SlideShare a Scribd company logo
GENERATOR OPERATION LIMITS
By Pradeep Yadav,
Dy. Director.
When a manufacturer designs & construct an
alternator, It will specify the MCR ( max.
continuous rating )of the machine in terms of;
1. Stator current.
The operation of the generator must be such that
none of the design limitations are exceeded as
otherwise damage to the generator may result.
2. Stator voltage.
3. Rotor current.
4. Rotor voltage.
5. MW.
6. MVA.
7. Power factor.
There are 5 principal limitations on the
generator operation.
Principal limitations:
A convenient way of presenting these
limitations is in the form of a diagram
called as “ Capability curve”.
1. Stator current limit.
2. Rotor current limit.
3. MW limit.
4. Stability limit.
5. Stator end heating limit.
Assumption: Generator terminal voltage is
maintained constant
Erect a voltage vector “OA”.
Capability curve :
Principal limitations:
1. Stator current limit : Heat developed in the
winding is limited by the class of Insulation.
At higher current, overheating may damage
insulation.
Class “B” Insulation - 130 Deg. Cel.
Class “F” or “H” - 180 Deg. Cel.
2. MW limit
The Max. continuous MW rating is
dictated by the steam generation
capability of boiler & the H.P rating of the
turbine.
In theory, generators are capable of
generating an output equal to MVA rating.
But generators are designed to operate at a
lagging p.f. ( 0.85 ). So that max.output is
achieved at max.stator current & at rated p.f.
MW = MVA X Cos =MVA at unity p.f.
= V X I X Cos
A horizontal line line drawn from point B
will give MW limit boundary
3. Rotor current limit:
Same reasoning as in case of stator current
limit.
Short Circuit Ratio( SCR ) is the ratio of field
current required to induce rated nominal
voltage in the Gen.terminal in open circuit
condition
TO
the field current required to circulate rated
stator current in the Gen. terminals with the
terminals short circuited.
Then, GB will represent full load rotor current or
total field current. With GB as radius , draw an
arc. It will be locus of rotor current and its limit.
Angle between GO & GB will be Rotor angle or
stability angle ().
Select a point “G”, such that OG/OB = SCR of
the generator.
4. Stability limit/Minimum rotor current
limit:
For every load condition of the generator, a
minimum rotor current has to be supplied
to maintain magnetic coupling in the air
gap between stator & rotor.A reduction in
field current without any change in steam
admission will lead to break in magnetic
coupling ( increase in rotor angle) with the
subsequent loss of machine stability.
Rotor angle ()= 90° - Theoritical stability limit.
Practical stability limit () = 75°.
5. Stator end heating limit:
With high values of stator
current at leading power factor , heating
of the end sections of the stator core tend
to occur.
The end heating limit would normally only
be reached if the stability limits were
exceeded.
1.Variation of terminal voltage:
Voltage(KV) 14.18 14.96 15.75 16.54 16.7 16.85 17.01 17.17 17.32
-------------------------------------------------------------------------------------------------
Stator Current(KA)9.5 9.5 9.05 8.6 8.37 8.14 7.92 7.56 7.24
2.Frquency variation: +5%, -5%
3. Overloading:
Stator current(KA) 9.95 10.41 10.86 11.31 11.76 12.22 12.67 13.57
Rotor current(KA) 2.75 -- -- --- 3.12 -- 3.9 5.2
Time ( Sec. ) 3600 900 360 300 240 180 120 60
4.Operation at different Hydrogen pressure:
Hydrogen Pr.(Kg./Cm2) M.W. Duration
3.0 200 Continous
2.5 170 Not more than 5 Hrs.
2.0 140 -------do------
“Operation in air medium is not permitted”
6.One gas cooler out of service – 175 MW continously.
More than one gas cooler out – operation not permitted.
Coolent: Normal Limit Property
Cold Hydrogen gas temp. 44 Deg.cel 55Deg.cel 3.5Kg/cm2. 99% pure
Stator water temp. 45 Deg.cel 48 Deg.cel 27m3/hr.
Generator capability curve

More Related Content

What's hot

EXCITATION SYSTEM.ppt
EXCITATION SYSTEM.pptEXCITATION SYSTEM.ppt
EXCITATION SYSTEM.ppt
vishal laddha
 
Brushless excitation
Brushless excitationBrushless excitation
Brushless excitation
superbhuppi
 
Generator protection
Generator protectionGenerator protection
Generator protectionKeshar Rawal
 
Generator protection
Generator protectionGenerator protection
Generator protection
Sumeet Ratnawat
 
Electrohydraulic governing system
Electrohydraulic governing systemElectrohydraulic governing system
Electrohydraulic governing system
Ashvani Shukla
 
Design of substation (with Transformer Design)
Design of substation (with Transformer Design) Design of substation (with Transformer Design)
Design of substation (with Transformer Design)
SayanSarkar55
 
Protection of three phase synchronous generator
Protection of three phase synchronous generatorProtection of three phase synchronous generator
Protection of three phase synchronous generator
Mohammad Abdullah
 
Rotor earth fault protection of electric generator
Rotor earth fault protection of electric generatorRotor earth fault protection of electric generator
Rotor earth fault protection of electric generator
CS V
 
(7) overfluxing
(7) overfluxing(7) overfluxing
(7) overfluxing
Daniel Gray
 
Turbo generator
Turbo generator Turbo generator
Turbo generator
Molla Morshad
 
measurement of high voltage and high currents
 measurement of high voltage and high currents  measurement of high voltage and high currents
measurement of high voltage and high currents
mukund mukund.m
 
Study on Excitation system in Power sector
Study on Excitation system in Power sectorStudy on Excitation system in Power sector
Study on Excitation system in Power sector
Boben Anto Chemmannoor
 
Generator protection
Generator protectionGenerator protection
Generator protection
Parimal Bhagat
 
Transformer & OLTC
Transformer & OLTCTransformer & OLTC
Transformer & OLTCRohit Dave
 
Electrical substation (one and half breaker scheme)
Electrical substation (one and half breaker scheme)Electrical substation (one and half breaker scheme)
Electrical substation (one and half breaker scheme)
Sourabh sharma
 
Understanding transformer vector group
Understanding transformer vector groupUnderstanding transformer vector group
Understanding transformer vector group
Shyamkant Vasekar
 
Transformers protection, an introduction
Transformers protection, an introductionTransformers protection, an introduction
Transformers protection, an introduction
H. Kheir
 
Switchgear presentation
Switchgear presentationSwitchgear presentation
Switchgear presentation
Nadir Baloch
 
EXCITATION SYSTEMS
EXCITATION SYSTEMSEXCITATION SYSTEMS
EXCITATION SYSTEMS
Power System Operation
 
class on Protection.pptx
class on Protection.pptxclass on Protection.pptx
class on Protection.pptx
SubhroSen9
 

What's hot (20)

EXCITATION SYSTEM.ppt
EXCITATION SYSTEM.pptEXCITATION SYSTEM.ppt
EXCITATION SYSTEM.ppt
 
Brushless excitation
Brushless excitationBrushless excitation
Brushless excitation
 
Generator protection
Generator protectionGenerator protection
Generator protection
 
Generator protection
Generator protectionGenerator protection
Generator protection
 
Electrohydraulic governing system
Electrohydraulic governing systemElectrohydraulic governing system
Electrohydraulic governing system
 
Design of substation (with Transformer Design)
Design of substation (with Transformer Design) Design of substation (with Transformer Design)
Design of substation (with Transformer Design)
 
Protection of three phase synchronous generator
Protection of three phase synchronous generatorProtection of three phase synchronous generator
Protection of three phase synchronous generator
 
Rotor earth fault protection of electric generator
Rotor earth fault protection of electric generatorRotor earth fault protection of electric generator
Rotor earth fault protection of electric generator
 
(7) overfluxing
(7) overfluxing(7) overfluxing
(7) overfluxing
 
Turbo generator
Turbo generator Turbo generator
Turbo generator
 
measurement of high voltage and high currents
 measurement of high voltage and high currents  measurement of high voltage and high currents
measurement of high voltage and high currents
 
Study on Excitation system in Power sector
Study on Excitation system in Power sectorStudy on Excitation system in Power sector
Study on Excitation system in Power sector
 
Generator protection
Generator protectionGenerator protection
Generator protection
 
Transformer & OLTC
Transformer & OLTCTransformer & OLTC
Transformer & OLTC
 
Electrical substation (one and half breaker scheme)
Electrical substation (one and half breaker scheme)Electrical substation (one and half breaker scheme)
Electrical substation (one and half breaker scheme)
 
Understanding transformer vector group
Understanding transformer vector groupUnderstanding transformer vector group
Understanding transformer vector group
 
Transformers protection, an introduction
Transformers protection, an introductionTransformers protection, an introduction
Transformers protection, an introduction
 
Switchgear presentation
Switchgear presentationSwitchgear presentation
Switchgear presentation
 
EXCITATION SYSTEMS
EXCITATION SYSTEMSEXCITATION SYSTEMS
EXCITATION SYSTEMS
 
class on Protection.pptx
class on Protection.pptxclass on Protection.pptx
class on Protection.pptx
 

Similar to Generator capability curve

(9) limitations
(9) limitations(9) limitations
(9) limitations
Daniel Gray
 
(9) Synchronous Alternator Capability Graph
(9) Synchronous Alternator Capability Graph(9) Synchronous Alternator Capability Graph
(9) Synchronous Alternator Capability Graph
Daniel Gray
 
Excitation and capability curve
Excitation and capability curveExcitation and capability curve
Excitation and capability curve
Shashi Katiyar
 
Original Power Supply IC LNK632DG LNK632 632 SOP-7 New
Original Power Supply IC LNK632DG LNK632 632 SOP-7 NewOriginal Power Supply IC LNK632DG LNK632 632 SOP-7 New
Original Power Supply IC LNK632DG LNK632 632 SOP-7 New
AUTHELECTRONIC
 
Power Factor.ppt
Power Factor.pptPower Factor.ppt
Power Factor.ppt
Vidya Sagar
 
powerfactor.pdf
powerfactor.pdfpowerfactor.pdf
powerfactor.pdf
Saravanan A
 
268320253 hmwk5-solutions
268320253 hmwk5-solutions268320253 hmwk5-solutions
268320253 hmwk5-solutions
Muhammad Ammar Younas
 
Original Power Supply IC LNK616PG LNK616P LNK616 DIP-7 New
Original Power Supply IC LNK616PG LNK616P LNK616 DIP-7 NewOriginal Power Supply IC LNK616PG LNK616P LNK616 DIP-7 New
Original Power Supply IC LNK616PG LNK616P LNK616 DIP-7 New
AUTHELECTRONIC
 
AN.G7.02.pdf
AN.G7.02.pdfAN.G7.02.pdf
AN.G7.02.pdf
NISHAN466433
 
TOP412GN.pdf
TOP412GN.pdfTOP412GN.pdf
TOP412GN.pdf
TopTechnoLabCompany
 
Design turbo generator
Design turbo generatorDesign turbo generator
Design turbo generator
Molla Morshad
 
UNIT IV design of Electrical Apparatus
UNIT IV design of Electrical ApparatusUNIT IV design of Electrical Apparatus
UNIT IV design of Electrical Apparatus
nganesh90
 
Design of Synchronous machine.pdf
Design of Synchronous machine.pdfDesign of Synchronous machine.pdf
Design of Synchronous machine.pdf
MaulikPandya25
 
UPS operation, Rev 2.pptx
UPS operation, Rev 2.pptxUPS operation, Rev 2.pptx
UPS operation, Rev 2.pptx
Jaimohan15
 
Integrated circuit
Integrated circuitIntegrated circuit
Integrated circuit
ddsshukla
 
Electrical energy issues presented by arshad khan chiniot power limited
Electrical energy issues presented by arshad khan chiniot  power limitedElectrical energy issues presented by arshad khan chiniot  power limited
Electrical energy issues presented by arshad khan chiniot power limited
arshadkhanmarwat
 
TC-MODULE – 2.pdf
TC-MODULE – 2.pdfTC-MODULE – 2.pdf
TC-MODULE – 2.pdf
Nayan351985
 

Similar to Generator capability curve (20)

(9) limitations
(9) limitations(9) limitations
(9) limitations
 
(9) Synchronous Alternator Capability Graph
(9) Synchronous Alternator Capability Graph(9) Synchronous Alternator Capability Graph
(9) Synchronous Alternator Capability Graph
 
Excitation and capability curve
Excitation and capability curveExcitation and capability curve
Excitation and capability curve
 
Original Power Supply IC LNK632DG LNK632 632 SOP-7 New
Original Power Supply IC LNK632DG LNK632 632 SOP-7 NewOriginal Power Supply IC LNK632DG LNK632 632 SOP-7 New
Original Power Supply IC LNK632DG LNK632 632 SOP-7 New
 
000747
000747000747
000747
 
Power Factor.ppt
Power Factor.pptPower Factor.ppt
Power Factor.ppt
 
powerfactor.pdf
powerfactor.pdfpowerfactor.pdf
powerfactor.pdf
 
268320253 hmwk5-solutions
268320253 hmwk5-solutions268320253 hmwk5-solutions
268320253 hmwk5-solutions
 
Original Power Supply IC LNK616PG LNK616P LNK616 DIP-7 New
Original Power Supply IC LNK616PG LNK616P LNK616 DIP-7 NewOriginal Power Supply IC LNK616PG LNK616P LNK616 DIP-7 New
Original Power Supply IC LNK616PG LNK616P LNK616 DIP-7 New
 
AN.G7.02.pdf
AN.G7.02.pdfAN.G7.02.pdf
AN.G7.02.pdf
 
TOP412GN.pdf
TOP412GN.pdfTOP412GN.pdf
TOP412GN.pdf
 
Design turbo generator
Design turbo generatorDesign turbo generator
Design turbo generator
 
UNIT IV design of Electrical Apparatus
UNIT IV design of Electrical ApparatusUNIT IV design of Electrical Apparatus
UNIT IV design of Electrical Apparatus
 
GenDesign
GenDesignGenDesign
GenDesign
 
Lm555
Lm555Lm555
Lm555
 
Design of Synchronous machine.pdf
Design of Synchronous machine.pdfDesign of Synchronous machine.pdf
Design of Synchronous machine.pdf
 
UPS operation, Rev 2.pptx
UPS operation, Rev 2.pptxUPS operation, Rev 2.pptx
UPS operation, Rev 2.pptx
 
Integrated circuit
Integrated circuitIntegrated circuit
Integrated circuit
 
Electrical energy issues presented by arshad khan chiniot power limited
Electrical energy issues presented by arshad khan chiniot  power limitedElectrical energy issues presented by arshad khan chiniot  power limited
Electrical energy issues presented by arshad khan chiniot power limited
 
TC-MODULE – 2.pdf
TC-MODULE – 2.pdfTC-MODULE – 2.pdf
TC-MODULE – 2.pdf
 

More from Ashish Kumar Jain

Proximate & ultimate analysis of coal
Proximate & ultimate analysis of coalProximate & ultimate analysis of coal
Proximate & ultimate analysis of coal
Ashish Kumar Jain
 
Assessment of boiler performance
Assessment of boiler performanceAssessment of boiler performance
Assessment of boiler performance
Ashish Kumar Jain
 
Condensate
Condensate Condensate
Condensate
Ashish Kumar Jain
 
Belt conveyor-manufacturing & utilization
Belt conveyor-manufacturing & utilizationBelt conveyor-manufacturing & utilization
Belt conveyor-manufacturing & utilization
Ashish Kumar Jain
 
Cooling tower
Cooling towerCooling tower
Cooling tower
Ashish Kumar Jain
 
Permacare RO membrane expertise
Permacare RO membrane expertisePermacare RO membrane expertise
Permacare RO membrane expertise
Ashish Kumar Jain
 
Governing system
Governing systemGoverning system
Governing system
Ashish Kumar Jain
 
Hydraullically assisted pressure relief valve service sheet
Hydraullically assisted pressure relief valve service sheetHydraullically assisted pressure relief valve service sheet
Hydraullically assisted pressure relief valve service sheet
Ashish Kumar Jain
 
Bhel STEAM safety valve_1700_series
Bhel STEAM safety valve_1700_seriesBhel STEAM safety valve_1700_series
Bhel STEAM safety valve_1700_series
Ashish Kumar Jain
 
Deaerator -thermal power plants
Deaerator  -thermal power plantsDeaerator  -thermal power plants
Deaerator -thermal power plants
Ashish Kumar Jain
 
Chiller absorption machine working principle
Chiller absorption machine  working principleChiller absorption machine  working principle
Chiller absorption machine working principle
Ashish Kumar Jain
 
Belt Conveyor System
Belt Conveyor SystemBelt Conveyor System
Belt Conveyor System
Ashish Kumar Jain
 
STEAM TURBINES Governing System & TROUBLE SHOOTING
STEAM TURBINES Governing System & TROUBLE SHOOTINGSTEAM TURBINES Governing System & TROUBLE SHOOTING
STEAM TURBINES Governing System & TROUBLE SHOOTING
Ashish Kumar Jain
 
High speed balancing of turbine rotors
High speed balancing of turbine rotorsHigh speed balancing of turbine rotors
High speed balancing of turbine rotors
Ashish Kumar Jain
 
Excel Tips in computers
Excel Tips in computersExcel Tips in computers
Excel Tips in computers
Ashish Kumar Jain
 
Thermal Power Plant - Emergency situations
Thermal Power Plant   -   Emergency situations Thermal Power Plant   -   Emergency situations
Thermal Power Plant - Emergency situations
Ashish Kumar Jain
 
Boiler -Emergency Handling
 Boiler -Emergency Handling Boiler -Emergency Handling
Boiler -Emergency Handling
Ashish Kumar Jain
 
Cogeneration power plant
Cogeneration power plantCogeneration power plant
Cogeneration power plant
Ashish Kumar Jain
 
Rankine cycle
Rankine cycleRankine cycle
Rankine cycle
Ashish Kumar Jain
 
Thermax IR CFBC BOILER U BEAM TYPE
Thermax IR CFBC BOILER                U BEAM TYPEThermax IR CFBC BOILER                U BEAM TYPE
Thermax IR CFBC BOILER U BEAM TYPE
Ashish Kumar Jain
 

More from Ashish Kumar Jain (20)

Proximate & ultimate analysis of coal
Proximate & ultimate analysis of coalProximate & ultimate analysis of coal
Proximate & ultimate analysis of coal
 
Assessment of boiler performance
Assessment of boiler performanceAssessment of boiler performance
Assessment of boiler performance
 
Condensate
Condensate Condensate
Condensate
 
Belt conveyor-manufacturing & utilization
Belt conveyor-manufacturing & utilizationBelt conveyor-manufacturing & utilization
Belt conveyor-manufacturing & utilization
 
Cooling tower
Cooling towerCooling tower
Cooling tower
 
Permacare RO membrane expertise
Permacare RO membrane expertisePermacare RO membrane expertise
Permacare RO membrane expertise
 
Governing system
Governing systemGoverning system
Governing system
 
Hydraullically assisted pressure relief valve service sheet
Hydraullically assisted pressure relief valve service sheetHydraullically assisted pressure relief valve service sheet
Hydraullically assisted pressure relief valve service sheet
 
Bhel STEAM safety valve_1700_series
Bhel STEAM safety valve_1700_seriesBhel STEAM safety valve_1700_series
Bhel STEAM safety valve_1700_series
 
Deaerator -thermal power plants
Deaerator  -thermal power plantsDeaerator  -thermal power plants
Deaerator -thermal power plants
 
Chiller absorption machine working principle
Chiller absorption machine  working principleChiller absorption machine  working principle
Chiller absorption machine working principle
 
Belt Conveyor System
Belt Conveyor SystemBelt Conveyor System
Belt Conveyor System
 
STEAM TURBINES Governing System & TROUBLE SHOOTING
STEAM TURBINES Governing System & TROUBLE SHOOTINGSTEAM TURBINES Governing System & TROUBLE SHOOTING
STEAM TURBINES Governing System & TROUBLE SHOOTING
 
High speed balancing of turbine rotors
High speed balancing of turbine rotorsHigh speed balancing of turbine rotors
High speed balancing of turbine rotors
 
Excel Tips in computers
Excel Tips in computersExcel Tips in computers
Excel Tips in computers
 
Thermal Power Plant - Emergency situations
Thermal Power Plant   -   Emergency situations Thermal Power Plant   -   Emergency situations
Thermal Power Plant - Emergency situations
 
Boiler -Emergency Handling
 Boiler -Emergency Handling Boiler -Emergency Handling
Boiler -Emergency Handling
 
Cogeneration power plant
Cogeneration power plantCogeneration power plant
Cogeneration power plant
 
Rankine cycle
Rankine cycleRankine cycle
Rankine cycle
 
Thermax IR CFBC BOILER U BEAM TYPE
Thermax IR CFBC BOILER                U BEAM TYPEThermax IR CFBC BOILER                U BEAM TYPE
Thermax IR CFBC BOILER U BEAM TYPE
 

Recently uploaded

Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
Pipe Restoration Solutions
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
PrashantGoswami42
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdfCOLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
Kamal Acharya
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
MuhammadTufail242431
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
ssuser9bd3ba
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 

Recently uploaded (20)

Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdfCOLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 

Generator capability curve

  • 1. GENERATOR OPERATION LIMITS By Pradeep Yadav, Dy. Director.
  • 2. When a manufacturer designs & construct an alternator, It will specify the MCR ( max. continuous rating )of the machine in terms of; 1. Stator current. The operation of the generator must be such that none of the design limitations are exceeded as otherwise damage to the generator may result. 2. Stator voltage. 3. Rotor current. 4. Rotor voltage. 5. MW. 6. MVA. 7. Power factor.
  • 3. There are 5 principal limitations on the generator operation. Principal limitations: A convenient way of presenting these limitations is in the form of a diagram called as “ Capability curve”. 1. Stator current limit. 2. Rotor current limit. 3. MW limit. 4. Stability limit. 5. Stator end heating limit.
  • 4. Assumption: Generator terminal voltage is maintained constant Erect a voltage vector “OA”. Capability curve :
  • 5. Principal limitations: 1. Stator current limit : Heat developed in the winding is limited by the class of Insulation. At higher current, overheating may damage insulation. Class “B” Insulation - 130 Deg. Cel. Class “F” or “H” - 180 Deg. Cel.
  • 6.
  • 7. 2. MW limit The Max. continuous MW rating is dictated by the steam generation capability of boiler & the H.P rating of the turbine. In theory, generators are capable of generating an output equal to MVA rating. But generators are designed to operate at a lagging p.f. ( 0.85 ). So that max.output is achieved at max.stator current & at rated p.f. MW = MVA X Cos =MVA at unity p.f. = V X I X Cos
  • 8. A horizontal line line drawn from point B will give MW limit boundary
  • 9. 3. Rotor current limit: Same reasoning as in case of stator current limit. Short Circuit Ratio( SCR ) is the ratio of field current required to induce rated nominal voltage in the Gen.terminal in open circuit condition TO the field current required to circulate rated stator current in the Gen. terminals with the terminals short circuited.
  • 10. Then, GB will represent full load rotor current or total field current. With GB as radius , draw an arc. It will be locus of rotor current and its limit. Angle between GO & GB will be Rotor angle or stability angle (). Select a point “G”, such that OG/OB = SCR of the generator.
  • 11. 4. Stability limit/Minimum rotor current limit: For every load condition of the generator, a minimum rotor current has to be supplied to maintain magnetic coupling in the air gap between stator & rotor.A reduction in field current without any change in steam admission will lead to break in magnetic coupling ( increase in rotor angle) with the subsequent loss of machine stability.
  • 12. Rotor angle ()= 90° - Theoritical stability limit. Practical stability limit () = 75°.
  • 13.
  • 14. 5. Stator end heating limit: With high values of stator current at leading power factor , heating of the end sections of the stator core tend to occur. The end heating limit would normally only be reached if the stability limits were exceeded.
  • 15. 1.Variation of terminal voltage: Voltage(KV) 14.18 14.96 15.75 16.54 16.7 16.85 17.01 17.17 17.32 ------------------------------------------------------------------------------------------------- Stator Current(KA)9.5 9.5 9.05 8.6 8.37 8.14 7.92 7.56 7.24 2.Frquency variation: +5%, -5% 3. Overloading: Stator current(KA) 9.95 10.41 10.86 11.31 11.76 12.22 12.67 13.57 Rotor current(KA) 2.75 -- -- --- 3.12 -- 3.9 5.2 Time ( Sec. ) 3600 900 360 300 240 180 120 60 4.Operation at different Hydrogen pressure: Hydrogen Pr.(Kg./Cm2) M.W. Duration 3.0 200 Continous 2.5 170 Not more than 5 Hrs. 2.0 140 -------do------ “Operation in air medium is not permitted”
  • 16. 6.One gas cooler out of service – 175 MW continously. More than one gas cooler out – operation not permitted. Coolent: Normal Limit Property Cold Hydrogen gas temp. 44 Deg.cel 55Deg.cel 3.5Kg/cm2. 99% pure Stator water temp. 45 Deg.cel 48 Deg.cel 27m3/hr.