EPC OVERVIEW
stands for Engineering, procurement and
construction
EPC overview
EPC is
gaining
importance
worldwide. It
requires good
understandin
g by the
EPCC to
return a profit
An EPC
contract is a
complex
agreement.
In a global
context, EPC
management
is more
complex.
 EPC contract the contractor designs the
installation, procures the necessary materials
and builds the project, either directly or by
subcontracting part of the work. In some cases,
the contractor carries the project risk for
schedule as well as budget in return for a fixed
price, called lump sum or LSTK depending on
the agreed scope of work.[1]
 When the scope is restricted to engineering
and procurement, this is referred to as an EP,
E and P or E+P contract. This is often done in
situations where the construction risk is too
great for the contractor or when the owner does
the construction
Comparison of EPC/EPCM
 EPC company is able
to manage all levels
on site, with
Construction as well
 EPC contract is more
critical and destined
to the biggest
companies - it is
advantage indeed.
 EPCM company is
only managing build
site as a Site
Engineer (Supervisor
on behalf of final
customer.
 EPCM contract is
smaller type of
contract than EPC,
but safer for EPCM
company
EPCM (engineering,
procurement, and
construction management
EPC (engineering, procurement, and
construction )
IMPORTANCE OF EPC
An owner decides for an EPC contract for reasons that
include
 Reduced stress for owner
 easy work and growth of the company.
 Single point of contact for owner simplifies
communications.
 Ready availability of post-commissioning services
 Ensures quality and reduces practical issues faced in
other ways[clarification needed]
 Owner protected against changing prices for
materials, labor, etc.
 Cost is known at the start of the project
Owner defines to the EPC contract :
 Scope and the specifications of the plant
 Quality
 Project duration
 Cost
 The cost (the price to be paid to the EPCC) is
negotiated and finalised and paid in mutually
agreed installments.
Functions
Engineering Functions
 Initiation
 Planning
 Estimating ->
Request for Quote
 Design
Procurement
Functions
 Purchasing
 Expediting
 Receiving
 Invoicing
Construction Functions
 Construction Schedule
 On-site Material Handling
 Building Activities
 On-site Client Communications
 Closing
Projects Success by the owner and
the EPC contractor
Owner Defines
 Defines guarantees
well
 Defines scope and
quality very carefully
 Defines milestones
meticulously
 Defines LD/penalty
clauses
 Makes payment terms
very specific
EPC Contractor
improves
 Adopts similar terms
and conditions as
owner regarding
quality, guarantee
etc., for
subcontracts/vendors
 Do not keep terms
open-ended
 Coordinate vigilantly
to reduce chances of
errors at site.
Global arena
The EPCC
must have
data and
expertise in
all the
required
fields. Some
important
areas are
 Local market conditions for
materials and labour availability and
capabilities
 Local code, statutory etc.,
requirements
 Availability of local supervisory
personnel
 Availability of local engineering
services
 Local and global subcontractor
experience and performance
Cost Certainity & Owner
Responsiblity
 Cost certainty
 One main reason an owner may
prefer an EPC arrangement is
"certainty of cost". An EPC
contract binds the Contractor to
deliver the project at a firm,
predetermined price regardless
of any increase in costs that the
Contractor may incur after the
contract is signed. However,
changes to specifications
initiated by the owner (better
finishes for example) may be
incorporated through a "change
order". Here, the owner and the
Contractor negotiate the price to
make the changes and these
changes/prices are recorded in
the change order document
 Owner responsibility
 To ensure quality, the owner
must select an experienced EPC
contractor. A third-party or in-
house consultant can verify the
design of major structures and
inspect the main equipment
installations.
 Changes in scope of work can
affect project schedule, cost and
risk. Such changes are the
responsibility of the owner
EPC PROJECTS
OVERVIEW
Oil & energy projects
Oil and Gas Project
Categories
 Carbon Capture and Storage Facilties (11)
 Offshore Field Development (Drilling-Subsea)
(438)
 Offshore Production Facilities (127)
 Offshore Storage Facilities (1)
 Onshore Field Development (Drilling) (146)
 Onshore Production Facilities (112)
 Onshore Storage Facilities (7)
 Petrochemical and Chemical Refineries (128)
 Pipelines (57)
 Terminals (51)
Power and Energy Project
Categories
 Biomass/Energy Recovery Facilities (12)
 Carbon Capture and Storage Facilities (17)
 Coal-Fired Power Plants (75)
 Electrical Transmission and Distribution (21)
 Gas-Fired Power Plants (81)
 Geothermal Power Plants (4)
 Hydro Electric Power Plants (32)
 Nuclear Power Plants (127)
 Solar Power Plants (34)
 Wind Power (102)
Projects types
 Alumina Refinery (3)
 Boiling Water Reactor
(BWR) (7)
 Coal Export Terminal (1)
 Coal Seam Gas (2)
 Concentrators (2)
 Condeep (2)
 Condensate Field (9)
 Crude Oil Terminals (4)
 Drill Rig (11)
 Drill Ship (1)
 Fertilizer Plants (1)
 FPSO - Floating Production,
Storage and Offloading (25)
 LNG Terminal (13)
 Nickel Refinery (3) FSO -
Floating Storage and
Offloading (4)
 Gas Compression (1)
 Gas Field (73)
 Gas Processing (6)
 Gas To Liquids (GTL) Plants
(1)
 Heavy Lift Vessel (0)
 Jack Up Rigs (1)
 Jackets (9)
Projects Types
 Offshore Wind Farms (11)
 Oil Field (99)
 Oil Refinery (59)
 Oil Sands (12)
 Onshore Wind Farms (13)
 Open Pit Mine (55)
 Photovoltaic (12)
 Pipelay Vessel (5)
 Pressurised Water Reactor (PWR)
(10)
 Semi-Submersible (13)
 Shale Oil and Gas (2
 Slurry Pipeline (0)
 Solar Thermal (6)
 Solar Thermal - Dish and Sterling
(1)
 Solar Thermal - Fresnel (0)
 Solar Thermal - Parabolic (5)
 Solar Thermal - Tower (3)
 Solids Handling Facilities (1)
 Steel Plants (1)
 SURF Systems (6)
 Tailings (1)
 Tension Leg Platform (TLP) (6)
 Underground Mine (29)

Epc overview

  • 1.
    EPC OVERVIEW stands forEngineering, procurement and construction
  • 2.
    EPC overview EPC is gaining importance worldwide.It requires good understandin g by the EPCC to return a profit An EPC contract is a complex agreement. In a global context, EPC management is more complex.  EPC contract the contractor designs the installation, procures the necessary materials and builds the project, either directly or by subcontracting part of the work. In some cases, the contractor carries the project risk for schedule as well as budget in return for a fixed price, called lump sum or LSTK depending on the agreed scope of work.[1]  When the scope is restricted to engineering and procurement, this is referred to as an EP, E and P or E+P contract. This is often done in situations where the construction risk is too great for the contractor or when the owner does the construction
  • 3.
    Comparison of EPC/EPCM EPC company is able to manage all levels on site, with Construction as well  EPC contract is more critical and destined to the biggest companies - it is advantage indeed.  EPCM company is only managing build site as a Site Engineer (Supervisor on behalf of final customer.  EPCM contract is smaller type of contract than EPC, but safer for EPCM company EPCM (engineering, procurement, and construction management EPC (engineering, procurement, and construction )
  • 4.
    IMPORTANCE OF EPC Anowner decides for an EPC contract for reasons that include  Reduced stress for owner  easy work and growth of the company.  Single point of contact for owner simplifies communications.  Ready availability of post-commissioning services  Ensures quality and reduces practical issues faced in other ways[clarification needed]  Owner protected against changing prices for materials, labor, etc.  Cost is known at the start of the project
  • 5.
    Owner defines tothe EPC contract :  Scope and the specifications of the plant  Quality  Project duration  Cost  The cost (the price to be paid to the EPCC) is negotiated and finalised and paid in mutually agreed installments.
  • 6.
    Functions Engineering Functions  Initiation Planning  Estimating -> Request for Quote  Design Procurement Functions  Purchasing  Expediting  Receiving  Invoicing
  • 7.
    Construction Functions  ConstructionSchedule  On-site Material Handling  Building Activities  On-site Client Communications  Closing
  • 8.
    Projects Success bythe owner and the EPC contractor Owner Defines  Defines guarantees well  Defines scope and quality very carefully  Defines milestones meticulously  Defines LD/penalty clauses  Makes payment terms very specific EPC Contractor improves  Adopts similar terms and conditions as owner regarding quality, guarantee etc., for subcontracts/vendors  Do not keep terms open-ended  Coordinate vigilantly to reduce chances of errors at site.
  • 9.
    Global arena The EPCC musthave data and expertise in all the required fields. Some important areas are  Local market conditions for materials and labour availability and capabilities  Local code, statutory etc., requirements  Availability of local supervisory personnel  Availability of local engineering services  Local and global subcontractor experience and performance
  • 10.
    Cost Certainity &Owner Responsiblity  Cost certainty  One main reason an owner may prefer an EPC arrangement is "certainty of cost". An EPC contract binds the Contractor to deliver the project at a firm, predetermined price regardless of any increase in costs that the Contractor may incur after the contract is signed. However, changes to specifications initiated by the owner (better finishes for example) may be incorporated through a "change order". Here, the owner and the Contractor negotiate the price to make the changes and these changes/prices are recorded in the change order document  Owner responsibility  To ensure quality, the owner must select an experienced EPC contractor. A third-party or in- house consultant can verify the design of major structures and inspect the main equipment installations.  Changes in scope of work can affect project schedule, cost and risk. Such changes are the responsibility of the owner
  • 11.
  • 12.
    Oil and GasProject Categories  Carbon Capture and Storage Facilties (11)  Offshore Field Development (Drilling-Subsea) (438)  Offshore Production Facilities (127)  Offshore Storage Facilities (1)  Onshore Field Development (Drilling) (146)  Onshore Production Facilities (112)  Onshore Storage Facilities (7)  Petrochemical and Chemical Refineries (128)  Pipelines (57)  Terminals (51)
  • 13.
    Power and EnergyProject Categories  Biomass/Energy Recovery Facilities (12)  Carbon Capture and Storage Facilities (17)  Coal-Fired Power Plants (75)  Electrical Transmission and Distribution (21)  Gas-Fired Power Plants (81)  Geothermal Power Plants (4)  Hydro Electric Power Plants (32)  Nuclear Power Plants (127)  Solar Power Plants (34)  Wind Power (102)
  • 14.
    Projects types  AluminaRefinery (3)  Boiling Water Reactor (BWR) (7)  Coal Export Terminal (1)  Coal Seam Gas (2)  Concentrators (2)  Condeep (2)  Condensate Field (9)  Crude Oil Terminals (4)  Drill Rig (11)  Drill Ship (1)  Fertilizer Plants (1)  FPSO - Floating Production, Storage and Offloading (25)  LNG Terminal (13)  Nickel Refinery (3) FSO - Floating Storage and Offloading (4)  Gas Compression (1)  Gas Field (73)  Gas Processing (6)  Gas To Liquids (GTL) Plants (1)  Heavy Lift Vessel (0)  Jack Up Rigs (1)  Jackets (9)
  • 15.
    Projects Types  OffshoreWind Farms (11)  Oil Field (99)  Oil Refinery (59)  Oil Sands (12)  Onshore Wind Farms (13)  Open Pit Mine (55)  Photovoltaic (12)  Pipelay Vessel (5)  Pressurised Water Reactor (PWR) (10)  Semi-Submersible (13)  Shale Oil and Gas (2  Slurry Pipeline (0)  Solar Thermal (6)  Solar Thermal - Dish and Sterling (1)  Solar Thermal - Fresnel (0)  Solar Thermal - Parabolic (5)  Solar Thermal - Tower (3)  Solids Handling Facilities (1)  Steel Plants (1)  SURF Systems (6)  Tailings (1)  Tension Leg Platform (TLP) (6)  Underground Mine (29)