SlideShare a Scribd company logo
1 of 22
Wind power projects
Construction and O&M
Weero Koster
25 April 2013
Typical turbine structure
Typical PF Structure
PUBLIC ENTITY

SPONSOR
EQUITY

INSURERS

CONCESSION
CONTRACT

THIRD PARTY
EQUITY
INVESTORS

SPV
INVESTORS

MEZZANINE
FUNDERS

SENIOR
FUNDERS
(BANK/BOND)

SURPLUS REAL ESTATE
DISPOSAL

CONSTRUCTION

SUBCONTRACTOR 1

OPERATION &
MAINTENANCE

EQUIPMENT SUPPLY

SUBCONTRACTOR 3

DEVELOPER

BONDS &
GUARANTEES

DESIGNERS
DUE DILIGENCE
ADVISER 1

SURETIES &
GUARANTORS

DUE DILIGENCE
ADVISER 3
DUE DILIGENCE
ADVISER 2

3

SUBCONTRACTOR 2
EPC Structure
Where does EPC fit in?
Owner
assumes
risk
Construction
Management

RISK SPECTRUM

Traditional

Design &
Build

Contractor
retains risk

LSTK/
EPC

Except as otherwise stated in the Contract:

a)

the Contractor shall be deemed to have obtained all necessary information as to risks,
contingencies and other circumstances which may influence or affect the Works;

b)

by signing the Contract, the Contractor accepts total responsibility for having foreseen
all difficulties and costs of successfully completing the Works; and

c)

the Contract Price shall – Engineering Procurement and Construction
EPC not be adjusted to take account of any unforeseen difficulties or
costs.

LSTK – Lump Sum Turnkey

4
Forms of Contract

5
General application

•

Yellow Book: design/build contract
electrical/mechanical works, including plant supply
and construction works; allocation of risk on basis of
insurability, project management principles and
ability to foresee and mitigate

•

Silver Book: fixed-price, date-certain, lump-sum turnkey contract:

•
•

Little risk of price increase (but higher price) or delay for
Employer
Shift of risks to Contractor: design and execution
General risk profile: Shift of
• Employer’s Engineer is Employer’s risks
•
•
•
•

Representative
Employer’s ‘determinations’
Setting Out
(No) Unforeseeable difficulties &
verification/ interpretation of Employer data
(incl. sub-surface, hydrological and
Employer Requirements)
General design obligations, design error
Shift of risks, cont’d
•

No extension of Time for Completion for:

•

exceptionally adverse climatic conditions
(except FM)

•

unforeseeable shortages in personnel or
goods by epidemic or government actions

•
•
•

Errors in Employer’s Requirements
Setting Out
Unforeseeable physical conditions
Sh ift
o f r is
ks ,
c on t’
d

•

Emp
loyer
’s Ris
exclu
k
des:
•

Use
of wo
rks b
• Desi
y Em
gn o
ploy
f wor
Emp
er,
ks by
loyer
’s pe
• Unfo
rson
rese
nel,
eabl
of f o
e op
rces
erati
o f na
on
ture
General risk profile:
key employer issues
•
•
•
•
•

Contractor fully responsible for design and design
coordination (including Employer design)
Full ground condition risk to Contractor
Employer to retain influence over project
Right to Variations
Limited scope for Contractor claims for time/money;
Contractor will:

•
•

Price these risks, so increase initial Contract Sum
Do extensive due diligence to mitigate, leading to delay in
execution
Payment & security:
key employer issues
•
•
•
•
•

Fixed price lump sum payments against schedule of
payments & Performance Certificate
Long payment period
No claim for additional time or money for e.g.
Variations/innovations, ‘in country” Force Majeure,
Unforeseen ground conditions, setting out or discovery of
fossils
Robust security package: advance payment bond,
performance bond, retention of money
Warranty bond after Taking Over (> 2yrs)
P rog
ram m
key e
e/de
m pl o
lay:
yer is
sue s

•

Liqu
idate
d Da
dela
m ag
y (10
es f o
– 20
• Limit
r
%, >
ed r i
?)
g
exte
nsion hts for
Com
of T i
me f
pleti
or
on
• Susp
ensio
entit
n by
l es C
E mp
ontra
exte
loyer
n s i on
ctor
of tim
e/ co
sts
Testing and defects,
insurance: key employer
issues
•
•
•
•
•
•

Suitable testing regime
Employer technical advisors to set
performance/reliability standards and regime for
testing/ performance guarantee levels
Liquidated Damages for performance (10 – 20 %, > ?)
Defects liability period (1 – 2 yrs): default is 1 yr
Liability cap, sub-caps and ‘carve-outs’
Project specific insurance provisions; all insurance
monies go in separate insurance proceeds account
for benefit Employer
Permits, change in law,
FM: key employer issues
• Employer planning, environmental/
•
•
•

Contractor construction and transport:
permit schedule
Change in law after contract signing/ in
force, EH&S developments
Exhaustive FM list ?
Location of FM, “in country” FM: costs in
addition to EOT ?
EPC Construction
contracting: key features
Turnkey-, date certain-, fixed price-, Engineering, Procurement
& Construction (EPC) contract

Including Start-up, Testing & Commissioning
Bonus payment
Detailed scope of work (Employer’s requirements)
Performance testing & guarantees
LD’s for delay & performance
Assurances of creditworthiness
Construction contracting


Main risks:
 Experience, reputation, resources, credit Contractor











Increase in construction costs
Delay in completion
Performance
Force majeure (& contractual co-ordination/ resurrection)
Building materials: steel
Construction related facilities
Raw materials & utilities
Coordination with employer/ other contractors
IP rights/ escrows
Construction contracting


Customary issues:
 What are the ‘Works’ ? WTG’s, SCADA, foundations, crane
hardstands, roads, cables, substation, FCU ?
 Partial and deemed take over







Are all ‘Defects’ created equal ? Serial defects ?
How are measurements done ? SCADA, cup anemometers,
metmast, Lidar ?
How is green and grey metering doen ? By whom ?
Grid connection interface
Site risks (nature, archeology, fossils, ordinance, boulders,
excess/polluted water)
Operation & Maintenance
contracting
 Issues similar to EPC contract






Creditworthy, experienced Operator: turbine supplier ?



Performance guarantees with LD’s:

Can the Operator be replaced ?
What is ‘Operation” ? Scope of work
Agreed upon performance criteria at fixed/ predictable OPEX
Increased OPEX through latent defects/ new technology: typically
defects warranty ends after 2-5 years





Availability, power curve, sound
cover variety of costs, but also PPA damages ?
but usually low caps. What if operator cannot be replaced ?
Operation & Maintenance
contracting
 What is the maintenance standard ?








Does maintenance include replacement of ‘Components”:
blades, nacelle, tower, gearbox ?
Balance of Plant ?
Is maintenance work warranted for design, materials,
workmanship ? Serial defects ?
Is there access to the site for components ?
Is there an on-site stock and what’s in it ?
How long will spares remain available ?
Condition of the Works at the end of the maintenance term ?
Testing ?
Power Purchase Agreements
 Linchpin energy project financing




Financing & operating agreement
Linkage with EPC/O&M
CP’s & milestones




Delay in COD, testing, early production (at opex + price ?)
Failure to construct or acheive nameplate capacity



Approval by purchaser of project doc’s, e.g. pass-through
OPEX




Take-or-pay is not an absolute
Delivery point, connection & transport
Main linkages EPC, O&M
and PPA













Approval project contracts
CP’s & Milestone schedule
Testing procedures & take pver
Delay LD’s up to COD
Nameplate capacity, defects- & performance LD’s
Early production revenues
Capacity and energy payments
Delivery point & connection, metering
Term & termination
Third party sales, RFR’s
Force Majeure
Change in law

IN SHORT: EVERYTHING !

More Related Content

What's hot

Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of ContractSession W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of ContractProject Controls Expo
 
Claim Preparation and Project Records - 2014 Olswang Construction Law Conference
Claim Preparation and Project Records - 2014 Olswang Construction Law ConferenceClaim Preparation and Project Records - 2014 Olswang Construction Law Conference
Claim Preparation and Project Records - 2014 Olswang Construction Law ConferenceFrancis Ho
 
Extension of time in construction contracts
Extension of time in construction contractsExtension of time in construction contracts
Extension of time in construction contractsKheng Hoe Advocates
 
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanFIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanAdrias TAN
 
Epc project interdepency and Work Flow- promo
Epc project interdepency and Work Flow- promoEpc project interdepency and Work Flow- promo
Epc project interdepency and Work Flow- promoignitetribes
 
Project Controls Expo - 31st Oct 2012 - Delay Analysis Letting the Evidence S...
Project Controls Expo - 31st Oct 2012 - Delay Analysis Letting the Evidence S...Project Controls Expo - 31st Oct 2012 - Delay Analysis Letting the Evidence S...
Project Controls Expo - 31st Oct 2012 - Delay Analysis Letting the Evidence S...Project Controls Expo
 
It Pays to Be Right: Payment in Construction Contracts
It Pays to Be Right: Payment in Construction ContractsIt Pays to Be Right: Payment in Construction Contracts
It Pays to Be Right: Payment in Construction ContractsFrancis Ho
 
Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)mohamed Ismail
 
Project Controls Expo - 31st Oct 2012 - Forensic Delay Analysis The Ultimate ...
Project Controls Expo - 31st Oct 2012 - Forensic Delay Analysis The Ultimate ...Project Controls Expo - 31st Oct 2012 - Forensic Delay Analysis The Ultimate ...
Project Controls Expo - 31st Oct 2012 - Forensic Delay Analysis The Ultimate ...Project Controls Expo
 
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...Project Controls Expo
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closuresrinivas2036
 
Session-02 17-09-2011
Session-02 17-09-2011Session-02 17-09-2011
Session-02 17-09-2011Tahir B Mirza
 
Advanced training for construction management: CONTRACTS MANAGEMENT part 2 (...
Advanced training for  construction management: CONTRACTS MANAGEMENT part 2 (...Advanced training for  construction management: CONTRACTS MANAGEMENT part 2 (...
Advanced training for construction management: CONTRACTS MANAGEMENT part 2 (...Antonio Coladarce
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementASHISH KUMAR SINGH
 
FIDIC Lecture - Joint operation of multiple Fidic Forms - A Case Study
FIDIC Lecture - Joint operation of multiple Fidic Forms - A Case StudyFIDIC Lecture - Joint operation of multiple Fidic Forms - A Case Study
FIDIC Lecture - Joint operation of multiple Fidic Forms - A Case StudyKhalil Hasan
 
Epc issues and recommendations
Epc issues and recommendationsEpc issues and recommendations
Epc issues and recommendationsubk1411
 
M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...
M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...
M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...Project Controls Expo
 
Advance Payments in Works
Advance Payments in WorksAdvance Payments in Works
Advance Payments in WorksDr K M SONI
 

What's hot (20)

Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of ContractSession W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
 
Claim Preparation and Project Records - 2014 Olswang Construction Law Conference
Claim Preparation and Project Records - 2014 Olswang Construction Law ConferenceClaim Preparation and Project Records - 2014 Olswang Construction Law Conference
Claim Preparation and Project Records - 2014 Olswang Construction Law Conference
 
Why EPC
Why EPCWhy EPC
Why EPC
 
Extension of time in construction contracts
Extension of time in construction contractsExtension of time in construction contracts
Extension of time in construction contracts
 
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanFIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
 
Epc project interdepency and Work Flow- promo
Epc project interdepency and Work Flow- promoEpc project interdepency and Work Flow- promo
Epc project interdepency and Work Flow- promo
 
Project Controls Expo - 31st Oct 2012 - Delay Analysis Letting the Evidence S...
Project Controls Expo - 31st Oct 2012 - Delay Analysis Letting the Evidence S...Project Controls Expo - 31st Oct 2012 - Delay Analysis Letting the Evidence S...
Project Controls Expo - 31st Oct 2012 - Delay Analysis Letting the Evidence S...
 
It Pays to Be Right: Payment in Construction Contracts
It Pays to Be Right: Payment in Construction ContractsIt Pays to Be Right: Payment in Construction Contracts
It Pays to Be Right: Payment in Construction Contracts
 
Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)
 
Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...
Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...
Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...
 
Project Controls Expo - 31st Oct 2012 - Forensic Delay Analysis The Ultimate ...
Project Controls Expo - 31st Oct 2012 - Forensic Delay Analysis The Ultimate ...Project Controls Expo - 31st Oct 2012 - Forensic Delay Analysis The Ultimate ...
Project Controls Expo - 31st Oct 2012 - Forensic Delay Analysis The Ultimate ...
 
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closure
 
Session-02 17-09-2011
Session-02 17-09-2011Session-02 17-09-2011
Session-02 17-09-2011
 
Advanced training for construction management: CONTRACTS MANAGEMENT part 2 (...
Advanced training for  construction management: CONTRACTS MANAGEMENT part 2 (...Advanced training for  construction management: CONTRACTS MANAGEMENT part 2 (...
Advanced training for construction management: CONTRACTS MANAGEMENT part 2 (...
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time Management
 
FIDIC Lecture - Joint operation of multiple Fidic Forms - A Case Study
FIDIC Lecture - Joint operation of multiple Fidic Forms - A Case StudyFIDIC Lecture - Joint operation of multiple Fidic Forms - A Case Study
FIDIC Lecture - Joint operation of multiple Fidic Forms - A Case Study
 
Epc issues and recommendations
Epc issues and recommendationsEpc issues and recommendations
Epc issues and recommendations
 
M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...
M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...
M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...
 
Advance Payments in Works
Advance Payments in WorksAdvance Payments in Works
Advance Payments in Works
 

Similar to Wind power epc o&m april 2013

Episode 28 : Project Management Contract
Episode 28 : Project Management ContractEpisode 28 : Project Management Contract
Episode 28 : Project Management ContractSAJJAD KHUDHUR ABBAS
 
Engineering, Procurement and Construction Contracts for Infrastructure Projec...
Engineering, Procurement and Construction Contracts for Infrastructure Projec...Engineering, Procurement and Construction Contracts for Infrastructure Projec...
Engineering, Procurement and Construction Contracts for Infrastructure Projec...John Buchovecky
 
Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)Tahir B Mirza
 
Managing Technical & Project Risks on Small Renewable Energy Projects (...
Managing Technical & Project Risks on Small Renewable Energy Projects (...Managing Technical & Project Risks on Small Renewable Energy Projects (...
Managing Technical & Project Risks on Small Renewable Energy Projects (...mtingle
 
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1Antonio Coladarce
 
Strategic Planning : the best way to manage EPC Contract Risks
Strategic Planning : the best way to manage EPC Contract RisksStrategic Planning : the best way to manage EPC Contract Risks
Strategic Planning : the best way to manage EPC Contract RisksPankaj K Sinha
 
Session 16 contract structure & agreement
Session 16   contract structure & agreementSession 16   contract structure & agreement
Session 16 contract structure & agreementChirag Jain
 
"Types and Causes of Construction Claims"
"Types and Causes of Construction Claims""Types and Causes of Construction Claims"
"Types and Causes of Construction Claims"Abhishek Shah
 
Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Gregoire Lesecq
 
Design & Build contracts - key points for a main contractor with technology a...
Design & Build contracts - key points for a main contractor with technology a...Design & Build contracts - key points for a main contractor with technology a...
Design & Build contracts - key points for a main contractor with technology a...Bhalindra Bath - projects & M&A law
 
AJITHKUMAR_Original
AJITHKUMAR_OriginalAJITHKUMAR_Original
AJITHKUMAR_OriginalAJITH KUMAR
 
AJITHKUMAR_Original
AJITHKUMAR_OriginalAJITHKUMAR_Original
AJITHKUMAR_OriginalAJITH KUMAR
 
PECDisputeResolution25102018.pptx
PECDisputeResolution25102018.pptxPECDisputeResolution25102018.pptx
PECDisputeResolution25102018.pptxIrfanAwan25
 
Managing the Risks of Delay in Construction Projects
Managing the Risks of Delay in Construction ProjectsManaging the Risks of Delay in Construction Projects
Managing the Risks of Delay in Construction ProjectsFrancis Ho
 
Solar PPA Presentation
Solar PPA PresentationSolar PPA Presentation
Solar PPA Presentationmatt_UCI
 

Similar to Wind power epc o&m april 2013 (20)

Episode 28 : Project Management Contract
Episode 28 : Project Management ContractEpisode 28 : Project Management Contract
Episode 28 : Project Management Contract
 
Engineering, Procurement and Construction Contracts for Infrastructure Projec...
Engineering, Procurement and Construction Contracts for Infrastructure Projec...Engineering, Procurement and Construction Contracts for Infrastructure Projec...
Engineering, Procurement and Construction Contracts for Infrastructure Projec...
 
Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)
 
Managing Technical & Project Risks on Small Renewable Energy Projects (...
Managing Technical & Project Risks on Small Renewable Energy Projects (...Managing Technical & Project Risks on Small Renewable Energy Projects (...
Managing Technical & Project Risks on Small Renewable Energy Projects (...
 
Epc contracts.
Epc contracts.Epc contracts.
Epc contracts.
 
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
 
Strategic Planning : the best way to manage EPC Contract Risks
Strategic Planning : the best way to manage EPC Contract RisksStrategic Planning : the best way to manage EPC Contract Risks
Strategic Planning : the best way to manage EPC Contract Risks
 
Session 16 contract structure & agreement
Session 16   contract structure & agreementSession 16   contract structure & agreement
Session 16 contract structure & agreement
 
"Types and Causes of Construction Claims"
"Types and Causes of Construction Claims""Types and Causes of Construction Claims"
"Types and Causes of Construction Claims"
 
Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016
 
2014 PV Reliability O&M Workshop: PV Operations & Maintenance - An Independen...
2014 PV Reliability O&M Workshop: PV Operations & Maintenance - An Independen...2014 PV Reliability O&M Workshop: PV Operations & Maintenance - An Independen...
2014 PV Reliability O&M Workshop: PV Operations & Maintenance - An Independen...
 
Contracting strategies for_terminal_construction
Contracting strategies for_terminal_constructionContracting strategies for_terminal_construction
Contracting strategies for_terminal_construction
 
Contracting strategies for_terminal_construction
Contracting strategies for_terminal_constructionContracting strategies for_terminal_construction
Contracting strategies for_terminal_construction
 
Design & Build contracts - key points for a main contractor with technology a...
Design & Build contracts - key points for a main contractor with technology a...Design & Build contracts - key points for a main contractor with technology a...
Design & Build contracts - key points for a main contractor with technology a...
 
AJITHKUMAR_Original
AJITHKUMAR_OriginalAJITHKUMAR_Original
AJITHKUMAR_Original
 
AJITHKUMAR_Original
AJITHKUMAR_OriginalAJITHKUMAR_Original
AJITHKUMAR_Original
 
PECDisputeResolution25102018.pptx
PECDisputeResolution25102018.pptxPECDisputeResolution25102018.pptx
PECDisputeResolution25102018.pptx
 
Epc Vs Epcm
Epc Vs EpcmEpc Vs Epcm
Epc Vs Epcm
 
Managing the Risks of Delay in Construction Projects
Managing the Risks of Delay in Construction ProjectsManaging the Risks of Delay in Construction Projects
Managing the Risks of Delay in Construction Projects
 
Solar PPA Presentation
Solar PPA PresentationSolar PPA Presentation
Solar PPA Presentation
 

More from Weero Koster

Nationaal energieakkoord
Nationaal energieakkoordNationaal energieakkoord
Nationaal energieakkoordWeero Koster
 
Energy project finance
Energy project financeEnergy project finance
Energy project financeWeero Koster
 
Warsaw presentation
Warsaw presentationWarsaw presentation
Warsaw presentationWeero Koster
 
Energy opportunities in the netherlands
Energy opportunities in the netherlandsEnergy opportunities in the netherlands
Energy opportunities in the netherlandsWeero Koster
 
Nat windenergiecongres 16 mei 2013
Nat windenergiecongres 16 mei 2013Nat windenergiecongres 16 mei 2013
Nat windenergiecongres 16 mei 2013Weero Koster
 
Nationaal energie forum 28 nov 2012
Nationaal energie forum 28 nov 2012Nationaal energie forum 28 nov 2012
Nationaal energie forum 28 nov 2012Weero Koster
 

More from Weero Koster (6)

Nationaal energieakkoord
Nationaal energieakkoordNationaal energieakkoord
Nationaal energieakkoord
 
Energy project finance
Energy project financeEnergy project finance
Energy project finance
 
Warsaw presentation
Warsaw presentationWarsaw presentation
Warsaw presentation
 
Energy opportunities in the netherlands
Energy opportunities in the netherlandsEnergy opportunities in the netherlands
Energy opportunities in the netherlands
 
Nat windenergiecongres 16 mei 2013
Nat windenergiecongres 16 mei 2013Nat windenergiecongres 16 mei 2013
Nat windenergiecongres 16 mei 2013
 
Nationaal energie forum 28 nov 2012
Nationaal energie forum 28 nov 2012Nationaal energie forum 28 nov 2012
Nationaal energie forum 28 nov 2012
 

Recently uploaded

VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Roomdivyansh0kumar0
 
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Tech Startup Growth Hacking 101  - Basics on Growth MarketingTech Startup Growth Hacking 101  - Basics on Growth Marketing
Tech Startup Growth Hacking 101 - Basics on Growth MarketingShawn Pang
 
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...lizamodels9
 
rishikeshgirls.in- Rishikesh call girl.pdf
rishikeshgirls.in- Rishikesh call girl.pdfrishikeshgirls.in- Rishikesh call girl.pdf
rishikeshgirls.in- Rishikesh call girl.pdfmuskan1121w
 
Islamabad Escorts | Call 03274100048 | Escort Service in Islamabad
Islamabad Escorts | Call 03274100048 | Escort Service in IslamabadIslamabad Escorts | Call 03274100048 | Escort Service in Islamabad
Islamabad Escorts | Call 03274100048 | Escort Service in IslamabadAyesha Khan
 
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / NcrCall Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncrdollysharma2066
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfpollardmorgan
 
Marketing Management Business Plan_My Sweet Creations
Marketing Management Business Plan_My Sweet CreationsMarketing Management Business Plan_My Sweet Creations
Marketing Management Business Plan_My Sweet Creationsnakalysalcedo61
 
BEST Call Girls In BELLMONT HOTEL ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In BELLMONT HOTEL ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In BELLMONT HOTEL ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In BELLMONT HOTEL ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,noida100girls
 
Catalogue ONG NUOC PPR DE NHAT .pdf
Catalogue ONG NUOC PPR DE NHAT      .pdfCatalogue ONG NUOC PPR DE NHAT      .pdf
Catalogue ONG NUOC PPR DE NHAT .pdfOrient Homes
 
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...lizamodels9
 
CATALOG cáp điện Goldcup (bảng giá) 1.4.2024.PDF
CATALOG cáp điện Goldcup (bảng giá) 1.4.2024.PDFCATALOG cáp điện Goldcup (bảng giá) 1.4.2024.PDF
CATALOG cáp điện Goldcup (bảng giá) 1.4.2024.PDFOrient Homes
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst SummitHolger Mueller
 
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...lizamodels9
 
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝soniya singh
 
Call Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any TimeCall Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any Timedelhimodelshub1
 
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsCash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsApsara Of India
 
Call Girls In ⇛⇛Chhatarpur⇚⇚. Brings Offer Delhi Contact Us 8377877756
Call Girls In ⇛⇛Chhatarpur⇚⇚. Brings Offer Delhi Contact Us 8377877756Call Girls In ⇛⇛Chhatarpur⇚⇚. Brings Offer Delhi Contact Us 8377877756
Call Girls In ⇛⇛Chhatarpur⇚⇚. Brings Offer Delhi Contact Us 8377877756dollysharma2066
 
RE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman LeechRE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman LeechNewman George Leech
 

Recently uploaded (20)

VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
 
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Tech Startup Growth Hacking 101  - Basics on Growth MarketingTech Startup Growth Hacking 101  - Basics on Growth Marketing
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
 
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
 
rishikeshgirls.in- Rishikesh call girl.pdf
rishikeshgirls.in- Rishikesh call girl.pdfrishikeshgirls.in- Rishikesh call girl.pdf
rishikeshgirls.in- Rishikesh call girl.pdf
 
Best Practices for Implementing an External Recruiting Partnership
Best Practices for Implementing an External Recruiting PartnershipBest Practices for Implementing an External Recruiting Partnership
Best Practices for Implementing an External Recruiting Partnership
 
Islamabad Escorts | Call 03274100048 | Escort Service in Islamabad
Islamabad Escorts | Call 03274100048 | Escort Service in IslamabadIslamabad Escorts | Call 03274100048 | Escort Service in Islamabad
Islamabad Escorts | Call 03274100048 | Escort Service in Islamabad
 
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / NcrCall Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
 
Marketing Management Business Plan_My Sweet Creations
Marketing Management Business Plan_My Sweet CreationsMarketing Management Business Plan_My Sweet Creations
Marketing Management Business Plan_My Sweet Creations
 
BEST Call Girls In BELLMONT HOTEL ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In BELLMONT HOTEL ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In BELLMONT HOTEL ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In BELLMONT HOTEL ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
 
Catalogue ONG NUOC PPR DE NHAT .pdf
Catalogue ONG NUOC PPR DE NHAT      .pdfCatalogue ONG NUOC PPR DE NHAT      .pdf
Catalogue ONG NUOC PPR DE NHAT .pdf
 
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
 
CATALOG cáp điện Goldcup (bảng giá) 1.4.2024.PDF
CATALOG cáp điện Goldcup (bảng giá) 1.4.2024.PDFCATALOG cáp điện Goldcup (bảng giá) 1.4.2024.PDF
CATALOG cáp điện Goldcup (bảng giá) 1.4.2024.PDF
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst Summit
 
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
 
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
 
Call Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any TimeCall Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any Time
 
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsCash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
 
Call Girls In ⇛⇛Chhatarpur⇚⇚. Brings Offer Delhi Contact Us 8377877756
Call Girls In ⇛⇛Chhatarpur⇚⇚. Brings Offer Delhi Contact Us 8377877756Call Girls In ⇛⇛Chhatarpur⇚⇚. Brings Offer Delhi Contact Us 8377877756
Call Girls In ⇛⇛Chhatarpur⇚⇚. Brings Offer Delhi Contact Us 8377877756
 
RE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman LeechRE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman Leech
 

Wind power epc o&m april 2013

  • 1. Wind power projects Construction and O&M Weero Koster 25 April 2013
  • 3. Typical PF Structure PUBLIC ENTITY SPONSOR EQUITY INSURERS CONCESSION CONTRACT THIRD PARTY EQUITY INVESTORS SPV INVESTORS MEZZANINE FUNDERS SENIOR FUNDERS (BANK/BOND) SURPLUS REAL ESTATE DISPOSAL CONSTRUCTION SUBCONTRACTOR 1 OPERATION & MAINTENANCE EQUIPMENT SUPPLY SUBCONTRACTOR 3 DEVELOPER BONDS & GUARANTEES DESIGNERS DUE DILIGENCE ADVISER 1 SURETIES & GUARANTORS DUE DILIGENCE ADVISER 3 DUE DILIGENCE ADVISER 2 3 SUBCONTRACTOR 2
  • 4. EPC Structure Where does EPC fit in? Owner assumes risk Construction Management RISK SPECTRUM Traditional Design & Build Contractor retains risk LSTK/ EPC Except as otherwise stated in the Contract: a) the Contractor shall be deemed to have obtained all necessary information as to risks, contingencies and other circumstances which may influence or affect the Works; b) by signing the Contract, the Contractor accepts total responsibility for having foreseen all difficulties and costs of successfully completing the Works; and c) the Contract Price shall – Engineering Procurement and Construction EPC not be adjusted to take account of any unforeseen difficulties or costs. LSTK – Lump Sum Turnkey 4
  • 6. General application • Yellow Book: design/build contract electrical/mechanical works, including plant supply and construction works; allocation of risk on basis of insurability, project management principles and ability to foresee and mitigate • Silver Book: fixed-price, date-certain, lump-sum turnkey contract: • • Little risk of price increase (but higher price) or delay for Employer Shift of risks to Contractor: design and execution
  • 7. General risk profile: Shift of • Employer’s Engineer is Employer’s risks • • • • Representative Employer’s ‘determinations’ Setting Out (No) Unforeseeable difficulties & verification/ interpretation of Employer data (incl. sub-surface, hydrological and Employer Requirements) General design obligations, design error
  • 8. Shift of risks, cont’d • No extension of Time for Completion for: • exceptionally adverse climatic conditions (except FM) • unforeseeable shortages in personnel or goods by epidemic or government actions • • • Errors in Employer’s Requirements Setting Out Unforeseeable physical conditions
  • 9. Sh ift o f r is ks , c on t’ d • Emp loyer ’s Ris exclu k des: • Use of wo rks b • Desi y Em gn o ploy f wor Emp er, ks by loyer ’s pe • Unfo rson rese nel, eabl of f o e op rces erati o f na on ture
  • 10. General risk profile: key employer issues • • • • • Contractor fully responsible for design and design coordination (including Employer design) Full ground condition risk to Contractor Employer to retain influence over project Right to Variations Limited scope for Contractor claims for time/money; Contractor will: • • Price these risks, so increase initial Contract Sum Do extensive due diligence to mitigate, leading to delay in execution
  • 11. Payment & security: key employer issues • • • • • Fixed price lump sum payments against schedule of payments & Performance Certificate Long payment period No claim for additional time or money for e.g. Variations/innovations, ‘in country” Force Majeure, Unforeseen ground conditions, setting out or discovery of fossils Robust security package: advance payment bond, performance bond, retention of money Warranty bond after Taking Over (> 2yrs)
  • 12. P rog ram m key e e/de m pl o lay: yer is sue s • Liqu idate d Da dela m ag y (10 es f o – 20 • Limit r %, > ed r i ?) g exte nsion hts for Com of T i me f pleti or on • Susp ensio entit n by l es C E mp ontra exte loyer n s i on ctor of tim e/ co sts
  • 13. Testing and defects, insurance: key employer issues • • • • • • Suitable testing regime Employer technical advisors to set performance/reliability standards and regime for testing/ performance guarantee levels Liquidated Damages for performance (10 – 20 %, > ?) Defects liability period (1 – 2 yrs): default is 1 yr Liability cap, sub-caps and ‘carve-outs’ Project specific insurance provisions; all insurance monies go in separate insurance proceeds account for benefit Employer
  • 14. Permits, change in law, FM: key employer issues • Employer planning, environmental/ • • • Contractor construction and transport: permit schedule Change in law after contract signing/ in force, EH&S developments Exhaustive FM list ? Location of FM, “in country” FM: costs in addition to EOT ?
  • 15. EPC Construction contracting: key features Turnkey-, date certain-, fixed price-, Engineering, Procurement & Construction (EPC) contract Including Start-up, Testing & Commissioning Bonus payment Detailed scope of work (Employer’s requirements) Performance testing & guarantees LD’s for delay & performance Assurances of creditworthiness
  • 16. Construction contracting  Main risks:  Experience, reputation, resources, credit Contractor          Increase in construction costs Delay in completion Performance Force majeure (& contractual co-ordination/ resurrection) Building materials: steel Construction related facilities Raw materials & utilities Coordination with employer/ other contractors IP rights/ escrows
  • 17. Construction contracting  Customary issues:  What are the ‘Works’ ? WTG’s, SCADA, foundations, crane hardstands, roads, cables, substation, FCU ?  Partial and deemed take over      Are all ‘Defects’ created equal ? Serial defects ? How are measurements done ? SCADA, cup anemometers, metmast, Lidar ? How is green and grey metering doen ? By whom ? Grid connection interface Site risks (nature, archeology, fossils, ordinance, boulders, excess/polluted water)
  • 18.
  • 19. Operation & Maintenance contracting  Issues similar to EPC contract      Creditworthy, experienced Operator: turbine supplier ?  Performance guarantees with LD’s: Can the Operator be replaced ? What is ‘Operation” ? Scope of work Agreed upon performance criteria at fixed/ predictable OPEX Increased OPEX through latent defects/ new technology: typically defects warranty ends after 2-5 years    Availability, power curve, sound cover variety of costs, but also PPA damages ? but usually low caps. What if operator cannot be replaced ?
  • 20. Operation & Maintenance contracting  What is the maintenance standard ?        Does maintenance include replacement of ‘Components”: blades, nacelle, tower, gearbox ? Balance of Plant ? Is maintenance work warranted for design, materials, workmanship ? Serial defects ? Is there access to the site for components ? Is there an on-site stock and what’s in it ? How long will spares remain available ? Condition of the Works at the end of the maintenance term ? Testing ?
  • 21. Power Purchase Agreements  Linchpin energy project financing    Financing & operating agreement Linkage with EPC/O&M CP’s & milestones   Delay in COD, testing, early production (at opex + price ?) Failure to construct or acheive nameplate capacity  Approval by purchaser of project doc’s, e.g. pass-through OPEX   Take-or-pay is not an absolute Delivery point, connection & transport
  • 22. Main linkages EPC, O&M and PPA             Approval project contracts CP’s & Milestone schedule Testing procedures & take pver Delay LD’s up to COD Nameplate capacity, defects- & performance LD’s Early production revenues Capacity and energy payments Delivery point & connection, metering Term & termination Third party sales, RFR’s Force Majeure Change in law IN SHORT: EVERYTHING !

Editor's Notes

  1. _____________________________________________________________ _____________________________________________________________ _____________________________________________________________ _____________________________________________________________ _____________________________________________________________ _____________________________________________________________ _____________________________________________________________ _____________________________________________________________ _____________________________________________________________