SlideShare a Scribd company logo
1 of 26
Download to read offline
Evaluation of
Large Standby Power System
Architectures
As facility power needs get very large, what’s the best
design for optimum reliability?
2
Agenda
Current Trends on Data Centers Design
Reliability Indicators
Overview of System Designs
Lessons Learned
Conclusions and Take-aways
3
Data Center Power System Designs
Huge variety of designs
– Simple Systems - Single genset and transfer switches
• Bypass/Isolation and closed transition options
– Paralleling with ATS
– Paralleling with Power Transfer, Bus Ties
– Other variations (Swing generators)
Systems becoming very large (>100MW in many sites)
– 1GW in the future?
High speed diesel gensets still most common choice: lowest
cost/kW, fast starting, local fuel supply, stable, easy to service
Tendency for Redundant and Modular Systems
4
Big is not necessarily complex…
Long Island Power Demand Response Site
– 48MW, each machine individually paralleled to grid, controlled by SCADA software
– Emissions compliant
– No switchgear or additional controls required
5
Reliability Indicators
MTBF goes up with hours of successful operation of a specific design
– New designs are hard to evaluate
• New logic reliability
• Hidden Flaws
• Failure Mode Effects
– Common Assumptions: Avoid Single Points of Failure
• But are all failure points equal?
• Generator single points of failure; Redundancy
– Prototype Testing Impact (ref: NFPA110)
– Number of systems in service
Impact of Number of Components on overall reliability
PowerCommand Genset Control Example
– 150K MTBF at launch in 1994
• Thousands of hours of development
• Thousands of hours of testing
• Hundreds of hours at seed sites
– After 15 years of service: >1 M MTBF
Easier to be confident in a design that is proven over time
6
A GOOD QUESTION
OK, it’s easy to see that reliability is positively
impacted by consistent quality control on a lot of
widgits,
but how do we deal with large, complex “one of a
kind” systems?
7
Simplest Designs
Genset with one or more ATS
– Best for smaller projects
– Can be multiplied for larger projects
Genset operating power transfer
breaker pair
– Best for larger generators, switching
near service
– Lowest cost, smallest footprint
– Can synchronize and ramp loads
between live sources
– Breakers can trip, so need to deal
with that logically
– Can be multiplied for any size
project
When used in multiples, each
genset/transfer equipment has single
points of failure, but only part of
system fails
8
Paralleling Applications
Paralleling functions are the same on every project
Generator set paralleling functions commonly integrated
– No/very limited switchgear space for separate control equipment
– Dedicated purpose controllers with firmware rather than PLC-based or
component functions
9
Parallel Applications
Paralleling Systems Utilize Major
Control Blocks with Common Functions
– Parallel Controllers (PLL)
• Start/Stop/Protect Genset
• Black Start Control
• Synchronize
• Load Share
• Bus Protection
– Transfer Controllers (ATS)
• Source Availability
• Transfer Logic
– System Control
• System monitoring
• Load Management (load add/shed)
• Capacity Management (load demand)
Distributed Logic Strategy
Design Control
– “One Throat to Choke”
10
Isolated Bus Master Control Functions
Load Management (load add & shed sequence)
– Back-up for overide of automatic sequence
– Controls feeder breakers, ATS, or interface to BMS
System Capacity (load demand)
– Provides means of minimizing fuel consumption in long runs
Local Operator Interface
– What do you want the operator to do? Where?
Remote Monitor & Control
Digital Control
11
Remote Monitoring & Control
! "# $
$
%
& $' ()
*
! "# $
$
%
& $' ()
*
%
Multiple Networks/Multiple Uses
– Isolated for speed, ease of installation
Remote Monitoring is Very Common
– Tons of data and control is available
12
More Complex Designs
“Main-tie-Main” Configuration
Service issues due to gensets on common bus with
utility
Logic Variations due to automated tie can be
problematic
13
More Complex Designs
%
A combination of core paralleling and power transfer control
blocks
May have many generators and many transfer pairs
Common to have multiple feeds to downstream devices
Usually includes a central monitoring system for entire
package
14
Impact of Automated Ties
Automating Tie
operation
complicates design
Best accomplished
with core controls,
orchestrated with
PLC
Best practice is
to exercise
design control
on PLC logic
“modules”
15
More Examples
Most designs use many core functions
PARALLELING
POWER TRANSFER
SUPERVISORY
16
Tier 3 Data Center Design
More duplicated functions…
PARALLELING
PWR TRANS
17
Lessons Learned:
Effective Use of Redundancy
Single points of failure have a big impact on
reliability
Address by:
– Design it out
– True Redundancy
– Live with it/Best Quality
Genset Example
MasterControl Example
18
Lessons Learned:
Support for Complex Systems
Look for ability to have support local to the project site
– Local support should be equipped with software necessary for
PLC and HMI (if different)
– Training is critical
Consider ability to support the PLC and HMI and other
controls’ software in the future
– 30-year life is not unexpected at many sites
– Vendors’ commitment to backward compatibility
• This capability varies with vendor
– Number of software sets needed for total service is a major
concern over time
19
Lessons Learned:
Hot Standby (Vendor 1) + Hot Standby (Vendor 2)
What does “Redundant PLC” mean?
– Redundant Processor? Redundant I/O? Redundant Power
Supply? Redundant Power Supply Bus? Redundant Coms
Links?
Hot Standby practices can significantly impact PLC operation
time (responsiveness)
– Impact on display responsiveness
– Operation time for critical functions
Capabilities of each PLC/Touchscreen differ by vendor
– Every system supplier standardizes on specific vendors, and has
limited flexibility to use others
20
Lessons Learned:
On-going Operator Instruction & Training
Posted Manual Operation Instructions
– Consider all critical operations,
• power transfer from utility to gensets and return
• gensets on and off bus (if paralleled)
• manual load add and shed
Pay Attention to Operator Panel Information
– What are operator capabilities?
– What do you want them to do?
– Where do you want them to do it?
21
Conclusions
There’s a lot of wisdom in the first rule of
engineering: KISS
BUT, we are dealing with complicated facilities and
demanding performance requirements
Use Distributed Logic Strategy
Make sure of support plan in the long run
Keep learning from experience
22
Utility Paralleling
Connected to Utility
kW/kVar level
23
Product Configurations
Cummins Caterpillar/Asco4000 Generac
This slide shows the genset and paralleling control functions for
different suppliers
Cat/Asco/Generac all have 6-8 level load add/shed and load demand
in their arrangement
– Most global control competitors use the Cat/Asco model, except SDMO
24
Cummins Paralleling Topology
Typical Isolated Bus architecture
25
Typical Isolated Bus Architecture
Caterpillar shown, Asco, many others similar
Others…
26
CPG Interconnect Block Diagram
AC for accessories
Status to Master
Breaker Commands
Breaker Status
Power Conductors

More Related Content

What's hot

Typical layout of a Sub-Station
Typical layout of a Sub-StationTypical layout of a Sub-Station
Typical layout of a Sub-StationTowfiqur Rahman
 
ETAP - Short circuit analysis iec standard
ETAP - Short circuit analysis iec standardETAP - Short circuit analysis iec standard
ETAP - Short circuit analysis iec standardHimmelstern
 
Blackout Avoidance & Undervoltage Load Shedding
Blackout Avoidance & Undervoltage Load SheddingBlackout Avoidance & Undervoltage Load Shedding
Blackout Avoidance & Undervoltage Load Sheddingmichaeljmack
 
Generator Set Transient Performance
Generator Set Transient PerformanceGenerator Set Transient Performance
Generator Set Transient Performancemichaeljmack
 
Solar PV Codes and Standards
Solar PV Codes and StandardsSolar PV Codes and Standards
Solar PV Codes and StandardsSolar Reference
 
TESTING AND COMMISSIONING OF ELECTRICAL EQUIPMENTS. TESTING OF CURRENT TRANSF...
TESTING AND COMMISSIONING OF ELECTRICAL EQUIPMENTS. TESTING OF CURRENT TRANSF...TESTING AND COMMISSIONING OF ELECTRICAL EQUIPMENTS. TESTING OF CURRENT TRANSF...
TESTING AND COMMISSIONING OF ELECTRICAL EQUIPMENTS. TESTING OF CURRENT TRANSF...Jobin Abraham
 
Lv switchgear & lv cable sizing
Lv switchgear & lv cable sizingLv switchgear & lv cable sizing
Lv switchgear & lv cable sizingAsif Eqbal
 
Power System Control
Power System ControlPower System Control
Power System ControlRidwanul Hoque
 
Principles and Design of LV System
Principles and Design of LV SystemPrinciples and Design of LV System
Principles and Design of LV SystemYE MYO
 
Load forecasting
Load forecastingLoad forecasting
Load forecastingsushrut p
 
Ehv substation
Ehv substationEhv substation
Ehv substationDemsew Mitiku
 
Generator Protection Relay Setting Calculations
Generator Protection Relay Setting CalculationsGenerator Protection Relay Setting Calculations
Generator Protection Relay Setting CalculationsPower System Operation
 
Factors to be considered while selecting CT
Factors to be considered while selecting CTFactors to be considered while selecting CT
Factors to be considered while selecting CTParth Patel
 
ETAP - Coordination and protecion 2
ETAP -  Coordination and protecion 2ETAP -  Coordination and protecion 2
ETAP - Coordination and protecion 2Himmelstern
 
Generator Protection
Generator ProtectionGenerator Protection
Generator ProtectionPriten Vasa
 
Electrical grounding and earthing systems
Electrical grounding and earthing systemsElectrical grounding and earthing systems
Electrical grounding and earthing systemsBiswajit Pratihari
 

What's hot (20)

Typical layout of a Sub-Station
Typical layout of a Sub-StationTypical layout of a Sub-Station
Typical layout of a Sub-Station
 
ETAP - Short circuit analysis iec standard
ETAP - Short circuit analysis iec standardETAP - Short circuit analysis iec standard
ETAP - Short circuit analysis iec standard
 
Blackout Avoidance & Undervoltage Load Shedding
Blackout Avoidance & Undervoltage Load SheddingBlackout Avoidance & Undervoltage Load Shedding
Blackout Avoidance & Undervoltage Load Shedding
 
Generator Set Transient Performance
Generator Set Transient PerformanceGenerator Set Transient Performance
Generator Set Transient Performance
 
Solar PV Codes and Standards
Solar PV Codes and StandardsSolar PV Codes and Standards
Solar PV Codes and Standards
 
TESTING AND COMMISSIONING OF ELECTRICAL EQUIPMENTS. TESTING OF CURRENT TRANSF...
TESTING AND COMMISSIONING OF ELECTRICAL EQUIPMENTS. TESTING OF CURRENT TRANSF...TESTING AND COMMISSIONING OF ELECTRICAL EQUIPMENTS. TESTING OF CURRENT TRANSF...
TESTING AND COMMISSIONING OF ELECTRICAL EQUIPMENTS. TESTING OF CURRENT TRANSF...
 
Lv switchgear & lv cable sizing
Lv switchgear & lv cable sizingLv switchgear & lv cable sizing
Lv switchgear & lv cable sizing
 
Power System Control
Power System ControlPower System Control
Power System Control
 
Principles and Design of LV System
Principles and Design of LV SystemPrinciples and Design of LV System
Principles and Design of LV System
 
Load forecasting
Load forecastingLoad forecasting
Load forecasting
 
2. genset ratings (3)
2. genset ratings (3)2. genset ratings (3)
2. genset ratings (3)
 
Introduction to mv switchgear
Introduction to mv switchgearIntroduction to mv switchgear
Introduction to mv switchgear
 
GIS 400kv substation
GIS  400kv substationGIS  400kv substation
GIS 400kv substation
 
Ehv substation
Ehv substationEhv substation
Ehv substation
 
Generator Protection Relay Setting Calculations
Generator Protection Relay Setting CalculationsGenerator Protection Relay Setting Calculations
Generator Protection Relay Setting Calculations
 
Factors to be considered while selecting CT
Factors to be considered while selecting CTFactors to be considered while selecting CT
Factors to be considered while selecting CT
 
Protection and Switchgear
Protection and SwitchgearProtection and Switchgear
Protection and Switchgear
 
ETAP - Coordination and protecion 2
ETAP -  Coordination and protecion 2ETAP -  Coordination and protecion 2
ETAP - Coordination and protecion 2
 
Generator Protection
Generator ProtectionGenerator Protection
Generator Protection
 
Electrical grounding and earthing systems
Electrical grounding and earthing systemsElectrical grounding and earthing systems
Electrical grounding and earthing systems
 

Viewers also liked

ATS, Grounding Issues & Installation Considerations
ATS, Grounding Issues & Installation ConsiderationsATS, Grounding Issues & Installation Considerations
ATS, Grounding Issues & Installation Considerationsmichaeljmack
 
Global mkt this is cpg - final extended version - april2013
Global mkt   this is cpg - final extended version - april2013Global mkt   this is cpg - final extended version - april2013
Global mkt this is cpg - final extended version - april2013Cummins Power Generation
 
This is Cummins Power Generation 2011
This is Cummins Power Generation 2011This is Cummins Power Generation 2011
This is Cummins Power Generation 2011Cummins Power Generation
 
LTE Testing | 4G Testing
LTE Testing | 4G TestingLTE Testing | 4G Testing
LTE Testing | 4G TestingIxia
 
Ats powerpoint presentation
Ats powerpoint presentationAts powerpoint presentation
Ats powerpoint presentationatsops
 
Critical power: Transfer switches and switchgear
Critical power: Transfer switches and switchgearCritical power: Transfer switches and switchgear
Critical power: Transfer switches and switchgearConsultingSpecifyingEngineer
 
Cummins Customer Engineering Presentation
Cummins Customer Engineering PresentationCummins Customer Engineering Presentation
Cummins Customer Engineering PresentationDibyajyoti Laha
 
Cummins Marketing
Cummins MarketingCummins Marketing
Cummins MarketingStuart Joy
 
Basic gsm principles
Basic gsm principlesBasic gsm principles
Basic gsm principlesSupper Mario
 
Automatic transfer switch (ats)
Automatic transfer switch (ats)Automatic transfer switch (ats)
Automatic transfer switch (ats)Mark Anthony Enoy
 
GSM, Cell Planning & Frequency Reuse
GSM, Cell Planning & Frequency ReuseGSM, Cell Planning & Frequency Reuse
GSM, Cell Planning & Frequency Reusesanjida2222
 
The cellular concept
The cellular conceptThe cellular concept
The cellular conceptZunAib Ali
 
Gsm channel calculations
Gsm channel calculationsGsm channel calculations
Gsm channel calculationsAlthaf Hussain
 
cellular ppt
cellular pptcellular ppt
cellular pptDivya Bansal
 
Presentation Rf Optimization And Planning
Presentation  Rf Optimization And PlanningPresentation  Rf Optimization And Planning
Presentation Rf Optimization And PlanningUmmaarraa Raa
 
Lte drive test parameter introduction
Lte drive test parameter introductionLte drive test parameter introduction
Lte drive test parameter introductionRay KHASTUR
 
Huawei - Access failures troubleshooting work shop
Huawei - Access failures troubleshooting work shopHuawei - Access failures troubleshooting work shop
Huawei - Access failures troubleshooting work shopnavaidkhan
 

Viewers also liked (20)

ATS, Grounding Issues & Installation Considerations
ATS, Grounding Issues & Installation ConsiderationsATS, Grounding Issues & Installation Considerations
ATS, Grounding Issues & Installation Considerations
 
Global mkt this is cpg - final extended version - april2013
Global mkt   this is cpg - final extended version - april2013Global mkt   this is cpg - final extended version - april2013
Global mkt this is cpg - final extended version - april2013
 
This is Cummins Power Generation 2011
This is Cummins Power Generation 2011This is Cummins Power Generation 2011
This is Cummins Power Generation 2011
 
LTE Testing | 4G Testing
LTE Testing | 4G TestingLTE Testing | 4G Testing
LTE Testing | 4G Testing
 
Ats powerpoint presentation
Ats powerpoint presentationAts powerpoint presentation
Ats powerpoint presentation
 
Critical power: Transfer switches and switchgear
Critical power: Transfer switches and switchgearCritical power: Transfer switches and switchgear
Critical power: Transfer switches and switchgear
 
LTE Measurement: How to test a device
LTE Measurement: How to test a deviceLTE Measurement: How to test a device
LTE Measurement: How to test a device
 
Cummins Customer Engineering Presentation
Cummins Customer Engineering PresentationCummins Customer Engineering Presentation
Cummins Customer Engineering Presentation
 
Cummins Marketing
Cummins MarketingCummins Marketing
Cummins Marketing
 
Basic gsm principles
Basic gsm principlesBasic gsm principles
Basic gsm principles
 
Automatic transfer switch (ats)
Automatic transfer switch (ats)Automatic transfer switch (ats)
Automatic transfer switch (ats)
 
GSM, Cell Planning & Frequency Reuse
GSM, Cell Planning & Frequency ReuseGSM, Cell Planning & Frequency Reuse
GSM, Cell Planning & Frequency Reuse
 
The cellular concept
The cellular conceptThe cellular concept
The cellular concept
 
Gsm channel calculations
Gsm channel calculationsGsm channel calculations
Gsm channel calculations
 
cellular ppt
cellular pptcellular ppt
cellular ppt
 
Presentation Rf Optimization And Planning
Presentation  Rf Optimization And PlanningPresentation  Rf Optimization And Planning
Presentation Rf Optimization And Planning
 
GSM channels
GSM channelsGSM channels
GSM channels
 
Lte drive test parameter introduction
Lte drive test parameter introductionLte drive test parameter introduction
Lte drive test parameter introduction
 
Umts Kpi
Umts KpiUmts Kpi
Umts Kpi
 
Huawei - Access failures troubleshooting work shop
Huawei - Access failures troubleshooting work shopHuawei - Access failures troubleshooting work shop
Huawei - Access failures troubleshooting work shop
 

Similar to Evaluation of standby power system architectures

The Challenges and Solutions to Integrate Multi-Facility/Buildings Disparate ...
The Challenges and Solutions to Integrate Multi-Facility/Buildings Disparate ...The Challenges and Solutions to Integrate Multi-Facility/Buildings Disparate ...
The Challenges and Solutions to Integrate Multi-Facility/Buildings Disparate ...Schneider Electric
 
Smarter Grid Solutions Company Overview
Smarter Grid Solutions Company OverviewSmarter Grid Solutions Company Overview
Smarter Grid Solutions Company OverviewSmarter Grid Solutions
 
Four Ways to Improve Linux Performance IEEE Webinar, R2.0
Four Ways to Improve Linux Performance IEEE Webinar, R2.0Four Ways to Improve Linux Performance IEEE Webinar, R2.0
Four Ways to Improve Linux Performance IEEE Webinar, R2.0Michael Christofferson
 
System on Chip Based RTC in Power Electronics
System on Chip Based RTC in Power ElectronicsSystem on Chip Based RTC in Power Electronics
System on Chip Based RTC in Power ElectronicsjournalBEEI
 
TRAINING REPORT ON INDUSTRIAL AUTOMATION- PLC SCADA, VARIABLE FREQUENCY DRIVE
TRAINING REPORT ON INDUSTRIAL AUTOMATION- PLC SCADA, VARIABLE FREQUENCY DRIVETRAINING REPORT ON INDUSTRIAL AUTOMATION- PLC SCADA, VARIABLE FREQUENCY DRIVE
TRAINING REPORT ON INDUSTRIAL AUTOMATION- PLC SCADA, VARIABLE FREQUENCY DRIVEAKSHAY SACHAN
 
Embedded system.pptx
Embedded system.pptxEmbedded system.pptx
Embedded system.pptxSaransh Garg
 
Basic Control System unit5
Basic Control System unit5Basic Control System unit5
Basic Control System unit5Asraf Malik
 
6dec2011 - Power Back-up_1
6dec2011 - Power Back-up_16dec2011 - Power Back-up_1
6dec2011 - Power Back-up_1Agora Group
 
Driving Forces and Key Benefits of Control System Migrations
Driving Forces and Key Benefits of Control System MigrationsDriving Forces and Key Benefits of Control System Migrations
Driving Forces and Key Benefits of Control System MigrationsOptima Control Solutions
 
PLC SCADA report Paras Singhal
PLC SCADA report Paras SinghalPLC SCADA report Paras Singhal
PLC SCADA report Paras SinghalPARAS SINGHAL
 
DeployingAnAdvancedDistribution.pdf
DeployingAnAdvancedDistribution.pdfDeployingAnAdvancedDistribution.pdf
DeployingAnAdvancedDistribution.pdfbayu162365
 
Parallex - The Supercomputer
Parallex - The SupercomputerParallex - The Supercomputer
Parallex - The SupercomputerAnkit Singh
 
Rapid Control Prototyping Solutions
Rapid Control Prototyping SolutionsRapid Control Prototyping Solutions
Rapid Control Prototyping SolutionsOPAL-RT TECHNOLOGIES
 

Similar to Evaluation of standby power system architectures (20)

The Challenges and Solutions to Integrate Multi-Facility/Buildings Disparate ...
The Challenges and Solutions to Integrate Multi-Facility/Buildings Disparate ...The Challenges and Solutions to Integrate Multi-Facility/Buildings Disparate ...
The Challenges and Solutions to Integrate Multi-Facility/Buildings Disparate ...
 
Smarter Grid Solutions Company Overview
Smarter Grid Solutions Company OverviewSmarter Grid Solutions Company Overview
Smarter Grid Solutions Company Overview
 
Four Ways to Improve Linux Performance IEEE Webinar, R2.0
Four Ways to Improve Linux Performance IEEE Webinar, R2.0Four Ways to Improve Linux Performance IEEE Webinar, R2.0
Four Ways to Improve Linux Performance IEEE Webinar, R2.0
 
Lectrue 1.pptx
Lectrue 1.pptxLectrue 1.pptx
Lectrue 1.pptx
 
System on Chip Based RTC in Power Electronics
System on Chip Based RTC in Power ElectronicsSystem on Chip Based RTC in Power Electronics
System on Chip Based RTC in Power Electronics
 
Lect01
Lect01Lect01
Lect01
 
lect 01 (1).pdf
lect 01 (1).pdflect 01 (1).pdf
lect 01 (1).pdf
 
TRAINING REPORT ON INDUSTRIAL AUTOMATION- PLC SCADA, VARIABLE FREQUENCY DRIVE
TRAINING REPORT ON INDUSTRIAL AUTOMATION- PLC SCADA, VARIABLE FREQUENCY DRIVETRAINING REPORT ON INDUSTRIAL AUTOMATION- PLC SCADA, VARIABLE FREQUENCY DRIVE
TRAINING REPORT ON INDUSTRIAL AUTOMATION- PLC SCADA, VARIABLE FREQUENCY DRIVE
 
Training 17
Training 17Training 17
Training 17
 
Embedded system.pptx
Embedded system.pptxEmbedded system.pptx
Embedded system.pptx
 
Basic Control System unit5
Basic Control System unit5Basic Control System unit5
Basic Control System unit5
 
6dec2011 - Power Back-up_1
6dec2011 - Power Back-up_16dec2011 - Power Back-up_1
6dec2011 - Power Back-up_1
 
Driving Forces and Key Benefits of Control System Migrations
Driving Forces and Key Benefits of Control System MigrationsDriving Forces and Key Benefits of Control System Migrations
Driving Forces and Key Benefits of Control System Migrations
 
Plc basics
Plc   basicsPlc   basics
Plc basics
 
PLC SCADA report Paras Singhal
PLC SCADA report Paras SinghalPLC SCADA report Paras Singhal
PLC SCADA report Paras Singhal
 
Intro720T5.pptx
Intro720T5.pptxIntro720T5.pptx
Intro720T5.pptx
 
DeployingAnAdvancedDistribution.pdf
DeployingAnAdvancedDistribution.pdfDeployingAnAdvancedDistribution.pdf
DeployingAnAdvancedDistribution.pdf
 
Computer Application in Power system chapter one - introduction
Computer Application in Power system chapter one - introductionComputer Application in Power system chapter one - introduction
Computer Application in Power system chapter one - introduction
 
Parallex - The Supercomputer
Parallex - The SupercomputerParallex - The Supercomputer
Parallex - The Supercomputer
 
Rapid Control Prototyping Solutions
Rapid Control Prototyping SolutionsRapid Control Prototyping Solutions
Rapid Control Prototyping Solutions
 

More from michaeljmack

Auburn, NY - 200 Years of History 1793-1993
Auburn, NY - 200 Years of History  1793-1993Auburn, NY - 200 Years of History  1793-1993
Auburn, NY - 200 Years of History 1793-1993michaeljmack
 
Auburn High School, Auburn, NY, 1982 Yearbook
Auburn High School, Auburn, NY, 1982 YearbookAuburn High School, Auburn, NY, 1982 Yearbook
Auburn High School, Auburn, NY, 1982 Yearbookmichaeljmack
 
Auburn High School, Auburn, NY, 1980 Yearbook
Auburn High School, Auburn, NY, 1980 YearbookAuburn High School, Auburn, NY, 1980 Yearbook
Auburn High School, Auburn, NY, 1980 Yearbookmichaeljmack
 
Surge Protection
Surge ProtectionSurge Protection
Surge Protectionmichaeljmack
 
Diesel Particulate Filters Control Systems
Diesel Particulate Filters Control SystemsDiesel Particulate Filters Control Systems
Diesel Particulate Filters Control Systemsmichaeljmack
 
Understanding Arc Flash
Understanding Arc FlashUnderstanding Arc Flash
Understanding Arc Flashmichaeljmack
 
Siemens MV GIS Switchgear
Siemens MV GIS SwitchgearSiemens MV GIS Switchgear
Siemens MV GIS Switchgearmichaeljmack
 
Fundamentals of transformer inrush
Fundamentals of transformer inrushFundamentals of transformer inrush
Fundamentals of transformer inrushmichaeljmack
 
Building information modeling
Building information modelingBuilding information modeling
Building information modelingmichaeljmack
 
15 years of experience stator ground fault protection
15 years of experience stator ground fault protection15 years of experience stator ground fault protection
15 years of experience stator ground fault protectionmichaeljmack
 
Emergency, Legally Required and Optional Standby Systems
Emergency, Legally Required and Optional Standby SystemsEmergency, Legally Required and Optional Standby Systems
Emergency, Legally Required and Optional Standby Systemsmichaeljmack
 
Lighting Control Solutions for Daylit Spaces
Lighting Control Solutions for Daylit SpacesLighting Control Solutions for Daylit Spaces
Lighting Control Solutions for Daylit Spacesmichaeljmack
 
COPS: An Arresting Look at NEC Article 708
COPS: An Arresting Look at NEC Article 708COPS: An Arresting Look at NEC Article 708
COPS: An Arresting Look at NEC Article 708michaeljmack
 
Seismic Compliance of Electrical Distribution
Seismic Compliance of Electrical DistributionSeismic Compliance of Electrical Distribution
Seismic Compliance of Electrical Distributionmichaeljmack
 
Modeling of a digital protective relay in a RT Digital Simulator
Modeling of a digital protective relay in a RT Digital SimulatorModeling of a digital protective relay in a RT Digital Simulator
Modeling of a digital protective relay in a RT Digital Simulatormichaeljmack
 
Facts on Grid Friendly Wind Plants
Facts on Grid Friendly Wind PlantsFacts on Grid Friendly Wind Plants
Facts on Grid Friendly Wind Plantsmichaeljmack
 
Power Plant Horror Stories
Power Plant Horror StoriesPower Plant Horror Stories
Power Plant Horror Storiesmichaeljmack
 
Transformer Fundamentals
Transformer FundamentalsTransformer Fundamentals
Transformer Fundamentalsmichaeljmack
 
Selectivity and Coodination
Selectivity and CoodinationSelectivity and Coodination
Selectivity and Coodinationmichaeljmack
 

More from michaeljmack (20)

Auburn, NY - 200 Years of History 1793-1993
Auburn, NY - 200 Years of History  1793-1993Auburn, NY - 200 Years of History  1793-1993
Auburn, NY - 200 Years of History 1793-1993
 
Auburn High School, Auburn, NY, 1982 Yearbook
Auburn High School, Auburn, NY, 1982 YearbookAuburn High School, Auburn, NY, 1982 Yearbook
Auburn High School, Auburn, NY, 1982 Yearbook
 
Auburn High School, Auburn, NY, 1980 Yearbook
Auburn High School, Auburn, NY, 1980 YearbookAuburn High School, Auburn, NY, 1980 Yearbook
Auburn High School, Auburn, NY, 1980 Yearbook
 
Surge Protection
Surge ProtectionSurge Protection
Surge Protection
 
Diesel Particulate Filters Control Systems
Diesel Particulate Filters Control SystemsDiesel Particulate Filters Control Systems
Diesel Particulate Filters Control Systems
 
Understanding Arc Flash
Understanding Arc FlashUnderstanding Arc Flash
Understanding Arc Flash
 
Siemens MV GIS Switchgear
Siemens MV GIS SwitchgearSiemens MV GIS Switchgear
Siemens MV GIS Switchgear
 
Fundamentals of transformer inrush
Fundamentals of transformer inrushFundamentals of transformer inrush
Fundamentals of transformer inrush
 
Building information modeling
Building information modelingBuilding information modeling
Building information modeling
 
15 years of experience stator ground fault protection
15 years of experience stator ground fault protection15 years of experience stator ground fault protection
15 years of experience stator ground fault protection
 
Emergency, Legally Required and Optional Standby Systems
Emergency, Legally Required and Optional Standby SystemsEmergency, Legally Required and Optional Standby Systems
Emergency, Legally Required and Optional Standby Systems
 
Lighting Control Solutions for Daylit Spaces
Lighting Control Solutions for Daylit SpacesLighting Control Solutions for Daylit Spaces
Lighting Control Solutions for Daylit Spaces
 
COPS: An Arresting Look at NEC Article 708
COPS: An Arresting Look at NEC Article 708COPS: An Arresting Look at NEC Article 708
COPS: An Arresting Look at NEC Article 708
 
Seismic Compliance of Electrical Distribution
Seismic Compliance of Electrical DistributionSeismic Compliance of Electrical Distribution
Seismic Compliance of Electrical Distribution
 
Modeling of a digital protective relay in a RT Digital Simulator
Modeling of a digital protective relay in a RT Digital SimulatorModeling of a digital protective relay in a RT Digital Simulator
Modeling of a digital protective relay in a RT Digital Simulator
 
Facts on Grid Friendly Wind Plants
Facts on Grid Friendly Wind PlantsFacts on Grid Friendly Wind Plants
Facts on Grid Friendly Wind Plants
 
Power Plant Horror Stories
Power Plant Horror StoriesPower Plant Horror Stories
Power Plant Horror Stories
 
Transformer Fundamentals
Transformer FundamentalsTransformer Fundamentals
Transformer Fundamentals
 
Arc Flash
Arc FlashArc Flash
Arc Flash
 
Selectivity and Coodination
Selectivity and CoodinationSelectivity and Coodination
Selectivity and Coodination
 

Recently uploaded

(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZTE
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...9953056974 Low Rate Call Girls In Saket, Delhi NCR
 

Recently uploaded (20)

(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 

Evaluation of standby power system architectures

  • 1. Evaluation of Large Standby Power System Architectures As facility power needs get very large, what’s the best design for optimum reliability?
  • 2. 2 Agenda Current Trends on Data Centers Design Reliability Indicators Overview of System Designs Lessons Learned Conclusions and Take-aways
  • 3. 3 Data Center Power System Designs Huge variety of designs – Simple Systems - Single genset and transfer switches • Bypass/Isolation and closed transition options – Paralleling with ATS – Paralleling with Power Transfer, Bus Ties – Other variations (Swing generators) Systems becoming very large (>100MW in many sites) – 1GW in the future? High speed diesel gensets still most common choice: lowest cost/kW, fast starting, local fuel supply, stable, easy to service Tendency for Redundant and Modular Systems
  • 4. 4 Big is not necessarily complex… Long Island Power Demand Response Site – 48MW, each machine individually paralleled to grid, controlled by SCADA software – Emissions compliant – No switchgear or additional controls required
  • 5. 5 Reliability Indicators MTBF goes up with hours of successful operation of a specific design – New designs are hard to evaluate • New logic reliability • Hidden Flaws • Failure Mode Effects – Common Assumptions: Avoid Single Points of Failure • But are all failure points equal? • Generator single points of failure; Redundancy – Prototype Testing Impact (ref: NFPA110) – Number of systems in service Impact of Number of Components on overall reliability PowerCommand Genset Control Example – 150K MTBF at launch in 1994 • Thousands of hours of development • Thousands of hours of testing • Hundreds of hours at seed sites – After 15 years of service: >1 M MTBF Easier to be confident in a design that is proven over time
  • 6. 6 A GOOD QUESTION OK, it’s easy to see that reliability is positively impacted by consistent quality control on a lot of widgits, but how do we deal with large, complex “one of a kind” systems?
  • 7. 7 Simplest Designs Genset with one or more ATS – Best for smaller projects – Can be multiplied for larger projects Genset operating power transfer breaker pair – Best for larger generators, switching near service – Lowest cost, smallest footprint – Can synchronize and ramp loads between live sources – Breakers can trip, so need to deal with that logically – Can be multiplied for any size project When used in multiples, each genset/transfer equipment has single points of failure, but only part of system fails
  • 8. 8 Paralleling Applications Paralleling functions are the same on every project Generator set paralleling functions commonly integrated – No/very limited switchgear space for separate control equipment – Dedicated purpose controllers with firmware rather than PLC-based or component functions
  • 9. 9 Parallel Applications Paralleling Systems Utilize Major Control Blocks with Common Functions – Parallel Controllers (PLL) • Start/Stop/Protect Genset • Black Start Control • Synchronize • Load Share • Bus Protection – Transfer Controllers (ATS) • Source Availability • Transfer Logic – System Control • System monitoring • Load Management (load add/shed) • Capacity Management (load demand) Distributed Logic Strategy Design Control – “One Throat to Choke”
  • 10. 10 Isolated Bus Master Control Functions Load Management (load add & shed sequence) – Back-up for overide of automatic sequence – Controls feeder breakers, ATS, or interface to BMS System Capacity (load demand) – Provides means of minimizing fuel consumption in long runs Local Operator Interface – What do you want the operator to do? Where? Remote Monitor & Control Digital Control
  • 11. 11 Remote Monitoring & Control ! "# $ $ % & $' () * ! "# $ $ % & $' () * % Multiple Networks/Multiple Uses – Isolated for speed, ease of installation Remote Monitoring is Very Common – Tons of data and control is available
  • 12. 12 More Complex Designs “Main-tie-Main” Configuration Service issues due to gensets on common bus with utility Logic Variations due to automated tie can be problematic
  • 13. 13 More Complex Designs % A combination of core paralleling and power transfer control blocks May have many generators and many transfer pairs Common to have multiple feeds to downstream devices Usually includes a central monitoring system for entire package
  • 14. 14 Impact of Automated Ties Automating Tie operation complicates design Best accomplished with core controls, orchestrated with PLC Best practice is to exercise design control on PLC logic “modules”
  • 15. 15 More Examples Most designs use many core functions PARALLELING POWER TRANSFER SUPERVISORY
  • 16. 16 Tier 3 Data Center Design More duplicated functions… PARALLELING PWR TRANS
  • 17. 17 Lessons Learned: Effective Use of Redundancy Single points of failure have a big impact on reliability Address by: – Design it out – True Redundancy – Live with it/Best Quality Genset Example MasterControl Example
  • 18. 18 Lessons Learned: Support for Complex Systems Look for ability to have support local to the project site – Local support should be equipped with software necessary for PLC and HMI (if different) – Training is critical Consider ability to support the PLC and HMI and other controls’ software in the future – 30-year life is not unexpected at many sites – Vendors’ commitment to backward compatibility • This capability varies with vendor – Number of software sets needed for total service is a major concern over time
  • 19. 19 Lessons Learned: Hot Standby (Vendor 1) + Hot Standby (Vendor 2) What does “Redundant PLC” mean? – Redundant Processor? Redundant I/O? Redundant Power Supply? Redundant Power Supply Bus? Redundant Coms Links? Hot Standby practices can significantly impact PLC operation time (responsiveness) – Impact on display responsiveness – Operation time for critical functions Capabilities of each PLC/Touchscreen differ by vendor – Every system supplier standardizes on specific vendors, and has limited flexibility to use others
  • 20. 20 Lessons Learned: On-going Operator Instruction & Training Posted Manual Operation Instructions – Consider all critical operations, • power transfer from utility to gensets and return • gensets on and off bus (if paralleled) • manual load add and shed Pay Attention to Operator Panel Information – What are operator capabilities? – What do you want them to do? – Where do you want them to do it?
  • 21. 21 Conclusions There’s a lot of wisdom in the first rule of engineering: KISS BUT, we are dealing with complicated facilities and demanding performance requirements Use Distributed Logic Strategy Make sure of support plan in the long run Keep learning from experience
  • 22. 22 Utility Paralleling Connected to Utility kW/kVar level
  • 23. 23 Product Configurations Cummins Caterpillar/Asco4000 Generac This slide shows the genset and paralleling control functions for different suppliers Cat/Asco/Generac all have 6-8 level load add/shed and load demand in their arrangement – Most global control competitors use the Cat/Asco model, except SDMO
  • 24. 24 Cummins Paralleling Topology Typical Isolated Bus architecture
  • 25. 25 Typical Isolated Bus Architecture Caterpillar shown, Asco, many others similar Others…
  • 26. 26 CPG Interconnect Block Diagram AC for accessories Status to Master Breaker Commands Breaker Status Power Conductors