SlideShare a Scribd company logo
R.V.Kolhe
Grouting METHODS
BY
Prof. Rushikesh v. Kolhe
Department of Civil engineering
Sanjivani college of Engineering
R.V.Kolhe
Grouting
• INJECTION OF SLURRY/LIQUID SOLUTION INTO
ROCK OR SOIL.
• INJECTED MTRL IS GROUT
• TECHNIQUE DEVELOPED FOR MAKING VERTICAL
SEEPAGE BARRIER BY CEMENT SLURRY.
• CEMENTING CAPABILITY INCREASES SOIL/ROCK STR.
• CEMENT SLURRY IS NON-PERMEABLE SO
SPL CHEMICALS WERE INVENTED.
R.V.Kolhe
TYPE OF GROUTS
• SUSPENSIONS – CEMENT OR
BENTONITE GROUT
• EMULSIONS- BITUMEN EMULSIONS
• SOLUTIONS- SODIUM SILICATE
OR ACRYLIC RAISIN.
R.V.Kolhe
DESIRABLE CHAR OF GROUTS
• STABLITY: CAPABLITY OF GROUT TO
REMAIN IN FLUID STATE.
– GROUT NOT TO SEGREGATE BEFORE
REACHING DESTINATION.
– STABLITY OF CLAY CEMENT GROUT >
CEMENT GROUT
R.V.Kolhe
DESIRABLE CHAR OF GROUTS
• SETTING TIME : TIME TO SET TO
CEMENTED MASS OR GEL.
– EARLY SETTING : REACHING DESTINATION.
– LATE SETTING: GROUT WASHED AWAY. (SEEPAGE)
– RETARD OR ACCELERATE BY ADDITIVES
R.V.Kolhe
DESIRABLE CHAR OF GROUTS
• PERMANENCE: RESISTANCE OF GROUT AGAINST
DISPLACEMENT FROM SOIL WITH TIME.
– CEMENT GROUTS > BENTONITE GROUT ( WASHED
AWAY BY SEEPAGE WATER)
R.V.Kolhe
DESIRABLE CHAR OF GROUTS
• TOXICITY: CONTAMINATE SURROUNDING
SOIL AND GROUND WATER.
• HEALTH HAZARD
R.V.Kolhe
TYPES OF GROUTING TECHNIQUES
• GROUTING METHODS FOR SOILS ARE CLASSIFIED AS:
(I) PERMEATION GROUTING
(II) DISPLACEMENT-SOIL FRACTURE GROUTING
(III) DISPLACEMENT-COMPACTION GROUTING
(IV) JET OR REPLACEMENT-DISPLACEMENTGROUTING
R.V.Kolhe
PERMEATION GROUTING
If the injection of grout in soil is done in a manner that the arrangement
of the soil grains is not disturbed and only the void space is filled by a
process of permeation, that is, seepage, the method is referred to as
permeation grouting as shown in fig.
R.V.Kolhe
Displacement Grouting
R.V.Kolhe
If, however, the process of injection displaces the soil grains, the
method is termed as displacement grouting. Displacement grouting is
further divided into two sub— types, namely, compaction grouting and
soil fracture grouting. Compaction grouting consists of injecting a thick
viscous paste—like slurry at high pressure to form a bulb shaped
grouted mass in soil as shown in fig.
R.V.Kolhe
On the other hand when lean slurry of high fluidity is injected
into the soil at high pressure to form root-like lenses of grout
material in the soil mass as depicted in fig. , the method is
termed as soil fracture grouting.
R.V.Kolhe
Jet Grouting
Displacement-Replacement
Grouting
R.V.Kolhe
In yet another method the grout material is injected into the
soil mass in the form of a jet to form a grouted column as
shown in fig. by partly replacing the soil, partly mixing with the
remaining soil and also through displacing the soil. This
method is referred to as jet grouting or replacement-
displacement grouting.
R.V.Kolhe
R.V.Kolhe
Permeation Grouting
R.V.Kolhe
Permeation Grouting
• CEMENT GROUTS, BENTENITE GROUTS AND
CHEMICAL GROUTS ARE USED FOR
PERMEATION GROUTING AS SUMMARIZED
1N TABLE.
• CHEMLCAL GROUTS ARE SUITABLE FOR THE
MAXIMUM RANGE OF GRAIN SIZES BUT THEY
ARE VERY EXPENSIVE
R.V.Kolhe
PERMEATION GROUTING
• Cement grout not only fills the voids and reduces
permeability but also sets with time and binds
the soil grains together. As a consequence, the
strength of the soil mass increases and its
compressibility decreases. Sometimes cement in
grout is replaced by clay to reduce cost. solved
• When the objective of grouting is only to reduce
permeability, bentonite grouts can be used.
However, the permanence of such grouts under
high hydraulic gradients is questionable and
often cement is added.
R.V.Kolhe
• Permeation grouting is widely used for making vertical seepage barriers
beneath hydraulic structures as shown in fig.
• It is also used for stabilization of soil around tunnels and shafts as
depicted in fig. (b).
• other uses include stoppage of seepage through joints of underground
structures such as tunnel lining, basement wall
etc.
R.V.Kolhe
GROUTING PLANT FOR PERMEATION (CEMENTGROUT )
• Grout slurry is prepared by mixing
cement with water in a slow-
speed paddle mixer followed by a
high-speed agitator.
• A positive displacement pump
(reciprocating or diaphragm type) is-
used for pumping the slurry into a
grout supply line (pipe of 30' to 50 mm
diameter) which transports the slurry
under pressure to the point of
injection in the soil.
• The grout pipe is lowered into the
grout hole that has already been
drilled to the grouting point.
• The annularspace between the grout
hole and grout pipe is sealed and the
grout slurry injected into the soil at
the prescribed pressure.
• Packers, in the form of leather cups or
inflatable rubber seals, are used for
Sealing the annular space—see Fig.
31,4,
R.V.Kolhe
• when the grouting has to
be executed down to the
shallow depth below the
ground surface (few
meters.
• Grout hole is drilled
completely.
• grout pipe is inserted
from top
• annular spaces are sealed
and grouting is done
under low pressure
R.V.Kolhe
R.V.Kolhe
R.V.Kolhe
R.V.Kolhe
PERMEATION GROUT DETAILS
R.V.Kolhe
Descending and Ascending Stage
Grouting:
• For grouting to larger depths, grouting is executed in stages.
• In the DESCENDING STAGE grouting, drilling and grouting
are executed alternatively in stages of 3 to 5 m in the
downward direction as shown in Fig.
• For each stage, as one goes deeper, one can use higher
grout pressure.
• ASCENDING STAGE grouting shown in Fig. is executed in a
reverse manner
• The grout hole is drilled to the full depth in one operation.
• Subsequently the grout pipe is lowered to the deepest segment
of the hole and the annular space sealed using a packer.
• Grouting is carried out at high pressure. Thereafter, the grout
pipe and the packer is raised in stagesof3 to 5 m and the
R.V.Kolhe
R.V.Kolhe
ASCENDING STAGE GROUTING
R.V.Kolhe
Descending and Ascending Stage
Grouting:
• ASCENDING STAGE GROUTING HAS THE ADVANTAGE
THAT THE DRILLING IS ALL DONE IN ONE GO.
• IN DESCENDING STAGE GROUTING, ONE CAN
USE HIGHER GROUT PRESSURES AS ONE MOVES
TO LOWER STAGES
• NOT ONLY BECAUSE OF GREATER DEPTH BUT ALSO
BECAUSE THE UPPER LEVELS HAVE BEEN GROUTED
AND THE SOIL FORMATION IS MORE FIRM ESPECIALLY
WHEN GROUTS USED ARE OF TYPES THAT SET AND
ADD TO STRENGTH.
R.V.Kolhe
GROUTING USING SLEEVED PIPE
• ASCENDING STAGE GROUTING IN SOIL MAY BE HAMPERED
DUE TO IMPROPER FUNCTIONING OF PACKERS WHEN PUSHED
OR EXPANDED AGAINST AN UNEVEN GROUT HOLE WALL.
• HENCE SLEEVED PIPE GROUTING DEPICTED IN FIG. 31.8 IS
OFTEN MORE SUCCESSFUL. IN THIS A SLOTTED PIPE,
HAVING VERTICAL SLOTS COVERED WITH THIN RUBBER
SLEEVES, IS LOWERED INTO THE GROUT HOLE.
• THE SPACE BETWEEN THE SLOTTED PIPE AND THE GROUT HOLE
IS SEALED WITH CEMENT-BENTONITE SEAL.
• GROUTING IS DONE BY LOWERING THE GROUT PIPE WITH A
PAIR OF PACKERS TO THE DESIRED ELEVATION INSIDE THE
SLOTTED PIPE AND INJECTING THE GROUT UNDER PRESSURE.
• GROUT PRESSURE BRUSTS THE TEMP RUBBER SLEEVE AND
CEMENT BENTONITE SEAL.
• GROUT PERMEATES INTP ADJOINING SOIL.
R.V.Kolhe
Grouting using sleeved pipe
R.V.Kolhe
R.V.Kolhe
Grouting using sleeved pipe
R.V.Kolhe
Grouting using sleeved pipe
R.V.Kolhe
CURTAIN GROUTING
• GROUTING ARRANGEMENTS THAT PERMEATION GROUTING
IS OFTEN USED FOR MAKING VERTICAL SEEPAGE BARRIERS
BENEATH HYDRAULIC STRUCTURES HAS ALREADY BEEN
HIGHLIGHTED EARLIER.
• THIS GROUTING ARRANGEMENT IS CALLED CURTAIN
GROUTING. TYPICALLY, GROUTING IS CARRIED OUT TO THE
REQUIRED DEPTH ALONG 2 TO 3 ROWS OF GROUT HOLES.
• THE GROUT HOLES IN EACH ROW MAY BE SPACED AT 2 TO 4
M AND STAGGERED IN PLAN ALONG THE ROWS.
• GROUTING IS FIRST DONE IN PRIMARY HOLES SPACED 15—
25 M APART FOLLOWED BY SECONDARY HOLES AT
INTERMEDIATE LOC AND THEN TERTIARY HOLES AT 2—4 M
SPACING AS SHOWN IN FIG. 31.9.
R.V.Kolhe
CURTAIN GROUTING
R.V.Kolhe
BLANKET GROUTING
• IT REFERS PERMEATION GROUTING CARRIED OUT
OVER A LARGE AREA IN PLAN DOWN TO A SHALLOW
FIXED DEPTH.
• SUCH A GROUTED ZONE IN THE SHAPE OF A BLANKET
IS OFTEN CREATED BEHIND HYDRAULIC STRUCTURE
TO REDUCE WATER LOSS BY SEEPAGE FROM THE
RESERVOIR,
• THE GROUTED BLANKET INCREASES THE SEEPAGE PATH.
• GROUTING IS FIRST EXECUTED IN PRIMARY HOLES AT
A GRID SPACING OF ABOUT 20 M FOLLOWED BY
SECONDARY HOLES AT A GRID SPACEING OF ABOUT
R.V.Kolhe
10 M AND FINALLY IN A CLOSELY SPACED TERTIARY
GRID OF HOLES AT A SPACING OF ABOUT 5 M.
R.V.Kolhe
BLANKET GROUTING
R.V.Kolhe
DISPLACEMENT-COMPACTION
GROUTING
• INJECTION OF GROUT UNDER HIGH PRESSURE IN SOIL MASS.
• CAUSES DISPLACEMENT OF SOIL PARTICLES.
• BULBOUS/SPHERICAL SHAPED INTRUSIONS RANGE OF 0.5 TO 1.0
M ARE FORMED.
• THE GROUT MATERIAL USED IS A MIXTURE OF SOIL AND CEMENT,
SEE TABLE 31.2.
•
• THE SOIL USED IN THE GROUT HAS SUFFICIENT SAND SIZED
PARTICLES TO DEVELOP INTERNAL FRICTION AS WELL AS ENOUGH
FINE GRAINED PARTICLES TO PROVIDE PLASTICITY TO THE GROUT.
R.V.Kolhe
DISPLACEMENT-COMPACTION
GROUTING
• WATER IS ADDED TO YIELD A PASTE-LIKE CONSISTENCY
OF THE GROUT.
• WE NEED TO USE JUST ENOUGH CEMENT SO THAT THE
ENGINEERING PROPERTIES OF THE GROUTED MASS ARE
SIMILAR TO OR BETTER THAN THOSE OF THE NATURAL SOIL
IN A COMPACTEDSTATE.
• IN SOME CASES, WHEN PERMANENCE IS NOT AN ISSUE,
CEMENT NEED NOT BE USED AT ALL AND THE GROUT CAN
BE JUST A SOIL SLURRY.
R.V.Kolhe
GROUT MATERIAL:DISPLACEMENT-
COMPACTION GROUTING
R.V.Kolhe
DISPLACEMENT-COMPACTION
GROUTING
• THE TECHNOLOGY OF INJECTION OF GROUT IS SIMILAR TO THAT FOR
PERMEATIONGROUTING.
• HOWEVER, SINCE THE GROUT MIX IS MUCH STIFFER THAN IN PERMEATION
GROUTING AND GROUT PRESSURES ARE MUCH HIGHER, THE GROUT PUMPS USED
ARE HEAVY-DUTY CONCRETE PUMPS.
• GROUT PIPE DIAMETERS RANGE FROM 50 TO 75 MM.
• THE QUANTITY OF GROUT INJECTED IS OBSERVED TO RANGE FROM 3 TO
12 PERCENT BY VOLUME OF THE TREATED LOOSE SOIL,
• DISPLACEMENT-COMPACTIONGROUTING IS SUITABLE FOR ALL TYPES OF LOOSE
COARSE GRAINED SOILS, SOFT FINE GRAINED SOILS WHICH ARE NOT
SATURATED AND FOR FILLING UNDERGROUND CAVITIES.
• IT IS NOT USED IN SOFT SATURATED FINE GRAINED SOILS BECAUSE GROUTING
RAISES THE PORE WATER PRESSURE IN THE SOIL MASS LEADING TO UNEVEN
AND AGGRAVATED SETTLEMENT PROBLEMS.
R.V.Kolhe
DISPLACEMENT-COMPACTION
GROUTING
• IN COMPARISON TO OTHER TYPES OF GROUTING,
DISPLACEMENT— COMPACTION GROUTING IS OBSERVED TO BE
USEFUL FOR THE FOLLOWING SITUATIONS:
• (I) DENSIFICATION OF THIN LOOSE STRATUM UNDERLYING DENSE
SOIL AND LOCATED AT CONSIDERABLE DEPTH—SEE FIG. 31.11(A) AND
(B)
• (II) DENSIFICATION OF POCKETS OF LOOSE SOILS BENEATH
FOUNDATIONS OR FLOOR SLABS THAT ARE REVEALED AFTER
CONSTRUCTION IS COMPLETED INCLUDING LEVELING OF SUNKEN
FLOORS—ALSO REFERRED TO AS SLAB-JACKING OR BACK-
PACKING— SEE FIG. 31.11(C),
R.V.Kolhe
DISPLACEMENT-COMPACTION
GROUTING
• (III) FILLING OF LARGE UNDERGROUND CAVITIES CAUSED BY BROKEN
UNDERGROUND UTILITY LINES, BY PIPING/ EROSION, OR BY
DISSOLUTION AS DEPICTED IN FIG. 31.11(D) AND (E); IN SUCH CASES,
THE CAVITIES ARE FIRST FILLED WITH GROUT AND THEN THE
DENSITY OF SURROUNDING SOIL IS INCREASED BY GROUTING WITH
APPROPRIATE GROUT PRESSURE, AND
• (IV) DENSIFICATION OF SOILS SHOWING ORGANIC
DEGRADATION WITH TIME. DISPLACEMENT-COMPACTION
GROUTING IS MOST OFTEN USED IN SMALL AREAS OR POCKETS
AS A REMEDIATION TECHNIQUE. IT IS RARELY COST EFFECTIVE
FOR GROUND IMPROVEMENT OVER LARGE AREAS.
R.V.Kolhe
DISPLACEMENT-
COMPACTION GROUTING
R.V.Kolhe
DISPLACEMENT-
COMPACTION GROUTING
R.V.Kolhe
DISPLACEMENT-
COMPACTION GROUTING
R.V.Kolhe
DISPLACEMENT-
COMPACTION GROUTING
R.V.Kolhe
Displacement—Soil Fracture Grouting
• SOIL FRACTURE GROUTING TECHNIQUE IS A
DISPLACEMENT GROUTING TECHNIQUE IN WHICH A
LEAN SLURRY OF CEMENT, SOIL AND WATER IS
INJECTED INTO THE SOIL AT HIGH PRESSURE TO
FRACTURE THE SOIL AND FORM ROOT—LIKE OR THIN
LENS SHAPED ZONES OF GROUT MATERIAL IN THE
SOIL MASS.
• THE GROUT MATERIAL SPREADS ALL AROUND THE
GROUT HOLE CAUSING DENSIFICATION OF THE
SOIL MASS AND AN INCREASE IN ITS
MACROSCOPIC STRENGTH.
•
R.V.Kolhe
SOIL FRACTURE GROUTING
R.V.Kolhe
SUCH GROUTING ALSO CAUSES THE GROUND TO
HEAVE AND THAT CAN BE USED TO ADVANTAGE,
FOR EXAMPLE, IN RECTIFYING TILT IN BUILDINGS
AND RESTORING THEIR VERTICALITY AS SHOWN IN
FIG. 31.12.
R.V.Kolhe
Restoration of verticality of a tilted
building
• RESTORATION OF VERTICALITY OF A TILTED
BUILDING SUCH GROUTING IS USUALLY
ACCOMPLISHED USING THE SLEEVED PIPE
GROUTING TECHNIQUE AS DEPICTED IN FIG. 31.13.
• GROUT HOLES, 100 MM IN DIAMETER, ARE DRILLED
AT REGULAR INTERVALS AND SLEEVED PIPES WITH
MULTIPLE SLOTS ARE PLACED IN THE GROUT HOLES.
GROUTING IS DONE IN SEGMENTS OF 0.3 TO 1.0 M
ALONG THE LENGTH OF EACH SLOTTED PIPE USING
GROUT PRESSURES AS HIGH AS 4000 KN/MZ.
R.V.Kolhe
JET GROUTING
R.V.Kolhe
Jet or Replacement—Displacement
Grouting
• GROUTING IN THIS TECHNIQUE, A SPECIAL GROUT PIPE CALLED
THE MONITOR HAVING HIGH-SPEED JETS OF WATER OR GROUT IS
USED TO ERODE AND EXCAVATE THE SOIL
• THEREAFTER, AS THE MONITOR IS WITHDRAWN, STRONG,
IMPERVIOUS COLUMNS ARE PRODUCED BY MIXING GROUT
WITH THE REMAINING SOIL.
• THE TECHNIQUE IS CALLED REPLACEMENT  DISPLACEMENT BECAUSE
A PART OF THE SOIL IS REMOVED BY THE JETTING ACTION AND IS
REPLACED BY THE GROUT MATERIAL AND BECAUSE THE GROUT IS
INJECTED AT HIGH PRESSURE PARTLY TO MIX WITH THE REMAINING
SOIL AND BARTLY TO DISPLACE THE SURROUNDING SOIL.
R.V.Kolhe
Jet or Replacement—Displacement
Grouting
• THE GROUT MATERIALS USED ARE CEMENT AND WATER WITH
SOME ADDITIVE AS INDICATED IN TABLE 31.3.
• JET GROUTING IS THE YOUNGEST OF GROUTING TECHNIQUES
AND CONSULTING GEOTECHNICAL ENGINEERS HAVE BEGUN TO
USE IT AFTER THE MID-1980S.
• IT IS MORE EXPENSIVE THAN PERMEATION GROUTING, DUE TO
LARGER CONSUMPTION OF CEMENT PER UNIT VOLUME OF
SOIL MASS TREATED.
R.V.Kolhe
• NEVERTHELESS, IT IS NOW EXTENSIVELY USED AS IT PRODUCES
MORE UNIFORM GROUTING, CAN BE USED IN MOST SOILS AND HAS
A HIGHER RATE OF PRODUCTIVITY
R.V.Kolhe
Jet or Replacement—Displacement
Grouting
R.V.Kolhe
Jet or Replacement—Displacement
Grouting
• TYPES OF JET GROUTING
– SINGLE JET OR ONE FLUID SYSTEM
– DOUBLE JET OR 02 FLUID SYSTEM
– TRIPLE JET OR 03 FLUID SYSTEM.
• THE FIRST STEP IS TO DRILL A GROUT HOLE OF 100 TO 150 MM DIAMETER.
• THE HOLE IS KEPT STABLE BY USING WATER CIRCULATION OR BENTONITE
SLURRY CIRCULATION.
• IN THE SECOND STEP, JETTING COMMENCES IN THE HORIZONTALDIRECTION
THROUGH NOZZLES (2 TO 4 MM IN DIAMETER)AT THE TIP OF THE MONITOR
THAT IS ROTATED AT 5 TO 30 REVOLUTIONS PER MINUTE.
• THE SOIL CUTTINGS TRAVEL TO THE GROUND SURFACE THROUGH THE
ANNULAR SPACE BETWEEN THE BOREHOLEAND THE MONITOR.
• THE MONITOR IS LIFTED AT A RATE OF 50 TO 300 MM PER MINUTE IN THE
THIRD STEP RESULTING IN THE FORMATLON OF A GROUTED COLUMN.
R.V.Kolhe
Jet Grouting Tech
R.V.Kolhe
• IN THE SINGLE JET SYSTEM, A HORIZONTAL JET OF GROUT AS
SHOWN IN FIG. SIMULTANEOUSLY ERODES THE SOIL AND
MIXES WITH A PART OF THE REMAINING SOIL TO FORM A
GROUTED COLUMN.
• IN THE DOUBLE JET SYSTEM, THE EROSIVE EFFECT OF THE GROUT
JET IS CONSIDERABLY ENHANCED BY THE ADDITION OF A SHROUD
OF COMPRESSED AIR
• THE TRIPLE JET SYSTEM USES A WATER JET SHROUDED BY AIR TO
ERODE THE SOIL AND A SEPARATE NOZZLE BENEATH THE WATER
JET TO PLACE THE GROUT AS DEPICTED IN FIG. 31.15(C).
R.V.Kolhe
GROUTED COLUMNS -DIAMETER
• JET GROUTED COLUMNS CAN BE FORMED IN ALMOST ALL TYPES OF
SOILS RANGING FROM SANDY GRAVELS TO CLAYS.
• SANDS ARE BEST SUITED FOR TREATMENT YIELDING THE LARGEST DIAMETER
OF COLUMNS.
• PRESENCE OF INTERPARTICLEATTRACTIVE FORCES REDUCES THE
EROSIVE EFFICIENCY OF THE JETS.
• HENCE DIAMETERSOF GROUTED COLUMNS ARE PROGRESSIVELY SMALLER
IN SANDY SILTS, SILTS, CLAYEY SILTS AND CLAYS.
• GRAVELS DO NOT RESPOND WELL TO JET GROUTING BOTH BECAUSE OF LOSS OF
WATER OR GROUT THROUGH ITS VOIDS AND THE DIFFICULTY IN REMOVING
GRAVEL PARTICLES VIA THE ANNULAR SPACE BETWEEN THE GROUTHOLE AND
THE MONITOR.
• SANDY GRAVEL CAN BE TREATED BY JET GROUTING.
• JET GROUTED COLUMN DIAMETERS IN SANDS, SILTY SANDS AND CLAYEY SILTS
ARE TYPICALLY OF THE ORDER OF
– 1.0, 0.85 AND 0.5 M RESPECTIVELY FOR SINGLE JET SYSTEM AND
– 2.0, 1.5 AND 1.0 M RESPECTIVELY FOR TRIPLE JETSYSTEM.
R.V.Kolhe
THE TRIPLE JET SYSTEM IS THE MOST EFFECTIVE IN REMOVING SOIL
AND GIVES THE LARGEST DIAMETER OF GROUTED COLUMNS
AMONGST THE THREE SYSTEMS. IN EACH SYSTEM, THE DIAMETER OF
THE GROUTED COLUMN CAN BE VARIED BY CHANGING THE RATE OF
WITHDRAWAL OF THE MONITOR. FIG. SHOWS THE COMPONENTS OF
EQUIPMENT FOR TRIPLE JET GROUTING.
R.V.Kolhe
ROWS OF GROUTED
COLUMNS AS SHOWN
IN FIG. ARE USED
BENEATH DAMS TO
FORM SEEPAGE
BARRIERS WITH
COEFFICIENT OF
PERMEABILITY IN THE
RANGE OF 10
-7
TO 10
-9
M/SEC.
R.V.Kolhe
SUB-HORIZONTAL JET GROUTED COLUMNS ARE USED
FOR STABILIZATION OF SOIL DURING TUNNELING
R.V.Kolhe
OTHER APPLICATIONS OF JET GROUTING
ARE FOR EARTH RETENTION IN DEEP
EXCAVATIONS AS SHOWN IN FIG

More Related Content

What's hot

Ground improvement techniques
Ground improvement techniquesGround improvement techniques
Ground improvement techniques
Rakesh Reddy
 
Soil exploration part i
Soil exploration part  iSoil exploration part  i
Soil exploration part i
Avinash Kumar Gupta
 
Ground Improvement Techniques
Ground Improvement TechniquesGround Improvement Techniques
Ground Improvement Techniques
Nilesh Bhosale
 
Field compaction methods
Field compaction methodsField compaction methods
Field compaction methods
Shivarajteggi
 
Bearing failure
Bearing failureBearing failure
Bearing failure
galaly12345
 
Types of samplers used in soil sampling
Types of samplers used in soil samplingTypes of samplers used in soil sampling
Types of samplers used in soil samplingAna Debbarma
 
Reinforced soil
Reinforced soilReinforced soil
Reinforced soil
Mohit Goyal
 
Ground improvement techniques compaction vibration
Ground improvement techniques  compaction vibrationGround improvement techniques  compaction vibration
Ground improvement techniques compaction vibration
Anjana R Menon
 
Civil Engineering-Dewatering
Civil Engineering-DewateringCivil Engineering-Dewatering
Civil Engineering-DewateringMoe Abadla
 
Soil stabilisation
Soil stabilisation Soil stabilisation
Soil stabilisation
pradip dangar
 
Rigid pavement
Rigid pavementRigid pavement
Rigid pavement
pjainrahul
 
ELECTRO OSMOSIS METHOD OF DEWATERING
ELECTRO OSMOSIS METHOD OF DEWATERINGELECTRO OSMOSIS METHOD OF DEWATERING
ELECTRO OSMOSIS METHOD OF DEWATERING
TejaswiniNarayane
 
Micropiles
Micropiles Micropiles
Micropiles
Sumit Rawat
 
Expansive soil
Expansive soilExpansive soil
Expansive soil
NeerajGupta397
 
Grouting
GroutingGrouting
Deep compaction techniques
Deep compaction techniquesDeep compaction techniques
Deep compaction techniques
JNTUK
 
Dewatering by well point system
Dewatering by well point systemDewatering by well point system
Dewatering by well point system
Sivasai Pratap Reddy
 
5. stabilization.ppt
5. stabilization.ppt5. stabilization.ppt
5. stabilization.ppt
SivaRamaKrishnaUppul
 
ground improvement
ground improvementground improvement
ground improvement
junaid bashir
 
GROUND IMPROVEMENT TECHNIQUES
GROUND IMPROVEMENT TECHNIQUES GROUND IMPROVEMENT TECHNIQUES
GROUND IMPROVEMENT TECHNIQUES
harshitha alishetty
 

What's hot (20)

Ground improvement techniques
Ground improvement techniquesGround improvement techniques
Ground improvement techniques
 
Soil exploration part i
Soil exploration part  iSoil exploration part  i
Soil exploration part i
 
Ground Improvement Techniques
Ground Improvement TechniquesGround Improvement Techniques
Ground Improvement Techniques
 
Field compaction methods
Field compaction methodsField compaction methods
Field compaction methods
 
Bearing failure
Bearing failureBearing failure
Bearing failure
 
Types of samplers used in soil sampling
Types of samplers used in soil samplingTypes of samplers used in soil sampling
Types of samplers used in soil sampling
 
Reinforced soil
Reinforced soilReinforced soil
Reinforced soil
 
Ground improvement techniques compaction vibration
Ground improvement techniques  compaction vibrationGround improvement techniques  compaction vibration
Ground improvement techniques compaction vibration
 
Civil Engineering-Dewatering
Civil Engineering-DewateringCivil Engineering-Dewatering
Civil Engineering-Dewatering
 
Soil stabilisation
Soil stabilisation Soil stabilisation
Soil stabilisation
 
Rigid pavement
Rigid pavementRigid pavement
Rigid pavement
 
ELECTRO OSMOSIS METHOD OF DEWATERING
ELECTRO OSMOSIS METHOD OF DEWATERINGELECTRO OSMOSIS METHOD OF DEWATERING
ELECTRO OSMOSIS METHOD OF DEWATERING
 
Micropiles
Micropiles Micropiles
Micropiles
 
Expansive soil
Expansive soilExpansive soil
Expansive soil
 
Grouting
GroutingGrouting
Grouting
 
Deep compaction techniques
Deep compaction techniquesDeep compaction techniques
Deep compaction techniques
 
Dewatering by well point system
Dewatering by well point systemDewatering by well point system
Dewatering by well point system
 
5. stabilization.ppt
5. stabilization.ppt5. stabilization.ppt
5. stabilization.ppt
 
ground improvement
ground improvementground improvement
ground improvement
 
GROUND IMPROVEMENT TECHNIQUES
GROUND IMPROVEMENT TECHNIQUES GROUND IMPROVEMENT TECHNIQUES
GROUND IMPROVEMENT TECHNIQUES
 

Similar to Grouting Methods

Special Concreting Techniques
Special Concreting Techniques Special Concreting Techniques
Special Concreting Techniques
GAURAV. H .TANDON
 
Compaction grouting hassan
Compaction  grouting hassanCompaction  grouting hassan
Compaction grouting hassan
Hassan Mohammed Hassan
 
Dewatering
DewateringDewatering
Dewatering
JNTUK
 
Grouting n gunintung
Grouting n gunintungGrouting n gunintung
mordern soil_improvement.ppt
mordern soil_improvement.pptmordern soil_improvement.ppt
mordern soil_improvement.ppt
HabibFatimi
 
Soil improvement
Soil improvementSoil improvement
Soil improvement
Mithra G
 
Grouting various techniques of grouting.pptx
Grouting various techniques of grouting.pptxGrouting various techniques of grouting.pptx
Grouting various techniques of grouting.pptx
UmarSaba1
 
dewateringtechniques 2.pptx
dewateringtechniques 2.pptxdewateringtechniques 2.pptx
dewateringtechniques 2.pptx
CarolTumaneng
 
Under reamed piles
Under reamed pilesUnder reamed piles
Under reamed piles
AkhilaSaraVarghese1
 
5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTU
5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTU5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTU
5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTU
VATSAL PATEL
 
Chapter 4 control of ground water in excavations
Chapter 4 control of ground water in excavationsChapter 4 control of ground water in excavations
Chapter 4 control of ground water in excavations
KHUSHBU SHAH
 
Wash boring
Wash boringWash boring
Wash boring
MachenLink
 
Petroleum Refinery Engineering
Petroleum Refinery EngineeringPetroleum Refinery Engineering
Petroleum Refinery Engineering
MuhammadAhmedSaleem3
 
Pretroleum Engineering
Pretroleum EngineeringPretroleum Engineering
Repair techniques : Grouting (RR&S)
Repair techniques : Grouting (RR&S)Repair techniques : Grouting (RR&S)
Repair techniques : Grouting (RR&S)
RAMPRASAD KUMAWAT
 
Sinking of well foundation
Sinking of well foundationSinking of well foundation
Sinking of well foundation
Sourabh Jain
 
Unconventional measurers sde11
Unconventional measurers  sde11Unconventional measurers  sde11
Unconventional measurers sde11
vigyanashram
 
Presentation on surface investigation techniques for foundation
Presentation on surface investigation techniques  for foundationPresentation on surface investigation techniques  for foundation
Presentation on surface investigation techniques for foundation
ashishcivil098
 
5. Dewatering.pdf
5. Dewatering.pdf5. Dewatering.pdf
5. Dewatering.pdf
EmmanuelKiamaMutinda
 

Similar to Grouting Methods (20)

Special Concreting Techniques
Special Concreting Techniques Special Concreting Techniques
Special Concreting Techniques
 
Compaction grouting hassan
Compaction  grouting hassanCompaction  grouting hassan
Compaction grouting hassan
 
Dewatering
DewateringDewatering
Dewatering
 
Grouting n gunintung
Grouting n gunintungGrouting n gunintung
Grouting n gunintung
 
mordern soil_improvement.ppt
mordern soil_improvement.pptmordern soil_improvement.ppt
mordern soil_improvement.ppt
 
Soil improvement
Soil improvementSoil improvement
Soil improvement
 
Grouting various techniques of grouting.pptx
Grouting various techniques of grouting.pptxGrouting various techniques of grouting.pptx
Grouting various techniques of grouting.pptx
 
dewateringtechniques 2.pptx
dewateringtechniques 2.pptxdewateringtechniques 2.pptx
dewateringtechniques 2.pptx
 
W16 ground improvement techniques-dycus
W16 ground improvement techniques-dycusW16 ground improvement techniques-dycus
W16 ground improvement techniques-dycus
 
Under reamed piles
Under reamed pilesUnder reamed piles
Under reamed piles
 
5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTU
5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTU5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTU
5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTU
 
Chapter 4 control of ground water in excavations
Chapter 4 control of ground water in excavationsChapter 4 control of ground water in excavations
Chapter 4 control of ground water in excavations
 
Wash boring
Wash boringWash boring
Wash boring
 
Petroleum Refinery Engineering
Petroleum Refinery EngineeringPetroleum Refinery Engineering
Petroleum Refinery Engineering
 
Pretroleum Engineering
Pretroleum EngineeringPretroleum Engineering
Pretroleum Engineering
 
Repair techniques : Grouting (RR&S)
Repair techniques : Grouting (RR&S)Repair techniques : Grouting (RR&S)
Repair techniques : Grouting (RR&S)
 
Sinking of well foundation
Sinking of well foundationSinking of well foundation
Sinking of well foundation
 
Unconventional measurers sde11
Unconventional measurers  sde11Unconventional measurers  sde11
Unconventional measurers sde11
 
Presentation on surface investigation techniques for foundation
Presentation on surface investigation techniques  for foundationPresentation on surface investigation techniques  for foundation
Presentation on surface investigation techniques for foundation
 
5. Dewatering.pdf
5. Dewatering.pdf5. Dewatering.pdf
5. Dewatering.pdf
 

More from Rushikesh Kolhe

Programming in Civil Engineering_UNIT 3_NOTES
Programming in Civil Engineering_UNIT 3_NOTESProgramming in Civil Engineering_UNIT 3_NOTES
Programming in Civil Engineering_UNIT 3_NOTES
Rushikesh Kolhe
 
Programming in Civil Engineering_UNIT 2_NOTES
Programming in Civil Engineering_UNIT 2_NOTESProgramming in Civil Engineering_UNIT 2_NOTES
Programming in Civil Engineering_UNIT 2_NOTES
Rushikesh Kolhe
 
Programming in Civil Engineering_UNIT 1_NOTES
Programming in Civil Engineering_UNIT 1_NOTESProgramming in Civil Engineering_UNIT 1_NOTES
Programming in Civil Engineering_UNIT 1_NOTES
Rushikesh Kolhe
 
VARIABLES AND DATA TYPES IN PYTHON NEED TO STUDY
VARIABLES AND DATA TYPES IN PYTHON NEED TO STUDYVARIABLES AND DATA TYPES IN PYTHON NEED TO STUDY
VARIABLES AND DATA TYPES IN PYTHON NEED TO STUDY
Rushikesh Kolhe
 
Why Python in required in Civil Engineering
Why Python in required in Civil EngineeringWhy Python in required in Civil Engineering
Why Python in required in Civil Engineering
Rushikesh Kolhe
 
Introduction to Python Programming in Civil Engineering
Introduction to Python Programming in Civil EngineeringIntroduction to Python Programming in Civil Engineering
Introduction to Python Programming in Civil Engineering
Rushikesh Kolhe
 
Smart city Developments in India
Smart city Developments in IndiaSmart city Developments in India
Smart city Developments in India
Rushikesh Kolhe
 
Framework for Smart City
Framework for Smart CityFramework for Smart City
Framework for Smart City
Rushikesh Kolhe
 
E governance.pptx
E governance.pptxE governance.pptx
E governance.pptx
Rushikesh Kolhe
 
Human Resource Information System
Human Resource Information SystemHuman Resource Information System
Human Resource Information System
Rushikesh Kolhe
 
Introduction to TQM
Introduction to TQMIntroduction to TQM
Introduction to TQM
Rushikesh Kolhe
 
Fuzzy Logic
Fuzzy LogicFuzzy Logic
Fuzzy Logic
Rushikesh Kolhe
 
Human Resource Management: Training and Development (HRM)
Human Resource Management: Training and Development (HRM)Human Resource Management: Training and Development (HRM)
Human Resource Management: Training and Development (HRM)
Rushikesh Kolhe
 
Work Breakdown Structure (WBS)
Work Breakdown Structure (WBS)Work Breakdown Structure (WBS)
Work Breakdown Structure (WBS)
Rushikesh Kolhe
 
Materials Codification and Classification
Materials Codification and ClassificationMaterials Codification and Classification
Materials Codification and Classification
Rushikesh Kolhe
 
Economic Ordered Quantity (EOQ)
Economic Ordered Quantity (EOQ)Economic Ordered Quantity (EOQ)
Economic Ordered Quantity (EOQ)
Rushikesh Kolhe
 
Materials Management in Civil Engineering
Materials Management in Civil EngineeringMaterials Management in Civil Engineering
Materials Management in Civil Engineering
Rushikesh Kolhe
 
Ready Mix Concrete (RMC) Production Efficiency
Ready Mix Concrete (RMC) Production EfficiencyReady Mix Concrete (RMC) Production Efficiency
Ready Mix Concrete (RMC) Production Efficiency
Rushikesh Kolhe
 
Ready Mix Concrete (RMC) quality controls
Ready Mix Concrete (RMC) quality controls Ready Mix Concrete (RMC) quality controls
Ready Mix Concrete (RMC) quality controls
Rushikesh Kolhe
 

More from Rushikesh Kolhe (19)

Programming in Civil Engineering_UNIT 3_NOTES
Programming in Civil Engineering_UNIT 3_NOTESProgramming in Civil Engineering_UNIT 3_NOTES
Programming in Civil Engineering_UNIT 3_NOTES
 
Programming in Civil Engineering_UNIT 2_NOTES
Programming in Civil Engineering_UNIT 2_NOTESProgramming in Civil Engineering_UNIT 2_NOTES
Programming in Civil Engineering_UNIT 2_NOTES
 
Programming in Civil Engineering_UNIT 1_NOTES
Programming in Civil Engineering_UNIT 1_NOTESProgramming in Civil Engineering_UNIT 1_NOTES
Programming in Civil Engineering_UNIT 1_NOTES
 
VARIABLES AND DATA TYPES IN PYTHON NEED TO STUDY
VARIABLES AND DATA TYPES IN PYTHON NEED TO STUDYVARIABLES AND DATA TYPES IN PYTHON NEED TO STUDY
VARIABLES AND DATA TYPES IN PYTHON NEED TO STUDY
 
Why Python in required in Civil Engineering
Why Python in required in Civil EngineeringWhy Python in required in Civil Engineering
Why Python in required in Civil Engineering
 
Introduction to Python Programming in Civil Engineering
Introduction to Python Programming in Civil EngineeringIntroduction to Python Programming in Civil Engineering
Introduction to Python Programming in Civil Engineering
 
Smart city Developments in India
Smart city Developments in IndiaSmart city Developments in India
Smart city Developments in India
 
Framework for Smart City
Framework for Smart CityFramework for Smart City
Framework for Smart City
 
E governance.pptx
E governance.pptxE governance.pptx
E governance.pptx
 
Human Resource Information System
Human Resource Information SystemHuman Resource Information System
Human Resource Information System
 
Introduction to TQM
Introduction to TQMIntroduction to TQM
Introduction to TQM
 
Fuzzy Logic
Fuzzy LogicFuzzy Logic
Fuzzy Logic
 
Human Resource Management: Training and Development (HRM)
Human Resource Management: Training and Development (HRM)Human Resource Management: Training and Development (HRM)
Human Resource Management: Training and Development (HRM)
 
Work Breakdown Structure (WBS)
Work Breakdown Structure (WBS)Work Breakdown Structure (WBS)
Work Breakdown Structure (WBS)
 
Materials Codification and Classification
Materials Codification and ClassificationMaterials Codification and Classification
Materials Codification and Classification
 
Economic Ordered Quantity (EOQ)
Economic Ordered Quantity (EOQ)Economic Ordered Quantity (EOQ)
Economic Ordered Quantity (EOQ)
 
Materials Management in Civil Engineering
Materials Management in Civil EngineeringMaterials Management in Civil Engineering
Materials Management in Civil Engineering
 
Ready Mix Concrete (RMC) Production Efficiency
Ready Mix Concrete (RMC) Production EfficiencyReady Mix Concrete (RMC) Production Efficiency
Ready Mix Concrete (RMC) Production Efficiency
 
Ready Mix Concrete (RMC) quality controls
Ready Mix Concrete (RMC) quality controls Ready Mix Concrete (RMC) quality controls
Ready Mix Concrete (RMC) quality controls
 

Recently uploaded

AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
Vijay Dialani, PhD
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 

Recently uploaded (20)

AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 

Grouting Methods

  • 1. R.V.Kolhe Grouting METHODS BY Prof. Rushikesh v. Kolhe Department of Civil engineering Sanjivani college of Engineering
  • 2. R.V.Kolhe Grouting • INJECTION OF SLURRY/LIQUID SOLUTION INTO ROCK OR SOIL. • INJECTED MTRL IS GROUT • TECHNIQUE DEVELOPED FOR MAKING VERTICAL SEEPAGE BARRIER BY CEMENT SLURRY. • CEMENTING CAPABILITY INCREASES SOIL/ROCK STR. • CEMENT SLURRY IS NON-PERMEABLE SO SPL CHEMICALS WERE INVENTED.
  • 3. R.V.Kolhe TYPE OF GROUTS • SUSPENSIONS – CEMENT OR BENTONITE GROUT • EMULSIONS- BITUMEN EMULSIONS • SOLUTIONS- SODIUM SILICATE OR ACRYLIC RAISIN.
  • 4. R.V.Kolhe DESIRABLE CHAR OF GROUTS • STABLITY: CAPABLITY OF GROUT TO REMAIN IN FLUID STATE. – GROUT NOT TO SEGREGATE BEFORE REACHING DESTINATION. – STABLITY OF CLAY CEMENT GROUT > CEMENT GROUT
  • 5. R.V.Kolhe DESIRABLE CHAR OF GROUTS • SETTING TIME : TIME TO SET TO CEMENTED MASS OR GEL. – EARLY SETTING : REACHING DESTINATION. – LATE SETTING: GROUT WASHED AWAY. (SEEPAGE) – RETARD OR ACCELERATE BY ADDITIVES
  • 6. R.V.Kolhe DESIRABLE CHAR OF GROUTS • PERMANENCE: RESISTANCE OF GROUT AGAINST DISPLACEMENT FROM SOIL WITH TIME. – CEMENT GROUTS > BENTONITE GROUT ( WASHED AWAY BY SEEPAGE WATER)
  • 7. R.V.Kolhe DESIRABLE CHAR OF GROUTS • TOXICITY: CONTAMINATE SURROUNDING SOIL AND GROUND WATER. • HEALTH HAZARD
  • 8. R.V.Kolhe TYPES OF GROUTING TECHNIQUES • GROUTING METHODS FOR SOILS ARE CLASSIFIED AS: (I) PERMEATION GROUTING (II) DISPLACEMENT-SOIL FRACTURE GROUTING (III) DISPLACEMENT-COMPACTION GROUTING (IV) JET OR REPLACEMENT-DISPLACEMENTGROUTING
  • 9. R.V.Kolhe PERMEATION GROUTING If the injection of grout in soil is done in a manner that the arrangement of the soil grains is not disturbed and only the void space is filled by a process of permeation, that is, seepage, the method is referred to as permeation grouting as shown in fig.
  • 11. R.V.Kolhe If, however, the process of injection displaces the soil grains, the method is termed as displacement grouting. Displacement grouting is further divided into two sub— types, namely, compaction grouting and soil fracture grouting. Compaction grouting consists of injecting a thick viscous paste—like slurry at high pressure to form a bulb shaped grouted mass in soil as shown in fig.
  • 12. R.V.Kolhe On the other hand when lean slurry of high fluidity is injected into the soil at high pressure to form root-like lenses of grout material in the soil mass as depicted in fig. , the method is termed as soil fracture grouting.
  • 14. R.V.Kolhe In yet another method the grout material is injected into the soil mass in the form of a jet to form a grouted column as shown in fig. by partly replacing the soil, partly mixing with the remaining soil and also through displacing the soil. This method is referred to as jet grouting or replacement- displacement grouting.
  • 17. R.V.Kolhe Permeation Grouting • CEMENT GROUTS, BENTENITE GROUTS AND CHEMICAL GROUTS ARE USED FOR PERMEATION GROUTING AS SUMMARIZED 1N TABLE. • CHEMLCAL GROUTS ARE SUITABLE FOR THE MAXIMUM RANGE OF GRAIN SIZES BUT THEY ARE VERY EXPENSIVE
  • 18. R.V.Kolhe PERMEATION GROUTING • Cement grout not only fills the voids and reduces permeability but also sets with time and binds the soil grains together. As a consequence, the strength of the soil mass increases and its compressibility decreases. Sometimes cement in grout is replaced by clay to reduce cost. solved • When the objective of grouting is only to reduce permeability, bentonite grouts can be used. However, the permanence of such grouts under high hydraulic gradients is questionable and often cement is added.
  • 19. R.V.Kolhe • Permeation grouting is widely used for making vertical seepage barriers beneath hydraulic structures as shown in fig. • It is also used for stabilization of soil around tunnels and shafts as depicted in fig. (b). • other uses include stoppage of seepage through joints of underground structures such as tunnel lining, basement wall etc.
  • 20. R.V.Kolhe GROUTING PLANT FOR PERMEATION (CEMENTGROUT ) • Grout slurry is prepared by mixing cement with water in a slow- speed paddle mixer followed by a high-speed agitator. • A positive displacement pump (reciprocating or diaphragm type) is- used for pumping the slurry into a grout supply line (pipe of 30' to 50 mm diameter) which transports the slurry under pressure to the point of injection in the soil. • The grout pipe is lowered into the grout hole that has already been drilled to the grouting point. • The annularspace between the grout hole and grout pipe is sealed and the grout slurry injected into the soil at the prescribed pressure. • Packers, in the form of leather cups or inflatable rubber seals, are used for Sealing the annular space—see Fig. 31,4,
  • 21. R.V.Kolhe • when the grouting has to be executed down to the shallow depth below the ground surface (few meters. • Grout hole is drilled completely. • grout pipe is inserted from top • annular spaces are sealed and grouting is done under low pressure
  • 26. R.V.Kolhe Descending and Ascending Stage Grouting: • For grouting to larger depths, grouting is executed in stages. • In the DESCENDING STAGE grouting, drilling and grouting are executed alternatively in stages of 3 to 5 m in the downward direction as shown in Fig. • For each stage, as one goes deeper, one can use higher grout pressure. • ASCENDING STAGE grouting shown in Fig. is executed in a reverse manner • The grout hole is drilled to the full depth in one operation. • Subsequently the grout pipe is lowered to the deepest segment of the hole and the annular space sealed using a packer. • Grouting is carried out at high pressure. Thereafter, the grout pipe and the packer is raised in stagesof3 to 5 m and the
  • 29. R.V.Kolhe Descending and Ascending Stage Grouting: • ASCENDING STAGE GROUTING HAS THE ADVANTAGE THAT THE DRILLING IS ALL DONE IN ONE GO. • IN DESCENDING STAGE GROUTING, ONE CAN USE HIGHER GROUT PRESSURES AS ONE MOVES TO LOWER STAGES • NOT ONLY BECAUSE OF GREATER DEPTH BUT ALSO BECAUSE THE UPPER LEVELS HAVE BEEN GROUTED AND THE SOIL FORMATION IS MORE FIRM ESPECIALLY WHEN GROUTS USED ARE OF TYPES THAT SET AND ADD TO STRENGTH.
  • 30. R.V.Kolhe GROUTING USING SLEEVED PIPE • ASCENDING STAGE GROUTING IN SOIL MAY BE HAMPERED DUE TO IMPROPER FUNCTIONING OF PACKERS WHEN PUSHED OR EXPANDED AGAINST AN UNEVEN GROUT HOLE WALL. • HENCE SLEEVED PIPE GROUTING DEPICTED IN FIG. 31.8 IS OFTEN MORE SUCCESSFUL. IN THIS A SLOTTED PIPE, HAVING VERTICAL SLOTS COVERED WITH THIN RUBBER SLEEVES, IS LOWERED INTO THE GROUT HOLE. • THE SPACE BETWEEN THE SLOTTED PIPE AND THE GROUT HOLE IS SEALED WITH CEMENT-BENTONITE SEAL. • GROUTING IS DONE BY LOWERING THE GROUT PIPE WITH A PAIR OF PACKERS TO THE DESIRED ELEVATION INSIDE THE SLOTTED PIPE AND INJECTING THE GROUT UNDER PRESSURE. • GROUT PRESSURE BRUSTS THE TEMP RUBBER SLEEVE AND CEMENT BENTONITE SEAL. • GROUT PERMEATES INTP ADJOINING SOIL.
  • 35. R.V.Kolhe CURTAIN GROUTING • GROUTING ARRANGEMENTS THAT PERMEATION GROUTING IS OFTEN USED FOR MAKING VERTICAL SEEPAGE BARRIERS BENEATH HYDRAULIC STRUCTURES HAS ALREADY BEEN HIGHLIGHTED EARLIER. • THIS GROUTING ARRANGEMENT IS CALLED CURTAIN GROUTING. TYPICALLY, GROUTING IS CARRIED OUT TO THE REQUIRED DEPTH ALONG 2 TO 3 ROWS OF GROUT HOLES. • THE GROUT HOLES IN EACH ROW MAY BE SPACED AT 2 TO 4 M AND STAGGERED IN PLAN ALONG THE ROWS. • GROUTING IS FIRST DONE IN PRIMARY HOLES SPACED 15— 25 M APART FOLLOWED BY SECONDARY HOLES AT INTERMEDIATE LOC AND THEN TERTIARY HOLES AT 2—4 M SPACING AS SHOWN IN FIG. 31.9.
  • 37. R.V.Kolhe BLANKET GROUTING • IT REFERS PERMEATION GROUTING CARRIED OUT OVER A LARGE AREA IN PLAN DOWN TO A SHALLOW FIXED DEPTH. • SUCH A GROUTED ZONE IN THE SHAPE OF A BLANKET IS OFTEN CREATED BEHIND HYDRAULIC STRUCTURE TO REDUCE WATER LOSS BY SEEPAGE FROM THE RESERVOIR, • THE GROUTED BLANKET INCREASES THE SEEPAGE PATH. • GROUTING IS FIRST EXECUTED IN PRIMARY HOLES AT A GRID SPACING OF ABOUT 20 M FOLLOWED BY SECONDARY HOLES AT A GRID SPACEING OF ABOUT
  • 38. R.V.Kolhe 10 M AND FINALLY IN A CLOSELY SPACED TERTIARY GRID OF HOLES AT A SPACING OF ABOUT 5 M.
  • 40. R.V.Kolhe DISPLACEMENT-COMPACTION GROUTING • INJECTION OF GROUT UNDER HIGH PRESSURE IN SOIL MASS. • CAUSES DISPLACEMENT OF SOIL PARTICLES. • BULBOUS/SPHERICAL SHAPED INTRUSIONS RANGE OF 0.5 TO 1.0 M ARE FORMED. • THE GROUT MATERIAL USED IS A MIXTURE OF SOIL AND CEMENT, SEE TABLE 31.2. • • THE SOIL USED IN THE GROUT HAS SUFFICIENT SAND SIZED PARTICLES TO DEVELOP INTERNAL FRICTION AS WELL AS ENOUGH FINE GRAINED PARTICLES TO PROVIDE PLASTICITY TO THE GROUT.
  • 41. R.V.Kolhe DISPLACEMENT-COMPACTION GROUTING • WATER IS ADDED TO YIELD A PASTE-LIKE CONSISTENCY OF THE GROUT. • WE NEED TO USE JUST ENOUGH CEMENT SO THAT THE ENGINEERING PROPERTIES OF THE GROUTED MASS ARE SIMILAR TO OR BETTER THAN THOSE OF THE NATURAL SOIL IN A COMPACTEDSTATE. • IN SOME CASES, WHEN PERMANENCE IS NOT AN ISSUE, CEMENT NEED NOT BE USED AT ALL AND THE GROUT CAN BE JUST A SOIL SLURRY.
  • 43. R.V.Kolhe DISPLACEMENT-COMPACTION GROUTING • THE TECHNOLOGY OF INJECTION OF GROUT IS SIMILAR TO THAT FOR PERMEATIONGROUTING. • HOWEVER, SINCE THE GROUT MIX IS MUCH STIFFER THAN IN PERMEATION GROUTING AND GROUT PRESSURES ARE MUCH HIGHER, THE GROUT PUMPS USED ARE HEAVY-DUTY CONCRETE PUMPS. • GROUT PIPE DIAMETERS RANGE FROM 50 TO 75 MM. • THE QUANTITY OF GROUT INJECTED IS OBSERVED TO RANGE FROM 3 TO 12 PERCENT BY VOLUME OF THE TREATED LOOSE SOIL, • DISPLACEMENT-COMPACTIONGROUTING IS SUITABLE FOR ALL TYPES OF LOOSE COARSE GRAINED SOILS, SOFT FINE GRAINED SOILS WHICH ARE NOT SATURATED AND FOR FILLING UNDERGROUND CAVITIES. • IT IS NOT USED IN SOFT SATURATED FINE GRAINED SOILS BECAUSE GROUTING RAISES THE PORE WATER PRESSURE IN THE SOIL MASS LEADING TO UNEVEN AND AGGRAVATED SETTLEMENT PROBLEMS.
  • 44. R.V.Kolhe DISPLACEMENT-COMPACTION GROUTING • IN COMPARISON TO OTHER TYPES OF GROUTING, DISPLACEMENT— COMPACTION GROUTING IS OBSERVED TO BE USEFUL FOR THE FOLLOWING SITUATIONS: • (I) DENSIFICATION OF THIN LOOSE STRATUM UNDERLYING DENSE SOIL AND LOCATED AT CONSIDERABLE DEPTH—SEE FIG. 31.11(A) AND (B) • (II) DENSIFICATION OF POCKETS OF LOOSE SOILS BENEATH FOUNDATIONS OR FLOOR SLABS THAT ARE REVEALED AFTER CONSTRUCTION IS COMPLETED INCLUDING LEVELING OF SUNKEN FLOORS—ALSO REFERRED TO AS SLAB-JACKING OR BACK- PACKING— SEE FIG. 31.11(C),
  • 45. R.V.Kolhe DISPLACEMENT-COMPACTION GROUTING • (III) FILLING OF LARGE UNDERGROUND CAVITIES CAUSED BY BROKEN UNDERGROUND UTILITY LINES, BY PIPING/ EROSION, OR BY DISSOLUTION AS DEPICTED IN FIG. 31.11(D) AND (E); IN SUCH CASES, THE CAVITIES ARE FIRST FILLED WITH GROUT AND THEN THE DENSITY OF SURROUNDING SOIL IS INCREASED BY GROUTING WITH APPROPRIATE GROUT PRESSURE, AND • (IV) DENSIFICATION OF SOILS SHOWING ORGANIC DEGRADATION WITH TIME. DISPLACEMENT-COMPACTION GROUTING IS MOST OFTEN USED IN SMALL AREAS OR POCKETS AS A REMEDIATION TECHNIQUE. IT IS RARELY COST EFFECTIVE FOR GROUND IMPROVEMENT OVER LARGE AREAS.
  • 50. R.V.Kolhe Displacement—Soil Fracture Grouting • SOIL FRACTURE GROUTING TECHNIQUE IS A DISPLACEMENT GROUTING TECHNIQUE IN WHICH A LEAN SLURRY OF CEMENT, SOIL AND WATER IS INJECTED INTO THE SOIL AT HIGH PRESSURE TO FRACTURE THE SOIL AND FORM ROOT—LIKE OR THIN LENS SHAPED ZONES OF GROUT MATERIAL IN THE SOIL MASS. • THE GROUT MATERIAL SPREADS ALL AROUND THE GROUT HOLE CAUSING DENSIFICATION OF THE SOIL MASS AND AN INCREASE IN ITS MACROSCOPIC STRENGTH. •
  • 52. R.V.Kolhe SUCH GROUTING ALSO CAUSES THE GROUND TO HEAVE AND THAT CAN BE USED TO ADVANTAGE, FOR EXAMPLE, IN RECTIFYING TILT IN BUILDINGS AND RESTORING THEIR VERTICALITY AS SHOWN IN FIG. 31.12.
  • 53. R.V.Kolhe Restoration of verticality of a tilted building • RESTORATION OF VERTICALITY OF A TILTED BUILDING SUCH GROUTING IS USUALLY ACCOMPLISHED USING THE SLEEVED PIPE GROUTING TECHNIQUE AS DEPICTED IN FIG. 31.13. • GROUT HOLES, 100 MM IN DIAMETER, ARE DRILLED AT REGULAR INTERVALS AND SLEEVED PIPES WITH MULTIPLE SLOTS ARE PLACED IN THE GROUT HOLES. GROUTING IS DONE IN SEGMENTS OF 0.3 TO 1.0 M ALONG THE LENGTH OF EACH SLOTTED PIPE USING GROUT PRESSURES AS HIGH AS 4000 KN/MZ.
  • 55. R.V.Kolhe Jet or Replacement—Displacement Grouting • GROUTING IN THIS TECHNIQUE, A SPECIAL GROUT PIPE CALLED THE MONITOR HAVING HIGH-SPEED JETS OF WATER OR GROUT IS USED TO ERODE AND EXCAVATE THE SOIL • THEREAFTER, AS THE MONITOR IS WITHDRAWN, STRONG, IMPERVIOUS COLUMNS ARE PRODUCED BY MIXING GROUT WITH THE REMAINING SOIL. • THE TECHNIQUE IS CALLED REPLACEMENT DISPLACEMENT BECAUSE A PART OF THE SOIL IS REMOVED BY THE JETTING ACTION AND IS REPLACED BY THE GROUT MATERIAL AND BECAUSE THE GROUT IS INJECTED AT HIGH PRESSURE PARTLY TO MIX WITH THE REMAINING SOIL AND BARTLY TO DISPLACE THE SURROUNDING SOIL.
  • 56. R.V.Kolhe Jet or Replacement—Displacement Grouting • THE GROUT MATERIALS USED ARE CEMENT AND WATER WITH SOME ADDITIVE AS INDICATED IN TABLE 31.3. • JET GROUTING IS THE YOUNGEST OF GROUTING TECHNIQUES AND CONSULTING GEOTECHNICAL ENGINEERS HAVE BEGUN TO USE IT AFTER THE MID-1980S. • IT IS MORE EXPENSIVE THAN PERMEATION GROUTING, DUE TO LARGER CONSUMPTION OF CEMENT PER UNIT VOLUME OF SOIL MASS TREATED.
  • 57. R.V.Kolhe • NEVERTHELESS, IT IS NOW EXTENSIVELY USED AS IT PRODUCES MORE UNIFORM GROUTING, CAN BE USED IN MOST SOILS AND HAS A HIGHER RATE OF PRODUCTIVITY
  • 59. R.V.Kolhe Jet or Replacement—Displacement Grouting • TYPES OF JET GROUTING – SINGLE JET OR ONE FLUID SYSTEM – DOUBLE JET OR 02 FLUID SYSTEM – TRIPLE JET OR 03 FLUID SYSTEM. • THE FIRST STEP IS TO DRILL A GROUT HOLE OF 100 TO 150 MM DIAMETER. • THE HOLE IS KEPT STABLE BY USING WATER CIRCULATION OR BENTONITE SLURRY CIRCULATION. • IN THE SECOND STEP, JETTING COMMENCES IN THE HORIZONTALDIRECTION THROUGH NOZZLES (2 TO 4 MM IN DIAMETER)AT THE TIP OF THE MONITOR THAT IS ROTATED AT 5 TO 30 REVOLUTIONS PER MINUTE. • THE SOIL CUTTINGS TRAVEL TO THE GROUND SURFACE THROUGH THE ANNULAR SPACE BETWEEN THE BOREHOLEAND THE MONITOR. • THE MONITOR IS LIFTED AT A RATE OF 50 TO 300 MM PER MINUTE IN THE THIRD STEP RESULTING IN THE FORMATLON OF A GROUTED COLUMN.
  • 61. R.V.Kolhe • IN THE SINGLE JET SYSTEM, A HORIZONTAL JET OF GROUT AS SHOWN IN FIG. SIMULTANEOUSLY ERODES THE SOIL AND MIXES WITH A PART OF THE REMAINING SOIL TO FORM A GROUTED COLUMN. • IN THE DOUBLE JET SYSTEM, THE EROSIVE EFFECT OF THE GROUT JET IS CONSIDERABLY ENHANCED BY THE ADDITION OF A SHROUD OF COMPRESSED AIR • THE TRIPLE JET SYSTEM USES A WATER JET SHROUDED BY AIR TO ERODE THE SOIL AND A SEPARATE NOZZLE BENEATH THE WATER JET TO PLACE THE GROUT AS DEPICTED IN FIG. 31.15(C).
  • 62. R.V.Kolhe GROUTED COLUMNS -DIAMETER • JET GROUTED COLUMNS CAN BE FORMED IN ALMOST ALL TYPES OF SOILS RANGING FROM SANDY GRAVELS TO CLAYS. • SANDS ARE BEST SUITED FOR TREATMENT YIELDING THE LARGEST DIAMETER OF COLUMNS. • PRESENCE OF INTERPARTICLEATTRACTIVE FORCES REDUCES THE EROSIVE EFFICIENCY OF THE JETS. • HENCE DIAMETERSOF GROUTED COLUMNS ARE PROGRESSIVELY SMALLER IN SANDY SILTS, SILTS, CLAYEY SILTS AND CLAYS. • GRAVELS DO NOT RESPOND WELL TO JET GROUTING BOTH BECAUSE OF LOSS OF WATER OR GROUT THROUGH ITS VOIDS AND THE DIFFICULTY IN REMOVING GRAVEL PARTICLES VIA THE ANNULAR SPACE BETWEEN THE GROUTHOLE AND THE MONITOR. • SANDY GRAVEL CAN BE TREATED BY JET GROUTING. • JET GROUTED COLUMN DIAMETERS IN SANDS, SILTY SANDS AND CLAYEY SILTS ARE TYPICALLY OF THE ORDER OF – 1.0, 0.85 AND 0.5 M RESPECTIVELY FOR SINGLE JET SYSTEM AND – 2.0, 1.5 AND 1.0 M RESPECTIVELY FOR TRIPLE JETSYSTEM.
  • 63. R.V.Kolhe THE TRIPLE JET SYSTEM IS THE MOST EFFECTIVE IN REMOVING SOIL AND GIVES THE LARGEST DIAMETER OF GROUTED COLUMNS AMONGST THE THREE SYSTEMS. IN EACH SYSTEM, THE DIAMETER OF THE GROUTED COLUMN CAN BE VARIED BY CHANGING THE RATE OF WITHDRAWAL OF THE MONITOR. FIG. SHOWS THE COMPONENTS OF EQUIPMENT FOR TRIPLE JET GROUTING.
  • 64. R.V.Kolhe ROWS OF GROUTED COLUMNS AS SHOWN IN FIG. ARE USED BENEATH DAMS TO FORM SEEPAGE BARRIERS WITH COEFFICIENT OF PERMEABILITY IN THE RANGE OF 10 -7 TO 10 -9 M/SEC.
  • 65. R.V.Kolhe SUB-HORIZONTAL JET GROUTED COLUMNS ARE USED FOR STABILIZATION OF SOIL DURING TUNNELING
  • 66. R.V.Kolhe OTHER APPLICATIONS OF JET GROUTING ARE FOR EARTH RETENTION IN DEEP EXCAVATIONS AS SHOWN IN FIG