SlideShare a Scribd company logo
M74 Motorway Completion - Scotland
• The M74 Completion scheme was a Design and Built Scheme and so design drawings
were issued in packages to suit a compressed programme where the design and
construction phases overlap
• Cat 3 Independent Design Check
• Used design codes: BS5400-4, BD37/01, BD21/01, TD19/06, BS6779 – 3 and 8500 -1
• Understood the principles of designing of RC concrete and prestressed concrete
structures
• Used design software: SuperSTRESS and SAM 2000
• liaised with geotechnical team and Introduced to geotechnical design principles
Glasgow Rd Underbridge
A three-span, 86m long, semi-integral bridge.
The bridge deck made of prestressed precast
U12 beams and an in-situ RC slab.
I designed the following elements:
•Pile caps
•Piers and abutments
•RC deck slab
•Prestressed beams
•Bearings for the abutments.
Farmeloan Rd Underbridge
A 58m long, three-span, integral bridge.
The deck is of prestressed precast concrete Y7
beams and an in-situ RC slab.
I designed the following elements:
•Created and analysed a 3D grillage model
using Super STRESS
•Piles and pile Caps
•Abutments and piers
•Prestressed beams
•RC Deck Slab and RC Parapet
•Diaphragm and Wing Walls.
Cambuslang Rd Underbridge
A 94.9m long, four-span, semi-integral bridge.
The superstructure consists of prestressed Y6
beams and a cast in-situ RC deck.
I designed the following elements:
•Piles and Pile Caps
•Abutments and Piers
•Prestressed beams
•RC Deck Slab and RC Parapet.
An example of Checkers Comments Sheet
Salford Meadows International Footbridge Design Competition
I took part in the international RIBA competition for the design of a new pedestrian bridge
across the River Irwell led by Salford City Council.
My team of 4 engineers developed a conceptual design of underslung cable truss bridge.
Out of 203 submissions our design reached Stage 2, the short listed four submissions.
The submission can still be viewed on RIBA Competition web site
http://www.ribacompetitions.com/salfordmeadowsbridge/shortlist.html
Design activities:
•Attended 3 day Lusas training course
•Undertaken an Initial dynamic analysis of behaviour of the structure to the moving and
pulsating pedestrian load
•I understood the basics of dynamic analysis.
•The bridge designed to carry 5kN/m2 crowd loading.
•The acceleration comfort criteria of the UK National Annex to Eurocode 1991-2
The following Engineering analysis work undertaken at competition stage.
I have created a 3D model of the bridge and completed preliminary static structural analysis
at Stages 1 of the competition, considering all the relevant load effects.
At Stage 2, I have additionally completed a preliminary dynamic analysis of the main span.
Several modes of the bridge had frequencies requiring further detailed consideration. For
these, I have undertaken a detailed time-history analysis, which showed that the bridge deck
accelerations satisfy the pedestrian comfort criteria.
Lancashire Bridge Assessment
• I have undertaken non intrusive Inspection For Assessment (dims, condition
survey and covemeter scan for reinforcement location)
• I produced Site Inspections method statements
• Produced a 3D space frame model using SuperSTRESS
• Carried out full structural assessment of the RC portal frame bridge.
• Section capacity checked using hand calculation methods as well as “SKALE”
design software.
• Example of 44t vehicle located on Portal 55 to gain Max Hogging moment.
• Bridge Assessment proved that the structure
can stand on its own but it is not able to
support any live loading including pedestrians.
•I have produced Assessment Report
recommending demolition of the bridge.
•Shortly after the Report, Stockport Council
decided to close the bridge for the traffic and
soon after that the bridge has been
demolished.
Marsh House Bridge
I have undertaken an initial hand calculation design of an abutment of a single leaf lifting
bridge carrying Marsh House Lane over the disused St Helen’s Canal. The deck was
hinged on the south side with hydraulic machinery in the designed box.
The box substructures consisted of reinforced concrete abutment founded on piles with
reinforced concrete canal walls approaching the abutments on both sides.
An extract from my design calculation
Red Brook Footbridge Refurbishment
• Assessed the bridge in accordance with
BS 5268 Part 2
• Produced Assessment Report
• Understood the principles of
permissible stress design of timber
structures,
• Understood different timber Strength
and service classes
• Produced Design, Specification and Bill
of Quantities for the bridge
refurbishment
• The following loadings have been used
during the design: 1.4kN/m load applied
to the top 1800mm high parapet to TD
19/06; 5kN/m2 footway loading to BD
37/01 and 8.12kN point load to The
British Horse Society Advice Note.
Specification and the Bill of Quantities
Dumvilles Brow Retaining Wall Strengthening
A hand sketch produced for the draughtsman
• Detailed design of strengthening of 3 No. masonry retaining walls supporting
highways.
• Wall A (8.0m high) – designed as reinforced concrete retaining wall. Due to
overturning and sliding instability the new wall was tied back to the existing
masonry wall and down to the rock foundation
• Wall B (5.5m high) – designed as brick wall fixed at the top to the RC stair case
and bottom to the bed rock. Also dowelled back in to the existing brick wall and to
the new adjacent RC L-shape wall.
• Wall C (4.0m high) – designed an underpinning for the foundation of wall that
showed signs of settlement. The underpinning in form of a series of pile caps
cantilevering under the wall. Wall B anchored to the staircase slab with series of
dowels.
• RC structures were designed using hand methods, however crack width and early
thermal cracking were checked using Excel spreadsheets.
• Progress control during construction
• Daily Site visits
• Dealing with site queries
• Producing clerk of works reports
• Undertaking CDM compliance checks
• Programme and quality control
Piccadilly Gardens Water Tank Replacement
• RC water tank design to BS EN 1992, 1997 and BD37/01
– Hand calculations using Two-way slab, fixed along all edges,
elastic analysis method.
– Self check using 3D space frame model analysis (SuperSTRESS
software).
• Coordination of information between disciplines
• Design team management
• Resource planning
• Close cooperation with Principal Designer (CDM 2015)
• Understood the relationship between engineers and draughtsmen team and how
to convey the information for good quality drawings
• Tender package preparation and submission
• Competitive tender evaluation
• Value engineering exercise
• Daily Site visits
• Dealing with site queries
• Programme, quality control and temporary works check against RAMS
• Approved Invoices and Interim Applications
• Precast Concrete Fabrication design calcs. and drawings check
• Understood the relationship between engineers and the contractors and
subcontractors
• Appreciated importance on temporary works and their impact of the
delivery/programme/design.
Hendham Vale Retaining wall Rebuild
• Produced the initial scheme design
• Detailed design of mass concrete retaining wall and scour protection works
• Coordination of information between disciplines
• Design team management
• Resource planning
• Tender package preparation and submission
• Competitive tender evaluation
• Programme and quality control
• Value engineering exercise
• Understood the principles of design for mass concrete structures
• Site supervision and dealing with Site Queries daily
• Chairing Progress Meetings on site
• Approved Invoices and Interim Applications
• Reviewing Contractors RAMS
Harpurhey Rd Reservoir Retaining Wall refurbishment
• Produced Bill of Quantities for initial scheme pricing and budget request
• Produced detailed design of water tight, sheet pile wall with RC pile
cap/walkway to BS EN 1993-5:2007 and BS EN 1992
• Cooperated with external companies for economic design
• Requested Ground investigation works (bore holes, chemical test for
hazardous waste, stats search)
• Japanese Knotweed management
• Tender package submission
• Competitive tender evaluation
• Value engineering exercise
• Understood the principles of design for steel sheet pile structures
• Site supervision and dealing with Site Queries daily
• Chairing Progress Meetings on site
• Approved Invoices and Interim Applications
• Reviewing Contractors RAMS
Linkedin Presentation Krysyian Gnysinski

More Related Content

What's hot

JAT4 Kick off Introduction - UAE Navy
JAT4 Kick off Introduction - UAE NavyJAT4 Kick off Introduction - UAE Navy
JAT4 Kick off Introduction - UAE NavyMike Bisland
 
Backlick Run Gravity Sewer Abandonment Project June 2020
Backlick Run Gravity Sewer Abandonment Project June 2020Backlick Run Gravity Sewer Abandonment Project June 2020
Backlick Run Gravity Sewer Abandonment Project June 2020
Fairfax County
 
Celedon Lane Virtual Community Meeting Slipline Replacement August 19, 2020
Celedon Lane Virtual Community Meeting Slipline Replacement August 19, 2020Celedon Lane Virtual Community Meeting Slipline Replacement August 19, 2020
Celedon Lane Virtual Community Meeting Slipline Replacement August 19, 2020
Fairfax County
 
Western Works Construction Liaison Committee Meeting - September 2017
Western Works Construction Liaison Committee Meeting - September 2017Western Works Construction Liaison Committee Meeting - September 2017
Western Works Construction Liaison Committee Meeting - September 2017
Crosstown TO
 
Laird Station Open House - April 2017
Laird Station Open House - April 2017Laird Station Open House - April 2017
Laird Station Open House - April 2017
Crosstown TO
 
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Crosstown TO
 
Stations Presentation - Corridor Wide
Stations Presentation - Corridor WideStations Presentation - Corridor Wide
Stations Presentation - Corridor Wide
Crosstown TO
 
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017
Crosstown TO
 
Chaplin - Avenue Construction Liaison Committee Meeting - June 2017
Chaplin - Avenue Construction Liaison Committee Meeting - June 2017Chaplin - Avenue Construction Liaison Committee Meeting - June 2017
Chaplin - Avenue Construction Liaison Committee Meeting - June 2017
Crosstown TO
 
Forest Hill Station Open House - June 2017
Forest Hill Station Open House - June 2017Forest Hill Station Open House - June 2017
Forest Hill Station Open House - June 2017
Crosstown TO
 
Avenue Station Open House - May 2017
Avenue Station Open House - May 2017Avenue Station Open House - May 2017
Avenue Station Open House - May 2017
Crosstown TO
 
Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017
Crosstown TO
 
Zach Maddox - CV 2016 May 01
Zach Maddox - CV 2016 May 01Zach Maddox - CV 2016 May 01
Zach Maddox - CV 2016 May 01Zachary Maddox
 
Caledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 finalCaledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 final
Crosstown TO
 
Difficult Run Force Main Rehabilitation
Difficult Run Force Main RehabilitationDifficult Run Force Main Rehabilitation
Difficult Run Force Main Rehabilitation
Fairfax County
 
Langley School Pump Station Community Meeting October 22, 2020
Langley School Pump Station Community Meeting October 22, 2020Langley School Pump Station Community Meeting October 22, 2020
Langley School Pump Station Community Meeting October 22, 2020
Fairfax County
 
Leaside - Laird Construction Liaison Committee Meeting - July 2017
Leaside - Laird Construction Liaison Committee Meeting  - July 2017Leaside - Laird Construction Liaison Committee Meeting  - July 2017
Leaside - Laird Construction Liaison Committee Meeting - July 2017
Crosstown TO
 
Eglinton Station Open House - March 2017
Eglinton Station Open House - March 2017Eglinton Station Open House - March 2017
Eglinton Station Open House - March 2017
Crosstown TO
 
Substantial completion flatlick branch iii stream restoration
Substantial completion   flatlick branch iii stream restorationSubstantial completion   flatlick branch iii stream restoration
Substantial completion flatlick branch iii stream restoration
Fairfax County
 

What's hot (20)

JAT4 Kick off Introduction - UAE Navy
JAT4 Kick off Introduction - UAE NavyJAT4 Kick off Introduction - UAE Navy
JAT4 Kick off Introduction - UAE Navy
 
Backlick Run Gravity Sewer Abandonment Project June 2020
Backlick Run Gravity Sewer Abandonment Project June 2020Backlick Run Gravity Sewer Abandonment Project June 2020
Backlick Run Gravity Sewer Abandonment Project June 2020
 
Celedon Lane Virtual Community Meeting Slipline Replacement August 19, 2020
Celedon Lane Virtual Community Meeting Slipline Replacement August 19, 2020Celedon Lane Virtual Community Meeting Slipline Replacement August 19, 2020
Celedon Lane Virtual Community Meeting Slipline Replacement August 19, 2020
 
Western Works Construction Liaison Committee Meeting - September 2017
Western Works Construction Liaison Committee Meeting - September 2017Western Works Construction Liaison Committee Meeting - September 2017
Western Works Construction Liaison Committee Meeting - September 2017
 
Dariush.resume
Dariush.resumeDariush.resume
Dariush.resume
 
Laird Station Open House - April 2017
Laird Station Open House - April 2017Laird Station Open House - April 2017
Laird Station Open House - April 2017
 
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
 
Stations Presentation - Corridor Wide
Stations Presentation - Corridor WideStations Presentation - Corridor Wide
Stations Presentation - Corridor Wide
 
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017
 
Chaplin - Avenue Construction Liaison Committee Meeting - June 2017
Chaplin - Avenue Construction Liaison Committee Meeting - June 2017Chaplin - Avenue Construction Liaison Committee Meeting - June 2017
Chaplin - Avenue Construction Liaison Committee Meeting - June 2017
 
Forest Hill Station Open House - June 2017
Forest Hill Station Open House - June 2017Forest Hill Station Open House - June 2017
Forest Hill Station Open House - June 2017
 
Avenue Station Open House - May 2017
Avenue Station Open House - May 2017Avenue Station Open House - May 2017
Avenue Station Open House - May 2017
 
Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017
 
Zach Maddox - CV 2016 May 01
Zach Maddox - CV 2016 May 01Zach Maddox - CV 2016 May 01
Zach Maddox - CV 2016 May 01
 
Caledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 finalCaledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 final
 
Difficult Run Force Main Rehabilitation
Difficult Run Force Main RehabilitationDifficult Run Force Main Rehabilitation
Difficult Run Force Main Rehabilitation
 
Langley School Pump Station Community Meeting October 22, 2020
Langley School Pump Station Community Meeting October 22, 2020Langley School Pump Station Community Meeting October 22, 2020
Langley School Pump Station Community Meeting October 22, 2020
 
Leaside - Laird Construction Liaison Committee Meeting - July 2017
Leaside - Laird Construction Liaison Committee Meeting  - July 2017Leaside - Laird Construction Liaison Committee Meeting  - July 2017
Leaside - Laird Construction Liaison Committee Meeting - July 2017
 
Eglinton Station Open House - March 2017
Eglinton Station Open House - March 2017Eglinton Station Open House - March 2017
Eglinton Station Open House - March 2017
 
Substantial completion flatlick branch iii stream restoration
Substantial completion   flatlick branch iii stream restorationSubstantial completion   flatlick branch iii stream restoration
Substantial completion flatlick branch iii stream restoration
 

Viewers also liked

имею право иметь права
имею право иметь праваимею право иметь права
Alexandra Knopp resume vitae
Alexandra Knopp resume vitaeAlexandra Knopp resume vitae
Alexandra Knopp resume vitaeAlexandra Knopp
 
AHundredFishinaTank-LolitaBeylina
AHundredFishinaTank-LolitaBeylinaAHundredFishinaTank-LolitaBeylina
AHundredFishinaTank-LolitaBeylinaLolita Beylina
 
La mirada pedagógica para el siglo xxi  teorías , temas y prácticas en cuesti...
La mirada pedagógica para el siglo xxi  teorías , temas y prácticas en cuesti...La mirada pedagógica para el siglo xxi  teorías , temas y prácticas en cuesti...
La mirada pedagógica para el siglo xxi  teorías , temas y prácticas en cuesti...
Andra Solanyi Bonilla Carabali
 
Spring essentials 2 Spring Series 02)
Spring essentials 2 Spring Series 02)Spring essentials 2 Spring Series 02)
Spring essentials 2 Spring Series 02)
Heartin Jacob
 
MEAN - A Stack That Drives Digital Transformation
MEAN - A Stack That Drives Digital TransformationMEAN - A Stack That Drives Digital Transformation
MEAN - A Stack That Drives Digital Transformation
JK Tech
 
Cyber Security for Digital-Era
Cyber Security for Digital-EraCyber Security for Digital-Era
Cyber Security for Digital-Era
JK Tech
 
Dilg memorandum circular no. 2016 116
Dilg memorandum circular no. 2016 116Dilg memorandum circular no. 2016 116
Dilg memorandum circular no. 2016 116
bituko butiki
 
License
LicenseLicense
License
Pekerja lepas
 
Cyber security threats for 2017
Cyber security threats for 2017Cyber security threats for 2017
Cyber security threats for 2017
Ramiro Cid
 

Viewers also liked (11)

имею право иметь права
имею право иметь праваимею право иметь права
имею право иметь права
 
Alexandra Knopp resume vitae
Alexandra Knopp resume vitaeAlexandra Knopp resume vitae
Alexandra Knopp resume vitae
 
AHundredFishinaTank-LolitaBeylina
AHundredFishinaTank-LolitaBeylinaAHundredFishinaTank-LolitaBeylina
AHundredFishinaTank-LolitaBeylina
 
La mirada pedagógica para el siglo xxi  teorías , temas y prácticas en cuesti...
La mirada pedagógica para el siglo xxi  teorías , temas y prácticas en cuesti...La mirada pedagógica para el siglo xxi  teorías , temas y prácticas en cuesti...
La mirada pedagógica para el siglo xxi  teorías , temas y prácticas en cuesti...
 
Spring essentials 2 Spring Series 02)
Spring essentials 2 Spring Series 02)Spring essentials 2 Spring Series 02)
Spring essentials 2 Spring Series 02)
 
CV-R.B.Guinir Jr.(01-15-17)
CV-R.B.Guinir Jr.(01-15-17)CV-R.B.Guinir Jr.(01-15-17)
CV-R.B.Guinir Jr.(01-15-17)
 
MEAN - A Stack That Drives Digital Transformation
MEAN - A Stack That Drives Digital TransformationMEAN - A Stack That Drives Digital Transformation
MEAN - A Stack That Drives Digital Transformation
 
Cyber Security for Digital-Era
Cyber Security for Digital-EraCyber Security for Digital-Era
Cyber Security for Digital-Era
 
Dilg memorandum circular no. 2016 116
Dilg memorandum circular no. 2016 116Dilg memorandum circular no. 2016 116
Dilg memorandum circular no. 2016 116
 
License
LicenseLicense
License
 
Cyber security threats for 2017
Cyber security threats for 2017Cyber security threats for 2017
Cyber security threats for 2017
 

Similar to Linkedin Presentation Krysyian Gnysinski

Washinton State University/Manchester Fuel Depot Senior Project
Washinton State University/Manchester Fuel Depot Senior ProjectWashinton State University/Manchester Fuel Depot Senior Project
Washinton State University/Manchester Fuel Depot Senior Project
WSUME_2013_A-TEAM
 
Ralls ncc meeting-san_antonio_04-01-09
Ralls ncc meeting-san_antonio_04-01-09Ralls ncc meeting-san_antonio_04-01-09
Ralls ncc meeting-san_antonio_04-01-09zaff69
 
accelerated bridge construction(ABC)
accelerated bridge construction(ABC)accelerated bridge construction(ABC)
accelerated bridge construction(ABC)
varun km
 
Arup Presentation Iqpc Warschau 03112010
Arup Presentation Iqpc Warschau 03112010Arup Presentation Iqpc Warschau 03112010
Arup Presentation Iqpc Warschau 03112010
Sander den Blanken
 
Chandler Geoff 2016 cv
Chandler Geoff 2016 cvChandler Geoff 2016 cv
Chandler Geoff 2016 cvGeoff Chandler
 
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinarNorth West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
Association for Project Management
 
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinarNorth West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
Association for Project Management
 
Aldar Headquarters Dubai
Aldar Headquarters DubaiAldar Headquarters Dubai
Aldar Headquarters Dubai
Neha Rampuria
 
UMAID IQBAL SEMINAR.pptx
UMAID IQBAL SEMINAR.pptxUMAID IQBAL SEMINAR.pptx
UMAID IQBAL SEMINAR.pptx
Praveendubey82
 
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVEMODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
Dr K M SONI
 
S S N PRASAD AKSHINTALA - CIVIL ME +4 YEARS EXP
S S N PRASAD AKSHINTALA - CIVIL ME +4 YEARS EXPS S N PRASAD AKSHINTALA - CIVIL ME +4 YEARS EXP
S S N PRASAD AKSHINTALA - CIVIL ME +4 YEARS EXPs s n prasad akshintala
 
No 1 Licensed structural auditor in Mumbai CSR consultant and associates
No 1 Licensed structural auditor in Mumbai CSR consultant and associatesNo 1 Licensed structural auditor in Mumbai CSR consultant and associates
No 1 Licensed structural auditor in Mumbai CSR consultant and associates
CSR Consultant and Associates
 
Bridges in Hilly areas seminar
Bridges in Hilly areas seminarBridges in Hilly areas seminar
Bridges in Hilly areas seminar
Abhinav Pateriya
 
Alberta Transportation's First Design-Build (DB) Project - Stony Plain Road I...
Alberta Transportation's First Design-Build (DB) Project - Stony Plain Road I...Alberta Transportation's First Design-Build (DB) Project - Stony Plain Road I...
Alberta Transportation's First Design-Build (DB) Project - Stony Plain Road I...
AamerShakoor
 
2018 general frc_2018_12
2018 general frc_2018_122018 general frc_2018_12
2018 general frc_2018_12
AsuSSEBENA
 
05 AASHTO Bridge Committee Awards Presentation
05 AASHTO Bridge Committee Awards Presentation05 AASHTO Bridge Committee Awards Presentation
05 AASHTO Bridge Committee Awards Presentation
AISC/NSBA
 
San Francisco Public Utilities Commission Headquarters
San Francisco Public Utilities Commission HeadquartersSan Francisco Public Utilities Commission Headquarters
San Francisco Public Utilities Commission Headquarters
PostTensioningInstitute
 
First Use Of Geosynthetic Reinforced Soil – Integrated Bridge System in Il...
First Use Of Geosynthetic Reinforced Soil – Integrated Bridge System in Il...First Use Of Geosynthetic Reinforced Soil – Integrated Bridge System in Il...
First Use Of Geosynthetic Reinforced Soil – Integrated Bridge System in Il...
thomas-engineering
 
Reinforcement of Driscoll Bridge
Reinforcement of Driscoll BridgeReinforcement of Driscoll Bridge
Reinforcement of Driscoll Bridge
PostTensioningInstitute
 

Similar to Linkedin Presentation Krysyian Gnysinski (20)

Washinton State University/Manchester Fuel Depot Senior Project
Washinton State University/Manchester Fuel Depot Senior ProjectWashinton State University/Manchester Fuel Depot Senior Project
Washinton State University/Manchester Fuel Depot Senior Project
 
Ralls ncc meeting-san_antonio_04-01-09
Ralls ncc meeting-san_antonio_04-01-09Ralls ncc meeting-san_antonio_04-01-09
Ralls ncc meeting-san_antonio_04-01-09
 
Resume
ResumeResume
Resume
 
accelerated bridge construction(ABC)
accelerated bridge construction(ABC)accelerated bridge construction(ABC)
accelerated bridge construction(ABC)
 
Arup Presentation Iqpc Warschau 03112010
Arup Presentation Iqpc Warschau 03112010Arup Presentation Iqpc Warschau 03112010
Arup Presentation Iqpc Warschau 03112010
 
Chandler Geoff 2016 cv
Chandler Geoff 2016 cvChandler Geoff 2016 cv
Chandler Geoff 2016 cv
 
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinarNorth West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
 
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinarNorth West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
 
Aldar Headquarters Dubai
Aldar Headquarters DubaiAldar Headquarters Dubai
Aldar Headquarters Dubai
 
UMAID IQBAL SEMINAR.pptx
UMAID IQBAL SEMINAR.pptxUMAID IQBAL SEMINAR.pptx
UMAID IQBAL SEMINAR.pptx
 
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVEMODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
 
S S N PRASAD AKSHINTALA - CIVIL ME +4 YEARS EXP
S S N PRASAD AKSHINTALA - CIVIL ME +4 YEARS EXPS S N PRASAD AKSHINTALA - CIVIL ME +4 YEARS EXP
S S N PRASAD AKSHINTALA - CIVIL ME +4 YEARS EXP
 
No 1 Licensed structural auditor in Mumbai CSR consultant and associates
No 1 Licensed structural auditor in Mumbai CSR consultant and associatesNo 1 Licensed structural auditor in Mumbai CSR consultant and associates
No 1 Licensed structural auditor in Mumbai CSR consultant and associates
 
Bridges in Hilly areas seminar
Bridges in Hilly areas seminarBridges in Hilly areas seminar
Bridges in Hilly areas seminar
 
Alberta Transportation's First Design-Build (DB) Project - Stony Plain Road I...
Alberta Transportation's First Design-Build (DB) Project - Stony Plain Road I...Alberta Transportation's First Design-Build (DB) Project - Stony Plain Road I...
Alberta Transportation's First Design-Build (DB) Project - Stony Plain Road I...
 
2018 general frc_2018_12
2018 general frc_2018_122018 general frc_2018_12
2018 general frc_2018_12
 
05 AASHTO Bridge Committee Awards Presentation
05 AASHTO Bridge Committee Awards Presentation05 AASHTO Bridge Committee Awards Presentation
05 AASHTO Bridge Committee Awards Presentation
 
San Francisco Public Utilities Commission Headquarters
San Francisco Public Utilities Commission HeadquartersSan Francisco Public Utilities Commission Headquarters
San Francisco Public Utilities Commission Headquarters
 
First Use Of Geosynthetic Reinforced Soil – Integrated Bridge System in Il...
First Use Of Geosynthetic Reinforced Soil – Integrated Bridge System in Il...First Use Of Geosynthetic Reinforced Soil – Integrated Bridge System in Il...
First Use Of Geosynthetic Reinforced Soil – Integrated Bridge System in Il...
 
Reinforcement of Driscoll Bridge
Reinforcement of Driscoll BridgeReinforcement of Driscoll Bridge
Reinforcement of Driscoll Bridge
 

Linkedin Presentation Krysyian Gnysinski

  • 1. M74 Motorway Completion - Scotland • The M74 Completion scheme was a Design and Built Scheme and so design drawings were issued in packages to suit a compressed programme where the design and construction phases overlap • Cat 3 Independent Design Check • Used design codes: BS5400-4, BD37/01, BD21/01, TD19/06, BS6779 – 3 and 8500 -1 • Understood the principles of designing of RC concrete and prestressed concrete structures • Used design software: SuperSTRESS and SAM 2000 • liaised with geotechnical team and Introduced to geotechnical design principles
  • 2. Glasgow Rd Underbridge A three-span, 86m long, semi-integral bridge. The bridge deck made of prestressed precast U12 beams and an in-situ RC slab. I designed the following elements: •Pile caps •Piers and abutments •RC deck slab •Prestressed beams •Bearings for the abutments.
  • 3. Farmeloan Rd Underbridge A 58m long, three-span, integral bridge. The deck is of prestressed precast concrete Y7 beams and an in-situ RC slab. I designed the following elements: •Created and analysed a 3D grillage model using Super STRESS •Piles and pile Caps •Abutments and piers •Prestressed beams •RC Deck Slab and RC Parapet •Diaphragm and Wing Walls.
  • 4. Cambuslang Rd Underbridge A 94.9m long, four-span, semi-integral bridge. The superstructure consists of prestressed Y6 beams and a cast in-situ RC deck. I designed the following elements: •Piles and Pile Caps •Abutments and Piers •Prestressed beams •RC Deck Slab and RC Parapet.
  • 5. An example of Checkers Comments Sheet
  • 6. Salford Meadows International Footbridge Design Competition I took part in the international RIBA competition for the design of a new pedestrian bridge across the River Irwell led by Salford City Council. My team of 4 engineers developed a conceptual design of underslung cable truss bridge. Out of 203 submissions our design reached Stage 2, the short listed four submissions. The submission can still be viewed on RIBA Competition web site http://www.ribacompetitions.com/salfordmeadowsbridge/shortlist.html
  • 7.
  • 8. Design activities: •Attended 3 day Lusas training course •Undertaken an Initial dynamic analysis of behaviour of the structure to the moving and pulsating pedestrian load •I understood the basics of dynamic analysis. •The bridge designed to carry 5kN/m2 crowd loading. •The acceleration comfort criteria of the UK National Annex to Eurocode 1991-2 The following Engineering analysis work undertaken at competition stage. I have created a 3D model of the bridge and completed preliminary static structural analysis at Stages 1 of the competition, considering all the relevant load effects. At Stage 2, I have additionally completed a preliminary dynamic analysis of the main span. Several modes of the bridge had frequencies requiring further detailed consideration. For these, I have undertaken a detailed time-history analysis, which showed that the bridge deck accelerations satisfy the pedestrian comfort criteria.
  • 9. Lancashire Bridge Assessment • I have undertaken non intrusive Inspection For Assessment (dims, condition survey and covemeter scan for reinforcement location) • I produced Site Inspections method statements • Produced a 3D space frame model using SuperSTRESS • Carried out full structural assessment of the RC portal frame bridge. • Section capacity checked using hand calculation methods as well as “SKALE” design software.
  • 10. • Example of 44t vehicle located on Portal 55 to gain Max Hogging moment.
  • 11. • Bridge Assessment proved that the structure can stand on its own but it is not able to support any live loading including pedestrians. •I have produced Assessment Report recommending demolition of the bridge. •Shortly after the Report, Stockport Council decided to close the bridge for the traffic and soon after that the bridge has been demolished.
  • 12. Marsh House Bridge I have undertaken an initial hand calculation design of an abutment of a single leaf lifting bridge carrying Marsh House Lane over the disused St Helen’s Canal. The deck was hinged on the south side with hydraulic machinery in the designed box. The box substructures consisted of reinforced concrete abutment founded on piles with reinforced concrete canal walls approaching the abutments on both sides.
  • 13. An extract from my design calculation
  • 14.
  • 15. Red Brook Footbridge Refurbishment
  • 16. • Assessed the bridge in accordance with BS 5268 Part 2 • Produced Assessment Report • Understood the principles of permissible stress design of timber structures, • Understood different timber Strength and service classes • Produced Design, Specification and Bill of Quantities for the bridge refurbishment • The following loadings have been used during the design: 1.4kN/m load applied to the top 1800mm high parapet to TD 19/06; 5kN/m2 footway loading to BD 37/01 and 8.12kN point load to The British Horse Society Advice Note.
  • 17. Specification and the Bill of Quantities
  • 18. Dumvilles Brow Retaining Wall Strengthening
  • 19.
  • 20. A hand sketch produced for the draughtsman
  • 21.
  • 22. • Detailed design of strengthening of 3 No. masonry retaining walls supporting highways. • Wall A (8.0m high) – designed as reinforced concrete retaining wall. Due to overturning and sliding instability the new wall was tied back to the existing masonry wall and down to the rock foundation • Wall B (5.5m high) – designed as brick wall fixed at the top to the RC stair case and bottom to the bed rock. Also dowelled back in to the existing brick wall and to the new adjacent RC L-shape wall. • Wall C (4.0m high) – designed an underpinning for the foundation of wall that showed signs of settlement. The underpinning in form of a series of pile caps cantilevering under the wall. Wall B anchored to the staircase slab with series of dowels. • RC structures were designed using hand methods, however crack width and early thermal cracking were checked using Excel spreadsheets. • Progress control during construction • Daily Site visits • Dealing with site queries • Producing clerk of works reports • Undertaking CDM compliance checks • Programme and quality control
  • 23. Piccadilly Gardens Water Tank Replacement
  • 24.
  • 25. • RC water tank design to BS EN 1992, 1997 and BD37/01 – Hand calculations using Two-way slab, fixed along all edges, elastic analysis method. – Self check using 3D space frame model analysis (SuperSTRESS software). • Coordination of information between disciplines • Design team management • Resource planning • Close cooperation with Principal Designer (CDM 2015) • Understood the relationship between engineers and draughtsmen team and how to convey the information for good quality drawings • Tender package preparation and submission • Competitive tender evaluation • Value engineering exercise • Daily Site visits • Dealing with site queries • Programme, quality control and temporary works check against RAMS • Approved Invoices and Interim Applications • Precast Concrete Fabrication design calcs. and drawings check • Understood the relationship between engineers and the contractors and subcontractors • Appreciated importance on temporary works and their impact of the delivery/programme/design.
  • 26.
  • 27.
  • 28.
  • 29. Hendham Vale Retaining wall Rebuild
  • 30. • Produced the initial scheme design • Detailed design of mass concrete retaining wall and scour protection works • Coordination of information between disciplines • Design team management • Resource planning • Tender package preparation and submission • Competitive tender evaluation • Programme and quality control • Value engineering exercise • Understood the principles of design for mass concrete structures • Site supervision and dealing with Site Queries daily • Chairing Progress Meetings on site • Approved Invoices and Interim Applications • Reviewing Contractors RAMS
  • 31.
  • 32. Harpurhey Rd Reservoir Retaining Wall refurbishment
  • 33. • Produced Bill of Quantities for initial scheme pricing and budget request • Produced detailed design of water tight, sheet pile wall with RC pile cap/walkway to BS EN 1993-5:2007 and BS EN 1992 • Cooperated with external companies for economic design • Requested Ground investigation works (bore holes, chemical test for hazardous waste, stats search) • Japanese Knotweed management • Tender package submission • Competitive tender evaluation • Value engineering exercise • Understood the principles of design for steel sheet pile structures • Site supervision and dealing with Site Queries daily • Chairing Progress Meetings on site • Approved Invoices and Interim Applications • Reviewing Contractors RAMS