SlideShare a Scribd company logo
First Use Of
Geosynthetic Reinforced Soil –
Integrated Bridge System
in Illinois
Keith Sargent, P.E.
Associate
Thomas Engineering Group
Dr. Riyad Wahab, P.E.
State Geotechnical Engineer
IL Dept. of Transportation
What is GRS-IBS?
• Alternating layers of compacted granular fill
material and sheets of geotextile reinforcement.
• Face of GRS-IBS wall is CMU or modular blocks.
• Wall is constructed on top of a “Reinforced Soil
Foundation” (RSF).
• FHWA promotes the use of GRS-IBS through their
“Every Day Counts” and “Accelerated Bridge
Construction” programs.
Typical GRS Section
Construction Sequence: Step One
• Lay a row of facing blocks.
Construction Sequence: Step Two
• Add a layer of compacted fill.
Construction Sequence: Step Three
• Add a layer of geosynthetic fabric
What are the benefits?
• GRS uses common, readily available materials and
equipment.
• Cost can be up to 25 to 60 percent less than
bridges built with traditional methods.
• Easy to maintain due to fewer construction items.
• Reduces construction time.
• Eliminates deep foundations and approach slabs.
Approximate GRS-IBS Costs
• FHWA estimates GRS-IBS using CMU facing to be
approximately $33/SF.
• If a wet-cast modular block is used, the estimated
cost increase is approximately $28/SF ($61/SF).
• Costs for approach slabs and deep foundations
eliminated.
• Comparison: MSE wall costs approximately
$55/SF.
GRS-IBS Use in Illinois
FHWA contacted IDOT to search for projects, and
in turn IDOT contacted Districts and Local
agencies looking for suitable projects:
• Competent soils resistant to scour
• Waterways with 100-yr velocities of 3 ft/sec max
• Non-staged construction
• Low Average Daily Traffic volumes
• Single Span superstructure - range (25 ft - 80 ft)
• Skew 15° or less
• Abutment wall heights not exceeding 30 ft
GRS-IBS Use in Illinois
• The Village of Lombard showed interest in using
the GRS-IBS technology for their Great Western
Trail project.
• Original plan was to use MSE wall retaining pile
supported abutments
• Bollinger, Lach and Associates worked with FHWA
and the Village to incorporate GRS-IBS technology
into Contract Drawings.
Project Location
MSE Configuration to be Replaced
• 48” deep precast prestressed concrete I beams spanning 92’-6”.
•Integral abutments supported by 8 H-piles 80’ long.
• 30 ft approach pavement spanning to 10’ wide spread footing.
• MSE retaining walls used to shorten span and retain embankment.
• Although bridge is for pedestrian use, it is designed for H-20 loading
MSE Configuration to be Replaced
GRS-IBS Design
• FHWA has assembled guidelines for design of
GRS-IBS.
• Guidelines provide example plan sheets and
details along with approximate quantities.
• Detailed construction specifications are also
provided within the guidelines.
• Guidelines account for “favorable” and “poor” soil
conditions.
Normal Use is with Concrete Deck Beams
Revised Elevation with GRS-IBS
• Increased Span Length by 6 ft to accommodate blocks and footing.
• Deleted 30 ft by 15 in. thick approach pavement and 10 ft footings.
• Deleted piles, added 6 ft wide spread footings.
• Kept Aggregate column ground improvement.
.
Revised Section with GRS-IBS
• C.I.P. Footing.
• Reinforced Soil
Foundation (RSF) on
Aggregate Columns.
• Used Extra GRS
Aggregate Backfill to
transition approach
settlement.
• Approach is 3” HMA.
Current Construction Status
• Project was on September 23, 2011 Letting.
• Aggregate Column Ground Improvements -
completed on May 29th
, 2012.
• Reinforced Soil Foundation and Modular Block
Walls (both east and west sides) - completed on
August 17th
.
• C.I.P. footings - installed August 25th
.
• PPC I-Beams to be erected in October.
• Instrumentation to monitor wall movement
installed at the end of August (paid for by
FHWA).
Aggregate Column Installation
Aggregate Column Installation
Aggregate Column Installation
• Installation of Aggregate Columns went
smoothly.
• Approximately two days of work for each
abutment.
• Approximately 65 columns per abutment.
• Test column provided excellent results.
– Loaded to 150% of design load (48 kips)
– Deflected less than a ½”
• Total Cost: $108,000
RSF Shop Drawings
RSF Installation
• Four Step Process:
– Install geotextile fabric on subgrade leaving excess on
the sides.
– Compact lifts of CA-06 stone.
– Install layers of geogrid reinforcement.
– Wrap foundation with geotextile fabric.
• Installation of RSF is simple, however this
project required foundation steps that
complicated the construction.
RSF Construction
Block Shop Drawings
RECON Blocks
Selected
• 16”tall, 48”wide
24”deep
• Other approved
blocks included Redi
Rock and Stone
Strong
• Wet Cast Block
Required
• To be stained and
anti-graffiti surface
applied
Modular Block Installation
• Block installation took longer than anticipated given
the size of the block (4FT wide x 16” tall x 24”
deep).
• FHWA intent is to use 45 LB CMU blocks, not 1600
LB wet cast blocks.
• Approximately 400 blocks per wall.
• Making certain blocks are level and set into place
is very important.
• Block constructed with no batter, so precision was
crucial.
Modular Block Installation
Setting first row level and in line was very important.
Modular Block Installation
Excavator needed to set block – very time
consuming and difficult to perform precisely.
Geosynthetic Reinforced Soil Installation
• Soil reinforcement was Tenax TT L Type 70
geogrid.
– Delivered in 4 FT wide rolls.
– Difficult to cut and lay flat.
– Stretching tight was important.
• Select Fill was CA-16.
– Required little compaction
– Easy to work with.
Geosynthetic Reinforced Soil Installation
Tenax installed between blocks and halfway up block.
Geosynthetic Reinforced Soil Installation
Final Product
FHWA Monitoring Research
• FHWA hired TEG to perform survey monitoring at
regular intervals over the next two years
• Goal is to monitor horizontal and vertical displacement of
the wall.
Remaining Work
• Installation of PPC I-Beams
• Superstructure with Safety Railing
• Decorative lighting
• Staining/Coloring of Wall
• Anti-Graffiti Coating with UV Protection
Final Thoughts
• The use of GRS-IBS for the Great Western
Trail project in Lombard may not be
representative of a usual GRS-IBS project.
• Modular block used for Great Western Trail
was large and required heavy machinery and
added labor to set in place.
• Modular block used was much more expensive
than a standard CMU.
• Overall cost was higher than MSE wall.
Questions?
Email: keiths@thomas-engineering.com
http://www.fhwa.dot.gov/everydaycounts/technology/grs_ibs/

More Related Content

What's hot

Foundations
FoundationsFoundations
Foundations
Julian Swindell
 
Shallow Foundation
Shallow FoundationShallow Foundation
Shallow Foundation
Md. Shahadat Hossain
 
Stone column
Stone columnStone column
Stone column
GEOMIND
 
Ground improvement techniques
Ground improvement techniquesGround improvement techniques
Ground improvement techniques
Qasim Virk
 
Determining equivalent single wheel load.(ESWL)
Determining equivalent single wheel load.(ESWL) Determining equivalent single wheel load.(ESWL)
Determining equivalent single wheel load.(ESWL)
Imran Nawaz
 
High strength concrete
High strength concrete  High strength concrete
High strength concrete
Pranuthi Konda
 
Pervious concrete
Pervious concretePervious concrete
Pervious concrete
Abhishek Gupta
 
GEOSYNTHETICS
GEOSYNTHETICSGEOSYNTHETICS
GEOSYNTHETICS
Amjad Ansari
 
07 101+ ground improvement techniques
07 101+ ground improvement techniques07 101+ ground improvement techniques
07 101+ ground improvement techniques
AHMED NADIM JILANI
 
Pile Foundation presentation
Pile Foundation presentationPile Foundation presentation
Pile Foundation presentation
Sevar Dilkhaz
 
Transparent concrete ppt
Transparent concrete pptTransparent concrete ppt
Transparent concrete ppt
mukul srivastava
 
Pre stressed concrete
Pre stressed concretePre stressed concrete
Pre stressed concrete
froskhan08
 
High strength concrete
High strength concreteHigh strength concrete
High strength concrete
Dr K M SONI
 
MECHANICALLY STABILIZED EARTH WALLS AND REINFORCED SOIL SLOPES (1).pptx
MECHANICALLY STABILIZED EARTH WALLS AND REINFORCED SOIL SLOPES (1).pptxMECHANICALLY STABILIZED EARTH WALLS AND REINFORCED SOIL SLOPES (1).pptx
MECHANICALLY STABILIZED EARTH WALLS AND REINFORCED SOIL SLOPES (1).pptx
ShahidAmeen10
 
Principles and design concepts of reinforced soil walls
Principles and design concepts of reinforced soil wallsPrinciples and design concepts of reinforced soil walls
Principles and design concepts of reinforced soil walls
Prakash Ravindran
 
Self compacting concrete (scc)
Self compacting concrete (scc)Self compacting concrete (scc)
Self compacting concrete (scc)
y Sahaja
 
Re wall12
Re wall12Re wall12
Design of simple beam using staad pro
Design of simple beam using staad proDesign of simple beam using staad pro
Design of simple beam using staad pro
SHAMJITH KM
 
Pt slabs
Pt slabsPt slabs
Pt slabs
ajay nagaraj
 
GEOGRIDS IN CONCRETE
GEOGRIDS IN CONCRETEGEOGRIDS IN CONCRETE
GEOGRIDS IN CONCRETE
Chandra Vardhan
 

What's hot (20)

Foundations
FoundationsFoundations
Foundations
 
Shallow Foundation
Shallow FoundationShallow Foundation
Shallow Foundation
 
Stone column
Stone columnStone column
Stone column
 
Ground improvement techniques
Ground improvement techniquesGround improvement techniques
Ground improvement techniques
 
Determining equivalent single wheel load.(ESWL)
Determining equivalent single wheel load.(ESWL) Determining equivalent single wheel load.(ESWL)
Determining equivalent single wheel load.(ESWL)
 
High strength concrete
High strength concrete  High strength concrete
High strength concrete
 
Pervious concrete
Pervious concretePervious concrete
Pervious concrete
 
GEOSYNTHETICS
GEOSYNTHETICSGEOSYNTHETICS
GEOSYNTHETICS
 
07 101+ ground improvement techniques
07 101+ ground improvement techniques07 101+ ground improvement techniques
07 101+ ground improvement techniques
 
Pile Foundation presentation
Pile Foundation presentationPile Foundation presentation
Pile Foundation presentation
 
Transparent concrete ppt
Transparent concrete pptTransparent concrete ppt
Transparent concrete ppt
 
Pre stressed concrete
Pre stressed concretePre stressed concrete
Pre stressed concrete
 
High strength concrete
High strength concreteHigh strength concrete
High strength concrete
 
MECHANICALLY STABILIZED EARTH WALLS AND REINFORCED SOIL SLOPES (1).pptx
MECHANICALLY STABILIZED EARTH WALLS AND REINFORCED SOIL SLOPES (1).pptxMECHANICALLY STABILIZED EARTH WALLS AND REINFORCED SOIL SLOPES (1).pptx
MECHANICALLY STABILIZED EARTH WALLS AND REINFORCED SOIL SLOPES (1).pptx
 
Principles and design concepts of reinforced soil walls
Principles and design concepts of reinforced soil wallsPrinciples and design concepts of reinforced soil walls
Principles and design concepts of reinforced soil walls
 
Self compacting concrete (scc)
Self compacting concrete (scc)Self compacting concrete (scc)
Self compacting concrete (scc)
 
Re wall12
Re wall12Re wall12
Re wall12
 
Design of simple beam using staad pro
Design of simple beam using staad proDesign of simple beam using staad pro
Design of simple beam using staad pro
 
Pt slabs
Pt slabsPt slabs
Pt slabs
 
GEOGRIDS IN CONCRETE
GEOGRIDS IN CONCRETEGEOGRIDS IN CONCRETE
GEOGRIDS IN CONCRETE
 

Viewers also liked

Geosynthetics
GeosyntheticsGeosynthetics
Geosynthetics
Padarabinda Parida
 
Applications of Micro Geo Data for Urban Monitoring
Applications of Micro Geo Data  for Urban Monitoring Applications of Micro Geo Data  for Urban Monitoring
Applications of Micro Geo Data for Urban Monitoring
Yuki Akiyama
 
Separation & reinforcement temp. roads
Separation & reinforcement temp. roadsSeparation & reinforcement temp. roads
Separation & reinforcement temp. roads
Geotextiles EastAfrica
 
Narrow Pavement Widening - Geosynthetic Reinforcement
Narrow Pavement Widening - Geosynthetic ReinforcementNarrow Pavement Widening - Geosynthetic Reinforcement
Narrow Pavement Widening - Geosynthetic Reinforcement
Center for Transportation Research - UT Austin
 
087 active crack control of continuously reinforced concrete pavements throug...
087 active crack control of continuously reinforced concrete pavements throug...087 active crack control of continuously reinforced concrete pavements throug...
087 active crack control of continuously reinforced concrete pavements throug...
CROW
 
Earth Retention Solutions
Earth Retention SolutionsEarth Retention Solutions
Earth Retention Solutions
Communications Branding
 
GEO Gridの過去・現在・未来 @FOSS4G 2011 Tokyo
GEO Gridの過去・現在・未来 @FOSS4G 2011 TokyoGEO Gridの過去・現在・未来 @FOSS4G 2011 Tokyo
GEO Gridの過去・現在・未来 @FOSS4G 2011 Tokyo
Naotaka YAMAMOTO CHIKASADA
 
Use of geogrids as reinforcement in road construction
Use of geogrids as reinforcement in road constructionUse of geogrids as reinforcement in road construction
Use of geogrids as reinforcement in road construction
Pratyusha Banerjee
 
Electrokinetic geosynthetics
Electrokinetic geosyntheticsElectrokinetic geosynthetics
Electrokinetic geosynthetics
nithisha niha
 
Geogrid-As a soil reinforcement
Geogrid-As a soil reinforcementGeogrid-As a soil reinforcement
Geogrid-As a soil reinforcement
ssp1505
 
Geosynthetics- Types, and their use in Retaining Walls
Geosynthetics- Types, and their use in Retaining WallsGeosynthetics- Types, and their use in Retaining Walls
Geosynthetics- Types, and their use in Retaining Walls
Abhishek Bharti
 
Reinforced earth structures
Reinforced earth structuresReinforced earth structures
Reinforced earth structures
Umer Farooq
 
Geosynthetics Applications in Civil Engineering by Sirmoi_Geosynthetics EA Ltd
Geosynthetics Applications in Civil Engineering by Sirmoi_Geosynthetics EA LtdGeosynthetics Applications in Civil Engineering by Sirmoi_Geosynthetics EA Ltd
Geosynthetics Applications in Civil Engineering by Sirmoi_Geosynthetics EA Ltd
Sirmoi Wekesa
 
Electrokinetic Remediation of Heavy Metal contaminated soil
Electrokinetic Remediation of Heavy Metal contaminated soilElectrokinetic Remediation of Heavy Metal contaminated soil
Electrokinetic Remediation of Heavy Metal contaminated soil
Vijai Krishnan
 
Slideshare Powerpoint presentation
Slideshare Powerpoint presentationSlideshare Powerpoint presentation
Slideshare Powerpoint presentation
elliehood
 
LinkedIn SlideShare: Knowledge, Well-Presented
LinkedIn SlideShare: Knowledge, Well-PresentedLinkedIn SlideShare: Knowledge, Well-Presented
LinkedIn SlideShare: Knowledge, Well-Presented
SlideShare
 
State of the Word 2011
State of the Word 2011State of the Word 2011
State of the Word 2011
photomatt
 
TEDx Manchester: AI & The Future of Work
TEDx Manchester: AI & The Future of WorkTEDx Manchester: AI & The Future of Work
TEDx Manchester: AI & The Future of Work
Volker Hirsch
 

Viewers also liked (18)

Geosynthetics
GeosyntheticsGeosynthetics
Geosynthetics
 
Applications of Micro Geo Data for Urban Monitoring
Applications of Micro Geo Data  for Urban Monitoring Applications of Micro Geo Data  for Urban Monitoring
Applications of Micro Geo Data for Urban Monitoring
 
Separation & reinforcement temp. roads
Separation & reinforcement temp. roadsSeparation & reinforcement temp. roads
Separation & reinforcement temp. roads
 
Narrow Pavement Widening - Geosynthetic Reinforcement
Narrow Pavement Widening - Geosynthetic ReinforcementNarrow Pavement Widening - Geosynthetic Reinforcement
Narrow Pavement Widening - Geosynthetic Reinforcement
 
087 active crack control of continuously reinforced concrete pavements throug...
087 active crack control of continuously reinforced concrete pavements throug...087 active crack control of continuously reinforced concrete pavements throug...
087 active crack control of continuously reinforced concrete pavements throug...
 
Earth Retention Solutions
Earth Retention SolutionsEarth Retention Solutions
Earth Retention Solutions
 
GEO Gridの過去・現在・未来 @FOSS4G 2011 Tokyo
GEO Gridの過去・現在・未来 @FOSS4G 2011 TokyoGEO Gridの過去・現在・未来 @FOSS4G 2011 Tokyo
GEO Gridの過去・現在・未来 @FOSS4G 2011 Tokyo
 
Use of geogrids as reinforcement in road construction
Use of geogrids as reinforcement in road constructionUse of geogrids as reinforcement in road construction
Use of geogrids as reinforcement in road construction
 
Electrokinetic geosynthetics
Electrokinetic geosyntheticsElectrokinetic geosynthetics
Electrokinetic geosynthetics
 
Geogrid-As a soil reinforcement
Geogrid-As a soil reinforcementGeogrid-As a soil reinforcement
Geogrid-As a soil reinforcement
 
Geosynthetics- Types, and their use in Retaining Walls
Geosynthetics- Types, and their use in Retaining WallsGeosynthetics- Types, and their use in Retaining Walls
Geosynthetics- Types, and their use in Retaining Walls
 
Reinforced earth structures
Reinforced earth structuresReinforced earth structures
Reinforced earth structures
 
Geosynthetics Applications in Civil Engineering by Sirmoi_Geosynthetics EA Ltd
Geosynthetics Applications in Civil Engineering by Sirmoi_Geosynthetics EA LtdGeosynthetics Applications in Civil Engineering by Sirmoi_Geosynthetics EA Ltd
Geosynthetics Applications in Civil Engineering by Sirmoi_Geosynthetics EA Ltd
 
Electrokinetic Remediation of Heavy Metal contaminated soil
Electrokinetic Remediation of Heavy Metal contaminated soilElectrokinetic Remediation of Heavy Metal contaminated soil
Electrokinetic Remediation of Heavy Metal contaminated soil
 
Slideshare Powerpoint presentation
Slideshare Powerpoint presentationSlideshare Powerpoint presentation
Slideshare Powerpoint presentation
 
LinkedIn SlideShare: Knowledge, Well-Presented
LinkedIn SlideShare: Knowledge, Well-PresentedLinkedIn SlideShare: Knowledge, Well-Presented
LinkedIn SlideShare: Knowledge, Well-Presented
 
State of the Word 2011
State of the Word 2011State of the Word 2011
State of the Word 2011
 
TEDx Manchester: AI & The Future of Work
TEDx Manchester: AI & The Future of WorkTEDx Manchester: AI & The Future of Work
TEDx Manchester: AI & The Future of Work
 

Similar to First Use Of Geosynthetic Reinforced Soil – Integrated Bridge System in Illinois

UMAID IQBAL SEMINAR.pptx
UMAID IQBAL SEMINAR.pptxUMAID IQBAL SEMINAR.pptx
UMAID IQBAL SEMINAR.pptx
Praveendubey82
 
Lowcost prefebrication and infrastructure services
Lowcost prefebrication and infrastructure servicesLowcost prefebrication and infrastructure services
Lowcost prefebrication and infrastructure services
Ar Jitendra
 
Slip formwork for chimney
Slip formwork for chimneySlip formwork for chimney
Slip formwork for chimney
Axay Sharma
 
accelerated bridge construction(ABC)
accelerated bridge construction(ABC)accelerated bridge construction(ABC)
accelerated bridge construction(ABC)
varun km
 
Final_ppt_puneeth.pptx
Final_ppt_puneeth.pptxFinal_ppt_puneeth.pptx
Final_ppt_puneeth.pptx
Doctor Sadaf Qasim
 
Building construction
Building constructionBuilding construction
Building construction
nhmurad
 
Ralls ncc meeting-san_antonio_04-01-09
Ralls ncc meeting-san_antonio_04-01-09Ralls ncc meeting-san_antonio_04-01-09
Ralls ncc meeting-san_antonio_04-01-09
zaff69
 
Linkedin Presentation Krysyian Gnysinski
Linkedin Presentation Krysyian GnysinskiLinkedin Presentation Krysyian Gnysinski
Linkedin Presentation Krysyian Gnysinski
Krystian Gnysinski
 
Construction portfolio (manvi)
Construction portfolio (manvi)Construction portfolio (manvi)
Construction portfolio (manvi)
ManviVarshney2
 
Slipform construction
Slipform constructionSlipform construction
Slipform construction
ErankajKumar
 
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVEMODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
Dr K M SONI
 
pavementppt-150321132200-conversion-gate01.pdf
pavementppt-150321132200-conversion-gate01.pdfpavementppt-150321132200-conversion-gate01.pdf
pavementppt-150321132200-conversion-gate01.pdf
sunilghosh11
 
Pavement ppt
Pavement pptPavement ppt
Pavement ppt
Harsha Singh
 
Segmental bridge construction
Segmental bridge constructionSegmental bridge construction
Segmental bridge construction
Construction Tech. and Mgmt., VNIT Nagpur
 
Essentials slide in bridge construction a guide for bridge designers
Essentials slide in bridge construction a guide for bridge designersEssentials slide in bridge construction a guide for bridge designers
Essentials slide in bridge construction a guide for bridge designers
jose bonifacio de souza leite cuadros
 
Tubular Rivet Foundation (Part 1) .pdf
Tubular Rivet Foundation (Part 1) .pdfTubular Rivet Foundation (Part 1) .pdf
Tubular Rivet Foundation (Part 1) .pdf
DongyuanWang1
 
Aryyaka Sarkar Repair ^0 Rehabilitation of Structure.pptx
Aryyaka Sarkar Repair ^0 Rehabilitation of Structure.pptxAryyaka Sarkar Repair ^0 Rehabilitation of Structure.pptx
Aryyaka Sarkar Repair ^0 Rehabilitation of Structure.pptx
aryyaka99
 
ALTERNATE BUILDING MATERIALS & TECHNOLOGICAL ALTERNATIVES IN CONSTRUCTION
ALTERNATE BUILDING MATERIALS  & TECHNOLOGICAL ALTERNATIVES IN  CONSTRUCTIONALTERNATE BUILDING MATERIALS  & TECHNOLOGICAL ALTERNATIVES IN  CONSTRUCTION
ALTERNATE BUILDING MATERIALS & TECHNOLOGICAL ALTERNATIVES IN CONSTRUCTION
Rajesh Kolli
 
New Building Materials
New Building MaterialsNew Building Materials
New Building Materials
Dr K M SONI
 
2022-07-13.pptx
2022-07-13.pptx2022-07-13.pptx
2022-07-13.pptx
AshrafulHaqueTushar1
 

Similar to First Use Of Geosynthetic Reinforced Soil – Integrated Bridge System in Illinois (20)

UMAID IQBAL SEMINAR.pptx
UMAID IQBAL SEMINAR.pptxUMAID IQBAL SEMINAR.pptx
UMAID IQBAL SEMINAR.pptx
 
Lowcost prefebrication and infrastructure services
Lowcost prefebrication and infrastructure servicesLowcost prefebrication and infrastructure services
Lowcost prefebrication and infrastructure services
 
Slip formwork for chimney
Slip formwork for chimneySlip formwork for chimney
Slip formwork for chimney
 
accelerated bridge construction(ABC)
accelerated bridge construction(ABC)accelerated bridge construction(ABC)
accelerated bridge construction(ABC)
 
Final_ppt_puneeth.pptx
Final_ppt_puneeth.pptxFinal_ppt_puneeth.pptx
Final_ppt_puneeth.pptx
 
Building construction
Building constructionBuilding construction
Building construction
 
Ralls ncc meeting-san_antonio_04-01-09
Ralls ncc meeting-san_antonio_04-01-09Ralls ncc meeting-san_antonio_04-01-09
Ralls ncc meeting-san_antonio_04-01-09
 
Linkedin Presentation Krysyian Gnysinski
Linkedin Presentation Krysyian GnysinskiLinkedin Presentation Krysyian Gnysinski
Linkedin Presentation Krysyian Gnysinski
 
Construction portfolio (manvi)
Construction portfolio (manvi)Construction portfolio (manvi)
Construction portfolio (manvi)
 
Slipform construction
Slipform constructionSlipform construction
Slipform construction
 
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVEMODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
 
pavementppt-150321132200-conversion-gate01.pdf
pavementppt-150321132200-conversion-gate01.pdfpavementppt-150321132200-conversion-gate01.pdf
pavementppt-150321132200-conversion-gate01.pdf
 
Pavement ppt
Pavement pptPavement ppt
Pavement ppt
 
Segmental bridge construction
Segmental bridge constructionSegmental bridge construction
Segmental bridge construction
 
Essentials slide in bridge construction a guide for bridge designers
Essentials slide in bridge construction a guide for bridge designersEssentials slide in bridge construction a guide for bridge designers
Essentials slide in bridge construction a guide for bridge designers
 
Tubular Rivet Foundation (Part 1) .pdf
Tubular Rivet Foundation (Part 1) .pdfTubular Rivet Foundation (Part 1) .pdf
Tubular Rivet Foundation (Part 1) .pdf
 
Aryyaka Sarkar Repair ^0 Rehabilitation of Structure.pptx
Aryyaka Sarkar Repair ^0 Rehabilitation of Structure.pptxAryyaka Sarkar Repair ^0 Rehabilitation of Structure.pptx
Aryyaka Sarkar Repair ^0 Rehabilitation of Structure.pptx
 
ALTERNATE BUILDING MATERIALS & TECHNOLOGICAL ALTERNATIVES IN CONSTRUCTION
ALTERNATE BUILDING MATERIALS  & TECHNOLOGICAL ALTERNATIVES IN  CONSTRUCTIONALTERNATE BUILDING MATERIALS  & TECHNOLOGICAL ALTERNATIVES IN  CONSTRUCTION
ALTERNATE BUILDING MATERIALS & TECHNOLOGICAL ALTERNATIVES IN CONSTRUCTION
 
New Building Materials
New Building MaterialsNew Building Materials
New Building Materials
 
2022-07-13.pptx
2022-07-13.pptx2022-07-13.pptx
2022-07-13.pptx
 

Recently uploaded

一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理
一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理
一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理
sydezfe
 
UNIT 4 LINEAR INTEGRATED CIRCUITS-DIGITAL ICS
UNIT 4 LINEAR INTEGRATED CIRCUITS-DIGITAL ICSUNIT 4 LINEAR INTEGRATED CIRCUITS-DIGITAL ICS
UNIT 4 LINEAR INTEGRATED CIRCUITS-DIGITAL ICS
vmspraneeth
 
Blood finder application project report (1).pdf
Blood finder application project report (1).pdfBlood finder application project report (1).pdf
Blood finder application project report (1).pdf
Kamal Acharya
 
2. protection of river banks and bed erosion protection works.ppt
2. protection of river banks and bed erosion protection works.ppt2. protection of river banks and bed erosion protection works.ppt
2. protection of river banks and bed erosion protection works.ppt
abdatawakjira
 
Zener Diode and its V-I Characteristics and Applications
Zener Diode and its V-I Characteristics and ApplicationsZener Diode and its V-I Characteristics and Applications
Zener Diode and its V-I Characteristics and Applications
Shiny Christobel
 
1FIDIC-CONSTRUCTION-CONTRACT-2ND-ED-2017-RED-BOOK.pdf
1FIDIC-CONSTRUCTION-CONTRACT-2ND-ED-2017-RED-BOOK.pdf1FIDIC-CONSTRUCTION-CONTRACT-2ND-ED-2017-RED-BOOK.pdf
1FIDIC-CONSTRUCTION-CONTRACT-2ND-ED-2017-RED-BOOK.pdf
MadhavJungKarki
 
Generative AI Use cases applications solutions and implementation.pdf
Generative AI Use cases applications solutions and implementation.pdfGenerative AI Use cases applications solutions and implementation.pdf
Generative AI Use cases applications solutions and implementation.pdf
mahaffeycheryld
 
P5 Working Drawings.pdf floor plan, civil
P5 Working Drawings.pdf floor plan, civilP5 Working Drawings.pdf floor plan, civil
P5 Working Drawings.pdf floor plan, civil
AnasAhmadNoor
 
NATURAL DEEP EUTECTIC SOLVENTS AS ANTI-FREEZING AGENT
NATURAL DEEP EUTECTIC SOLVENTS AS ANTI-FREEZING AGENTNATURAL DEEP EUTECTIC SOLVENTS AS ANTI-FREEZING AGENT
NATURAL DEEP EUTECTIC SOLVENTS AS ANTI-FREEZING AGENT
Addu25809
 
Tools & Techniques for Commissioning and Maintaining PV Systems W-Animations ...
Tools & Techniques for Commissioning and Maintaining PV Systems W-Animations ...Tools & Techniques for Commissioning and Maintaining PV Systems W-Animations ...
Tools & Techniques for Commissioning and Maintaining PV Systems W-Animations ...
Transcat
 
Mechanical Engineering on AAI Summer Training Report-003.pdf
Mechanical Engineering on AAI Summer Training Report-003.pdfMechanical Engineering on AAI Summer Training Report-003.pdf
Mechanical Engineering on AAI Summer Training Report-003.pdf
21UME003TUSHARDEB
 
Supermarket Management System Project Report.pdf
Supermarket Management System Project Report.pdfSupermarket Management System Project Report.pdf
Supermarket Management System Project Report.pdf
Kamal Acharya
 
TIME TABLE MANAGEMENT SYSTEM testing.pptx
TIME TABLE MANAGEMENT SYSTEM testing.pptxTIME TABLE MANAGEMENT SYSTEM testing.pptx
TIME TABLE MANAGEMENT SYSTEM testing.pptx
CVCSOfficial
 
AI-Based Home Security System : Home security
AI-Based Home Security System : Home securityAI-Based Home Security System : Home security
AI-Based Home Security System : Home security
AIRCC Publishing Corporation
 
Software Engineering and Project Management - Software Testing + Agile Method...
Software Engineering and Project Management - Software Testing + Agile Method...Software Engineering and Project Management - Software Testing + Agile Method...
Software Engineering and Project Management - Software Testing + Agile Method...
Prakhyath Rai
 
一比一原版(USF毕业证)旧金山大学毕业证如何办理
一比一原版(USF毕业证)旧金山大学毕业证如何办理一比一原版(USF毕业证)旧金山大学毕业证如何办理
一比一原版(USF毕业证)旧金山大学毕业证如何办理
uqyfuc
 
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
ecqow
 
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Sinan KOZAK
 
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
ydzowc
 
Introduction to Computer Networks & OSI MODEL.ppt
Introduction to Computer Networks & OSI MODEL.pptIntroduction to Computer Networks & OSI MODEL.ppt
Introduction to Computer Networks & OSI MODEL.ppt
Dwarkadas J Sanghvi College of Engineering
 

Recently uploaded (20)

一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理
一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理
一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理
 
UNIT 4 LINEAR INTEGRATED CIRCUITS-DIGITAL ICS
UNIT 4 LINEAR INTEGRATED CIRCUITS-DIGITAL ICSUNIT 4 LINEAR INTEGRATED CIRCUITS-DIGITAL ICS
UNIT 4 LINEAR INTEGRATED CIRCUITS-DIGITAL ICS
 
Blood finder application project report (1).pdf
Blood finder application project report (1).pdfBlood finder application project report (1).pdf
Blood finder application project report (1).pdf
 
2. protection of river banks and bed erosion protection works.ppt
2. protection of river banks and bed erosion protection works.ppt2. protection of river banks and bed erosion protection works.ppt
2. protection of river banks and bed erosion protection works.ppt
 
Zener Diode and its V-I Characteristics and Applications
Zener Diode and its V-I Characteristics and ApplicationsZener Diode and its V-I Characteristics and Applications
Zener Diode and its V-I Characteristics and Applications
 
1FIDIC-CONSTRUCTION-CONTRACT-2ND-ED-2017-RED-BOOK.pdf
1FIDIC-CONSTRUCTION-CONTRACT-2ND-ED-2017-RED-BOOK.pdf1FIDIC-CONSTRUCTION-CONTRACT-2ND-ED-2017-RED-BOOK.pdf
1FIDIC-CONSTRUCTION-CONTRACT-2ND-ED-2017-RED-BOOK.pdf
 
Generative AI Use cases applications solutions and implementation.pdf
Generative AI Use cases applications solutions and implementation.pdfGenerative AI Use cases applications solutions and implementation.pdf
Generative AI Use cases applications solutions and implementation.pdf
 
P5 Working Drawings.pdf floor plan, civil
P5 Working Drawings.pdf floor plan, civilP5 Working Drawings.pdf floor plan, civil
P5 Working Drawings.pdf floor plan, civil
 
NATURAL DEEP EUTECTIC SOLVENTS AS ANTI-FREEZING AGENT
NATURAL DEEP EUTECTIC SOLVENTS AS ANTI-FREEZING AGENTNATURAL DEEP EUTECTIC SOLVENTS AS ANTI-FREEZING AGENT
NATURAL DEEP EUTECTIC SOLVENTS AS ANTI-FREEZING AGENT
 
Tools & Techniques for Commissioning and Maintaining PV Systems W-Animations ...
Tools & Techniques for Commissioning and Maintaining PV Systems W-Animations ...Tools & Techniques for Commissioning and Maintaining PV Systems W-Animations ...
Tools & Techniques for Commissioning and Maintaining PV Systems W-Animations ...
 
Mechanical Engineering on AAI Summer Training Report-003.pdf
Mechanical Engineering on AAI Summer Training Report-003.pdfMechanical Engineering on AAI Summer Training Report-003.pdf
Mechanical Engineering on AAI Summer Training Report-003.pdf
 
Supermarket Management System Project Report.pdf
Supermarket Management System Project Report.pdfSupermarket Management System Project Report.pdf
Supermarket Management System Project Report.pdf
 
TIME TABLE MANAGEMENT SYSTEM testing.pptx
TIME TABLE MANAGEMENT SYSTEM testing.pptxTIME TABLE MANAGEMENT SYSTEM testing.pptx
TIME TABLE MANAGEMENT SYSTEM testing.pptx
 
AI-Based Home Security System : Home security
AI-Based Home Security System : Home securityAI-Based Home Security System : Home security
AI-Based Home Security System : Home security
 
Software Engineering and Project Management - Software Testing + Agile Method...
Software Engineering and Project Management - Software Testing + Agile Method...Software Engineering and Project Management - Software Testing + Agile Method...
Software Engineering and Project Management - Software Testing + Agile Method...
 
一比一原版(USF毕业证)旧金山大学毕业证如何办理
一比一原版(USF毕业证)旧金山大学毕业证如何办理一比一原版(USF毕业证)旧金山大学毕业证如何办理
一比一原版(USF毕业证)旧金山大学毕业证如何办理
 
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
 
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
 
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
 
Introduction to Computer Networks & OSI MODEL.ppt
Introduction to Computer Networks & OSI MODEL.pptIntroduction to Computer Networks & OSI MODEL.ppt
Introduction to Computer Networks & OSI MODEL.ppt
 

First Use Of Geosynthetic Reinforced Soil – Integrated Bridge System in Illinois

  • 1. First Use Of Geosynthetic Reinforced Soil – Integrated Bridge System in Illinois Keith Sargent, P.E. Associate Thomas Engineering Group Dr. Riyad Wahab, P.E. State Geotechnical Engineer IL Dept. of Transportation
  • 2. What is GRS-IBS? • Alternating layers of compacted granular fill material and sheets of geotextile reinforcement. • Face of GRS-IBS wall is CMU or modular blocks. • Wall is constructed on top of a “Reinforced Soil Foundation” (RSF). • FHWA promotes the use of GRS-IBS through their “Every Day Counts” and “Accelerated Bridge Construction” programs.
  • 4. Construction Sequence: Step One • Lay a row of facing blocks.
  • 5. Construction Sequence: Step Two • Add a layer of compacted fill.
  • 6. Construction Sequence: Step Three • Add a layer of geosynthetic fabric
  • 7. What are the benefits? • GRS uses common, readily available materials and equipment. • Cost can be up to 25 to 60 percent less than bridges built with traditional methods. • Easy to maintain due to fewer construction items. • Reduces construction time. • Eliminates deep foundations and approach slabs.
  • 8. Approximate GRS-IBS Costs • FHWA estimates GRS-IBS using CMU facing to be approximately $33/SF. • If a wet-cast modular block is used, the estimated cost increase is approximately $28/SF ($61/SF). • Costs for approach slabs and deep foundations eliminated. • Comparison: MSE wall costs approximately $55/SF.
  • 9. GRS-IBS Use in Illinois FHWA contacted IDOT to search for projects, and in turn IDOT contacted Districts and Local agencies looking for suitable projects: • Competent soils resistant to scour • Waterways with 100-yr velocities of 3 ft/sec max • Non-staged construction • Low Average Daily Traffic volumes • Single Span superstructure - range (25 ft - 80 ft) • Skew 15° or less • Abutment wall heights not exceeding 30 ft
  • 10. GRS-IBS Use in Illinois • The Village of Lombard showed interest in using the GRS-IBS technology for their Great Western Trail project. • Original plan was to use MSE wall retaining pile supported abutments • Bollinger, Lach and Associates worked with FHWA and the Village to incorporate GRS-IBS technology into Contract Drawings.
  • 12. MSE Configuration to be Replaced • 48” deep precast prestressed concrete I beams spanning 92’-6”. •Integral abutments supported by 8 H-piles 80’ long. • 30 ft approach pavement spanning to 10’ wide spread footing. • MSE retaining walls used to shorten span and retain embankment. • Although bridge is for pedestrian use, it is designed for H-20 loading
  • 13. MSE Configuration to be Replaced
  • 14. GRS-IBS Design • FHWA has assembled guidelines for design of GRS-IBS. • Guidelines provide example plan sheets and details along with approximate quantities. • Detailed construction specifications are also provided within the guidelines. • Guidelines account for “favorable” and “poor” soil conditions.
  • 15.
  • 16.
  • 17.
  • 18.
  • 19. Normal Use is with Concrete Deck Beams
  • 20. Revised Elevation with GRS-IBS • Increased Span Length by 6 ft to accommodate blocks and footing. • Deleted 30 ft by 15 in. thick approach pavement and 10 ft footings. • Deleted piles, added 6 ft wide spread footings. • Kept Aggregate column ground improvement. .
  • 21. Revised Section with GRS-IBS • C.I.P. Footing. • Reinforced Soil Foundation (RSF) on Aggregate Columns. • Used Extra GRS Aggregate Backfill to transition approach settlement. • Approach is 3” HMA.
  • 22. Current Construction Status • Project was on September 23, 2011 Letting. • Aggregate Column Ground Improvements - completed on May 29th , 2012. • Reinforced Soil Foundation and Modular Block Walls (both east and west sides) - completed on August 17th . • C.I.P. footings - installed August 25th . • PPC I-Beams to be erected in October. • Instrumentation to monitor wall movement installed at the end of August (paid for by FHWA).
  • 25. Aggregate Column Installation • Installation of Aggregate Columns went smoothly. • Approximately two days of work for each abutment. • Approximately 65 columns per abutment. • Test column provided excellent results. – Loaded to 150% of design load (48 kips) – Deflected less than a ½” • Total Cost: $108,000
  • 27. RSF Installation • Four Step Process: – Install geotextile fabric on subgrade leaving excess on the sides. – Compact lifts of CA-06 stone. – Install layers of geogrid reinforcement. – Wrap foundation with geotextile fabric. • Installation of RSF is simple, however this project required foundation steps that complicated the construction.
  • 30. RECON Blocks Selected • 16”tall, 48”wide 24”deep • Other approved blocks included Redi Rock and Stone Strong • Wet Cast Block Required • To be stained and anti-graffiti surface applied
  • 31. Modular Block Installation • Block installation took longer than anticipated given the size of the block (4FT wide x 16” tall x 24” deep). • FHWA intent is to use 45 LB CMU blocks, not 1600 LB wet cast blocks. • Approximately 400 blocks per wall. • Making certain blocks are level and set into place is very important. • Block constructed with no batter, so precision was crucial.
  • 32. Modular Block Installation Setting first row level and in line was very important.
  • 33. Modular Block Installation Excavator needed to set block – very time consuming and difficult to perform precisely.
  • 34. Geosynthetic Reinforced Soil Installation • Soil reinforcement was Tenax TT L Type 70 geogrid. – Delivered in 4 FT wide rolls. – Difficult to cut and lay flat. – Stretching tight was important. • Select Fill was CA-16. – Required little compaction – Easy to work with.
  • 35. Geosynthetic Reinforced Soil Installation Tenax installed between blocks and halfway up block.
  • 38. FHWA Monitoring Research • FHWA hired TEG to perform survey monitoring at regular intervals over the next two years • Goal is to monitor horizontal and vertical displacement of the wall.
  • 39. Remaining Work • Installation of PPC I-Beams • Superstructure with Safety Railing • Decorative lighting • Staining/Coloring of Wall • Anti-Graffiti Coating with UV Protection
  • 40. Final Thoughts • The use of GRS-IBS for the Great Western Trail project in Lombard may not be representative of a usual GRS-IBS project. • Modular block used for Great Western Trail was large and required heavy machinery and added labor to set in place. • Modular block used was much more expensive than a standard CMU. • Overall cost was higher than MSE wall.

Editor's Notes

  1. Kane County Q&A from Bowes Road Interview:   What is your biggest weakness and how have you overcome? How much experience do you have with surveying and construction layout? What appeals to you about this project? What type of person are you? What type of person do you have troubles/difficulties with? How would you accelerate this project? How much experience do you have with 3-sided structures? What motivates you? Have you ever been removed from a project? What are some of the lessons you’ve learn on past projects?