SlideShare a Scribd company logo
PERT/CPM Models for Project Management
Agenda What is Project Management Discuss PERT/CPM Motivating Case Study: The Reliable Construction Company Ways of Finding the Critical Path Considering Time-Cost Trade-Offs
What is Project Management Project management can be defined as the coordination of activities with the potential use of many organizations, both internal and external to the business, in order to conduct a large scale project from beginning to end. There are two management science techniques that are used for project management: Program and Evaluation Review Technique (PERT) Critical Path Method (CPM)
PERT/CPM PERT PERT was designed to examine projects from the standpoint of uncertainty. CPM CPM was designed to examine projects from the standpoint of costs. PERT and CPM techniques have been combined over time. PERT and CPM both rely heavily on the use of networks to help plan and display the coordination of all the activities for a project.
The Reliable Construction Company Reliable has just secured a contract to construct a new plant for a major manufacturer. The contract is for $5.4 million to cover all costs and any profits. The plant must be finished in a year. A penalty of $300,000 will be assessed if Reliable does not complete the project within 47 weeks. A bonus of $150,000 will be paid to Reliable if the plant is completed within 40 weeks.
Needed Terminology Activity A distinct task that needs to be performed as part of the project. Start Node This is a node that represents the beginning of the project. Finish Node This node represents the end of the project.
Needed Terminology Cont. Immediate Predecessor These are activities that must be completed by no later than the start time of the given activity. Immediate Successor Given the immediate predecessor of an activity, this activity becomes the immediate successor of each of these immediate predecessors. If an immediate successor has multiple immediate predecessors, then all must be finished before an activity can begin.
Activity List for Reliable Construction
Questions Needed to be Answered How can the project be displayed graphically? How much time is required to finish the project if no delays occur? When is earliest start and finish times for each activity if no delays occur? What activities are critical bottleneck activities where delays must be avoided to finish the project on time?
Questions Needed to be Answered Cont. For non bottleneck activities, how much can an activity be delayed and yet still keep the project on time? What is the probability of completing the project by the deadline? What is the least amount of money needed to expedite the project to obtain the bonus? How should costs be monitored to keep the project within budget?
Project Network A project network is a network diagram that uses nodes and arcs to represent the progression of the activities is a project from start to finish. Three pieces of information needed: Activity information Precedence relationship Time information
Project Network Cont. Two types of project networks Activity-on-Arc (AOA) On this diagram, the activity is represented on an arc, while a node is used to separate an activity from its immediate predecessors.  Activity-on-Node (AON) On this diagram, the activity is represented by the node, while the arc is used to showed the precedence relationship between the activities.
Microsoft Project Visual Diagram: Gantt Chart
Scheduling Using PERT/CPM A path through a project network is a route that follows a set of arcs from the start node to the finish node. The length of a path is defined as the sum of the durations of the activities of the path. What are the paths and their corresponding lengths for Reliable?
Critical Path This is the path that has the longest length through the project. The shortest time that a project can conceivably be finished is the critical path. Why?
More Terminology Earliest start time of an activity (ES) The time at which an activity will begin if there are no delays in a project. Earliest finish time of an activity (EF) The time at which an activity will finish if there are no delays in a project. Latest start time of an activity (LS) The latest possible time that an activity can start without delaying the project.
More Terminology Cont. Latest finish time of an activity (LF) The latest possible time that an activity can be completed without delaying the project. Forward pass The process of moving through a project from start to finish to determine the earliest start and finish times for the activities in the project.
More Terminology Cont. Backward pass The process of moving through a project from finish to start to determine the latest start and finish times for the activities in the project. Slack for an activity The amount of time that a particular activity can be delayed without delaying the whole project. It is calculated by taking the difference between the latest finish time with the earliest finish time.
More Terminology Cont. Earliest start time rule The earliest start time for an activity is equal to the largest of the earliest finish times of its immediate predecessors. Latest finish time rule The latest finish time is equal to the smallest of the latest start times of its immediate successors.
Procedure for Obtaining Earliest Times Step 1: For the activity that starts the project, assign an earliest start time of zero, i.e., ES=0. Step 2: For each activity whose ES has just been obtained, calculate its earliest finish time as ES plus duration of the activity. Step 3: For each new activity whose immediate predecessors have EF values, obtain its ES by using the earliest start time rule.
Procedure for Obtaining Earliest Times Cont. Step 4: Apply step 2 to calculate EF. Step 5: Repeat step 3 until ES and EF have been obtained for all activities including the finish node.
Procedure for Obtaining Latest Times Step 1: For each of the activities that together complete the project, set its latest finish time equal to the earliest finish time of the finish node. Step 2: For each activity whose LF value has just been obtained, calculate its latest start time as LS equals LF minus the duration of the activity.
Procedure for Obtaining Latest Times Cont. Step 3: For each new activity whose immediate successors now have LS values, obtain its LF by applying the latest finish time rule. Step 4: Apply step 2 to calculate its LS. Step 5: Repeat step 3 until LF and LS have been obtained for all activities.
Ways of Finding the Critical Path Examine all the paths and find the path with the maximum length. Calculate the slack for an activity. If the slack is zero, it is on the critical path. If the slack is positive, it is not on the critical path.
Time-Cost Trade-Offs Reliable had an incentive bonus of $150,000 to finish the project in 40 weeks. Is it worth while for Reliable to speed-up the project?
Crashing Crashing an activity refers to taking on extra expenditures in order to reduce the duration of an activity below its expected value. Crashing a project refers to crashing a number of activities to reduce the duration of the project.
CPM Method of Time-Cost Trade-Offs This is a method concerned with whether it is worthwhile to crash activities to reduce the anticipated duration of the project to a desired value. This assumes that there is a trade-off between time and cost that has an inverse relationship.
More Terminology Normal Point is the time and cost of an activity when it is performed in a normal way. Crash point show the time and cost when the activity is fully crashed.
Graph of Normal and Crash Points
Marginal Cost Analysis It is a method of using the marginal cost of crashing individual activities on the current critical path to determine the least expensive way of reducing the project duration to an acceptable level. This method requires you to calculate the cost per desired time unit and compare each cost with the other costs.
Marginal Cost Analysis Cont. Once the marginal cost for crashing each activity has been conducted, you next want to choose the crashing that has the smallest marginal cost. Next, calculate the effect that the crash has on each path. Note: Crashing can potentially cause another path to become a critical path.
Solving Crashing Problems Using LP There are three decisions to be made: The start time of each activity The reduction in each activity due to crashing The finish time of the project LP model will be examined in class.

More Related Content

What's hot

Project integration management
Project integration managementProject integration management
Project integration management
Prabudh Dhingra
 
Project management process and Project Management Knowledge areas
Project management process and Project Management Knowledge areasProject management process and Project Management Knowledge areas
Project management process and Project Management Knowledge areas
Mazen Zbib
 
Critical path method
Critical path methodCritical path method
Critical path method
Dushyant Nasit
 
Project management
Project managementProject management
Project management
Dr. RICHA SINGHAL
 
Project Scheduling & Controls
Project Scheduling & ControlsProject Scheduling & Controls
Project Scheduling & Controls
Procept Associates
 
Critical path method(cpm)
Critical path method(cpm)Critical path method(cpm)
Critical path method(cpm)
chandkec
 
Pmp quality chapter 8
Pmp quality chapter 8Pmp quality chapter 8
Pmp quality chapter 8
Ahmed Elshaboury,PMP,LEED GA
 
Project Management Tools and Techniques
Project Management Tools and TechniquesProject Management Tools and Techniques
Project Management Tools and Techniques
MaRS Discovery District
 
Project Scheduling
Project SchedulingProject Scheduling
Project Scheduling
Baker Khader Abdallah, PMP
 
7.4 Earned Value Analysis
7.4 Earned Value Analysis7.4 Earned Value Analysis
7.4 Earned Value Analysis
DavidMcLachlan1
 
Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )
Akaresh Jose Kaviyil JY
 
Critical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/SlacksCritical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/Slacks
Prasad Thanthratey
 
Network analysis & cpm
Network analysis & cpmNetwork analysis & cpm
Network analysis & cpm
Ganesh Kandalkar
 
Project Schedule Management - Sequence Activities - PMP Workgroup
Project Schedule Management - Sequence Activities - PMP WorkgroupProject Schedule Management - Sequence Activities - PMP Workgroup
Project Schedule Management - Sequence Activities - PMP Workgroup
Tùng Trần Thanh
 
project planning-estimation
project planning-estimationproject planning-estimation
project planning-estimation
Reetesh Gupta
 
Project Planning and Management Notes
Project Planning and Management NotesProject Planning and Management Notes
Project Planning and Management Notes
Haris Hassan
 
Lect-6&7: Network Diagrams, PERT and CPM
Lect-6&7: Network Diagrams, PERT and CPMLect-6&7: Network Diagrams, PERT and CPM
Lect-6&7: Network Diagrams, PERT and CPM
Mubashir Ali
 
Work breakdown structures
Work breakdown structures Work breakdown structures
Work breakdown structures
Ian Cammack
 
00 Introduction of project scheduling
00 Introduction of project scheduling00 Introduction of project scheduling
00 Introduction of project scheduling
Soe Naing Win
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
Ajeesh Mk
 

What's hot (20)

Project integration management
Project integration managementProject integration management
Project integration management
 
Project management process and Project Management Knowledge areas
Project management process and Project Management Knowledge areasProject management process and Project Management Knowledge areas
Project management process and Project Management Knowledge areas
 
Critical path method
Critical path methodCritical path method
Critical path method
 
Project management
Project managementProject management
Project management
 
Project Scheduling & Controls
Project Scheduling & ControlsProject Scheduling & Controls
Project Scheduling & Controls
 
Critical path method(cpm)
Critical path method(cpm)Critical path method(cpm)
Critical path method(cpm)
 
Pmp quality chapter 8
Pmp quality chapter 8Pmp quality chapter 8
Pmp quality chapter 8
 
Project Management Tools and Techniques
Project Management Tools and TechniquesProject Management Tools and Techniques
Project Management Tools and Techniques
 
Project Scheduling
Project SchedulingProject Scheduling
Project Scheduling
 
7.4 Earned Value Analysis
7.4 Earned Value Analysis7.4 Earned Value Analysis
7.4 Earned Value Analysis
 
Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )
 
Critical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/SlacksCritical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/Slacks
 
Network analysis & cpm
Network analysis & cpmNetwork analysis & cpm
Network analysis & cpm
 
Project Schedule Management - Sequence Activities - PMP Workgroup
Project Schedule Management - Sequence Activities - PMP WorkgroupProject Schedule Management - Sequence Activities - PMP Workgroup
Project Schedule Management - Sequence Activities - PMP Workgroup
 
project planning-estimation
project planning-estimationproject planning-estimation
project planning-estimation
 
Project Planning and Management Notes
Project Planning and Management NotesProject Planning and Management Notes
Project Planning and Management Notes
 
Lect-6&7: Network Diagrams, PERT and CPM
Lect-6&7: Network Diagrams, PERT and CPMLect-6&7: Network Diagrams, PERT and CPM
Lect-6&7: Network Diagrams, PERT and CPM
 
Work breakdown structures
Work breakdown structures Work breakdown structures
Work breakdown structures
 
00 Introduction of project scheduling
00 Introduction of project scheduling00 Introduction of project scheduling
00 Introduction of project scheduling
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
 

Viewers also liked

E governance, gartner's model by bhim upadhyaya
E governance, gartner's model by bhim upadhyayaE governance, gartner's model by bhim upadhyaya
E governance, gartner's model by bhim upadhyaya
Bhim Upadhyaya
 
Rebirth of the_eagle
Rebirth of the_eagleRebirth of the_eagle
Rebirth of the_eagle
Bhim Upadhyaya
 
Apj abdul kalam's vision of developed nepal nov 2008
Apj abdul kalam's vision of developed nepal nov 2008Apj abdul kalam's vision of developed nepal nov 2008
Apj abdul kalam's vision of developed nepal nov 2008
Bhim Upadhyaya
 
My nepal is great ! (mero nepal mahaan)
My nepal is great ! (mero nepal mahaan)My nepal is great ! (mero nepal mahaan)
My nepal is great ! (mero nepal mahaan)Bhim Upadhyaya
 
A vision of prosperous new nepal by bhim upadhyaya 064.11.5
A vision of prosperous new nepal  by bhim upadhyaya 064.11.5A vision of prosperous new nepal  by bhim upadhyaya 064.11.5
A vision of prosperous new nepal by bhim upadhyaya 064.11.5Bhim Upadhyaya
 
जलस्रोत विकास परिषद्को कार्यविधि तथा गठनविधि 054.08.19
जलस्रोत विकास परिषद्को कार्यविधि तथा गठनविधि 054.08.19जलस्रोत विकास परिषद्को कार्यविधि तथा गठनविधि 054.08.19
जलस्रोत विकास परिषद्को कार्यविधि तथा गठनविधि 054.08.19
Bhim Upadhyaya
 
Workshop on Understnding E governance
Workshop on Understnding E governance Workshop on Understnding E governance
Workshop on Understnding E governance
Venkat Subbu
 
E gov lecture1
E gov lecture1E gov lecture1
E gov lecture1
Krishna Pandey
 
Final ppg 520 group ppt (group 5)
Final ppg 520 group ppt (group 5)Final ppg 520 group ppt (group 5)
Final ppg 520 group ppt (group 5)
litonielts
 
Electronic Transaction Act 2063 (ETA 2063)
Electronic Transaction Act 2063 (ETA 2063)Electronic Transaction Act 2063 (ETA 2063)
Electronic Transaction Act 2063 (ETA 2063)Krishna Pandey
 
Cyber law in nepal and implementation
Cyber law in nepal and implementationCyber law in nepal and implementation
Cyber law in nepal and implementation
Information Technology Society Nepal
 
FACTORS INFLUENCING THE ADOPTION OF E-GOVERNMENT SERVICES IN PAKISTAN
FACTORS INFLUENCING THE ADOPTION OF E-GOVERNMENT SERVICES IN PAKISTANFACTORS INFLUENCING THE ADOPTION OF E-GOVERNMENT SERVICES IN PAKISTAN
FACTORS INFLUENCING THE ADOPTION OF E-GOVERNMENT SERVICES IN PAKISTAN
Muhammad Ahmad
 
Lesson02_new
Lesson02_newLesson02_new
Lesson02_newshengvn
 
Pre-Con Ed: Critical Path Analysis with CA Workload Automation (AE) iDash - O...
Pre-Con Ed: Critical Path Analysis with CA Workload Automation (AE) iDash - O...Pre-Con Ed: Critical Path Analysis with CA Workload Automation (AE) iDash - O...
Pre-Con Ed: Critical Path Analysis with CA Workload Automation (AE) iDash - O...
CA Technologies
 
Syam critical path cpa
Syam critical path cpaSyam critical path cpa
Syam critical path cpasyamputra
 
Education management information system nepal
Education management information system   nepalEducation management information system   nepal
Education management information system nepalMero Campus
 
Boeing C-17 Critical Path Tooling ASQ(Oct_11 _R2)
Boeing  C-17 Critical Path Tooling  ASQ(Oct_11 _R2)Boeing  C-17 Critical Path Tooling  ASQ(Oct_11 _R2)
Boeing C-17 Critical Path Tooling ASQ(Oct_11 _R2)Ron Gill
 
Critical Path Analysis for a New Product Release
Critical Path Analysis for a New Product ReleaseCritical Path Analysis for a New Product Release
Critical Path Analysis for a New Product Release
Asia Pacific Marketing Institute
 
Integrated Marketing Communications
Integrated Marketing CommunicationsIntegrated Marketing Communications
Integrated Marketing Communications
Jeff Hilton
 

Viewers also liked (20)

The ant story
The ant storyThe ant story
The ant story
 
E governance, gartner's model by bhim upadhyaya
E governance, gartner's model by bhim upadhyayaE governance, gartner's model by bhim upadhyaya
E governance, gartner's model by bhim upadhyaya
 
Rebirth of the_eagle
Rebirth of the_eagleRebirth of the_eagle
Rebirth of the_eagle
 
Apj abdul kalam's vision of developed nepal nov 2008
Apj abdul kalam's vision of developed nepal nov 2008Apj abdul kalam's vision of developed nepal nov 2008
Apj abdul kalam's vision of developed nepal nov 2008
 
My nepal is great ! (mero nepal mahaan)
My nepal is great ! (mero nepal mahaan)My nepal is great ! (mero nepal mahaan)
My nepal is great ! (mero nepal mahaan)
 
A vision of prosperous new nepal by bhim upadhyaya 064.11.5
A vision of prosperous new nepal  by bhim upadhyaya 064.11.5A vision of prosperous new nepal  by bhim upadhyaya 064.11.5
A vision of prosperous new nepal by bhim upadhyaya 064.11.5
 
जलस्रोत विकास परिषद्को कार्यविधि तथा गठनविधि 054.08.19
जलस्रोत विकास परिषद्को कार्यविधि तथा गठनविधि 054.08.19जलस्रोत विकास परिषद्को कार्यविधि तथा गठनविधि 054.08.19
जलस्रोत विकास परिषद्को कार्यविधि तथा गठनविधि 054.08.19
 
Workshop on Understnding E governance
Workshop on Understnding E governance Workshop on Understnding E governance
Workshop on Understnding E governance
 
E gov lecture1
E gov lecture1E gov lecture1
E gov lecture1
 
Final ppg 520 group ppt (group 5)
Final ppg 520 group ppt (group 5)Final ppg 520 group ppt (group 5)
Final ppg 520 group ppt (group 5)
 
Electronic Transaction Act 2063 (ETA 2063)
Electronic Transaction Act 2063 (ETA 2063)Electronic Transaction Act 2063 (ETA 2063)
Electronic Transaction Act 2063 (ETA 2063)
 
Cyber law in nepal and implementation
Cyber law in nepal and implementationCyber law in nepal and implementation
Cyber law in nepal and implementation
 
FACTORS INFLUENCING THE ADOPTION OF E-GOVERNMENT SERVICES IN PAKISTAN
FACTORS INFLUENCING THE ADOPTION OF E-GOVERNMENT SERVICES IN PAKISTANFACTORS INFLUENCING THE ADOPTION OF E-GOVERNMENT SERVICES IN PAKISTAN
FACTORS INFLUENCING THE ADOPTION OF E-GOVERNMENT SERVICES IN PAKISTAN
 
Lesson02_new
Lesson02_newLesson02_new
Lesson02_new
 
Pre-Con Ed: Critical Path Analysis with CA Workload Automation (AE) iDash - O...
Pre-Con Ed: Critical Path Analysis with CA Workload Automation (AE) iDash - O...Pre-Con Ed: Critical Path Analysis with CA Workload Automation (AE) iDash - O...
Pre-Con Ed: Critical Path Analysis with CA Workload Automation (AE) iDash - O...
 
Syam critical path cpa
Syam critical path cpaSyam critical path cpa
Syam critical path cpa
 
Education management information system nepal
Education management information system   nepalEducation management information system   nepal
Education management information system nepal
 
Boeing C-17 Critical Path Tooling ASQ(Oct_11 _R2)
Boeing  C-17 Critical Path Tooling  ASQ(Oct_11 _R2)Boeing  C-17 Critical Path Tooling  ASQ(Oct_11 _R2)
Boeing C-17 Critical Path Tooling ASQ(Oct_11 _R2)
 
Critical Path Analysis for a New Product Release
Critical Path Analysis for a New Product ReleaseCritical Path Analysis for a New Product Release
Critical Path Analysis for a New Product Release
 
Integrated Marketing Communications
Integrated Marketing CommunicationsIntegrated Marketing Communications
Integrated Marketing Communications
 

Similar to Critical path method & pert

Chap 4- CPM & PERT.pptx
Chap 4- CPM & PERT.pptxChap 4- CPM & PERT.pptx
Chap 4- CPM & PERT.pptx
mohammad_bilal
 
Cpm n pert
Cpm n pertCpm n pert
Cpm n pert
Sheetu Goel
 
Chapter 12(cpm pert)
Chapter 12(cpm pert)Chapter 12(cpm pert)
Chapter 12(cpm pert)Debanjan15
 
Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERT
S.Vijaya Bhaskar
 
CPM AND PERT
CPM AND PERTCPM AND PERT
CPM AND PERT
SimranGrewal33
 
06 pert cpm
06 pert cpm06 pert cpm
06 pert cpm
alhusami2006
 
Critical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel TemplateCritical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel Template
SHAZEBALIKHAN1
 
CPM, Network Analysis A-O-A, A-O-N, Resource management
CPM, Network Analysis A-O-A, A-O-N, Resource managementCPM, Network Analysis A-O-A, A-O-N, Resource management
CPM, Network Analysis A-O-A, A-O-N, Resource management
Amit Kumbar
 
Chapter 3.pptx
Chapter 3.pptxChapter 3.pptx
Chapter 3.pptx
BetshaTizazu2
 
project management-cpm and pert methods for managers
project management-cpm and pert methods for managersproject management-cpm and pert methods for managers
project management-cpm and pert methods for managers
Naganna Chetty
 
time mamangement.ppt
time mamangement.ppttime mamangement.ppt
time mamangement.ppt
Madhusha15
 
Pert cpm
Pert cpm Pert cpm
Pert cpm
Drprem Jerusha
 
06_Pert cpmugfhghfhxr justify gfghhhhhhh
06_Pert cpmugfhghfhxr justify gfghhhhhhh06_Pert cpmugfhghfhxr justify gfghhhhhhh
06_Pert cpmugfhghfhxr justify gfghhhhhhh
AmitDeshai
 
Advanced project management mod 4
Advanced project management mod 4Advanced project management mod 4
Advanced project management mod 4
POOJA UDAYAN
 
(PROGRAM EVALUATION AND REVIE TECHNIQUE)
(PROGRAM EVALUATION AND REVIE TECHNIQUE)(PROGRAM EVALUATION AND REVIE TECHNIQUE)
(PROGRAM EVALUATION AND REVIE TECHNIQUE)
hannahpepino1
 

Similar to Critical path method & pert (20)

Chap 4- CPM & PERT.pptx
Chap 4- CPM & PERT.pptxChap 4- CPM & PERT.pptx
Chap 4- CPM & PERT.pptx
 
Cpm n pert
Cpm n pertCpm n pert
Cpm n pert
 
Chapter 12(cpm pert)
Chapter 12(cpm pert)Chapter 12(cpm pert)
Chapter 12(cpm pert)
 
pert/cpm
pert/cpmpert/cpm
pert/cpm
 
Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERT
 
CPM AND PERT
CPM AND PERTCPM AND PERT
CPM AND PERT
 
Pert
PertPert
Pert
 
PERT CPM Intro
PERT CPM IntroPERT CPM Intro
PERT CPM Intro
 
Pert 182
Pert 182Pert 182
Pert 182
 
06 pert cpm
06 pert cpm06 pert cpm
06 pert cpm
 
Critical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel TemplateCritical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel Template
 
CPM, Network Analysis A-O-A, A-O-N, Resource management
CPM, Network Analysis A-O-A, A-O-N, Resource managementCPM, Network Analysis A-O-A, A-O-N, Resource management
CPM, Network Analysis A-O-A, A-O-N, Resource management
 
Chapter 3.pptx
Chapter 3.pptxChapter 3.pptx
Chapter 3.pptx
 
project management-cpm and pert methods for managers
project management-cpm and pert methods for managersproject management-cpm and pert methods for managers
project management-cpm and pert methods for managers
 
time mamangement.ppt
time mamangement.ppttime mamangement.ppt
time mamangement.ppt
 
Pert & Cpm
Pert & CpmPert & Cpm
Pert & Cpm
 
Pert cpm
Pert cpm Pert cpm
Pert cpm
 
06_Pert cpmugfhghfhxr justify gfghhhhhhh
06_Pert cpmugfhghfhxr justify gfghhhhhhh06_Pert cpmugfhghfhxr justify gfghhhhhhh
06_Pert cpmugfhghfhxr justify gfghhhhhhh
 
Advanced project management mod 4
Advanced project management mod 4Advanced project management mod 4
Advanced project management mod 4
 
(PROGRAM EVALUATION AND REVIE TECHNIQUE)
(PROGRAM EVALUATION AND REVIE TECHNIQUE)(PROGRAM EVALUATION AND REVIE TECHNIQUE)
(PROGRAM EVALUATION AND REVIE TECHNIQUE)
 

More from Bhim Upadhyaya

Role of engineers in infrastructure development for the prosperity of nepal ...
Role of engineers  in infrastructure development for the prosperity of nepal ...Role of engineers  in infrastructure development for the prosperity of nepal ...
Role of engineers in infrastructure development for the prosperity of nepal ...
Bhim Upadhyaya
 
India's vision and roadmap for development of sanskrit report
India's vision and roadmap for development of sanskrit reportIndia's vision and roadmap for development of sanskrit report
India's vision and roadmap for development of sanskrit report
Bhim Upadhyaya
 
Nepal faecal sludge management and regulatory framework 2074
Nepal faecal sludge management and regulatory framework 2074Nepal faecal sludge management and regulatory framework 2074
Nepal faecal sludge management and regulatory framework 2074
Bhim Upadhyaya
 
Nepal- Total sanitation guidelines 2073 ministry of water supply and sanitat...
Nepal- Total  sanitation guidelines 2073 ministry of water supply and sanitat...Nepal- Total  sanitation guidelines 2073 ministry of water supply and sanitat...
Nepal- Total sanitation guidelines 2073 ministry of water supply and sanitat...
Bhim Upadhyaya
 
जल तथा उर्जा आयोग गठनको गठन आदेश राजपत्र 049.3.15
जल तथा उर्जा आयोग गठनको गठन आदेश राजपत्र 049.3.15जल तथा उर्जा आयोग गठनको गठन आदेश राजपत्र 049.3.15
जल तथा उर्जा आयोग गठनको गठन आदेश राजपत्र 049.3.15
Bhim Upadhyaya
 
Water resources of nepal- in the context of climate change 2011 by wecs
Water resources of nepal- in the context of climate change 2011 by wecsWater resources of nepal- in the context of climate change 2011 by wecs
Water resources of nepal- in the context of climate change 2011 by wecs
Bhim Upadhyaya
 
Energy demand projection 2030 a study done by nepal investment board
Energy demand projection 2030  a study done by nepal investment boardEnergy demand projection 2030  a study done by nepal investment board
Energy demand projection 2030 a study done by nepal investment board
Bhim Upadhyaya
 
Nepal Energy strategy 2013 by wecs
Nepal Energy strategy 2013 by wecsNepal Energy strategy 2013 by wecs
Nepal Energy strategy 2013 by wecs
Bhim Upadhyaya
 
National Water Plan Nepal 2005 by WECS
National Water Plan Nepal 2005 by WECSNational Water Plan Nepal 2005 by WECS
National Water Plan Nepal 2005 by WECS
Bhim Upadhyaya
 
Water Resources Strategy Nepal 2002 by WECs
Water Resources Strategy Nepal 2002 by WECsWater Resources Strategy Nepal 2002 by WECs
Water Resources Strategy Nepal 2002 by WECs
Bhim Upadhyaya
 
Nepal - energy sector synopsis report 2010- wecs
Nepal - energy sector synopsis report 2010- wecsNepal - energy sector synopsis report 2010- wecs
Nepal - energy sector synopsis report 2010- wecs
Bhim Upadhyaya
 
Nepal final report on energy sectors vision 2050 ad
Nepal  final report on energy sectors vision 2050 adNepal  final report on energy sectors vision 2050 ad
Nepal final report on energy sectors vision 2050 ad
Bhim Upadhyaya
 
Andhra pradesh(india) sunrise vision 2029 draft by chandrababu naidu
Andhra pradesh(india) sunrise vision 2029 draft by chandrababu naiduAndhra pradesh(india) sunrise vision 2029 draft by chandrababu naidu
Andhra pradesh(india) sunrise vision 2029 draft by chandrababu naidu
Bhim Upadhyaya
 
Facebook sambad with naya patrika daily push 9th 2071
Facebook sambad with naya patrika daily push 9th 2071Facebook sambad with naya patrika daily push 9th 2071
Facebook sambad with naya patrika daily push 9th 2071
Bhim Upadhyaya
 
Ma pradhanmantri bhayeko bhaye as pub nayapatrika म प्रम भएको भए
Ma pradhanmantri bhayeko bhaye as pub nayapatrika म प्रम भएको भएMa pradhanmantri bhayeko bhaye as pub nayapatrika म प्रम भएको भए
Ma pradhanmantri bhayeko bhaye as pub nayapatrika म प्रम भएको भए
Bhim Upadhyaya
 
Gurustrotam in sanskrit and hindi
Gurustrotam in sanskrit and hindiGurustrotam in sanskrit and hindi
Gurustrotam in sanskrit and hindi
Bhim Upadhyaya
 
Engineering council uk guidance on security for engineers & technicians
Engineering council uk guidance on security for engineers & techniciansEngineering council uk guidance on security for engineers & technicians
Engineering council uk guidance on security for engineers & technicians
Bhim Upadhyaya
 
Sankskrit and science by dr raja ramanna
Sankskrit and  science by dr raja ramannaSankskrit and  science by dr raja ramanna
Sankskrit and science by dr raja ramanna
Bhim Upadhyaya
 
Ayurveda swadeshi chikitsa- part 1 by rajiv dixit
Ayurveda swadeshi chikitsa- part 1 by rajiv dixitAyurveda swadeshi chikitsa- part 1 by rajiv dixit
Ayurveda swadeshi chikitsa- part 1 by rajiv dixit
Bhim Upadhyaya
 
Ayurveda aapka swasthya aap ke haath by rajiv dixit
Ayurveda aapka swasthya aap ke haath by rajiv dixitAyurveda aapka swasthya aap ke haath by rajiv dixit
Ayurveda aapka swasthya aap ke haath by rajiv dixit
Bhim Upadhyaya
 

More from Bhim Upadhyaya (20)

Role of engineers in infrastructure development for the prosperity of nepal ...
Role of engineers  in infrastructure development for the prosperity of nepal ...Role of engineers  in infrastructure development for the prosperity of nepal ...
Role of engineers in infrastructure development for the prosperity of nepal ...
 
India's vision and roadmap for development of sanskrit report
India's vision and roadmap for development of sanskrit reportIndia's vision and roadmap for development of sanskrit report
India's vision and roadmap for development of sanskrit report
 
Nepal faecal sludge management and regulatory framework 2074
Nepal faecal sludge management and regulatory framework 2074Nepal faecal sludge management and regulatory framework 2074
Nepal faecal sludge management and regulatory framework 2074
 
Nepal- Total sanitation guidelines 2073 ministry of water supply and sanitat...
Nepal- Total  sanitation guidelines 2073 ministry of water supply and sanitat...Nepal- Total  sanitation guidelines 2073 ministry of water supply and sanitat...
Nepal- Total sanitation guidelines 2073 ministry of water supply and sanitat...
 
जल तथा उर्जा आयोग गठनको गठन आदेश राजपत्र 049.3.15
जल तथा उर्जा आयोग गठनको गठन आदेश राजपत्र 049.3.15जल तथा उर्जा आयोग गठनको गठन आदेश राजपत्र 049.3.15
जल तथा उर्जा आयोग गठनको गठन आदेश राजपत्र 049.3.15
 
Water resources of nepal- in the context of climate change 2011 by wecs
Water resources of nepal- in the context of climate change 2011 by wecsWater resources of nepal- in the context of climate change 2011 by wecs
Water resources of nepal- in the context of climate change 2011 by wecs
 
Energy demand projection 2030 a study done by nepal investment board
Energy demand projection 2030  a study done by nepal investment boardEnergy demand projection 2030  a study done by nepal investment board
Energy demand projection 2030 a study done by nepal investment board
 
Nepal Energy strategy 2013 by wecs
Nepal Energy strategy 2013 by wecsNepal Energy strategy 2013 by wecs
Nepal Energy strategy 2013 by wecs
 
National Water Plan Nepal 2005 by WECS
National Water Plan Nepal 2005 by WECSNational Water Plan Nepal 2005 by WECS
National Water Plan Nepal 2005 by WECS
 
Water Resources Strategy Nepal 2002 by WECs
Water Resources Strategy Nepal 2002 by WECsWater Resources Strategy Nepal 2002 by WECs
Water Resources Strategy Nepal 2002 by WECs
 
Nepal - energy sector synopsis report 2010- wecs
Nepal - energy sector synopsis report 2010- wecsNepal - energy sector synopsis report 2010- wecs
Nepal - energy sector synopsis report 2010- wecs
 
Nepal final report on energy sectors vision 2050 ad
Nepal  final report on energy sectors vision 2050 adNepal  final report on energy sectors vision 2050 ad
Nepal final report on energy sectors vision 2050 ad
 
Andhra pradesh(india) sunrise vision 2029 draft by chandrababu naidu
Andhra pradesh(india) sunrise vision 2029 draft by chandrababu naiduAndhra pradesh(india) sunrise vision 2029 draft by chandrababu naidu
Andhra pradesh(india) sunrise vision 2029 draft by chandrababu naidu
 
Facebook sambad with naya patrika daily push 9th 2071
Facebook sambad with naya patrika daily push 9th 2071Facebook sambad with naya patrika daily push 9th 2071
Facebook sambad with naya patrika daily push 9th 2071
 
Ma pradhanmantri bhayeko bhaye as pub nayapatrika म प्रम भएको भए
Ma pradhanmantri bhayeko bhaye as pub nayapatrika म प्रम भएको भएMa pradhanmantri bhayeko bhaye as pub nayapatrika म प्रम भएको भए
Ma pradhanmantri bhayeko bhaye as pub nayapatrika म प्रम भएको भए
 
Gurustrotam in sanskrit and hindi
Gurustrotam in sanskrit and hindiGurustrotam in sanskrit and hindi
Gurustrotam in sanskrit and hindi
 
Engineering council uk guidance on security for engineers & technicians
Engineering council uk guidance on security for engineers & techniciansEngineering council uk guidance on security for engineers & technicians
Engineering council uk guidance on security for engineers & technicians
 
Sankskrit and science by dr raja ramanna
Sankskrit and  science by dr raja ramannaSankskrit and  science by dr raja ramanna
Sankskrit and science by dr raja ramanna
 
Ayurveda swadeshi chikitsa- part 1 by rajiv dixit
Ayurveda swadeshi chikitsa- part 1 by rajiv dixitAyurveda swadeshi chikitsa- part 1 by rajiv dixit
Ayurveda swadeshi chikitsa- part 1 by rajiv dixit
 
Ayurveda aapka swasthya aap ke haath by rajiv dixit
Ayurveda aapka swasthya aap ke haath by rajiv dixitAyurveda aapka swasthya aap ke haath by rajiv dixit
Ayurveda aapka swasthya aap ke haath by rajiv dixit
 

Recently uploaded

Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345
beazzy04
 
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
EugeneSaldivar
 
The Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdfThe Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdf
kaushalkr1407
 
Palestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptxPalestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptx
RaedMohamed3
 
Chapter 3 - Islamic Banking Products and Services.pptx
Chapter 3 - Islamic Banking Products and Services.pptxChapter 3 - Islamic Banking Products and Services.pptx
Chapter 3 - Islamic Banking Products and Services.pptx
Mohd Adib Abd Muin, Senior Lecturer at Universiti Utara Malaysia
 
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
Levi Shapiro
 
How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...
Jisc
 
Supporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptxSupporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptx
Jisc
 
The French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free downloadThe French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free download
Vivekanand Anglo Vedic Academy
 
The approach at University of Liverpool.pptx
The approach at University of Liverpool.pptxThe approach at University of Liverpool.pptx
The approach at University of Liverpool.pptx
Jisc
 
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXXPhrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
MIRIAMSALINAS13
 
Francesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptxFrancesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptx
EduSkills OECD
 
Synthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptxSynthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptx
Pavel ( NSTU)
 
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
Nguyen Thanh Tu Collection
 
CACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdfCACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdf
camakaiclarkmusic
 
Biological Screening of Herbal Drugs in detailed.
Biological Screening of Herbal Drugs in detailed.Biological Screening of Herbal Drugs in detailed.
Biological Screening of Herbal Drugs in detailed.
Ashokrao Mane college of Pharmacy Peth-Vadgaon
 
Home assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdfHome assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdf
Tamralipta Mahavidyalaya
 
Acetabularia Information For Class 9 .docx
Acetabularia Information For Class 9  .docxAcetabularia Information For Class 9  .docx
Acetabularia Information For Class 9 .docx
vaibhavrinwa19
 
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCECLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
BhavyaRajput3
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
siemaillard
 

Recently uploaded (20)

Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345
 
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
 
The Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdfThe Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdf
 
Palestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptxPalestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptx
 
Chapter 3 - Islamic Banking Products and Services.pptx
Chapter 3 - Islamic Banking Products and Services.pptxChapter 3 - Islamic Banking Products and Services.pptx
Chapter 3 - Islamic Banking Products and Services.pptx
 
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
 
How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...
 
Supporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptxSupporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptx
 
The French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free downloadThe French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free download
 
The approach at University of Liverpool.pptx
The approach at University of Liverpool.pptxThe approach at University of Liverpool.pptx
The approach at University of Liverpool.pptx
 
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXXPhrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
 
Francesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptxFrancesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptx
 
Synthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptxSynthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptx
 
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
 
CACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdfCACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdf
 
Biological Screening of Herbal Drugs in detailed.
Biological Screening of Herbal Drugs in detailed.Biological Screening of Herbal Drugs in detailed.
Biological Screening of Herbal Drugs in detailed.
 
Home assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdfHome assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdf
 
Acetabularia Information For Class 9 .docx
Acetabularia Information For Class 9  .docxAcetabularia Information For Class 9  .docx
Acetabularia Information For Class 9 .docx
 
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCECLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
 

Critical path method & pert

  • 1. PERT/CPM Models for Project Management
  • 2. Agenda What is Project Management Discuss PERT/CPM Motivating Case Study: The Reliable Construction Company Ways of Finding the Critical Path Considering Time-Cost Trade-Offs
  • 3. What is Project Management Project management can be defined as the coordination of activities with the potential use of many organizations, both internal and external to the business, in order to conduct a large scale project from beginning to end. There are two management science techniques that are used for project management: Program and Evaluation Review Technique (PERT) Critical Path Method (CPM)
  • 4. PERT/CPM PERT PERT was designed to examine projects from the standpoint of uncertainty. CPM CPM was designed to examine projects from the standpoint of costs. PERT and CPM techniques have been combined over time. PERT and CPM both rely heavily on the use of networks to help plan and display the coordination of all the activities for a project.
  • 5. The Reliable Construction Company Reliable has just secured a contract to construct a new plant for a major manufacturer. The contract is for $5.4 million to cover all costs and any profits. The plant must be finished in a year. A penalty of $300,000 will be assessed if Reliable does not complete the project within 47 weeks. A bonus of $150,000 will be paid to Reliable if the plant is completed within 40 weeks.
  • 6. Needed Terminology Activity A distinct task that needs to be performed as part of the project. Start Node This is a node that represents the beginning of the project. Finish Node This node represents the end of the project.
  • 7. Needed Terminology Cont. Immediate Predecessor These are activities that must be completed by no later than the start time of the given activity. Immediate Successor Given the immediate predecessor of an activity, this activity becomes the immediate successor of each of these immediate predecessors. If an immediate successor has multiple immediate predecessors, then all must be finished before an activity can begin.
  • 8. Activity List for Reliable Construction
  • 9. Questions Needed to be Answered How can the project be displayed graphically? How much time is required to finish the project if no delays occur? When is earliest start and finish times for each activity if no delays occur? What activities are critical bottleneck activities where delays must be avoided to finish the project on time?
  • 10. Questions Needed to be Answered Cont. For non bottleneck activities, how much can an activity be delayed and yet still keep the project on time? What is the probability of completing the project by the deadline? What is the least amount of money needed to expedite the project to obtain the bonus? How should costs be monitored to keep the project within budget?
  • 11. Project Network A project network is a network diagram that uses nodes and arcs to represent the progression of the activities is a project from start to finish. Three pieces of information needed: Activity information Precedence relationship Time information
  • 12. Project Network Cont. Two types of project networks Activity-on-Arc (AOA) On this diagram, the activity is represented on an arc, while a node is used to separate an activity from its immediate predecessors. Activity-on-Node (AON) On this diagram, the activity is represented by the node, while the arc is used to showed the precedence relationship between the activities.
  • 13.
  • 14. Microsoft Project Visual Diagram: Gantt Chart
  • 15. Scheduling Using PERT/CPM A path through a project network is a route that follows a set of arcs from the start node to the finish node. The length of a path is defined as the sum of the durations of the activities of the path. What are the paths and their corresponding lengths for Reliable?
  • 16. Critical Path This is the path that has the longest length through the project. The shortest time that a project can conceivably be finished is the critical path. Why?
  • 17. More Terminology Earliest start time of an activity (ES) The time at which an activity will begin if there are no delays in a project. Earliest finish time of an activity (EF) The time at which an activity will finish if there are no delays in a project. Latest start time of an activity (LS) The latest possible time that an activity can start without delaying the project.
  • 18. More Terminology Cont. Latest finish time of an activity (LF) The latest possible time that an activity can be completed without delaying the project. Forward pass The process of moving through a project from start to finish to determine the earliest start and finish times for the activities in the project.
  • 19. More Terminology Cont. Backward pass The process of moving through a project from finish to start to determine the latest start and finish times for the activities in the project. Slack for an activity The amount of time that a particular activity can be delayed without delaying the whole project. It is calculated by taking the difference between the latest finish time with the earliest finish time.
  • 20. More Terminology Cont. Earliest start time rule The earliest start time for an activity is equal to the largest of the earliest finish times of its immediate predecessors. Latest finish time rule The latest finish time is equal to the smallest of the latest start times of its immediate successors.
  • 21. Procedure for Obtaining Earliest Times Step 1: For the activity that starts the project, assign an earliest start time of zero, i.e., ES=0. Step 2: For each activity whose ES has just been obtained, calculate its earliest finish time as ES plus duration of the activity. Step 3: For each new activity whose immediate predecessors have EF values, obtain its ES by using the earliest start time rule.
  • 22. Procedure for Obtaining Earliest Times Cont. Step 4: Apply step 2 to calculate EF. Step 5: Repeat step 3 until ES and EF have been obtained for all activities including the finish node.
  • 23. Procedure for Obtaining Latest Times Step 1: For each of the activities that together complete the project, set its latest finish time equal to the earliest finish time of the finish node. Step 2: For each activity whose LF value has just been obtained, calculate its latest start time as LS equals LF minus the duration of the activity.
  • 24. Procedure for Obtaining Latest Times Cont. Step 3: For each new activity whose immediate successors now have LS values, obtain its LF by applying the latest finish time rule. Step 4: Apply step 2 to calculate its LS. Step 5: Repeat step 3 until LF and LS have been obtained for all activities.
  • 25.
  • 26. Ways of Finding the Critical Path Examine all the paths and find the path with the maximum length. Calculate the slack for an activity. If the slack is zero, it is on the critical path. If the slack is positive, it is not on the critical path.
  • 27. Time-Cost Trade-Offs Reliable had an incentive bonus of $150,000 to finish the project in 40 weeks. Is it worth while for Reliable to speed-up the project?
  • 28. Crashing Crashing an activity refers to taking on extra expenditures in order to reduce the duration of an activity below its expected value. Crashing a project refers to crashing a number of activities to reduce the duration of the project.
  • 29. CPM Method of Time-Cost Trade-Offs This is a method concerned with whether it is worthwhile to crash activities to reduce the anticipated duration of the project to a desired value. This assumes that there is a trade-off between time and cost that has an inverse relationship.
  • 30. More Terminology Normal Point is the time and cost of an activity when it is performed in a normal way. Crash point show the time and cost when the activity is fully crashed.
  • 31. Graph of Normal and Crash Points
  • 32. Marginal Cost Analysis It is a method of using the marginal cost of crashing individual activities on the current critical path to determine the least expensive way of reducing the project duration to an acceptable level. This method requires you to calculate the cost per desired time unit and compare each cost with the other costs.
  • 33.
  • 34. Marginal Cost Analysis Cont. Once the marginal cost for crashing each activity has been conducted, you next want to choose the crashing that has the smallest marginal cost. Next, calculate the effect that the crash has on each path. Note: Crashing can potentially cause another path to become a critical path.
  • 35. Solving Crashing Problems Using LP There are three decisions to be made: The start time of each activity The reduction in each activity due to crashing The finish time of the project LP model will be examined in class.