SlideShare a Scribd company logo
1 of 38
PRESENTATION ON ELECTRO
HYDRAULIC CONTROL SYSTEM
 By
 Ashvani Shukla
 C&I
 Reliance
EHTC = ELECTRO-HYDRAULIC TURBINE CONTROLLER
IT IS THE GOVERNOR FOR TURBINE.
SYSTEM SUPPLIED BY BHEL-EDN, BANGALORE.
IMPLEMENTED IN THE METSO DNA DCS.
CONTROLLERS IN EHTC
• SPEED CONTROLLER – (MODES: PI, PD)
• ISOCHRONOUS FREQUENCY CONTROLLER
• LOAD CONTROLLER
• EXTRACTION-1 (IP EXTRACTION) CONTROLLER
• EXTRACTION-2 (LP EXTRACTION) CONTROLLER
EHTC
R
A
T
I
O
S
E
T
T
E
R
M
A
X
M
I
N
SPEED CONTROLLER
PI/PD MODE
LOAD / ISO FREQ
CONTROLLER
SPEED REF
LOAD REF
LOAD ACTUAL
SPEED ACTUAL
SPEED/LOAD LIMITERLIMIT REF
EXTRACTION-1
PRESSURE
CONTROLLER
PRESSURE REF
PRESSURE
ACTUAL
M
I
N
EXTRACTION-1 PRESSURE
LIMITER
LIMIT REF
EXTRACTION-2
PRESSURE
CONTROLLER
PRESSURE REF
PRESSURE
ACTUAL
M
I
N
EXTRACTION-2 PRESSURE
LIMITER
LIMIT REF
VALVE
CHARACTERISTIC
COMPENSATOR
HPCV LIFT REFERENCE
IPCV LIFT REFERENCE
LPCV LIFT REFERENCE
FREQ REF
FREQ ACTUAL
EHTC BLOCK DIAGRAM
EHTC FUNCTIONS
ROLLING
WARM UP
CRITICAL SPEED AVOIDANCE
LOAD / SPEED CONTROL
EXTRACTION PRESSURE
CONTROL
ISLANDING
TURBINE AUXILIARIES ARE STARTED, I.E. LUBE OIL SYS, CONDENSATE EXTRACTION SYS, ETC.
TURBINE PROTECTION IS RESET FROM ABB DCS AFTER FULFILLING THE CRITERIA
THE EMERGENCY SHUTOFF VALVE (ESV) IS OPENED
DEPENDING ON THE SHUTDOWN DURATION, THE TYPE OF TURBINE STARTS ARE AS FOLLOWS:
1. COLD START: AFTER 250 HOURS
2. WARM START: AFTER 40 HOURS
3. HOT START: AFTER 16 HOURS
WARM UP / SOAK TIME IS REQUIRED AS ROTOR EXPANDS FASTER THAN CASING DUE TO MASS
DIFFERENCE. WARM UP ENSURES THAT BOTH EXPAND PARALLELY AND CLEARANCES ARE
MAINTAINED & RUBBING OF PARTS IS AVOIDED.
TG SET IS THEN ROLLED USING THE SPEED CONTROL-PI MODE.
THE SPEED REFERENCE IS SELECTED AS PER THE START-UP CURVES GIVEN IN THE FOLLOWING
IMAGE I.E. 500 RPM / 3000 RPM / 5000 RPM.
ROLLING, WARM UP
CRITICAL SPEED AVOIDANCE
THE EHTC SPEED CONTROL RAISES THE SPEED AT FASTER RATE IN THE
CRITICAL SPEED BANDS TO MINIMIZE THE TIME OF OPERATION IN THIS
ZONE. AFTER WARM UP THE SPEED REFERENCE IS SET TO RATED VALUE FOR
SYNCHRONIZATION
CRITICAL SPEED BANDS
1300 TO 1700 RPM
2000 TO 2500 RPM
TG SET RUN AT RATED SPEED I.E. 5000 RPM
AVR VOLT CONTROL SWITCHED ON & GEN STATOR VOLT BUILT UP THRO’ AVR
TG FREQ IS VARIED BY CHANGING SPEED REF
THE FREQ, VOLT & PHASE ANGLE OF TG ARE MATCHED TO GRID BEFORE CLOSING GCB
GCB IS CLOSED. THIS SYNCHRONIZES THE TG SET WITH THE GRID
AS GCB CLOSES, THE EHTC MODE SWITCHES TO SPEED CONTROL-PD
SPEED CONTROLLER O/P INCREASES BY ABOUT 10% SO AS TO LOAD THE TG TO BLOCK LOAD OF
AROUND 1-2MW SO THAT GCB DOES NOT TRIP ON LOW FORWARD POWER.
AVR MODE IS MANUALLY CHANGED FROM VOLT CONTROL TO PF CONTROL
SYNCHRONIZATION AFTER ROLLING
SPEED CONTROLLER
PI -> PD MODE
SPEED REF
5000 -> 5083
SPEED ACTUAL
5000 RPM
15% -> 25%
SPEED CONTROLLER
AFTER SYNCHRONIZATION, LOAD CONTROLLER IS SWITCHED ON
EHTC SETS THE LOAD REF TO THE RUNNING LOAD AND ITS OUTPUT IS SET TO THE VALUE OF SPEED CONTROLLER OUTPUT
BY TRACKING I-ACTION
PD MODE
OUTPUT
=%ERROR *
GAIN
=0.16667*18=3.0
3.0%
SPEED REF
(SV) 5010
SPEED ACTUAL
(PV) 5000
%ERROR
=((SV-PV)/RANGE)*100
((5010-5000)/6000)*100
=0.16667%
LOAD CONTROL
SPEED CONTROLLER
PD MODE
LOAD CONTROLLER
PID
P=0, D=0, as SV=PV
I-action tracks 25%
SPEED REF
5083
LOAD REF
2 MW
LOAD ACTUAL
2 MW
SPEED ACTUAL
5000 RPM
25%
25%
SPEED CONTROL-PD SWITCHES TO SPEED TRACKING MODE I.E. THE SPEED REF TRACKS THE ACTUAL SPEED + 10 RPM TO
SET SPEED CONTROLLER OUTPUT AT 3.0% FIXED. (THE GAIN IS PRESSURE COMPENSATED AND INCREASES FROM 17 TO 22
AS MS PRESSURE REDUCES FROM 110 TO 90 ATA.)
NORMALLY TG SETS ARE IN LOAD CONTROL MODE WHEN SYNCHRONIZED WITH GRID.
IF THE TIE OPENS THEN TG SET(S) ARE ISLANDED, LOAD CONTROLLER SWITCHES OFF & SPEED
CONTROL-PD MODE TAKES OVER BUMPLESSLY.
DURING THIS SWITCH OVER, THE SPEED REF IS CALCULATED SUCH THAT THE OUTPUT OF LOAD
CONTROLLER (2S DELAYED) IS AVAILABLE AT SPEED CONTROLLER OUTPUT IN PD MODE. AFTER THIS
THE LOAD CONTROLLER SWITCHES OFF & TG SET RUNS IN SPEED CONTROL-PD MODE.
ISLANDING
SPEED CONTROLLER
PD MODE
LOAD CONTROLLER
PID
P=0, D=0, as SV=PV
I-action tracks 25%
SPEED REF
5010 -> 5167
LOAD REF
20 -> 0
LOAD ACTUAL
20 MW
SPEED ACTUAL
5000 RPM
3% -> 50%
50% -> 0%
DROOP
DROOP CONTROL IS REQUIRED IN SYSTEMS WHERE A COMMON PARAMETER IS CONTROLLED BY 2 OR
MORE SYSTEMS.
E.G. FREQ OR VOLT CONTROL IN CASE OF 2 OR MORE SYNCHRONIZED TG SETS.
COMMON HEADER PRESSURE CONTROL IN CASE OF 2 OR MORE BOILERS.
IF A COMMON PARAMETER IS SENSED BY TWO OR MORE SENSORS, THE READINGS CANNOT MATCH
EXACTLY. THERE WILL ALWASYS BE SOME DIFFERENCE EVEN THOUGH IT MAY BE VERY SMALL. IF
BOTH SENSORS PROVIDE PV TO TWO DIFFEENT PID CONTROLLERS THEN THEY WILL TEND TO
SATURATE IN OPPOSITE DIRECTIONS.
E.G. CONSIDER A CASE OF TWO TG SETS “L” & “H” RUNNING IN SYNCHRONIZED CONDITION. LET BOTH
TG GOVERNORS BE SET TO ISOCHRONOUS FREQ CONTROL I.E. SPEED PID CONTROL. LET REF OF
BOTH TG BE SET AT 50.00HZ.
LET THE ACTUAL SYSTEM BUS FREQ BE 50.00HZ, AND ONE SENSOR SENSES L=49.99 & OTHER H=50.01.
THE INTEGRAL ACTION OF L WILL INCREASE OUTPUT AND H WILL DECREASE OUTPUT TO BRING FREQ
TO 50.00. THIS PROCESS WILL CONTINUE AS THERE WILL ALWAYS BE OFFSET IN THE READINGS OF L &
H, SO GRADUALLY L OUTPUT WILL SATURATE TO 100% AND H OUTPUT WILL SATURATE TO 0%.
SO EITHER THE INTEGRAL ACTION IS REMOVED I.E PD ACTION SELECTED OR REF IS CHANGED AS PER
CONTROLLER OUTPUT TO INSERT DROOP OR OFFSET IN THE CONTROL ACTION I.E. REF & PV ARE NOT
MATCHED.
DROOP
% DROOP MEANS % CHANGE IN FREQ FOR 100 % CHANGE IN LOAD.
4% DROOP IMPLIES 4% FREQ CHANGE WILL CAUSE 100% CHANGE IN LOAD. i.e. GAIN=100/4=25%
DROOP
FRE
Q
Hz
LOAD
MW320
50.0
2711
51.5
DROOP = % CHANGE IN FREQ FOR 100 % CHANGE IN LOAD = (3/50)*100 = 6%
GAIN = 100/DROOP = 16.7
LOAD ON TG IS REDUCED FROM 27MW TO 11MW I.E. 16MW OR 50% LOAD THROW
SO GOVERNOR OUPUT SHOULD REDUCE by 50% I.E. FROM 81.4% TO 34.4% FOR
STABLE FREQ
(IN TG SPEED CONTROL THE GOV VLV OPENING SHOULD EXACTLY MATCH THE LOAD ELSE SPEED WILL
KEEP ON RAMPING. THIS IS KNOWN AS INTEGRATING TYPE OF PROCESS.)
THE 34.4% O/P IS REQUIRED AT 11MW LOAD TO KEEP FREQ STABLE. BUT 34.4% O/P IS AVAILABLE AT 51.5HZ
FREQ. THIS OFFSET IS RESET BY MANUALLY DECREASING THE SPEED REF (SV) SO THAT 34.4% O/P IS
1.5 Hz = 3%
27-11
= 16MW
=50%
10
0
0 84.
4
34.4 GOV O/P
%
84.4%
SPEED CONTROLLER
PD MODE
OUTPUT
=%ERROR *
GAIN
%ERROR
=((SV-
PV)/RANGE)*100
O/P %
SPEED CONTROLLER
=5.05*16.7=84.4
((5253-
5000)/5000)*100
=5.05%
34.4%
SPEED CONTROLLER
=2.06*16.7=34.4
((5253-
5150)/5000)*100
=2.06%
SPEED REF SV
SPEED
ACTUAL PV
5253
5000
5253
5150
34.4%
SPEED CONTROLLER
=2.06*16.7=34.4
((5103-
5000)/5000)*100
=2.06%
5103
5000
DROOP
ISOCHRONOUS FREQ CONTROL
CONSIDER FOLL SEQUENCE OF EVENTS:
THREE TG SETS LOADED AT 27MW EACH, GRID AT 15MW I.E. TOTAL LOAD 96MW
CHEMICAL DIV. TRIPS (70MW LOAD THROW), BALANCE LOAD IS 96MW-70MW=26MW
GRID TRIPS (15MW) ON REV POWER
THE 3 TG SETS ARE ISLANDED IN DROOP MODE (DROOP=6%), CONNECTED LOAD = 26MW, I.E. 8.67MW PER TG
SO, FOR EACH TG SET % LOAD REDUCTION = [(27 - 8.67)/32]*100 = 57.28%
THE GOV O/P CHANGE = (%FREQ ERROR)*(GAIN)
So, % FREQ ERROR = 57.28/16.7 = 3.43% I.E. 3.43/2 = 1.7HZ
SO FINAL FREQ WILL STABILIZE AT 51.7HZ, WHICH WILL TRIP ALL TG SETS ON OVERFREQ
IF ONE TG IS IN ISOCHRONOUS FREQ CONTROL IN ISLAND MODE, THEN THIS TG SET WILL TRIP AFTER FULLY
UNLOADING & ONLY 2 TG SETS WITH DROOP WILL RUN I.E. 13MW PER TG SET
SO, FOR EACH TG SET % LOAD REDUCTION = [(27 - 13)/32]*100 = 57.28%
THE GOV O/P CHANGE = (%FREQ ERROR)*(GAIN)
So, % FREQ ERROR = 57.28/16.7 = 3.43% I.E. 3.43/2 = 1.7HZ
ISO FREQ CONTROL MODE IS PRESELECTED WHILE TG RUNNING IN LOAD
CONTROL MODE, SO THAT DURING ISLANDING, THE ISO FREQ CONTROL MODE
WILL BECOME ACTIVE. AT PRESENT, ONE TG IS SELECTED FOR ISO & OTHER
TWO FOR SPEED CONTROL-PD MODE (DROOP).
SO ON ISLANDING, THE THREE TG SETS ARE ISLANDED WITH ONE IN ISO MODE
& OTHER TWO IN DROOP MODE. IF DURING OR AFTER ISLANDING LOAD IS
ADDED OR REMOVED, THEN SYSTEM FREQ WILL CHANGE, BUT THE TURBINE
ON FREQ CONTROL MODE WILL KEEP ON CHANGING OUPUT TILL THE SYSTEM
FREQ RETURNS TO 50HZ. THUS SYSTEM FREQ IS MAINTAINED.
TWO OR MORE TG SETS IN A SYNCHRONIZED SYSTEM CANNOT BE PUT IN
ISOCHRONOUS MODE AT THE SAME TIME, AS ONE TG SET WILL LOAD FULLY &
OTHER WILL FULLY UNLOAD DEPENDING ON MINOR DIFFERENCES IN
SPEED/FREQ SENSORS OF THE TWO TG SETS. THEREBY DROOP MODE IS
REQUIRED.
ISOCHRONOUS FREQ CONTROL
LOAD
CONTROLLER
PID
LOAD REF
25MW
LOAD ACTUAL
20MW ISOCHRONOUS
FREQ
CONTROLLER
PIDFREQ REF
50HZ
FREQ ACTUAL
50HZ
ISOCHRONOUS FREQ CONTROL
LOAD CONTROL
TG SYNCHRONIZED WITH GRID
ISOCHRONOUS FREQ
CONTROL
TG ISLANDED
LOAD REF
20MW
LOAD
ACTUAL
20MW
FREQ REF
50HZ
FREQ ACTUAL
51HZ
ISLANDI
NG
LOAD SHEDDING LOGIC
IF TIE/GRID BREAKER TRIPS, & PRO RATA LOAD ON GRID IS NOT SHED THEN THE BALANCE TG SETS MAY TRIP ON
UNDER-FREQUENCY.
IF A TG SET TRIPS, ITS LOAD SHIFTS TO GRID, & TIE BREAKER TRIPS IF IMPORT EXCEEDS 20MVA (CONTRACT
DEMAND LIMITATION). AFTER ISLANDING THE ENTIRE LOAD OF (GRID+TRIPPED TG) SHIFTS TO BALANCE TG SETS
WHICH RESULTS IN UNDER-FREQ TRIPPING OF BALANCE TG SETS & BLACKOUT. SO, PROPORTIONATE LOAD IS TO
BE SHED TO PREVENT BALANCE TG SETS FROM TRIPPING ON UNDER-FREQUENCY.
THE RECTIFORMER NOS. 1,2,3,4 ARE SHED FROM DCS AS PART OF LOAD SHEDDING LOGIC. THE PROPORTIONAL
LOAD IS SHED WITHIN 400MS THROUGH DCS.
G1
25MW
G2
25MW
G3
25MW
GRID
15MW
CD
60MWVSF
25MW
CPP
5MW
TOTAL LOAD=90MW
G1
25MW
G2
25MW
G3
25MW
GRID
45MW
VSF
25MW
CPP
5MW
TOTAL LOAD=30MW
EXPORT=45MW
TG GEN=75MW
TG GEN=75MW
IMPORT=15MW
G1
25MW
G2
25MW
GRID
40MW
CD
60MWVSF
25MW
CPP
5MW
TOTAL LOAD=90MW
TG GEN=50MWIMPORT=40MW
CASE1: TG TRIP CASE2: LOAD THROW
RATIO SETTER
Exhaust flow
HP CV OPN
HP CV CLS
EXT CV
OPN
EXT CV
CLS
RATIO SETTER
TO CALCULATE THE TURBINE INTERNAL PRESSURE RATIOS AND LIMITS,THE
INTERSECTION POINTS NEEDED ARE A,B,C
A: MAX POWER @ MIN EXTRACTION
B: MIN POWER @ MAX EXTRACTION
C: MIN HP FLOW @ MIN EXTRACTION
THE TURBINE SPEED/LOAD & EXTRACTION PRESSURE NEED TO BE
MAINTAINED AT CONSTANT LEVELS SIMULTANEOUSLY. CHANGING THE
POSITION OF EITHER THE HP, IP OR LP VALVE AFFECTS BOTH TURBINE
SPEED/LOAD AND EXTRACTION PRESSURE. SO, TO CHANGE SPEED/LOAD
ALL VALVES NEED TO BE ADJUSTED SO THAT ONLY THE SPEED/LOAD IS
AFFECTED WITH MIN. OR NO DISTURBANCE TO THE EXTRACTION
PRESSURES. SIMILARLY WHILE CHANGING IP EXTRACTION PRESSURE THE
SPEED/LOAD OR THE LP EXTRACTION SHOULD NOT BE DISTURBED. RATIO
SETTER CALCULATES THE OUTPUTS TO MINIMIZE THE CONTROLLED
PARAMETERS INTERACTIONS EFFECTING EACH OTHER, AND TO KEEP THE
ACTUATOR OUTPUTS WITHIN THE BOUNDARIES OF TURBINE STEAM MAP OR
ENVELOPE CURVE.
RATIO SETTER
S.N. EXTR-1
CONTROL
O/P
(YE1)
EXTR-2
CONTROL O/P
(YE2)
SPEED
CONTROL
GAIN
RATIO SETTER
GAIN FOR
SPEED/LOAD
CONTROL O/P (YN)
EFFECTIVE
GAIN
1 0 0 8 1.2 9.6
2 1 1 8 7.5 60
THE RATIO SETTER DETAILS WERE OBTAINED FROM BHEL-HYD & FOUND THAT GAIN WAS THROUGHOUT
LINEAR FOR ALL THREE CONTROLLER OUTPUTS I.E. YN, YE1 & YE2.
FOR, YN (LOAD/SPEED CONTROLLER O/P) THE GAIN WAS THROUGHOUT LINEAR AT 0.632.
THE SNAPSHOTS WERE SENT TO BHEL-HYD FOR CONFIRMATION AND FOUND THAT WRONG RATIO SETTER
WAS INSTALLED IN ALL THREE TG SET CONTROLLERS BY BHEL-EDN.
RATIO SETTER RELATED ISSUES
THE ORIGINAL RATIO SETTER IMPLEMENTED BY BHEL-EDN WAS FAULTY WITH NON-LINEAR GAIN AS GIVEN
IN THE BELOW TABLE.
TURBINE GOVERNING SYSTEM RELATED ISSUES PERTAINING TO ISLAND CONDITION:
IN ISLAND CONDITION, SPEED TRANSIENT OVERSHOOT, SPEED HUNTING & STABILITY ISSUES WERE PERSISTING.
FOLLOWING MAJOR CHANGES WERE IMPLEMENTED:
1) THE RATIO SETTER GAIN FOR HPCV OUTPUT WAS FOUND TO BE VARYING FROM “9” TO “59” DEPENDING ON
THE EXTRACTION CONTROLLER OUTPUTS. RATIO SETTER FROM BHEL-HYD WITH FIXED GAIN & LINEAR
CHARACTERISTIC WAS IMPLEMENTED. TRANSFER FUNCTION WAS OBTAINED FROM BHEL-HYD & THE SPEED
CONTROLLER P-GAIN VALUE CHANGED FROM “8” TO “18”.
2) DURING ISLANDING THE HP & IP EXTRACTION CONTROLLERS SWITCH OVER TO MANUAL MODE TO PREVENT
EXTRACTION LOOP INTERACTIONS FROM DISTURBING THE SPEED CONTROLLER & REDUCE THE TRANSIENT
SETTLING TIME. AFTER STEADY STATE ACHIEVED, OPERATOR CAN SWITCH THE CONTROLLERS TO AUTO.
3) IN MAIN DCS, LOAD SHEDDING SCHEME IMPLEMENTED BY SHEDDING THE PRIORITY BASED PRO-RATA LOADS
OF THE RECTIFORMER NOS. 1-4.
4) FREQUENCY CONTROL MODE OR ISOCHRONOUS MODE WAS IMPLEMENTED SO THAT THE SYSTEM
FREQUENCY RETURNS TO 50 HZ AT STEADY STATE AFTER A DISTURBANCE IN ISLANDING CONDITION.
K = SYSTEM GAIN = 100/(% STEADY STATE SPEED REGULATION) = 100/5 = 20
T1 = GOVERNOR TIME CONSTANT = 0.02-0.1S
T2 = DERIVATIVE GAIN X GOVERNOR TIME CONST = 0.1S
T3 = CONTROL VALVE ACTUATOR TIME CONST = 0.1S
PUP = CV OPEN = 1 PU PER S
PDOWN = CV CLOSE = 2.5 PU PER S
PMIN = MIN POWER LIMIT
PMAX = MAX POWER LIMIT
PGV = POWER AT VALVE OUTLET
S = COMPLEX FREQ VARIABLE (LAPLACE TRANSFORM)
FHP = HP TURBINE POWER FRACTION = 0.505
FIP = IP TURBINE POWER FRACTION = 0.256
FLP = LP TURBINE POWER FRACTION = 0.239
THP = HP TURBINE TIME CONST = 0.115S
TIP = IP TURBINE TIME CONST = 0.122S
TLP = LP TURBINE TIME CONST = 0.125S
DW = SPEED DEVIATION
PM = MECH POWER
P0 = INITIAL POWER
PGV = POWER AT VALVE OUTLET
BEFORE SYNCHRONIZING AN INCOMING UNIT TO A RUNNING SYSTEM, THE
FOLLOWING PARAMETERS SHOULD BE MATCHED CLOSELY SO TO MINIMIZE
TRANSFER OF ENERGY
•VOLTAGE
•FREQUENCY
•PHASE ANGLE
•PHASE SEQUENCE
THE CIRCUIT BREAKER IS CLOSED TO TIE THE “INCOMING” SYSTEM TO THE
“RUNNING” SYSTEM ELECTRICALLY
GENERAT
OR
DC CURRENT IS FED TO FIELD WINDING IN ROTOR TO CREATE MAGNETIC
FIELD
THIS ROTATING MAGNETIC FIELD INDUCES VOLTAGE IN THE STATOR
ARMATURE WINDING
THE DC CURRENT TO THE ROTOR FIELD WINDING IS CALLED FIELD
CURRENT.
RPM=120*(f/P)
f = frequency (Hz)
P = total number of poles
G1
100
MW
100
MW
LOAD SIDE
PF=COSΦ=0.8
ACTIVE POWER=VI.COSΦ=100MW
TOTAL POWER=VI=125MVA
SO REACTIVE POWER = 25MVAr
BOTH ACTIVE PWR 100MW &
REACTIVE PWR 25MVAr
SUPPLIED BY G1 .
AVR MODE = VOLT CONTROL
G1
50
MW
100
MW
G1 ACTIVE PWR CONTROL BY STEAM FLOW
CONTROL
G1 REACTIVE PWR CONTROL BY EXCITATION
CONTROL
AVR MODE = PF CONTROL OR REACTIVE PWR
CONTROL
G1 OVEREXCITED => PF LEADING => REACTIVE
PWR OUT .
G1 UNDEREXCITED => PF LAGGING => REACTIVE
GRID
50MW
PF=0.8
25MVAr
PF=0.
8
PF=0.
8
PF=0.9
5.5MVAr
PF=0.72
19.5MVAr
CAPABILITY CURVE
REGION A-B: LAGGING POWER FACTOR
•GENERATOR IS OVER-EXCITED I.E. MORE FIELD CURRENT
•CAPABILITY LIMITATION IS FIELD OVERHEATING
•
REGION B-C: RATED POWER FACTOR
•CAPABILITY LIMITATION IS DEPENDENT ON THE STATOR CURRENT
•MAXIMUM GENERATOR NAMEPLATE STATOR AMPERES SHOULD NOT BE
EXCEEDED
REGION C-D: LEADING POWER FACTOR
•CAPABILITY LIMITATION DUE TO EXCESSIVE HEATING IN THE STATOR IRON
CORE DUE TO FLUX LEAKAGE
•THIS IS ALSO AN UNDEREXCITATION REGION & CAPABILITY IS FURTHER
REDUCED BY THE VOLTAGE SQUARED DURING REDUCED TERMINAL
VOLTAGE OPERATION
LOAD
ANGLE
AT ZERO LOAD, FIELD POLE OF
ROTOR IS “IN PHASE” WITH
STATOR FIELD, SO POWER
ANGLE IS 0
AS LOAD ADDED , ROTOR
ADVANCES WITH RESPECT TO
THE STATOR, THE LOAD ANGLE
INCREASES.
LOAD ANGLE ALSO INCREASES
WITH UNDEREXCITATION AND
MAY RESULT IN ROTOR
GETTING OUT OF
SYNCHRONISM WITH
NETWORK FREQ IF ROTOR
STABILITY LIMIT IS
TRANSGRESSED
 THANK YOU

More Related Content

What's hot

turbine governing oil system
turbine governing oil systemturbine governing oil system
turbine governing oil systempradeep chotia
 
Handling of turbine side emergencies
Handling of turbine side emergenciesHandling of turbine side emergencies
Handling of turbine side emergenciesManohar Tatwawadi
 
Thermal Power Plant - Emergency situations
Thermal Power Plant   -   Emergency situations Thermal Power Plant   -   Emergency situations
Thermal Power Plant - Emergency situations Ashish Kumar Jain
 
INTRODUCTION TO GOVERNING
INTRODUCTION TO GOVERNINGINTRODUCTION TO GOVERNING
INTRODUCTION TO GOVERNINGSURAJ KUMAR
 
Hp/ lp bypass system for steam turbines
Hp/ lp bypass system for steam turbinesHp/ lp bypass system for steam turbines
Hp/ lp bypass system for steam turbinesBoben Anto Chemmannoor
 
Turbine Governing System
Turbine Governing SystemTurbine Governing System
Turbine Governing SystemSalil Vaidya
 
Generator cooling and sealing system 2
Generator cooling and sealing system 2Generator cooling and sealing system 2
Generator cooling and sealing system 2Mohammad Basid
 
Furnace Guard Supervisory System (FSSS)
Furnace Guard Supervisory System (FSSS)Furnace Guard Supervisory System (FSSS)
Furnace Guard Supervisory System (FSSS)Jigyasa Singh
 
Starting & Recommended Interlocks for AH,ID,FD,PA Fans & BD Valves for 270 MW...
Starting & Recommended Interlocks for AH,ID,FD,PA Fans & BD Valves for 270 MW...Starting & Recommended Interlocks for AH,ID,FD,PA Fans & BD Valves for 270 MW...
Starting & Recommended Interlocks for AH,ID,FD,PA Fans & BD Valves for 270 MW...Manohar Tatwawadi
 
Unit lightup synchronisation & shutdown
Unit lightup synchronisation & shutdownUnit lightup synchronisation & shutdown
Unit lightup synchronisation & shutdownNitin Mahalle
 
Governing and protection system
Governing and protection systemGoverning and protection system
Governing and protection systemSachin Pyasi
 
Unit shutdown procedure operation
Unit shutdown procedure operationUnit shutdown procedure operation
Unit shutdown procedure operationNitin Patel
 
AUTOMATIC TURBINE RUNUP SYSTEM
AUTOMATIC TURBINE RUNUP SYSTEMAUTOMATIC TURBINE RUNUP SYSTEM
AUTOMATIC TURBINE RUNUP SYSTEMkumarswamy927
 
STEAM TURBINES Governing System & TROUBLE SHOOTING
STEAM TURBINES Governing System & TROUBLE SHOOTINGSTEAM TURBINES Governing System & TROUBLE SHOOTING
STEAM TURBINES Governing System & TROUBLE SHOOTINGAshish Kumar Jain
 

What's hot (20)

Boiler light up & loading
Boiler light up & loadingBoiler light up & loading
Boiler light up & loading
 
turbine governing oil system
turbine governing oil systemturbine governing oil system
turbine governing oil system
 
Handling of turbine side emergencies
Handling of turbine side emergenciesHandling of turbine side emergencies
Handling of turbine side emergencies
 
Thermal Power Plant - Emergency situations
Thermal Power Plant   -   Emergency situations Thermal Power Plant   -   Emergency situations
Thermal Power Plant - Emergency situations
 
INTRODUCTION TO GOVERNING
INTRODUCTION TO GOVERNINGINTRODUCTION TO GOVERNING
INTRODUCTION TO GOVERNING
 
Hp/ lp bypass system for steam turbines
Hp/ lp bypass system for steam turbinesHp/ lp bypass system for steam turbines
Hp/ lp bypass system for steam turbines
 
Turbine Governing System
Turbine Governing SystemTurbine Governing System
Turbine Governing System
 
Generator cooling and sealing system 2
Generator cooling and sealing system 2Generator cooling and sealing system 2
Generator cooling and sealing system 2
 
Furnace Guard Supervisory System (FSSS)
Furnace Guard Supervisory System (FSSS)Furnace Guard Supervisory System (FSSS)
Furnace Guard Supervisory System (FSSS)
 
Starting & Recommended Interlocks for AH,ID,FD,PA Fans & BD Valves for 270 MW...
Starting & Recommended Interlocks for AH,ID,FD,PA Fans & BD Valves for 270 MW...Starting & Recommended Interlocks for AH,ID,FD,PA Fans & BD Valves for 270 MW...
Starting & Recommended Interlocks for AH,ID,FD,PA Fans & BD Valves for 270 MW...
 
Boiler safety protection
Boiler  safety protectionBoiler  safety protection
Boiler safety protection
 
Unit lightup synchronisation & shutdown
Unit lightup synchronisation & shutdownUnit lightup synchronisation & shutdown
Unit lightup synchronisation & shutdown
 
Turbine safety protection
Turbine safety protectionTurbine safety protection
Turbine safety protection
 
200 mw FSSS
200 mw FSSS200 mw FSSS
200 mw FSSS
 
Governing and protection system
Governing and protection systemGoverning and protection system
Governing and protection system
 
Unit shutdown procedure operation
Unit shutdown procedure operationUnit shutdown procedure operation
Unit shutdown procedure operation
 
Stator water system chemistry
Stator water system chemistryStator water system chemistry
Stator water system chemistry
 
AUTOMATIC TURBINE RUNUP SYSTEM
AUTOMATIC TURBINE RUNUP SYSTEMAUTOMATIC TURBINE RUNUP SYSTEM
AUTOMATIC TURBINE RUNUP SYSTEM
 
FURNACE SAFEGUARD SUPERVISORY SYSTEM (FSSS)
FURNACE SAFEGUARD SUPERVISORY SYSTEM (FSSS)FURNACE SAFEGUARD SUPERVISORY SYSTEM (FSSS)
FURNACE SAFEGUARD SUPERVISORY SYSTEM (FSSS)
 
STEAM TURBINES Governing System & TROUBLE SHOOTING
STEAM TURBINES Governing System & TROUBLE SHOOTINGSTEAM TURBINES Governing System & TROUBLE SHOOTING
STEAM TURBINES Governing System & TROUBLE SHOOTING
 

Viewers also liked

Combined ff and iec applications
Combined ff and iec applications  Combined ff and iec applications
Combined ff and iec applications Ashvani Shukla
 
Temperature measurement
Temperature measurementTemperature measurement
Temperature measurementAshvani Shukla
 
Furnace safegaurd supervisory system logic-1
Furnace safegaurd supervisory system logic-1Furnace safegaurd supervisory system logic-1
Furnace safegaurd supervisory system logic-1Ashvani Shukla
 
Endurance Testing of Aircraft Electro-Hydraulic Actuator Using LabVIEW
Endurance Testing of Aircraft Electro-Hydraulic Actuator Using LabVIEWEndurance Testing of Aircraft Electro-Hydraulic Actuator Using LabVIEW
Endurance Testing of Aircraft Electro-Hydraulic Actuator Using LabVIEWWaqas Tariq
 
Electro Pneaumatic Breaking system
Electro Pneaumatic Breaking systemElectro Pneaumatic Breaking system
Electro Pneaumatic Breaking systemGnana Deepa Choudary
 
2010 electro hydraulic%20braking%20system%20for%20autonomous%20vehicles
2010 electro hydraulic%20braking%20system%20for%20autonomous%20vehicles2010 electro hydraulic%20braking%20system%20for%20autonomous%20vehicles
2010 electro hydraulic%20braking%20system%20for%20autonomous%20vehiclesakhilphani
 
Device exchange and calibration
Device exchange and calibration Device exchange and calibration
Device exchange and calibration Ashvani Shukla
 
Control configuration in digital control
Control configuration in digital controlControl configuration in digital control
Control configuration in digital controlAshvani Shukla
 
A process control primer
A process control primerA process control primer
A process control primerPhilani Ngema
 
DCS and Fieldbus Software installation
DCS and Fieldbus Software installation DCS and Fieldbus Software installation
DCS and Fieldbus Software installation Ashvani Shukla
 
Control configuration in digital control
Control configuration in digital controlControl configuration in digital control
Control configuration in digital controlAshvani Shukla
 
Water analysis from_intake_well_to_boiler_drum-n
Water analysis from_intake_well_to_boiler_drum-nWater analysis from_intake_well_to_boiler_drum-n
Water analysis from_intake_well_to_boiler_drum-npriyank.modi
 
Furnace pressure control
Furnace pressure controlFurnace pressure control
Furnace pressure controlAshvani Shukla
 
K11619 rishabh jain
K11619 rishabh jainK11619 rishabh jain
K11619 rishabh jainRishabh Jain
 

Viewers also liked (20)

Modern coupling
Modern couplingModern coupling
Modern coupling
 
Combined ff and iec applications
Combined ff and iec applications  Combined ff and iec applications
Combined ff and iec applications
 
Temperature measurement
Temperature measurementTemperature measurement
Temperature measurement
 
Furnace safegaurd supervisory system logic-1
Furnace safegaurd supervisory system logic-1Furnace safegaurd supervisory system logic-1
Furnace safegaurd supervisory system logic-1
 
Endurance Testing of Aircraft Electro-Hydraulic Actuator Using LabVIEW
Endurance Testing of Aircraft Electro-Hydraulic Actuator Using LabVIEWEndurance Testing of Aircraft Electro-Hydraulic Actuator Using LabVIEW
Endurance Testing of Aircraft Electro-Hydraulic Actuator Using LabVIEW
 
Electro Pneaumatic Breaking system
Electro Pneaumatic Breaking systemElectro Pneaumatic Breaking system
Electro Pneaumatic Breaking system
 
2010 electro hydraulic%20braking%20system%20for%20autonomous%20vehicles
2010 electro hydraulic%20braking%20system%20for%20autonomous%20vehicles2010 electro hydraulic%20braking%20system%20for%20autonomous%20vehicles
2010 electro hydraulic%20braking%20system%20for%20autonomous%20vehicles
 
Device exchange and calibration
Device exchange and calibration Device exchange and calibration
Device exchange and calibration
 
Control configuration in digital control
Control configuration in digital controlControl configuration in digital control
Control configuration in digital control
 
A process control primer
A process control primerA process control primer
A process control primer
 
DCS and Fieldbus Software installation
DCS and Fieldbus Software installation DCS and Fieldbus Software installation
DCS and Fieldbus Software installation
 
Lecture 03 overview of micro fabrication
Lecture 03   overview of micro fabricationLecture 03   overview of micro fabrication
Lecture 03 overview of micro fabrication
 
Lecture 05 cmos logic gates
Lecture 05   cmos logic gatesLecture 05   cmos logic gates
Lecture 05 cmos logic gates
 
Lecture 06,07 cmos fabrication
Lecture 06,07   cmos fabricationLecture 06,07   cmos fabrication
Lecture 06,07 cmos fabrication
 
Control configuration in digital control
Control configuration in digital controlControl configuration in digital control
Control configuration in digital control
 
Water analysis from_intake_well_to_boiler_drum-n
Water analysis from_intake_well_to_boiler_drum-nWater analysis from_intake_well_to_boiler_drum-n
Water analysis from_intake_well_to_boiler_drum-n
 
Furnace pressure control
Furnace pressure controlFurnace pressure control
Furnace pressure control
 
Lecture 04 wafer technology & basics of cmos
Lecture 04   wafer technology & basics of cmosLecture 04   wafer technology & basics of cmos
Lecture 04 wafer technology & basics of cmos
 
K11619 rishabh jain
K11619 rishabh jainK11619 rishabh jain
K11619 rishabh jain
 
Lecture 02 history & characteristics of mems
Lecture 02   history & characteristics of memsLecture 02   history & characteristics of mems
Lecture 02 history & characteristics of mems
 

Similar to Electrohydraulic governing system

Automatic generation control&voltage control(module 5:ktu syllabus)
Automatic generation control&voltage control(module 5:ktu syllabus)Automatic generation control&voltage control(module 5:ktu syllabus)
Automatic generation control&voltage control(module 5:ktu syllabus)Asha Anu Kurian
 
gas turbine generator set operation and maintenance
gas turbine generator set operation and maintenancegas turbine generator set operation and maintenance
gas turbine generator set operation and maintenanceAmrSherif54
 
Cruise control simulation using matlab
Cruise control simulation using matlabCruise control simulation using matlab
Cruise control simulation using matlabHira Shaukat
 
GenSync - User Guide
GenSync - User GuideGenSync - User Guide
GenSync - User GuideRichard Smith
 
LOAD FREQUENCY CONTROL USING ELECTRIC VEICHLE SYSTEM IN INTERCONNECTED POWER ...
LOAD FREQUENCY CONTROL USING ELECTRIC VEICHLE SYSTEM IN INTERCONNECTED POWER ...LOAD FREQUENCY CONTROL USING ELECTRIC VEICHLE SYSTEM IN INTERCONNECTED POWER ...
LOAD FREQUENCY CONTROL USING ELECTRIC VEICHLE SYSTEM IN INTERCONNECTED POWER ...NarendraKasana1
 
SPEED GOVERNOR SYSYTEM AND ITS DERIVATIONS
SPEED GOVERNOR SYSYTEM AND ITS DERIVATIONSSPEED GOVERNOR SYSYTEM AND ITS DERIVATIONS
SPEED GOVERNOR SYSYTEM AND ITS DERIVATIONSDeepthipriyaSK
 
SIPAT 660 MW Turbo- Governing & Protection System.ppt
SIPAT 660 MW Turbo- Governing & Protection System.pptSIPAT 660 MW Turbo- Governing & Protection System.ppt
SIPAT 660 MW Turbo- Governing & Protection System.pptMarcWorld
 
Frequency Control & AGC.ppt
Frequency Control & AGC.pptFrequency Control & AGC.ppt
Frequency Control & AGC.pptSurajit Banerjee
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentIJERD Editor
 
PID Compensator Control Scheme of Synchronous Buck DC-DC Converter with ZVS L...
PID Compensator Control Scheme of Synchronous Buck DC-DC Converter with ZVS L...PID Compensator Control Scheme of Synchronous Buck DC-DC Converter with ZVS L...
PID Compensator Control Scheme of Synchronous Buck DC-DC Converter with ZVS L...IJRES Journal
 

Similar to Electrohydraulic governing system (20)

Automatic generation control&voltage control(module 5:ktu syllabus)
Automatic generation control&voltage control(module 5:ktu syllabus)Automatic generation control&voltage control(module 5:ktu syllabus)
Automatic generation control&voltage control(module 5:ktu syllabus)
 
CMC.pptx
CMC.pptxCMC.pptx
CMC.pptx
 
On off controller
On off controllerOn off controller
On off controller
 
3.CONTROL ACTIONS.pptx
3.CONTROL ACTIONS.pptx3.CONTROL ACTIONS.pptx
3.CONTROL ACTIONS.pptx
 
digital
digitaldigital
digital
 
gas turbine generator set operation and maintenance
gas turbine generator set operation and maintenancegas turbine generator set operation and maintenance
gas turbine generator set operation and maintenance
 
Cruise control simulation using matlab
Cruise control simulation using matlabCruise control simulation using matlab
Cruise control simulation using matlab
 
GenSync - User Guide
GenSync - User GuideGenSync - User Guide
GenSync - User Guide
 
LOAD FREQUENCY CONTROL USING ELECTRIC VEICHLE SYSTEM IN INTERCONNECTED POWER ...
LOAD FREQUENCY CONTROL USING ELECTRIC VEICHLE SYSTEM IN INTERCONNECTED POWER ...LOAD FREQUENCY CONTROL USING ELECTRIC VEICHLE SYSTEM IN INTERCONNECTED POWER ...
LOAD FREQUENCY CONTROL USING ELECTRIC VEICHLE SYSTEM IN INTERCONNECTED POWER ...
 
SPEED GOVERNOR SYSYTEM AND ITS DERIVATIONS
SPEED GOVERNOR SYSYTEM AND ITS DERIVATIONSSPEED GOVERNOR SYSYTEM AND ITS DERIVATIONS
SPEED GOVERNOR SYSYTEM AND ITS DERIVATIONS
 
PPT V-F control.ppt
PPT V-F control.pptPPT V-F control.ppt
PPT V-F control.ppt
 
SIPAT 660 MW Turbo- Governing & Protection System.ppt
SIPAT 660 MW Turbo- Governing & Protection System.pptSIPAT 660 MW Turbo- Governing & Protection System.ppt
SIPAT 660 MW Turbo- Governing & Protection System.ppt
 
FEEDER SINGH 2.ppt
FEEDER SINGH 2.pptFEEDER SINGH 2.ppt
FEEDER SINGH 2.ppt
 
Frequency Control & AGC.ppt
Frequency Control & AGC.pptFrequency Control & AGC.ppt
Frequency Control & AGC.ppt
 
Inverter Control.ppsx
Inverter Control.ppsxInverter Control.ppsx
Inverter Control.ppsx
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and Development
 
PID Compensator Control Scheme of Synchronous Buck DC-DC Converter with ZVS L...
PID Compensator Control Scheme of Synchronous Buck DC-DC Converter with ZVS L...PID Compensator Control Scheme of Synchronous Buck DC-DC Converter with ZVS L...
PID Compensator Control Scheme of Synchronous Buck DC-DC Converter with ZVS L...
 
Averaging - 1.docx
Averaging - 1.docxAveraging - 1.docx
Averaging - 1.docx
 
Floating mode controller
Floating mode controllerFloating mode controller
Floating mode controller
 
Hamza Kazmi (GTE)
Hamza Kazmi (GTE)Hamza Kazmi (GTE)
Hamza Kazmi (GTE)
 

More from Ashvani Shukla

Adc.pptx ashvani 151503
Adc.pptx ashvani 151503Adc.pptx ashvani 151503
Adc.pptx ashvani 151503Ashvani Shukla
 
Pin photodiode.pptx ashvani
Pin photodiode.pptx ashvaniPin photodiode.pptx ashvani
Pin photodiode.pptx ashvaniAshvani Shukla
 
Pressure measuring devices
Pressure measuring devicesPressure measuring devices
Pressure measuring devicesAshvani Shukla
 
Urea manufacturing process
Urea manufacturing processUrea manufacturing process
Urea manufacturing processAshvani Shukla
 
Amonia manufacturing process
Amonia manufacturing process Amonia manufacturing process
Amonia manufacturing process Ashvani Shukla
 
Paper production process
Paper production processPaper production process
Paper production processAshvani Shukla
 
Steel manufacturing process
Steel manufacturing processSteel manufacturing process
Steel manufacturing processAshvani Shukla
 
Cement manufacturing process new
Cement manufacturing process newCement manufacturing process new
Cement manufacturing process newAshvani Shukla
 
Pulverized coal fired boiler startup procedure
Pulverized coal fired boiler startup procedurePulverized coal fired boiler startup procedure
Pulverized coal fired boiler startup procedureAshvani Shukla
 
Devices not in abb device library
Devices not in abb device library Devices not in abb device library
Devices not in abb device library Ashvani Shukla
 
Foundation fieldbus library
Foundation fieldbus library Foundation fieldbus library
Foundation fieldbus library Ashvani Shukla
 
Function blocks and scheduling
Function blocks and scheduling Function blocks and scheduling
Function blocks and scheduling Ashvani Shukla
 
Hse subnet configuration
Hse subnet configuration Hse subnet configuration
Hse subnet configuration Ashvani Shukla
 

More from Ashvani Shukla (20)

Adc.pptx ashvani 151503
Adc.pptx ashvani 151503Adc.pptx ashvani 151503
Adc.pptx ashvani 151503
 
Pin photodiode.pptx ashvani
Pin photodiode.pptx ashvaniPin photodiode.pptx ashvani
Pin photodiode.pptx ashvani
 
Mechanical coupling
Mechanical couplingMechanical coupling
Mechanical coupling
 
Pressure measuring devices
Pressure measuring devicesPressure measuring devices
Pressure measuring devices
 
Urea manufacturing process
Urea manufacturing processUrea manufacturing process
Urea manufacturing process
 
Amonia manufacturing process
Amonia manufacturing process Amonia manufacturing process
Amonia manufacturing process
 
Control valve
Control valveControl valve
Control valve
 
Paper production process
Paper production processPaper production process
Paper production process
 
Steel manufacturing process
Steel manufacturing processSteel manufacturing process
Steel manufacturing process
 
Cement manufacturing process new
Cement manufacturing process newCement manufacturing process new
Cement manufacturing process new
 
Pulverized coal fired boiler startup procedure
Pulverized coal fired boiler startup procedurePulverized coal fired boiler startup procedure
Pulverized coal fired boiler startup procedure
 
Nuclear reactor
Nuclear reactorNuclear reactor
Nuclear reactor
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
Flow measurement
Flow measurementFlow measurement
Flow measurement
 
Orifice plate
Orifice plateOrifice plate
Orifice plate
 
Devices not in abb device library
Devices not in abb device library Devices not in abb device library
Devices not in abb device library
 
Ff fundamentals
Ff fundamentalsFf fundamentals
Ff fundamentals
 
Foundation fieldbus library
Foundation fieldbus library Foundation fieldbus library
Foundation fieldbus library
 
Function blocks and scheduling
Function blocks and scheduling Function blocks and scheduling
Function blocks and scheduling
 
Hse subnet configuration
Hse subnet configuration Hse subnet configuration
Hse subnet configuration
 

Recently uploaded

VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAbhinavSharma374939
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxhumanexperienceaaa
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 

Recently uploaded (20)

VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog Converter
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 

Electrohydraulic governing system

  • 1. PRESENTATION ON ELECTRO HYDRAULIC CONTROL SYSTEM  By  Ashvani Shukla  C&I  Reliance
  • 2. EHTC = ELECTRO-HYDRAULIC TURBINE CONTROLLER IT IS THE GOVERNOR FOR TURBINE. SYSTEM SUPPLIED BY BHEL-EDN, BANGALORE. IMPLEMENTED IN THE METSO DNA DCS. CONTROLLERS IN EHTC • SPEED CONTROLLER – (MODES: PI, PD) • ISOCHRONOUS FREQUENCY CONTROLLER • LOAD CONTROLLER • EXTRACTION-1 (IP EXTRACTION) CONTROLLER • EXTRACTION-2 (LP EXTRACTION) CONTROLLER EHTC
  • 3. R A T I O S E T T E R M A X M I N SPEED CONTROLLER PI/PD MODE LOAD / ISO FREQ CONTROLLER SPEED REF LOAD REF LOAD ACTUAL SPEED ACTUAL SPEED/LOAD LIMITERLIMIT REF EXTRACTION-1 PRESSURE CONTROLLER PRESSURE REF PRESSURE ACTUAL M I N EXTRACTION-1 PRESSURE LIMITER LIMIT REF EXTRACTION-2 PRESSURE CONTROLLER PRESSURE REF PRESSURE ACTUAL M I N EXTRACTION-2 PRESSURE LIMITER LIMIT REF VALVE CHARACTERISTIC COMPENSATOR HPCV LIFT REFERENCE IPCV LIFT REFERENCE LPCV LIFT REFERENCE FREQ REF FREQ ACTUAL EHTC BLOCK DIAGRAM
  • 4. EHTC FUNCTIONS ROLLING WARM UP CRITICAL SPEED AVOIDANCE LOAD / SPEED CONTROL EXTRACTION PRESSURE CONTROL ISLANDING
  • 5. TURBINE AUXILIARIES ARE STARTED, I.E. LUBE OIL SYS, CONDENSATE EXTRACTION SYS, ETC. TURBINE PROTECTION IS RESET FROM ABB DCS AFTER FULFILLING THE CRITERIA THE EMERGENCY SHUTOFF VALVE (ESV) IS OPENED DEPENDING ON THE SHUTDOWN DURATION, THE TYPE OF TURBINE STARTS ARE AS FOLLOWS: 1. COLD START: AFTER 250 HOURS 2. WARM START: AFTER 40 HOURS 3. HOT START: AFTER 16 HOURS WARM UP / SOAK TIME IS REQUIRED AS ROTOR EXPANDS FASTER THAN CASING DUE TO MASS DIFFERENCE. WARM UP ENSURES THAT BOTH EXPAND PARALLELY AND CLEARANCES ARE MAINTAINED & RUBBING OF PARTS IS AVOIDED. TG SET IS THEN ROLLED USING THE SPEED CONTROL-PI MODE. THE SPEED REFERENCE IS SELECTED AS PER THE START-UP CURVES GIVEN IN THE FOLLOWING IMAGE I.E. 500 RPM / 3000 RPM / 5000 RPM. ROLLING, WARM UP
  • 6.
  • 7. CRITICAL SPEED AVOIDANCE THE EHTC SPEED CONTROL RAISES THE SPEED AT FASTER RATE IN THE CRITICAL SPEED BANDS TO MINIMIZE THE TIME OF OPERATION IN THIS ZONE. AFTER WARM UP THE SPEED REFERENCE IS SET TO RATED VALUE FOR SYNCHRONIZATION CRITICAL SPEED BANDS 1300 TO 1700 RPM 2000 TO 2500 RPM
  • 8. TG SET RUN AT RATED SPEED I.E. 5000 RPM AVR VOLT CONTROL SWITCHED ON & GEN STATOR VOLT BUILT UP THRO’ AVR TG FREQ IS VARIED BY CHANGING SPEED REF THE FREQ, VOLT & PHASE ANGLE OF TG ARE MATCHED TO GRID BEFORE CLOSING GCB GCB IS CLOSED. THIS SYNCHRONIZES THE TG SET WITH THE GRID AS GCB CLOSES, THE EHTC MODE SWITCHES TO SPEED CONTROL-PD SPEED CONTROLLER O/P INCREASES BY ABOUT 10% SO AS TO LOAD THE TG TO BLOCK LOAD OF AROUND 1-2MW SO THAT GCB DOES NOT TRIP ON LOW FORWARD POWER. AVR MODE IS MANUALLY CHANGED FROM VOLT CONTROL TO PF CONTROL SYNCHRONIZATION AFTER ROLLING SPEED CONTROLLER PI -> PD MODE SPEED REF 5000 -> 5083 SPEED ACTUAL 5000 RPM 15% -> 25%
  • 9. SPEED CONTROLLER AFTER SYNCHRONIZATION, LOAD CONTROLLER IS SWITCHED ON EHTC SETS THE LOAD REF TO THE RUNNING LOAD AND ITS OUTPUT IS SET TO THE VALUE OF SPEED CONTROLLER OUTPUT BY TRACKING I-ACTION PD MODE OUTPUT =%ERROR * GAIN =0.16667*18=3.0 3.0% SPEED REF (SV) 5010 SPEED ACTUAL (PV) 5000 %ERROR =((SV-PV)/RANGE)*100 ((5010-5000)/6000)*100 =0.16667% LOAD CONTROL SPEED CONTROLLER PD MODE LOAD CONTROLLER PID P=0, D=0, as SV=PV I-action tracks 25% SPEED REF 5083 LOAD REF 2 MW LOAD ACTUAL 2 MW SPEED ACTUAL 5000 RPM 25% 25% SPEED CONTROL-PD SWITCHES TO SPEED TRACKING MODE I.E. THE SPEED REF TRACKS THE ACTUAL SPEED + 10 RPM TO SET SPEED CONTROLLER OUTPUT AT 3.0% FIXED. (THE GAIN IS PRESSURE COMPENSATED AND INCREASES FROM 17 TO 22 AS MS PRESSURE REDUCES FROM 110 TO 90 ATA.)
  • 10. NORMALLY TG SETS ARE IN LOAD CONTROL MODE WHEN SYNCHRONIZED WITH GRID. IF THE TIE OPENS THEN TG SET(S) ARE ISLANDED, LOAD CONTROLLER SWITCHES OFF & SPEED CONTROL-PD MODE TAKES OVER BUMPLESSLY. DURING THIS SWITCH OVER, THE SPEED REF IS CALCULATED SUCH THAT THE OUTPUT OF LOAD CONTROLLER (2S DELAYED) IS AVAILABLE AT SPEED CONTROLLER OUTPUT IN PD MODE. AFTER THIS THE LOAD CONTROLLER SWITCHES OFF & TG SET RUNS IN SPEED CONTROL-PD MODE. ISLANDING SPEED CONTROLLER PD MODE LOAD CONTROLLER PID P=0, D=0, as SV=PV I-action tracks 25% SPEED REF 5010 -> 5167 LOAD REF 20 -> 0 LOAD ACTUAL 20 MW SPEED ACTUAL 5000 RPM 3% -> 50% 50% -> 0%
  • 11. DROOP DROOP CONTROL IS REQUIRED IN SYSTEMS WHERE A COMMON PARAMETER IS CONTROLLED BY 2 OR MORE SYSTEMS. E.G. FREQ OR VOLT CONTROL IN CASE OF 2 OR MORE SYNCHRONIZED TG SETS. COMMON HEADER PRESSURE CONTROL IN CASE OF 2 OR MORE BOILERS. IF A COMMON PARAMETER IS SENSED BY TWO OR MORE SENSORS, THE READINGS CANNOT MATCH EXACTLY. THERE WILL ALWASYS BE SOME DIFFERENCE EVEN THOUGH IT MAY BE VERY SMALL. IF BOTH SENSORS PROVIDE PV TO TWO DIFFEENT PID CONTROLLERS THEN THEY WILL TEND TO SATURATE IN OPPOSITE DIRECTIONS. E.G. CONSIDER A CASE OF TWO TG SETS “L” & “H” RUNNING IN SYNCHRONIZED CONDITION. LET BOTH TG GOVERNORS BE SET TO ISOCHRONOUS FREQ CONTROL I.E. SPEED PID CONTROL. LET REF OF BOTH TG BE SET AT 50.00HZ. LET THE ACTUAL SYSTEM BUS FREQ BE 50.00HZ, AND ONE SENSOR SENSES L=49.99 & OTHER H=50.01. THE INTEGRAL ACTION OF L WILL INCREASE OUTPUT AND H WILL DECREASE OUTPUT TO BRING FREQ TO 50.00. THIS PROCESS WILL CONTINUE AS THERE WILL ALWAYS BE OFFSET IN THE READINGS OF L & H, SO GRADUALLY L OUTPUT WILL SATURATE TO 100% AND H OUTPUT WILL SATURATE TO 0%. SO EITHER THE INTEGRAL ACTION IS REMOVED I.E PD ACTION SELECTED OR REF IS CHANGED AS PER CONTROLLER OUTPUT TO INSERT DROOP OR OFFSET IN THE CONTROL ACTION I.E. REF & PV ARE NOT MATCHED.
  • 12. DROOP % DROOP MEANS % CHANGE IN FREQ FOR 100 % CHANGE IN LOAD. 4% DROOP IMPLIES 4% FREQ CHANGE WILL CAUSE 100% CHANGE IN LOAD. i.e. GAIN=100/4=25%
  • 13. DROOP FRE Q Hz LOAD MW320 50.0 2711 51.5 DROOP = % CHANGE IN FREQ FOR 100 % CHANGE IN LOAD = (3/50)*100 = 6% GAIN = 100/DROOP = 16.7 LOAD ON TG IS REDUCED FROM 27MW TO 11MW I.E. 16MW OR 50% LOAD THROW SO GOVERNOR OUPUT SHOULD REDUCE by 50% I.E. FROM 81.4% TO 34.4% FOR STABLE FREQ (IN TG SPEED CONTROL THE GOV VLV OPENING SHOULD EXACTLY MATCH THE LOAD ELSE SPEED WILL KEEP ON RAMPING. THIS IS KNOWN AS INTEGRATING TYPE OF PROCESS.) THE 34.4% O/P IS REQUIRED AT 11MW LOAD TO KEEP FREQ STABLE. BUT 34.4% O/P IS AVAILABLE AT 51.5HZ FREQ. THIS OFFSET IS RESET BY MANUALLY DECREASING THE SPEED REF (SV) SO THAT 34.4% O/P IS 1.5 Hz = 3% 27-11 = 16MW =50% 10 0 0 84. 4 34.4 GOV O/P % 84.4% SPEED CONTROLLER PD MODE OUTPUT =%ERROR * GAIN %ERROR =((SV- PV)/RANGE)*100 O/P % SPEED CONTROLLER =5.05*16.7=84.4 ((5253- 5000)/5000)*100 =5.05% 34.4% SPEED CONTROLLER =2.06*16.7=34.4 ((5253- 5150)/5000)*100 =2.06% SPEED REF SV SPEED ACTUAL PV 5253 5000 5253 5150 34.4% SPEED CONTROLLER =2.06*16.7=34.4 ((5103- 5000)/5000)*100 =2.06% 5103 5000
  • 14. DROOP
  • 15. ISOCHRONOUS FREQ CONTROL CONSIDER FOLL SEQUENCE OF EVENTS: THREE TG SETS LOADED AT 27MW EACH, GRID AT 15MW I.E. TOTAL LOAD 96MW CHEMICAL DIV. TRIPS (70MW LOAD THROW), BALANCE LOAD IS 96MW-70MW=26MW GRID TRIPS (15MW) ON REV POWER THE 3 TG SETS ARE ISLANDED IN DROOP MODE (DROOP=6%), CONNECTED LOAD = 26MW, I.E. 8.67MW PER TG SO, FOR EACH TG SET % LOAD REDUCTION = [(27 - 8.67)/32]*100 = 57.28% THE GOV O/P CHANGE = (%FREQ ERROR)*(GAIN) So, % FREQ ERROR = 57.28/16.7 = 3.43% I.E. 3.43/2 = 1.7HZ SO FINAL FREQ WILL STABILIZE AT 51.7HZ, WHICH WILL TRIP ALL TG SETS ON OVERFREQ IF ONE TG IS IN ISOCHRONOUS FREQ CONTROL IN ISLAND MODE, THEN THIS TG SET WILL TRIP AFTER FULLY UNLOADING & ONLY 2 TG SETS WITH DROOP WILL RUN I.E. 13MW PER TG SET SO, FOR EACH TG SET % LOAD REDUCTION = [(27 - 13)/32]*100 = 57.28% THE GOV O/P CHANGE = (%FREQ ERROR)*(GAIN) So, % FREQ ERROR = 57.28/16.7 = 3.43% I.E. 3.43/2 = 1.7HZ
  • 16. ISO FREQ CONTROL MODE IS PRESELECTED WHILE TG RUNNING IN LOAD CONTROL MODE, SO THAT DURING ISLANDING, THE ISO FREQ CONTROL MODE WILL BECOME ACTIVE. AT PRESENT, ONE TG IS SELECTED FOR ISO & OTHER TWO FOR SPEED CONTROL-PD MODE (DROOP). SO ON ISLANDING, THE THREE TG SETS ARE ISLANDED WITH ONE IN ISO MODE & OTHER TWO IN DROOP MODE. IF DURING OR AFTER ISLANDING LOAD IS ADDED OR REMOVED, THEN SYSTEM FREQ WILL CHANGE, BUT THE TURBINE ON FREQ CONTROL MODE WILL KEEP ON CHANGING OUPUT TILL THE SYSTEM FREQ RETURNS TO 50HZ. THUS SYSTEM FREQ IS MAINTAINED. TWO OR MORE TG SETS IN A SYNCHRONIZED SYSTEM CANNOT BE PUT IN ISOCHRONOUS MODE AT THE SAME TIME, AS ONE TG SET WILL LOAD FULLY & OTHER WILL FULLY UNLOAD DEPENDING ON MINOR DIFFERENCES IN SPEED/FREQ SENSORS OF THE TWO TG SETS. THEREBY DROOP MODE IS REQUIRED. ISOCHRONOUS FREQ CONTROL
  • 17. LOAD CONTROLLER PID LOAD REF 25MW LOAD ACTUAL 20MW ISOCHRONOUS FREQ CONTROLLER PIDFREQ REF 50HZ FREQ ACTUAL 50HZ ISOCHRONOUS FREQ CONTROL LOAD CONTROL TG SYNCHRONIZED WITH GRID ISOCHRONOUS FREQ CONTROL TG ISLANDED LOAD REF 20MW LOAD ACTUAL 20MW FREQ REF 50HZ FREQ ACTUAL 51HZ ISLANDI NG
  • 18. LOAD SHEDDING LOGIC IF TIE/GRID BREAKER TRIPS, & PRO RATA LOAD ON GRID IS NOT SHED THEN THE BALANCE TG SETS MAY TRIP ON UNDER-FREQUENCY. IF A TG SET TRIPS, ITS LOAD SHIFTS TO GRID, & TIE BREAKER TRIPS IF IMPORT EXCEEDS 20MVA (CONTRACT DEMAND LIMITATION). AFTER ISLANDING THE ENTIRE LOAD OF (GRID+TRIPPED TG) SHIFTS TO BALANCE TG SETS WHICH RESULTS IN UNDER-FREQ TRIPPING OF BALANCE TG SETS & BLACKOUT. SO, PROPORTIONATE LOAD IS TO BE SHED TO PREVENT BALANCE TG SETS FROM TRIPPING ON UNDER-FREQUENCY. THE RECTIFORMER NOS. 1,2,3,4 ARE SHED FROM DCS AS PART OF LOAD SHEDDING LOGIC. THE PROPORTIONAL LOAD IS SHED WITHIN 400MS THROUGH DCS.
  • 19. G1 25MW G2 25MW G3 25MW GRID 15MW CD 60MWVSF 25MW CPP 5MW TOTAL LOAD=90MW G1 25MW G2 25MW G3 25MW GRID 45MW VSF 25MW CPP 5MW TOTAL LOAD=30MW EXPORT=45MW TG GEN=75MW TG GEN=75MW IMPORT=15MW G1 25MW G2 25MW GRID 40MW CD 60MWVSF 25MW CPP 5MW TOTAL LOAD=90MW TG GEN=50MWIMPORT=40MW CASE1: TG TRIP CASE2: LOAD THROW
  • 21. Exhaust flow HP CV OPN HP CV CLS EXT CV OPN EXT CV CLS RATIO SETTER
  • 22. TO CALCULATE THE TURBINE INTERNAL PRESSURE RATIOS AND LIMITS,THE INTERSECTION POINTS NEEDED ARE A,B,C A: MAX POWER @ MIN EXTRACTION B: MIN POWER @ MAX EXTRACTION C: MIN HP FLOW @ MIN EXTRACTION THE TURBINE SPEED/LOAD & EXTRACTION PRESSURE NEED TO BE MAINTAINED AT CONSTANT LEVELS SIMULTANEOUSLY. CHANGING THE POSITION OF EITHER THE HP, IP OR LP VALVE AFFECTS BOTH TURBINE SPEED/LOAD AND EXTRACTION PRESSURE. SO, TO CHANGE SPEED/LOAD ALL VALVES NEED TO BE ADJUSTED SO THAT ONLY THE SPEED/LOAD IS AFFECTED WITH MIN. OR NO DISTURBANCE TO THE EXTRACTION PRESSURES. SIMILARLY WHILE CHANGING IP EXTRACTION PRESSURE THE SPEED/LOAD OR THE LP EXTRACTION SHOULD NOT BE DISTURBED. RATIO SETTER CALCULATES THE OUTPUTS TO MINIMIZE THE CONTROLLED PARAMETERS INTERACTIONS EFFECTING EACH OTHER, AND TO KEEP THE ACTUATOR OUTPUTS WITHIN THE BOUNDARIES OF TURBINE STEAM MAP OR ENVELOPE CURVE. RATIO SETTER
  • 23.
  • 24.
  • 25. S.N. EXTR-1 CONTROL O/P (YE1) EXTR-2 CONTROL O/P (YE2) SPEED CONTROL GAIN RATIO SETTER GAIN FOR SPEED/LOAD CONTROL O/P (YN) EFFECTIVE GAIN 1 0 0 8 1.2 9.6 2 1 1 8 7.5 60 THE RATIO SETTER DETAILS WERE OBTAINED FROM BHEL-HYD & FOUND THAT GAIN WAS THROUGHOUT LINEAR FOR ALL THREE CONTROLLER OUTPUTS I.E. YN, YE1 & YE2. FOR, YN (LOAD/SPEED CONTROLLER O/P) THE GAIN WAS THROUGHOUT LINEAR AT 0.632. THE SNAPSHOTS WERE SENT TO BHEL-HYD FOR CONFIRMATION AND FOUND THAT WRONG RATIO SETTER WAS INSTALLED IN ALL THREE TG SET CONTROLLERS BY BHEL-EDN. RATIO SETTER RELATED ISSUES THE ORIGINAL RATIO SETTER IMPLEMENTED BY BHEL-EDN WAS FAULTY WITH NON-LINEAR GAIN AS GIVEN IN THE BELOW TABLE.
  • 26. TURBINE GOVERNING SYSTEM RELATED ISSUES PERTAINING TO ISLAND CONDITION: IN ISLAND CONDITION, SPEED TRANSIENT OVERSHOOT, SPEED HUNTING & STABILITY ISSUES WERE PERSISTING. FOLLOWING MAJOR CHANGES WERE IMPLEMENTED: 1) THE RATIO SETTER GAIN FOR HPCV OUTPUT WAS FOUND TO BE VARYING FROM “9” TO “59” DEPENDING ON THE EXTRACTION CONTROLLER OUTPUTS. RATIO SETTER FROM BHEL-HYD WITH FIXED GAIN & LINEAR CHARACTERISTIC WAS IMPLEMENTED. TRANSFER FUNCTION WAS OBTAINED FROM BHEL-HYD & THE SPEED CONTROLLER P-GAIN VALUE CHANGED FROM “8” TO “18”. 2) DURING ISLANDING THE HP & IP EXTRACTION CONTROLLERS SWITCH OVER TO MANUAL MODE TO PREVENT EXTRACTION LOOP INTERACTIONS FROM DISTURBING THE SPEED CONTROLLER & REDUCE THE TRANSIENT SETTLING TIME. AFTER STEADY STATE ACHIEVED, OPERATOR CAN SWITCH THE CONTROLLERS TO AUTO. 3) IN MAIN DCS, LOAD SHEDDING SCHEME IMPLEMENTED BY SHEDDING THE PRIORITY BASED PRO-RATA LOADS OF THE RECTIFORMER NOS. 1-4. 4) FREQUENCY CONTROL MODE OR ISOCHRONOUS MODE WAS IMPLEMENTED SO THAT THE SYSTEM FREQUENCY RETURNS TO 50 HZ AT STEADY STATE AFTER A DISTURBANCE IN ISLANDING CONDITION.
  • 27. K = SYSTEM GAIN = 100/(% STEADY STATE SPEED REGULATION) = 100/5 = 20 T1 = GOVERNOR TIME CONSTANT = 0.02-0.1S T2 = DERIVATIVE GAIN X GOVERNOR TIME CONST = 0.1S T3 = CONTROL VALVE ACTUATOR TIME CONST = 0.1S PUP = CV OPEN = 1 PU PER S PDOWN = CV CLOSE = 2.5 PU PER S PMIN = MIN POWER LIMIT PMAX = MAX POWER LIMIT PGV = POWER AT VALVE OUTLET S = COMPLEX FREQ VARIABLE (LAPLACE TRANSFORM)
  • 28. FHP = HP TURBINE POWER FRACTION = 0.505 FIP = IP TURBINE POWER FRACTION = 0.256 FLP = LP TURBINE POWER FRACTION = 0.239 THP = HP TURBINE TIME CONST = 0.115S TIP = IP TURBINE TIME CONST = 0.122S TLP = LP TURBINE TIME CONST = 0.125S DW = SPEED DEVIATION PM = MECH POWER P0 = INITIAL POWER PGV = POWER AT VALVE OUTLET
  • 29.
  • 30.
  • 31. BEFORE SYNCHRONIZING AN INCOMING UNIT TO A RUNNING SYSTEM, THE FOLLOWING PARAMETERS SHOULD BE MATCHED CLOSELY SO TO MINIMIZE TRANSFER OF ENERGY •VOLTAGE •FREQUENCY •PHASE ANGLE •PHASE SEQUENCE THE CIRCUIT BREAKER IS CLOSED TO TIE THE “INCOMING” SYSTEM TO THE “RUNNING” SYSTEM ELECTRICALLY
  • 32. GENERAT OR DC CURRENT IS FED TO FIELD WINDING IN ROTOR TO CREATE MAGNETIC FIELD THIS ROTATING MAGNETIC FIELD INDUCES VOLTAGE IN THE STATOR ARMATURE WINDING THE DC CURRENT TO THE ROTOR FIELD WINDING IS CALLED FIELD CURRENT.
  • 33. RPM=120*(f/P) f = frequency (Hz) P = total number of poles
  • 34. G1 100 MW 100 MW LOAD SIDE PF=COSΦ=0.8 ACTIVE POWER=VI.COSΦ=100MW TOTAL POWER=VI=125MVA SO REACTIVE POWER = 25MVAr BOTH ACTIVE PWR 100MW & REACTIVE PWR 25MVAr SUPPLIED BY G1 . AVR MODE = VOLT CONTROL G1 50 MW 100 MW G1 ACTIVE PWR CONTROL BY STEAM FLOW CONTROL G1 REACTIVE PWR CONTROL BY EXCITATION CONTROL AVR MODE = PF CONTROL OR REACTIVE PWR CONTROL G1 OVEREXCITED => PF LEADING => REACTIVE PWR OUT . G1 UNDEREXCITED => PF LAGGING => REACTIVE GRID 50MW PF=0.8 25MVAr PF=0. 8 PF=0. 8 PF=0.9 5.5MVAr PF=0.72 19.5MVAr
  • 36. REGION A-B: LAGGING POWER FACTOR •GENERATOR IS OVER-EXCITED I.E. MORE FIELD CURRENT •CAPABILITY LIMITATION IS FIELD OVERHEATING • REGION B-C: RATED POWER FACTOR •CAPABILITY LIMITATION IS DEPENDENT ON THE STATOR CURRENT •MAXIMUM GENERATOR NAMEPLATE STATOR AMPERES SHOULD NOT BE EXCEEDED REGION C-D: LEADING POWER FACTOR •CAPABILITY LIMITATION DUE TO EXCESSIVE HEATING IN THE STATOR IRON CORE DUE TO FLUX LEAKAGE •THIS IS ALSO AN UNDEREXCITATION REGION & CAPABILITY IS FURTHER REDUCED BY THE VOLTAGE SQUARED DURING REDUCED TERMINAL VOLTAGE OPERATION
  • 37. LOAD ANGLE AT ZERO LOAD, FIELD POLE OF ROTOR IS “IN PHASE” WITH STATOR FIELD, SO POWER ANGLE IS 0 AS LOAD ADDED , ROTOR ADVANCES WITH RESPECT TO THE STATOR, THE LOAD ANGLE INCREASES. LOAD ANGLE ALSO INCREASES WITH UNDEREXCITATION AND MAY RESULT IN ROTOR GETTING OUT OF SYNCHRONISM WITH NETWORK FREQ IF ROTOR STABILITY LIMIT IS TRANSGRESSED