SlideShare a Scribd company logo
Essentials of Slide-in Bridge Construction:
A Guide for Bridge Designers
Bala Sivakumar
HNTB Corp.
Agenda
 Introduction to ABC
 Introduction to Slide-In Bridge Construction (SIBC)
 Slide shoes
 Movement systems
 Components of SIBC design
 Permanent Bridge Design
 Temporary Support System
 Push / Pull System
 Sliding Bearings
 Sliding Forces
 SIBC Case Study
Accelerated Bridge Construction (ABC)
ABC is bridge construction that uses innovative
planning, design and construction methods to
reduce when replacing /
rehabilitating existing bridges.
What is ABC ?
ABC Elements and Methods
ACCELERATED BRIDGE CONSTRUCTION
Prefabricated
Elements &
Systems (PBES)
Accelerated
Geo-tech Work
Rapid Demolition
Structure
Placement
Methods
Innovative
Contracting
Benefits of ABC
Reduces disruption
to operations/
service
Safer; reduces
exposure of workers
and public to
construction activities
Better quality control
due to prefabricated
elements
Reduced
environmental
impacts
Time Metrics for ABC – Mobility Impact Time
Mobility Impacts Within:
Tier 1: Overnight or < 24 hours
Tier 2: Weekend or < 3 days
Tier 3: Up to 2 weeks
ABC Time
1. On-site construction time
2. Mobility impact time (ABC closure period)
ABC can minimize both
Project R04
Innovative Bridge Designs for Rapid Renewal
2007 – 2013
HNTB – Prime
SHRP 2 ABC Toolkit
• SHRP 2 ABC Toolkit
• Published 2012
– Prefabricated
elements
– Slide-In Bridge
Construction (SIBC)
www.trb.org
Prefabricated Elements & Systems (PBES)
• Multi-axle platform
• Each axle moves independently
• Moves on uneven terrain
Self-Propelled Modular Transporter (SPMT)
Lake Champlain Bridge, NY – Float-In
Slide in Replacement
What is Slide In Bridge Construction (SIBC)
• A method of accelerated bridge construction also known as
horizontal or lateral sliding.
• New superstructure is built parallel to existing bridge on
temporary supports.
• Old bridge is then demolished, new substructure constructed,
and then new bridge is slid into place.
• In some instances the new substructure is constructed below
the existing structure, this reduces the overall traffic
disruption time.
Slide-In Bridge Construction (SIBC)
• Sliding technique allows the new superstructure to be built alongside the
exiting reducing traffic impacts.
• Requires availability of ROW / space.
Alternate Approach to SIBC
• In other instances, the existing bridge is first slid off of the
existing alignment and then used as a temporary bypass
bridge while the new bridge is constructed on the old
(existing) alignment.
• In this case, the temporary substructure system must not only
provide support for the bridge, but also live load and other
transient loads.
Impediments to Using SIBC
• Impediments to SIBC
– Limited ROW
– Terrain around existing bridge is rugged
– Geotechnical conditions cannot adequately support
temporary works
– Alignment restrictions
When to Use SIBC
• Bridges on high ADT routes over low ADT routes
• Bridges over waterways
• Railroad bridges
• Ideal conditions for SIBC
– Wide, flat area(s) adjacent to original structure
NJ Transit Hogback Bridge – Gladstone Line
Weekend Slide in Replacement 2004
3 June 2008 20
Roll-Out Roll-In
Hood Canal Bridge WSDOT
Before During After
Roll-Out Roll-In
New York City 2005
• Bridge over I-678 – Van Wyck Expressway
• NYSDOT
Slide Bearings
• Rollers
• Teflon Pads
Skid Shoes
Skidding System
Sliding System Main Components: skid shoes, push-pull units, skid
tracks, hydraulic pumps and a monitoring and control system.
VSL Skidding System
Series of Teflon pads are mounted on the skid track
Skidding System
• Special skid tracks are available for use when moving loads
along curves.
• A simplified version called a skid beam can be used if the load
does not need to be raised in the vertical direction
• Capacity up to 250 tons per shoe
Synchronous Jacking and Skidding Systems
Hydraulic Power Pack
Control System
Load, stroke in the skidding jacks is monitored
on the control computer
Movement Systems
Push/Pull hydraulic jacks
Movement Systems
Push/Pull hydraulic jacks
Pulling with
strand jacks / Power winch
NJ TRANSIT,
Hogback Bridge
Come-Along cable puller
Movement Systems
Components of Slide-In Construction Design
1. Permanent Bridge Design
2. Temporary Support System
3. Push / Pull System
4. Sliding Bearings
5. Sliding Forces
1. Permanent Bridge Design
• The design of the permanent bridge must consider
anticipated construction activities.
• Consideration of the how the new bridge will be slid into
place.
• Strengthening or modifying components of the superstructure
and the substructure
– Local areas where the push/pull system will be attached,
– Where the sliding plates and/or rollers will support the
structure, and
– Where the sliding track will be installed.
• End diaphragms and end diaphragm connections which support
the bridge during the lateral slide
• Flexural, shear effects on capbeam from moving vertical load
Slide Support at Abutment
I-84 NY Bridge Slide
Diaphragm Slide Shoe
End Diaphragm & Slide Shoes
2. Temp Support System (falsework)
• Design must consider all applicable load effects including
environmental loads as well as the anticipated load effects
applied by the sliding system. (Contractor designed)
• Relative stiffness of permanent support structures (likely
relatively stiff) versus stiffness of temporary support
structures (likely relatively flexible).
• Anticipated deflection / settlement of the temporary system.
• Provisions for vertical adjustment of track girder
• Attach the temp support to the permanent structure for
lateral restraint
2. Temp Support System (falsework)
• Temporary works usually lies within the contractor’s
responsibilities.
• Must be conducted by a competent, registered professional
engineer.
• Geotechnical work must be the responsibility of the engineer
of record.
• Additionally geotechnical borings and report may be required
to ensure that the temporary foundation system operates as
desired/needed.
Design of Temp Support System (falsework)
3. Push / Pull System
• Adequate force application to overcome frictional forces
• Hydraulic jacks offer the opportunity to either push or pull the
system. Strand jacks and winches are used for “pull only”
• Pairs of opposing strand jacks and winches can be used to
develop a push/pull system
• System controls to ensure all components of the push/pull
system work together
• Displacement control during the slide to ensure that the ends
of the superstructure move at the same rate and thus avoid
any racking or binding.
• Contingency planning in the event of equipment failure
4. Sliding Bearings
• Steel rollers, slide plates or PTFE sliding bearings can be used as
sliding elements.
• Rollers have higher load capacity
• Rollers and slide plates require removal whereas a slide
bearings could be designed to remain as part of the permanent
structure.
• Eliminates vertical jacking requirements at the conclusion of the
slide, saving money and time
• Rollers are more costly than pads and are often used on bridge
projects with larger load requirements.
4. Sliding Bearings
• Pads also allow the use of an unguided system that will not bind
if ends of the bridge move at different rates.
• Continuous lubrication of the pads is critical during the slide.
• Normally, the sliding surface of the shoe consists of polished
stainless steel.
• Often, slide pads are reused in a slide as the bridge slides over
them. For the final move into the bridge’s permanent position,
new pads are placed and left in place.
• Monitoring is especially important on bridges moved without
guides.
Slide Shoes & Slide Bearings
PTFE Bonded to Elastomeric Pad
5. Sliding Forces
• Coefficients of friction for PTFE (Teflon) bearings are given in the
AASHTO LRFD Specifications.
• Static coefficients in the range of 0.09 to 0.12 and dynamic
coefficients in the range of 0.05 to 0.06 . Rollers have lower
friction values
• Use a trial slide to verify friction values
• Pushing or pulling mechanisms
should have a capacity in excess
of the calculated pushing or
pulling force in anticipation of
higher frictional effects.
FHWA SIBC Implementation Guides
Slide In Bridge Construction:
Case Study
SHRP2 Demonstration Project
Slide-In Bridge Construction
Weekend Replacement of NY I-84 Twin Bridges
• 20 Hr closure
• Two weekend nights
• Sept 21, 2013
• Oct 19, 2013
Weekend Replacement of NY I-84 Twin Bridges
• Over 75,000 ADT
• 16% trucks
• Existing bridges are too narrow for cross-overs
• Elevation differences between EB & WB roadways
• Underpassing road at 16% grade
Original Plan
• Build new temporary bridge in the median to maintain traffic
• Additional cost of approximately $2.0 M
• One construction season for each bridge
• Significant traffic impact
ABC Design: Slide-In Replacement
• Slide-In replacement over two weekend nights
• Traffic disruption on I-84 reduced from two years to
two Saturday nights (20 hr closures).
• Incentive/disincentive clause: $10,000 per hour for
early or late completion ($50 K max incentive)
• Eliminates need for a temporary bridge & cross-overs –
over; $2 M savings.
• Both slides completed within 10 months after NTP
• Traffic detoured onto state Route 6 for 20 hrs.
ABC Approach
• Weekend Replacement
• 20 Hr Closure
Rapid Demolition – 4 Hrs
• Chop and Drop
• Local road below closed
Superstructure Sections
• Double T beams (NEXT)
• Precast approach slabs
• UHPC closure pour
ABC Design - New Bridges
• Single span 80’; three lanes at 12’
• Left shoulder 6’, right shoulder 12’
• Bridge width 33’-4” 57’-0”
• Use of asphalt wearing surface eliminates grinding
• Under passing Dingle Ridge Road on 16% grade
• New bridges are two feet higher than the existing to
provide 14’-6” under-clearance.
• Minimize structure depth using double Tee sections
Abutment Design
Drilled shafts supporting cap beam
T-Wall
Cap
Beam
T-Wall Wingwalls
Drilled Shafts Outside Existing Footprint
New Abutment
Straddle Bent Abutment
Diaphragm
Cap Beam
Slide Shoe
Falsework
Temporary Bents on H piles
Contractor designed
Slide Bearings
Stainless Steel on Elastomeric Bearings w/PTFE
PTFE bonded to Elastomeric Bearing
Slide-In Replacement Concept
Slide
Surface
Temporary
end span
Modular walls
During Slide
Precast Approach Slabs
Temporary End Spans Carrying Traffic
Inverted T Sleeper Slabs
Lateral Slide -- Oct 21 2013
7 hours to demolish bridge and slide-in new bridge
Raising The Approaches
• Takes time: Critical path for closure period
Bridge Slides Completed 10 Months After NTP
ABC Benefits
• Road Closure will be significantly reduced from two
construction seasons to two weekends.
• Safety within the work zone will be improved.
• Reduced Costs primarily by not building the
crossovers and temporary bridge in the median
($2.0 M savings)
• Impacts to the New York City watershed will be
substantially reduced; at least 5 acres of land will not
have to be disturbed using ABC.
ABC is the clear choice
Thank You for Attending
Questions ?

More Related Content

What's hot

Grouting Technique Repair and Rehabilitation of Structures
Grouting Technique Repair and Rehabilitation of StructuresGrouting Technique Repair and Rehabilitation of Structures
Grouting Technique Repair and Rehabilitation of Structures
Ramanuj Jaldhari
 
Balanced Cantilever Bridge
Balanced Cantilever BridgeBalanced Cantilever Bridge
Balanced Cantilever Bridge
Jeelkumar Patel
 
Ppt bridges &amp; types
Ppt bridges &amp; typesPpt bridges &amp; types
Ppt bridges &amp; types
pratik vanam
 
Bridge Engineering
Bridge EngineeringBridge Engineering
Bridge Engineering
KHUSHBU SHAH
 
Tunnelling methods
Tunnelling methodsTunnelling methods
Tunnelling methods
jagadish chintu
 
Road, Culvert & Bridge Training
Road, Culvert & Bridge TrainingRoad, Culvert & Bridge Training
Road, Culvert & Bridge Training
Abhishek Bharti
 
suspension bridge
suspension bridgesuspension bridge
suspension bridge
Gaurav Rawat
 
Precast segmental construction of bridges
Precast segmental construction of bridgesPrecast segmental construction of bridges
Precast segmental construction of bridges
mukul srivastava
 
Diaphragm wall construction
Diaphragm wall constructionDiaphragm wall construction
Diaphragm wall construction
ABHISHEK THAKKAE
 
Types Of Foundation
Types Of FoundationTypes Of Foundation
Types Of Foundationstooty s
 
Bridge foundation and its loading system
Bridge foundation and its loading systemBridge foundation and its loading system
Bridge foundation and its loading system
DEBASREE GHOSH
 
Design of flyover elements
Design of flyover elementsDesign of flyover elements
Design of flyover elements
subbu lakshmi
 
Pile driving equipments_Advanced Construction Technology (Semester-6), Civil ...
Pile driving equipments_Advanced Construction Technology (Semester-6), Civil ...Pile driving equipments_Advanced Construction Technology (Semester-6), Civil ...
Pile driving equipments_Advanced Construction Technology (Semester-6), Civil ...
A Makwana
 
2.7 BRIDGE LAUNCHING.ppt
2.7 BRIDGE LAUNCHING.ppt2.7 BRIDGE LAUNCHING.ppt
2.7 BRIDGE LAUNCHING.ppt
PrasannaRaniB
 
any
anyany
Suspension bridges
Suspension bridgesSuspension bridges
Suspension bridges
Rana Ibrahim
 
BALANCED CANTILEVER BRIDGE
BALANCED CANTILEVER BRIDGEBALANCED CANTILEVER BRIDGE
BALANCED CANTILEVER BRIDGE
srinivas cnu
 
civil enginnering industrial training report
civil enginnering industrial training report civil enginnering industrial training report
civil enginnering industrial training report
KRISHNA MURARI
 
Training report done on Bridge Construction
Training report done on Bridge ConstructionTraining report done on Bridge Construction
Training report done on Bridge Construction
Sukhdeep Jat
 
segmental construction of bridges
segmental construction of bridgessegmental construction of bridges
segmental construction of bridgesSravan Kumar
 

What's hot (20)

Grouting Technique Repair and Rehabilitation of Structures
Grouting Technique Repair and Rehabilitation of StructuresGrouting Technique Repair and Rehabilitation of Structures
Grouting Technique Repair and Rehabilitation of Structures
 
Balanced Cantilever Bridge
Balanced Cantilever BridgeBalanced Cantilever Bridge
Balanced Cantilever Bridge
 
Ppt bridges &amp; types
Ppt bridges &amp; typesPpt bridges &amp; types
Ppt bridges &amp; types
 
Bridge Engineering
Bridge EngineeringBridge Engineering
Bridge Engineering
 
Tunnelling methods
Tunnelling methodsTunnelling methods
Tunnelling methods
 
Road, Culvert & Bridge Training
Road, Culvert & Bridge TrainingRoad, Culvert & Bridge Training
Road, Culvert & Bridge Training
 
suspension bridge
suspension bridgesuspension bridge
suspension bridge
 
Precast segmental construction of bridges
Precast segmental construction of bridgesPrecast segmental construction of bridges
Precast segmental construction of bridges
 
Diaphragm wall construction
Diaphragm wall constructionDiaphragm wall construction
Diaphragm wall construction
 
Types Of Foundation
Types Of FoundationTypes Of Foundation
Types Of Foundation
 
Bridge foundation and its loading system
Bridge foundation and its loading systemBridge foundation and its loading system
Bridge foundation and its loading system
 
Design of flyover elements
Design of flyover elementsDesign of flyover elements
Design of flyover elements
 
Pile driving equipments_Advanced Construction Technology (Semester-6), Civil ...
Pile driving equipments_Advanced Construction Technology (Semester-6), Civil ...Pile driving equipments_Advanced Construction Technology (Semester-6), Civil ...
Pile driving equipments_Advanced Construction Technology (Semester-6), Civil ...
 
2.7 BRIDGE LAUNCHING.ppt
2.7 BRIDGE LAUNCHING.ppt2.7 BRIDGE LAUNCHING.ppt
2.7 BRIDGE LAUNCHING.ppt
 
any
anyany
any
 
Suspension bridges
Suspension bridgesSuspension bridges
Suspension bridges
 
BALANCED CANTILEVER BRIDGE
BALANCED CANTILEVER BRIDGEBALANCED CANTILEVER BRIDGE
BALANCED CANTILEVER BRIDGE
 
civil enginnering industrial training report
civil enginnering industrial training report civil enginnering industrial training report
civil enginnering industrial training report
 
Training report done on Bridge Construction
Training report done on Bridge ConstructionTraining report done on Bridge Construction
Training report done on Bridge Construction
 
segmental construction of bridges
segmental construction of bridgessegmental construction of bridges
segmental construction of bridges
 

Similar to Essentials slide in bridge construction a guide for bridge designers

accelerated bridge construction(ABC)
accelerated bridge construction(ABC)accelerated bridge construction(ABC)
accelerated bridge construction(ABC)
varun km
 
Bridges in Hilly areas seminar
Bridges in Hilly areas seminarBridges in Hilly areas seminar
Bridges in Hilly areas seminar
Abhinav Pateriya
 
UMAID IQBAL SEMINAR.pptx
UMAID IQBAL SEMINAR.pptxUMAID IQBAL SEMINAR.pptx
UMAID IQBAL SEMINAR.pptx
Praveendubey82
 
RINA - AOG 2017 - Development of Self Installing Deepwater Spar - ARUP - Ashi...
RINA - AOG 2017 - Development of Self Installing Deepwater Spar - ARUP - Ashi...RINA - AOG 2017 - Development of Self Installing Deepwater Spar - ARUP - Ashi...
RINA - AOG 2017 - Development of Self Installing Deepwater Spar - ARUP - Ashi...
Nick Bentley
 
CCTVHeadquarters.pdf
CCTVHeadquarters.pdfCCTVHeadquarters.pdf
CCTVHeadquarters.pdf
DANISHPUTRAMDFARIS
 
Slip formwork for chimney
Slip formwork for chimneySlip formwork for chimney
Slip formwork for chimney
Axay Sharma
 
Metro rail segments
Metro rail segmentsMetro rail segments
Metro rail segments
Axay Sharma
 
Lecture 0 design of spilways an overview
Lecture 0 design of spilways an overviewLecture 0 design of spilways an overview
Lecture 0 design of spilways an overview
Addis Ababa Science and Technology University
 
Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...
Rajesh Prasad
 
1.5 class a,b
1.5 class a,b1.5 class a,b
1.5 class a,b
Mani Das
 
Tower crane
Tower craneTower crane
Tower crane
Amman Athif
 
Prefabricated Column
Prefabricated ColumnPrefabricated Column
Prefabricated Column
Anees Khan
 
Team rhythmdesignathon
Team rhythmdesignathonTeam rhythmdesignathon
Team rhythmdesignathon
MaazKhan273
 
02_Practical_Design_Balanced_Cantilever_Bridges_Piyush_R1.pdf
02_Practical_Design_Balanced_Cantilever_Bridges_Piyush_R1.pdf02_Practical_Design_Balanced_Cantilever_Bridges_Piyush_R1.pdf
02_Practical_Design_Balanced_Cantilever_Bridges_Piyush_R1.pdf
pulakrajpadhai
 
Construction portfolio (manvi)
Construction portfolio (manvi)Construction portfolio (manvi)
Construction portfolio (manvi)
ManviVarshney2
 
2019 CRW - esign, Fabrication and Testing of Cantilever Beams and Triangle Pl...
2019 CRW - esign, Fabrication and Testing of Cantilever Beams and Triangle Pl...2019 CRW - esign, Fabrication and Testing of Cantilever Beams and Triangle Pl...
2019 CRW - esign, Fabrication and Testing of Cantilever Beams and Triangle Pl...
Specialized Carriers & Rigging Association
 
Telescopic crane
Telescopic crane Telescopic crane
Telescopic crane
Bismillah Arif
 
Prefabricated structures
Prefabricated structuresPrefabricated structures
Prefabricated structures
Aishwarya Deopujari
 
Ralls ncc meeting-san_antonio_04-01-09
Ralls ncc meeting-san_antonio_04-01-09Ralls ncc meeting-san_antonio_04-01-09
Ralls ncc meeting-san_antonio_04-01-09zaff69
 

Similar to Essentials slide in bridge construction a guide for bridge designers (20)

accelerated bridge construction(ABC)
accelerated bridge construction(ABC)accelerated bridge construction(ABC)
accelerated bridge construction(ABC)
 
Bridges in Hilly areas seminar
Bridges in Hilly areas seminarBridges in Hilly areas seminar
Bridges in Hilly areas seminar
 
UMAID IQBAL SEMINAR.pptx
UMAID IQBAL SEMINAR.pptxUMAID IQBAL SEMINAR.pptx
UMAID IQBAL SEMINAR.pptx
 
RINA - AOG 2017 - Development of Self Installing Deepwater Spar - ARUP - Ashi...
RINA - AOG 2017 - Development of Self Installing Deepwater Spar - ARUP - Ashi...RINA - AOG 2017 - Development of Self Installing Deepwater Spar - ARUP - Ashi...
RINA - AOG 2017 - Development of Self Installing Deepwater Spar - ARUP - Ashi...
 
CCTVHeadquarters.pdf
CCTVHeadquarters.pdfCCTVHeadquarters.pdf
CCTVHeadquarters.pdf
 
Slip formwork for chimney
Slip formwork for chimneySlip formwork for chimney
Slip formwork for chimney
 
Metro rail segments
Metro rail segmentsMetro rail segments
Metro rail segments
 
Lecture 0 design of spilways an overview
Lecture 0 design of spilways an overviewLecture 0 design of spilways an overview
Lecture 0 design of spilways an overview
 
Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...
 
1.5 class a,b
1.5 class a,b1.5 class a,b
1.5 class a,b
 
Tower crane
Tower craneTower crane
Tower crane
 
Prefabricated Column
Prefabricated ColumnPrefabricated Column
Prefabricated Column
 
PFS.pptx
PFS.pptxPFS.pptx
PFS.pptx
 
Team rhythmdesignathon
Team rhythmdesignathonTeam rhythmdesignathon
Team rhythmdesignathon
 
02_Practical_Design_Balanced_Cantilever_Bridges_Piyush_R1.pdf
02_Practical_Design_Balanced_Cantilever_Bridges_Piyush_R1.pdf02_Practical_Design_Balanced_Cantilever_Bridges_Piyush_R1.pdf
02_Practical_Design_Balanced_Cantilever_Bridges_Piyush_R1.pdf
 
Construction portfolio (manvi)
Construction portfolio (manvi)Construction portfolio (manvi)
Construction portfolio (manvi)
 
2019 CRW - esign, Fabrication and Testing of Cantilever Beams and Triangle Pl...
2019 CRW - esign, Fabrication and Testing of Cantilever Beams and Triangle Pl...2019 CRW - esign, Fabrication and Testing of Cantilever Beams and Triangle Pl...
2019 CRW - esign, Fabrication and Testing of Cantilever Beams and Triangle Pl...
 
Telescopic crane
Telescopic crane Telescopic crane
Telescopic crane
 
Prefabricated structures
Prefabricated structuresPrefabricated structures
Prefabricated structures
 
Ralls ncc meeting-san_antonio_04-01-09
Ralls ncc meeting-san_antonio_04-01-09Ralls ncc meeting-san_antonio_04-01-09
Ralls ncc meeting-san_antonio_04-01-09
 

More from jose bonifacio de souza leite cuadros

PUENTE PONTE BRIDGE UÑA DE GATO PERU Y BANEGAS BOLIVIA.pptx
PUENTE PONTE BRIDGE  UÑA DE GATO PERU Y BANEGAS BOLIVIA.pptxPUENTE PONTE BRIDGE  UÑA DE GATO PERU Y BANEGAS BOLIVIA.pptx
PUENTE PONTE BRIDGE UÑA DE GATO PERU Y BANEGAS BOLIVIA.pptx
jose bonifacio de souza leite cuadros
 
Puente eternidad de chupaca junin peru 1
Puente eternidad de chupaca junin peru 1Puente eternidad de chupaca junin peru 1
Puente eternidad de chupaca junin peru 1
jose bonifacio de souza leite cuadros
 
Empalme de los fierros en un edificio como japon 2019
Empalme de los fierros en un edificio como japon 2019Empalme de los fierros en un edificio como japon 2019
Empalme de los fierros en un edificio como japon 2019
jose bonifacio de souza leite cuadros
 
Parto mecanismo de rusia 10 aaa
Parto mecanismo de rusia 10 aaaParto mecanismo de rusia 10 aaa
Parto mecanismo de rusia 10 aaa
jose bonifacio de souza leite cuadros
 
Presentaciones fetales en el parto de argentina 3 aaa
Presentaciones fetales en el parto de argentina 3 aaaPresentaciones fetales en el parto de argentina 3 aaa
Presentaciones fetales en el parto de argentina 3 aaa
jose bonifacio de souza leite cuadros
 
Zapatas de casas para terremotos medianos 2019
Zapatas  de casas para  terremotos medianos  2019Zapatas  de casas para  terremotos medianos  2019
Zapatas de casas para terremotos medianos 2019
jose bonifacio de souza leite cuadros
 
Presentaciones fetales en el parto de argentina
Presentaciones fetales en el parto de argentinaPresentaciones fetales en el parto de argentina
Presentaciones fetales en el parto de argentina
jose bonifacio de souza leite cuadros
 
Parto presentaciones fetales 9 aaa
Parto  presentaciones fetales 9 aaaParto  presentaciones fetales 9 aaa
Parto presentaciones fetales 9 aaa
jose bonifacio de souza leite cuadros
 
Parto normal vaginal presentaciones 8 aaa
Parto normal vaginal presentaciones 8 aaaParto normal vaginal presentaciones 8 aaa
Parto normal vaginal presentaciones 8 aaa
jose bonifacio de souza leite cuadros
 
Parto normal cefalico presentaciones 7 aaa
Parto normal cefalico presentaciones 7 aaaParto normal cefalico presentaciones 7 aaa
Parto normal cefalico presentaciones 7 aaa
jose bonifacio de souza leite cuadros
 
Ranking de las mujeres mas hermosas del mundo 2
Ranking de las mujeres mas hermosas del mundo 2Ranking de las mujeres mas hermosas del mundo 2
Ranking de las mujeres mas hermosas del mundo 2
jose bonifacio de souza leite cuadros
 
Puente domingo savio huancayo fotos
Puente domingo savio huancayo  fotosPuente domingo savio huancayo  fotos
Puente domingo savio huancayo fotos
jose bonifacio de souza leite cuadros
 
Puente domingo savio gaviones huancayo
Puente domingo savio gaviones  huancayoPuente domingo savio gaviones  huancayo
Puente domingo savio gaviones huancayo
jose bonifacio de souza leite cuadros
 
Parto normal eutocico oiia 6 aaa
Parto normal eutocico oiia 6 aaaParto normal eutocico oiia 6 aaa
Parto normal eutocico oiia 6 aaa
jose bonifacio de souza leite cuadros
 
Altura de presentacion fetal y parto 1 aaa
Altura de presentacion fetal y parto 1 aaaAltura de presentacion fetal y parto 1 aaa
Altura de presentacion fetal y parto 1 aaa
jose bonifacio de souza leite cuadros
 
Atencion del recien nacido 1 aaa
Atencion del recien nacido 1 aaaAtencion del recien nacido 1 aaa
Atencion del recien nacido 1 aaa
jose bonifacio de souza leite cuadros
 
Mecanismo de parto obstetricia williams 23 4 aaa
Mecanismo de parto obstetricia williams 23 4 aaaMecanismo de parto obstetricia williams 23 4 aaa
Mecanismo de parto obstetricia williams 23 4 aaa
jose bonifacio de souza leite cuadros
 
Mecanismo de parto cefalico normal en oiia 3 aaa
Mecanismo de parto cefalico normal en oiia  3 aaaMecanismo de parto cefalico normal en oiia  3 aaa
Mecanismo de parto cefalico normal en oiia 3 aaa
jose bonifacio de souza leite cuadros
 
Veredas de cemento y plazas publicas de cemento 2
Veredas de cemento y plazas publicas de cemento 2Veredas de cemento y plazas publicas de cemento 2
Veredas de cemento y plazas publicas de cemento 2
jose bonifacio de souza leite cuadros
 
Columnas distancia entre ellas segun tipo del terreno o piso
Columnas distancia entre ellas segun tipo del terreno o pisoColumnas distancia entre ellas segun tipo del terreno o piso
Columnas distancia entre ellas segun tipo del terreno o piso
jose bonifacio de souza leite cuadros
 

More from jose bonifacio de souza leite cuadros (20)

PUENTE PONTE BRIDGE UÑA DE GATO PERU Y BANEGAS BOLIVIA.pptx
PUENTE PONTE BRIDGE  UÑA DE GATO PERU Y BANEGAS BOLIVIA.pptxPUENTE PONTE BRIDGE  UÑA DE GATO PERU Y BANEGAS BOLIVIA.pptx
PUENTE PONTE BRIDGE UÑA DE GATO PERU Y BANEGAS BOLIVIA.pptx
 
Puente eternidad de chupaca junin peru 1
Puente eternidad de chupaca junin peru 1Puente eternidad de chupaca junin peru 1
Puente eternidad de chupaca junin peru 1
 
Empalme de los fierros en un edificio como japon 2019
Empalme de los fierros en un edificio como japon 2019Empalme de los fierros en un edificio como japon 2019
Empalme de los fierros en un edificio como japon 2019
 
Parto mecanismo de rusia 10 aaa
Parto mecanismo de rusia 10 aaaParto mecanismo de rusia 10 aaa
Parto mecanismo de rusia 10 aaa
 
Presentaciones fetales en el parto de argentina 3 aaa
Presentaciones fetales en el parto de argentina 3 aaaPresentaciones fetales en el parto de argentina 3 aaa
Presentaciones fetales en el parto de argentina 3 aaa
 
Zapatas de casas para terremotos medianos 2019
Zapatas  de casas para  terremotos medianos  2019Zapatas  de casas para  terremotos medianos  2019
Zapatas de casas para terremotos medianos 2019
 
Presentaciones fetales en el parto de argentina
Presentaciones fetales en el parto de argentinaPresentaciones fetales en el parto de argentina
Presentaciones fetales en el parto de argentina
 
Parto presentaciones fetales 9 aaa
Parto  presentaciones fetales 9 aaaParto  presentaciones fetales 9 aaa
Parto presentaciones fetales 9 aaa
 
Parto normal vaginal presentaciones 8 aaa
Parto normal vaginal presentaciones 8 aaaParto normal vaginal presentaciones 8 aaa
Parto normal vaginal presentaciones 8 aaa
 
Parto normal cefalico presentaciones 7 aaa
Parto normal cefalico presentaciones 7 aaaParto normal cefalico presentaciones 7 aaa
Parto normal cefalico presentaciones 7 aaa
 
Ranking de las mujeres mas hermosas del mundo 2
Ranking de las mujeres mas hermosas del mundo 2Ranking de las mujeres mas hermosas del mundo 2
Ranking de las mujeres mas hermosas del mundo 2
 
Puente domingo savio huancayo fotos
Puente domingo savio huancayo  fotosPuente domingo savio huancayo  fotos
Puente domingo savio huancayo fotos
 
Puente domingo savio gaviones huancayo
Puente domingo savio gaviones  huancayoPuente domingo savio gaviones  huancayo
Puente domingo savio gaviones huancayo
 
Parto normal eutocico oiia 6 aaa
Parto normal eutocico oiia 6 aaaParto normal eutocico oiia 6 aaa
Parto normal eutocico oiia 6 aaa
 
Altura de presentacion fetal y parto 1 aaa
Altura de presentacion fetal y parto 1 aaaAltura de presentacion fetal y parto 1 aaa
Altura de presentacion fetal y parto 1 aaa
 
Atencion del recien nacido 1 aaa
Atencion del recien nacido 1 aaaAtencion del recien nacido 1 aaa
Atencion del recien nacido 1 aaa
 
Mecanismo de parto obstetricia williams 23 4 aaa
Mecanismo de parto obstetricia williams 23 4 aaaMecanismo de parto obstetricia williams 23 4 aaa
Mecanismo de parto obstetricia williams 23 4 aaa
 
Mecanismo de parto cefalico normal en oiia 3 aaa
Mecanismo de parto cefalico normal en oiia  3 aaaMecanismo de parto cefalico normal en oiia  3 aaa
Mecanismo de parto cefalico normal en oiia 3 aaa
 
Veredas de cemento y plazas publicas de cemento 2
Veredas de cemento y plazas publicas de cemento 2Veredas de cemento y plazas publicas de cemento 2
Veredas de cemento y plazas publicas de cemento 2
 
Columnas distancia entre ellas segun tipo del terreno o piso
Columnas distancia entre ellas segun tipo del terreno o pisoColumnas distancia entre ellas segun tipo del terreno o piso
Columnas distancia entre ellas segun tipo del terreno o piso
 

Recently uploaded

在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
Runway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptxRunway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptx
SupreethSP4
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 

Recently uploaded (20)

在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
Runway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptxRunway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptx
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 

Essentials slide in bridge construction a guide for bridge designers

  • 1. Essentials of Slide-in Bridge Construction: A Guide for Bridge Designers Bala Sivakumar HNTB Corp.
  • 2. Agenda  Introduction to ABC  Introduction to Slide-In Bridge Construction (SIBC)  Slide shoes  Movement systems  Components of SIBC design  Permanent Bridge Design  Temporary Support System  Push / Pull System  Sliding Bearings  Sliding Forces  SIBC Case Study
  • 3. Accelerated Bridge Construction (ABC) ABC is bridge construction that uses innovative planning, design and construction methods to reduce when replacing / rehabilitating existing bridges. What is ABC ?
  • 4. ABC Elements and Methods ACCELERATED BRIDGE CONSTRUCTION Prefabricated Elements & Systems (PBES) Accelerated Geo-tech Work Rapid Demolition Structure Placement Methods Innovative Contracting
  • 5. Benefits of ABC Reduces disruption to operations/ service Safer; reduces exposure of workers and public to construction activities Better quality control due to prefabricated elements Reduced environmental impacts
  • 6. Time Metrics for ABC – Mobility Impact Time Mobility Impacts Within: Tier 1: Overnight or < 24 hours Tier 2: Weekend or < 3 days Tier 3: Up to 2 weeks
  • 7. ABC Time 1. On-site construction time 2. Mobility impact time (ABC closure period) ABC can minimize both
  • 8. Project R04 Innovative Bridge Designs for Rapid Renewal 2007 – 2013 HNTB – Prime
  • 9. SHRP 2 ABC Toolkit • SHRP 2 ABC Toolkit • Published 2012 – Prefabricated elements – Slide-In Bridge Construction (SIBC) www.trb.org
  • 10. Prefabricated Elements & Systems (PBES)
  • 11. • Multi-axle platform • Each axle moves independently • Moves on uneven terrain Self-Propelled Modular Transporter (SPMT)
  • 12. Lake Champlain Bridge, NY – Float-In
  • 14. What is Slide In Bridge Construction (SIBC) • A method of accelerated bridge construction also known as horizontal or lateral sliding. • New superstructure is built parallel to existing bridge on temporary supports. • Old bridge is then demolished, new substructure constructed, and then new bridge is slid into place. • In some instances the new substructure is constructed below the existing structure, this reduces the overall traffic disruption time.
  • 15. Slide-In Bridge Construction (SIBC) • Sliding technique allows the new superstructure to be built alongside the exiting reducing traffic impacts. • Requires availability of ROW / space.
  • 16. Alternate Approach to SIBC • In other instances, the existing bridge is first slid off of the existing alignment and then used as a temporary bypass bridge while the new bridge is constructed on the old (existing) alignment. • In this case, the temporary substructure system must not only provide support for the bridge, but also live load and other transient loads.
  • 17. Impediments to Using SIBC • Impediments to SIBC – Limited ROW – Terrain around existing bridge is rugged – Geotechnical conditions cannot adequately support temporary works – Alignment restrictions
  • 18. When to Use SIBC • Bridges on high ADT routes over low ADT routes • Bridges over waterways • Railroad bridges • Ideal conditions for SIBC – Wide, flat area(s) adjacent to original structure
  • 19. NJ Transit Hogback Bridge – Gladstone Line Weekend Slide in Replacement 2004
  • 20. 3 June 2008 20 Roll-Out Roll-In Hood Canal Bridge WSDOT Before During After
  • 21. Roll-Out Roll-In New York City 2005 • Bridge over I-678 – Van Wyck Expressway • NYSDOT
  • 24. Skidding System Sliding System Main Components: skid shoes, push-pull units, skid tracks, hydraulic pumps and a monitoring and control system. VSL Skidding System Series of Teflon pads are mounted on the skid track
  • 25. Skidding System • Special skid tracks are available for use when moving loads along curves. • A simplified version called a skid beam can be used if the load does not need to be raised in the vertical direction • Capacity up to 250 tons per shoe
  • 26. Synchronous Jacking and Skidding Systems Hydraulic Power Pack Control System Load, stroke in the skidding jacks is monitored on the control computer
  • 28. Movement Systems Push/Pull hydraulic jacks Pulling with strand jacks / Power winch
  • 29. NJ TRANSIT, Hogback Bridge Come-Along cable puller Movement Systems
  • 30. Components of Slide-In Construction Design 1. Permanent Bridge Design 2. Temporary Support System 3. Push / Pull System 4. Sliding Bearings 5. Sliding Forces
  • 31. 1. Permanent Bridge Design • The design of the permanent bridge must consider anticipated construction activities. • Consideration of the how the new bridge will be slid into place. • Strengthening or modifying components of the superstructure and the substructure – Local areas where the push/pull system will be attached, – Where the sliding plates and/or rollers will support the structure, and – Where the sliding track will be installed. • End diaphragms and end diaphragm connections which support the bridge during the lateral slide • Flexural, shear effects on capbeam from moving vertical load
  • 32. Slide Support at Abutment I-84 NY Bridge Slide Diaphragm Slide Shoe
  • 33. End Diaphragm & Slide Shoes
  • 34. 2. Temp Support System (falsework) • Design must consider all applicable load effects including environmental loads as well as the anticipated load effects applied by the sliding system. (Contractor designed) • Relative stiffness of permanent support structures (likely relatively stiff) versus stiffness of temporary support structures (likely relatively flexible). • Anticipated deflection / settlement of the temporary system. • Provisions for vertical adjustment of track girder • Attach the temp support to the permanent structure for lateral restraint
  • 35. 2. Temp Support System (falsework)
  • 36. • Temporary works usually lies within the contractor’s responsibilities. • Must be conducted by a competent, registered professional engineer. • Geotechnical work must be the responsibility of the engineer of record. • Additionally geotechnical borings and report may be required to ensure that the temporary foundation system operates as desired/needed. Design of Temp Support System (falsework)
  • 37. 3. Push / Pull System • Adequate force application to overcome frictional forces • Hydraulic jacks offer the opportunity to either push or pull the system. Strand jacks and winches are used for “pull only” • Pairs of opposing strand jacks and winches can be used to develop a push/pull system • System controls to ensure all components of the push/pull system work together • Displacement control during the slide to ensure that the ends of the superstructure move at the same rate and thus avoid any racking or binding. • Contingency planning in the event of equipment failure
  • 38. 4. Sliding Bearings • Steel rollers, slide plates or PTFE sliding bearings can be used as sliding elements. • Rollers have higher load capacity • Rollers and slide plates require removal whereas a slide bearings could be designed to remain as part of the permanent structure. • Eliminates vertical jacking requirements at the conclusion of the slide, saving money and time • Rollers are more costly than pads and are often used on bridge projects with larger load requirements.
  • 39. 4. Sliding Bearings • Pads also allow the use of an unguided system that will not bind if ends of the bridge move at different rates. • Continuous lubrication of the pads is critical during the slide. • Normally, the sliding surface of the shoe consists of polished stainless steel. • Often, slide pads are reused in a slide as the bridge slides over them. For the final move into the bridge’s permanent position, new pads are placed and left in place. • Monitoring is especially important on bridges moved without guides.
  • 40. Slide Shoes & Slide Bearings PTFE Bonded to Elastomeric Pad
  • 41. 5. Sliding Forces • Coefficients of friction for PTFE (Teflon) bearings are given in the AASHTO LRFD Specifications. • Static coefficients in the range of 0.09 to 0.12 and dynamic coefficients in the range of 0.05 to 0.06 . Rollers have lower friction values • Use a trial slide to verify friction values • Pushing or pulling mechanisms should have a capacity in excess of the calculated pushing or pulling force in anticipation of higher frictional effects.
  • 43. Slide In Bridge Construction: Case Study SHRP2 Demonstration Project
  • 44. Slide-In Bridge Construction Weekend Replacement of NY I-84 Twin Bridges • 20 Hr closure • Two weekend nights • Sept 21, 2013 • Oct 19, 2013
  • 45. Weekend Replacement of NY I-84 Twin Bridges • Over 75,000 ADT • 16% trucks • Existing bridges are too narrow for cross-overs • Elevation differences between EB & WB roadways • Underpassing road at 16% grade
  • 46. Original Plan • Build new temporary bridge in the median to maintain traffic • Additional cost of approximately $2.0 M • One construction season for each bridge • Significant traffic impact
  • 47. ABC Design: Slide-In Replacement • Slide-In replacement over two weekend nights • Traffic disruption on I-84 reduced from two years to two Saturday nights (20 hr closures). • Incentive/disincentive clause: $10,000 per hour for early or late completion ($50 K max incentive) • Eliminates need for a temporary bridge & cross-overs – over; $2 M savings. • Both slides completed within 10 months after NTP • Traffic detoured onto state Route 6 for 20 hrs.
  • 48. ABC Approach • Weekend Replacement • 20 Hr Closure
  • 49. Rapid Demolition – 4 Hrs • Chop and Drop • Local road below closed
  • 50. Superstructure Sections • Double T beams (NEXT) • Precast approach slabs • UHPC closure pour
  • 51. ABC Design - New Bridges • Single span 80’; three lanes at 12’ • Left shoulder 6’, right shoulder 12’ • Bridge width 33’-4” 57’-0” • Use of asphalt wearing surface eliminates grinding • Under passing Dingle Ridge Road on 16% grade • New bridges are two feet higher than the existing to provide 14’-6” under-clearance. • Minimize structure depth using double Tee sections
  • 52. Abutment Design Drilled shafts supporting cap beam T-Wall Cap Beam
  • 53. T-Wall Wingwalls Drilled Shafts Outside Existing Footprint
  • 56. Falsework Temporary Bents on H piles Contractor designed
  • 57. Slide Bearings Stainless Steel on Elastomeric Bearings w/PTFE PTFE bonded to Elastomeric Bearing
  • 59. Precast Approach Slabs Temporary End Spans Carrying Traffic
  • 61. Lateral Slide -- Oct 21 2013 7 hours to demolish bridge and slide-in new bridge
  • 62. Raising The Approaches • Takes time: Critical path for closure period
  • 63. Bridge Slides Completed 10 Months After NTP
  • 64.
  • 65. ABC Benefits • Road Closure will be significantly reduced from two construction seasons to two weekends. • Safety within the work zone will be improved. • Reduced Costs primarily by not building the crossovers and temporary bridge in the median ($2.0 M savings) • Impacts to the New York City watershed will be substantially reduced; at least 5 acres of land will not have to be disturbed using ABC. ABC is the clear choice
  • 66. Thank You for Attending Questions ?