowned for its abundant oil and gas resources. It's the largest exporter of petroleum and holds some of the world's most significant reserves. Let's delve into the top 10 oil and gas projects shaping Saudi Arabia's energy future in 2024.
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdffxintegritypublishin
Advancements in technology unveil a myriad of electrical and electronic breakthroughs geared towards efficiently harnessing limited resources to meet human energy demands. The optimization of hybrid solar PV panels and pumped hydro energy supply systems plays a pivotal role in utilizing natural resources effectively. This initiative not only benefits humanity but also fosters environmental sustainability. The study investigated the design optimization of these hybrid systems, focusing on understanding solar radiation patterns, identifying geographical influences on solar radiation, formulating a mathematical model for system optimization, and determining the optimal configuration of PV panels and pumped hydro storage. Through a comparative analysis approach and eight weeks of data collection, the study addressed key research questions related to solar radiation patterns and optimal system design. The findings highlighted regions with heightened solar radiation levels, showcasing substantial potential for power generation and emphasizing the system's efficiency. Optimizing system design significantly boosted power generation, promoted renewable energy utilization, and enhanced energy storage capacity. The study underscored the benefits of optimizing hybrid solar PV panels and pumped hydro energy supply systems for sustainable energy usage. Optimizing the design of solar PV panels and pumped hydro energy supply systems as examined across diverse climatic conditions in a developing country, not only enhances power generation but also improves the integration of renewable energy sources and boosts energy storage capacities, particularly beneficial for less economically prosperous regions. Additionally, the study provides valuable insights for advancing energy research in economically viable areas. Recommendations included conducting site-specific assessments, utilizing advanced modeling tools, implementing regular maintenance protocols, and enhancing communication among system components.
Welcome to WIPAC Monthly the magazine brought to you by the LinkedIn Group Water Industry Process Automation & Control.
In this month's edition, along with this month's industry news to celebrate the 13 years since the group was created we have articles including
A case study of the used of Advanced Process Control at the Wastewater Treatment works at Lleida in Spain
A look back on an article on smart wastewater networks in order to see how the industry has measured up in the interim around the adoption of Digital Transformation in the Water Industry.
Water Industry Process Automation and Control Monthly - May 2024.pdf
TRAINING REPORT ON COSTRUCTION OF FLYOVER FROM MITHAPUR TO CHIRIYATAND (BIHAR)
1. VOCATIONAL TRAINING REPORT
STUDY ON CONSTRUCTION OF FLYOVER
OF BRPNNL, PATNA
COSTRUCTION OF FLYOVER FROM
MITHAPUR TO CHIRIYATAND
Submitted by- Under guidance of:
Vishal Prakash Er. Arvind Kumar
Enrol no.-CIV/93/13 Project engineer
Reference no.- NIT/T&P/15/159 Dt.01.10.15 BRPNNL, Patna
National institute of technology, Srinagar
2. ACKNOWLEDGEMENT
I would like to express my deepest appreciation to all those who
provided me the possibility to complete this report . A special
gratitude I give to project manager Er. Arvind Kumar,( BRPNNL) ,
whose contribution in stimulating suggestions & encouragement,
helped me to coordinate my project especially in writing this report.
Furthermore I would also like to acknowledge with much
appreciation the crucial role of Er. Tanweer siddique(Bridge), Er.
Rishu Singh(Q.S), Er. Ashish Kumar (Survey) and S.P. Singla
construction Pvt. Ltd. Staffs for best possible guidance regarding the
Project.
Lastly, I would like to appreciate the efforts made by BRPNNL, Patna
for providing the professional experience to the us.
Date: 22/01/2016 VISHAL PRAKASH
Place: Patna
3. BIHAR RAJYA PUL NIRMAN NIGAM
LIMITED, PATNA
CERTIFICATE
This is to certify that the project named “Study on
construction of Flyover from Mithapur to chiriyantand”
submitted by Mr. VISHAL PRAKASH Enrol no.- CIV/93/13 in
partial fulfilment of the requirement for Bachelor of
Technology Degree in Civil Engineering at National
institute of technology, Srinagar
And this work has not Plagiarized from elsewhere to best of
my knowledge.
Date: 22/01/2016 Er. Arvind Kumar
Project Engineer
5. INTRODUCTION
BIHAR RAJYA PUL NIRMAN NIGAM LIMITED, PATNA(BRPNNL)
was established on 11th June 1975 as Govt. Company.
The recent project , flyover from “mithapur to chriyantand” is
also in construction under BRPNNL .
It will reduce the Traffic problems . In Patna due to excess
vehicles and poor traffic system and poor road space i is
necessary to construct flyovers.
The Flyover is 2x2 lane of carriage way 5.5m from Mithapur
R.O.B to chiriyantand via station road (854m. Elevated +207m
ramp) in Patna.
6. CONSTRUCTION DETAILS
Project title Construction of flyover (2 lane and
1 lane) carriage way (5.5m) from
G.P.O golembur to Chiriyatand
flyover via station road
Project estimated cost 150 crores
Contractor S.P. Singla constructions Pvt.Ltd.
Consultant Stup Association with treetek
Client BRPNNL, Patna
Site Location Station Road
7. EXECUTION OF PROJECT
Sequence of construction:
1. Surveying
2. Analysis and design of the structure
3. Piling
a. Drilling
b. Pile cap Construction
4. Construction of Pier shaft and Pier cap
5. Construction of Pedestal and seismic stopper
6. Construction of segments and/or girders
7. Launching and gluing of segments
8. Construction of road over bridge
8. SURVEYING
TOPOGRAPHICAL SURVEY:
Topography is used to determine the position or any point in
both the horizontal and vertical coordinates( Latitudes,
Longitudes, Altitudes).
Survey includes Reconnaissance. Then
various maps are studied and then detailed
is done by Total station and layouts are
given on AutoCAD.
With the help of this total space for the
construction of the flyover ,no. Of lanes and
total carriage are decided.
9. TRAFFIC SURVEY:
Is done carry out design improvement traffic system and
management. Traffic forecasts predicts the future traffic levels
on the road. In this flyover design is so made to meet for next
25 yrs.
TRAFFIC MONITORING:
Traffic control includes CCTV and other means for monitoring
traffic by local and state roadways to manage traffic flow and
providing advice concerning traffic congestion.
TRAFFIC CONTROL:
Traffic controllers(T.C) usually known as Lollipop men shows
the their Stop/Slow sign known as STOP. A camera is also
installed to detect the traffic rule violations, including
speeding of vehicles.
10. FOUNDATIONS:
Foundations are the structures which are constructed below
existing ground level. It sustains the loads coming from the
sub structures and superstructures.
Bridges had to carry a big load so PILE FOUNDATION are
preferred.
It is a type of foundation which where good soil are at the
depth of 10-15m or soil having low bearing capacity.
In this flyover Group of piles drilled for piling:
for P1 to P14- 10 Piles (140 nos.), for P21, P23, P24, P26, P27,
P29, P30, P32,33& P21A- 4 Piles(40 nos.), for P22, P25, P28,
P31, P22A- 6 Piles(30 nos.), P16 to P19 – 8 Piles(32 nos.)
Total nos. Of piles =242 piles
11. PILE FOUNDATION
All piles have Dia. =1200mm
Depth =25m (except for P1A, P1B, P1D which have 30m piling)
M35 Grade of concrete
Piles are structure that are made up of steel, concrete, timber.
They are used to build pile foundation, and use of piles is
necessary to ensure safety.
• PILES are divided
in given category:
Steel
piles
Concrete
piles
Wooden(
Timber)
piles
12. CONCRETE PILES
In this flyover ,Piles used are Concrete cast in-situ piles.
Types of Concrete Piles:
PrecastPiles
These are
prepared by using
ordinary
Reinforcements &
they can be
octagonal
These Piles are
casted to any
Length& cured.
Precisepiles
These are
Prestressed by
use of high
strength steel
cables. Ultimate
Strength= 260ksi.
After curing ,the
cables are cut,
thus producing
high compressive
force on piles.
Castin-situpiles
Piles are built by
making hole in
the ground and
then filling it with
concrete.
Two types – a)
Cased, b)
Uncased
13. PILE BORING:
Digging in ground for strong foundation is Pile Boring. For
excavation on top soil 2-3 m an instrument named AGAR is
Placed on the top of the digging machine.
Liner is used to maintain the stability of the soil.
SOFT GROUND DIGGING HEAD:
It is being made for digging clay and it is made of heavy duty
high carbon. It is being is done in 3 phases:
A) EXCAVATION- Digging is done by Auger Machine( MAT) up to
28m. After digging flushed Bentonite to prevent the bore hole
from collapse and installing the bottom section of temporary
casing in ground by oscillating and jacking.
14. B)CONCRETE PLACEMENT:
Concreting is done by transit Mix Truck and it has got ability
to take 7 cubic m of concrete which are casted in foundation
and settled by TREMIE Pipe.
The pile shaft will be concreted by underwater Tremie
technique the pipe is inserted to the bottom of pile leaving
cover of “500mm”. Concrete will be poured by tremie pipe by
using concrete skip.
C) INSTALLATION OF REINFORCEMENT:
After completion of concreting, dowel bars of required length
and nos. Will be installed to pile shaft and down to the
predetermined level before extraction of bottom steel casing.
Reinforcements is done by steel, cage and Liner.
17. Pile cap:
• Formation of pile-
pile cap= R.L of existing ground level-cut off
level
Pile cap is formed by combination of pile and
then binding the steel followed by shuttering
• Dimension of pile caps-
for P1 to P15:
length= 16m, breadth=5.2m, height=1.8m
for P16 to P19:
length= 12.4m, breadth= 5.2m, height= 1.8m
for P21, P23, P24, P26, P27, P29, P30, P32,
P33, P21A, P20A, P23A, P20
length=breadth= 5.2m, height=1.8m
for P22,P25, P28, P28, P31, P22A
length= 8.8m, breadth= 5.2m, height= 1.8m
After piling
completion, soil is
excavated for
construction of pile
cap.
For proper pile cap
P.C.C. Is provided for
separation from
mud. At site 75mm
thick PCC is carried
out for control over
seepage.
18. • Reinforcement steel in Pile cap
• Grade of concrete used
M35
S.no. BARS
1. 20mm @140mm c/c
2. 16mm @140mm c/c
3. 32mm @90mm c/c
4. 32mm @180mm c/c
5. 16mm @180mm c/c
19. PIER SHAFT
A pier shaft is a raised structure provided mostly at the centre
of the pile cap which supports the structure and transfer the
several types of load to the foundation.
DIMENSION OF THE SHAFT:
length= 2m, breadth= 2m, height=
and length= 1.5m, breadth= 1.5m, height=
REINFORCEMENTS IN SHAFT:
S.no. BARS
1. 4 sides 17 NOS. 32mm
2. 4 sides 10mm @100 c/c
3. 4 sides 10mm @200 c/c
4. 16mm @100 c/c
5. 12mm @200 c/c
6. Links 10mm @200 c/c
20. PIER CAP-
Pier caps are the topmost structure of the substructure. Above
these the superstructures (segments & girders) are placed.
DIMENSIONS OF PIER CAPS:
For P1 to P14: Length= 6m, Breadth= 3.3m
For P23, P26, P29, P32, P33, P20A : Length= 5.4m,
Breadth= 2.8m
For P21, P24, P27, P30, P31, P21A : Length= 5.4m, Breadth=
1.9m
For P15, P19 : Length= 11.4m, Breadth= 2.8m
For P16 to P18 : Length= 11.4m, Breadth= 2.4m
GRADE OF CONCRETE FOR CASTING
M 35 Except pier 17 ,where M 40 is used.
21. REINFORCEMENT USED IN PIER CAP
S.no. BARS
1. 12mm @150 c/c
2. 25 nos. 32mm ,top bar
3. 2*5 16mm
4. 12mm @150mm c/c, LV bar
5. 17 nos. 20mm, hunch bar
6. 25mm @125 c/c, Loop
7. 5 nos. 16mm @125mm c/c, Ring
8. 3 nos. 16mm @200mm c/c, Ring
9. 12mm @150mm c/c, bottom bar
10. 24 nos. 20mm @435 c/c in four layers, 6 in each layer
22.
23. BEARINGS, PEDESTALS, SEISMIC STOPPERS
After the accumulation of all the reinforcements in pier cap a
surface is formed over which Bearings, Pedestals and Seismic
stoppers are provided as per the design.
Seismic stopper: The current designs of seismically designs
as a second line of defence. These structures allow
development of in-service moments of the deck, without
transmitting loads on pier and foundation, while during
earthquake they resist the entire seismic action.
Height of stopper= 1.2m
LV bars are used of 400mm
& 700mm ,16mm dia.
25. DIMENSIONS :
• Pedestal: Length= 700mm, Breadth= 700mm, Height= 500mm
• Bearing: Height= 137mm
A bearing is an element of superstructure which provides an
interface between superstructure and sub structure. This is
important because of the deformations and dimensional
changes in superstructure due to Thermal expansion, seismic
forces, wind loads etc. & here use POT PTFE bearing
REINFORCEMENTS :
A mesh of dimension 750mm*850mm is used inside pedestal at
20mm and 100 mm from the top.
8mm @75mm c/c and12mm @100 c/c
26. MAKING OF PILE AND PIER CAP
PROCESS-
Messing of Pile caps, pier shafts & pier caps by different
reinforced steel bars.
Welding by Arc welding method.
Shuttering and then casting(concreting).
CONCRETING OF STRUCTURES
Concrete is a composite material made up of mainly cement,
water and aggregates in definite proportion as per the grade
of the concrete to achieve the desired physical properties.
After casting of the structures curing is done.
27. CURING OF THE STRUCTURE:-
For attaining the full strength of the concrete i.e.
Compressive strength curing with water is properly done on
the casted structure. It takes almost 28 to 30 days for a
concrete structure to attain its strength and durability.
28. DIA. AND DEPTH OF THE BORE HOLES:
• Diameter of the pile =1200mm
• Depth =25m (foundation level)
• Lap length =50D
• Reinforcements : 18 nos. 20mm dia.
& 18mm @150c/c
The 25m of depth consists of following
4 layers:
clay(7m)
Gravel & clay mixes(6m)
Clay(3m)
Sand gravel mix
29. SUPERSTRUCTURE
Structures which are above the pier cap and placed on
the bearings are superstructure. Roads are further
constructed over it.
SEGMENTS
• TWO TYPES: A) PIER
SEGMENT, B) NORMAL
SEGMENT
GIRDERS
• Used I –girder in this
project
30. SEGMENTS:
Placed on the bearing plate. These are used to make a span
of the flyover. Segments are precast made up of M45 GRADE
concrete and FE 500. These structures are posses both
Tension and Compression members, so designs are made by
taking in account both forces on it.
31. TYPES OF SEGMENT USED:
• Pier segment(P.S)- These are placed at the end of the span on
the pier cap. Length of P.S is smaller than the normal segment
and the anchor hole are inclined. Two P.S are used in making
of the span.
• NORMAL SEGMENT- These are placed in between two P.S for
making the span and anchor hole are straight. Total 9
segments are used in between two pier.
Total length of span= 2*2.35+9*3.25=33.95m
S.NO. SEGMENTS LENGTH
1. PIER SEGMENT 2.35m
2. NORMAL SEGMENT 3.25m
32. GIRDERS:
Individual beam like structure which are separately placed on
the bearings. These structures are shorter in length than
segment and stressing are done precast by using cables
certain in nos. Depends on the design.
In this project I-girder of 3 and 6 span are used.
33. LAUNCHING OF SEGMENT:
The segments are launched by launching girder or
gantry girder. Beam are connected both end of the
segment and pressure are applied in segments. All
the segments are joined to each other by gluing.
LAUNCHING OF DECK BY LAUNCHING
MACHINE:
Launching machine is used to uplift the segment of
the bridge all the segments are lifted at once by the
use of lifter.
Number of segment between two pier:
no. Of segment= 11
weight of one segment =600T
After placing of the segments Stressing is done by
use of high tensile cables, so that loads came to the
cable & bridge should be stable.
34. JOINTING OF SEGMENT:
Mixing of both type of chemical (Nitobond Pc base thixotropic
epoxy adhesive& Nitobond Pc 30 harder) is done and every
time two segments are compressed(glued) to each other.
After 24 hours the process checked by flushing water and
leakage in anchor hole.
ANCHOR HOLE-
These are present in entire segment to for stressing of it. 6
nos. Of hole are present at one side of segment. Parabolic
shape.
TENSILE WIRE-
It is a high tensile steel wire inserted in all 11 segment for
stressing. No. Of wire depend on the design(12, 19,25etc.).
Grade of the wire is 19T15.
35. PRESTRESSING:
Pre-stressing means creating a permanent stress in the
structure. In this process dead end are fixed with life wedge to
hold the tensile wire. And the free end is fixed with hydraulic
jack and force are applied approximately 369 T.
GROUTING:
Grouting involves injection of cemented material in a certain
ratio of cement and water for isolated pore or void space is
often called Simple grouting.
Quantity of material:
o Cement :1 bag
o Water: 22 litres
o Admixtures: cibex 100
36. SPAN:
The distance between two span is 500mm.
Total span length between two pier varies in this project
P1-P5 =34m, P6-P19=37m and rest have distance= 20m
PRECAUSTION TO BE TAKEN DURING PLACING
CONCRETE
o Water should not be added to concrete during its passage
from mixer to form work.
o The form work(surface) which has to receive the fresh
concrete should be properly watered(cured).
o Concrete should be placed in single thickness.
o Concrete should be tapped in such a way that no honeycomb
surface appear on the surface.
37. TECHNICAL SPECIFICATION
1) Chiriyatand to Gandhi maidan:
OTHER SPECIFICATION:
o Pile group -4 and 6
o A1-P1- 33.25m, P1-P17- 34m, P17-A2- 33.25m
o Length of flyover= 612 m elevated , approach(RE Panel)= 147m fill.
Diameter of pile 1200mm
Vertical & horizontal loads 250T & 30T
Depth of pile cap 1800mm
Number of Piles 110
Number of pile cap 19
Number of segment 198
38. 2) Station to Mithapur
DIAMETER OF PILES 1800MM
VETICAL& HORIZONTAL LOADS 230T& 20T
CONCRETE USED M35(EXCEPT P17: M40)
DEPTH OF PILE CAP 1.8m
NUMBER OF PILES 267
NUMBER OF PILE CAP 38
NUMBER OF SEGMENT 182
NUMBER OF SHAFT 40
NUMBER OF HAMMER HEAD 37
39. CONCLUSION
The project report involves construction of flyover and shows
concern over every written word.
Bridges break down separation and foster connectedness
across gulfs and rivers, between people and countries. As far
back as we can see in history, human beings have used new
technology to solve problem and ease their physical burdens.
The distinctiveness of humans as a species is defined by their
use of tools, and bridge are technological tools that aims to
solve the problem of crossing and obstacle in such a way as to
cut down the efforts and time needed to do so.
As the traffic problem arises in the cities due to more vehicles
in the cities because of big population. This flyover change the
face of the city Patna and Paved the way to progress.
40. REFERENCES: