What is Estimation
An estimate is a calculation of the quantities of various items of work,
and the expenses likely to be incurred there on.
The total of these probable expenses to be incurred on the work is
known as estimated cost of the work.
4-Dec-20 3/23
Objective of ECV
.
The students will acquire knowledge in estimation, tender practices,
contract procedures, and valuation and will be able to prepare
estimates, call for tenders and execute works.
4-Dec-20
4/23
Outcomes of ECV
The student will be able to
Estimate the quantities for buildings.
Rate Analysis for all Building works, canals, and Roads and Cost Estimate.
Understand types of specifications, principles for report preparation,
tender notices types.
Gain knowledge on types of contracts.
Evaluate valuation for building and land.
4-Dec-20
5/23
Important of ECV
.
Valuer & Er.Goundamani.mp4
4-Dec-20
6/23
Important of ECV
Estimating in construction is important because almost everyone has a
budget they have to meet for a project.
Almost everyone wants to know how much it will cost before they are
willing to start.
Estimates are also used to narrow down a choice in a contractor.
4-Dec-20
7/23
Placement opportunities
.
Valuer
Valuers can work under the following area,
Real Estate, Building Construction, Town Planning, Land
Development, Etc,.
A) Qualifications and Experience
Qualification Experience
B.E./B.Tech. (Civil Engineering,
Architecture or Town Planning)
10-years experience in Building
Construction, Town Planning etc.
M.E./ M.Tech in valuation 2-years experience
4-Dec-20
8/23
Placement opportunities
B ) Categories of Valuers
Empanelment of valuers by the Bank shall be in the following
categories:
PSB- Public Sector Banks
Category Work Experience Valuation limit
A
Min. 10 years + already empanelled
with at least 2 PSBs
* No limit
B
Between 5 to 10 years + already
empanelled with at least 1 PSB
* Up to Rs. 50 crore
4-Dec-20
9/23
UNIT I - QUANTITY ESTIMATION / ESTIMATE OF
BUILDINGS
4-Dec-20 10/23
UNIT II - RATE ANALYSIS AND COSTING /
ESTIMATE OF OTHER STRUCTURES
4-Dec-20 11/23
UNIT III - SPECIFICATIONS, REPORTS AND TENDERS /
SPECIFICATION AND TENDERS
4-Dec-20 12/23
UNIT IV – CONTRACTS / VALUATION
4-Dec-20 13/23
UNIT V – VALUATION / REPORT PREPARATION
4-Dec-20 14/23
UNIT I - QUANTITY ESTIMATION / ESTIMATE OF
BUILDINGS
Philosophy – Purpose – Methods of estimation – Types of estimates –
Approximate estimates –Detailed estimate – Estimation of quantities for
buildings, bituminous and cement concrete roads, septic tank, soak pit,
retaining walls – culverts (additional practice in class room using
computer softwares)
Load bearing and framed structures – Calculation of quantities of brick
work, RCC, PCC,Plastering, white washing, colour washing and painting /
varnishing for shops, rooms,residential building with flat and pitched roof
– Various types of arches – Calculation of brick work and RCC works in
arches – Estimate of joineries for panelled and glazed doors, windows,
ventilators, handrails etc.
4-Dec-20 15/23
UNIT II - RATE ANALYSIS AND COSTING / ESTIMATE OF
OTHER STRUCTURES
Standard Data – Observed Data – Schedule of rates – Market rates –
Standard Data for Man Hours and Machineries for common civil works –
Rate Analysis for all Building works, canals, and Roads– Cost Estimates
(additional practice in class room using Computer softwares) - (Analysis of
rates for the item of work asked, the data regarding labour, rates of material
and rates of labour to be given in the Examination Question Paper)
Estimating of septic tank, soak pit – sanitary and water supply installations
– water supply pipe line– sewer line – tube well – open well – estimate of
bituminous and cement concrete roads –estimate of retaining walls –
culverts.
4-Dec-20 16/23
UNIT III - SPECIFICATIONS, REPORTS AND TENDERS /
SPECIFICATION AND TENDERS
Specifications – Detailed and general specifications – Constructions –
Sources – Types of specifications – Principles for report preparation –
report on estimate of residential building – Culvert – Roads – TTT Act 2000
– Tender notices – types – tender procedures – Drafting model tenders , E-
tendering-Digital signature certificates- Encrypting -Decrypting – Reverse
auctions.
Data – Schedule of rates – Analysis of rates – Specifications – sources –
Preparation of detailed and general specifications – Tenders – TTT Act – e-
tender – Preparation of Tender Notice and Document – Contracts – Types
of contracts – Drafting of contract documents – Arbitration and legal
requirements.
4-Dec-20 17/23
UNIT IV – CONTRACTS / VALUATION
Contract – Types of contracts – Formation of contract – Contract
conditions – Contract for labour, material, design, construction – Drafting
of contract documents based on IBRD / MORTH Standard bidding
documents – Construction contracts – Contract problems – Arbitration
and legal requirements.
Necessity – Basics of value engineering – Capitalised value – Depreciation –
Escalation – Value of building – Calculation of Standard rent – Mortgage –
Lease
4-Dec-20 18/23
UNIT V – VALUATION / REPORT PREPARATION
Definitions – Various types of valuations – Valuation methods - Necessity –
Capitalised value – Depreciation – Escalation – Valuation of land –
Buildings – Calculation of Standard rent – Mortgage – Lease
Principles for report preparation – report on estimate of residential
building – Culvert – Roads – Water supply and sanitary installations.
4-Dec-20 19/23
Books
TEXTBOOKS:
1.B.N Dutta ‘Estimating and Costing in Civil
Engineering’, UBS Publishers & Distributors (P)
Ltd, 2010.
2. B.S.Patil, ‘Civil Engineering Contracts and
Estimates’, University Press, 2006
3.D.N. Banerjee, ‘Principles and Practices of
Valuation’, V Edition, Eastern Law House, 1998.
4. Rangwala. S.C “Estimating and Costing in
Civil Engineering”, Charotar Publishing
House, 2006. .(UNIT I,II,III,IV,V)
4-Dec-20 20/23
Books and Web links
REFERENCES:
1. Hand Book of Consolidated Data – 8/2000, Vol.1, TNPWD
2. Tamil Nadu Transparencies in Tenders Act, 1998
3. Arbitration and Conciliation Act, 1996
4.Standard Bid elevation From, procurement of Good or works, The
world bank, April 1996.
5. Standard Data Book for Analysis and Rates, IRC, New Delhi, 2003.
WEB RESOURCES
http://nptel.ac.in/courses/105103023/35
4-Dec-20 21/23
The Most lovable place in Earth is Classroom
4-Dec-20 22/23
Way to achieve Goals
A-D-R-P-R
A - ASSIGNMENTS
D- DISCIPLINE
R- REGULAR TO THE CLASS
P- PUNCTUVALITY
R- RESULT Happy Learning

More Related Content

What's hot

Repair, rehabilitation and retrofitting of structures - RRS
Repair, rehabilitation and retrofitting of structures - RRSRepair, rehabilitation and retrofitting of structures - RRS
Repair, rehabilitation and retrofitting of structures - RRS
Shanmugasundaram N
 
Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contracts
srinivas2036
 
Specifications, reports and tenders
Specifications, reports and tendersSpecifications, reports and tenders
Specifications, reports and tenders
gayu pandian
 
Valuation
ValuationValuation
Valuation
Aditya Mistry
 
Non destructive test on concrete (ndt)
Non destructive test on concrete (ndt)Non destructive test on concrete (ndt)
Non destructive test on concrete (ndt)Abhishek Gupta
 
Properties of Fresh and Hardened Concrete
Properties of Fresh and Hardened ConcreteProperties of Fresh and Hardened Concrete
Properties of Fresh and Hardened Concrete
Rishabh Lala
 
District schedule rates (DSR), specification of items of work as per PWD
District schedule rates (DSR), specification of items of work as per PWDDistrict schedule rates (DSR), specification of items of work as per PWD
District schedule rates (DSR), specification of items of work as per PWD
AshwiniChaudhari13
 
Aggregate - coarse aggregates, testing & limits
Aggregate - coarse aggregates, testing & limitsAggregate - coarse aggregates, testing & limits
Aggregate - coarse aggregates, testing & limits
lalitha moorthy
 
Self compacting concrete (scc)
Self compacting concrete (scc)Self compacting concrete (scc)
Self compacting concrete (scc)
y Sahaja
 
Rate analysis in civil engineering
Rate analysis in civil engineeringRate analysis in civil engineering
Rate analysis in civil engineering
Kailash Chander
 
Creep and shrinkage
Creep and shrinkageCreep and shrinkage
Creep and shrinkage
Asad Rehman
 
AGGREGATES & ITS PROPERTIES
AGGREGATES & ITS PROPERTIESAGGREGATES & ITS PROPERTIES
AGGREGATES & ITS PROPERTIES
Vishal Sharma
 
Cube test for compressive strength of concrete
Cube test for compressive strength of concreteCube test for compressive strength of concrete
Cube test for compressive strength of concrete
Ayaz khan
 
Concrete Mix Design
Concrete Mix DesignConcrete Mix Design
Concrete Mix Design
GAURAV. H .TANDON
 
Analysis of rates for labour and material
Analysis of rates for labour and materialAnalysis of rates for labour and material
Analysis of rates for labour and material
ALI HYDER GADHI
 
Rate analysis
Rate analysisRate analysis
Rate analysis
DhavalMithaiwala
 
Design of flexible pavement
Design of flexible pavementDesign of flexible pavement
Design of flexible pavement
Bhavik A Shah
 
Load carrying capacity of piles
Load carrying capacity of pilesLoad carrying capacity of piles
Load carrying capacity of piles
Latif Hyder Wadho
 
2. testing of cement ppt
2. testing of cement ppt2. testing of cement ppt
2. testing of cement pptBhaswati Sharma
 
Structural audit
Structural auditStructural audit
Structural audit
Bharti Shinde
 

What's hot (20)

Repair, rehabilitation and retrofitting of structures - RRS
Repair, rehabilitation and retrofitting of structures - RRSRepair, rehabilitation and retrofitting of structures - RRS
Repair, rehabilitation and retrofitting of structures - RRS
 
Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contracts
 
Specifications, reports and tenders
Specifications, reports and tendersSpecifications, reports and tenders
Specifications, reports and tenders
 
Valuation
ValuationValuation
Valuation
 
Non destructive test on concrete (ndt)
Non destructive test on concrete (ndt)Non destructive test on concrete (ndt)
Non destructive test on concrete (ndt)
 
Properties of Fresh and Hardened Concrete
Properties of Fresh and Hardened ConcreteProperties of Fresh and Hardened Concrete
Properties of Fresh and Hardened Concrete
 
District schedule rates (DSR), specification of items of work as per PWD
District schedule rates (DSR), specification of items of work as per PWDDistrict schedule rates (DSR), specification of items of work as per PWD
District schedule rates (DSR), specification of items of work as per PWD
 
Aggregate - coarse aggregates, testing & limits
Aggregate - coarse aggregates, testing & limitsAggregate - coarse aggregates, testing & limits
Aggregate - coarse aggregates, testing & limits
 
Self compacting concrete (scc)
Self compacting concrete (scc)Self compacting concrete (scc)
Self compacting concrete (scc)
 
Rate analysis in civil engineering
Rate analysis in civil engineeringRate analysis in civil engineering
Rate analysis in civil engineering
 
Creep and shrinkage
Creep and shrinkageCreep and shrinkage
Creep and shrinkage
 
AGGREGATES & ITS PROPERTIES
AGGREGATES & ITS PROPERTIESAGGREGATES & ITS PROPERTIES
AGGREGATES & ITS PROPERTIES
 
Cube test for compressive strength of concrete
Cube test for compressive strength of concreteCube test for compressive strength of concrete
Cube test for compressive strength of concrete
 
Concrete Mix Design
Concrete Mix DesignConcrete Mix Design
Concrete Mix Design
 
Analysis of rates for labour and material
Analysis of rates for labour and materialAnalysis of rates for labour and material
Analysis of rates for labour and material
 
Rate analysis
Rate analysisRate analysis
Rate analysis
 
Design of flexible pavement
Design of flexible pavementDesign of flexible pavement
Design of flexible pavement
 
Load carrying capacity of piles
Load carrying capacity of pilesLoad carrying capacity of piles
Load carrying capacity of piles
 
2. testing of cement ppt
2. testing of cement ppt2. testing of cement ppt
2. testing of cement ppt
 
Structural audit
Structural auditStructural audit
Structural audit
 

Similar to Estimation introduction - Estimation, Costing and Valuation (ECV)

NCIT civil Syllabus 2013-2014
NCIT civil Syllabus 2013-2014NCIT civil Syllabus 2013-2014
NCIT civil Syllabus 2013-2014
LAKSHITHA RAJAPAKSHA
 
estimation,costingandvaluation.pdf
estimation,costingandvaluation.pdfestimation,costingandvaluation.pdf
estimation,costingandvaluation.pdf
Ictsol
 
CV waqar Azeem QS
CV waqar Azeem QSCV waqar Azeem QS
CV waqar Azeem QS
WAQAR AZEEM
 
EstimationandCosting.ppt
EstimationandCosting.pptEstimationandCosting.ppt
EstimationandCosting.ppt
BALAMURUGANR53
 
presentation quantity survey and estimate
presentation quantity survey and estimatepresentation quantity survey and estimate
Ibe quantity surveyor 2013
Ibe quantity surveyor 2013Ibe quantity surveyor 2013
Ibe quantity surveyor 2013nurun2010
 
Sxsw 2011 construction enviroment
Sxsw 2011 construction enviromentSxsw 2011 construction enviroment
Sxsw 2011 construction enviromentjuwes
 
A Course Material On Estimation And Quantity Surveying
A Course Material On Estimation And Quantity SurveyingA Course Material On Estimation And Quantity Surveying
A Course Material On Estimation And Quantity Surveying
Claire Webber
 
EDUARDO H. PARE CV - CIRCA - 04.07.2021
EDUARDO H. PARE CV - CIRCA - 04.07.2021EDUARDO H. PARE CV - CIRCA - 04.07.2021
EDUARDO H. PARE CV - CIRCA - 04.07.2021
Eduardo H. Pare
 
Amr Moneim CV March 2016
Amr Moneim CV March 2016Amr Moneim CV March 2016
Amr Moneim CV March 2016
Amr Abdul-Moneim
 
Furrukh Shahzad CV Quantity Surveyor
Furrukh Shahzad CV Quantity SurveyorFurrukh Shahzad CV Quantity Surveyor
Furrukh Shahzad CV Quantity SurveyorFurrukh Shahzad
 
0111CE702-ESTIMATION AND QUANTITY SURVEYING VII SEMESTER E-LEARNING MATERIAL
0111CE702-ESTIMATION AND QUANTITY SURVEYING VII SEMESTER E-LEARNING MATERIAL0111CE702-ESTIMATION AND QUANTITY SURVEYING VII SEMESTER E-LEARNING MATERIAL
0111CE702-ESTIMATION AND QUANTITY SURVEYING VII SEMESTER E-LEARNING MATERIAL
Nat Rice
 
Resume-Mubbasher-Railway
Resume-Mubbasher-RailwayResume-Mubbasher-Railway
Resume-Mubbasher-RailwayMubasher Malik
 
Q130302108111
Q130302108111Q130302108111
Q130302108111
IOSR Journals
 
1.Cost Estimation of Civil Structures Orientation.pptx
1.Cost Estimation of Civil Structures Orientation.pptx1.Cost Estimation of Civil Structures Orientation.pptx
1.Cost Estimation of Civil Structures Orientation.pptx
VenkataRamana602302
 

Similar to Estimation introduction - Estimation, Costing and Valuation (ECV) (20)

NCIT civil Syllabus 2013-2014
NCIT civil Syllabus 2013-2014NCIT civil Syllabus 2013-2014
NCIT civil Syllabus 2013-2014
 
Resume_[Sr. Estimator - Sr. QS]
Resume_[Sr. Estimator - Sr. QS]Resume_[Sr. Estimator - Sr. QS]
Resume_[Sr. Estimator - Sr. QS]
 
estimation,costingandvaluation.pdf
estimation,costingandvaluation.pdfestimation,costingandvaluation.pdf
estimation,costingandvaluation.pdf
 
CV waqar Azeem QS
CV waqar Azeem QSCV waqar Azeem QS
CV waqar Azeem QS
 
EstimationandCosting.ppt
EstimationandCosting.pptEstimationandCosting.ppt
EstimationandCosting.ppt
 
presentation quantity survey and estimate
presentation quantity survey and estimatepresentation quantity survey and estimate
presentation quantity survey and estimate
 
Ibe quantity surveyor 2013
Ibe quantity surveyor 2013Ibe quantity surveyor 2013
Ibe quantity surveyor 2013
 
Curriculum Vitae
Curriculum VitaeCurriculum Vitae
Curriculum Vitae
 
Zuher Mirza CV
Zuher Mirza CVZuher Mirza CV
Zuher Mirza CV
 
Sxsw 2011 construction enviroment
Sxsw 2011 construction enviromentSxsw 2011 construction enviroment
Sxsw 2011 construction enviroment
 
CV
CVCV
CV
 
A Course Material On Estimation And Quantity Surveying
A Course Material On Estimation And Quantity SurveyingA Course Material On Estimation And Quantity Surveying
A Course Material On Estimation And Quantity Surveying
 
CV_Civil_Engineer
CV_Civil_EngineerCV_Civil_Engineer
CV_Civil_Engineer
 
EDUARDO H. PARE CV - CIRCA - 04.07.2021
EDUARDO H. PARE CV - CIRCA - 04.07.2021EDUARDO H. PARE CV - CIRCA - 04.07.2021
EDUARDO H. PARE CV - CIRCA - 04.07.2021
 
Amr Moneim CV March 2016
Amr Moneim CV March 2016Amr Moneim CV March 2016
Amr Moneim CV March 2016
 
Furrukh Shahzad CV Quantity Surveyor
Furrukh Shahzad CV Quantity SurveyorFurrukh Shahzad CV Quantity Surveyor
Furrukh Shahzad CV Quantity Surveyor
 
0111CE702-ESTIMATION AND QUANTITY SURVEYING VII SEMESTER E-LEARNING MATERIAL
0111CE702-ESTIMATION AND QUANTITY SURVEYING VII SEMESTER E-LEARNING MATERIAL0111CE702-ESTIMATION AND QUANTITY SURVEYING VII SEMESTER E-LEARNING MATERIAL
0111CE702-ESTIMATION AND QUANTITY SURVEYING VII SEMESTER E-LEARNING MATERIAL
 
Resume-Mubbasher-Railway
Resume-Mubbasher-RailwayResume-Mubbasher-Railway
Resume-Mubbasher-Railway
 
Q130302108111
Q130302108111Q130302108111
Q130302108111
 
1.Cost Estimation of Civil Structures Orientation.pptx
1.Cost Estimation of Civil Structures Orientation.pptx1.Cost Estimation of Civil Structures Orientation.pptx
1.Cost Estimation of Civil Structures Orientation.pptx
 

More from Shanmugasundaram N

Types of arches
Types of arches   Types of arches
Types of arches
Shanmugasundaram N
 
Total station survey
Total station surveyTotal station survey
Total station survey
Shanmugasundaram N
 
Gps survey
Gps surveyGps survey
Gps survey
Shanmugasundaram N
 
Control surveying
Control surveyingControl surveying
Control surveying
Shanmugasundaram N
 
Response of structures to earthquake - Structural dynamics and Earthquake Eng...
Response of structures to earthquake - Structural dynamics and Earthquake Eng...Response of structures to earthquake - Structural dynamics and Earthquake Eng...
Response of structures to earthquake - Structural dynamics and Earthquake Eng...
Shanmugasundaram N
 
Elements of seismology - Structural dynamics and Earthquake Engineering (SD&EE)
Elements of seismology - Structural dynamics and Earthquake Engineering (SD&EE)Elements of seismology - Structural dynamics and Earthquake Engineering (SD&EE)
Elements of seismology - Structural dynamics and Earthquake Engineering (SD&EE)
Shanmugasundaram N
 
Lessons learned from past earthquake - Structural dynamics and Earthquake Eng...
Lessons learned from past earthquake - Structural dynamics and Earthquake Eng...Lessons learned from past earthquake - Structural dynamics and Earthquake Eng...
Lessons learned from past earthquake - Structural dynamics and Earthquake Eng...
Shanmugasundaram N
 
Techniques for repair and protection methods II- Repair and rehabilitation of...
Techniques for repair and protection methods II- Repair and rehabilitation of...Techniques for repair and protection methods II- Repair and rehabilitation of...
Techniques for repair and protection methods II- Repair and rehabilitation of...
Shanmugasundaram N
 
Techniques for repair and protection methods - Repair and rehabilitation of s...
Techniques for repair and protection methods - Repair and rehabilitation of s...Techniques for repair and protection methods - Repair and rehabilitation of s...
Techniques for repair and protection methods - Repair and rehabilitation of s...
Shanmugasundaram N
 
Strength and durability of concrete - Repair and rehabilitation of structures...
Strength and durability of concrete - Repair and rehabilitation of structures...Strength and durability of concrete - Repair and rehabilitation of structures...
Strength and durability of concrete - Repair and rehabilitation of structures...
Shanmugasundaram N
 
Special concretes- Repair and rehabilitation of structures(RRS) - Concrete Te...
Special concretes- Repair and rehabilitation of structures(RRS) - Concrete Te...Special concretes- Repair and rehabilitation of structures(RRS) - Concrete Te...
Special concretes- Repair and rehabilitation of structures(RRS) - Concrete Te...
Shanmugasundaram N
 
Maintenance and repair strategies - Repair and rehabilitation of structures(RRS)
Maintenance and repair strategies - Repair and rehabilitation of structures(RRS)Maintenance and repair strategies - Repair and rehabilitation of structures(RRS)
Maintenance and repair strategies - Repair and rehabilitation of structures(RRS)
Shanmugasundaram N
 
Moment distribution method - Structural Analysis
Moment distribution method  - Structural AnalysisMoment distribution method  - Structural Analysis
Moment distribution method - Structural Analysis
Shanmugasundaram N
 
Portal frames with sway - - Structural Analysis
Portal frames with sway -  - Structural AnalysisPortal frames with sway -  - Structural Analysis
Portal frames with sway - - Structural Analysis
Shanmugasundaram N
 
Basics of sdm and equations - - Structural Analysis
Basics of sdm and equations -  - Structural AnalysisBasics of sdm and equations -  - Structural Analysis
Basics of sdm and equations - - Structural Analysis
Shanmugasundaram N
 
Determination of static and kinematic indeterminacies - Structural Analysis
Determination of static and kinematic indeterminacies - Structural AnalysisDetermination of static and kinematic indeterminacies - Structural Analysis
Determination of static and kinematic indeterminacies - Structural Analysis
Shanmugasundaram N
 
Basics of structural analysis
Basics of structural analysisBasics of structural analysis
Basics of structural analysis
Shanmugasundaram N
 
Valuation - Estimation, Costing and Valuation Engineering
Valuation - Estimation, Costing and Valuation EngineeringValuation - Estimation, Costing and Valuation Engineering
Valuation - Estimation, Costing and Valuation Engineering
Shanmugasundaram N
 
Contracts - Estimation, Costing and Valuation Engineering
Contracts - Estimation, Costing and Valuation EngineeringContracts - Estimation, Costing and Valuation Engineering
Contracts - Estimation, Costing and Valuation Engineering
Shanmugasundaram N
 
Philosophy, purpose of estimation, load bearing and framed structure - Estima...
Philosophy, purpose of estimation, load bearing and framed structure - Estima...Philosophy, purpose of estimation, load bearing and framed structure - Estima...
Philosophy, purpose of estimation, load bearing and framed structure - Estima...
Shanmugasundaram N
 

More from Shanmugasundaram N (20)

Types of arches
Types of arches   Types of arches
Types of arches
 
Total station survey
Total station surveyTotal station survey
Total station survey
 
Gps survey
Gps surveyGps survey
Gps survey
 
Control surveying
Control surveyingControl surveying
Control surveying
 
Response of structures to earthquake - Structural dynamics and Earthquake Eng...
Response of structures to earthquake - Structural dynamics and Earthquake Eng...Response of structures to earthquake - Structural dynamics and Earthquake Eng...
Response of structures to earthquake - Structural dynamics and Earthquake Eng...
 
Elements of seismology - Structural dynamics and Earthquake Engineering (SD&EE)
Elements of seismology - Structural dynamics and Earthquake Engineering (SD&EE)Elements of seismology - Structural dynamics and Earthquake Engineering (SD&EE)
Elements of seismology - Structural dynamics and Earthquake Engineering (SD&EE)
 
Lessons learned from past earthquake - Structural dynamics and Earthquake Eng...
Lessons learned from past earthquake - Structural dynamics and Earthquake Eng...Lessons learned from past earthquake - Structural dynamics and Earthquake Eng...
Lessons learned from past earthquake - Structural dynamics and Earthquake Eng...
 
Techniques for repair and protection methods II- Repair and rehabilitation of...
Techniques for repair and protection methods II- Repair and rehabilitation of...Techniques for repair and protection methods II- Repair and rehabilitation of...
Techniques for repair and protection methods II- Repair and rehabilitation of...
 
Techniques for repair and protection methods - Repair and rehabilitation of s...
Techniques for repair and protection methods - Repair and rehabilitation of s...Techniques for repair and protection methods - Repair and rehabilitation of s...
Techniques for repair and protection methods - Repair and rehabilitation of s...
 
Strength and durability of concrete - Repair and rehabilitation of structures...
Strength and durability of concrete - Repair and rehabilitation of structures...Strength and durability of concrete - Repair and rehabilitation of structures...
Strength and durability of concrete - Repair and rehabilitation of structures...
 
Special concretes- Repair and rehabilitation of structures(RRS) - Concrete Te...
Special concretes- Repair and rehabilitation of structures(RRS) - Concrete Te...Special concretes- Repair and rehabilitation of structures(RRS) - Concrete Te...
Special concretes- Repair and rehabilitation of structures(RRS) - Concrete Te...
 
Maintenance and repair strategies - Repair and rehabilitation of structures(RRS)
Maintenance and repair strategies - Repair and rehabilitation of structures(RRS)Maintenance and repair strategies - Repair and rehabilitation of structures(RRS)
Maintenance and repair strategies - Repair and rehabilitation of structures(RRS)
 
Moment distribution method - Structural Analysis
Moment distribution method  - Structural AnalysisMoment distribution method  - Structural Analysis
Moment distribution method - Structural Analysis
 
Portal frames with sway - - Structural Analysis
Portal frames with sway -  - Structural AnalysisPortal frames with sway -  - Structural Analysis
Portal frames with sway - - Structural Analysis
 
Basics of sdm and equations - - Structural Analysis
Basics of sdm and equations -  - Structural AnalysisBasics of sdm and equations -  - Structural Analysis
Basics of sdm and equations - - Structural Analysis
 
Determination of static and kinematic indeterminacies - Structural Analysis
Determination of static and kinematic indeterminacies - Structural AnalysisDetermination of static and kinematic indeterminacies - Structural Analysis
Determination of static and kinematic indeterminacies - Structural Analysis
 
Basics of structural analysis
Basics of structural analysisBasics of structural analysis
Basics of structural analysis
 
Valuation - Estimation, Costing and Valuation Engineering
Valuation - Estimation, Costing and Valuation EngineeringValuation - Estimation, Costing and Valuation Engineering
Valuation - Estimation, Costing and Valuation Engineering
 
Contracts - Estimation, Costing and Valuation Engineering
Contracts - Estimation, Costing and Valuation EngineeringContracts - Estimation, Costing and Valuation Engineering
Contracts - Estimation, Costing and Valuation Engineering
 
Philosophy, purpose of estimation, load bearing and framed structure - Estima...
Philosophy, purpose of estimation, load bearing and framed structure - Estima...Philosophy, purpose of estimation, load bearing and framed structure - Estima...
Philosophy, purpose of estimation, load bearing and framed structure - Estima...
 

Recently uploaded

ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
Vijay Dialani, PhD
 
Runway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptxRunway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptx
SupreethSP4
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
BrazilAccount1
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
Pipe Restoration Solutions
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 

Recently uploaded (20)

ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
 
Runway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptxRunway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptx
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 

Estimation introduction - Estimation, Costing and Valuation (ECV)

  • 1. SNS COLLEGE OF ENGINEERING & TECHNOLOGY An Autonomous Institutions Accredited by NBA – AICTE and Accredited by NAAC – UGC with ‘A’ & ‘A+’Grade Approved by AICTE, New Delhi & Affiliated to Anna University, Chennai DEPARTMENT OF CIVIL ENGINEERING COURSE NAME: CE8701 - ESTIMATION, COSTING AND VALUATION ENGINEERING (SNSCE) 16CE402 - ESTIMATION, COSTING AND VALUATION (SNSCT) IV YEAR / VII SEMESTER Topic 1 : Introduction
  • 2. 4-Dec-20 2/23 What is Estimation An estimate is a calculation of the quantities of various items of work, and the expenses likely to be incurred there on. The total of these probable expenses to be incurred on the work is known as estimated cost of the work.
  • 3. 4-Dec-20 3/23 Objective of ECV . The students will acquire knowledge in estimation, tender practices, contract procedures, and valuation and will be able to prepare estimates, call for tenders and execute works.
  • 4. 4-Dec-20 4/23 Outcomes of ECV The student will be able to Estimate the quantities for buildings. Rate Analysis for all Building works, canals, and Roads and Cost Estimate. Understand types of specifications, principles for report preparation, tender notices types. Gain knowledge on types of contracts. Evaluate valuation for building and land.
  • 6. 4-Dec-20 6/23 Important of ECV Estimating in construction is important because almost everyone has a budget they have to meet for a project. Almost everyone wants to know how much it will cost before they are willing to start. Estimates are also used to narrow down a choice in a contractor.
  • 7. 4-Dec-20 7/23 Placement opportunities . Valuer Valuers can work under the following area, Real Estate, Building Construction, Town Planning, Land Development, Etc,. A) Qualifications and Experience Qualification Experience B.E./B.Tech. (Civil Engineering, Architecture or Town Planning) 10-years experience in Building Construction, Town Planning etc. M.E./ M.Tech in valuation 2-years experience
  • 8. 4-Dec-20 8/23 Placement opportunities B ) Categories of Valuers Empanelment of valuers by the Bank shall be in the following categories: PSB- Public Sector Banks Category Work Experience Valuation limit A Min. 10 years + already empanelled with at least 2 PSBs * No limit B Between 5 to 10 years + already empanelled with at least 1 PSB * Up to Rs. 50 crore
  • 9. 4-Dec-20 9/23 UNIT I - QUANTITY ESTIMATION / ESTIMATE OF BUILDINGS
  • 10. 4-Dec-20 10/23 UNIT II - RATE ANALYSIS AND COSTING / ESTIMATE OF OTHER STRUCTURES
  • 11. 4-Dec-20 11/23 UNIT III - SPECIFICATIONS, REPORTS AND TENDERS / SPECIFICATION AND TENDERS
  • 12. 4-Dec-20 12/23 UNIT IV – CONTRACTS / VALUATION
  • 13. 4-Dec-20 13/23 UNIT V – VALUATION / REPORT PREPARATION
  • 14. 4-Dec-20 14/23 UNIT I - QUANTITY ESTIMATION / ESTIMATE OF BUILDINGS Philosophy – Purpose – Methods of estimation – Types of estimates – Approximate estimates –Detailed estimate – Estimation of quantities for buildings, bituminous and cement concrete roads, septic tank, soak pit, retaining walls – culverts (additional practice in class room using computer softwares) Load bearing and framed structures – Calculation of quantities of brick work, RCC, PCC,Plastering, white washing, colour washing and painting / varnishing for shops, rooms,residential building with flat and pitched roof – Various types of arches – Calculation of brick work and RCC works in arches – Estimate of joineries for panelled and glazed doors, windows, ventilators, handrails etc.
  • 15. 4-Dec-20 15/23 UNIT II - RATE ANALYSIS AND COSTING / ESTIMATE OF OTHER STRUCTURES Standard Data – Observed Data – Schedule of rates – Market rates – Standard Data for Man Hours and Machineries for common civil works – Rate Analysis for all Building works, canals, and Roads– Cost Estimates (additional practice in class room using Computer softwares) - (Analysis of rates for the item of work asked, the data regarding labour, rates of material and rates of labour to be given in the Examination Question Paper) Estimating of septic tank, soak pit – sanitary and water supply installations – water supply pipe line– sewer line – tube well – open well – estimate of bituminous and cement concrete roads –estimate of retaining walls – culverts.
  • 16. 4-Dec-20 16/23 UNIT III - SPECIFICATIONS, REPORTS AND TENDERS / SPECIFICATION AND TENDERS Specifications – Detailed and general specifications – Constructions – Sources – Types of specifications – Principles for report preparation – report on estimate of residential building – Culvert – Roads – TTT Act 2000 – Tender notices – types – tender procedures – Drafting model tenders , E- tendering-Digital signature certificates- Encrypting -Decrypting – Reverse auctions. Data – Schedule of rates – Analysis of rates – Specifications – sources – Preparation of detailed and general specifications – Tenders – TTT Act – e- tender – Preparation of Tender Notice and Document – Contracts – Types of contracts – Drafting of contract documents – Arbitration and legal requirements.
  • 17. 4-Dec-20 17/23 UNIT IV – CONTRACTS / VALUATION Contract – Types of contracts – Formation of contract – Contract conditions – Contract for labour, material, design, construction – Drafting of contract documents based on IBRD / MORTH Standard bidding documents – Construction contracts – Contract problems – Arbitration and legal requirements. Necessity – Basics of value engineering – Capitalised value – Depreciation – Escalation – Value of building – Calculation of Standard rent – Mortgage – Lease
  • 18. 4-Dec-20 18/23 UNIT V – VALUATION / REPORT PREPARATION Definitions – Various types of valuations – Valuation methods - Necessity – Capitalised value – Depreciation – Escalation – Valuation of land – Buildings – Calculation of Standard rent – Mortgage – Lease Principles for report preparation – report on estimate of residential building – Culvert – Roads – Water supply and sanitary installations.
  • 19. 4-Dec-20 19/23 Books TEXTBOOKS: 1.B.N Dutta ‘Estimating and Costing in Civil Engineering’, UBS Publishers & Distributors (P) Ltd, 2010. 2. B.S.Patil, ‘Civil Engineering Contracts and Estimates’, University Press, 2006 3.D.N. Banerjee, ‘Principles and Practices of Valuation’, V Edition, Eastern Law House, 1998. 4. Rangwala. S.C “Estimating and Costing in Civil Engineering”, Charotar Publishing House, 2006. .(UNIT I,II,III,IV,V)
  • 20. 4-Dec-20 20/23 Books and Web links REFERENCES: 1. Hand Book of Consolidated Data – 8/2000, Vol.1, TNPWD 2. Tamil Nadu Transparencies in Tenders Act, 1998 3. Arbitration and Conciliation Act, 1996 4.Standard Bid elevation From, procurement of Good or works, The world bank, April 1996. 5. Standard Data Book for Analysis and Rates, IRC, New Delhi, 2003. WEB RESOURCES http://nptel.ac.in/courses/105103023/35