SlideShare a Scribd company logo
15-Month Executive MBA 2010

Course: Project Management

Authors:

   Abhik Tushar Das (20104001)
   Ajay Cecil (20104002)




PMC Report: Construction of a
Marine Tank Farm




                                  School of Petroleum Management,
                                  Gandhinagar, Gujarat, India

                                  www.spm.pdpu.ac.in

                                  Comments:
                                  spm_pdpu_emba10@googlegroups.com
Contents:                 The authors would like to thank Mr. ANAND
                          KUMAR SINGH (Energy Risk Professional) for his
                          sincere efforts towards guiding them through the
                          project in terms of Project Risk Management.

                                             -   Abhik Tushar Das / Ajay Cecil




       1. Project Charter
       2. Project Objectives
       3. Technical Details
       4. Project Organization Structure
       5. Work-Breakdown-Structure (WBS)
       6. Network Diagram (PERT/ CPM)
       7. Project Risk Management
       8. Microsoft Project Applications
       9. Conclusions
       10.     Key Findings




                All facts and data used in this report are hypothetical and do
                not correlate to an actual project.

                The sole purpose of this report is to demonstrate
                understanding of concepts learnt in the course titled “Project
                Management in Oil & Gas”.
Project Charter:


Trade is an important facet in the economic development of any nation. The ASSOCHAM
STUDY ON PETROLEUM TRADE™ for the period FY 1999-00 to 2006-07 has found that
petroleum products exported by India have been growing at a whopping rate of 73 per cent
for last three years with the value of oil exports expected to surpass its imports in next six
years. Petroleum is emerging as the largest foreign exchange sector in India with 16.2 per
cent share petroleum exports are expected to exceed US$ 20 billion in FY07. To facilitate
this trade, it is essential to supplement our ports with custom-bonded storage warehouses
to reduce ship turnaround time and help exporters reduce inventories at their
manufacturing locations thus reducing transaction cost.

This project envisages constructing a marine tank farm near the port of NHAVA SHEVA
(JNPT) which will cater to the numerous chemical/ petrochemical industries in the MIDC
(Maharashtra Industrial Development Corporation) as also to the two PSU refineries (BPCL
and HPCL) located at Mumbai. The Marine Tank Farm would be spread over an area of
5acres and have a cargo capacity of 100000 kilolitres with a receiving/ discharging capacity
of 200 kilolitres per hour (pumping rate). The tanks farm will be designed to store
hazardous liquid cargo (Class-A Storage) and will conform to best-in-class safety standards.

The tank farm shall have an access from NH4B which is a spur from NH 4 which links four of
the 10 most populous Indian cities - Mumbai, Pune, Bangalore and Chennai. NH 4
constitutes roughly 90% of the Golden Quadrilateral's Mumbai-Chennai segment and hence
the tank farm is strategically connected to highly industrialized cities. The tank farm is also
in proximity to Mumbai, the financial hub of India and caters to JNPT which is spread over
10 square kilometres (2,500 acres) handling bulk consignments of 7.88 million tons per
annum. The port handles 65% of India's container traffic has an average berthing period of
37 hours which is considered very long. Hence the tank farm is expected to cater to high
business volumes.
Project Objectives:


The project objectives can be listed as;




       Project area: 5 acres


       Project location: Off-NH4B (NHAVA SHEVA Port, JNPT, NaviMumbai)


       Shell Capacity: 100000 kilolitres


       Project Type: Turnkey contract


       Project construction deadline: 36 months


       Project Cost: US$ 200 million




Project Location:




                                                                         Project Area
Technical Details:
The technical details for construction can be detailed as;

    Material of construction is Mild Steel

    Type of Tank: Floating Roof tanks (20 nos)

    Diameter of Tanks: 20 meters (largest tank)

    Height of Tanks: 12 meters (highest tank)

    Tank foundation: Reinforced Concrete piling with Bitumen and sand surfacing

    Associated pipelines: 2650 meters (diameter 100mm and 200mm NB)

    Material of Storage: Petroleum derivatives (non-reactive)

    Design guidelines: OISD-STD-105/ OISD-RP-108/ OISD-STD-110/ OISD-STD-112/ OISD-

      STD-113/ OISD-STD-114/ OISD-GDN-115/ OISD-STD-117/ OISD-STD-118/ OISD-STD-

      119/ OISD-RP-149/ OISD-STD-156/ OISD-GDN-166/ OISD-RP-167

    Tank construction method: Jack-up method


Tank Foundation Details:
Project Organization Structure:



                                 Project Director



                                 Project Manager




   Project Management                Resource              Risk Management
           Team                   Management Team                Team


    1. Technical Manager          1.   Finance Manager     1. Configuration
    2. Communication              2.   Accountant             Manager
       Manager                    3.   Purchase Manager    2. Scheduler
    3. Personnel Manager          4.   Transportation/     3. Estimator
    4. Project Administrator           Logistics Manager   4. Senior    Consultant
    5. Mechanical Engineer        5.   IT Manager             (vendor)
    6. Civil Engineer             6.   Systems Manager     5. Senior    Consultant
    7. Electrical Engineer        7.   Metrics Analyst        (customer)
    8. Draftsman                  8.   Contract Manager    6. Insurance Consultant
    9. Safety Manager
    10.Contractors



PMI’s Standard for Portfolio Management:
Work Breakdown Structure (WBS):
Work breakdown structure (WBS), in project management and systems engineering, is a
deliverable oriented decomposition of a project into smaller components. It defines and
groups a project's discrete work elements in a way that helps organize and define the total
work scope of the project.

    Preconstruction Activities:
     1. Develop Technical Specifications
     2. Contractor Solicitation
     3. Pre-construction Meetings
     4. Acquisition of Permits and Licences
     5. Construction Agreements with vendors, suppliers and sub-contractors
     6. Land surveys/ Aerial Photographs/ Soil Tests
    Construction Preparation:
     1. Clearing of Site/ Demolition
     2. Land excavation/ filling
     3. Levelling
     4. Ground water removal
    Resource Acquisition:
     1. RFQ/ Tendering
     2. Vendor Selection
     3. Ordering
     4. Delivery
     5. Testing
     6. Payments
     7. Construction Equipment hiring
    Construction:
     1. Excavation
     2. Piling
     3. Tank Foundation
     4. Plate welding
    Testing and Handover:
     1. NDT Testing for Welding joints
     2. Hydro test of Tank
     3. Handover to operations
Tank Construction pictorial representation:




Some Pictures:
Network Diagram:
Precedence Table:
Task   Project Activity                              Duration   Phase   Predecessor
No.                                                  (days)
1-     Recurring Morning Meetings (Daily Activity)   Daily
137
138    Preconstruction Activities                    27
139    Develop Technical Specifications              5          1
140    Contractor Solicitation                       15                 139
141    Acquisition of Permits and Licences           20
142    Construction Agreements with vendors,         7                  140
       suppliers and sub-contractors
143 Land surveys/ Aerial Photographs/ Soil Tests     6                  141
144 Construction Preparation                         3                  141
145 Clearing of Site/ Demolition                     9                  138
146 Land excavation/ filling                         4          2       143
147 Levelling                                        2                  146
148 Ground water removal                             5                  146
149 Resource Acquisition                             60                 145
150 RFQ/ Tendering                                   30         3       139
151 Vendor Selection                                 7                  150
152 Ordering                                         3                  150
153 Delivery                                         15                 152
154 Testing                                          5                  153
155 Payments                                         7                  154
156 Construction Equipments Hiring                   3                  144
157 Construction                                     35                 149
158 Piling                                           4          4       156
159 Tank Foundation                                  6                  158
160 Plate Welding                                    25                 159
161 Testing and Handover                             4                  157
162 NDT Testing for Welding joints                   2          5       160
163 Hydro test of Tank                               3                  160
164 Handover to operations                           1                  163
Total Project Duration: 126days

Activity No’s:
Network Diagram (Critical Path Method):




   Abbreviations:

         Critical Path:
         Non Critical Path:
         Dummy Path:
         Node:



         Project time (Early/ Late finish):
Project Evaluation & Review Technique (PERT):
      Optimistic Time of completion: t0
      Most Likely Time of completion: tl
      Pessimistic Time of completion: tp
      Expected Time of completion: te

Task No. Project Activity                       t0        tl        tp        te         Std Dev Variance
      138 Preconstruction Activities
      139 Develop Technical Specifications            3         5         7          5 0.666667 0.444444
      140 Contractor Solicitation                    12        15        21       15.5      1.5     2.25
      141 Acquisition of Permits and Licences        15        20        60   25.83333      7.5    56.25
          Construction Agreements with
          vendors, suppliers and sub-
      142 contractors                                5         7         10   7.166667 0.833333 0.694444
          Land surveys/ Aerial Photographs/
      143 Soil Tests                                 4         6         7    5.833333        0.5     0.25
      144 Construction Preparation                   2         3         5    3.166667        0.5     0.25
      145 Clearing of Site/ Demolition
      146 Land excavation/ filling                   3         4         6    4.166667      0.5     0.25
      147 Levelling                                  1         2         5    2.333333 0.666667 0.444444
      148 Ground water removal                       4         5         7    5.166667      0.5     0.25
      149 Resource Acquisition
      150 RFQ/ Tendering                             20        30        60   33.33333 6.666667 44.44444
      151 Vendor Selection                            5         7         8   6.833333      0.5     0.25
      152 Ordering                                    1         3         7   3.333333        1        1
      153 Delivery                                   12        15        20   15.33333 1.333333 1.777778
      154 Testing                                     3         5         6   4.833333      0.5     0.25
      155 Payments                                    2         7         8   6.333333        1        1
      156 Construction Equipments Hiring              2         3         5   3.166667      0.5     0.25
      157 Construction
      158 Piling                                      3         4         7   4.333333 0.666667 0.444444
      159 Tank Foundation                             5         6         7          6 0.333333 0.111111
      160 Plate Welding                              22        25        35   26.16667 2.166667 4.694444
      161 Testing and Handover
      162 NDT Testing for Welding joints             1         2         4    2.166667      0.5     0.25
      163 Hydro test of Tank                         2         3         4           3 0.333333 0.111111
      164 Handover to operations                     1         1         3    1.333333 0.333333 0.111111

Here critical path is: 139-140-142-150-152-153-154-155-158-159-160-163-164
Computation of Event Times
Task No.                              Project Activity                       Duration (D)   TEi             TLi          TEj         TLj         Total Float Free Float Independent Float
     138 Preconstruction Activities
     139 Develop Technical Specifications                                               5          0               0            5           5             0          0                  0
     140 Contractor Solicitation                                                       15          5               5           20          20             0          0                  0
     141 Acquisition of Permits and Licences                                           20          0              49           20          69            49          0                -49
     142 Construction Agreements with vendors, suppliers and sub-contractors            7         20              20           27          27             0          0                  0
     143 Land surveys/ Aerial Photographs/ Soil Tests                                   6         20              69           26          75            49          0                -49
     144 Construction Preparation                                                       3         20              69           23          84            61          0                -49
     145 Clearing of Site/ Demolition
     146 Land excavation/ filling                                                       4         26              75           30          79            49          0                -49
     147 Levelling                                                                      2         30              79           32          85            53          0                -49
     148 Ground water removal                                                           5         30              79           35          84            49          0                -49
     149 Resource Acquisition
     150 RFQ/ Tendering                                                                30         27              27           57          57             0          0                  0
     151 Vendor Selection                                                               7         57              57           64          88            24          0                  0
     152 Ordering                                                                       3         57              57           60          60             0          0                  0
     153 Delivery                                                                      15         60              60           75          75             0          0                  0
     154 Testing                                                                        5         75              75           80          80             0          0                  0
     155 Payments                                                                       7         80              80           87          87             0          0                  0
     156 Construction Equipments Hiring                                                 3         35              84           38          87            49          0                -49
     157 Construction
     158 Piling                                                                         4         87              87          91            91            0          0                  0
     159 Tank Foundation                                                                6         91              91          97            97            0          0                  0
     160 Plate Welding                                                                 25         97              97         122           122            0          0                  0
     161 Testing and Handover
     162 NDT Testing for Welding joints                                                 2     122                 122        124           125            1          0                  0
     163 Hydro test of Tank                                                             3     122                 122        125           125            0          0                  0
     164 Handover to operations                                                         1     125                 125        126           126            0          0                  0

For Critical Tasks: TF=FF=IF=0

                                                                           Critical Path
Activity Nos                              Activity Name                                       t0                   tl           tp        Weightage           te    Std Dev     Variance
         139 Develop Technical Specifications                                                           3                5            7                         5   0.666667    0.444444
         140 Contractor Solicitation                                                                   12               15           21                      15.5         1.5        2.25
         142 Construction Agreements with vendors, suppliers and sub-contractors                        5                7           10                  7.166667   0.833333    0.694444
         150 RFQ/ Tendering                                                                            20               30           60                  33.33333   6.666667    44.44444
         152 Ordering                                                                                   1                3            7                  3.333333           1           1
         153 Delivery                                                                                  12               15           20                  15.33333   1.333333    1.777778
         154 Testing                                                                                    3                5            6                  4.833333         0.5        0.25
         155 Payments                                                                                   2                7            8                  6.333333           1           1
         158 Piling                                                                                     3                4            7                  4.333333   0.666667    0.444444
         159 Tank Foundation                                                                            5                6            7                         6   0.333333    0.111111
         160 Plate Welding                                                                             22               25           35                  26.16667   2.166667    4.694444
         163 Hydro test of Tank                                                                         2                3            4                         3   0.333333    0.111111
         164 Handover to operations                                                                     1                1            3                  1.333333   0.333333    0.111111
                                                                                                                                                         131.6667               57.33333

             Expected Project Duration (days)                                               131.6667
             Expected Project Variance                                                      57.33333
             Activities to be monitored                                                     44.44444 RFQ/ Tendering
             Scheduled completion of project (days)                                              120
             Probability of completion within 120 days                                      -1.54079 0.061684       6%
Project Risk Management:
Risk likelihood is the probability that a potential risk factor will actually materialize. It is
expressed numerically between:

     never happen (0)
     will happen (1)

Risk likelihood table:

S No.                                               Qualitative                                                                   Quantitative
  1                                                    Low                                                                          0 to 0.20
  2                                                  Medium                                                                        0.21 to 0.50
  3                                                   High                                                                         0.51 to 1.00


                                                                 Composite Likelihood Factor (CLF)
Activity Nos                              Activity Name                          Likelihood of Failure Weight-1 (Finance) Weight-2 (Manpower) Weight-3 (Technology)      CLF
         139 Develop Technical Specifications                                                       0.1               0.05                0.05                   0.2      0.03
         140 Contractor Solicitation                                                                0.3               0.05               0.055                  0.05    0.0465
         142 Construction Agreements with vendors, suppliers and sub-contractors                    0.5               0.01              0.0025                  0.03   0.02125
         150 RFQ/ Tendering                                                                         0.5                0.2                0.05                  0.05      0.15
         152 Ordering                                                                               0.1             0.0025                0.01                  0.01   0.00225
         153 Delivery                                                                               0.7               0.05                0.03                0.055     0.0945
         154 Testing                                                                                0.7             0.0025                0.25                   0.2   0.31675
         155 Payments                                                                               0.3               0.05                0.05                  0.05     0.045
         158 Piling                                                                                 0.3              0.055                0.05                  0.25    0.1065
         159 Tank Foundation                                                                        0.5                0.2                 0.2                  0.05     0.225
         160 Plate Welding                                                                          0.7               0.25                 0.2                  0.05      0.35
         163 Hydro test of Tank                                                                     0.9               0.03                0.05               0.0025    0.07425
         164 Handover to operations                                                                 0.5               0.05              0.0025               0.0025     0.0275
             Project CLF (max value)                                                                                     1                   1                     1      0.35

                                                                  Composite Impact Factor (CIF)
Activity Nos                              Activity Name                                 Cost impact Weight-1 (Financial) Time impact Weight-2 (Schedule)               CIF
         139 Develop Technical Specifications                                                    0.1                               0.7                                   0.28
         140 Contractor Solicitation                                                             0.5                               0.7                                   0.56
         142 Construction Agreements with vendors, suppliers and sub-contractors                 0.3                               0.5                                   0.36
         150 RFQ/ Tendering                                                                      0.3                               0.3                                    0.3
         152 Ordering                                                                            0.1                               0.7                                   0.28
         153 Delivery                                                                            0.1                               0.7                                   0.28
         154 Testing                                                                             0.1       0.7                     0.5       0.3                         0.22
         155 Payments                                                                            0.1                               0.5                                   0.22
         158 Piling                                                                              0.5                               0.7                                   0.56
         159 Tank Foundation                                                                     0.5                               0.7                                   0.56
         160 Plate Welding                                                                       0.9                               0.7                                    0.5
         163 Hydro test of Tank                                                                  0.3                               0.7                                   0.42
         164 Handover to operations                                                              0.1                               0.9                                   0.34
             Project CLF (max value)                                                                                                                                     0.56
Low                                      0.1
            Minor                                    0.3           RCR (Risk Consequence Rating)   0.714
 Likelihood Moderate                                 0.5
            Significant                              0.7
            High                                     0.9
RCR = Impact * Likelihood

Since the RCR of the project is 0.64, it is a moderately risky project and hence can be
executed with proper safeguards.

# for detailed calculations, please refer to the attached MS Excel worksheet.



MS Projects Applications:
Project Overview:
Critical Tasks:




Project Resources:
Conclusion:
The tank farm project, which is supposed to be a very lucrative project in terms of future
business prospects, faces immediate project implementation challenges in terms of high
risk of failure. Also the project envisages to be completed in 4months, would face a delay of
a fortnight, where only a remote possibility of completion (6%) within the timeframe
announced by the promoters. Although a detailed cost analysis was not undertaken due to
resource constraints, it can be safely concluded that adequate safeguards should be
implemented to mitigate project risks. In case of cost over runs due to delays in project
implementation, a cost-benefit-analysis should be performed to ascertain the benefits of
employing more man-hours during for the project vis-a-vis the cost of capital and the
opportunity cost of completing the project before time. Contractors can be given
commensurate benefits based on early completion of project.



Key Findings:
The key findings in the project can be summarized as;

   1. Lucrative business prospects
   2. Project deadline would be breached by a fortnight (inclusive of holidays)
   3. Project risk is high (RCR=0.714)
   4. High risk due to critical activities like Piling & Plate Wielding
   5. Mitigation required for the above activities which would significantly reduce risk
      exposure
   6. Manpower deployment to increase at the fag-end of the project (phase- 4/5)
   7. RFQ/ Tendering process has to be critically monitored for smooth project execution
   8. Due to high project risk, equity should be preferred over debt for capital infusion as
      high cost of capital (debt) could make the project unfeasable

More Related Content

What's hot

Building work method statement cm - ms- bw - 001
Building work method statement  cm - ms- bw - 001Building work method statement  cm - ms- bw - 001
Building work method statement cm - ms- bw - 001Minh Bui Si
 
Construction Presentations 2019
Construction Presentations 2019Construction Presentations 2019
Construction Presentations 2019
David H Moloney
 
CV for Static & Package Equipment Engineer (PMC) - V.M.Rao.
CV for Static & Package Equipment Engineer (PMC) - V.M.Rao.CV for Static & Package Equipment Engineer (PMC) - V.M.Rao.
CV for Static & Package Equipment Engineer (PMC) - V.M.Rao.Madhava Rao V
 
269831351-PIPING-Q-C-AG-UG.pdf
269831351-PIPING-Q-C-AG-UG.pdf269831351-PIPING-Q-C-AG-UG.pdf
269831351-PIPING-Q-C-AG-UG.pdf
moumo1
 
Pre bid meeting presentation
Pre bid meeting presentationPre bid meeting presentation
Pre bid meeting presentation
Riaz Zalil
 
Precommisioning and commissioning updated
Precommisioning and commissioning updatedPrecommisioning and commissioning updated
Precommisioning and commissioning updated
Personal Secret
 
Dart Underground, Dublin - Light Rail Network in Tunnels
Dart Underground, Dublin - Light Rail Network in TunnelsDart Underground, Dublin - Light Rail Network in Tunnels
Dart Underground, Dublin - Light Rail Network in Tunnels
David H Moloney
 
Project control plan_draft
Project control plan_draftProject control plan_draft
Project control plan_draft
ignitetribes
 
Engineering, procurement and construction (EPC) projects
Engineering, procurement and construction (EPC) projectsEngineering, procurement and construction (EPC) projects
Engineering, procurement and construction (EPC) projects
Nam N.N Tran M.Eng, PMP
 
Method statement piping works
Method statement piping worksMethod statement piping works
Method statement piping works
Surya Kant
 
Pipeline Design
Pipeline Design Pipeline Design
Pipeline Design
RAPHAEL AGORUA
 
6 71-0051 rev. 4 standard specification for pipeline construction (onshore)
6 71-0051 rev. 4 standard specification for pipeline construction (onshore)6 71-0051 rev. 4 standard specification for pipeline construction (onshore)
6 71-0051 rev. 4 standard specification for pipeline construction (onshore)
MAHESH PANDIT
 
Pipeline Design Report
Pipeline Design ReportPipeline Design Report
Pipeline Design Report
RAPHAEL AGORUA
 
Testing And Commissioning
Testing And CommissioningTesting And Commissioning
Testing And Commissioning
Nagarajan Subramaniam
 
Tank Design_training report_mo
Tank Design_training report_moTank Design_training report_mo
Tank Design_training report_moUdayan Biswas
 
Proposed Methodology Shore Approach
Proposed Methodology  Shore ApproachProposed Methodology  Shore Approach
Proposed Methodology Shore ApproachMohd Zaini Baharum
 
Resume_Lead Mechanical Engineer - Static Equipment and Package Units
Resume_Lead Mechanical Engineer - Static Equipment and Package UnitsResume_Lead Mechanical Engineer - Static Equipment and Package Units
Resume_Lead Mechanical Engineer - Static Equipment and Package UnitsNirav Mistry
 
Storage tanks basic training (rev 2)
Storage tanks basic training (rev 2)Storage tanks basic training (rev 2)
Storage tanks basic training (rev 2)ledzung
 

What's hot (20)

Building work method statement cm - ms- bw - 001
Building work method statement  cm - ms- bw - 001Building work method statement  cm - ms- bw - 001
Building work method statement cm - ms- bw - 001
 
Construction Presentations 2019
Construction Presentations 2019Construction Presentations 2019
Construction Presentations 2019
 
CV for Static & Package Equipment Engineer (PMC) - V.M.Rao.
CV for Static & Package Equipment Engineer (PMC) - V.M.Rao.CV for Static & Package Equipment Engineer (PMC) - V.M.Rao.
CV for Static & Package Equipment Engineer (PMC) - V.M.Rao.
 
269831351-PIPING-Q-C-AG-UG.pdf
269831351-PIPING-Q-C-AG-UG.pdf269831351-PIPING-Q-C-AG-UG.pdf
269831351-PIPING-Q-C-AG-UG.pdf
 
Pre bid meeting presentation
Pre bid meeting presentationPre bid meeting presentation
Pre bid meeting presentation
 
Precommisioning and commissioning updated
Precommisioning and commissioning updatedPrecommisioning and commissioning updated
Precommisioning and commissioning updated
 
Dart Underground, Dublin - Light Rail Network in Tunnels
Dart Underground, Dublin - Light Rail Network in TunnelsDart Underground, Dublin - Light Rail Network in Tunnels
Dart Underground, Dublin - Light Rail Network in Tunnels
 
Project control plan_draft
Project control plan_draftProject control plan_draft
Project control plan_draft
 
Epc presentation robert foxpresentation
Epc presentation robert foxpresentationEpc presentation robert foxpresentation
Epc presentation robert foxpresentation
 
Engineering, procurement and construction (EPC) projects
Engineering, procurement and construction (EPC) projectsEngineering, procurement and construction (EPC) projects
Engineering, procurement and construction (EPC) projects
 
Method statement piping works
Method statement piping worksMethod statement piping works
Method statement piping works
 
Pipeline Design
Pipeline Design Pipeline Design
Pipeline Design
 
MP Singh_ Resume 001
MP Singh_ Resume 001MP Singh_ Resume 001
MP Singh_ Resume 001
 
6 71-0051 rev. 4 standard specification for pipeline construction (onshore)
6 71-0051 rev. 4 standard specification for pipeline construction (onshore)6 71-0051 rev. 4 standard specification for pipeline construction (onshore)
6 71-0051 rev. 4 standard specification for pipeline construction (onshore)
 
Pipeline Design Report
Pipeline Design ReportPipeline Design Report
Pipeline Design Report
 
Testing And Commissioning
Testing And CommissioningTesting And Commissioning
Testing And Commissioning
 
Tank Design_training report_mo
Tank Design_training report_moTank Design_training report_mo
Tank Design_training report_mo
 
Proposed Methodology Shore Approach
Proposed Methodology  Shore ApproachProposed Methodology  Shore Approach
Proposed Methodology Shore Approach
 
Resume_Lead Mechanical Engineer - Static Equipment and Package Units
Resume_Lead Mechanical Engineer - Static Equipment and Package UnitsResume_Lead Mechanical Engineer - Static Equipment and Package Units
Resume_Lead Mechanical Engineer - Static Equipment and Package Units
 
Storage tanks basic training (rev 2)
Storage tanks basic training (rev 2)Storage tanks basic training (rev 2)
Storage tanks basic training (rev 2)
 

Similar to Project Management Report for Tank Farm

Manajemen proyek epci offshore utk kontraktor EPCI 23 aug 2014
Manajemen proyek epci offshore utk kontraktor EPCI 23 aug 2014Manajemen proyek epci offshore utk kontraktor EPCI 23 aug 2014
Manajemen proyek epci offshore utk kontraktor EPCI 23 aug 2014
Aestikani Mahani
 
IDT's Presentation.pptx
IDT's Presentation.pptxIDT's Presentation.pptx
IDT's Presentation.pptx
ONGCWCS
 
INDUSTRIAL TRAINING REPORT
INDUSTRIAL TRAINING REPORTINDUSTRIAL TRAINING REPORT
INDUSTRIAL TRAINING REPORTNur Ain Samsudin
 
Anthony pangras latest
Anthony pangras latestAnthony pangras latest
Anthony pangras latest
Vincent Anthony Pangras
 
Lead Process Engineer
Lead Process EngineerLead Process Engineer
Lead Process EngineerJuber Loharia
 
Project Route Map - OMC South Kaliapani Chromite UG Mine
Project Route Map - OMC South Kaliapani Chromite UG MineProject Route Map - OMC South Kaliapani Chromite UG Mine
Project Route Map - OMC South Kaliapani Chromite UG Mine
Tapas Das
 
Civil-Report on industrial training at URCC
Civil-Report on industrial training at URCCCivil-Report on industrial training at URCC
Civil-Report on industrial training at URCC
Rakshita Raghunath
 
Method statement tank base concrete pouring
Method statement  tank base concrete pouringMethod statement  tank base concrete pouring
Method statement tank base concrete pouring
Bharatha Rathnayke
 
Ian_Rowell_Resume_June_2015
Ian_Rowell_Resume_June_2015Ian_Rowell_Resume_June_2015
Ian_Rowell_Resume_June_2015Ian Rowell
 
General_ENTRION_Presentation_December2015
General_ENTRION_Presentation_December2015General_ENTRION_Presentation_December2015
General_ENTRION_Presentation_December2015Arun Jothilingam
 
FPSO & FLNG Asia 2016 - Final
FPSO & FLNG Asia 2016 - FinalFPSO & FLNG Asia 2016 - Final
FPSO & FLNG Asia 2016 - FinalGurin Hanspal
 

Similar to Project Management Report for Tank Farm (20)

Manajemen proyek epci offshore utk kontraktor EPCI 23 aug 2014
Manajemen proyek epci offshore utk kontraktor EPCI 23 aug 2014Manajemen proyek epci offshore utk kontraktor EPCI 23 aug 2014
Manajemen proyek epci offshore utk kontraktor EPCI 23 aug 2014
 
IDT's Presentation.pptx
IDT's Presentation.pptxIDT's Presentation.pptx
IDT's Presentation.pptx
 
Salakidis Savvas
Salakidis SavvasSalakidis Savvas
Salakidis Savvas
 
INDUSTRIAL TRAINING REPORT
INDUSTRIAL TRAINING REPORTINDUSTRIAL TRAINING REPORT
INDUSTRIAL TRAINING REPORT
 
Anthony pangras latest
Anthony pangras latestAnthony pangras latest
Anthony pangras latest
 
Lead Process Engineer
Lead Process EngineerLead Process Engineer
Lead Process Engineer
 
Project Route Map - OMC South Kaliapani Chromite UG Mine
Project Route Map - OMC South Kaliapani Chromite UG MineProject Route Map - OMC South Kaliapani Chromite UG Mine
Project Route Map - OMC South Kaliapani Chromite UG Mine
 
Civil-Report on industrial training at URCC
Civil-Report on industrial training at URCCCivil-Report on industrial training at URCC
Civil-Report on industrial training at URCC
 
Resume
ResumeResume
Resume
 
CV-PM
CV-PMCV-PM
CV-PM
 
AH15019
AH15019AH15019
AH15019
 
Method statement tank base concrete pouring
Method statement  tank base concrete pouringMethod statement  tank base concrete pouring
Method statement tank base concrete pouring
 
Ian_Rowell_Resume_June_2015
Ian_Rowell_Resume_June_2015Ian_Rowell_Resume_June_2015
Ian_Rowell_Resume_June_2015
 
CV-Pon
CV-PonCV-Pon
CV-Pon
 
Monthly Progress Report - September 2014
Monthly Progress Report - September 2014Monthly Progress Report - September 2014
Monthly Progress Report - September 2014
 
CV
CVCV
CV
 
General_ENTRION_Presentation_December2015
General_ENTRION_Presentation_December2015General_ENTRION_Presentation_December2015
General_ENTRION_Presentation_December2015
 
CV of broosto -7-2016
CV of broosto -7-2016CV of broosto -7-2016
CV of broosto -7-2016
 
FPSO & FLNG Asia 2016 - Final
FPSO & FLNG Asia 2016 - FinalFPSO & FLNG Asia 2016 - Final
FPSO & FLNG Asia 2016 - Final
 
CV_Thangaraj Raja
CV_Thangaraj RajaCV_Thangaraj Raja
CV_Thangaraj Raja
 

More from Abhik Tushar Das

Final Presentation on Renewable Energy_GSFC_EMC_23.05.2015
Final Presentation on Renewable Energy_GSFC_EMC_23.05.2015Final Presentation on Renewable Energy_GSFC_EMC_23.05.2015
Final Presentation on Renewable Energy_GSFC_EMC_23.05.2015Abhik Tushar Das
 
Microsoft Projects; a step by-step guide for beginner's
Microsoft Projects; a step by-step guide for beginner'sMicrosoft Projects; a step by-step guide for beginner's
Microsoft Projects; a step by-step guide for beginner's
Abhik Tushar Das
 
CGD Business in India: a report
CGD Business in India: a reportCGD Business in India: a report
CGD Business in India: a report
Abhik Tushar Das
 
Cement Industry Analysis
Cement Industry AnalysisCement Industry Analysis
Cement Industry Analysis
Abhik Tushar Das
 
Status and potential of energy and carbon trading in india
Status and potential of energy and carbon trading in indiaStatus and potential of energy and carbon trading in india
Status and potential of energy and carbon trading in india
Abhik Tushar Das
 
Cross Cultural Report on South Africa
Cross Cultural Report on South AfricaCross Cultural Report on South Africa
Cross Cultural Report on South AfricaAbhik Tushar Das
 
Marketing Plan for Cold Bitumen in India
Marketing Plan for Cold Bitumen in IndiaMarketing Plan for Cold Bitumen in India
Marketing Plan for Cold Bitumen in IndiaAbhik Tushar Das
 
Concept of a Global Currency
Concept of a Global CurrencyConcept of a Global Currency
Concept of a Global CurrencyAbhik Tushar Das
 
College Offsite emergency for PDPU
College Offsite emergency for PDPUCollege Offsite emergency for PDPU
College Offsite emergency for PDPUAbhik Tushar Das
 
Information Technology At Ici
Information Technology At IciInformation Technology At Ici
Information Technology At IciAbhik Tushar Das
 
Innovation: In the minds of Young India
Innovation: In the minds of Young IndiaInnovation: In the minds of Young India
Innovation: In the minds of Young IndiaAbhik Tushar Das
 
Report on Feminine Car (business research methods)
Report on Feminine Car (business research methods)Report on Feminine Car (business research methods)
Report on Feminine Car (business research methods)
Abhik Tushar Das
 
Service oriented architecture
Service oriented architectureService oriented architecture
Service oriented architectureAbhik Tushar Das
 
Smm marketing mix project_exe-mba-10_20104001
Smm marketing mix project_exe-mba-10_20104001Smm marketing mix project_exe-mba-10_20104001
Smm marketing mix project_exe-mba-10_20104001Abhik Tushar Das
 
Service oriented architecture & web 2.0
Service oriented architecture & web 2.0Service oriented architecture & web 2.0
Service oriented architecture & web 2.0Abhik Tushar Das
 

More from Abhik Tushar Das (20)

Final Presentation on Renewable Energy_GSFC_EMC_23.05.2015
Final Presentation on Renewable Energy_GSFC_EMC_23.05.2015Final Presentation on Renewable Energy_GSFC_EMC_23.05.2015
Final Presentation on Renewable Energy_GSFC_EMC_23.05.2015
 
Microsoft Projects; a step by-step guide for beginner's
Microsoft Projects; a step by-step guide for beginner'sMicrosoft Projects; a step by-step guide for beginner's
Microsoft Projects; a step by-step guide for beginner's
 
CGD Business in India: a report
CGD Business in India: a reportCGD Business in India: a report
CGD Business in India: a report
 
Cement Industry Analysis
Cement Industry AnalysisCement Industry Analysis
Cement Industry Analysis
 
Status and potential of energy and carbon trading in india
Status and potential of energy and carbon trading in indiaStatus and potential of energy and carbon trading in india
Status and potential of energy and carbon trading in india
 
Cross Cultural Report on South Africa
Cross Cultural Report on South AfricaCross Cultural Report on South Africa
Cross Cultural Report on South Africa
 
Marketing Plan for Cold Bitumen in India
Marketing Plan for Cold Bitumen in IndiaMarketing Plan for Cold Bitumen in India
Marketing Plan for Cold Bitumen in India
 
Concept of a Global Currency
Concept of a Global CurrencyConcept of a Global Currency
Concept of a Global Currency
 
College Offsite emergency for PDPU
College Offsite emergency for PDPUCollege Offsite emergency for PDPU
College Offsite emergency for PDPU
 
Bp Amoco (case study)
Bp Amoco (case study)Bp Amoco (case study)
Bp Amoco (case study)
 
Fuel substitution report
Fuel substitution reportFuel substitution report
Fuel substitution report
 
Training & Development
Training & DevelopmentTraining & Development
Training & Development
 
Information Technology At Ici
Information Technology At IciInformation Technology At Ici
Information Technology At Ici
 
Innovation: In the minds of Young India
Innovation: In the minds of Young IndiaInnovation: In the minds of Young India
Innovation: In the minds of Young India
 
Report on Feminine Car (business research methods)
Report on Feminine Car (business research methods)Report on Feminine Car (business research methods)
Report on Feminine Car (business research methods)
 
Service oriented architecture
Service oriented architectureService oriented architecture
Service oriented architecture
 
Branding in advertising
Branding in advertisingBranding in advertising
Branding in advertising
 
Smm marketing mix project_exe-mba-10_20104001
Smm marketing mix project_exe-mba-10_20104001Smm marketing mix project_exe-mba-10_20104001
Smm marketing mix project_exe-mba-10_20104001
 
Service oriented architecture & web 2.0
Service oriented architecture & web 2.0Service oriented architecture & web 2.0
Service oriented architecture & web 2.0
 
Innovation
InnovationInnovation
Innovation
 

Recently uploaded

Taurus Zodiac Sign_ Personality Traits and Sign Dates.pptx
Taurus Zodiac Sign_ Personality Traits and Sign Dates.pptxTaurus Zodiac Sign_ Personality Traits and Sign Dates.pptx
Taurus Zodiac Sign_ Personality Traits and Sign Dates.pptx
my Pandit
 
Lookback Analysis
Lookback AnalysisLookback Analysis
Lookback Analysis
Safe PaaS
 
April 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products NewsletterApril 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products Newsletter
NathanBaughman3
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
Cynthia Clay
 
Memorandum Of Association Constitution of Company.ppt
Memorandum Of Association Constitution of Company.pptMemorandum Of Association Constitution of Company.ppt
Memorandum Of Association Constitution of Company.ppt
seri bangash
 
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdfSearch Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Arihant Webtech Pvt. Ltd
 
Filing Your Delaware Franchise Tax A Detailed Guide
Filing Your Delaware Franchise Tax A Detailed GuideFiling Your Delaware Franchise Tax A Detailed Guide
Filing Your Delaware Franchise Tax A Detailed Guide
YourLegal Accounting
 
Attending a job Interview for B1 and B2 Englsih learners
Attending a job Interview for B1 and B2 Englsih learnersAttending a job Interview for B1 and B2 Englsih learners
Attending a job Interview for B1 and B2 Englsih learners
Erika906060
 
Brand Analysis for an artist named Struan
Brand Analysis for an artist named StruanBrand Analysis for an artist named Struan
Brand Analysis for an artist named Struan
sarahvanessa51503
 
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdfMeas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
dylandmeas
 
The Parable of the Pipeline a book every new businessman or business student ...
The Parable of the Pipeline a book every new businessman or business student ...The Parable of the Pipeline a book every new businessman or business student ...
The Parable of the Pipeline a book every new businessman or business student ...
awaisafdar
 
Role of Remote Sensing and Monitoring in Mining
Role of Remote Sensing and Monitoring in MiningRole of Remote Sensing and Monitoring in Mining
Role of Remote Sensing and Monitoring in Mining
Naaraayani Minerals Pvt.Ltd
 
Enterprise Excellence is Inclusive Excellence.pdf
Enterprise Excellence is Inclusive Excellence.pdfEnterprise Excellence is Inclusive Excellence.pdf
Enterprise Excellence is Inclusive Excellence.pdf
KaiNexus
 
BeMetals Presentation_May_22_2024 .pdf
BeMetals Presentation_May_22_2024   .pdfBeMetals Presentation_May_22_2024   .pdf
BeMetals Presentation_May_22_2024 .pdf
DerekIwanaka1
 
What is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdfWhat is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdf
seoforlegalpillers
 
Skye Residences | Extended Stay Residences Near Toronto Airport
Skye Residences | Extended Stay Residences Near Toronto AirportSkye Residences | Extended Stay Residences Near Toronto Airport
Skye Residences | Extended Stay Residences Near Toronto Airport
marketingjdass
 
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
BBPMedia1
 
FINAL PRESENTATION.pptx12143241324134134
FINAL PRESENTATION.pptx12143241324134134FINAL PRESENTATION.pptx12143241324134134
FINAL PRESENTATION.pptx12143241324134134
LR1709MUSIC
 
anas about venice for grade 6f about venice
anas about venice for grade 6f about veniceanas about venice for grade 6f about venice
anas about venice for grade 6f about venice
anasabutalha2013
 
Premium MEAN Stack Development Solutions for Modern Businesses
Premium MEAN Stack Development Solutions for Modern BusinessesPremium MEAN Stack Development Solutions for Modern Businesses
Premium MEAN Stack Development Solutions for Modern Businesses
SynapseIndia
 

Recently uploaded (20)

Taurus Zodiac Sign_ Personality Traits and Sign Dates.pptx
Taurus Zodiac Sign_ Personality Traits and Sign Dates.pptxTaurus Zodiac Sign_ Personality Traits and Sign Dates.pptx
Taurus Zodiac Sign_ Personality Traits and Sign Dates.pptx
 
Lookback Analysis
Lookback AnalysisLookback Analysis
Lookback Analysis
 
April 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products NewsletterApril 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products Newsletter
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
 
Memorandum Of Association Constitution of Company.ppt
Memorandum Of Association Constitution of Company.pptMemorandum Of Association Constitution of Company.ppt
Memorandum Of Association Constitution of Company.ppt
 
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdfSearch Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdf
 
Filing Your Delaware Franchise Tax A Detailed Guide
Filing Your Delaware Franchise Tax A Detailed GuideFiling Your Delaware Franchise Tax A Detailed Guide
Filing Your Delaware Franchise Tax A Detailed Guide
 
Attending a job Interview for B1 and B2 Englsih learners
Attending a job Interview for B1 and B2 Englsih learnersAttending a job Interview for B1 and B2 Englsih learners
Attending a job Interview for B1 and B2 Englsih learners
 
Brand Analysis for an artist named Struan
Brand Analysis for an artist named StruanBrand Analysis for an artist named Struan
Brand Analysis for an artist named Struan
 
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdfMeas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
 
The Parable of the Pipeline a book every new businessman or business student ...
The Parable of the Pipeline a book every new businessman or business student ...The Parable of the Pipeline a book every new businessman or business student ...
The Parable of the Pipeline a book every new businessman or business student ...
 
Role of Remote Sensing and Monitoring in Mining
Role of Remote Sensing and Monitoring in MiningRole of Remote Sensing and Monitoring in Mining
Role of Remote Sensing and Monitoring in Mining
 
Enterprise Excellence is Inclusive Excellence.pdf
Enterprise Excellence is Inclusive Excellence.pdfEnterprise Excellence is Inclusive Excellence.pdf
Enterprise Excellence is Inclusive Excellence.pdf
 
BeMetals Presentation_May_22_2024 .pdf
BeMetals Presentation_May_22_2024   .pdfBeMetals Presentation_May_22_2024   .pdf
BeMetals Presentation_May_22_2024 .pdf
 
What is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdfWhat is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdf
 
Skye Residences | Extended Stay Residences Near Toronto Airport
Skye Residences | Extended Stay Residences Near Toronto AirportSkye Residences | Extended Stay Residences Near Toronto Airport
Skye Residences | Extended Stay Residences Near Toronto Airport
 
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
 
FINAL PRESENTATION.pptx12143241324134134
FINAL PRESENTATION.pptx12143241324134134FINAL PRESENTATION.pptx12143241324134134
FINAL PRESENTATION.pptx12143241324134134
 
anas about venice for grade 6f about venice
anas about venice for grade 6f about veniceanas about venice for grade 6f about venice
anas about venice for grade 6f about venice
 
Premium MEAN Stack Development Solutions for Modern Businesses
Premium MEAN Stack Development Solutions for Modern BusinessesPremium MEAN Stack Development Solutions for Modern Businesses
Premium MEAN Stack Development Solutions for Modern Businesses
 

Project Management Report for Tank Farm

  • 1. 15-Month Executive MBA 2010 Course: Project Management Authors:  Abhik Tushar Das (20104001)  Ajay Cecil (20104002) PMC Report: Construction of a Marine Tank Farm School of Petroleum Management, Gandhinagar, Gujarat, India www.spm.pdpu.ac.in Comments: spm_pdpu_emba10@googlegroups.com
  • 2. Contents: The authors would like to thank Mr. ANAND KUMAR SINGH (Energy Risk Professional) for his sincere efforts towards guiding them through the project in terms of Project Risk Management. - Abhik Tushar Das / Ajay Cecil 1. Project Charter 2. Project Objectives 3. Technical Details 4. Project Organization Structure 5. Work-Breakdown-Structure (WBS) 6. Network Diagram (PERT/ CPM) 7. Project Risk Management 8. Microsoft Project Applications 9. Conclusions 10. Key Findings All facts and data used in this report are hypothetical and do not correlate to an actual project. The sole purpose of this report is to demonstrate understanding of concepts learnt in the course titled “Project Management in Oil & Gas”.
  • 3. Project Charter: Trade is an important facet in the economic development of any nation. The ASSOCHAM STUDY ON PETROLEUM TRADE™ for the period FY 1999-00 to 2006-07 has found that petroleum products exported by India have been growing at a whopping rate of 73 per cent for last three years with the value of oil exports expected to surpass its imports in next six years. Petroleum is emerging as the largest foreign exchange sector in India with 16.2 per cent share petroleum exports are expected to exceed US$ 20 billion in FY07. To facilitate this trade, it is essential to supplement our ports with custom-bonded storage warehouses to reduce ship turnaround time and help exporters reduce inventories at their manufacturing locations thus reducing transaction cost. This project envisages constructing a marine tank farm near the port of NHAVA SHEVA (JNPT) which will cater to the numerous chemical/ petrochemical industries in the MIDC (Maharashtra Industrial Development Corporation) as also to the two PSU refineries (BPCL and HPCL) located at Mumbai. The Marine Tank Farm would be spread over an area of 5acres and have a cargo capacity of 100000 kilolitres with a receiving/ discharging capacity of 200 kilolitres per hour (pumping rate). The tanks farm will be designed to store hazardous liquid cargo (Class-A Storage) and will conform to best-in-class safety standards. The tank farm shall have an access from NH4B which is a spur from NH 4 which links four of the 10 most populous Indian cities - Mumbai, Pune, Bangalore and Chennai. NH 4 constitutes roughly 90% of the Golden Quadrilateral's Mumbai-Chennai segment and hence the tank farm is strategically connected to highly industrialized cities. The tank farm is also in proximity to Mumbai, the financial hub of India and caters to JNPT which is spread over 10 square kilometres (2,500 acres) handling bulk consignments of 7.88 million tons per annum. The port handles 65% of India's container traffic has an average berthing period of 37 hours which is considered very long. Hence the tank farm is expected to cater to high business volumes.
  • 4. Project Objectives: The project objectives can be listed as; Project area: 5 acres Project location: Off-NH4B (NHAVA SHEVA Port, JNPT, NaviMumbai) Shell Capacity: 100000 kilolitres Project Type: Turnkey contract Project construction deadline: 36 months Project Cost: US$ 200 million Project Location: Project Area
  • 5. Technical Details: The technical details for construction can be detailed as;  Material of construction is Mild Steel  Type of Tank: Floating Roof tanks (20 nos)  Diameter of Tanks: 20 meters (largest tank)  Height of Tanks: 12 meters (highest tank)  Tank foundation: Reinforced Concrete piling with Bitumen and sand surfacing  Associated pipelines: 2650 meters (diameter 100mm and 200mm NB)  Material of Storage: Petroleum derivatives (non-reactive)  Design guidelines: OISD-STD-105/ OISD-RP-108/ OISD-STD-110/ OISD-STD-112/ OISD- STD-113/ OISD-STD-114/ OISD-GDN-115/ OISD-STD-117/ OISD-STD-118/ OISD-STD- 119/ OISD-RP-149/ OISD-STD-156/ OISD-GDN-166/ OISD-RP-167  Tank construction method: Jack-up method Tank Foundation Details:
  • 6. Project Organization Structure: Project Director Project Manager Project Management Resource Risk Management Team Management Team Team 1. Technical Manager 1. Finance Manager 1. Configuration 2. Communication 2. Accountant Manager Manager 3. Purchase Manager 2. Scheduler 3. Personnel Manager 4. Transportation/ 3. Estimator 4. Project Administrator Logistics Manager 4. Senior Consultant 5. Mechanical Engineer 5. IT Manager (vendor) 6. Civil Engineer 6. Systems Manager 5. Senior Consultant 7. Electrical Engineer 7. Metrics Analyst (customer) 8. Draftsman 8. Contract Manager 6. Insurance Consultant 9. Safety Manager 10.Contractors PMI’s Standard for Portfolio Management:
  • 7. Work Breakdown Structure (WBS): Work breakdown structure (WBS), in project management and systems engineering, is a deliverable oriented decomposition of a project into smaller components. It defines and groups a project's discrete work elements in a way that helps organize and define the total work scope of the project.  Preconstruction Activities: 1. Develop Technical Specifications 2. Contractor Solicitation 3. Pre-construction Meetings 4. Acquisition of Permits and Licences 5. Construction Agreements with vendors, suppliers and sub-contractors 6. Land surveys/ Aerial Photographs/ Soil Tests  Construction Preparation: 1. Clearing of Site/ Demolition 2. Land excavation/ filling 3. Levelling 4. Ground water removal  Resource Acquisition: 1. RFQ/ Tendering 2. Vendor Selection 3. Ordering 4. Delivery 5. Testing 6. Payments 7. Construction Equipment hiring  Construction: 1. Excavation 2. Piling 3. Tank Foundation 4. Plate welding  Testing and Handover: 1. NDT Testing for Welding joints 2. Hydro test of Tank 3. Handover to operations
  • 8. Tank Construction pictorial representation: Some Pictures:
  • 10. Precedence Table: Task Project Activity Duration Phase Predecessor No. (days) 1- Recurring Morning Meetings (Daily Activity) Daily 137 138 Preconstruction Activities 27 139 Develop Technical Specifications 5 1 140 Contractor Solicitation 15 139 141 Acquisition of Permits and Licences 20 142 Construction Agreements with vendors, 7 140 suppliers and sub-contractors 143 Land surveys/ Aerial Photographs/ Soil Tests 6 141 144 Construction Preparation 3 141 145 Clearing of Site/ Demolition 9 138 146 Land excavation/ filling 4 2 143 147 Levelling 2 146 148 Ground water removal 5 146 149 Resource Acquisition 60 145 150 RFQ/ Tendering 30 3 139 151 Vendor Selection 7 150 152 Ordering 3 150 153 Delivery 15 152 154 Testing 5 153 155 Payments 7 154 156 Construction Equipments Hiring 3 144 157 Construction 35 149 158 Piling 4 4 156 159 Tank Foundation 6 158 160 Plate Welding 25 159 161 Testing and Handover 4 157 162 NDT Testing for Welding joints 2 5 160 163 Hydro test of Tank 3 160 164 Handover to operations 1 163 Total Project Duration: 126days Activity No’s:
  • 11. Network Diagram (Critical Path Method): Abbreviations:  Critical Path:  Non Critical Path:  Dummy Path:  Node:  Project time (Early/ Late finish):
  • 12. Project Evaluation & Review Technique (PERT):  Optimistic Time of completion: t0  Most Likely Time of completion: tl  Pessimistic Time of completion: tp  Expected Time of completion: te Task No. Project Activity t0 tl tp te Std Dev Variance 138 Preconstruction Activities 139 Develop Technical Specifications 3 5 7 5 0.666667 0.444444 140 Contractor Solicitation 12 15 21 15.5 1.5 2.25 141 Acquisition of Permits and Licences 15 20 60 25.83333 7.5 56.25 Construction Agreements with vendors, suppliers and sub- 142 contractors 5 7 10 7.166667 0.833333 0.694444 Land surveys/ Aerial Photographs/ 143 Soil Tests 4 6 7 5.833333 0.5 0.25 144 Construction Preparation 2 3 5 3.166667 0.5 0.25 145 Clearing of Site/ Demolition 146 Land excavation/ filling 3 4 6 4.166667 0.5 0.25 147 Levelling 1 2 5 2.333333 0.666667 0.444444 148 Ground water removal 4 5 7 5.166667 0.5 0.25 149 Resource Acquisition 150 RFQ/ Tendering 20 30 60 33.33333 6.666667 44.44444 151 Vendor Selection 5 7 8 6.833333 0.5 0.25 152 Ordering 1 3 7 3.333333 1 1 153 Delivery 12 15 20 15.33333 1.333333 1.777778 154 Testing 3 5 6 4.833333 0.5 0.25 155 Payments 2 7 8 6.333333 1 1 156 Construction Equipments Hiring 2 3 5 3.166667 0.5 0.25 157 Construction 158 Piling 3 4 7 4.333333 0.666667 0.444444 159 Tank Foundation 5 6 7 6 0.333333 0.111111 160 Plate Welding 22 25 35 26.16667 2.166667 4.694444 161 Testing and Handover 162 NDT Testing for Welding joints 1 2 4 2.166667 0.5 0.25 163 Hydro test of Tank 2 3 4 3 0.333333 0.111111 164 Handover to operations 1 1 3 1.333333 0.333333 0.111111 Here critical path is: 139-140-142-150-152-153-154-155-158-159-160-163-164
  • 13. Computation of Event Times Task No. Project Activity Duration (D) TEi TLi TEj TLj Total Float Free Float Independent Float 138 Preconstruction Activities 139 Develop Technical Specifications 5 0 0 5 5 0 0 0 140 Contractor Solicitation 15 5 5 20 20 0 0 0 141 Acquisition of Permits and Licences 20 0 49 20 69 49 0 -49 142 Construction Agreements with vendors, suppliers and sub-contractors 7 20 20 27 27 0 0 0 143 Land surveys/ Aerial Photographs/ Soil Tests 6 20 69 26 75 49 0 -49 144 Construction Preparation 3 20 69 23 84 61 0 -49 145 Clearing of Site/ Demolition 146 Land excavation/ filling 4 26 75 30 79 49 0 -49 147 Levelling 2 30 79 32 85 53 0 -49 148 Ground water removal 5 30 79 35 84 49 0 -49 149 Resource Acquisition 150 RFQ/ Tendering 30 27 27 57 57 0 0 0 151 Vendor Selection 7 57 57 64 88 24 0 0 152 Ordering 3 57 57 60 60 0 0 0 153 Delivery 15 60 60 75 75 0 0 0 154 Testing 5 75 75 80 80 0 0 0 155 Payments 7 80 80 87 87 0 0 0 156 Construction Equipments Hiring 3 35 84 38 87 49 0 -49 157 Construction 158 Piling 4 87 87 91 91 0 0 0 159 Tank Foundation 6 91 91 97 97 0 0 0 160 Plate Welding 25 97 97 122 122 0 0 0 161 Testing and Handover 162 NDT Testing for Welding joints 2 122 122 124 125 1 0 0 163 Hydro test of Tank 3 122 122 125 125 0 0 0 164 Handover to operations 1 125 125 126 126 0 0 0 For Critical Tasks: TF=FF=IF=0 Critical Path Activity Nos Activity Name t0 tl tp Weightage te Std Dev Variance 139 Develop Technical Specifications 3 5 7 5 0.666667 0.444444 140 Contractor Solicitation 12 15 21 15.5 1.5 2.25 142 Construction Agreements with vendors, suppliers and sub-contractors 5 7 10 7.166667 0.833333 0.694444 150 RFQ/ Tendering 20 30 60 33.33333 6.666667 44.44444 152 Ordering 1 3 7 3.333333 1 1 153 Delivery 12 15 20 15.33333 1.333333 1.777778 154 Testing 3 5 6 4.833333 0.5 0.25 155 Payments 2 7 8 6.333333 1 1 158 Piling 3 4 7 4.333333 0.666667 0.444444 159 Tank Foundation 5 6 7 6 0.333333 0.111111 160 Plate Welding 22 25 35 26.16667 2.166667 4.694444 163 Hydro test of Tank 2 3 4 3 0.333333 0.111111 164 Handover to operations 1 1 3 1.333333 0.333333 0.111111 131.6667 57.33333 Expected Project Duration (days) 131.6667 Expected Project Variance 57.33333 Activities to be monitored 44.44444 RFQ/ Tendering Scheduled completion of project (days) 120 Probability of completion within 120 days -1.54079 0.061684 6%
  • 14. Project Risk Management: Risk likelihood is the probability that a potential risk factor will actually materialize. It is expressed numerically between:  never happen (0)  will happen (1) Risk likelihood table: S No. Qualitative Quantitative 1 Low 0 to 0.20 2 Medium 0.21 to 0.50 3 High 0.51 to 1.00 Composite Likelihood Factor (CLF) Activity Nos Activity Name Likelihood of Failure Weight-1 (Finance) Weight-2 (Manpower) Weight-3 (Technology) CLF 139 Develop Technical Specifications 0.1 0.05 0.05 0.2 0.03 140 Contractor Solicitation 0.3 0.05 0.055 0.05 0.0465 142 Construction Agreements with vendors, suppliers and sub-contractors 0.5 0.01 0.0025 0.03 0.02125 150 RFQ/ Tendering 0.5 0.2 0.05 0.05 0.15 152 Ordering 0.1 0.0025 0.01 0.01 0.00225 153 Delivery 0.7 0.05 0.03 0.055 0.0945 154 Testing 0.7 0.0025 0.25 0.2 0.31675 155 Payments 0.3 0.05 0.05 0.05 0.045 158 Piling 0.3 0.055 0.05 0.25 0.1065 159 Tank Foundation 0.5 0.2 0.2 0.05 0.225 160 Plate Welding 0.7 0.25 0.2 0.05 0.35 163 Hydro test of Tank 0.9 0.03 0.05 0.0025 0.07425 164 Handover to operations 0.5 0.05 0.0025 0.0025 0.0275 Project CLF (max value) 1 1 1 0.35 Composite Impact Factor (CIF) Activity Nos Activity Name Cost impact Weight-1 (Financial) Time impact Weight-2 (Schedule) CIF 139 Develop Technical Specifications 0.1 0.7 0.28 140 Contractor Solicitation 0.5 0.7 0.56 142 Construction Agreements with vendors, suppliers and sub-contractors 0.3 0.5 0.36 150 RFQ/ Tendering 0.3 0.3 0.3 152 Ordering 0.1 0.7 0.28 153 Delivery 0.1 0.7 0.28 154 Testing 0.1 0.7 0.5 0.3 0.22 155 Payments 0.1 0.5 0.22 158 Piling 0.5 0.7 0.56 159 Tank Foundation 0.5 0.7 0.56 160 Plate Welding 0.9 0.7 0.5 163 Hydro test of Tank 0.3 0.7 0.42 164 Handover to operations 0.1 0.9 0.34 Project CLF (max value) 0.56
  • 15. Low 0.1 Minor 0.3 RCR (Risk Consequence Rating) 0.714 Likelihood Moderate 0.5 Significant 0.7 High 0.9 RCR = Impact * Likelihood Since the RCR of the project is 0.64, it is a moderately risky project and hence can be executed with proper safeguards. # for detailed calculations, please refer to the attached MS Excel worksheet. MS Projects Applications: Project Overview:
  • 17. Conclusion: The tank farm project, which is supposed to be a very lucrative project in terms of future business prospects, faces immediate project implementation challenges in terms of high risk of failure. Also the project envisages to be completed in 4months, would face a delay of a fortnight, where only a remote possibility of completion (6%) within the timeframe announced by the promoters. Although a detailed cost analysis was not undertaken due to resource constraints, it can be safely concluded that adequate safeguards should be implemented to mitigate project risks. In case of cost over runs due to delays in project implementation, a cost-benefit-analysis should be performed to ascertain the benefits of employing more man-hours during for the project vis-a-vis the cost of capital and the opportunity cost of completing the project before time. Contractors can be given commensurate benefits based on early completion of project. Key Findings: The key findings in the project can be summarized as; 1. Lucrative business prospects 2. Project deadline would be breached by a fortnight (inclusive of holidays) 3. Project risk is high (RCR=0.714) 4. High risk due to critical activities like Piling & Plate Wielding 5. Mitigation required for the above activities which would significantly reduce risk exposure 6. Manpower deployment to increase at the fag-end of the project (phase- 4/5) 7. RFQ/ Tendering process has to be critically monitored for smooth project execution 8. Due to high project risk, equity should be preferred over debt for capital infusion as high cost of capital (debt) could make the project unfeasable